4 Inspection, Maintenance and Repair For Civil Works: Source: Manual of Hydrological Analysis, Nippon Koei Co., LTD
4 Inspection, Maintenance and Repair For Civil Works: Source: Manual of Hydrological Analysis, Nippon Koei Co., LTD
4 Inspection, Maintenance and Repair For Civil Works: Source: Manual of Hydrological Analysis, Nippon Koei Co., LTD
(ii) Water levels of reservoirs (and regulating ponds for run-of-river type
station) and also the water levels in the river downstream of the tailrace.
• The hourly observation of rainfall during floods is useful for forecasting water
levels of reservoirs and regulating ponds during future floods. However, because
the hourly observation of rainfall during floods may endanger the observer, hourly
observations should be carried out only using automatic rain gauges.
• Also, it is recommended to carry out daily observation of water levels in the river
downstream of the tailrace to grasp the volume of river flow.
• The readings of staff gauges should be accurate and recorded to the nearest centimeter.
• The installation of automatic water level gauges is convenient for the observation
of water levels in regulating ponds where the water levels are always variable
Automatic recorder
Conduit of water
pressure transmission
Water Level Gauge Housing Automatic Recorder with Water Pressure Type
• The hourly observation data of water levels during floods is useful for forecasting
water levels of reservoirs and regulating ponds during floods in future. In addition,
the hourly observation of water levels in the river downstream of the tailrace
during the flood is also useful. However, in due consideration that hourly
observation of water levels during floods may endanger the observer, hourly
observation is recommended to be carried out only when an automatic water level
gauge is installed.
• Further to the recording of water levels observed in the river downstream from the
tailrace during floods, the data of the maximum water level will be useful for
further confirmation of the safety of hydraulic facilities relevant to the
hydroelectric power station.
Failure or partial failure of the hydroelectric power facilities (see the following figure)
could jeopardise operation of the facilities, endanger the lives and safety of the public
and staff or cause substantial property damage.
Power Station
Intake De-Silting Basin Head Tank
Penstock Line Tailrace
Waterway
Tailrace Exit
Intake Weir
Sand Flushing Channel Spillway Channel
River Flow
(2) Plan
“No”
“Yes”
Cycle of Inspection
Source: JICA Study Team
Figure 4.2.2 Cycle of Inspection
The items to be inspected for Civil Works structures are as shown in Table 4.3.1.
2 To identify adverse phenomena and classify them into (i) items related to a
decrease in available discharge for power generation, (ii) those related to a decrease
in regulation capacity of the head pond, and (iii) those related to a decrease in the
safety factor of civil structures.
With respect to each stage (1 - 5), the detailed discussions are exhibited in Figure
4.3.1(1/5) - 4.3.1(5/5) in reference to the inspection of the civil works structures of Zi
Chaung power station which was carried out in the course of both of the 7th and 8th
field investigations in Myanmar:
Slope Easy to Slide Big Stone Fallen from Slope Debris Once Entered and Removed
PHENOMENA
CALCULATIONS, ETC.
270
Canal wall Bed El (m)
269 W.S.El (m)
268 Wall El. (m)
EL. (m)
267
Water surface
Figure 4.3.1 (3/5) Detailed Procedure of Inspection/ Monitoring 266
265 Floor of canal
264
-20 -15 -10 -5 0 5 10 15 20
BP+ (m)
Hydraulic Calculations
Intake and Water Way Hydraulic Calculations (BP-20m ~ +20m)
Hydraulic Calculations
(i) Items related to a decrease in 1 Sediments upstream of weir and intake, 2 Inappropriate flow
available discharge for power conditions of Intake, 3 Damaged screen, 4 Sediment transport in
4 TO GRASP CAUSES OF
generation headrace canal, and 5 Erosion of foot of wall in headrace canal.
ADVERSE PHENOMENA
Causes for Damaged Side-Spillway: Possibility-a:1 Damaged screen, and 2 Erosion of foot of
side-spillway. Possibility-b: 1Lack of stability in side-spillway due to less thickness of wall.
(iii) Items related to a decrease in
the safety factor of civil structures
(i) Items related to a decrease in 1 Provision of “Gabion Training Walls” for achievement of appropriate flow
5TO IDENTIFY COUNTERMEASURES
available discharge for power conditions of intake, to reduce sediment inflow into headrace canal, 2
FOR ADVERSE PHENOMENA
generation Removal of sediment in headrace canal, and 3 Repair of eroded portion in
headrace canal.
(ii) Items related to a decrease in 1 Periodical removal of sediment in head pond, and 2 Removal of sediment in de-silting
regulation capacity of the head pond basin through operation of sand flushing gates.
1 Placement of concrete covers over headrace canal in such section where the mountainside
Source: JICA Study Team slope is found apt to collapse.
(4) Head tank and (a) Body of head tanks/ spillway channels,
spillway water level gauges and staff gauges
channel
(b) Surrounding areas
Note: The mark denoted as “ ” means a item to be inspected. Source: JICA Study Team
As seen from the above table, the discharge available for power generation was 1.21
m3/s (decreased to 69.5% of the inflow of 1.74 m3/s) due to the leakage of water from
the headrace canal estimated at 0.53 m3/s (30.5% of inflow of 1.74 m3/s).
(2) Sediment inside the Headrace Canal and Erosion of the Headrace Canal
Nippon Koei / IEEJ The Study on Introduction of Renewable Energies
Volume 4 Manuals In Rural Areas in MYANMAR
Part 1
- 103 -
On May 25, 2003 during the 8th field investigation in Myanmar the intake gates were
closed so that the headrace canal was dewatered and inspection of the canal was
carried out along the footpath. It revealed much sediment inside the headrace canal
beyond expectations as shown in the following photographs. In particular, the
sediments just downstream of the side-spillway, for example, measured about 35 cm
thick as shown in the following photographs:
- Several countermeasures are to be sought to stop water leakage and the most
appropriate countermeasures selected, depending on the cause of water leakage,
i.e. erosion of floor slab, erosion of foot of side wall, erosion of foundation of
canal due to leakage water, etc.
Topographic Survey
In the course of monitoring of the headrace canal, the discharge capacity of the
waterway, especially for the section of waterway from the beginning of the intake to
the end of the side-spillway, was of great concern to confirm the discharge available
for power generation. The following cases were adopted for hydraulic calculations:
(i) In the case of the headrace canal having no sediment, discharge capacity
was the same as the design.
(ii) In the case of the headrace canal having sediment, surveyed data were used
to calculate discharge capacity.
In advance of hydraulic calculations, the leveling survey was carried out over the
whole 3400 m of the headrace canal in order to achieve the canal data for hydraulic
calculations.
Weir
Headrace Canal
Further, the comparison between the designed profile of the headrace canal (i.e. the
top of floor before sedimentation) and the surveyed one (i.e. the top of floor after
sedimentation) is as shown below.
264 3
262
260 2
Surveyed bed slope: 1/624.4
258
1
-200 0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 3400 3600
BP+ (m)
Note: n = 0.014
Comparison of Headrace Canal between The Surveyed and The Designed
The balance between the designed floor level of the canal and the surveyed one is
shown below for the upstream section of the canal from the beginning point to the
downstream point 200 m along, which corresponds to the extent of the sediment
deposition:
Table 4.3.3 Comparison of Floor Level between The Designed and The Surveyed
In the case of the hydraulic calculations for the headrace canal having no sediment, it
was confirmed that the upstream section between the beginning of the intake and the
end of the side-spillway has a discharge capacity of 4.0 m3/s, the same as the design
discharge, with a sufficient free board of 30 cm, as shown below.
Location (BP+) Floor Level Water Surface Top of Wall Free Board Velocity Fr
(m) (EL. - m) (EL. - m) (EL. - m) (EL. - m) (m/s)
-19.4 265.66 266.69 268.80 2.11 0.5 0.16
-13.2 265.66 266.69 268.80 2.11 0.5 0.16
-4.5 264.80 266.03 268.80 2.77 1.31 0.38
0.0 264.80 265.98 267.00 1.02 1.58 0.46
3.0 264.80 265.97 266.27 0.30 1.77 0.52
25.0 264.76 265.91 266.27 0.36 1.77 0.53
50.0 264.72 265.88 266.40 0.52 1.77 0.52
100.0 264.65 265.81 266.33 0.52 1.77 0.52
200.0 264.51 265.66 266.18 0.52 1.77 0.53
Source: Calculation by JICA Study Team
270 1
Bed El (m)
269 W.S.El (m)
268 Q=4.0 m3/s
Wall El. (m)
EL. (m)
267
266
265
264
-20 0 20 40 60 80 100160 120 180 140
200
Note: n = n=0.014
0.014
BP+ (m)
Figure 4.3.10 Hydraulic Calculations in The Case of Headrace Canal Having No
Sediment As Same As Design (BP-20 - BP+200)
Source: Calculation by JICA Study Team
In the case of the hydraulic calculations for the headrace canal having sediment as
surveyed, it was confirmed that the side-spillway started to overflow when the
discharge reached 3.8 m3/s. The discharge capacity of headrace canal is therefore
restricted to a discharge capacity of 3.8 m3/s, i.e. 96% of the design discharge of
headrace canal (4.0 m3/s ) as shown below.
266.5
(Designed) (266.27 m)
266
As seen from the above figure, the overflow weir of the side-spillway starts to
overflow at a discharge of 5.5 m3/s in the case of no sediment as designed. In the case
of the headrace canal having sediments as surveyed, the overflow weir of side-
spillway starts to overflow at a discharge of 3.8 m3/s, which is less than the design
discharge of 4.0 m3/s. After application of several roughness coefficients for the
hydraulic calculations of the headrace canal having no sediment, it was confirmed that
application of a roughness coefficient of 0.019 allowed the overflow weir of the side-
spillway to start to overflow at the design discharge of 4.0 m3/s with almost the same
freeboard as designed, 0.75 feet (= 22.8 cm).
The roughness coefficient of 0.019 was applied for the hydraulic calculations of
Baluchaung hydroelectric power project by reference to its design criteria (refer to
Nippon Koei / IEEJ The Study on Introduction of Renewable Energies
Volume 4 Manuals In Rural Areas in MYANMAR
Part 1
- 108 -
Appendix 3 of Part 6-2 in Vol.6: Supporting Report). Such a roughness coefficient of
0.019 was decided in due consideration of Baluchaung power plant that about 80% of
the energy required for the whole of Myanmar would be covered by Baluchaung
power plant, which would not allow the Baluchaung power plant to be stopped for
dewatering of the headrace canal for removal of sediment after the commencement of
power generation.
Further, it was confirmed that MEPE used the roughness coefficient of 0.018 for the
design of Zi Chaung power plant (completed in 1997); however, the Department of
Hydroelectric Power (DHP), Ministry of Electric Power has recently used the
roughness coefficient of 0.013 for the design of hydraulic structures.
The intake is located beside the overflow weir and is in the same direction of the river
flow as shown in Figure 4.3.7. This location of the intake is judged to be a major cause
for sediment from the river entering the headrace canal. Refer to Figure 4.3.12 for a
recommendation on the selection of an intake.
“River Flow”
Convex Side
“Intake”
Concave Side
Case-2:
Convex Side
Therefore, it is recommended that the intake be located where the convex shape of
river flow exists, for reduction of sediment.
In addition, Figure 4.3.15 shows the profile of the intake in the original design,
indicating the permissible height of sediment of 5.974 m (= the intake sill level at
EL.265.633 m minus the original river bed at EL.259.659 m). However, the river bed
has risen to EL.266.200 m around the weir and several water passages to the intake
exist according to the results of topographic survey.
It is noted that the topographic survey of about 1.5 ha for the upstream of the intake
was carried out in advance of this planning of the gabion training wall in the course of
the 8th field investigation.
Source: MEPE
Damaged Screen
Generally speaking, an inclined screen is suitable for removal of drift leaves and
driftwoods from screens as compared with a vertical screen.
Nevertheless, the intake of Zie Chaung power station is facilitated with a vertical
screen and it is hard to remove drift leaves and driftwoods from the screen. In addition,
the operation deck at the site seems impractical for removal of leaves and driftwoods
from the vertical screen. Consequently, these conditions prevent removal of drift
leaves and driftwoods from the vertical screen. The screen has become damaged due
to large water pressure. The damaged screen has then allowed entry of sediment such
as cobbles, gravel, sand, etc. into the headrace canal and caused erosion of the
headrace canal as illustrated below:
In addition to the preventive measures for drift leaves and driftwoods by repair of the
screen and modification of the operation deck, one more option is considerable as is
shown in Figure 4.3.11, which is to utilize a frames made of reinforcing bars arranged
at 50 cm intervals in the gabion training wall.
Skimmer Wall
Another possible preventive measure for driftwoods is to provide a skimmer wall with
piers at the inlet for protection of the screen and the sand flushing gates as shown
below.
With regard to determining the method for protection of the weir crest and the
downstream slope against erosion by rocks, stones, cobbles, etc. transported by
overflow water, a yardstick is whether the damaged portion can be repaired or not
in future.
For example, Figure 4.3.19 shows a lining (SUS 304) applied for dams in Japan to
protect a sand flushing facility from sediment. The lining is planned to be durable for
100 years as it is located upstream of the dam body making it difficult to repair
damaged portions of the sand flushing facility in future.
The Study on Introduction of Renewable Energies
Nippon Koei / IEEJ in Rural Areas in MYANMAR
Volume 4 Manuals
Part 1
- 115 -
In addition to repairing the damaged portion, the following options are considerable
for protection of the weir crest and the downstream slope of Zi Chaung power station:
- Construction of check dams by gabions similar to the gabion training wall (refer to
Figure 4.3.14), steel frame gabions (refer to Figure 4.3.21), concreted gabions, etc.
to reduce the amount of gravel and sediment transported by overflow water.
In establishment of the rehabilitation plan and design for the weir of Zi Chaung power
station, it is suggested that MEPE consult with the concerned staff of the Department
of Hydroelectric Power (DHP), Ministry of Electric Power.
4.3.10
Source: JICA Study Team
The items to be inspected for gates, trashracks and penstocks are shown in Table
4.4.1.
4.4.2 Operational Check Points of Discharge Control Gates for Intake and Head Pond
The operational check points of discharge control gates for the intake and head pond,
when provided, are as follows:
• Gate leaves are to be in complete contact with the gate sheets to secure water
tightness and appropriate countermeasures are to be taken for the prevention of
water leakage, if any.
During floods, it is recommended to stop power generation and to close the control
gates of the intake to prevent sediment and drift wood from affecting the associated
structures.
Operations of the control gate of the intake are generally required for: (i) the mandatory
release of water for irrigation and environmental requirements in downstream reaches,
even with the reduction of discharge for power generation, (ii) water filling and de-
watering for the purpose of inspection and repairs of the waterway structures, and (iii)
prevention of waterway structures from sediment and drift wood during flood
conditions.
In Japan, it has been recently required to achieve appropriate and precise gate
operations for the water intake and the mandatory release of water, being subject to the
quantity of river flow and the regulations for utilization of river flow. In reference to
the run-of-river-type hydroelectric power stations in Japan, the control of water intake
and the mandatory release of water are explained as follows:
Agreed max.
Water level gauge
discharge (Qm )
Design discharge (Qd)
Design discharge of power generation (Qd)
Overflow weir
(m3/s) c d
River flow Water level
QL Qo + Qd
e
b
“Water level” a
a
Qo FSL
MOL
Time
Gate opening(%) Full opened
100 %
0%
Full closed Full closed Time
It is noted that in respect of the gate operation for the intake gate of Zi Chaung power
station, which is located about 3.4 km from the powerhouse, the daily gate operation is
not necessary as there are no requirements for mandatory release of water and there are
a side-spillway just downstream of the intake gate and another side-spillway in the
regulating pond neighboring the powerhouse.
Operation of Control Gate to Secure Mandatory Release of Water for Irrigation and
Environmental Requirements:
In the case when the river flow (Qr) is smaller than the mandatory water for irrigation
and environmental requirements (Qo), the control gate of the intake should be operated
to secure the mandatory release of water for irrigation and environmental requirements
and to head for achievement of the FSL (Full Supply Water Level) in the upstream of
the overflow weir.
In the case when the river flow (Qr) is greater than the mandatory water for irrigation
and environmental requirements (Qo) and it is smaller than the total of the mandatory
water for irrigation and environmental requirements (Qo) and the design discharge of
waterway for power generation (Qd), the control gate of the intake will be gradually
opened to the full opening and maintain the FSL.
In the case when the river flow (Qr) becomes greater than the discharge limit (QL), i.e.
the total of the mandatory water for irrigation and environmental requirements (Qo) and
the design discharge of waterway (Qd), the full opening of the control gate will
continue to keep the FSL and opening of the sand flushing gate will start for the
purpose of sand flushing.
In the case when the river flow (Qr) becomes less than the discharge limit (QL = Qo +
Qd), the sand flushing gate should be fully closed and the control gate of the intake
should be gradually closed.
Operation of Control Gate to Secure Mandatory Release of Water for Irrigation and
Environmental Requirements :
In the case when the river flow (Qr) becomes less than the mandatory water for
irrigation and environmental requirements (Qo), the control gate of the intake should be
fully closed for achievement of (Qo).
De-silting basins are provided for the settling and flushing of sediment particles to
reduce abrasion of the waterway, penstock pipe, hydraulic turbines, etc., and eventually
to achieve stable and efficient operation of the hydroelectric power plant.
De-silting ditch
Sand flushing gate
Waterway
River flow
• No operation of sand-flushing gates for a long time may cause serious sediment
deposits which may not be able to be removed by operation of the sand-flushing
gates. It is essential to carry out periodical sand flushing.
• During and after floods, the sand flushing gates are to be opened for flushing of
sediments deposits.
• Also during and after floods, drift leaves and driftwoods may cause clogging of the
screen, and eventually may cause crushing of the screens due to the water pressure
acting on the upstream surface of the screens resulting from the raised water level
The application of reliable and efficient methods of sediment control and removing
sediment from waterways is one of the most important considerations for the successful
utilization of water resources in a hydroelectric power scheme. It is generally expected
that appropriate operations of both the sand-flushing gates installed in neighboring
dams or weirs and the sand flushing gates in the de-silting basin will effectively return
sediment back to the river.
However, it is a fact that run-of-river projects and storage schemes with large dams for
hydroelectric power projects have suffered from serious sediment deposits that have not
been removed by the sand-flushing gates.
- The ‘Saxophone’ suction head has open slots in the invert portion of the pipes.
- Upon opening the valve, a suction head caused by the water head between the Pond
and outlet will give rise to a velocity of water inside the pipe. The velocity of water
will give the inside of the pipe negative pressures to absorb sediment and it will
transport the sediment to the outside of the pipe.
- Once absorption of sediment starts, collapse of the sediment deposits will occur
automatically and it will supply sediment to the open slots, which will cause
repeated absorption of sediment and its transportation.
- In the case when the open slots are provided in the crown portion of pipes, the open
slots will be plugged by sediment during collapse of sediment deposits.
Accordingly, the open slots are to be provided in the invert portion of pipes.
- It is a special property of the ‘Saxophone’ suction head that sediment will not cause
plugging of the absorption pipe even with the occurrence of settlement of the
‘Saxophone’ suction head.
Head
Valve
Open slots
Source: See foot notes
- The sand flushing through the slotted pipe sediment sluicer is a fixed sluicing
system to utilize the water head between the pond and the outlet.
- Upon opening the valve, a suction head caused by water head between the pond and
outlet will give rise to a velocity of water inside the pipe. The velocity of water will
give the inside of the pipe negative pressures to absorb sediment and it will
transport the sediment to the outside of pipe.
- Once absorption of sediment starts, collapse of the sediment deposits will occur
automatically and will supply sediment to the open slots, which will cause repeated
absorption of sediment and its transportation.
- When the open slots are provided in the crown portion of pipes, the open slots will
be plugged by sediment during collapse of sediment deposits. Accordingly, the
open slots are to be provided in the invert portion of pipes.
Sediment removed
Slotted pipes Sediment
Head
Open slots
Valve
2g ⋅ H
V=
1 + fe + N ⋅ fb + f
fe = 1.00 (inlet loss), N·fb = 0.40 (bend loss), f = fr ·L/φ = 4.5 (friction loss)
Sand = 131 m3/hr x 3%*1 = 3.9 m3/hr (= 31 m3/day*2): sand volume flushed
Note; *1: 3% of the discharge is applied in reference to the results of test operation for
‘Saxophone’ Suction Head as shown in Table A1.14.9 of Appendix 1-14 in Vol.6
Supporting Report.
Notes; Source: “Sediment control: recent developments for headworks” by D.K. Lysne, N.R.B.Olsen,
H.St∅le and T.Jacobsen, The Norwegian Institute of Technology, Trondhelm, Norway, pp.46 – 49 of
Hydropower and Dam March 1995 (See Appendix 1-12 of Supporting Report in Volume 6).
The hydraulic functions of the ‘Saxophone’ suction head and ‘Flute’ pipe were
confirmed in the 7th and 8th field investigations in Myanmar using trial devices made
in the field. However, the sand flushing efficiency of ‘Saxophone’ suction head was at
about 3% of the discharge in reference to Table A1.14.9 of Appendix 1-14 in Vol.6
Supporting Report.
Consequently, it was confirmed that further field tests would be necessary to achieve
practicable flushing devices based on these suction head concepts.