Designers' Desk Reference: Truebeam/Vitalbeam Edition
Designers' Desk Reference: Truebeam/Vitalbeam Edition
Designers' Desk Reference: Truebeam/Vitalbeam Edition
TrueBeam/VitalBeam Edition
D O C . # : D D R - H T- V
P/N: 100060817-12
List of Revisions
For revisions prior to those listed below, please contact your Varian Regional Planner.
Item # Version Section Page # Revision Remarks
197 Vol. 15, No. 1 Back of Added new heading:
Cover Language of Origin: This
publication is of
English-language origin
198 Vol. 15, No. 1 2.3 2-7 Figure 2-2: Revised the Changed from “8'-9" (2667)” to “9'-0" (2743)”
maximum couch arc
clearance dimension
iii
List of Revisions
200 Vol. 15, No. 1 2.4 2-11 Figure 2-4: Updated the
couch arcs on the Typical
(Intermediate) Vault
Configuration layout
201 Vol. 15, No. 1 2.4 2-11 Figure 2-5: Updated the
couch arcs on the
Traditional (Large) Vault
Configuration layout
202 Vol. 15, No. 1 2.4 2-13 Figure 2-6: Updated the
couch arcs on the
Minimum Vault
Configuration - Direct
Entry layout
203 Vol. 15, No. 1 2.4 2-13 Figure 2-6: Added new
note “This is the minimum
dimension to finished
wall”
204 Vol. 15, No. 1 2.4 2-13 Figure 2-6: Added new
note “This is the minimum
dimension to face of
concrete”
205 Vol. 15, No. 1 2.4 2-13 Figure 2-7: Updated the
couch arcs on the
Minimum Vault
Configuration - Maze
Entry layout
206 Vol. 15, No. 1 2.4 2-13 Figure 2-7: Added new
note “This is the minimum
dimension to finished
wall”
207 Vol. 15, No. 1 2.4 2-13 Figure 2-7: Added new
note “This is the minimum
dimension to face of
concrete”
208 Vol. 15, No. 1 2.5 2-15 Figure 2-8: Revised the Changed from “8'-9" (2667)” to “9'-0" (2743)”
maximum couch arc
clearance dimension
209 Vol. 15, No. 1 2.5 2-15 Figure 2-8: Revised the Changed from “7'-11" (2667)” to “8'-4 1/2"
minimum required couch (2553)”
arc clearance dimension
210 Vol. 15, No. 1 2.5 2-15 Figure 2-8: Added new
note for “Longitudinal
Axis Line”
215 Vol. 15, No. 1 2.7 2-21 Figure 2-12: Added new The Optional “Factory Break” Shipping
Optional “Factory Break” Configuration consists of a separated Stand and
Shipping Configuration Gantry
Layout
216 Vol. 15, No. 1 2.7 2-22 Figure 2-13: Added new
Shipping Configuration -
Weights layout
217 Vol. 15, No. 1 2.7 2-23 Figure 2-14: Added new
Minimum Rigging
Clearances for the
Standard Configuration
layout
218 Vol. 15, No. 1 2.7 2-24 Figure 2-15: Added new
Minimum Rigging
Clearances for the Optional
Factory Break
Configuration layout
219 Vol. 15, No. 1 Chapter 3 3-1 Figure 3-1: Updated the
couch arcs on the
Treatment Room
Overview, Sample Set-up
220 Vol. 15, No. 1 3.6 3-31 Revised Title Changed from “Calypso System (Optional)” to
“Calypso - Extracranial Radiosurgery
Subsystem (Optional)”
224 Vol. 15, No. 1 3.6.11.1 3-38 Added new note: “When
installing Camera #2 on the
GCX Optical Imaging post
the concrete ceiling height
must at or below 11'-6"
[3505] from finished floor.
If the concrete ceiling
mounting height is above
11'-6" [3505] from finished
floor use Section 3.6.11.2
to locate the Camera #2
ceiling mount load plate.”
225 Vol. 15, No. 1 3.6.11.1 3-39 Figure 3-33: Updated Changed from “4'-4" ± 1" [1320 ± 25] and 6'-2"
Camera #1 and Camera #3 ± 1" [1880 ± 25]” to “4'-4 3/16" ± 1" [1325 ±
Cartesian dimensions 25] and 6'-3 5/16" ± 1" [1928 ± 25]”
226 Vol. 15, No. 1 3.6.11.1 3-39 Figure 3-33: Updated Camera #2 now uses a GCX bracket and 18"
Camera #2 location [457] cantilever bar to attached to the GCX post
227 Vol. 15, No. 1 3.6.11.1 3-39 Figure 3-33: Added new
note: “Dimensions are to
the center of the Ceiling
Mount Load Plate”
228 Vol. 15, No. 1 3.6.11.1 3-39 Figure 3-33: Added new
note: “The ceiling mount
load plates should only be
installed after the
BaseFrame is grouted in
and isocenter is verified”
229 Vol. 15, No. 1 3.6.11.1 3-40 Figure 3-34: Updated Changed from “7'-6 9/16" ± 1" [2300 ± 25] at
Camera #1 and Camera #3 55°” to “7'-8 1/8" ± 2" [2340 ± 50] at 55.5° ±
Polar dimensions 1°”
230 Vol. 15, No. 1 3.6.11.1 3-40 Figure 3-34: Updated Camera #2 now uses a GCX bracket and 18"
Camera #2 location [457] cantilever bar to attach to the GCX post
232 Vol. 15, No. 1 3.6.11.1 3-40 Figure 3-34: Added new
note: “The ceiling mount
load plates should only be
installed after the
BaseFrame is grouted in
and isocenter is verified”
233 Vol. 15, No. 1 3.6.11.1 3-42 New Figure 3-36 Calypso
Camera #2 Mount
Location - Section View
234 Vol. 15, No. 1 3.6.11.2 3-43 Revised the description of Changed to “The following mounting location
the Acceptable Ceiling diagram applies to installations that are not able
Mount Load Plate Areas to obtain an unobstructed path to overhead
concrete mounting surface by using a Varian
provided post and cantilever extension bar.”
235 Vol. 15, No. 1 3.6.11.2 3-44 New Figure 3-37
Acceptable Camera Mount
Areas - Plan View
236 Vol. 15, No. 1 3.6.12 3-45 Figure 3-38: Updated the Changed the to the “Osprey” Camera
Calypso Infrared Camera -
Layout
237 Vol. 15, No. 1 3.6.13.1 3-46 Added new note: “The
ceiling mount load plates
should only be installed
after the BaseFrame is
grouted in and isocenter is
verified”
238 Vol. 15, No. 1 3.6.13.2 3-47 Removed Figure 3-42
Ceiling Mount Load Plate
Location w/Cantilever
Extension Bar
239 Vol. 15, No. 1 3.7 3-48 Revised Section Title Changed from “OSMS System (Optional)” to
“OSMS - - Intracranial Radiosurgery
Subsystem (Optional)”
240 Vol. 15, No. 1 3.8.4.1 3-60 Revised the Stand and Changed from “5.0 kW (17,065 Btu/hr)” to
Gantry Air Heat Load “5.25 kW (17,930 Btu/hr)”
during Ready and
Beam-On states.
241 Vol. 15, No. 1 3.8.4.1 3-60 Revised the Modulator Air Changed from “7.0 kW (23,891 Btu/hr)” to
Heat Load during “7.25 kW (24,760 Btu/hr)”
Beam-On state
242 Vol. 15, No. 1 3.8.4.1 3-60 Removed the Side by Side
and Split Configurations
from the TrueBeam
Control Console
248 Vol. 15, No. 1 3.11 3-70 Figure 3-57: Revised the Changed from “9'-7" [2921] and 11'-0" [3353]”
isocenter to rear to “To Rear Concrete Wall (15'-0" max.)”
BaseFrame Pit dimension
249 Vol. 15, No. 1 3.11 3-70 Figure 3-57: Revised the Changed from “11" [279]” to “10" [254]”
lateral offset dimension
from isocenter to the center
of the cooling line conduit
sleeves at back of the
BaseFrame
250 Vol. 15, No. 1 3.12 3-71 Figure 3-58: Revised the Changed from “11" [279]” to “10" [254]”
lateral offset dimension
from isocenter to the center
of the cooling line conduit
sleeves at back of the
BaseFrame
251 Vol. 15, No. 1 3.12 3-71 Figure 3-58: Revised the Changed “4'-0" [1219]” to “2'-6" [760]”
lateral offset dimension
from isocenter to the center
of the customer supplied
cooling lines on the rear
concrete wall
266 Vol. 15, No. 2 3.3.2 3-16 Figure 3-10: Added the
Modulator pull box cover
plate to the “Left” moving
modulator configuration
layout
267 Vol. 15, No. 2 3.3.2 3-16 Figure 3-10: Revised the Changed from “The contractor-provided
note for the Modulator pull drop-in anchor is not required for the Left
box cover plate drop-in Moving Modulator configuration.” to “Drill
anchor and install (1) 1/4" x 20 x 1" contractor-
provided drop-in anchor 2" [50] from the right
edge Modulator pull box on both Left and Right
Moving configurations.”
271 Vol. 15, No. 2 3.11 3-69 Figure 3-56: Revised the Changed from “94" (2388)" to "86" (2185)”
cooling conduit sleeve
maximum length limitation
272 Vol. 15, No. 2 3.11 3-70 Figure 3-57: Added Added “9'-7" to 15'-0" (2921 to 4572)”
minimum and maximum
isocenter to rear concrete
wall dimension for the
Baseframe pit
273 Vol. 15, No. 2 3.11 3-70 Figure 3-57: Revised the Changed from “94" (2388)" to "86" (2185)”
cooling conduit sleeve
maximum length limitation
274 Vol. 15, No. 2 3.12 3-71 Figure 3-58: Revised the Changed from “20" (508)" to "30" (762)”
maximum distance from
the end of conduit to the
NPT valves
275 Vol. 15, No. 2 3.12 3-71 Figure 3-58: Revised the Changed from “94" (2388)" to "86" (2185)”
cooling conduit sleeve
maximum length limitation
276 Vol. 15, No. 2 3.12 3-72 Figure 3-59: Revised the Changed from “20" (508)" to "30" (762)”
maximum distance from
the end of conduit to the
NPT valves
277 Vol. 15, No. 2 3.12 3-72 Figure 3-59: Revised the Changed from “94" (2388)" to "86" (2185)”
cooling conduit sleeve
maximum length limitation
278 Vol. 15, No. 2 3.12 3-73 Figure 3-60: Revised the Changed from “20" (508)" to "30" (762)”
maximum distance from
the end of conduit to the
NPT valves
279 Vol. 15, No. 2 3.12 3-73 Figure 3-60: Revised the Changed from “94" (2388)" to "86" (2185)”
cooling conduit sleeve
maximum length limitation
284 Vol. 15, No. 3 3.6.4 3-32 Figure 3-28: Revised the Changed from “Power Supply/Hub and Related
figure name System Components” to “Camera Power
Supply and Hub Unit”
285 Vol. 15, No. 3 3.7.1 3-48 Revised OSMS Changed from “120V” to “100-240V @
Workstation voltage power 50/60 Hz”
range
286 Vol. 15, No. 3 3.7.1 3-48 Added physical 6.6"w x 1"h x 5"d (170 x 25 x 130), 1.3 lbs
specifications for the KVM (0.6 kg)
switch
287 Vol. 15, No. 3 3.7.1 3-48 Added physical 7"w x 4"h x 10.5"d (170 x 95 x 270), 16.5 lbs
specifications for the (7.5 kg)
600VA Isolation
transformer
288 Vol. 15, No. 3 3.7.1 3-48 Added the power The PSU requires one 100-240V @ 50/60 Hz
requirement for the OSMS switched power receptacle
PSU
289 Vol. 15, No. 3 3.7.3 3-49 Revised OSMS Remote Changed from “120V” to “100-240V @
Terminal voltage power 50/60 Hz”
range
290 Vol. 15, No. 3 3.7.3 3-49 Added physical 6.6"w x 1"h x 5"d (170 x 25 x 130), 1.3 lbs
specifications for the KVM (0.6 kg)
switch
291 Vol. 15, No. 3 3.7.3 3-49 Added physical 6"w x 3.5"h x 9.5"d (150 x 85 x 240), 9.9 lbs
specifications for the (4.5 kg)
300VA Isolation
transformer
292 Vol. 15, No. 3 3.7.3 3-49 Added physical 16"w x 16.5"h x 7.5"d (404 x 419 x 188),
specifications for the 8.5 lbs (3.83 kg)
Remote Terminal Monitor
293 Vol. 15, No. 3 3.7.4.1 3-50 Figure 3-45: Added a
100-240V @ 50/60 Hz
receptacle for the Remote
Terminal
294 Vol. 15, No. 3 5.1 5-5 Figure 5-3: Revised the Changed from “March 2015” to
Valid for Equipment “July/August 2015”
delivery date
314 Vol. 15, No. 4 Chapter 4 4-1 Table 4-1: Revised Changed from “30A” to “20A”
Console 50Hz Amperage
315 Vol. 15, No. 4 Chapter 4 4-1 Table 4-1: Revised the Changed from “These feeds can be supplied” to
footnote “These feeds are supplied”
xv
3.5 Minor System Components – Live View Camera, CCTV, VVS, and
Intercom Subsystems................................................................................................... 3-26
3.5.1 Live View Camera Subsystem ......................................................................... 3-27
3.5.1.1 Live View Mounting Locations and Method ............................................. 3-27
3.5.1.2 Dedicated Ground Wire – Live View Camera.......................................... 3-27
3.5.2 Closed Circuit TV (Motion View) Subsystem.................................................... 3-28
3.5.2.1 Mounting Locations ................................................................................. 3-28
3.5.3 Audio Subsystem – Microphone(s) and Speakers ........................................... 3-30
3.5.3.1 Dedicated Ground Wire – Microphone(s) ................................................ 3-30
3.6 Calypso Extracranial Radiosurgery Subsystem (Optional) .......................................... 3-31
3.6.1 Treatment Room Console ................................................................................ 3-31
3.6.2 Array Panel....................................................................................................... 3-32
3.6.3 Touch Screen Computer .................................................................................. 3-32
3.6.4 Optical System ................................................................................................. 3-32
3.6.4.1 Infrared Cameras..................................................................................... 3-33
3.6.4.2 Camera Power Supply/Hub Unit.............................................................. 3-33
3.6.5 Tracking Station ............................................................................................... 3-33
3.6.6 Beacon Transponders ...................................................................................... 3-34
3.6.7 Software ........................................................................................................... 3-34
3.6.8 Fixtures............................................................................................................. 3-34
3.6.8.1 QA Fixture ............................................................................................... 3-34
3.6.8.2 Calibration Fixtures.................................................................................. 3-35
3.6.9 System Options ................................................................................................ 3-35
3.6.9.1 Radiation Detector................................................................................... 3-35
3.6.9.2 Dynamic Edge Gating.............................................................................. 3-35
3.6.9.3 Adaptive Couch Repositioning ................................................................ 3-36
3.6.9.4 Treatment Planning Data Import ............................................................. 3-36
3.6.10 Calypso System Assembly............................................................................... 3-37
3.6.10.1 Typical Room Configuration .................................................................... 3-37
3.6.11 Camera Mounting Locations ............................................................................ 3-38
3.6.11.1 Preferred Ceiling Mount Load Plate Locations ........................................ 3-38
3.6.11.2 Acceptable Ceiling Mount Load Plate Areas ........................................... 3-43
3.6.12 Camera Elevation Heights and Clearances ..................................................... 3-45
3.6.13 Camera Support Mounting Methods ................................................................ 3-46
3.6.13.1 Ceiling Mount Load Plate ........................................................................ 3-46
3.6.13.2 Ceiling Mount Cantilever Extension Bar .................................................. 3-47
3.6.14 Shipping/Rigging Dimension Clearances ......................................................... 3-47
3.7 OSMS Intracranial Radiosurgery Subsystem (Optional).............................................. 3-48
3.7.1 OSMS Workstation........................................................................................... 3-48
3.7.2 OSMS Optical System...................................................................................... 3-48
3.7.3 Treatment Room Remote Terminal.................................................................. 3-49
GLOSSARY...................................................................................................................GLOSSARY-1
xx Table of Contents
List of Figures
CHAPTER 2
Figure 2-1 Typical Room Isometric View .......................................................................... 2-5
Figure 2-2 Typical (Intermediate) Room Plan View .......................................................... 2-7
Figure 2-3 Typical (Intermediate) Room Section .............................................................. 2-9
Figure 2-4 Typical (Intermediate) Vault Configuration - Exterior Primary Barriers.......... 2-11
Figure 2-5 Traditional (Large) Vault Configuration.......................................................... 2-11
Figure 2-6 Minimum Vault Configuration - Direct Entry (Silhouette Retrofit) .................. 2-13
Figure 2-7 Minimum Vault Configuration - Maze Entry (Silhouette Retrofit) ................... 2-13
Figure 2-8 Plan View....................................................................................................... 2-15
Figure 2-9 Side Elevation................................................................................................ 2-17
Figure 2-10 Front Elevation .............................................................................................. 2-19
Figure 2-11 Standard Shipping Configuration — Dimensions .......................................... 2-20
Figure 2-12 Optional “Factory Break” Shipping Configuration — Dimensions.................. 2-21
Figure 2-13 Shipping Configuration — Weights................................................................ 2-22
Figure 2-14 Minimum Rigging Clearances for the Standard Configuration ...................... 2-23
Figure 2-15 Minimum Rigging Clearances for the Optional Factory Break Configuration 2-24
CHAPTER 3
Figure 3-1 Treatment Room Overview, Sample Set-up.................................................... 3-1
Figure 3-2 Typical TrueBeam Conduit Diagram (Plan View) ............................................ 3-5
Figure 3-3 Typical TrueBeam Conduit Diagram (Section View) ....................................... 3-7
Figure 3-4 Modulator Cabinet, Plan View ......................................................................... 3-9
Figure 3-5 Modulator Cabinet, Elevation View................................................................ 3-10
Figure 3-6 Left Moving Modulator Pull Box Location ...................................................... 3-12
Figure 3-7 Right Moving Modulator Pull Box Location.................................................... 3-13
Figure 3-8 Moving Modulator Cabinet – Plan View......................................................... 3-14
Figure 3-9 Moving Modulator Cabinet – Elevation View ................................................. 3-15
Figure 3-10 Moving Modulator Floor Positioning – Plan View .......................................... 3-16
Figure 3-11 Optical Imaging and In-Room Monitors (Typical) – Front Elevation .............. 3-17
Figure 3-12 TrueBeam Optical Imaging Mount – Plan View............................................. 3-18
Figure 3-13 TrueBeam Optical Imaging Mount – Elevation Views ................................... 3-19
Figure 3-14 Ceiling Mounting Plate – Optical Imaging Camera........................................ 3-20
Figure 3-15 Dual In-Room Monitor Mount – Plan View .................................................... 3-22
Figure 3-16 Dual In-Room Monitor Mount – Elevation View............................................. 3-23
Figure 3-17 Ceiling Mounting Plate – In-Room Monitor Bracket....................................... 3-24
Figure 3-18 Alternate Wall-Mount Dual In-Room Monitor Installation............................... 3-25
xxi
Figure 3-19 Interior Elevation – Component Location ...................................................... 3-26
Figure 3-20 Live View Camera – Wall Mount (Section View) ........................................... 3-27
Figure 3-21 Typical CCTV System Diagram..................................................................... 3-28
Figure 3-22 Multiple CCTV Camera Locations – Elevation .............................................. 3-29
Figure 3-23 Treatment Room Speaker, Microphone, and Live View Camera
Layout: Top View........................................................................................... 3-30
Figure 3-24 Treatment Room Console ............................................................................. 3-31
Figure 3-25 Array Panel.................................................................................................... 3-31
Figure 3-26 Touch Screen Computer ............................................................................... 3-31
Figure 3-27 Infrared Camera ............................................................................................ 3-32
Figure 3-28 Camera Power Supply and Hub Unit ............................................................ 3-32
Figure 3-29 Tracking Station, Keyboard, Monitor, and Mouse ......................................... 3-33
Figure 3-30 Beacon Transponder..................................................................................... 3-34
Figure 3-31 Radiation Detector......................................................................................... 3-35
Figure 3-32 Calypso System Conduit Diagram – Typical Plan View ................................ 3-37
Figure 3-33 Preferred Ceiling Mount Load Plate Locations – Plan View
(Cartesian Dimensions)................................................................................. 3-39
Figure 3-34 Preferred Ceiling Mount Load Plate Locations – Plan View
(Polar Dimensions)........................................................................................ 3-40
Figure 3-35 Preferred Ceiling Mount Load Plate Locations – Typical Section ................. 3-41
Figure 3-36 Calypso Camera #2 Mount Location – Section View .................................... 3-42
Figure 3-37 Acceptable Camera Mount Areas – Plan View ............................................. 3-44
Figure 3-38 Calypso Infrared Camera – Typical Elevation ............................................... 3-45
Figure 3-39 Ceiling Mount Load Plate – Infrared Camera ................................................ 3-46
Figure 3-40 Ceiling Mount Load Plate – Isometric............................................................ 3-46
Figure 3-41 Cantilever Extension Bar............................................................................... 3-47
Figure 3-42 Camera with Cantilever Extension Bar.......................................................... 3-47
Figure 3-43 OSMS Camera .............................................................................................. 3-48
Figure 3-44 OSMS Power Supply Unit (PSU) .................................................................. 3-48
Figure 3-45 OSMS System Conduit Diagram – Typical Plan View .................................. 3-50
Figure 3-46 OSMS Camera Mount Locations – Plan View............................................... 3-51
Figure 3-47 OSMS Camera Mount Locations – Section View.......................................... 3-52
Figure 3-48 OSMS Camera – Typical Elevation............................................................... 3-53
Figure 3-49 Ceiling Mount Load Plate – OSMS Camera.................................................. 3-54
Figure 3-50 Minimum Coolant Flow Requirements .......................................................... 3-56
Figure 3-51 TrueBeam Coolant System Diagram............................................................. 3-57
Figure 3-52 TrueBeam Baseframe Pit Dimensions .......................................................... 3-65
Figure 3-53 TrueBeam Baseframe Installed..................................................................... 3-66
Figure 3-54 Grout After Baseframe Installation ................................................................ 3-67
CHAPTER 4
Figure 4-1 Ground/Earthing Conductor Diagram .............................................................. 4-5
Figure 4-2 Interconnection Wiring Diagram .................................................................... 4-15
Figure 4-3 Varian Relay Junction Box ............................................................................ 4-23
CHAPTER 5
Figure 5-1 Typical Control Equipment Layout, 2-1 Cabinet Configuration........................ 5-1
Figure 5-2 TrueBeam/VitalBeam 2-1 Cabinet Floor Positioning Bracket
Installation – Plan View ................................................................................... 5-3
Figure 5-3 Control Equipment Layout, Stacked Configuration.......................................... 5-5
Figure 5-4 ARIA Treatment Workstation (Optional) .......................................................... 5-7
Figure 5-5 Typical Room Storage Elevation ..................................................................... 5-8
Figure 5-6 Wedge Storage................................................................................................ 5-9
Figure 5-7 Block Storage ................................................................................................ 5-10
Figure 5-8 Applicator Storage ......................................................................................... 5-11
Figure 5-9 Typical Reflected Ceiling Plan....................................................................... 5-14
CHAPTER 2
Table 2-1 Typical Shielding for Standard Procedures......................................................2-1
Table 2-2 Typical Shielding for Standard Procedures with 50% IMRT of a Factor F=3...2-1
Table 2-3 Typical Shielding for SRS Procedures with 20% IMRT of a Factor F=3..........2-2
Table 2-4 Concrete to Lead and Steel Ratios..................................................................2-2
Table 2-5 Tenth Value Layer (TVL) for Concrete vs. X-Ray Energy ................................2-2
Table 2-6 Typical Minimum TrueBeam Room Door Shielding .........................................2-3
Table 2-7 Quality of X-Ray Beams (BJR 11 vs. BJR 17 Values) .....................................2-3
CHAPTER 3
Table 3-1 Ideal Mechanical Specifications.....................................................................3-55
Table 3-2 TrueBeam Coolant Requirements .................................................................3-58
Table 3-3 Coolant Specifications for External and Internal Water Sources ...................3-59
CHAPTER 4
Table 4-1 Recommended Power Specification Summary ...............................................4-1
Table 4-2 TrueBeam/VitalBeam Linear Accelerator Power Requirements ......................4-9
xxv
This page intentionally left blank.
The Varian Medical Systems, Inc. TrueBeam is the only system specifically designed to deliver both
radiotherapy and radiosurgery. A sophisticated and highly intelligent technology, this breakthrough
system unlocks the ability to do tailored ground-breaking treatments with unprecedented ease,
versatility, and speed. The TrueBeam system brings together state-of-the-art, real time imaging with
the ability to deliver higher doses with high precision. Because of this intelligent design, physicians
are able to treat more complex cases and more patients. As sophisticated as it is, the TrueBeam system
has been developed for ease of use. Single-button operation and fast treatments are the cornerstone of
a system that optimizes clinical workflow. Designed with an emphasis on efficiency, the TrueBeam
system is easy for a technician or a clinician to learn and operate.
TrueBeam/VitalBeam Accelerator
Multiple Full Field (40 x 40) Photon Energy Accelerator @ 600 MU/min in High Intensity
Mode (HIM).
High Intensity Mode Beams.
6MV@1400 MU/min in HIM.
10MV @ 2400MU/min in HIM with HD MLC (TrueBeam only).
Up to Nine (9) Electron Energies.
Standard 80, 120, or High Definition 120 Leaf MLC.
Standard Definition 80 leaf MLC with 10mm leaves. Maximum field size of 40 x 40 for fixed
field (VitalBeam only).
Standard Definition 120 leaf MLC with 5mm leaves for the central 20cm and 10mm leaves
for the external 10cm on each side. Maximum field size of 40 x 40 for fixed field and
32 x 40 for IMRT (TrueBeam only).
Optional High Definition 120 leaf MLC with 2.5 mm leaves for the central 8cm and 5mm
leaves for the external 7cm on each side. Maximum field size of 22 x 40 for fixed field and
22 x 32 for IMRT (TrueBeam only).
Integrated MV Portal Imaging system with 1024 x 768 resolution, option for VitalBeam.
.5mm radius Isocenter (Gantry/Collimator), .75mm radius Isocenter (Gantry/Collimator/Couch).
1-1
Technical Key Features TrueBeam/VitalBeam Edition
Integrated Imaging
Gantry mounted Oil cooled kV X-ray tube and Amorphous Silicon Imaging panel.
Robotic arms allowing both in room and console area control for retracting imaging system and
moving into position.
Radiographic Mode: Allowing Stereoscopic Imaging including Marker matching mode.
Cone Beam CT: 3D Imaging with full 3D Volumetric Matching Capabilities, option on
VitalBeam.
Allowing sub-cGy volumetric Cone Beam CT acquisition in both full (360 degrees) and half
rotation (200 degrees) modes.
Fluoroscopic Mode: Allowing Pre-treatment Fluoro verification of treatment field.
This document provides essential information and detailed descriptions about the
TrueBeam/VitalBeam Edition’s installation requirements.
Note: Varian highly recommends you read this document prior to the baseframe and
pre-installation kit delivery. To ensure a simple and timely system installation, several
pre-working/pre-assembly steps must be accomplished. It is also very important to
inform Varian of all information regarding the hospital’s electrical and spatial
conditions.
Note: This DDR does not apply to Clinac 2100C/D, Clinac 21EX, Clinac 23EX, Clinac iX,
Silhouette, Novalis Tx, Novalis Tx Silhouette, or Trilogy.
For unsupported accelerators, as described above, please contact your Regional Planner or Varian’s
Global Planning Department for the appropriate planning documents at:
Varian Medical Systems
Planning Group, Site Services
660 N. McCarthy Blvd., Milpitas, CA 95035
Phone: (800) 278-2747 or (408) 232-4231
Email: planning@varian.com
http://www.varian.com/us/oncology/services_and_support/architectural_planning/contact.html
The IPA for the TrueBeam will begin no later than the 5th week, barring unforeseen conditions, and
will require full-time services of the site physicist.
The Sample timeline is based on the following assumptions and is in a perfect world scenario.
The Design and Planning, Contract Bid and Mobilization, and Construction processes shall take
5 weeks, 3 weeks, and 9 weeks, respectively, after the placement of the TrueBeam accelerator
order. Activities prior to order placement are not considered in this timeline.
The accelerator rig date shall be no earlier than 120 days after the order initiation date. This is
Varian’s standard manufacturing lead time.
The Baseframe shall be installed ~30 days prior to the accelerator rig date.
All pre-installation dates and considerations are individually scheduled by the Varian Project
Manager, based on mutual agreement between the customer and project manager and
communications with Varian Planning and Sales. The District Sales Manager will coordinate with the
customer and the Varian Project Manager for a Configuration Confirmation Meeting or conference
call. The Project Manager will engage the customer with regular communications throughout all
phases of the project. In addition, the Project Manager typically performs site visits to help answer
questions and observe construction progress. Site visits are commonly held for the Initial Site
Meeting/Project Kickoff, the Baseframe Pre-Installation Inspection or the Baseframe installation, and
the Construction Completion/Pre-Installation Final Inspection. This final visit typically occurs 10-14
days prior to the rig date to verify 100% completion as defined by the TrueBeam Final Checklist.
ID Task Name Duration Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30
0 TrueBeam Timeline - Sample 141 days 01/06 07/20
1 Project Launch 35 days 01/06 02/21
2 Receive Installation Request (GPOT) 1 day 01/06 01/06
3 Create project, include all equipment / upgrades 1 day 01/07 01/07
4 Send Letter of Introduction to Client 1 day 01/07 01/07
5 Prepare ALL Sales Orders & Project Folders 1 day 01/07 01/07
6 Ensure Customer has DDR Iinformation 1 day 01/08 01/08
7 Review Sales Order w/ Sales and Contract Admin 1 day 01/14 01/14
8 Schedule customer kick-off meeting / site visit 1 day 01/15 01/15
9 Obtain Drawing Review from Varian Planning 3 wks 01/15 02/04
10 Confirm Drawing Review Comment Responses 2.6 wks 02/05 02/21
11 First Site Visit 5 days 01/29 02/05
12 Joint Initial Site Meeting 0 days 01/29
13 Review Sales Order & Customer's P.O. 1 day 01/30 01/30
14 Review Pre-Installation Check List 1 day 01/30 01/30
15 Verify Pulse Cables Less than 50Ft 1 day 01/30 01/30
16 Coordinate Room Readiness and Delivery Dates 1 day 01/30 01/30
Sa
17 Deliver State's Radiation License Letter 1 day 01/30 01/30
18 Prepare & Distribute Site Visit Report 1 day 01/31 01/31
19 Remedy Sales Order Problems 3 days 02/03 02/05
20 Initial Site Meeting Follow-up Complete 0 days 02/05
21 Customer Site Preparation 85 days 01/06 05/01
22 Existing Equipment Removal (If Applicable) 1.5 days 02/29 03/01
26 Desing and Planning 5 wks 01/06 02/07
27 Bid Process and Mobilization 3 wks 02/28
28 Construction/ Site Preperation 9 wks 03/02 05/01
29 TrueBeam Project 96 days 03/09 07/20
30 03/09 05/07
mp
TrueBeam Pre-Installation Coordination 44 days
31 MICAP Recived by Customer 0 days 04/13
32 MICAP Submitted by Customer & Posted to FTP Website 0 days 04/17
33 Issue Argus / Argus IMRT Pre-Install Survey 0 days 04/20
34 Request TrueBeam S/W Support 0 days 04/13
35 Schedule Outside Vendor Shipping & Delivery 1 day 03/09
36 Baseframe Coordination 1 day 03/
03/09
37 Confirm Baseframe Configuration, Availability & Shipping D 1 day 03/0
03/09
38 Schedule Baseframe installation with Site Contractor 1 day 03/0
03/09
39 Issue Baseframe Ship Request 1 day 03/09
40 Schedule Baseframe Rigger (3 week lead-time) 1 day 03/09
41 Pre-Baseframe Installation Visit 2 days
le
42 Complete Pre-Baseframe Installation Inspection 1 day
43 Obtain conduit lengths from Contractor 1 day
44 Release Baseframe for Delivery 1 day
45 Baseframe Installation - TrueBeam 1 day 03/31
46 Request Interconnect Cables (3 week lead time) 1 day
47 Final Site Coordination 12 days 05/07
48 Issue TrueBeam Ship Request 1 day
49 Confirm Extended Rigging Contractor 1 day
50 Inform Applications Department of Rig Dates 1 day 05/06
51 Final Site Inspection 3 days
52 Complete Pre-Installation Checklist 1 day
53 Confirm Radiation License Requirements Complete 1 day
54 Distribute Site Status and Pre-Installation Checklist 1 day 05/05
55 Confirm All Site Readiness Items Complete 1 day 05/07
56 Release Equipment for Delivery 1 day 05/05
57 TrueBeam System Installation 40 days 05/15 07/09
58 TrueBeam Installation 39 days 05/15 06/22
59 TrueBeam Start 1 day 05/15
60 Equipment Rig-In 2 days 05/15 05/16
61 Clinac Extended Rig-In 3 days 05/17 05/19
62 Electrical and Mechanical Setup/Test 34 days 05/20 06/22
63 Winston-Lutz Testing & Fine Isocenter Adjustment 1 day 06/04
64 4D ITC Installation & Integration 0 days 06/03
65 Customer Acceptance Testing 3 days 06/23 06/25
66 Varian Customer Acceptance Procedure 3 days 06/23 06/25
67 TrueBeam Complete 0 days 06/25
68 Physics Commissioning (Time Varies ) 2 wks 06/26 07/09
69 TrueBeam Education & Training 46 days 05/18 07/20
70 Varian Education - Las Vegas 5 days 05/18 05/22
71 Varian Education Cntr - OBI Clinical Implementation for Phy 5 days 05/18 05/22
72 Varian Education Cntr - OBI Clinical Implementation for RTs 3 days 05/18 05/20
73 Varian Education Cntr - Cone Beam CT eLearning 0 days 05/22
74 Varian Applications Training 5 days 07/14 07/20
75 TrueBeam Applications Training 2 days 07/14
76 OBI Applications Training 2 days 07/16
77 CBCT v1.x Applications Training 1 day 07/20
Project: TrueBeam Timeline - Sample Task Critical Task Slack Completed Milestone Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
Date: Thu 07/22/10
Task Progress Critical Task Progress Milestone Critical Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
Page 1
WARNING: Varian Medical Systems shall have no approval or other responsibility for any
matter affecting or related to the adequacy of the radiation protection walls and
barriers or related safety devices. All radiation shielding designs must meet codes
and regulations of all Authorities Having Jurisdiction (AHJ) and must be
approved by the Customer’s or Facility’s Physicist of Record and shall be the sole
responsibility of the Customer/Facility. The hours of operation, patient workload,
accelerator energy, and the shielding materials should all be taken into
consideration when calculating shielding requirements. Serious injury or death
can result from improper radiation shielding.
Table 2-2 Typical Shielding for Standard Procedures with 50% IMRT of a Factor F=3
2-1
Typical Room Shielding Tables TrueBeam/VitalBeam Edition
Table 2-3 Typical Shielding for SRS Procedures with 20% IMRT of a Factor F=3
4 MV 6 MV 8MV 10 MV 15 MV 18 MV 20 MV
Steel Primary Barrier 3.5 3.7 3.8 4.0 4.0 4.1 4.2
Secondary Barrier 3.2 3.5 3.6 3.6 3.8 3.8 3.9
Lead Primary Barrier 6.1 6.5 7.0 7.2 7.7 7.9 8.1
Secondary Barrier 5.4 6.2 6.3 6.6 7.0 7.0 7.0
Note: Inches (mm) of 147 lbs./cu. ft. (2355 kg/cu. M) Concrete Equal to Inches (mm) of Lead/Steel.
Table 2-5 Tenth Value Layer (TVL) for Concrete vs. X-Ray Energy
4 MV 6 MV 8 MV 10 MV 15 MV 18 MV 20 MV
Primary Beam X-Rays 11.4 (290) 13.5 (343) 14.3 (363) 15.3 (389) 17.0 (432) 17.5 (455) 18.0 (457)
Leakage X-Rays (90°) 10.0 (254) 11.0 (279) 11.5 (292) 12.0 (305) 13.0 (330) 13.0 (330) 13.5 (343)
Note: Inches (mm) of 147 lbs./cu. ft. (2355 kg/cu. M) Concrete.
4 MV 6 MV 8 MV 10 MV 15 MV 18 MV 20 MV
Lead 1/8 (3) 1/8 (3) 1/4 (6) 1/4 (6) n/a n/a n/a
Wood 2 (51) 2 (51) 3 (76) 3 (76) n/a n/a n/a
Lead n/a n/a n/a n/a 1/4 (6) 3/4 (19) 3/4 (19)
5% Borated Polyethylene n/a n/a n/a n/a 3 (76) 4 (102) 5 (127)
Steel-Both Sides n/a n/a n/a n/a 1/4 (6) 1/4 (6) 1/4 (6)
Note: Thickness in Inches (mm).
Modulator Cabinet
In-Room
Monitor
A sink with running hot and cold water is highly recommended
in Accelerator rooms. A hose spigot is necessary to fill the
water phantom, and a drain is necessary to service the
TrueBeam's internal cooling system and drain the water phantom. Line of
Floor drains and floor sinks should not be located in the Baseframe
room to avoid possible backup into the equipment floor TrueBeam pit.
recesses. Do not run water lines directly above the Door Actuator Couch
Accelerator components or control console. Switch
The patient's position on the Couch is fixed by body markings that are
aligned with "cross hairs" cast by the laser lights. Two wall laser positioning
lights at isocenter height, a ceiling laser and the sagittal laser are
Two-way verbal communication with the patient is required. The two powered by a common circuit controlled via the user interface in the
speakers should be located as shown in Figure 3-18. Speakers can Control Room or Couch Pendant or Couch Side Panels, through a relay.
be furnished with the TrueBeam system as an option, are Lasers are usually distributed and installed, at the Customer's option, by
Contractor-installed, and should be installed per the manufacturer’s Varian. The Customer is responsible for verification of laser types and
instructions. See section 3.5.3 for additional information. Beam-on and x-ray on lights. mounting configurations.
Emergency-off switches.
The layouts shown on DDR drawings represent typical plans only. Clearances and wall thickness may vary.
The sagittal laser positioning light is located on the wall at the end of
the longitudinal couch axis. Unlike the side lasers, which are at
isocenter height, the sagittal laser is typically mounted at a laser output
height of 7'-6" (2286) above the floor. Secondary shielding
Live View camera. This special radiation-hardened CCTV camera is Varian- Isocenter - This is the primary reference point for Varian equipment.
furnished, Contractor-installed. For installation details, see Figure 3-15. Show the isocenter location clearly on all relevant drawings. Maintain
the isocenter location on site by extending perpendicular axis lines
along slab and up walls in all four directions. The standard isocenter
There are no recognized acoustical standards for therapy rooms. The primary height for TrueBeam is 4'-3" (1295).
sound source on dual energy TrueBeam systems is the Modulator Cabinet. Modulator
Varian has met no acoustical problems when the Modulator is located in the Cabinet
treatment room. The patients are in the room for a very short time and some The patient's position on the Couch is fixed by body markings that
seem reassured by the changing sound levels as the machine goes through its are aligned with "cross hairs" cast by the laser lights. Two wall laser
cycles. Noise is a concern, however, when the Modulator Cabinet is located positioning lights at isocenter height, a ceiling laser and the sagittal
next to therapists or others who are exposed to it often. Placing the Modulator laser are powered by a common circuit controlled via the user
in a nearby closet is acceptable. Consult with the Customer regarding preferred interface in the Control Room or Couch Pendant or Couch Side
location. The use of acoustically absorbent materials is recommended. Panels, through a relay. Lasers are usually distributed and installed,
at the Customer's option, by Varian. The Customer is responsible for
verification of laser types and mounting configurations.
This dimension is provided for illustrative purposes only. Actual dimensions will
vary with shielding requirements and construction practices.
The two side laser positioning lights are located on the side walls at
isocenter height.
The layouts shown on DDR drawings represent typical plans only. Clearances and This is the recommended dimension to concrete. Recommended
wall thickness may vary. face of concrete dimensions assume up to 6" (150) of wall furring.
To reduce radiation exposure outside room, air handling ducts should The sagittal laser positioning light is located on the Exposed grid ceilings allow for access to the
enter/exit the room through penetration(s) above the maze door. The wall at the end of the longitudinal couch axis. overhead laser and relay junction box without
ducts should be placed as high as possible in order to minimize radiation Unlike the side lasers, which are at isocenter height, the use of access doors. Major service at the
exposure to occupied space. The ducts should be designed to minimize the sagittal laser is typically mounted at a laser equipment Stand is simplified where there are
the area of penetration through the wall. In most cases, duct shielding will output height of 7'-6" (2286) above the floor. removable ceiling tiles. Coordinate the layout
not be required, provided the duct design conforms to this criteria. Clear of ceiling tile to insure that ceiling support
space should be left around the duct (outside the treatment room) for shielding Optical Imaging Camera. Locate 7’-6” (2286) system shall not interfere with overhead laser
retrofit, in case the post installation radiation survey indicates a requirement. from finished floor (F.F.) and the bracket at positioning light beam port.
Penetration, including ducts, directly into the treatment room should be avoided. 6’-7” (2007) from isocenter as shown.
For no-maze treatment rooms, duct design and shielding must be addressed by The overhead laser positioning light
the Physicist of Record. is located directly over the isocenter.
In-Room monitors locate
as shown 7’-0” above FF.
For safety reasons, locate
monitors such that the
If possible, provide two 4" (100) conduits tight therapist doesn’t need to
to the ceiling, adjacent to the mechanical duct look away from the patient
opening, to facilitate cable access for future to view the monitors. For
room renovations. Review all vault penetrations mounting details, see
with the Physicist of Record. Section 3.4.2.
Isocenter - This is the primary reference point for A steel frame is used to anchor the TrueBeam Stand, Gantry,
Varian equipment. Show the isocenter location and Couch to the facility. The frame is set in a recessed
clearly on all relevant drawings. Maintain the equipment pit, leveled (by Varian), and held in place with
isocenter location on site by extending grout. Baseframes are positively anchored to the slab to avoid
perpendicular axis lines along slab and up floating during grout placement. Verify anchorage details with
walls in all four directions. The standard isocenter your Installation Project Manager office. Varian information
height for TrueBeam is 4'-3" (1295). regarding pit design assumes a ground floor installation.
Upper floor installations require a thorough review by a
qualified structural engineer. In typical installations,
The layouts shown on DDR drawings represent typical plans only. Clearances and wall thickness may vary. Baseframes for TrueBeams are not positively anchored
sufficiently to accommodate seismic loads. All seismic
anchoring is by the Customer. Sample seismic calculations
and details of the preferred anchoring methods for
TrueBeams are available from the Planning Department.
Figure 2-3 Typical (Intermediate) Room Section
Figure 2-4 Typical (Intermediate) Vault Configuration - Exterior Primary Barriers Figure 2-5 Traditional (Large) Vault Configuration
Figure 2-6 Minimum Vault Configuration - Direct Entry (Silhouette Retrofit) Figure 2-7 Minimum Vault Configuration - Maze Entry (Silhouette Retrofit)
The TrueBeam Couch with IGRT Couch top is standard with the TrueBeam.
The maximum Couch Arc clearance is 9'-0" (2743) - recommended.
The minimum REQUIRED Full Couch Arc clearance is 8'-4 1/2" (2553). This is the recommended minimum clear distance
to the side wall for full couch rotation. Provide
The recommended couch arc clearance allows complete rotation of the adequate additional clearance for side lasers.
Couch at its maximum radius (retracted). Obstructions inside the Longitudinal axis line
minimum required couch arc are unacceptable. However obstructions
between the minimum required couch arc and the maximum couch arc
may be acceptable provided they are reviewed and approved by Varian
and the Customer. In specific situations, such as dynamic stereotactic
treatment, a larger area may be required.
Isocenter - This is the primary reference point for
The couch top must be able to extend out to the maximum distance of Varian equipment. Show the isocenter location
8'-9" [2667] at a minimum of at least one angle along the couch rotation clearly on all relevant drawings. Maintain the
arc for calibration testing. isocenter location on site by extending perpendicular
axis lines along slab and up walls in all four
directions. The standard isocenter height for
Minimum required Couch Arc. TrueBeam is 4'-3" (1295).
TrueBeam
Couch
Create an overlay sheet to simulate the Gantry rig clearances during Rigging is defined as the positioning of the Baseframe
the project planning stage. Use the DWG file to print the Gantry and Linear Accelerator components into the treatment
(plan-view) onto a clear sheet of acetate to ensure scale accuracy. room. The Baseframe is rigged prior to the rest of the
equipment and delivery must be scheduled by the
Verify adequate equipment access into room and around maze. construction Contractor with the Installation Project
Manager. As designated in the final Varian/Customer
The dimensions shown on the rig route details are to face of finish Terms and Conditions of Sale, a rigging company is
and represent minimum configurations only. Verify adequate rigging hired by the Customer or Varian to off-load these items
clearances for specific site using the Shipping Configuration overlay. from the truck and to move them through the facility
If the templates cannot be easily rotated through the maze without and into the treatment room. The Customer’s architect
wall obstruction, review by a qualified Rigger will be required. Varian and structural engineers shall review the entire rig
will review the installation route upon request. Coordinate all rigging route for adequate clearance and structural support.
with the Installation Project Manager. Final confirmation of rig route The work can include temporary demolition and
clearances and review of adequate structural support along shoring. Final equipment positioning is part
the route is the responsibility of the Customer and the of the rigging contract.
Structural Engineer of Record.
Figure 2-15 Minimum Rigging Clearances for the Optional Factory Break Configuration
3-1
Cable Conduit/Ducts TrueBeam/VitalBeam Edition
This might affect the choice of cable routes, number of conduits, specifications of
mains power and data cables, and the choice of installation locations of some of the
system components.
The customer shall provide conduit or raceways for all system cables, as described in
this section.
The customer must be aware that fire protection engineering aspects (plenum rating)
may be affected when installing cables and system components.
Ensure all components are placed so that the shortest cable length is sufficient.
TrueBeam conduit runs must not exceed 75 feet (22,860), start to finish.
All conduits run underground shall be dry and watertight. Therefore, all PVC pipes must be glued
together, and metal conduits must be properly sealed.
All conduits must be terminated with insulating bushings or similar means to protect cables from
abrasion.
The Control Equipment pull box shall have a minimum size of 30" x 12" x 6" (750 x 300 x 150). This
pull box may be mounted below the control counter top or recessed in the floor slab similar to details
in “Baseframe Cable Access Details” on page 3-69. Locate this pull box so that the free ends of cables
are protected from physical damage and located within 5'-0" (1524) of the TrueBeam Control Cabinet.
The Modulator pull box is recessed into the floor slab and shall be 18" x 24" x 10" deep (450 x 600 x
250). As no connections are made at this location, many regulatory agencies allow a pull box to be
formed within the concrete floor in lieu of requiring a metallic pull box. The size and location of the
Modulator Pull Box is very specific, in order to ensure proper placement of the Modulator and
Interconnect Cable access. See “Major System Components – Modulator Cabinet” on page 3-9 for
further details
Note: If a Moving Modulator is required to keep the Modulator out of the primary beam path,
see Section 3.3.2 for the Modulator Pull Box dimensions.
1. Standard, recessed pull box below the BF pit, see Figure 3-56.
2. Alternative, surface-mounted pull box, see Figure 3-57.
In methods 1 and 2 above, the BF pull box shall have a size of 12" x 24" x 10" deep (300 x 600 x 250).
As no connections are made at this location, many regulatory agencies allow a pull box to be formed
within the concrete BF pit floor in lieu of a metallic pull box.
Provide a signal pull box for each pair of Dual In-Room Monitors. This is a standard computer signal
cable outlet. If the signal cables are to be recessed, provide a signal outlet and conduits from the
in-room monitor to the Accessory Junction Box.
Provide a 24" x 18" x 12" (600 x 450 x 300) Junction Box. Locate above the finished ceiling space
near the foot of the couch. Vertical-mounting, on a wall or suspended from the concrete ceiling with
side access, is recommended. This pull box serves as a collection/distribution point for the cable
conduits between the control console and all ancillary accelerator subsystems, such as In-Room
Monitor, Optical Imaging, Live View Camera, CCTV, Audio components, and so on. Consequently,
excess cable will be coiled and stored at this location.
The Accessory Pull Box shall incorporate a #6-32 x 1" (M3.5 -0.7 x 25mm) screw stud, with lock
washer and nut, to accommodate dedicated Ground or Earthing wires from multiple TrueBeam
Subsystems. See Section 4.1.4, “Dedicated Grounding Requirements” on page 3-2 for additional
details.
WARNING: To prevent injury during installation and service, DO NOT locate the RJB
directly above the TrueBeam Stand, Modulator Cabinet, or casework.
Provide one 2" (50) conduit between each set of Dual In-
For information on the TrueBeam Main Circuit Room Monitor pull boxes and the Accessory pull box
Breaker Panel see Sections 3.1.1.1 and 4.2.1.1. mounted in the ceiling space. The length of this conduit
run shall not exceed 75 feet (22,860) from monitor to
Control Room pull box.
Provide 1/2” (13) conduit(s) for AC and DC Door Interlock
Switches recessed within door frame. For more information, Provide one 1 1/4" (32) conduit from the IRM pull box and
see Section 4.3.4.7. the ceiling mounted Secondary Microphone.
Secondary
Provide two 4” (100) conduits tight to the ceiling, adjacent to the Microphone
mechanical duct opening, to facilitate cable access for future room
renovations. Review all vault penetrations with the Physicist of Record. As no connections are made at this location, many
regulatory agencies do not require a Baseframe pull box.
If a pull box is not used, keep this area free of grout. If
Provide two 2” (50) and one 3” (75) conduits from the Control Pull required, provide a 12” x 24” x 10” deep (300 x 600 x 250)
Box to the Accessory Pull Box. In-Room Baseframe pull box. Top access is required.
Monitor
Provide 1/2" (13) conduit between X-RAY warning light(s) and the
Relay Junction box.
Provide two 2" (50) conduits between the Baseframe pull
box and the Relay Junction box. The length of this conduit
run shall not exceed 68 feet (20,726).
Provide one 1" (25) conduit from the Accessory pull box to each of the
following devices: CCTV cameras (2), In-Room wireless keyboard with
optional VVS System (1), and speakers (2).
Provide one 3” (75) conduit from the Accessory Pull Box
Provide two 1-1/4" (32) conduits from the Accessory pull box to a 4" x 4" x 2"
to the Optical Imager mounting plate. Terminate conduit
(100 x 100 x 50) electrical enclosure for the following devices: the Live View
with an insulating bushing.
(Radiation Hardened) camera (1) and the Primary Microphone (1).
Opt. set of
Dual IRM
Provide one 3" (75) conduit from the Control Pull Box to the Accessory Pull
Box for the optional Calypso and OSMS systems, see Sections 3.6 and 3.7 The RJB is provided by Varian and is 20" x 16" x 6" (508 x
406 x 152). Wall mount this junction box above the
acoustical tile ceiling. Service access to the RJB must be
maintained. DO NOT locate directly above the
Provide a 24” x 18” x 12” (600 x 450 x 300) Accessory Pull Box mounted TrueBeam Stand, Modulator Cabinet, or treatment
in the ceiling space, typically located near the foot of the couch as shown. room casework.
Provide one 1" (25) conduit from the Accessory pull box to each of the following devices: CCTV
cameras (2), In-Room wireless keyboard with optional VVS System (1), and speakers (2).
TrueBeam Power Supply (Recommended) Provide two 1-1/4" (32) conduits from the Accessory pull box to a 4" x 4" x 2" (100 x 100 x 50)
480VAC, 48kVA, 60Hz, 3 Ph. + N + G (N. America) electrical enclosure for the following devices: the Live View (Radiation Hardened) camera (1) and the
400VAC, 48kVA, 50Hz 3 Ph. + N + G. Primary Microphone (1).
See Section 4.2, TrueBeam Linear Accelerator
Subsystem for complete power specification. Provide one 3" (75) conduit from Accessory pull box to the Optical Imaging mounting plate. Terminate
Provide two 4" (100) conduits, tight to conduit with an insulating bushing. The length of this conduit run shall not exceed
the ceiling, adjacent to the mechanical 75 feet (22,860) from Optical Imager to Control Room pull box..
duct opening, to facilitate cable access
for future room renovations. Review all Provide one 2" (50) conduit between each set of Dual In-Room Monitor (IRM) pull boxes and the
vault penetrations with the Physicist Accessory pull box mounted in the ceiling space. The length of this conduit run shall not exceed
of Record. 75 feet (22,860) from monitor to Control Room pull box.
Provide network cabling outlets at all Provide one 3" (75) conduit from the
server or workstation equipment Control Pull Box to the Accessory Pull Provide one 1 1/4" (32) conduit from the IRM pull box and the ceiling mounted Secondary Microphone.
locations. All network cabling must be in Box for the optional Calypso and OSMS
place and tested prior to equipment systems, see Sections 3.6 and 3.7
installation. Network patch panels, hubs
and routers are typically located in a Provide 1/2" (13) conduit between X-RAY
server room or closet. For information on the Accessory warning light(s) and the Relay Junction box.
Provide two 2" (50) and one 3" (75)
conduits from the Control Pull pull box, see Section 3.1.2.5.
Box to the Accessory Pull Box. Provide 1/2" (13) conduit(s) for AC and DC
Connections for two or more warning Door Interlock Switches recessed within door
lights, usually red colored, incandescent frame. For more information, see
(no fluorescent lighting) are provided. Section 4.3.4.7.
Locate over the door, on the outside of
the treatment room. They may be
required to blink when the x-ray is on. The RJB is provided by Varian and is 20" x 16" x 6"
Verify local requirements with regional (508 x 406 x 152). Wall mount this junction box
regulatory agencies. see Sections above the acoustical tile ceiling. Service access to
4.3.4.1 through 4.3.4.5 “Warning Lights.” the RJB must be maintained. DO NOT locate
directly above the TrueBeam Stand, Modulator
Cabinet, or treatment room casework.
Speaker Speaker
For information on the TrueBeam Provide two 2" (50) conduits
Dual between the Baseframe pull box
Main Circuit Breaker Panel, see
IRM and the Relay Junction box. The
Sections 3.1.1.1 and 4.2.1.1. Opt. set of
Dual IRM length of this conduit run shall
Secondary
not exceed 68 feet (20,726).
Microphone
Live View Camera
w/Microphone
Optical
Opt. VVS Imaging
CCTV Camera
Provide power outlet feed from Main Cameras
Circuit Breaker panel with IEC 60309 Keyboard and The Modulator pull box is
receptacle. See Sections 4.3.5.3 and Mouse recessed into the floor slab and
5.1 for details and exact location. shall be 18" x 24" x 10" deep
(450 x 600 x 250). Refer to the
"Modulator Cabinet" drawing for
Provide one 2" (50) conduit from the pull box location. The cable
Control Pull Box to the Main Circuit access to this box shall be
Breaker panel. similar to Baseframe Cable
Access Details.
Provide two 2" (50) conduits between
the Main Circuit Breaker panel and For information on the Control
the Modulator pull box. Provide three 4" (100) conduits
Equipment pull box see section 3.1.2.1.
between the Baseframe pull box
and the Modulator pull box. The
A 3" (75) experimental access (physics) conduit may be required Provide four 4" (100) conduits As no connections are made at this location, length of this conduit run shall not
by the Customer. The experimental access conduit is used to between the Control Console pull many regulatory agencies do not require a exceed 75 feet (22,860).
periodically monitor radiation in the equipment room. The conduit box and the Baseframe pull box. Baseframe pull box. If a pull box is not used,
should be oriented as perpendicular to the isocenter as possible. The length of this conduit run keep this area free of grout. If required, provide
Provide a locking 6" x 6" (150 x 150) access door at the conduit shall not exceed 75 feet (22,860). a 12" x 24" x 10" deep (300 x 600 x 250)
termination location. Review all vault penetrations with the Baseframe pull box. Top access is required.
Physicist of Record.
Provide a minimum
3" (76) clearance
behind the
Modulator Cabinet
Finished Wall. for ventilation.
Modulator Cabinet
The Modulator Cabinet may be located either in the TrueBeam room or remotely.
Ventilation, acoustics, service provisions and cable length must be considered. The
Modulator Cabinet has service panels at both sides and front. Provide 11'-0" (3353)
clear space, side to side. For non-U.S. sites, verify electrical equipment service
clearance requirements with applicable local code. Do not locate this cabinet in
the primary beam path.
Figure 3-4 Modulator Cabinet, Plan View
WARNING: DO NOT locate the Modulator Cabinet in the primary beam path.
See Section 3.3.2 for Moving Modulator option.
Minimum
Modulator Cabinet
This optional Moving Modulator Kit can be purchased separately from your Varian Regional Sales
Manager. The Moving Modulator Kit includes the following components:
(2) Floor positioning brackets (seismic)
(2) Castor Assemblies
(2) Modulator Cabinet locking pins
(1) NEMA 6P enclosure (IEC - IP68)
Terminal Block Assembly (3-phase and ground)
(1) TrueBeam main power cable
(1) Modulator pull box cover plate
There are two installation configurations for the Moving Modulator. A “Left” Moving
(recommended) and a “Right” Moving Modulator.
Concrete Wall
Finished Wall
Modulator Cabinet
(Service Position)
Isocenter
TrueBeam Stand
and Gantry
Radiation
beam path
Note: The Modulator pull box location is dimensioned from the face of the finished wall.
The Modulator Pull Box is recessed into the floor Modulator pull box cover plate
slab and shall be 40" x 18" x 16 to 24" deep 25" x 20" x 1/8" [635 x 508 x 3]
[1000 x 450 x 400 to 600].
Concrete Wall
Modulator Cabinet
(Clinical Position)
Finished Wall
Finished Wall
Modulator Cabinet
(Service Position)
Isocenter
Radiation
beam path
TrueBeam Stand
and Gantry
Note: The Modulator pull box location is dimensioned from the face of the finished wall.
Outline of Modulator
Note: The NEMA enclosure must be installed on the Modulator pit floor. Maintain a
minimum of 6" [152] clearance from the side wall to the NEMA enclosure (to the side
with [4] knockouts).
Conduit penetrations into the Modulator pull box must access through one of the side
walls. Maintain a minimum of 10" [254] from the conduit centerline to the pull box
floor with the exception of the 2" [50] power supply conduit.
Modulator Cabinet
Modulator Cabinet (Clinical Position)
(Service Position)
Note: The NEMA enclosure must be installed on the Modulator pit floor. Maintain a
minimum of 6" [152] clearance from the side wall to the NEMA enclosure (to the side
with four knockouts).
Conduit penetrations into the Modulator pull box must access through one of the side
walls. Maintain a minimum of 10" [254] from the conduit centerline to the pull box
floor with the exception of the 2" [50] power supply conduit.
Floor
Positioning
Brackets
Finished Wall
Floor
Positioning
Brackets
A minimum of 4 1/4" [108] is required from the edge of the Modulator pull box and
the face of the floor positioning bracket.
Drill and install (1) 1/4" x 20 x 1" contractor-provided drop-in anchor 2" [50] from the
right edge Modulator pull box on both Left and Right Moving configurations.
Figure 3-11 Optical Imaging and In-Room Monitors (Typical) – Front Elevation
(113) (113)
(121)
(51) (51)
The Contractor shall install one (1) 18 AWG (1.0 mm2) Ground or Earthing wire from the Optical
Imaging Ceiling Mount to the Accessory Pull Box using the existing 3" (75) conduit. The wire color
shall be green with yellow stripe. Each wire shall be terminated with #6 (M3.5) ring terminals, one
end of which shall be affixed to the Accessory Pull Box ground stud. The contractor shall leave excess
wire at the Ceiling Mount Bracket to reach a point 7'-0" (2134) above finished floor..
The In-Room Monitors should be located as shown in the plan and hung from the ceiling. For ceiling
mount details, see Figure 3-15 on page 3-22. The monitor provides information during patient setup
and it is unsafe to turn away from the patient while the machine is moving and the patient is on the
couch. Alternatively, the In-Room Monitors may be mounted on a wall (see Figure 3-18 on page 3-25
for mounting details).
CAUTION: Do not locate the In-Room Monitors inside or within 2'-0" (610) of the Primary Beam
Path.
The ceiling mount In-Room Monitor is standard with the TrueBeam. The ceiling mount monitor
bracket is furnished by Varian and shipped with the system, and the ceiling mount support bracket is
Contractor-installed.
Control Equipment pull box, Dual In-Room Monitors. For details, see Figures 3-16
see Section 3.1.2.1 and 3-17 for ceiling mounting plate details.
(113) (113)
(121)
(51) (51)
The Contractor shall install two (2) 18 AWG (1.0 mm2) Ground or Earthing wires from the In-Room
Monitor signal box to the Accessory Pull Box using the existing 2" (50) conduit. The wire color shall
be green with yellow stripe. Each wire shall be terminated with #6 (M3.5) ring terminals, one end of
which shall be affixed to the Accessory Pull Box ground stud. The contractor shall leave excess wire
at the In Room Monitor signal box to reach a point 7'-0" (2134) above finished floor.
If equipment is to be anchored to a wall or ceiling, provide structural backing and support (by
Customer/Contractor). Install per bracket manufacturer's instructions. Verify mounting height with
local codes. A ceiling mounting bracket is furnished by Varian, Customer/Contractor installed.
Elevation
In Room Keyboard
and Mouse
The Live View (LV) Camera is a radiation-hardened system that enables monitoring of the TrueBeam
and the patient and at all times, the system provides proximity information while the machine is
moving to help prevent injury to the patient.
The LV Camera should be mounted to the wall. Provide structural backing and support for a
maximum 10 lb. (4.5 kg) load. Install per bracket manufacturer’s instructions. Alternately, a
ceiling-mount is acceptable.
The Contractor shall install one (1) 18 AWG (1.0 mm2) Ground or Earthing wire from the Live View
Camera signal box to the Accessory Pull Box using one of the existing 1-1/4" (32) conduit. The wire
color shall be green with yellow stripe. The wire shall be terminated with #6 (M3.5) ring terminals,
one end of which shall be affixed to the Accessory Pull Box ground stud. The contractor shall leave
excess wire at the Live View Camera signal box to reach a point 7'-0" (2134) above finished floor.
As an option, up to three sets of CCTV cameras can be furnished with the TrueBeam.
When using a system with only two cameras, it is mandatory to position the cameras in the
Primary Location, as shown in Figure 3-22.
When using a system with four cameras, locate two of the cameras in the primary position. The
location shown for the second set of cameras is recommended as shown in Figure 3-22, but is at
the customer’s discretion.
When using a system with six cameras, locate two of the cameras in the primary position. The
second set of cameras should be located in the recommended secondary position, and the third set
shall be located at the customer’s complete discretion.
Never locate a CCTV camera in the Primary Beam path.
(1753)
MX112-1
Figure 3-23 Treatment Room Speaker, Microphone, and Live View Camera Layout: Top View
If the Microphone is mounted below 8'-2 1/2" (2500), the Contractor shall install one (1) 18 AWG
(1.0 mm2) Ground or Earthing wire from the Microphone signal box to the Accessory Pull Box using
one of the existing 1-1/4" (32) conduit. The wire color shall be green with yellow stripe. The wire
shall be terminated with #6 (M3.5) ring terminals, one end of which shall be affixed to the Accessory
Pull Box ground stud. The contractor shall leave excess wire at the Microphone signal box to reach a
point 7'-0" (2134) above finished floor.
In addition, the system has proprietary software that runs on the Treatment Room Console and
Tracking Station. These components are shown in Figure 3-24, Figure 3-25, Figure 3-26, and
Figure 3-29.
Treatment Room Console – 78.5"H x 23.4"W x 51"D (1995 x 595 x 1295), 650 lbs (295.5 kgs)
The Array is positioned over the patient during patient setup and, for most patients, remains in place
during radiation therapy to monitor treatment target motion relative to the linear accelerator isocenter.
The cameras detect infrared light emitted by the optical targets embedded in the Array. Each camera
is permanently attached to a ceiling mounting system. Ceiling mounting systems include concrete
anchors, I-beam mounts, and wall mount systems. The mount type is selected based on the treatment
vault survey. There are also cantilever offset options for the camera mounts that allow flexible
positioning of the ceiling mounts. The cameras receive their power and data connection through the
camera power supply/hub unit.
The power supply/hub unit is located in the treatment room, outside the beam, but within a 50-foot
cable run from each camera. It accepts all point-to-point Ethernet connections for the Calypso System
network (cables from the Console, the Tracking Station computer, and each camera) and requires
120 VAC power.
3.6.7 Software
The Calypso System software is a set of proprietary applications that run concurrently on the Tracking
Station and Console. The software enables all system control and signal-processing functions. Users
interact with the software both at the Console (by touching elements on the touch screen) and at the
Tracking Station (by clicking elements on the screen and typing and by using the mouse and
keyboard).
3.6.8 Fixtures
A set of fixtures are used to calibrate and ensure correct operation of the Calypso System.
3.6.8.1 QA Fixture
The Quality Assurance (QA) fixture is used to verify correct operation of the Calypso System. The
QA procedure is performed daily. The QA fixture is provided in a protective carrying case and is
stored between uses.
QA Phantom – 6.35" x 4" x 4" (159 x 102 x 102), 3 lb (1.4 kg)
Pelican Case – 11" x 10" x 7" (280 x 254 x 178), 6.5 lb (3 kg) with QA Phantom
The calibration fixtures are used to calibrate the cameras and to establish the coordinate reference
frame for the Calypso System relative to the linear accelerator isocenter. The calibration procedure is
performed monthly. There are three calibration fixtures: the L-Frame fixture, the T-Frame fixture, and
the isocenter calibration fixture. These fixtures are also provided in a protective carrying case and are
stored between uses.
T-Frame Fixture - 13.5" x 10.5" x .75" (343 x 267 x 20), 0.3 lbs (0.14 kg)
L-Frame Fixture - 19" x 11.25" x .75" (483 x 286 x 20), 1.5 lbs (0.68 kg)
Isocenter Calibration Fixture - 9" x 8" x 8" (229 x 203 x 203), 13 lbs (5.9 kg)
Pelican Case - 24" x 20" x 12" (610 x 508 x 305), 36.5 lbs (16.5 kg) with all 3 fixtures
The Calypso System’s Beam On Detection and Reporting feature provides an indicator to correlate
tumor position and motion with therapy beam on/off status documented in the daily patient session
report with tracking graphs timestamps. This option requires additional on-site support from the
customer’s physics group to setup the software and calibrate.
The Dynamic Edge Gating option provides automatic signaling to hold and re-enable the beam in
response to organ motion for Varian or Siemens linear accelerators capable of gating.
Provide one 3" (75) conduit Control Equipment pull box, Provide a dedicated receptacle (100-240V
from the Control Pull Box to see Section 3.1.2.1 @ 50/60Hz), locate within 3'-0" (914) from
the Accessory Pull Box for the the Calypso Tracking Station.
optional Calypso and OSMS
systems. See Figure 3-2
“Typical TrueBeam Conduit
Diagram (Plan View).”
Provide a dedicated receptacle (100-240V Provide a 6"w x 3"h x 3.5"d (150 x 75 x 90) Pull Box
@ 50/60Hz), locate within 3'-0" (914) from (min.) mounted in the wall, locate within 12" (305)
Power Supply & Hub Unit. from Power Supply & Hub Unit as shown.
Note: Conduit runs from the Power Supply and Hub Unit to each treatment room location
shall not exceed 40'-0" [12m].
The Ceiling Mount Load Plate Location details can be found in Figure 3-33 and Figure 3-34.
The following mounting location diagram applies to the TrueBeam accelerators with a clear
unobstructed path to overhead concrete mounting surface for Cameras #1 and #3. A Varian provided
bracket and cantilever bar will be used to attach Calypso Camera #2 to the TrueBeam’s GCX Optical
Imaging post.
Note: When installing Camera #2 on the GCX Optical Imaging post the concrete ceiling
height must at or below 11'-6" [3505] from finished floor, see Figure 3-36.
If the concrete ceiling mounting height is above 11'-6" [3505] from finished floor, use
Section 3.6.11.2 to locate the Camera #2 ceiling mount load plate.
For retro-fit installations, where the preferred ceiling mount load plate locations for
cameras #1 and #3 are obstructed by overhead objects, see Section 3.6.11.2 for
acceptable ceiling mount load plate areas.
CAUTION: Place Camera #2 on the same side of the longitudinal axis line as the maze opening,
and position the Treatment Room Console on the opposite side.
If the Treatment Room Console is located on the same side of the longitudinal axis line
as Camera #2, there will be a high likelihood for creating gray bars, making the system
inaccurate.
Figure 3-33 Preferred Ceiling Mount Load Plate Locations – Plan View (Cartesian Dimensions)
Note: Dimensions are to the center of the Ceiling Mount Load Plate. See Section 3.6.13.1 for
more information.
The ceiling mount load plates should only be installed after the BaseFrame is grouted
in and isocenter is verified.
Figure 3-34 Preferred Ceiling Mount Load Plate Locations – Plan View (Polar Dimensions)
Note: Dimensions are to the center of the Ceiling Mount Load Plate. See Section 3.6.13.1 for
more information.
The ceiling mount load plates should only be installed after the BaseFrame is grouted
in and isocenter is verified.
Figure 3-35 Preferred Ceiling Mount Load Plate Locations – Typical Section
Note: The Calypso camera lens height and mounting post length will be determined by the
Varian Project Manager using a site survey after isocenter is identified.
Note: When installing Camera #2 on the TrueBeam’s GCX Optical Imaging post, the
concrete ceiling height must be at or below 11'-6" [3505] from finished floor.
If the concrete ceiling mounting height is above 11'-6" [3505] from finished floor, use
Section 3.6.11.2 to locate the Camera #2 ceiling mount load plate.
The following mounting location diagram applies to installations that are not able to obtain an
unobstructed path to overhead concrete mounting surface as shown in Figure 3-33 and Figure 3-34 by
using a Varian provided post and cantilever extension bar (see Figure 3-37).
CAUTION: Place Camera #2 on the same side of the longitudinal axis line as the maze opening,
and position the Treatment Room Console on the opposite side.
If the Treatment Room Console is located on the same side of the longitudinal axis line
as Camera #2, there will be a high likelihood for creating gray bars, making the system
inaccurate.
Alternate
Camera #2 Area
Note: The cantilever extension bar allows placement of the ceiling mount load plate
anywhere within the green shaded area, which is centered directly over the preferred
camera position.
The center of the Ceiling Mount Load Plate must fit inside the Allowed Area.
See Section 3.6.13.1 for more information.
The ceiling mount load plates should only be installed after the BaseFrame is grouted
in and isocenter is verified.
Note: The ceiling mount must be free of contact with any object other than the concrete
ceiling, the camera cable, and the camera mount in order to prevent coupling of
vibrations into the mount or conduction of heat between the mount and other objects.
WARNING: The customer/contractor must maintain a minimum clearance of 7'-0' (2130) between
the floor and ceiling mounted equipment.
Expansion Anchors
(1/2" x 5 1/2" L)
Torque to 40 ft. lbs (54.23 Nm)
Note: The ceiling mount load plates should only be installed after the BaseFrame is grouted
in and isocenter is verified.
Do not install ceiling mount load plate closer than 3 1/4" (83) to a vertical surface.
For additional seismic mounting requirements, contact your Varian Regional Planner
for additional information.
When a suitable surface for the ceiling mount load plate cannot be obtained directly above the camera
location, a Cantilever Extension Bar can be used to achieve proper positioning.
Figure 3-41 Cantilever Extension Bar Figure 3-42 Camera with Cantilever
Extension Bar
Note: Cantilever Extension Bars are available in 6" (152), 12" (305), and 18" (457) offset
options.
Note:
(4.5 square meters) of secure storage area.
The Optical Surface Monitoring Solution (OSMS) System has three basic components:
OSMS Workstation
OSMS Optical System
Treatment Room Remote Terminal
Figure 3-43 OSMS Camera Figure 3-44 OSMS Power Supply Unit (PSU)
Provide a switched
receptacle (100-240V
@ 50/60 Hz) for the
OSMS PSU. Locate
within 3’-0” (914) from
the PSU.
Note: Camera POD #1 and #2 should be mounted symmetrically for best results.
Note: Do not install ceiling mount load plate closer than 3 1/4" (83) to a vertical surface. For
additional seismic mounting requirements, contact your Varian Regional Planner for
additional information. The Ceiling Mount Load Plate should be mounted parallel or
perpendicular to the longitudinal axis line.
The typical incoming coolant temperature range is 50 deg. F. to 75 deg. F. (10 Deg. C. to 25 deg. C.).
The coolant system must be designed to eliminate the possible formation of condensation. If lower
temperature coolant is used, a psychrometric chart must be consulted to determine the dew point in
the facility. If the inlet coolant temperature is at or below this dew point, condensation will form on the
coolant system pipes, which could result in equipment damage.
Domestic
Water Supply Internal heat exchanger
Fresh Water Supply
(Make-Up Water) (City Water)
Supply
Return
Low Power (Power Save) State coolant heat load. 2 kW (6,830 Btu/hr)
Normal treatment cycles (see “Operational States” on Requires heat dissipation into cooling water of
page 3-55). 13.3 kW (45,422 Btu/hr)
Maximum overall input pressure, including normal back 100 PSIG (7 kg/cm2)
pressure.
The pressure differential between the inlet and outlet fittings Adjusted to between 10 PSI (0.7 kg/cm2)
at the TrueBeam Stand. and 24 PSI (1.7 kg/cm2) @ 3.0 – 5.0 GPM
(11.4 – 18.9 LPM), respectively (while in the
Ready State).
Actual pressure drop through the TrueBeam. 24 PSI (1.7 kg/cm2) (under maximum heat load
conditions).
Periodic cooling water flow through the TrueBeam. 0 GPM (with the internal bypass valve closed
only).
Average water temperature rise during Beam-On, Standby, 27 deg. F. (15 deg. C.)
and Ready States (w/closed bypass valve).
The cooling water requirement can be satisfied with a Closed-Loop system or a One-Pass system.
Although most water and sanitary districts restrict the use of one-pass cooling, it can generally be used
for backup. If a closed-loop system is used, provide a one-pass system for backup.
Table 3-3 Coolant Specifications for External and Internal Water Sources
Water Sourcesa b Direct water from the domestic city Direct chilled/cold water from Hospital
water supply. Water is disposed in a closed loop system or chiller system
waste drain after it exits the machine. dedicated to machine
Base Water Qualityc Clean, Clear (non-turbid) water. Clean, Clear (non-turbid) industrial
Disinfected, Potable grade surface water, Appropriately treated with nitrite,
water, Aquifer, or Well water. Mo, silicate, borate, or other suitable
corrosion inhibitor.
Pathogens (cfu/ml) Nil Nil
pH 7.0-9.0 7.5-10.0
a. City Water is intended solely as a backup supply and is not recommended for permanent use as the external
coolant source.
b. Facility Water is preferred for permanent use as the external coolant source.
c. Experience has shown that some local potable water supplies have caused excessive corrosion and frequent replacement
of the internal heat exchanger.
d. Facility Water has higher conductivity and total dissolved solids limits because added corrosion inhibitors would raise
these control measures. In a small percentage of systems, the conductivity could be lower based on the type of corrosion
inhibitor used.
e. For systems where soft water or purified water is used for makeup, lower total hardness is acceptable if there is
sufficient corrosion inhibitor in the system.
When glycol is added to external facility water, propylene glycol is preferred (due to its better
environmental safety record compared to other glycols) at a strength not to exceed 50% by
volume (v/v).
External water (from city or facility) will require secondary disinfection (i.e. in addition to any
bleach/chlorine/chloramine reserve present) to avoid biofilm formation in the machines heat
exchanger. Seek advice from a water treatment professional.
Note: The water coolant specification in this section does not apply to the Accelerator’s
internal coolant water loop. Only qualified operators or service personnel should refer
to the appropriate Varian maintenance/service manual or contact the Varian Help Desk
at 1-(888)-Varian5 (827-4265) for the internal coolant water quality specifications.
3.8.4.1 Ventilation
TrueBeams will produce detectable levels of ozone under certain conditions. Four to six air changes
per hour are normally required to maintain undetectable levels, depending on the size of the vault and
air circulation efficiency. Ventilation required to remove the heat dissipated to the vault air normally
accomplishes this. The ventilation system should use fresh-air as part of its design. Treatments should
not be performed if the ventilation system is not in operation. Long irradiation's at high dose rates,
such as those performed for physics measurements, should be followed by airing out the vault. It is
important to provide positive air pressure in the TrueBeam vault to hold swing-type doors closed.
Provide ventilation sufficient for removal of equipment air heat load as follows:
TrueBeam Vault
7.25 kW (24,760 Btu/hr) at TrueBeam Stand/Gantry during Ready and Beam-On States.
1.5 kW (5,119 Btu/hr) at TrueBeam Stand/Gantry during No Mode State.
1.0 kW (3,413 Btu/hr) at TrueBeam Stand/Gantry during Power Save State.
5.25 kW (17,930 Btu/hr) at Modulator Cabinet during Beam-On State.
0.5 kW (1,707 Btu/hr) at Modulator Cabinet during other States.
TrueBeam Control Console Area (see Section 5.1)
2-1 Cabinet Configuration
0.75 kW (2,560 Btu/hr) at the Control Console Cabinet.
Stacked Configuration
0.5 kW (1,707 Btu/hr) at the Control Console Cabinet.
0.25 kW (853 Btu/hr) at the Control Console Imaging Cabinet.
0.5 kW (1,707 Btu/hr) at optional ARIA Workstation.
3.8.5 Plumbing
A sink with running hot and cold water is highly recommended in TrueBeam vaults. Appropriate
codes should be followed regarding paddle or foot controls and type of faucet. A hose spigot is
necessary to fill the water phantom and a drain is necessary to service the TrueBeam’s internal cooling
system and drain the water phantom. Floor drains and floor sinks should not be located in the vault to
avoid possible backup into the equipment floor recesses. Do not run water lines directly above the
TrueBeam components or control console.
3.9 Shielding
For detailed information on shielding data, see “Typical Room Shielding Tables” on page 2-1.
WARNING: Varian Medical Systems shall have no approval or other responsibility for any
matter affecting or related to the adequacy of the radiation protection walls and
barriers or related safety devices. All radiation shielding designs must meet codes
and regulations of all Authorities Having Jurisdiction (AHJ) and must be
approved by the Customer’s or Facility’s Physicist of Record and shall be the sole
responsibility of the Customer/Facility. The hours of operation, patient workload,
accelerator energy, and the shielding materials should all be taken into
consideration when calculating shielding requirements. Serious injury or death
can result from improper radiation shielding.
Steel or lead shielding at Linear Accelerator rooms may be embedded in or mounted on the inside
surface of concrete walls and ceiling. Additional structural reinforcement may be required.
Neutron shielding must be carefully analyzed by the Physicist of Record when lead or steel is to
be located on primary or secondary barriers on installations with photon energies higher than 10
MV.
Linear Accelerator shielding calculations follow the general guidelines of NCRP Reports 49 and
51. The TVL of leakage x-rays have been modified based on the report of W.R. Nelson and P.D.
LaRiviere: “Primary and leakage Radiation Calculations at 6, 10 and 25 MeV,” Health Physics,
38811 (1984). Copies are available on request.
The shielding table suggestions are based on calculations using NCRP report 151 methodology
and measured data. Distances of point of interest from isocenter are taken from Varian’s Typical
Room Configuration (see Figure 2-2 on page 2-7). The room dimensions are based on machine
clearance. This would translate into a distance of 10 feet from the isocenter to the nearest inner
wall surface of the primary barrier.
The workload for standard procedures is defined as 75000 rads/week with 0% IMRT procedures when
using the system for 10 hours per day, five days per week, five patients treated per hour at 250 rads
per session.
W = 75,000 rads per week for primary walls.
W = 75,000 rads per week for secondary walls.
The workload for standard procedures with 50% IMRT procedures and a modulation factor of F=3.
W = 75,000 rads per week for primary walls.
W = 150,000 rads per week for secondary walls.
The workload for SRS procedures in utilizing the High Intensity Mode (HIM) (dose rates >
1000 MU/min) is defined as 200,000 rads/week with 20% IMRT procedures and a modulation factor
of F=3. The assumed system usage is 10 hours per day, five days per week, two treatments per hour
at 2000 rads per treatment, average six sessions per day.
W = 200,000 rads per week for the primary walls.
W = 280,000 rads per week for the secondary walls.
The dose output in the HIM is assumed to be 1400 rads/min for the 6MV and 2400 rads/min
for 10MV.
Except where specifically noted, radiation leakage in non-controlled areas shall not exceed
20μSv/week (2 mrem/week), assuming 100% occupancy beyond the shielding barriers (per
NCRP Report 91 “Recommendations of Limits for Exposure to Ionizing Radiation”).
Most treatment rooms are entered through a maze. This hallway is designed to reduce radiation
levels at the entrance door. The length of the maze and the occupancy outside the entrance door
affects the amount of shielding required in the door. “No-maze” doors are available from several
shielding manufacturers. The use of these doors must be reviewed by the Physicist of Record
early in the design process.
Supplement No. 11 (1972) and Supplement No. 17 (1983) of the “British Journal of Radiology”
describes two different conventions for referencing the quality of an x-ray radiotherapy beam.
The convention presented in Supplement No. 11 has been adopted for this sheet.
The typical room shielding tables information is provided to assist early treatment room design.
The Physicist of Record for the project should become involved with the treatment room design
as early as possible. With regard to facility shielding, the Physicist of Record is responsible for
designing the treatment room radiation shield barriers and confirming they meet applicable
regulatory requirements. The facility design is based on regulatory requirements of the regulatory
body tasked with oversight of Radiation Producing Devices in the Region, and recommendations
of the national Council of Radiation Protection and Measurement (NCRP).
WARNING: In all seismically active locations, the design of the Baseframe Pit for this load, and its
anchorage, should be approved by a licensed Structural Engineer. During a seismic
event, serious injury or loss of life may result from a substandard design.
TrueBeam VEO
Baseframe
TrueBeam Stand
and Gantry
TrueBeam Couch
Outline at the
TrueBeam Stand
Hold down anchor bolts are installed
by Varian during the Baseframe
installation. These bolts are used
exclusively to avoid movement of the
frame during grouting. They are not
seismic attachment anchors.
Provide adequate
The conduits may terminate anywhere reinforcing steel
within the pull box. See the Cable in slab.
Access Diagram for quantity and size
of conduits.
Provide two 2" (50) conduits
for the Varian provided hose
For side conduit access situations,
kit, the maximum length for
provide a Baseframe pull box
each conduit is 86" (2185)
measuring 12” x 24 x 10” total depth
with a minimum bend radius
(300 x 600 x 250). Top access is
The Couch Turntable of 12" (305), see Section 3.12
required. As no connections are made
Assembly and Stand for detailed information.
at this location, many regulatory
mounting pads shall
agencies do not require a top box, If a
top pull box is not used, keep this be free of grout.
area free of grout.
Line of
Baseframe pit.
TrueBeam VEO
Baseframe
Isocenter to centerline
of pull box dimension.
A steel frame is used to anchor the TrueBeam Stand, Gantry and Couch to the Verification of appropriate utility and cable access is the
facility. The frame is set in a recessed equipment pit, leveled (by Varian), and held responsibility of the Customer. Selection of the appropriate
in place with grout. Baseframes are positively anchored to the slab to avoid floating cable access method is determined by site-specific conditions
during grout placement. Verify anchorage details with your Installation Project and Customer preference. The standard side access conduit
Manager office. Varian information regarding pit design assumes a ground floor details are appropriate for the majority of installations, those
installation. Upper floor installations require a thorough review by a qualified with sub-floor clearances of at least 24” (610). Alternate
structural engineer. In typical installations, Baseframes for TrueBeams are not bottom access conduit details are included for installations
positively anchored sufficiently to accommodate seismic loads. All seismic with subfloor clearances of at least 39” (991). Alternate duct
anchoring is by the Customer. Sample seismic calculations and details of the access details are included for installations with minimal
preferred anchoring methods for TrueBeams are available from the Planning sub-floor clearance. All conduits or cable ducts must be fully
Department. sealed and protected to keep them clean and dry.
Figure 3-56 Standard Side Cable Access Plan and Section at Pull Box
Outline at the
Hold down anchor bolts are installed TrueBeam Stand
by Varian during the Baseframe
installation. These bolts are used
exclusively to avoid movement of the
frame during grouting. They are not
seismic attachment anchors.
Line of
Baseframe pit
TrueBeam VEO
Baseframe
Isocenter to centerline
of pull box dimension
A steel frame is used to anchor the TrueBeam Stand, Gantry and Couch to the Verification of appropriate utility and cable access is the
facility. The frame is set in a recessed equipment pit, leveled (by Varian), and held responsibility of the Customer. Selection of the appropriate
in place with grout. Baseframes are positively anchored to the slab to avoid floating cable access method is determined by site-specific conditions
during grout placement. Verify anchorage details with your Installation Project and Customer preference. The standard side access conduit
Manager office. Varian information regarding pit design assumes a ground floor details are appropriate for the majority of installations, those
installation. Upper floor installations require a thorough review by a qualified with sub-floor clearances of at least 24” (610). Alternate
structural engineer. In typical installations, Baseframes for TrueBeams are not bottom access conduit details are included for installations
positively anchored sufficiently to accommodate seismic loads. All seismic with subfloor clearances of at least 39” (991). Alternate duct
anchoring is by the Customer. Sample seismic calculations and details of the access details are included for installations with minimal sub-
preferred anchoring methods for TrueBeams are available from the Planning floor clearance. All conduits or cable ducts must be fully
Department. sealed and protected to keep them clean and dry.
Figure 3-57 Alternate Bottom Cable Access Plan and Section at Pull Box
Customer provided
cooling water lines
(Supply and Return)
Isocenter
The maximum
distance from the end
of conduit to the NPT
valve is 30" (762)
52" VEO
Baseframe
Outline at the
TrueBeam Stand Terminate cooling water supply and
return lines in the rear wall behind
the Stand with 1" (25) female NPT
valves and plugs. The customer/
contractor will make the final
connection to the valves in
TrueBeam Stand using the Varian
provided hose kit during installation.
Note: Install the two conduit sleeves for the Varian provided cooling hoses after the
BaseFrame is installed (before grout). The conduits must rest against the rear of the
BaseFrame at the specified location, to ensure the stand will completely cover the
exposed end.
Customer-provided
cooling water lines
(Supply and Return)
Customer-provided access
Line of Baseframe pit
52” VEO
Baseframe
Outline at the Terminate cooling water supply
TrueBeam Stand and return lines in the rear wall
behind the Stand with 1" (25)
female NPT valves and plugs.
The customer/contractor will
make the final connection to
the valves in TrueBeam Stand
using the Varian-provided
hose kit during installation.
Note: Install the two conduit sleeves for the Varian provided cooling hoses after the
BaseFrame is installed (before grout). The conduits must rest against the rear of the
BaseFrame at the specified location, to ensure the stand will completely cover the
exposed end.
Customer-provided
cooling water lines
(Supply and Return)
Customer-provided access
52” VEO
Baseframe
Note: Install the final leg of the two conduit sleeves for the Varian provided cooling hoses
after the BaseFrame is installed (before grout). The conduits must rest against the rear
of the BaseFrame at the specified location, to ensure the stand will completely cover
the exposed end.
Varian-furnished,
Contractor-installed
1/4” (6) thick steel
backing plate.
Figure 3-63 Side Laser Mounting Details (Recessed in Wall) – Elevation View
Varian-furnished,
Contractor-installed Contractor-furnished,
steel backing plate. Contractor-installed
For dimensions, see anchors.
Figure 3-50.
Figure 3-64 Side Laser Mounting Details (Recessed in Wall) – Plan View
Varian-furnished, Contractor-installed,
1/4” x 14 5/8” x 8 5/16” (6 x 371 x 211)
mild steel plate required for mounting.
Figure 3-65 Side Laser Mounting Details (Recessed in Wall) – Section View
MX029-1
Varian-furnished,
Contractor-installed
1/4” (6) thick steel
backing plate.
Figure 3-67 Sagittal Laser Mounting Details (Recessed in Wall) – Elevation View
50 Hz 230V 20A
a. These feeds are supplied simultaneously by the GEXPRO VWB Series TrueBeam Main Circuit Breaker Panel.
CAUTION: Ground/Earthing conductor must meet or exceed local code requirements and be equal
in size (Parity-Sized) to the supply/power conductors, but no smaller than #6 AWG
(16mm2).
The main power and ground conductors as well as the room interconnection with the Relay Junction
Box are sized, pulled, and terminated by the Contractor. The Varian-provided control interconnect
cables are not shown in Figure 4-2, Interconnection Wiring Diagram.
4-1
General Electrical Specifications TrueBeam/VitalBeam Edition
The second grounding circuit is for wall- and ceiling-mounted TrueBeam/VitalBeam Accelerator’s
subsystems located at or below 8'-2 1/2" (2500) above finished floor (AFF). The Contractor shall
install a Ground or Earthing wire from each of the subsystems listed below to the Grounding Stud in
the Accessory Pull Box and from there to the facility’s main ground, as noted above. Please see
Figure 4-1, Ground/Earthing Conductor Diagram.
Dual In-Room Monitor Subsystem – See also Section 3.4.2.4, Dedicated Ground Wires –
TrueBeam IRM.
Live View Camera Subsystem – See also Section 3.5.1.2, Dedicated Ground Wire – Live View
Camera.
This grounding system provides compliance with IEC 60101 and -01.
Provide one 14 AWG (2 mm2) Ground/Earthing Provide Ground/Earthing conductor that is equal in size (Parity-Sized)
conductor from the Accessory Pull Box, via the Control to the supply/power conductors for Control Console Receptacle.
Equipment Pull box, to the facility's main ground. See Section 4.3.5.3 for details.
See Section 4.1.4 for details.
Control Console power outlet feed from TrueBeam Main Circuit
Breaker panel with IEC 60309 receptacle. See Section 4.3.5.3 and
Section 5.1 for details.
Caution should be taken when powering the TrueBeam/VitalBeam from the same distribution source
as elevators, HVAC equipment, and other phase-controlled loads, because of potential adverse affects
on the operation of the x-ray equipment. The supply voltage waveform should be practically
sinusoidal with less than 5% total harmonic distortion. Signals from devices that use the power line
as a means of distribution can be the source of problems. Efforts should be taken to minimize such
effects.
Transients lasting no more than a few cycles will not cause harm if limited to the specified steady state
line voltage regulation. Transient suppression is required where larger, longer lasting or frequent
transients occur as these can cause interruption of operation and/or equipment damage.
Note: If an isolation transformer and/or power conditioner is installed, verify the output
breaker size on this equipment and size the wiring accordingly before connecting to the
TrueBeam Main Circuit Breaker Panel. For more information on the TrueBeam Main
Circuit Breaker Panel requirements, see Section 4.2.2 on page 4-11.
4.1.6.1 Cabling
Network cabling must be minimum Category 5e with a minimum bandwidth of 100 Mbps full duplex
(100BaseT). The cable run must be a single segment of less than 100 meters (328 feet) from the wall
plate to the network switch or router, located within the telecommunications closet. The RJ-45
connector will be labeled as a DATA connection with a unique identifier that delineates the
termination point at the Patch Panel, Switch, or Router.
Note: The network data drops must be active at the time of installation with a live connection
to the network switch or router.
4.1.6.2 Termination
The Control Console requires a minimum of one (1) network cable outlet (RJ-45) located within
three (3) feet of the Control Console. Although the Control Console requires a single network drop,
Varian Medical Systems recommends three (3) additional drops for customer-supplied computers
and/or a network printer. Varian Medical Systems recommends the use of a modular wall plate that
4-7
TrueBeam/VitalBeam Edition
meets TIA/EIA and NEC standards and codes for data communications. The RJ-45 jack must meet
TIA/EIA-568-A wiring pattern. Orientation of the RJ-45 wall jack should be at a 45-degree down
angle.
Note: The customer may require additional workstations and printers in the vicinity of the
Control Console to run customer required applications. Therefore, Varian Medial
Systems recommends that the customer pulls three (3) additional Cat 5e cables and
terminates each connection into a four-plex modular wall plate. Thus bringing the total
number of network drops to the Control Console to four (4).
The Control Console makes use of the TCP/IP protocol suite. Varian Medical Systems recommends
that the customer eliminate all unnecessary protocols. Varian Medical Systems requires subnets for
the TCP/IP protocol in order to reduce the number of broadcast messages that must be processed by
the Control Console to the Radiation Oncology network. The subnet of the Radiation Oncology
Department should be kept as small as possible. Large, flat TCP/IP networks running broadcast
intensive software will adversely impact the performance of the radiation delivery system. Varian
Medical System recommends isolating the Radiation Oncology broadcast domain from the Enterprise
Network.
Note: The Control Console requires a static Internet Protocol (IP) address at the time of
installation. Varian Medical Systems requires that the network drop provided for the
Control Console is “hot” with a live connection to the network switch or router.
4-8
TrueBeam/VitalBeam Edition TrueBeam Linear Accelerator Subsystem
Input voltage 200VAC, 208VAC, 240VAC, 380VAC, 400VAC, 415VAC, or 480VAC (nominal),
line-to-line, 5-wire (3-phase, neutral, and ground [Parity-Sized]).
Line voltage ±5%. This is the maximum allowable steady-state deviation from nominal
regulation value selected.
Maximum phase 3% of the nominal value. This is the maximum difference between any two phase voltages
voltage imbalance when operating at full load (Beam-On).
Electrical loads 7kVA in Stand-By state, 48kVA in Beam-On state. (4kVA & 45 kVA Accelerator loads
(with Console) only, respectively.)
Long-Time Load 48kVA (45kVA Accelerator Only). This is the maximum load that the source is expected
(with Console) to sustain during normal (Beam-On) operation; that is, during treatment. It must also be
capable of sustaining this load occasionally for much longer periods of test and calibration.
Power factor Estimated to be 90% or more. Most of the load is inductive. The line-current waveform is
non-sinusoidal.
Source impedance 2.5% maximum. This maximum recommendation is based on the minimum required source
capacity; namely, 48kVA. At 208 VAC, this corresponds to 133A full load current. The
recommended maximum impedance is therefore 24mOhm. At 400 VAC, the full load
current is 69A and the recommended maximum impedance is 89mOhm. No minimum is
specified, however, the fault current available shall not exceed 10,000A.
Mandatory The minimum size of the copper wire ground conductor shall meet or exceed local code
grounding requirements and be equal in size (Parity-Sized) to the supply/power conductors, but no
conductor smaller than #6 AWG (16mm2). Ground equipment through the “Hospital Grid System.”
The equipment is sensitive to electrolysis from water pipe grounding. Do not use water
supply piping for ground.
CAUTION: Ground/Earthing conductor must meet or exceed local code requirements and be equal
in size (Parity-Sized) to the supply/power conductors, but no smaller than #6 AWG
(16mm2).
4-9
TrueBeam Linear Accelerator Subsystem TrueBeam/VitalBeam Edition
Varian Medical Systems strongly recommends the use of the TrueBeam Main Circuit Breaker Panel
specifically designed for the unique requirements of the TrueBeam/VitalBeam accelerator. This
custom panel provides a single-input, dual output design and incorporates/supports Emergency Off
and Console UPS circuitry.
Note: The TrueBeam Main Circuit Breaker Panel is typically contractor provided but may be
included with the equipment order, contact your Regional Planner to verify. Locate the
panel in sight and within 10 feet (3048) of the TrueBeam/VitalBeam console control
cabinet. The panel may be surface or semi-recessed mounted. The panel should be
conspicuously identified as “Main Disconnect for Accelerator” per NEC. This
statement may vary per country/region. Please consult the appropriate governing body.
For additional information, see Section 4.2.2, TrueBeam Main Circuit Breaker Panel – VWB Series.
If the TrueBeam Main Circuit Breaker Panel cannot be obtained, this panel must be replicated in full
functionality. Please contact your Regional Planner for additional specifications.
4-10
TrueBeam/VitalBeam Edition TrueBeam Linear Accelerator Subsystem
4.2.2.1 Application
Physical Specifications
Height: 36 inches (914.4 mm).
Width: 25.38 inches (644.5 mm).
Depth: 9.23 in. (234.5 mm).
Weight: 179 pounds (81.1 kg).
4-11
TrueBeam Linear Accelerator Subsystem TrueBeam/VitalBeam Edition
There are several configurations of the VWB panel to accommodate domestic and international power
requirements.
Catalog Number Ampere Rating Voltage Rating Short Circuit Current Rating
Single panel completely assembled and tested. A pre-engineered panel with a permanent wiring
diagram.
Custom tailored for Varian Systems. Standardized design and testing assures high
product quality and reliability.
4-12
TrueBeam/VitalBeam Edition TrueBeam Linear Accelerator Subsystem
Contact your Varian Regional Planner for order information in the following markets:
Latin America; Europe, Middle East, and Africa; and Asia/Pacific Rim.
4-13
TrueBeam Linear Accelerator Subsystem TrueBeam/VitalBeam Edition
4-14
TrueBeam/VitalBeam Edition Interconnection Wiring Diagram
4.3.3.1 Room Lights, Setup Lights, Laser Positioning Lights, and CCTV
The room lights, setup lights, laser positioning lights, In-Room Monitor, and Closed Circuit
Television System (CCTV) can be controlled by a single room master switch, often outside the room
and including a pilot light. The room lights can be on a separate circuit. Laser positioning lights
control is automatically subordinated to room lights control on TrueBeam/VitalBeam and Acuity. A
warning that lasers are on is implied when the room lights are off (lasers are turned off when room
lights are on). The room lights and laser positioning lights may have wall switches inside the room,
but this is not necessary when they are connected to the Relay Junction Box. Three-way switching is
not recommended.
Setup lights are normally dimmable incandescent fixtures, that allow the intensity to be adjusted by
the therapists, while aligning the patient to the laser lights. The setup lights are usually located above
and to either side of the longitudinal axis. The range of illumination for the setup lights is usually 25
to 40 foot-candles (269 to 431 meter-candles). Their operation is independent of the Pendant and
Couch controls.
Main room lights are used for general illumination, while the patient is moving into and out of the
room and for machine and room maintenance. Typically, fluorescent fixtures are used. The range of
illumination for this activity is 75 to 100 foot-candles (807 to 1076 meter-candles) at the working
level, approximately 3'-0" (914) above the floor. The fixtures are operated from the
TrueBeam/VitalBeam Couch and the Couch Pendant through a relay. If skylights and atria are used
for general illumination, their contribution to the light level must be coordinated with the
requirements during patient setup.
Each of the five Warning Light circuits has a maximum incandescent lamp load of 60 watts. If a
greater load is required, these circuits can be used to control separate, customer-provided relays.
Alternately, LED fixtures can be substituted. Fluorescent fixtures are not approved.
The BEAM ON warning light illuminates when treatment radiation (MV) is being produced by the
accelerator and is mandatory. Provide no less than one Beam On warning light located over the door,
on the outside of the treatment room. Verify additional requirements with regional regulatory
agencies.
The BEAM READY warning light illuminates when all interlock conditions have been cleared and the
accelerator is in a ready state to generate treatment radiation (MV). A Beam Ready warning light in
the room and/or over the door may be required. Verify local requirements with regional regulatory
agencies.
The X-RAY ON warning light illuminates when imaging radiation (KV) is being produced by the
Integrated Imaging and is mandatory. Provide no less than one X-RAY ON warning light, located over
the door, on the outside of the treatment room. This light is commonly red-colored and may be
required to blink when the Integrated Imaging X-Ray is on. Verify additional requirements with
regional regulatory agencies.
Provide Emergency-Off (E-Off) switches in treatment room. The TrueBeam/VitalBeam E-Off switch
shall be Allen-Bradley 800T-FX6AV or equivalent, two pole, dry contact type with manual reset.
Each switch shall be wired in series to two separate parallel circuits. The first contact shall be
normally closed (NC) and make up the “safety loop.” The second contact shall be normally open (NO)
and include the “sensor loop.” Each E-Off switch shall incorporate a Varian-provided,
contractor-installed resistor across the Sensor Loop pole (see Figure 4-2). Specific directions for
installing the Sensor Loop Resistors will be provided by the Varian Project Manager in advance of
and in preparation for his Pre-Installation Inspection Site Visit.
In addition to the switches required as part of the room, Emergency-Off devices are built into the
TrueBeam/VitalBeam Stand and Couch, Console, and at the TrueBeam/VitalBeam Modulator.
Therefore, an adequate quantity of switches must be provided in Accelerator rooms so that one need
not pass through the primary beam to disable the TrueBeam/VitalBeam. Do not locate
Emergency-Off switches in primary beam. Locate switches to avoid inadvertent contact, such as by
gurneys or carts. Verify all requirements with regional regulatory agencies.
The TrueBeam/VitalBeam system allows for several additional interlocks to be used at the customer’s
discretion for ancillary purposes such as roof hatches, in-vault storage room doors, radiation
dosimeter interlock, and so on. Contact your Regional Planner for additional details.
Provide a dimmer switch for setup lights. This switch is used to adjust the illumination level of the
set-up lights so that they are dim enough for clear visibility of the lasers, but bright enough for safe
movement through the room.
Provide one 200VAC-240VAC power receptacle with an IEC60309, Blue, 30A, 250V (UL/CSA) or
32A, 220/240V (European) 50/60HZ, 2 Pole, 3Wire, Grounding receptacle (available from GEXPRO
1-800-279-7925).
This receptacle shall be powered by the GEXPRO VWB-Series MCB, located below the counter, and
24" (610) to either side of the TrueBeam/VitalBeam Control Cabinet. Do not place this receptacle
directly behind either control cabinet. See Section 5.1, Typical Control Equipment Casework for
details.
The Contractor furnished receptacle provides power to the TrueBeam/VitalBeam Control Cabinet
through the Varian supplied W106 Cable with IEC60309 power plug.
The electrical loads for the Varian control console equipment are:
TrueBeam/VitalBeam Control Cabinet – Receives power from GEXPRO MCB-fed wall
receptacle via Varian-furnished W106 cable.
TrueBeam/VitalBeam Imaging Cabinet – Receives power from TrueBeam/VitalBeam Control
Cabinet.
Control Console and CCTV Monitors – Receive power from TrueBeam/VitalBeam Control
Cabinet.
Log Printer – 120VAC - 1A.
Provide one grounded 4-plex electrical power receptacle for the Log Printer. Locate below the
counter.
In addition, optional duplex or 4-plex electrical power receptacles should be provided above and/or
below the counter for operators’ convenience.
Provide a grounded 4 plex electrical power receptacle for any optional workstation.
Acoustical
Tile Ceiling
Upper Cabinets
TrueBeam/VitalBeam
Keyboard 2-1 Cabinet
Monitor
Dedicated
Keyboard
Exhaust Vent
200-240 VAC Outlet - Contractor
Dedicated Keyboard provided IEC 60309, 30A, 250V
receptacle. See Section 4.3.5.3.
5-1
Typical Control Equipment Casework TrueBeam/VitalBeam Edition
Concrete Wall
Finished Wall
Figure 5-2 TrueBeam/VitalBeam 2-1 Cabinet Floor Positioning Bracket Installation – Plan View
Note: The Positioning Bracket can be used as a seismic attachment. The minimum clearance
dimensions to Positioning Bracket is to the finished wall. Bottom flange of bracket is
pre-drilled for 7/16" [11] ø anchor bolts, contractor-provided.
*** This Console Layout is only valid for equipment delivery prior to July/August 2015 ***
ARIA Monitor
ARIA
Computer
Bulk and shelf storage are required for Varian accessories General TrueBeam/VitalBeam room storage requirements are The storage drawing shows a suggestion only
and various materials used for therapy. The Varian-supplied outlined below. This is only a partial list of storage items required for of possible storage provisions and is intended
Accessories include Electron Applicators (cones), Wedges, a typical TrueBeam/VitalBeam room: as a guide to aid in the design of site specific
and other field-defining devices. Storage space in the treatment > Treatment room furniture - chair, mirror, coat rack, foot stool, casework. Due to differences in treatment
room should be planned to reduce travel required for patient set-up. waste can, I.V. poles, oxygen bottle cart, film holder cart, soiled practices, the exact quantity and types of
Patient block tray storage should be located on the entrance side of linen cart and total body irradiation "stage." accessories varies with each institution. Verify
the Treatment Couch. Linen storage in the treatment room and > Miscellaneous storage items - spare parts, demineralized requirements and storage preferences with the
storage space for many patient positioning pads and devices is water, physics dosimetry equipment, film markers (letters), solder Customer. This is not a construction document.
desirable. wire, restraints, "easy mover" stretchers, immobilization devices, All casework/storage shall be provided by
patient shielding accessories, patient set-up accessories, patient the Customer.
Many spare parts are shipped with the equipment and an optional marking accessories, arm/shoulder extenders, hand grips, breast
spare parts kit can be ordered. These will require secure storage in boards and "alpha cradles (formed foam cradle).”
or near the treatment room.
Plan View
Elevation View
Solid shelving.
Detail 3
Provision should be considered for labeling Accessory Storage Compartments.
MX035-1
Due to the heavy weight of some block trays, a rear support rail is recommended.
Provide Block Tray storage. Block trays are accessories mounted to the Collimator that are
used to shape the treatment field. They are custom made for each patient. They are usually
stored in slots as shown on the storage dimensions drawing. Due to their heavy weight, store
them as near as possible to the Collimator and at accessible heights. Typical TrueBeam/VitalBeam
rooms require storage for 10 to 20 Block Trays. This may vary with the use of the Multileaf
(381) Collimator. Typical Their maximum weight is 50 lbs. (23 kg) per tray.
Plan View
Elevation View
Block Tray.
Detail 3
Provision should be considered for labeling Accessory Storage Compartments.
MX036-1
Figure 5-7 Block Storage
(381)
This is a minimum clear dimension.
Plan View
(279)
The Electron Applicator is typically suspended by its metal support rail for storage.
Elevation View
Provide a wood stop at support rails (required for non-computerized equipment only).
The Electron Applicator is typically suspended by its metal support rail for storage.
Detail 1
The Electron Applicator is typically suspended by its metal support rail for storage.
Provide a continuous wood stop.
Provide a continuous metal support angle.
Provide Electron Applicator Storage. Electron Applicators, otherwise known as "cones” are
accessories mounted to the Collimator that are used in combination with FFDAs to shape
the electron treatment field. They are usually stored in compartments with slots as shown
on the storage dimensions drawing. Due to their heavy weight, store them as near as
Detail 2 possible to the Collimator and at accessible heights. Typical TrueBeam/VitalBeam
rooms require storage for 6 Electron Applicators. Their maximum weight is 20 lbs.
(9 kg) per applicator.
Provision should be considered for labeling Accessory Storage Compartments.
MX034-1
Carpet, while having advantages, can make gurney movement difficult. In addition, liquids and stains
on carpeting can be difficult to clean/remove, thereby posing an infection control risk. Those facilities
that do choose carpeting often use carpet squares that can be replaced or cleaned and allow access to
floor conduit/duct if used. Similar to vinyl flooring above, the electrostatic propensity of carpeting
must be limited. Carpeting should not exceed a 2.0 kV rating at 20% relative humidity when measured
as outlined by the methods in AATCC-134 or equivalent.
To avoid potential damage to the accelerator and its sub-systems, it is recommended that the final
floor covering be installed before the equipment has been rigged onto the Baseframe. Coordinate
equipment rigging and required floor protection with the Varian Installation Project Manager prior to
machine delivery.
The recommended minimum finish floor to finish ceiling clearance is 9'-0" (2743). For sites with
ceiling clearance issues, a portion of the ceiling not located directly above the TrueBeam/VitalBeam
may be installed below the recommended height. However, to allow for rigging, assembly, and
operational clearances, certain area central to the accelerator must remain 9'-0" (2743) or greater.
See Figure 5-9, Typical Reflected Ceiling Plan for additional information.
To avoid interference with the overhead laser start the ceiling support grid pattern so that Isocenter is
at the center of a tile. If a solid ceiling is used, provide an access panel with adequate space for
servicing the laser. See Figure 5-9, Typical Reflected Ceiling Plan.
When laying out the air conditioning and fire suppression systems, do not route the duct or water pipes
directly over the accelerator. Inadvertent leaks may occur and can seriously damage the accelerator
and mechanical systems within the Baseframe.
Verify ceiling height requirements with local and regional regulatory agencies.
For ceiling conflicts located directly above the TrueBeam/VitalBeam, contact your Regional Planner.
In accordance with current Varian “Standard Terms and Conditions of Sale” RAD 1652 the following are minimum facility requirements to be
accomplished before the machine can be released for shipment. Requests for any exceptions should be referred to your Varian Installation Project
Manager. The Customer is responsible for meeting these minimum requirements prior to the scheduled day of this inspection. If delays in facility
completion postpone Varian’s installation, the Customer shall reimburse Varian, at Varian’s standard service rates, for any extra time and /or travel
by Varian made necessary by the delay. I have explained these requirements to the Customer on this date along with the specific requirements
listed below.
Site Name Address same as Sales Order “Ship To”. Serial Number
Address 1:
Address 2:
City, State, Postal Code:
NOTE: The Customer is responsible to confirm, provide, and/or demonstrate to the Varian Installation
Project Manager the following items meet or exceed minimum requirements set forth in Varian’s Designer
Desk Reference (DDR). The Varian work area is defined as the treatment room, control room, and ancillary
areas wherein Varian equipment will be installed.
A-1
TrueBeam/VitalBeam Edition
In the box below, precede all notes with the respective item number from the list above.
STOP DELIVERY
RIG AND HOLD
RIG AND CONTINUE – high risk for completion date.
RIG AND CONTINUE – at risk for completion date.
SITE READY
In accordance with current Varian “Standard Terms and Conditions of Sale” RAD 1652 the following are the minimum facility requirements to be
accomplished before the upgrade device can be released for shipment. Requests for any exceptions should be referred to your Varian Regional
Installation Project Manager. The Customer is responsible for having the building, utilities, lighting, ventilation, air conditioning, mounting facilities,
all necessary radiation shielding, and access to the room completed by the day of final inspection. (If delays in completion delay installation, the
Customer shall reimburse Varian, at Varian’s standard service rates, for any extra time and /or travel by Varian made necessary by the delay). I
have explained these requirements to the Customer on this date along with the specific requirements listed below.
Y N ARCHITECTURAL REQUIREMENTS:
1. Installation drawings reviewed by Varian. Customer Contact information:
2. All required permits completed. IT Weekend Support
Name: Number:
Y N GENERAL REQUIREMENTS FOR ALL SYSTEMS: Physics Support
Vault Name: Number:
3. Varian supplied ceiling mounts installed per DDR. Ensure Electrician
space available for a 3” camera mount protrusion below Name: Number:
drop ceiling. Bolts are torqued to 40 ft/lbs for 6 inch and
Other (specify)
25 ft/lbs for 5 inch ceiling mounts.
Name: Number:
4. Send PM vault elevations for each camera position as
soon as possible. Note: 12 week lead time on custom Control Room
camera mount fabrication.
16. Single 120VAC 15A un-switched power receptacle no
a. Height of drop ceiling from finished floor: more than 3’ away from Tracking Station.
Cam 1 cm Cam 2 cm Cam 3 cm 17. Customer approved console layout or drawing,
incorporating the new upgrade components insuring
b. Height of concrete overhead from finished floor adequate space and depth for cable service loop,
Cam 1 cm Cam 2 cm Cam 3 cm provided to Varian.
18. 3” cable access hole from Control Pull box to Tracking
c. Distance from Isocenter. Station for fiber optic cable. No more than 3’ away.
Cam 1 cm Cam 2 cm Cam 3 cm 19. Hospital LAN Connection.
Note: Not required for TrueBeam 2.0+
5. Camera Hub/Power Supply unit location outside beam but
within a 50’ cable run from each camera. (18”l x 12”w x 20. IT Data Template completed by customer and sent to
12”h). installer.
6. Single 120VAC 15A un-switched power receptacle no
more than 3’ away from Camera Hub/PS unit. Y N N/A CLINAC REQUIREMENTS
7. Electrical pull box 6”w x 3”h x 3.5”d (min.) in wall near 21. Dynamic Edge Gating on order? If so pre-requisites
Camera Hub/PS unit. No more than 3’ away. include:
8. Cover plate with 3” cable access hole and grommet for C-Series – 4D 10.0+, MMI, Type II MLC 120, Console
item #7 Software 7.6 +
9. (2) - 120VAC 15A un-switched power outlets for Calypso TrueBeam – 1.6 and below not available.
Console - (1) on sagittal line, (1) on the side wall opposite TrueBeam – 2.0+, MMI.
the longitudinal axis line from Cam #2, all within 13’ of Note: TrueBeams undergoing upgrade to 2.0+ , STB-IC-
couch midpoint. 543 and MMI STB-IC-544 must be completed before
10. (2) - Data drops no more than 6” away from Calypso Calypso can be scheduled.
Console power outlets (item #9). Varian will provide Siemens – Gating option
plenum rated CAT5 cable.
22. Automated Couch Repositioning on order? If so pre-
11. (2) – 3/4” Conduits. (1) Conduit from each data drop to the requisites include:
Accessory pull box. Pull string in place.
C-Series – Console Software 7.6 +, Juniper Router, 4D,
12. (3) – 1 1/4” Conduits. (1) Conduit from each Camera MMI, Remote Couch Motion if NO OBI
mount to the Accessory pull box. Pull string in place.
Note: May require linac serial number so that new console
13. (1) – 1 1/2” Conduit installed from the Control Pull box to configuration files can be created to have Dose Export
the Accessory pull box. Customer to provide conduit enabled for MMI if not already enabled.
length (38 meters max). Pull string in place.
TrueBeam – 1.6 and below not available.
14. (3) – 2” Conduits installed from the Accessory pull box to
the Camera Hub/PS electrical box. Pull string in place. TrueBeam – 2.0+ none
15. Identify Console storage location. Location MUST be Note: TrueBeams undergoing upgrade to 2.0+ , STB-IC-
outside the beam path. ConsoleSystem does NOT need 543 must be completed and if MMI is being installed STB-
to be plugged in while in storage. IC-544 must be completed before Calypso can be
scheduled.
B-1
TrueBeam/VitalBeam Edition
23. Data Import on order? If so pre-requisites include: 31. Provisions made for removal of shipping crates, boxes
Varian – Eclipse and packing material. Note: Arrangements can be
made to remove crates and packing material if delivery
Philips – Pinnacle 9.0+, may require customer to acquire
and installation coincide. If delivery and installation do
additional licensing form Philips.
not coincide, then arrangements will have to be made for
24. Radiation Detector on order? the customer to remove/dispose of crates and packing
25. Establish Network folder on Hospital network for material.
Patient Reports. 32. Ensure a qualified physicist is available for Acceptance
26. Confirm pedestal base for tabletop replacement per Testing.
linac manufacturer. (Reference compatibility list in DDR).
27. kVue Qfiix Kevlar couchtop on order? If so
prerequisites include:
TrueBeam – LaserGuard installed Y N VARIAN OTHER:
28. Confirm Tabletop replacement with customer. Ensure 33. Is project created for labor and expense?
all current accessories and test phantoms are compatible. 34. License files posted to PSE website and features match
If this is a relocation and a Qfix is on order ensure the Sales Order?
Universal Tips panel is on the order. 35. Provide Calypso SN, Sales Order, FRM0080 and MDA0078
to installers
36. Ship request completed and date of delivery provided to
installers?
Y N CUSTOMER OTHER:
37.Has Belair tools been scheduled for delivery?
29. Inform Applications of Installation Dates.
30. Provide 100 sq. ft. of temporary storage for Calypso
materials and tooling in close proximity to Treatment Provide completed copy of checklist to installer.
Room for tooling.
In the area below, please precede all notes or comments with the respective item number from the previous page.
Please use the area below for general notes/comments that DO NOT relate to any of the checklist items.
C-1
Varian TrueBeam Shipping List (Typical) TrueBeam/VitalBeam Edition
TrueBeam DDR
HE Clinac IDP
Specification
Specification
IDP Page # Vol. 10, No. 2 DDR Page # Change in Requirement
Architectural
D-1
TrueBeam/VitalBeam Edition
TrueBeam DDR
HE Clinac IDP
Specification
Specification
IDP Page # Vol. 10, No. 2 DDR Page # Change in Requirement
Laser Positioning 1.29 Patient Positioning 3-66 to 3-71
Lights Lasers
Unspecified- LAP laser recess: 10 Existing iX or
brand Laser 1/2" x 26" (267x660) TrueBeam sites will
Recess: 16" x 25" accommodate
(406 x 635) TrueBeam.
LAP laser mounting GC must mount plate
plate provided by directly to concrete
Varian wall or existing steel
plate.
Typical Closed 1.32 Minor System 3-26 to 3-30
Circuit Television Components
(CCTV) System
Details two Two CCTV cameras, Locations for primary
CCTV system Varian-furnished and set are specified.
location specific. Locations for optional
Additional camera sets are suggested.
sets are optional. Requires new conduit
runs from Console Pull
Box via Accessory Pull
Box located above
vault ceiling.a
Live view CCTV, 3-27 Location is specified.
Varian-furnished Requires new conduit
runs from Console Pull
Box via Accessory Pull
Box located above
vault ceiling.a
Intercom System Two, Locations are
with integrated Varian-furnished specified/suggested.
microphone and microphones Requires new conduit
speaker runs from Console Pull
Box via Accessory Pull
Box located above
vault ceiling.a
Two speakers 3-30 Locations are
supplied specified/suggested.
Requires new conduit
runs from Console Pull
Box via Accessory Pull
Box located above
vault ceiling.a
D-2 Appendix D H.E. Accelerator vs. TrueBeam Site Requirement Comparison Summary
TrueBeam/VitalBeam Edition
TrueBeam DDR
HE Clinac IDP
Specification
Specification
IDP Page # Vol. 10, No. 2 DDR Page # Change in Requirement
In-Room Monitor 1.33 TrueBeam Dual 3-21 to 3-24
(IRM) In-Room Monitors
(IRM)
Single IRM, Dual IRM display Location is specified.
usually wall with ceiling-mount Requires new conduit
mounted bracket runs from Console Pull
Box via Accessory Pull
Box located above
vault ceiling.a
Optical Guidance TrueBeam Optical 3-18 to 3-20 Location is specified.
Platform Imaging Subsystem Requires 3"conduit
(optional, not with ceiling-mount runs from Console Pull
shown) bracket (Standard Box via Accessory Pull
feature on all Box located above
TrueBeams) vault ceiling.
Structural
Baseframe Pit and 1.35 Baseframe Pit and 3-57 to 3-60 No change required.
Installation Installation
Electrical
Appendix D H.E. Accelerator vs. TrueBeam Site Requirement Comparison Summary D-3
TrueBeam/VitalBeam Edition
TrueBeam DDR
HE Clinac IDP
Specification
Specification
IDP Page # Vol. 10, No. 2 DDR Page # Change in Requirement
Baseframe Cable 1.36 Baseframe Cable 3-61 to 3-62 No change required.
Access Details (main Access Details
conduits)
Cable Access 1.37 Cable Access 3-2 to 3-7
Diagram Diagram
Console to Stand Console to Stand – Add one 4" (100)
– three 4" (100) four 4" (100) conduits conduit from Console
conduits to Stand.a
Console to Not required Abandon in place. May
Modulator – two be used as spares for
4" (100) conduits Value Engineering.a
Modulator to Modulator to Stand – No change required.
Stand – three 4" three 4" (100)
(100) conduits conduits
RJB to Modulator RJB to Stand – two Provide two 2" (50)
– two 2" (50) 2" (50) conduits conduits from RJB to
conduits Stand. In a retrofit
scenario, route cables
to Stand via Modulator
conduits.
Clinac Main TrueBeam MCB – Add one 2" (50)
Circuit Breaker – Two 2" (50) conduits conduit from MCB to
one 2" (50) to to Modulator (power Modulator.a
Modulator and signal)
Add one 2" (50)
TrueBeam MCB – conduit from MCB to
One 2" to Console Console Pull Box.a
Pull Box
Install one outlet at
TrueBeam MCB – Console, spec. per
One power outlet at code, with
Console, spec. per IEC 60309-32A
code, with receptacle. Location is
Varian-furnished specified in
receptacle Section 4.3.5.3.
OBI Breaker – Not required. Abandon in place. May
one 2" (50) to be used as spares for
Stand Value Engineering.a
D-4 Appendix D H.E. Accelerator vs. TrueBeam Site Requirement Comparison Summary
TrueBeam/VitalBeam Edition
TrueBeam DDR
HE Clinac IDP
Specification
Specification
IDP Page # Vol. 10, No. 2 DDR Page # Change in Requirement
Additional Additional Console to Install one 3" (75), and
Console to In-Room devices two 2" (50) conduits
In-Room devices (Minor System from Console Pull Box
(Minor System Components) to Accessory Pull Box
Components) in vault.a
Interconnection 1.39 Electrical Chapter 4
Wiring Diagram Requirements
Clinac Main TrueBeam Main Increased power from
Power Power Specification 45kVA to 48kVA.
Specification and and Main Circuit Now compatible with
Main Circuit Breaker multiple incoming
Breaker (VWR-series) – voltages.
(CBB-series) multiple voltage
compatibility Requires new
GEXPRO VWR-series
MCB.a
OBI (optional) Not required Abandon in place. May
Main Power be used in Value
Specification and Engineering.a
GEXPRO
OBI-series
Circuit Breaker
Control Console: Control Console: Install one outlet at
multiple outlets single outlet for Console, spec. per
for components components code, with IEC
60309-32A receptacle.
Location is specified in
Section 4.3.5.3.
Relay Junction Relay Junction Box Install
Box (RJB) (RJB) connects to Varian-furnished RJB.
connects to Stand Provide two 2" (50)
Modulator (Varian-furnished) conduits from RJB to
(GC-furnished) Stand. In a retrofit
scenario, route cables
to Stand via Modulator
conduits.
Appendix D H.E. Accelerator vs. TrueBeam Site Requirement Comparison Summary D-5
TrueBeam/VitalBeam Edition
TrueBeam DDR
HE Clinac IDP
Specification
Specification
IDP Page # Vol. 10, No. 2 DDR Page # Change in Requirement
Mechanical
a. Opportunities for Value Engineering and re-use of existing infrastructure possible. Please consult with
your Regional Planner for details.
D-6 Appendix D H.E. Accelerator vs. TrueBeam Site Requirement Comparison Summary
Glossary
Term Definition
Acuity™ Varian tradename for its simulator. The simulator is used to assist with
treatment planning for determining the method and position to use during
actual treatment.
Arc Therapy A form of radiation therapy in which the radiation beam is continuously
directed toward the isocenter as the Linear Accelerator Gantry is rotated in
an arc.
Backpointer Laser A Linear Accelerator accessory, usually mounted to the Gantry, used to
identify the central axis of the radiation beam.
Baseframe/Plate Varian-supplied assembly that anchors the Stand/Gantry and the Couch to
the building structure.
Blocks and Block Trays Accessories used to shape the treatment field. Blocks are custom made for
each patient and are supported by the Block Tray at the Clinac Collimator.
10 to 20 Block Trays may be in use daily.
Breakdown The manner in which a Clinac is disassembled for shipment. The two-piece
breakdown, or standard configuration, leaves the Stand and Gantry
connected. A three-piece breakdown, or factory breakdown, separates the
Stand and Gantry and is used to shorten the space required for passage into
the treatment room. The factory breakdown might involve extra cost.
CCTV A closed-circuit television is used for observing patients from the control
console. The system is typically color but can be black-and-white and
consists of two or more cameras and two or more monitors. Verify quantity
of cameras required with regional regulatory agencies. The primary camera
will normally include an auto-focus and low-light level lens with power
zoom. It will be mounted on a bracket incorporating pan-tilt features. The
control console must include remote controls for the zoom and pan-tilt.
Glossary-1
Term Definition
Clinac® Varian trade name for a range of Linear Accelerator models used in cancer
treatment and stereotactic radiosurgery. Low Energy (600C, 4EX, 6EX,
and 600SR) models have different facility requirements from Dual Energy
(2100C/D, 2300C/D, 21EX, 23EX, iX, and Trilogy) models. Rebuilt
Clinacs (4R, 6XR, and 18R) have similar characteristics to the
in-production models.
Couch The assembly used to support the patient during treatment or simulation. It
can move vertically, longitudinally, and transversely to position the patient
treatment field at isocenter. The minimum travel radius must be free of
obstructions. Its maximum travel radius defines the maximum distance
from isocenter throughout its travel range that the couch can operate. As the
couch is seldom used in all orientations, the maximum travel radius can
have obstructions without detriment, but it is recommended that the
Customer and Varian’s Planning Department be consulted.
Door Interlock A switch that enables a fail-safe safety circuit linked to the Clinac,
VariSource, GammaMed, or Acuity when the door to the room is closed.
The door must be closed before radiation treatment or simulator can
proceed. If the door is opened during treatment or simulation, the beam is
turned off.
Glossary-2
Term Definition
Dynamic Compensation A superset of the Dynamic Wedge where one or more mechanical axes
move during the course of an x-ray treatment to conform the dose
distribution to the treatment volume.
Electron Applicator An accessory, often called a cone that is mounted to the accelerator or
Acuity Collimator that defines the treatment field for electron therapy.
These are required for accelerators with energies above 10MV and are
optional with the Acuity. There are five, and one additional optional, units
per set. They measure approximately 1'-0" x 1'-0" x 1'-4" (305x305x406)
and weigh up to 20 lbs. (9kg) each. Their storage requires special design
attention when it is incorporated into the treatment and Simulator room
cabinetry.
Electron Radiation A Primary Beam of radiation generated by the Clinac for treatment. Low
energy accelerators have no electron mode, while Dual Energy accelerators
have several selectable electron energies. Electron Radiation is less
penetrating than Photon Radiation, and is used less often than Photon
Radiation.
Electronic Cart Assembly The VariSource Transportable 200t system comprises the VariSource
Remote Afterloader (VRA) and Electronic Cart Assembly (ECA). The
ECA houses the VariSource, GammaMed Control Console and Treatment
Planning System plus peripherals and storage for accessories. The ECA and
VRA form a single articulated vehicle facilitating transport and installation
once at the designated site. This ECA is connected via Varian supplied
cables to the Wall Box and the grounded duplex electrical power receptacle
located in the control console area.
Emergency-Off Switch A “mushroom” button used to disable the Clinac, TrueBeam, VariSource,
(also known as Emergency GammaMed or Acuity. The switch must have a manual reset feature.
Power Off Switch or [EPO] Emergency-Off switches are provided at equipment Stand, Couch, and
or as Emergency Stop Modulator Cabinet. Additional switches must be provided to disable the
Switch) TrueBeam without entering the Primary Beam and in accordance with local
regulations.
Emergency Stop Switch A “mushroom” button used to disable the TrueBeam. The switch must have
a manual reset feature. Emergency-Stop switches are provided at the
equipment Stand, Couch, and Modulator Cabinet. Additional switches
must be provided to disable the TrueBeam without entering the Primary
Beam and in accordance with local regulations.
Glossary-3
Term Definition
ExacTrac (ETX) A high resolution stereo x-ray imaging system that targets tumors and
corrects patient positioning with sub-millimeter precision. The room-based
design enables continuous tracking of patient and tumor movement,
including IGRT verification, throughout the treatment. This system is
combined with the Varian Clinac Linear Accelerator to form the Novalis
TX.
Experimental Access The installation of an experimental access (physics) conduit between the
Conduit (also known as interior of a Clinac or VariSource, GammaMed treatment room and an
Physics Port) accessible point outside the treatment room, may be requested by the
Customer. It is used periodically with a Water Phantom/Beam Scanner
System in Clinac treatment rooms. The conduit should be oriented as
perpendicular to the isocenter as possible.
Final Field Defining An accessory that is fabricated to shape a patient’s electron beam treatment
Aperture (FFDA) field. It installs into the Electron Applicator during patient set-up.
Freight Refers typically to the shipment of Varian equipment, beginning with the
pick-up at the factory and ending freight-on-board (FOB) at the facility.
See also Rigging.
In-Room Monitor Display that describes the status of the equipment setup and patient
parameters. The staff uses this monitor in the treatment room as they set up
the patient. It is important to locate the monitor such that viewing the
monitor during the Setup process shall not distract the therapist from the
patient. Consult with the Customer regarding monitor location preference.
The In-Room monitor should not be located in any x-ray primary beam.
Installation Product The IPA procedure provides testing procedures and data recording tables to
Acceptance (IPA) enable Varian to demonstrate that Varian Products have been successfully
installed and meet required manufacturer specifications.
Glossary-4
Term Definition
Isocenter The point in three-dimensional space about which the Gantry, Collimator
and Couch turntable rotate in common. This point is the central reference
for all calibrations and critical shielding dimensions. It is the reference for
positioning the Baseframe pit, Lasers, Couch, Clinac/TrueBeam/Acuity
and the patient during treatment procedures.
Junction Box A conduit body that is used to access and terminate conductors or house an
electrical device. For purposes of Clinac and Acuity requirements, the
Varian-supplied cables are pulled and housed in conduits terminated at Pull
Boxes, while the lighting control relays are housed in a junction box.
Laser Positioning Lights Laser devices used to position the patient on the couch for treatment or
simulation. Four lasers are used in the treatment room. Their light beams
intersect at the isocenter. The side and overhead lasers throw both vertical
and horizontal beam planes that create a crosshair. The sagittal laser is
located ahead of the Couch and at least seven feet above the floor and
throws only a vertical beam plane. Rigid installation of the lasers is critical.
A back pointer laser, which is mounted on the Gantry counterweight or
beamstopper, may be ordered with the equipment. The back pointer laser,
along with the wall-mounted lasers, creates an intersection of light defining
the radiation exit axis.
Longitudinal Axis also An imaginary vertical plane that coincides with the rotational axis of the
known as Sagittal Plane Gantry and bisects the patient couch.
Modulator Cabinet Power control unit for all Dual Energy Accelerators. The Modulator is
located in the cabinet behind the machine. Cable length should be
considered relative to the console.
Glossary-5
Term Definition
Multileaf Collimator Collimator system designed to define the silhouette of a beam of radiation.
(MLC) This optional system, available on all Varian Accelerators, reduces the
need for blocks and block trays. The effect of the MLC system on the
architectural requirements is limited to an increase in the control console
requirements.
Neutron Radiation A particle form of Secondary Radiation produced by high (>= 10 MV)
energy photons incident on high atomic number materials such as steel and
lead.
Occupancy The purpose or activity for which a space is used with regard to an
occupant's length of stay while radioactivity is present. The values used for
determining requirements in Varian documents are: 0% for no occupancy
within a 60 foot (18,300) radius from the radiation source; 10% for exterior
areas; 25% for service or circulation areas; 50% for treatment, exam and
waiting areas; 100% for control, office or areas of unknown occupancies.
Pendant Hand-held remote control unit attached to the Couch that is used to position
and adjust the Couch, Gantry and Collimator for patient treatment. The
Pendant also houses controls for room lights and Laser Positioning Lights.
Photon Radiation A Primary Beam of low (< 10 MV) or high (>= 10 MV) energy penetrating
x-ray radiation generated by the accelerator for treatment. Low energy
accelerators have a single x-ray energy of less than 10 MV, while Dual
Energy accelerators have one similar low energy, and one high energy
x-ray energy of 10 MV or greater. The term “Photon Radiation” also refers
to the x-ray leakage radiation and scatter radiation that is either emitted
from the accelerator or scattered from the shielding barriers, respectively.
Glossary-6
Term Definition
Physicist of Record The physicist with the responsibility for assessing parameters and limits
associated with the Clinac, TrueBeam, VariSource, or GammaMed. With
regard to facility shielding, the Physicist of Record is responsible for
designing the treatment room radiation shield barriers and confirming they
meet applicable regulatory requirements. The facility design is based on
regulatory requirements of the regulatory body tasked with oversight of
Radiation Producing Devices in the Region, and recommendations of the
National Council of Radiation Protection and Measurement (NCRP).
Confirmation of the shielding adequacy is assessed with a radiation survey
performed by a qualified physicist, which may or may not be the Physicist
of Record. The Physicist of Record will correspond with the Region's
Department of Health Services (or equivalent) regarding the design and
results of the radiation survey.
Physics Port See Experimental Access Conduit (also known as Physics Port).
PortalVision™ (PV) Real-time imaging system for monitoring and verification of treatment
field and shielding blocks in relation to anatomical landmarks. The effect
of PortalVision on the architectural requirements is limited to an increase
in the control console requirement.
Primary Beam Radiation The emission or propagation of photons or electrons along the main axis or
direction of the generating equipment (see Photon Radiation and Electron
Radiation). Varian accelerators generate a 28-degree primary radiation
beam cone from a source in the Gantry (measured one meter back from
isocenter). Acuity generates a 39-degree primary radiation beam cone from
a source in the Gantry (measured one meter back from isocenter). Shielding
for the primary beam must consider the 360-degree rotation of the Gantry
and should extend at least one-foot (305) beyond the beam cone.
Pull Box A conduit body that is used only to access conductors. The distinction is
made to simplify the NEC or other regulatory agency requirements for
placement and construction of these structures. The Control Console,
Baseframe, and Modulator boxes are Pull Boxes.
Radiation Device that senses radiation and issues a warning when the radiation level
monitor/detector exceeds the preset standards. Some jurisdictions require them in accelerator
rooms as a precautionary measure.
Radiosurgery A method of treatment that uses a single, high dose of radiation to alter the
tissue to cause necrosis or fibrosis. This procedure uses Gantry, and
sometimes Couch, movement during the treatment to minimize exposure to
surrounding tissue.
Glossary-7
Term Definition
Safety and Monitoring Special equipment required to assure that the technical and service
Devices personnel are not exposed to radiation. These items are Emergency-Off
Switch (also known as Emergency Power Off Switch or [EPO] or as
Emergency Stop Switch), Radiation monitor/detector, and Warning Light.
(See definitions.) Other monitoring equipment is used to observe and
position the patient during treatment. These items are CCTV, Intercom,
Laser Positioning Lights, and View Window. (See definitions.)
Sagittal Plane also known An imaginary vertical plane that coincides with the rotational axis of the
as Longitudinal Axis Gantry and bisects the patient couch.
Simulator Radiotherapy equipment, such as the Varian Acuity, that uses radiographic
and fluoroscopic imaging to duplicate the beam geometry of medical
Linear Accelerators as a means to localize the treatment field.
Stand Fixed part of the Stand/Gantry assembly containing the Klystron, power
converters, cooling water heat exchanger, microwave generator and other
elements of the Linear Accelerator and similar components of the Acuity.
Glossary-8
Term Definition
Stereotaxis (n), The principle of locating a point in three dimensional space, within the
Stereotactic (adj) brain, with a high degree of accuracy, by using an external reference
coordinate system or plane.
Total Body Irradiation A technique during which a large-field x-ray or electron beam is used to
(TBI) treat the entire patient's body. Due to the increased field size, a distance of
10 to 20 feet (3 to 6 meters) is required from the isocenter to the wall on one
side of treatment rooms designed to accommodate the procedure.
Under Voltage Release Safety feature that trips the breaker when an under-voltage condition
(UVR) occurs. Used in conjunction with the accelerator and Acuity emergency off
circuits to trip the main circuit breaker power to the equipment.
VariSource™ Varian's high dose rate remote afterloader delivers high radiation doses to
patients by way of a radioactive source wire that is extended through
catheters into body cavities.
View Window Patient monitoring opening in the wall between the Control Equipment
Casework and the Acuity room spanned with leaded glass. Low energy
accelerators occasionally have view windows but this is not recommended.
Warning Light A light (usually red) that indicates “beam-on” condition. A light for
“ready” mode may be required also.
Water Phantom/Beam A clear tank, part of a set of components, used to simulate a human body
Scanner System on the treatment couch to determine an accurate radiation output and dose
distributions of a Linear Accelerator. The water phantom, which measures
up to 2'-0" x 2'-0" x 2'-0" (610 x 610 x 610), is used by the therapists and
physicists. It needs to be filled with water before use and the water needs to
be siphoned off after use. Water supply, drain, and water-resistant storage
space for the tank should be provided within the treatment room.
Glossary-9
This page intentionally left blank.
Glossary-10
Index
Index-1
D I
detail infrared cameras 3-33
elevations 2-17 in-room monitor
plan view 2-15 alternate mounting location for 3-25
detector, radiation 3-35 and optical imaging 3-17
diagram mounting methods 3-22
cable access 3-5 pull box 3-3
coolant 3-57 standard mounting location 3-21
interconnection wiring 4-15 installation timeline description 1-3
dimensions for typical accessory storage 5-9 interconnection wiring diagram 4-15
ducts/cable conduit 3-2 Intracranial Radiosurgery Subsystem, OSMS 3-48
dynamic edge gating 3-35 introduction to TrueBeam DDR 1-1
isometric view for typical room 2-5
E
electrical J
connections 4-2 junction box, relay 4-22
requirements 4-1
specifications 4-1 K
elevations detail 2-17 key features of TrueBeam 1-1
emergency-off switches 4-19
environment specifications 3-60 L
Extracranial Radiosurgery Subsystem, Calypso 3-31 laser positioning lights 4-17
lasers
F ceiling, mounting detail for 3-78
facilities requirements 3-1 patient positioning 3-74
features 4-22 sagittal, mounting detail for 3-79
list for TrueBeam 1-1 side, mounting detail for 3-75
relay junction box 4-22 lighting and accessories circuits specifications 4-1
finishes 5-1 lights
fire protection 3-61 laser positioning 4-17
fixtures 3-34 room 4-17
calibration 3-35 setup 4-17, 4-18, 4-20
QA 3-34 Live View camera
flooring requirements 5-12 mounting locations for 3-27
subsystem 3-27
G load plate, ceiling mount 3-46
gating, dynamic edge 3-35
general M
electrical specifications 4-1 main
room storage requirements 5-8 circuit breaker panel 4-10, 4-11
system information 2-1 room lights 4-18
Generator ON (Integrated Imaging) warning light 4-19 main circuit breaker panel 3-2
major system components
H modulator cabinet 3-9
heights and clearances, camera elevation 3-45 optical imaging with IRM 3-17
hub unit 3-33 microphones and speakers 3-30
HVAC and plumbing requirements 3-55 minimum coolant flow requirements 3-56
minor system components 3-26
Index-2
modulator P
cabinet 3-9 patient positioning lasers 3-74
moving 3-11 plan view detail 2-15
pull box 3-3 plumbing
standard 3-9 described 3-61
mounting detail requirements 3-55
ceiling laser 3-78 positioning lights, laser 4-17
sagittal laser 3-79 power conditioning requirements 4-7
side laser 3-75 power receptacles
mounting locations ARIA workstation 4-21
camera 3-38 ARIA workstation components 4-21
closed circuit TV 3-28 CCTV camera 4-20
IRM 3-21, 3-25 control and imaging cabinets 4-20
Live View camera 3-27 power requirements for TrueBeam 4-9
optical imaging subsystem 3-18 power supply, camera 3-33
mounting methods power switches for setup lights 4-20
camera support 3-46 preferred ceiling mount load plate locations
in-room monitor 3-22 TrueBeam 3-38
optical imaging subsystem 3-20 pre-installation checklist A-1, B-1
moving modulator 3-11 pressure regulator specifications 3-60
Protocol, TCP/IP 4-8
N pull/junction boxes 3-2
network cabling and termination 4-7 accessory pull box 3-3
baseframe pull box 3-3
O control equipment pull box 3-2
operational states 3-55, 4-17 in-room monitor pull box 3-3
optical imaging subsystem 3-18 modulator pull box 3-3
mounting locations 3-18
mounting method 3-20 Q
optical imaging with IRM 3-17 QA fixture 3-34
optical system 3-32
optical system, OSMS 3-48 R
optional radiation detector 3-35
bypass/override switch 4-17 radiation shielding
Calypso Extracranial Radiosurgery Subsystem 3-31 calculation assumptions for 3-63
room configurations 2-11 details 3-62
options, system 3-35 relay junction box 3-4, 4-22
OSMS described 4-22
camera elevation heights and clearances 3-53 requirements
camera mounting locations 3-51 acoustical 5-12
camera support mounting methods 3-54 carpeting 5-12
ceiling mount load plate 3-54 coolant 3-58
Intracranial Radiosurgery Subsystem 3-48 electrical 4-1
optical system 3-48 facilities 3-1
system assembly 3-50 flooring 5-12
treatment room remote terminal 3-49 general room storage 5-8
typical room configuration 3-50 HVAC and plumbing 3-55
workstation 3-48 minimum coolant flow 3-56
power 4-9
power conditioning 4-7
Index-3
rigging/shipping dimension clearances 2-20, 3-47 supported accelerator models 1-3
room configurations, optional 2-11 switches
room lighting 4-17 bypass/override 4-17
CCTV 4-17 emergency-off 4-19
laser positioning lights 4-17 setup lights 4-20
main room lights 4-18 system assembly for OSMS 3-50
room lights 4-17 system components
setup lights 4-18 minor 3-26
room shielding tables 2-1 modulator cabinet 3-9
room storage requirements, general 5-8 optical imaging with IRM 3-17
system information, general 2-1
S system options 3-35
safety device systems 4-18 systems
Beam Ready warning light 4-19 coolant 3-56
Beam-Off warning light 4-19 safety device 4-18
Beam-On warning lights 4-18 TrueBeam Linear Accelerator 4-9
emergency-off switches 4-19
Generator ON (Integrated Imaging) warning T
light 4-19 tables for typical room shielding 2-1
safety door interlock switches 4-20 TCP/IP Protocol 4-8
X-RAY ON (Integrated Imaging) warning light 4-19 technical key features for TrueBeam 1-1
safety door interlock switches 4-20 termination 4-7
sagittal laser mounting detail 3-79 termination and cabling, network 4-7
sample timeline 2-5 timeline
setup lights 4-17, 4-18, 4-20 installation 1-3
shielding 3-62 sample 2-5
other 3-64 touch screen computer 3-32
radiation details 3-62 tracking station 3-33
shipping list C-1 transponders, Beacon 3-34
shipping/rigging dimension clearances 2-20, 3-47 treatment planning data import 3-36
side laser mounting detail 3-75 treatment room console 3-31
software 3-34 treatment room overview, sample set-up 3-1
speakers and microphones 3-30 treatment room remote terminal for OSMS 3-49
specifications TrueBeam, preferred ceiling mount locations 3-38
circuit breaker panel (with battery backup) 4-12 typical room
coolant 3-59 configuration 2-7, 3-37
electrical connections 4-2 configuration, OSMS 3-50
environmental 3-60 isometric view 2-5
general electrical 4-1 shielding tables 2-1
lighting and accessories circuits 4-1
V
power conditioning requirements 4-7
Varian relay junction box, described 4-22
pressure regulator 3-60
ventilation 3-60
wiring and components 4-1
standard modulator 3-9
W
standard mounting location for IRM 3-21 wiring and components, specifications 4-1
subsystems wiring diagram, interconnection 4-15
audio 3-30 workstation for OSMS 3-48
closed circuit TV 3-28
Live View camera 3-27 X
optical imaging 3-18 X-RAY ON (Integrated Imaging) warning light 4-19
Index-4