ITP For Etmam
ITP For Etmam
ITP For Etmam
TRAINING CENTER
CONTENTS
REVISION HISTORY
REVISION DESCRIPTION
Description
Added/
Employer Doc
No. Deleted/ Section
No.
Modified
Basrah Refinery Upgrading Project
TRAINING CENTER
SCOPE
This document describes the Inspection and Test Plan (ITP) including its check sheets and inspection
report format for only to Training Center’s construction work for Basrah Refinery Upgrade Project.
REFERENCES DOCUMENT
The following documents shall be referred to where required.
Abbreviations
The following abbreviations shall be applied for this project.
Term Description
EMP Employer
SUB Subcontractor
The following construction ITP shall be followed by Subcontractor and implement all inspection in
accordance with the ITP in Attachment 1.
Subcontractor shall fill all related CCS and ITR as per Attachment 2 list and Attachment 3 formats.
These CCS and ITR shall be approved by Contractor/EPC Subcontractor to verify its compliance
against required acceptance criteria.
Intervention abbreviation and notification rule for each intervention level are shown in the following
table and notification requirements shall be followed by Sub-contractor.
Subcontractor responsibilities
The witnessed inspections and document reviewed by Contractor/EPC Subcontractor does not relieve Subcontractor of his responsibilities or obligations
under the contract and governing statutory regulations / code.
contractor rights
Contractor/EPC Subcontractor reserve the rights to carry out more detailed inspection and modify this ITP as deemed necessary based on subcontractor
work performance.
2 Earth Work
Check for coordinate, elevation and CCS-3100-002 Survey
stability (Benchmark Installation & Report
2.1 Excavation) Applicable Drawing No deviation ITR-3100-002A I S
FDT
ITR-3100-003A Report
Check sand bedding, filling and Survey
structural soil backfilling CCS-3100-004 Report
2.2 Applicable Drawing No deviation I S
ITR-3100-004A FDT
Report
2.3 Conduct compaction test Applicable Drawing No deviation CCS-3100-003 I W
Basrah Refinery Upgrading Project
TRAINING CENTER
3 Concrete
Slump / Lab test Lab Test
3.1 Applicable Drawing No deviation CCS-3200-002 I W
Record
Check Form work Survey
3.2 Applicable Drawing No deviation CCS-3200-002 I S
Report
6.4 Corner and joint beads setting Applicable Drawing No deviation CCS-4000-205 I S
Basrah Refinery Upgrading Project
TRAINING CENTER
7.2 Location and size of Wall openings Applicable Drawing No deviation CCS-4000-206 I S
Location, alignment, spacing and
7.3 rigidity of runners / studs installed Applicable Drawing No deviation CCS-4000-206 I S
per manufacturer‘s recommendation
Reinforcement for wall openings,
7.4 Wall mounted M&E items, Applicable Drawing No deviation CCS-4000-206 I W
equipment, fixtures and fittings etc.
Check concealed M&E items has
7.5 Applicable Drawing No deviation CCS-4000-206 I W
been completed
Insulation board / blanket
7.6 Applicable Drawing No deviation CCS-4000-206 I W
installation
7.7 Type and thickness of Wall board Applicable Drawing No deviation CCS-4000-206 I S
Basrah Refinery Upgrading Project
TRAINING CENTER
8 Floor Works
Layout, marking and check of
8.1 Applicable Drawing No deviation CCS-4000-207 I R
substrate
Check location and size of
8.2 Applicable Drawing No deviation CCS-4000-207 I W
concealed M&E items
Verify the type, pattern and layout of
8.3 Applicable Drawing No deviation CCS-4000-207 I S
tiles
8.4 Corner and joint beads setting Applicable Drawing No deviation CCS-4000-207 I S
Method, type, mixing ratio and
8.5 application of bedding mortar / grout Applicable Drawing No deviation CCS-4000-207 I R
or adhesive
Alignment, level and flatness /
8.6 Applicable Drawing No deviation CCS-4000-207 I S
evenness of installed tiles
Conditions of cut tile edges and
8.7 projection around embedded pipes Applicable Drawing No deviation CCS-4000-207 I S
and fitting
9.14 Labels for fire rated door Windows Applicable Drawing No deviation CCS-4000-208 I W
Basrah Refinery Upgrading Project
TRAINING CENTER
10 Waterproofing
Location of up-stands, pipe
10 penetration, foundation bases, Applicable Drawing No deviation CCS-4000-302 I R
10.1 raisers, drain etc.
Installation of Waterproofing
10.6 membrane at corners, risers, end Applicable Drawing No deviation CCS-4000-302 I W
stop, penetrations and drain
11 Painting
Verification of Paint Material and MAR with
11.1 Certificate Applicable Drawing No deviation CCS-3930-001 I S Supplier’s
certificate
ATTACHMENT-2: Completion check sheet (CCS) & inspection test report (itr) list
4. CCS-3200-002 Completion Check Sheet for Design mix & Trial mix Approval
8. CCS-4000-207
Completion Check Sheet for Floor Works
9. CCS-4000-208
Completion Check Sheet for Doors & Windows
15. CCS-3930-002
Completion Check Sheet for Surface Preparation & Paint Application
17. CCS-3300-001
Completion Check Sheet for Material Inspection
18. CCS-3300-002 Completion Check Sheet for Base Connection
20. CCS-3300-005 Completion Check Sheet for Visual Check of Field Weld
25. CCS-4000-502 Completion Check Sheet for Performance Check for Plumbing Equipment
Attachment-3 Completion CHECK SHEET (CCS) & INSPECTION TEST REPORT (ITR) FORMAT
CCS No.:4000-201
PCWBS FWBS
General Remarks:
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
CCS No.:4000-202
PCWBS FWBS
2 Ceiling Works
2.13 Surface condition for exposed ceiling frame and panel boards
General Remarks:
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
CCS No.:4000-203
PCWBS FWBS
3.9 Location and type of electrical conduit, box and sleeve pipe etc
3.11 Grouting
3.13 Curing
General Remarks:
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
TAG No / ID TAG / ID
Description
PCWBS FWBS
Lab test
- Chloride content
- SO3 content
General Remarks:
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
CCS No.:4000-206
6.8 Wall board layout, height, number and spacing of tapping screws
6.9 Treatment of cut board edges, board joints and corner beads
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
CCS No.:4000-207
PCWBS FWBS
7 Floor Works
General Remarks:
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
CCS No.:4000-208
PCWBS FWBS
8.3 Type, size, location and orientation of door / window being installed
General Remarks:
SIGNATURE
PRINT NAME
DATE
COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER