BOTA FENCE BOQ(RYA)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

RYA Bill Of Qunatities Files..

BOQ

Proposed BOQ For the construction of a fence by Engr. Kila Sylvester


G+3 Fence Project Estimate
No Designation Unit Quantity Unit Price Total Price
100 Preliminary works: This involves the setting of the site before construction
101 Cleaning of site FF 1 100000 100000
102 Site Installation FF 1 100000 100000
103 Setting out of the building FF 1 150000 150000
Sub Total 100: XAF 350,000
200 Foundation works: this involves the realisation of the substructure
201 Purlines for setting Out no 50 1000 50000
202 Cement Dangote or CIMAF 42.5 bags 400 5500 2200000
203 Gravel tons 20 15000 300000
204 Sand no 15 10000 150000
205 Rod D10 for reinforced concrete works no 100 5100 510000
206 Rod D6 for reinforced concrete works no 120 1700 204000
207 Boards for Formwork 4m no 20 1500 30000
208 Foundation Blocks (20x20x40) no 2363 500 1181500
209 Binding Wire rolls 10 1000 10000
210 Nails pac 5 4500 22500
Sub Total 200: XAF 4,658,000
300 Fence Walls Errection works: This involves the realisation of the superstructure
301 cement blocks for masonry walls no 3780 500 1890000
302 Cement (Dangote 42.5) bags 300 5500 1650000
303 Sand tons 20 15000 300000
304 Gravel tons 35 10000 350000
305 Reinforcement (HA 10) no 130 5100 663000
306 Reinforcement (HA 6) no 150 1700 255000
307 Binding wires rolls 10 1000 10000
308 Nails pac 10 4500 45000
309 Boards for Formwork 4m no 25 6500 162500
Sub Total 300: XAF 5,325,500
400 Fence Finishings works: This involves the final beautification of the Struture
401 Plastering and finishings m2 550 2500 1375000
402 Painting and aesthetical improvements m2 550 5000 2750000
403 Doors and gates no 1 1500000 1500000

Quantity Surveyor : Nkwenti Rynie Detrich Cho/ (+237) 671 880 519
RYA Bill Of Qunatities Files.. BOQ

Installation of fence accessories and


404 electrifications
no 1 500000 500000
Sub Total 400: XAF 6,125,000
SUMMARY (A review of the entire BOQ)
PRELIMINARY SITE WORKS: 350000
FOUNDATION WORKS: 4658000
FENCING OF WALLS ELEVATION: 5325500
FENCE FINISHINGS 6125000
GENERAL TOTAL WITHOUT TAXES 16,458,500
COST OF LABOUR (30% Cost of materials) 4,937,550
COST OF EQUIPMENT (15% Cost of materials) 2,468,775
TOTAL PROJECT COST (excluding VAT) 23,864,825
Twenty three Million, Eight Hundred and Sixty Four Thousand, eight hundred and
twenty five francs CFA

Quantity Surveyor : Nkwenti Rynie Detrich Cho/ (+237) 671 880 519