Asha Sahani Construction .

BOUNDARY WALL ESTIMATE :- ( A.)

Estimate cost of Proposed Boundary wall Construction By Name of :- Mr. Tanweer Ahmed
AT . :- Simahuli , P.S. :- Pupri , Dist- Sitamarhi . Construction area Boundary wall –
( 1218 ft length ) .

SI Item Description
N No.
o.
01 5.2.2 Providing R.C.C M 20 columan with approved quality of
. stone chips 20 mm to 10 mm size graded and clean
course sand of F.M. 2.5 to 3 including screening , Cement = 200Bags
centring shuttering , mixing Cement concrete in mixture SAND = 1700 CFT
and placing in position , vibrating , striking , cutting ( but AGGREGATE = 1600 CFT
excluding the cost of reinforcement ) taxes and royalty STEEL= 1200 KG
all complete as per building specification and direction ( COLUMAN STEEL & RING )
of e/I.Providing R.C.C. M-20 In columns with approved
1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone
aggregate 20mm nominal size
For 10” x 10” column
98 no. x0’10” x 10”x10’’x10’
= 98 no. x0.83’x0.83’x0.83’ x10’
= 560.65 cft
01cum=35.319cft ,
than 560.65 cft/35.319 =15.86 cum

02 5.33A. Reinforced Cement Concrete work in beams Cement = 255 Bags


. 2.2 cases up to TOP & GROUND level excluding the cost SAND = 2100 CFT
of centring , shuttering , finishing , and reinforcement AGGREGATE = 1900 CFT
with 1:2:4 (1 cement :2coursesand : 4 STEEL= 1300 KG
graded stone aggregate 20 mm nominal size ). (BEEM STEEL & RING )
Beam plinth ,girders, bressumers , contileverse
Suspended etc.
(1). 20’ x 0’10” x 0’10”X 10 nos. = 138 cft
(2). 10’’x10’’x135’ x 2 nos. = 187.35 cft
(3). 10’’x1.5’x( 235’+247’) = 602.25 cft
(4).10’’x0.6’’x(231’+39’) = 112 cft
TOTAL = 1039.45 CFT
=1039.45cft/35.319cum = 29.43 cum

03 5.9.5 GROUNDLEVEL P.C.C TOP LEVREL Cement = 80 Bags


. SAND = 700 CFT
AGGREGATE = 1000 CFT
04 BONDARY ANGLE 165 Peas
.

05 6.18.4 Providing 125mm thick rain forced designation 100 mm BREAKS = 34500 PEAS
. A+ A brick work in C.M (1:4) IN Superstructure with Cement = 165 Bags
6.19A approved quality of clean coarse sand of F.M 2 TO 2.5 SAND = 1500 CFT
THE COST OF screening carriage of materials scaffolding
, raking out joints to 15mm depth , curing, taxes and
royalty (but excluding the cost of reinforcement) all
completers per.
10’’wall x 1218’x5’= 6090 sqft
1218’sqft x hight 5’=6090 ’sqft

TOTAL ITEMS. RATE Rs. .


CEMENT 700 BAGS 420 2,94,000/Rs
STEEL 2500 KG 66 1,65,000/Rs.
( COLUMAN , BEEM STEEL & RING )
SAND 6000 CFT 66 3,96,000/Rs.

AGGREGATE 4500 CFT 110 4,95,000/Rs.


BREAKS 35,000 8.20 2,87,000/Rs.
Peas
BONDARY ANGLE 165 Peas 600+ 1,15,500/Rs.
labor
100=
700
LABOR RATE 5083 Sqft 60 3,25,000/Rs.

TOTAL COST. = 20,77,500/Rs.


( TWENTY LACS FIFTEEN THOUSANDS FIVE HUNDREADS ONLY ).