MST for Stonce Cladding Dismantling
MST for Stonce Cladding Dismantling
MST for Stonce Cladding Dismantling
PROJECT
DOCUMENT: METHOD STATEMENT FOR
STONE CLADDING DISMANTLING
Name
Deputy Project
Job Title QA/QC Engineer QA/QC Manager Project Director
Director
Page 2 of 9
Signature
Page 2 of 9
Table of Contents
1 Introduction............................................................................................................................4
2 Scope of Work.......................................................................................................................4
3 References.............................................................................................................................4
4 Key Personnel.......................................................................................................................4
5 Roles and Responsibilities.....................................................................................................5
5.1 Project Manager....................................................................................................................5
5.2 Construction Manager...........................................................................................................5
5.3 QAQC Engineer.....................................................................................................................6
5.4 Site Engineer.........................................................................................................................6
5.5 HSE Engineer / Officer..........................................................................................................7
6 Material and equipment.........................................................................................................7
6.1 Material..................................................................................................................................7
6.2 Equipment..............................................................................................................................7
7 Methodology:.........................................................................................................................9
7.1 Procedure..............................................................................................................................9
7.1.1 Site Survey ......................................................................................................................9
7.1.2 Preparation of Tools and Equipment.................................................................................10
7.1.3 Set Up of Dismantling Zone ……………………………………………………………………..
7.1.4 Marble Removal …………………………………………………………………………………..
7.1.5 Lowering of Marble to the Ground ………………………………………………………………
8 Quality control........................................................................................................................9
9 Safety precautions.................................................................................................................9
10 Risk Assessment..................................................................................................................10
Page 2 of 9
1 Introduction
The objective of this Method Statement is to outline the efficient and safe method of
work to follow in order to safely and efficiently conduct the stone cladding works at the
project. Stone Cladding Dismantling will be conducted in compliance with relevant
safety regulations, local codes, and industry best practices to ensure the protection of
personnel, property, and the environment.
2 Scope of Work
The purpose of this method statement is to describe the detailed procedure for the safe
and efficient methodology of stone cladding dismantling.
3 References
Project Specification
Scope of Work
IFC Drawing
4 Key Personnel
Position Number
Project Manager 1
Construction Manager 1
QAQC Engineer 1
Site Engineer 1
HSE Engineer / Officer 1
Page 3 of 9
5 Roles and Responsibilities
5.1 Project Manager
Ensure and facilitate the effective implementation of the Project Health, Safety and
Environmental Management Plan and approved RAMS.
Ensure that site activities take place in accordance to Project Health, Safety and
Environmental Management Plan and approved RAMS.
Ensure that incidents, accidents and near miss incidents are recorded, reported and
investigated and that the necessary corrective actions are taken and implemented.
Ensure that all incidents and accidents are timeously reported to the Client and HSE
Director.
Ensure that all HSE Observations and NCR’s are closed out within the specified time
period.
Page 3 of 9
5.3 QAQC Engineer
QA/QC Engineer will manage and coordinate the Inspection and Testing in
accordance with the requirement of the Inspection & Test Plan and responsible for
ensuring all the activities are carried out as per the approved method statement,
project specification and approved quality control procedures.
He shall ensure the approved & controlled copies of the drawings only using at site,
which are issued to the site supervising team.
He is responsible for reviewing IRs for all the related day to day activities at site as
per the approved ITP and attending all the required day to day inspection along with
Site Engineer and the Consultant for approvals.
Conduct surveillance & monitoring activity from time to time on a daily basis while
work is in progress as per approved drawings and project specification.
Setting out inspection: Obtain approval from Engineer for setting out prior to
commence with installation
Work should be carried out as per latest approved drawings.
Ensure MEP clearance & signed off by concerned site engineer (if any) prior to
proceed with installation.
Prior to final inspection request for consultant, check and ensure required work is
completed.
He will keep records of all inspections and testing related to the activities.
Page 3 of 9
Ensure that all “No Objection” Certificates and Work Permits are obtained and all
preventive measures mentioned in the permits have been taken prior to
commencement of the work.
Ensure that required work permits are issued to the Foreman / Site Supervisor before
allowing them to proceed with any related works
Ensure that all your personnel have received HSE orientation training about site HSE
requirement and other related HSE training before assigning them to work
Ensure that good housekeeping is maintained at your work site at all times
Ensure that equipment, both power and hand tools are safe and maintained in good
operating condition and is suitable and safe to do the assigned job;
Ensure that his Personnel does not leave their work area unless permitted by you in
writing;
To ensure that all visitors visiting your area of responsibility, comply to the set HSE
requirements and standards as specified in the minimum requirements;
Assign a competent guide to assist drivers delivering materials to the site and lay
down areas;
Ensure that NO work requiring permit approval is permitted, unless proper permit
approval is obtained.
Raising the IR/MIR according to nature of job or specific site requirements
Page 3 of 9
Be proactive in addressing operational HSE issues to ensure that the risk to workers
and others are managed, minimized and prevented as well as the potential
environmental impact prevented / mitigated.
Ensure and facilitate communication and coordination between the company and
subcontractors with respect to health & safety requirements.
Establishing a list of hazardous tasks, requiring safe work permits, implement and
maintain the required permit systems.
6.2 Equipment
Fork Lift
Boom Truck
Cable Drum
Portable Generator
7 Methodology
7.1 Procedure
Page 3 of 9
7.1.2 Preparation of Tools and Equipment:
Appropriate demolition tools such as hammers, chisels, and cutting tools will be
prepared and inspected.
Mechanical equipment (e.g., angle grinder) folk lift can be used for lowering
heavy marbles to the ground
Safety equipment (PPE)
The marble will be firstly shifted to the scaffolding platform and then by judging
the size and weight of the marble the equipment should be used either by
forklift/scissor lift or boom truck to lower it down to the ground.
Adjust the folk lift tines as per the size of the marble, ensuring the folk lift is
parked on a stable surface.
Page 3 of 9
The boom truck/scissor lift should be well equipped with the web sling and
shackles.
Verify ground stability to support the weight of boom truck, scissor lift, scissor
lift.
In this process there should be clear communication between the workers.
Special attention should be given to the safety measure.
Avoid jerky movement to prevent damage to the workers or marble or loss of
control.
Assign spotters or handlers on the ground to guide as it descends.
9 Quality Control
Ensure that all materials are segregated and free from any damaged or defects.
Photographic report shall be initiated before the work starts and upon
completion of the activity
Salvage material to be counted if required bar code/qr code will be implemented
to ensure the quantity of the materials
10 Safety Precautions
Ensure all workers wear appropriate PPE, including helmets, gloves, safety
glasses, and boots.
Maintain proper ventilation when using bonding agents and other chemicals.
Implement fall protection measures when working at heights.
Provide adequate training for workers on the safe use of equipment and
Page 3 of 9
materials.
A Site Engineer and HSE officer will be monitoring the activity at all times.
Site Engineer will ensure that the RAMS are communicated to the operatives
prior to commencement of the activity.
Start briefing will be conducted and communicated to the operative. HSE
Officer will ensure that all required documents are valid and available. 3rd party
certificates for equipment, inspection on safety equipment and verify require
training of employees.
Prior to start activity work permit to issue and approved by all relevant parti
Page 3 of 9
Page 3 of 9