Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

MST for Stonce Cladding Dismantling

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 12

SOUTH TERMINAL REHABILITATION

PROJECT
DOCUMENT: METHOD STATEMENT FOR
STONE CLADDING DISMANTLING

South Terminal Rehabilitation General Works Package


King Abdulaziz International Airport (KAIA), Jeddah,
KSA

Method Statement for Stone Cladding Dismantling


Document No. : ATV-1300000403-GEN-MST-00002 Rev. 00
Issue Status : For Approval
Project Phase : Construction Stage

Prepared by: Reviewed & Checked by: Approved by:

Name

Deputy Project
Job Title QA/QC Engineer QA/QC Manager Project Director
Director

Page 2 of 9
Signature

Date 16-JAN-25 16-JAN-25 16-JAN-25 16-JAN-25

Page 2 of 9
Table of Contents
1 Introduction............................................................................................................................4
2 Scope of Work.......................................................................................................................4
3 References.............................................................................................................................4
4 Key Personnel.......................................................................................................................4
5 Roles and Responsibilities.....................................................................................................5
5.1 Project Manager....................................................................................................................5
5.2 Construction Manager...........................................................................................................5
5.3 QAQC Engineer.....................................................................................................................6
5.4 Site Engineer.........................................................................................................................6
5.5 HSE Engineer / Officer..........................................................................................................7
6 Material and equipment.........................................................................................................7
6.1 Material..................................................................................................................................7
6.2 Equipment..............................................................................................................................7
7 Methodology:.........................................................................................................................9
7.1 Procedure..............................................................................................................................9
7.1.1 Site Survey ......................................................................................................................9
7.1.2 Preparation of Tools and Equipment.................................................................................10
7.1.3 Set Up of Dismantling Zone ……………………………………………………………………..
7.1.4 Marble Removal …………………………………………………………………………………..
7.1.5 Lowering of Marble to the Ground ………………………………………………………………
8 Quality control........................................................................................................................9
9 Safety precautions.................................................................................................................9
10 Risk Assessment..................................................................................................................10

Page 2 of 9
1 Introduction
The objective of this Method Statement is to outline the efficient and safe method of
work to follow in order to safely and efficiently conduct the stone cladding works at the
project. Stone Cladding Dismantling will be conducted in compliance with relevant
safety regulations, local codes, and industry best practices to ensure the protection of
personnel, property, and the environment.

2 Scope of Work
The purpose of this method statement is to describe the detailed procedure for the safe
and efficient methodology of stone cladding dismantling.

3 References
 Project Specification
 Scope of Work
 IFC Drawing

4 Key Personnel
Position Number
Project Manager 1
Construction Manager 1
QAQC Engineer 1
Site Engineer 1
HSE Engineer / Officer 1

Page 3 of 9
5 Roles and Responsibilities
5.1 Project Manager
 Ensure and facilitate the effective implementation of the Project Health, Safety and
Environmental Management Plan and approved RAMS.
 Ensure that site activities take place in accordance to Project Health, Safety and
Environmental Management Plan and approved RAMS.
 Ensure that incidents, accidents and near miss incidents are recorded, reported and
investigated and that the necessary corrective actions are taken and implemented.
 Ensure that all incidents and accidents are timeously reported to the Client and HSE
Director.
 Ensure that all HSE Observations and NCR’s are closed out within the specified time
period.

5.2 Construction Manager


 Establish, as far as is reasonably practicable, what hazards are related to any work
undertaken at the workplace and ensuring that Risk Assessments are conducted,
recorded and implemented, this includes the development and review of method
statements;
 Ensure and facilitate the effective implementation of the task Method Statement and
Risk Assessment (RAMS);
 Ensure that daily Safety Task Analysis Risk Reduction Talks (START) are conducted
and recorded prior to the commencement of any task / activity;
 Eliminate or mitigate any hazard or potential hazard to the health and safety of
employees;
 Provide and maintain a work environment that is safe and without risk to the health
and safety of the employees and the environment;
 Provide such information, instructions, training and supervision as may be necessary
to ensure, as far as reasonably practicable, the health and safety of the employees
and environmental is protected;
 Taking the necessary, corrective and preventative actions on all deviations reported
and enforcing such measures and discipline as may be necessary in the interests of
employee health and safety and the environment;
 Maintaining proper written records of all aspects to HSE matters and HSE
operational requirements;
 Ensure that high standards and required levels of housekeeping is maintained;
 Ensure that Permit to Work requirements are complied with and adhered to;
 Ensure that ALL incidents are investigated, recorded and discussed at the HSE
Committee Meetings and corrective action implemented and communicated;
 Identifying areas of potential fire hazards and implement required control measures.

Page 3 of 9
5.3 QAQC Engineer
 QA/QC Engineer will manage and coordinate the Inspection and Testing in
accordance with the requirement of the Inspection & Test Plan and responsible for
ensuring all the activities are carried out as per the approved method statement,
project specification and approved quality control procedures.
 He shall ensure the approved & controlled copies of the drawings only using at site,
which are issued to the site supervising team.
 He is responsible for reviewing IRs for all the related day to day activities at site as
per the approved ITP and attending all the required day to day inspection along with
Site Engineer and the Consultant for approvals.
 Conduct surveillance & monitoring activity from time to time on a daily basis while
work is in progress as per approved drawings and project specification.
 Setting out inspection: Obtain approval from Engineer for setting out prior to
commence with installation
 Work should be carried out as per latest approved drawings.
 Ensure MEP clearance & signed off by concerned site engineer (if any) prior to
proceed with installation.
 Prior to final inspection request for consultant, check and ensure required work is
completed.
 He will keep records of all inspections and testing related to the activities.

5.4 Site Engineer


 Organize the project activities so that work is carried out as required in compliance
with standards, specifications and approved RAMS, with minimal risk to men,
existing facilities, equipment, materials or the environment.
 Ensure subordinates are instructed on the requirements of the Job Hazard Analysis,
Safe Work Procedures / Instructions, HSE Procedures and RAMS.
 Ensure that the identified HSE measures for specific tasks are in place prior to
activity commencement, and that corrective action has been taken to eliminate or
control any potential hazard or environmental impact
 Ensure that personnel are adequately trained and competent to complete their
assigned tasks in a safe and efficient manner.
 Monitor and check that subcontractors are working in accordance with the
requirements and approved RAMS.
 Ensure that daily Pre-Start Meetings and weekly Toolbox Talks, are conducted and
recorded.
 Give specific instructions, in consultation with Project HSE / Engineer / Officer, for
safe and correct work method for critical work areas such as working at elevated
positions.

Page 3 of 9
 Ensure that all “No Objection” Certificates and Work Permits are obtained and all
preventive measures mentioned in the permits have been taken prior to
commencement of the work.
 Ensure that required work permits are issued to the Foreman / Site Supervisor before
allowing them to proceed with any related works
 Ensure that all your personnel have received HSE orientation training about site HSE
requirement and other related HSE training before assigning them to work
 Ensure that good housekeeping is maintained at your work site at all times
 Ensure that equipment, both power and hand tools are safe and maintained in good
operating condition and is suitable and safe to do the assigned job;
 Ensure that his Personnel does not leave their work area unless permitted by you in
writing;
 To ensure that all visitors visiting your area of responsibility, comply to the set HSE
requirements and standards as specified in the minimum requirements;
 Assign a competent guide to assist drivers delivering materials to the site and lay
down areas;
 Ensure that NO work requiring permit approval is permitted, unless proper permit
approval is obtained.
 Raising the IR/MIR according to nature of job or specific site requirements

5.5 HSE Engineer / Officer


 Supervise on-site health & safety control and promote the safe conduct of site work
and environmental protection.
 Responsible for overseeing and ensuring the keeping of up-to-date HSE records,
forms and files in accordance to the Project H&S Plan to ensure compliance and to
enable auditing to be carried out.
 To prevent unsafe acts being undertaken by anyone on the site and to stop and
prevent work to continue / commence in prevailing unsafe conditions.
 Ensure that all employees / workers (including subcontractors) are issued with and
properly use the correct PPE and safety devices for the work being performed.
 Report any incidents, accidents or near misses immediately, as per the approved
procedure, (this may include liaison with police and / or authorities) and to secure the
area by preventing that the area be tampered with.
 Investigate incidents, accidents and near miss events to determine the root, basic
and immediate causes and ensure that correction / corrective / preventative actions
are implemented for all H&S related events.
 Ensure site welfare facilities (rest areas, water, toilets, etc.) are sufficient for the
number of personnel, and are being provided by the site supervisory staff as well as
ensuring that high standards of hygiene are maintained.
 Promote a positive HSE attitude to personnel, subcontractors, consultants and clients.

Page 3 of 9
 Be proactive in addressing operational HSE issues to ensure that the risk to workers
and others are managed, minimized and prevented as well as the potential
environmental impact prevented / mitigated.
 Ensure and facilitate communication and coordination between the company and
subcontractors with respect to health & safety requirements.
 Establishing a list of hazardous tasks, requiring safe work permits, implement and
maintain the required permit systems.

6 Material and Equipment


6.1 Material/Tools
 Hammer
 Chisel
 Pry bar
 Angle Grinder
 Wrench
 Spanner

6.2 Equipment
 Fork Lift
 Boom Truck
 Cable Drum
 Portable Generator

7 Methodology
7.1 Procedure

7.1.1 Site Survey:


 Conduct a site survey to assess the condition of the marble cladding and
identify potential risk.
 Isolate the work area using barriers, warning signs and safety tape to prevent
unauthorized access.
 Directly control and give instruction to the working personnel to perform the
work as per execution plan, proper PPE’s.
 Identify and de energize any electrical wiring/fixtures near the site.
 Look if there’s any piping’s or any fire hydrant.

Page 3 of 9
7.1.2 Preparation of Tools and Equipment:
 Appropriate demolition tools such as hammers, chisels, and cutting tools will be
prepared and inspected.
 Mechanical equipment (e.g., angle grinder) folk lift can be used for lowering
heavy marbles to the ground
 Safety equipment (PPE)

7.1.3 Setup of Dismantling Zone:


 The dismantling zone will be cordoned off with barriers, and use of safety tape
to prevent unauthorized access.
 Erect scaffolding or access platforms with proper safety features, such as toe
board, guard rails, harness connected to robust anchor points.
 Ensure the scaffolding is stable and can withstand the weight of tools, worker
and material.
 A designated area will be set aside for storing reusable materials, where
marbles will be cleaned and protected

7.1.4 Marble Removal

 Begin dismantling from the topmost row of cladding, working downwards.


 Carefully remove the silicone/sealant around the marble using a suitable sharp
tool.
 Install suction cups on the surface of the tile to be removed, ensuring they are
securely attached.
 If the marble is fixed with (bolts/screws) begin by removing these with tools like
angle grinder/chisel
 Collect the detached marble on a pallet on the scaffolding, with a maximum of 4-
5 marbles per pallet.
 Use appropriate tools (e.g., chisel, hammer, pry bar) or use any mechanical
equipment’s such as angle grinder or rotary hammer to detach it from the wall.
 To carefully detach the marble cladding, the topmost layer will be detached off
the wall and made to lay on the scaffolding platform using the suction cups by
workers, and same towards to the down.
 Using boom truck/forklift or scissor lift for lifting of marbles.

7.1.5 Lowering marble to the ground

 The marble will be firstly shifted to the scaffolding platform and then by judging
the size and weight of the marble the equipment should be used either by
forklift/scissor lift or boom truck to lower it down to the ground.
 Adjust the folk lift tines as per the size of the marble, ensuring the folk lift is
parked on a stable surface.

Page 3 of 9
 The boom truck/scissor lift should be well equipped with the web sling and
shackles.
 Verify ground stability to support the weight of boom truck, scissor lift, scissor
lift.
 In this process there should be clear communication between the workers.
Special attention should be given to the safety measure.
 Avoid jerky movement to prevent damage to the workers or marble or loss of
control.
 Assign spotters or handlers on the ground to guide as it descends.

8 ENVIRONMENTAL CONSIDERATIONS AND IMPACT


CONTROL MEASURES
8.1 Dust Control

 Sustainability: Prioritize recycling and reuse of materials where possible,


minimizing the environmental impact of demolition.
 Waste Segregation: Implement a system for separating recyclable and non-
recyclable materials.
 Dust and Noise Mitigation: Use dust control methods and minimize noise by
selecting quieter equipment for demolition.
 Using water sprinkling method/water spray when in confined space or as per
HSE requirement is a must
 Use vacuum system for collecting the dust within the perimeter where the work
is being held.

9 Quality Control

 Ensure that all materials are segregated and free from any damaged or defects.
 Photographic report shall be initiated before the work starts and upon
completion of the activity
 Salvage material to be counted if required bar code/qr code will be implemented
to ensure the quantity of the materials

10 Safety Precautions
 Ensure all workers wear appropriate PPE, including helmets, gloves, safety
glasses, and boots.
 Maintain proper ventilation when using bonding agents and other chemicals.
 Implement fall protection measures when working at heights.
 Provide adequate training for workers on the safe use of equipment and

Page 3 of 9
materials.
 A Site Engineer and HSE officer will be monitoring the activity at all times.
 Site Engineer will ensure that the RAMS are communicated to the operatives
prior to commencement of the activity.
 Start briefing will be conducted and communicated to the operative. HSE
Officer will ensure that all required documents are valid and available. 3rd party
certificates for equipment, inspection on safety equipment and verify require
training of employees.
 Prior to start activity work permit to issue and approved by all relevant parti

11 Risk Assessment (RAMS)


 Refer to Attachment

Page 3 of 9
Page 3 of 9

You might also like