Training New Building
Training New Building
Training New Building
Overview of Lecture
-1/88-
Part 1
Outline of hull survey system Requirements of the rules Plan approval Presence of surveyor Investigation of quality control of shipyard
-2/88-
If the distribution of accuracy is Gaussian, proportion within , 2, 3 is 68.26, 95.44, 99.74% respectively.
-3/88-
Head Office
(1), (2),
(3)
Local Office
(1), (2), (4)
Shipyard
(1) Documents to be approved at Head Office (2) Documents to be examined at Head Office (3) Documents for reference at Head Office (4) Document to be approved at Local Office (5) Documents for reference at Local Office
Note: Regarding plans and document hereafter, ones for application of CSR are excluded)
Presence of Surveyor
Surveyor is to attend to the followings inspection and test in relation to hull and equipment (free quotation from the rules Part B, Chapter 2, 2.1.4-1): Material test prescribed in Part K, L and M Acceptance inspection Block inspection Hydrostatic test, watertight test and non-destructive test Final inspection of hull Performance test Rudder Measurement of principal dimensions Loading computer Marking of Load Lines and ships identification number Sea trial Stability experiments Emergency towing arrangements Fire extinguishing arrangement, including its performance test
Patrol Survey
The purpose of patrol survey is to grasp the actual circumstance of quality control of the shipyard through an investigation of following points during the fabrication (it may be impossible at block inspection) Welding procedure (temporary fitting, edge preparation, position, back gouging, sequence, welders qualification, etc.) Handling of defective work (material, size, accuracy of fitting, record, etc.) Surveyor in charge execute a patrol survey at any time of following occasions, while he follows an application submitted by the shipyard for usual survey To pass through the work shop on his way to and from the place of usual survey, To execute in his spare time of survey, etc. The results of patrol survey should be periodically reported to the General Manager as the monthly report of investigation of QC of the shipyard Surveyor should review his attendance of survey, such as timing and method, according to the results of the investigation of QC of the shipyard
-4/88-
Layout of a Shipyard
Acceptance inspection Block inspection Block assembling, final, fitting, etc. Stability experiments, performance tests Seek for opportunity of patrol survey
-5/88-
Periodical Investigation
Timing (a) When the shipyard builds a ship being classed with NK for the first time (b) When about 5 years have passed from the previous periodical investigation (c) When the size of ship being classed with NK breaks through 10,000, 30,000 or 100,000 GT for the first time (d) When the shipyard re-starts building a ship being classed with NK after a blanc period of more than 2 years Contents Facilities and features of construction, number of welders, system and details for quality control, etc. (see Record A)
Annual Investigation
Timing When about 1 year has passed from the previous periodical or annual investigation Contents About 20 % of the items for a periodical investigation Record Prepare Record A
Occasional Investigation
Timing (a) When there is a change in the organization of the shipyard or in the layout of shipyard having influence on quality control (b) When the surveyor attending regular survey finds out a serious deficiency which may affect quality of ships (prepare Form S) (c) When the shipyard builds a ship using special production procedure (e.g. LNG carrier, low temperature LPG carrier, etc.) or special material (e.g. stainless steel, clad steel, etc.) (d) When the society deems necessary Contents The items that the society deems necessary relating to (a) to (d)
-6/88-
Monthly Investigation
Timing Notwithstanding its naming, the investigation should be done during daily survey. Report may be done 1 or 2 monthly. Contents Identification of steel, welding procedure, control of welding materials, observance of the quality standard, etc. are to be investigated at each stage such as in-shop fabrication, panel fabrication, block assembly and block loading Record Prepare Record B
Part 2
Record of Inspection
Form IR(H) Form IR (H-A948) Form IR(H) Attachment
Form IR
QC control record
Record A
Record B
Deficiency record
Form S
-7/88-
Part 3
1. 2. 3. 4. 5.
Survey on Site
11. 12. 13. 14. 15. 16. 17. Paint Markings Piping Fire protection Closing appliances Protection of crew Bottom inspection before Launching 18. Stability experiments 19. Navigation bridge visibility 20. Sea trial 21. Documents to be maintained on board
Acceptance inspection Welding Shop Work and Sub-Assembly Block inspection Block joining on building berth 6. Rudder 7. Final inspection of hull compartment 8. Tightness/ Hydrostatic test 9. NDT of welded joints 10. Measurement of principal dimensions
1. Acceptance Inspection
Object of inspection Material and equipment manufactured by subcontractors outside the shipyard, such as rolled steel, steel casting and forging, welding materials, construction materials for fire protection, anchors, anchor chains, ropes, scuttles, hatch tarpaulins, hull blocks (*), steel hatch covers, watertight doors, steering gears, etc. Purpose of inspection To confirm that they have been inspected by the society, and that they have not been damaged during transportation
-8/88-
The surveyor should confirm not only the stamp but also if the article is suitable for the intended ship; in this case ships Equipment Number.
Rolled Steel
Collation of plate and mill sheet Verification of control by the shipyard (checking-off of already used plate) should be done at least once before launching As to checking-up of mill sheet and actual usage of plate, see 4 Block inspection below
-9/88-
Sampling test
Rolled steel: Tensile test, and impact test if deemed necessary Cast steel and forged steel: NDT, mechanical test as appropriate to the material (tensile, hardness, impact, etc.)
Testing machine
The machine used for mechanical test must be certified by NK or appropriate body
Welding Material
Object of inspection: Welding rods, wire for semi-automatic welding, core wire and flux for automatic welding Manner of inspection: Verification of brand to confirm that they are of type approved by NK. Reference should be made to the approved welding procedures applicable to the ship in question. Actual status and control condition of facilities for drying welding materials are to be investigated at the initial stage of construction
-10/88-
2. Welding
Welding procedure qualification (general) Welder qualification Welding procedure specification (individual application of approved welding procedure qualification to a ship) Kind of members within 0.6 L amidships for on-site welding procedure The welding procedure applicable to the locations above, and welding position Execution of welding and control Control of welding consumables A proper welding shall be done by qualified welder with approved materials in accordance with approved procedure.
Welding procedure qualification and welder qualification approved by other IACS member society may be accepted. In such case, a stamp for reference is to be put and copy of the document sent to EQD.
Semi-automatic welding
Automatic welding
Submerged arc welding Electro-gas welding Statistics in 2001 (Japanese shipbuilders) CO2 semi-automatic 60% Automatic 30% Gravity 5% Manual (stick) 5%
-11/88-
-12/88-
Class F V H O Z P
Symbol CS SU AL 9N M S T G A N
Fixed pipe
Grade 1 2 3
Stainless steel Alminium alloy 9% Ni steel Manual arc welding Semi-automatic welding TIG welding Gas welding
Each welder intended to engage in the automatic welding operation is to be of a well experienced welder for the specific welding work concerned
Use of backing
Pipe
Plate The specimens are to show neither crack nor serious defect greater than 3mm in length in any direction on the outside surface due to the bending
The test assemblies are not to be changed their up-and-down or right-and-left position throughout the welding operation. The welding in vertical position is to be done upward procedure. The welding is to be carried out only on one side and back welding is not to be carried out unless specified otherwise. In general, the test assemblies for plates are to be so restrained or prestrained that the warping due to the welding does not exceed an angular distortion of 5 degrees. The test assemblies are not to be subjected to peening or heat treatment throughout the period before, during and after the welding.
-13/88-
Qualifications of Welder
A welder of Class Z is regarded to be qualified for all the Classes of F, V, H and O within the same Grade. Any welder who intends to be qualified for Classes V, H, O and P of each Grade and each Kind is to have qualification of Class F of the corresponding Kind and Grade. A welder of any Class of any Grade of Kind N may be regarded as the welder of the same Class of the same Grade of Kind A. If a welder having Class Z of any Grade passes the qualification test on any one welding position of Classes V, H and O (which is specified by the surveyor) and belonging to the same Kind and Grade, his qualifications can be continued. If a welder having Classes other than Class Z passes the qualification test for the Classes (except Class F), he can continue his qualifications including Class F. If a welder having Class P and Classes V, H or O, or Z passes the qualification test for the Class P, he can continue his qualification for plate without test.
Welding Consumables
Drying Control
Type of welding rods Non low-hydrogen Low-hydrogen Maximum period for weathering (hours) Type of steel MS HT Control target 8 4 Allowable limit 24 6 Standard drying conditions 70~150, 30~60 min. 300~350, 30~60 min.
Type of steel
Welding method
Submerged arc welding MS & HT Shielded arc welding CO2 gas arc welding Submerged arc welding 5 10 200~350,60 min.
Welding work outdoors is forbidden when it rains. When such a situation is unavoidable, a rain shelter or covering should be arranged, and special care must be taken to ensure the dryness of the groove of joints and other welding materials
* For KA40, KD40 and KE40, use the values for conventional HT, even if it is TMCP type. ** It is recommendable to be 30mm or more for KE32 and KE36
-14/88-
Patrol Survey
during Shop Work and Sub-Assembly
Identification of steels Confirmation of proper use of steels according to the approved drawings Accuracy of edge preparation Proper fitting of strong back, temporary tack-welding, run-off tab, etc. Accurate fitting of members and corrective measures for defects Proper welding sequence Adequate welding method (including back gouging conditions) conforming to approved welding procedure specification Strict enforcement of rules for arc striking and short bead especially for high tensile steel and Grade E mild steel Qualification of welders
ClassNK
Ship builder
For the allowable criteria of accuracy, refer to the shipyards standard recognized by the society, if available. In principle, such standard should be equivalent or superior to JSQS or SRQS If such standard is not available, refer to JSQS or SRQS JSQS: Japanese Shipbuilding Quality Standard SRQS: IACS Shipbuilding and Repair Quality Standard JSQS SRQS
-15/88-
(1) Are the steel plates per approved plan ? (2) Are the material and size reasonable comparing to mill sheets ? (3) Is the actual block per this plan ?
Cutting
Allowable depth of gas notch in edge preparation is: For a butt welding within 0.6L amidships2mm or less Elsewhere 3mm or less
No notch is allowed at those locations. The notch shall be welded up avoiding a short bead, and ground smoothly. Allowable depth of notch at other locations of free edge, is 1mm.
-16/88-
Size of Bracket
Depth of longer arm 150 200 250 1,000 1,050 1,100 1,150 Thickness Plane 6.5 7.0 8.0 ---11.5 12.0 12.5 12.5 95 100 105 110 Flanged 6.5 6.5 Breadth of flange 30 30
Mechanical Flanging
Accuracy of Processing
-17/88-
Different thickness
Part C 1.2.3-2 requires this tapering not more than 1/3 when there is the difference in the thickness over 4mm
Lap Joint
-18/88-
Lap joint
Tee joint
1. The size f for Tee joints is in general to be determined according to the web thickness of stiffener to deck plate, inner bottom plate, bulkhead plate, shell plate and face plate, and the thickness of the thinner plate in case of connection of other members 2. Lap joint is to have the fillet size of F1according to the thickness of the thinner plate 3. Intermittent fillet weld is to be staggered and w at ends is to be welded on both sides
Intermittent weld
F4
Usually, edge preparation is not required for fillet weld, except at intersection of important members. Instead, size of fillet shall be increased according to the thickness of the member.
-19/88-
Slot Weld
Cleanliness in groove
Tack Weld
Butt joint
Fillet joint
Tack weld should be shifted from the ends of welding Avoid short bead
-20/88-
Securing jig (strong back, bridge) should be used for important members in place of tack weld
Run-Off Tab
Tabs should be provided at both ends of butt welding, because defects are likely to occur here. Tabs are cut after completion of welding, to inspect for defects.
-21/88-
Then connect two strips Plates are relatively thicker, and cracks are likely to occur at the intersection of welding
If seam is not withheld, (1) Butt joint will be deformed due to heat (2) End of butt joint overlaps on the seam, and defect is likely to occur
(1) A scallop is provided to pass the weld of face plate (a scallop in highstress zone should be closed later) (2) Usually, thicker plate shall be welded first (to avoid deformation due to the heat)
-22/88-
Shell plate, Face plate of internal member, Web plate of internal member, Fillet welding between shell plate and web plate
Thickness 25mm
-23/88-
-24/88-
-25/88-
In downward pass of welding in the vertical direction, the throat thickness of the bead tends to become too small, if welding rod motion is incorrect.
Foul Welding
Not only too broad bead, but also too narrow bead is doubtful
-26/88-
Treatment of Mal-Fabrication
Shortage of Size at Fillet Joint
Treatment of Mal-Fabrication
Shortage of Size at Butt Joint
Allowable limit of misalignment is, according to JSQS, 1/3 (important members) or 1/2 (others) of the thickness.
-27/88-
Reconditioning of Misalignment
Butt joint
4. Block Inspection
Scope of survey Block plan Confirmation of steel (see 3. above) Confirmation of structure, accuracy and welding Others
Scope of Survey
The scope of the survey covers blocks below the uppermost continuous deck, blocks for superstructures and deckhouses on the first tier above the uppermost continuous deck, and other blocks deemed necessary by the surveyor. [ClassNK Instructions A20, 0144-5)
The requirements are prescribed for the superstructures/ deckhouses up to the third tier above the freeboard deck. [free quotation from Rules, Part C, Chapter 18 & 19]
-28/88-
Tightness of welding joints on the boundary may be locally tested in this stage (explained in Chapter 11), to start painting
-29/88-
Block Joining
Inspection of this joint only is enough at this stage, because each block has been already inspected
It is not so easy to find such problem, when different blocks or compartments are involved
Members should be extended and lapped each other because a steep knuckle can not transfer the load (maximum angle is about 30 for practice)
-30/88-
If surveyor is not well about the construction, he may overlook this inconvenience
Accuracy of Processing
Deformation of stiffener : where 1,000 mm = 5(8) mm where > 1,000 mm = 3(6) + 2 / 1,000 mm
Usually, lug and bracket connection are adopted for stiffeners of tank boundary that bears big lateral load, while snip connection for wall of accommodation, etc.
Lug
Bracket (lap)
Clip
Bracket (butt)
Snip
-31/88-
-32/88-
Continuous Welding
High stress zone
Cut-Water Weld
Water or oil penetrates from an accidental defect and travels through the gap to other compartments
If those holes are not provided, air/water cannot go out during charging/discharging.
-33/88-
Check point: Welding between steel plate and cast/ forged steel Slot welding Tightness test Centering
Special Block
Hatch Cover
Check point: Dimensions L & B 5mm, Height 3mm (standard) Distortion 1 2 5mm (standard) Gasket and equipment Tightness (if applicable) Note: The standard is for pontoon hatch covers for container carrier
-34/88-
Shipyard
Application/ Notification
Subcontractor
-/ Report
NK Office A
NK Office B
Upon delivery of the block, the surveyor in office A is to ask the shipyard for report on any damage during transportation and inspect it, if any
Positioning of Block
Reference marking
-35/88-
A crack generated at poor penetration of one-side welding of hatch side box girder, and propagated into the Second Deck
6. Rudder
Confirmation of material and welding procedure Internal/ External inspection Fitting of sleeve, pintle, bush, etc. Coupling (rudder plate and rudder stock) Alignment (centering of rudder and stern frame) Installation of rudder Measurement of clearance Swing test
-36/88-
Installation of Rudder
Coupling of rudder plate and rudder stock Fitting condition of coupling bolts Locking of nut Portable box Jumping stopper Measurement of clearance Lubrication of rudder carrier bearing Swing test (only for confirmation that the rudder does not come into contact with any part of the hull)
Kind of Rudder
Rules Part C
Type A Type B
Type C
Type D
Type E
-37/88-
-38/88-
Shrinkage fitting
Confirm the contact by the color remained on the gudgeon Standard is 65%, and the contact must be uniform
-39/88-
Centering of Rudder
Centering shall be carried out after hydrostatic test of aft construction is finished (to avoid its effect).
-40/88-
Horizontal coupling
Cone coupling
Sleeve coupling
Locking of Nut
-41/88-
Stuffing Box
Jumping Stopper
Bush Retainer
-42/88-
Portable Box
Even if the portable box only is missing, the reduction of area affects the performance of rudder, and generates unbalanced force
Rudder Carrier
Inside
Rudder lifted
-43/88-
Measurement of Clearance
Note: Clearances at shoe piece, rudder horn, packing gland of stuffing box and jumping stopper are also to be measured as applicable
-44/88-
Re-conditioning of Misalignment
Increase fillet size by 10 %
-45/88-
-46/88-
Local Reinforcement
(1) Compensation for cuttingoff to pass other members
A crack generated at poor welding of half-round-bar of hatch coaming propagated into Upper Deck
-47/88-
Insert
Doubler
Spigot
Longitudinal member: Enlarge the hole to 75 mm (if applicable) and close it by spigot, or Enlarge the hole to 300 mm (if applicable) and close it by insert Other members: Enlarge the hole to 200 mm (if applicable) and close it by insert or doubler Remarks Welding sequence, grinding of bead, NDT
-48/88-
-49/88-
Deep Tank
Deep tank is a tank designed for carriage of water, fuel oil and other liquids, forming a part of the hull, regardless of shape and location.
LWL
H H2/3 2.45m
Hydrostatic test with a head of water to ; (a) load water line, (b) top of overflow pipe, (c) level of 2.45m above the tank top, or, (d) level of 2/3H above the tank top, where H is the distance between the tank top and upper end of D Whichever is the greatest
0.6m
Hydrostatic test with a head of water to; (a) level of 2.45m above the deck at side, or (b) level of 0.6m above the top of hatch, Whichever is the greater
-50/88-
LWL
LWL 2/3D
APT (a) below LWL: hydrostatic test with a head of water to LWL (b) above LWL: hose test with pressure of 0.2MPa
FPT (a) below LWL: hydrostatic test with a head of water to LWL or to the draught of 2/3D whichever is the greater (b) above LWL: hose test with pressure of 0.2MPa
(a) hydrostatic test with head of 1.5D or 2d whichever is the smaller, or (b) airtight test with pressure of 0.05MPa
Hose Test
Pressure (in nozzle): 0.2MPa Diameter of nozzle: 12mm or more Maximum distance: 1.5m
Hose test is applicable to shell plating, water-tight deck, water-tight bulkhead, shaft tunnel, hatchway, etc. For shell plating of fully welded construction being inspected from both sides visually, the hose test may be omitted at the discretion of the surveyor.
-51/88-
Notwithstanding the requirements for deep tanks, ballast hold of bulk carrier may be tested as follows: Hydrostatic test is to be carried out with a head of water to the level of the top of the hatch coaming Hose test for weathertight steel hatch cover is to be carried out
(1) Dry-up the surface before the test (2) Apply water jet from lower part to upper (3) The speed must be restrained
As the ratio of compression of air is very high, special attention should be paid during its release (leakage, over pressure, exhaust)
Structural test is indispensable when following data are insufficient; Reliable direct calculation or model test, Experience of sister ships
-52/88-
Test Plan
Start
Building berth
Hydrostatic Test with Partial Head Specified tanks Hydrostatic Test with Full Head
Afloat
End
-53/88-
Vacuum Test
Test is meaningless when the gauge doesnt go down due to leakage of the box
This test may be done during in-shop fabrication or block inspection, in accordance with the approved procedure If the gauge doesnt go up, the tunnel is stuffed by any reason. The test becomes meaningless in such case.
-54/88-
The Society has approved the consistence of results of manufacturers ultrasonic test for at least 3 ships at 1/10 points to be subjected to radiographic test For strength deck, side shell plating and bottom shell plating, the number of inspection replaced by ultrasonic test is to be not more than 1/2. Furthermore, the intersections of butt welds are to be excluded. For internal members, all spots may be replaced by ultrasonic test, except the intersections of weld lines of plate members. The surveyor is to attend during ultrasonic test, in principle
NDT
Members and Number
Number of inspection for each member subject to inspection Members subject to inspection Hull within 0.6L amidships Butt joints Strength deck Side shell plating Bottom shell plating Other member Plates Plates Girders Frames 6L/10 (*) 3L/40 (*) 2L/40 3L/40 Seam joints 2L/10 L/40 L/40 Hull without 0.6L amidships Butt or seam joints 2L/10
* One-third thereof is to be the intersections of weld lines In addition, parts of start/ interrupted/ end points of automatic welded joint, welded joints of hatch corner, connection of stern frame or rudder horn made of casting steel to rolled steels for hull, welded joints of insert plate for working holes and welded joints in the vicinity of parts where stress is concentrated shall be tested.
-55/88-
Blow hole
Pipe
Slag inclusion
Incomplete infusion
Incomplete penetration
Longitudinal crack
-56/88-
Incomplete penetration: empty part in a full penetrate welding (Note) A fillet welding is not always a full penetrate welding
NDT
Classification of Defects
Classification of defects Type 1 Type 2 Type 3 A B Kind of defects Round blow holes and similar defects Incomplete fusion, elongated slag inclusion, pipe and similar defects Incomplete penetration Cracks and similar defects
NDT
Allowable Limit (Radiography)
Allowable limit of defect of Type 1
Thickness of base metal t (mm) Test field of vision Size of defect Maximum size of defect (mm) Sum of size of defect (mm) t 10 5 5 10 < t 25 5 t/2 25 < t 50 t/5 t/2 50 < t 100 10 25 10mm x 10mm 10mm x 20mm
-57/88-
NDT
Expansion of Scope
The first test Accepted Rejected Plate: 2 parts within the weld lines where the faulty welds are found Girder or frame: 2 welding joints for each member, where the same welding procedure with the faulty welds is applied to the same block joints Automatic welding: Full length or all number of the welded joints Accepted Rejected Plate: Full length Girder or frame: All number Accepted Rejected Failed Passed
-58/88-
Flatness of keel:
Length:
50 mm (per 100 m)
Slit gauge
Point of FP
Erect a pole at middle of L along the side shell Shift the height of the lower face of keel to the pole using a water level Measure the height from the deck line to the lower face of keel using a mould Measure the breadth at upper deck or bottom
-59/88-
11. Paint
Approved corrosion prevention scheme Ballast tank (full coating) Cargo hold/ tank Exemption from coating for bulk carriers Restriction of kind of paint for COT of tankers Oil tank (no need of coating) Cathodic protection Paint for fire protection (see 14. below)
Specification of Coating
Surface preparation
Remove mill scale, rust, other foreign object on the surface of steel plate, as well as apply certain roughness for better adhesiveness with coating
Various paint
Below water line: Corrosion by sea water, stain by marine creature Above water line: Impact of waves, alternation of dry/wetness due to wave splash and sunshine Shop primer Paint for accommodation Anti corrosive paint Paint for E/R, work shop Anti fouling paint Paint for cargo hold Boot top paint Paint for fresh water tank Top side paint Paint for ballast tank Paint for exposed deck etc.
Shop Primer
Temporary protection of the surface between surface preparation and coating, as well as improvement of adhesiveness with coating Wash primer Short/Long period of exposure. Long one is usually applied. Good for 3 months. Zinc-epoxy primer Weak points are noxious smoke during gas cutting and low weldability due to zinc. Good for 6 months. (Non-zinc) epoxy primer Pigment other than zinc is used. Durability is between wash primer and zinc epoxy primer. Non-organic zinc shop primer Chemical adhesion to steel plate is excellent and good for 8 months. But same problem as zincky primers.
-60/88-
Timing of Coating
Hydrostatic/watertight tests are to be carried out after all work in connection with water-tightness are completed but before painting except shop primer. However, the tests may be carried out after the protective coating has been applied, provided that following conditions are satisfied prior to the application of the protective coating: All the welds are completed and carefully examined visually to the satisfaction of the surveyor An airtight test is carried out
Resin contained in the chip prevents corrosion Inside of deck does not touch the chip, therefore coating should not be omitted
-61/88-
(Note) Inside of oil tanks need not be coated as exception, but coating of ballast tanks adjacent to oil tank with heating facility is likely to deteriorate
Cathodic Protection
Anodic protection system Zinc, aluminum, magnesium, etc. are used as sacrificial anode that has lower electric potential than the metal to be protected. This system is adopted as a back-up for protective coating for shell plate and ballast tank. Duration is usually designed as 2~4 years. Impressed current cathodic protection system The electric potential of the target is maintained by direct current supplied by the system
Metal Copper Low carbon steel Zinc Electric potential in sea water -0.36V -0.61V -1.03V
12. Markings
Load lines Position of each mark and line Accuracy (0.5 mm) Permanent marking (welding of thin steel plate or punching Color (in contrast with the color of the shell) Draught scale Ships identification number (SOLAS XI/3.4) CC mark (TM69)
-62/88-
Draught Scale
Marked at fore, aft and midship on both port/ starboard side, every 20 cm. The height the letter is 10 cm. The lower edge of the letter coincides with the draught line represented by it. (standard 1 mm, limit 2 mm)
-63/88-
Characters CC should be permanently marked at the compartments included in the calculation of net tonnage. Location of the marking is in principle as follows:
Cargo ship: Tanker: PCC: LPG carrier: Outside of hatch coaming Outside of cargo hatch Outside of entrance to the hold Coaming of tank on upper deck
13. Piping
Pipes and valves Pressure test Air pipe Sounding pipe Scupper and sanitary pipe Bilge and ballast line
-64/88-
Material of Pipe
Steel pipe
Carbon steel pipe for pressure piping (STPG) is the most commonly used for ship
Other material
Synthetic resin, PVC, etc.
Pressure Test
Object of test Pipes in Group I and II Steam pipes, feed water pipes, compressed air pipes and fuel oil pipes with the design pressure exceeding 0.35MPa (e.g. F.O. pipes and heating pipes) Cargo oil pipes, crude oil washing pipes for oil tanker Check point Hydrostatic test with pressure of 1.5 time (1.25 time for cargo oil pipes) the design pressure. The test may be replaced by airtight test by prior consultation. Test pressure is to be checked by JIS/ISO pressure gauge properly calibrated Welding of pipe is to be executed by qualified welders. Joints of pipes in Group I & II with a diameter of 50A or more is to be of butt welding type Others Penetration of air pipes, sounding pipes, etc. is to be confirmed at the time of pressure test of tanks Not applicable to the pipes with opening end
-65/88-
Gooseneck type
Mushroom type
(Note) Head of air pipe located on the exposed deck of a ship, whose keel is laid on or after 1/1/2005, should be of self closing type
Direct clamping may hider sometimes sufficient passage of air during ballast operation To prevent negative pressure of tank, air passage hole of about 10 mm in diameter may be drilled in the cover plate
-66/88-
1. Tanks having top plates not less than 7m either in length or in width are to be provided with two or more pipes arranged with a suitable distance 2. However, tanks having inclined top plate may be provided with one air pipe located at the highest part of the top plate
(1) Air pipes for water tank should open above Bulkhead Deck (2) Air pipes for oil tank should open at weather part (with wire gauze)
Note: The height is specified by ILLC, not for positions I and II but for kind of deck
-67/88-
In principle, the pipes are to be led to positions above the bulkhead deck which at all times readily accessible, and are to be provided with effective closing appliance at their upper ends Requirements for air pipes concerning name plate, protection and insulation are applicable to sounding pipes Self-closing device is required for sounding pipes which open in E/R
Head of short sounding pipe in E/R (With self-closing cock for confirmation of absence of oil before opening the cap)
-68/88-
Square gunwale
Round gunwale
The scupper piping within superstructure is not to be connected to the scupper piping on the weather deck In general, different systems of overboard discharge are not to be connected each other, unless specially approved by the society. In general, scupper piping should not pass through fresh water or potable water tank
-69/88-
* Not applicable to scupper pipes from spaces below the freeboard deck
(3)
(4)
(7)
(8)
-70/88-
If the pipes pass in cargo holds, they must be protected against cargo damage
-71/88-
(Bend type)
In ships having only one hold exceeding 33 m in length, bilge suctions are to be provided in suitable positions in the after half-length and in the forward half-length of the hold Slip-on joints are not to be used in pipe lines in cargo holds deep tanks, and other spaces which are not easily accessible, unless approved by the society.
Bilge Well
In either case, a should be less than d0/2, and b more than 460 mm Capacity of the well should be 0.17 m3 or more (reasonable capacity, in case of hat)
The same is applicable for bilge line in side tanks and bilge hopper tanks
-72/88-
This slide shows the arrangement for cargo mode. For ballast mode, a blank flange should be fitted to the hold bilge line
Fire protection materials Inspection at intermediate stage Inspection of fire protection, detection and extinction and means of escape
-73/88-
-74/88-
Class of Division
Class Construction Formed by bulkheads and decks Constructed of steel or equivalent material Suitably stiffened Insulated with approved non-combustible material Formed by bulkheads, decks, ceiling or linings Constructed of approved non-combustible materials and all materials entering into the construction and erection of B class divisions shall be non-combustible Constructed of approved non-combustible materials Rise of temperature of unexposed side Average: 140 Any point: 180 Time: 0, 15, 30, 60 minutes Average: 140 Any point: 225 Time: 0, 15 minutes Passage of smoke and flame Prevent the passage of smoke and flame for 1 hour
Non-combustible material is a material which neither burns nor gives off flammable vapours in sufficient quantity for self-ignition when heated to approximately 750
* Where an asterisk appears in the table, the division is required to be of steel or other equivalent material but is not required to be of A class standard
(1) Control stations (2) Corridor (3) Accommodation spaces (4) Stairways (5) Service spaces (low risk) (6) Machinery spaces of category A (7) Other machinery spaces (8) Cargo spaces (9) Service spaces (high risk) (10) Open decks (11) Ro-ro cargo spaces
Space below
* Where an asterisk appears in the table, the division is required to be of steel or other equivalent material but is not required to be of A class standard
-75/88-
-76/88-
No direct access is permitted between machinery space of category A and the space for emergency fire pump When this is impracticable, the access may be by means of an airlock with the door of the machinery space being of A60 class standard
Materials readily rendered ineffective by heat, such as PVC, FRP, aluminium alloys, lead, copper and copper alloys, should not be used for overboard scuppers and sanitary discharges at following parts: (1) The parts below the freeboard deck (2) The parts in the space having the open end (3) The parts in the spaces directly above the freeboard deck
If the pipe is made of material having low-heat conductivity character and a diameter of less than 150mm, the insulation may be terminated at the end of penetration piece or sleeve
-77/88-
Class B division
Working Drawing
Type approval of Fire Protection Material
The on-site survey is to confirm that the execution of works is in accordance with the approved drawing
-78/88-
A-60 Class
A-0 Class
Refer to a separate topic Load Lines and Stability for following topics: 15. Closing appliances 16. Protection of crew
-79/88-
Rules Part U assume that rolling angle 1 is proportionate to the root of s, which is functional to T (rolling period)
s T
Rolling angle Stability requirements in wind and waves
-80/88-
When the society gives a special approval, oscillation test may be dispensed with and rolling period may be determined by an approximate calculation
T= L 2B B 0.373 + 0.023 0.043 wl dm 100 G0M
Inclining Test
Prior to the measurement, the surveyor is to confirm that the ships condition, test circumstances and test devices conform to the requirements in Annex B2.3.2-2 Guidance for Inclining Test of the guidance During the measurement, the surveyor is to confirm that sufficient data is gathered to determine the particulars of stability information of the ship If the ship has not completed construction work, the weights and positions of items which are to be added, removed or relocated should be recorded by the shipyard and confirmed by the surveyor (within 2% of final lightweight) When the test report incorporating the data is submitted, the surveyor is to ensure that the data given in the report is consistent with that gathered during the test Note: 1. Small heel angle may result in deviation over tolerance limit (expected heel 1 to 4) 2. Mooring lines are to be free of transverse tension
-81/88-
Hydrostatic Curves
Measured draught W KM
Calculation of KG
The length of the pendulum should be so arranged to obtain a swing of about 100 mm, in order to improve the accuracy (This requires the length of 5.7 m to detect an angle of 1. It may be almost impracticable for big ships.)
-82/88-
Terminology
Main steering position
Wheel house
Bridge wings
Bridge
10
-83/88-
Blind Sectors
3 2
22.5
45
At conning position
45 60
At each bridge wing (The ships side is to be visible from the bridge wing.)
60
Horizontal forward must be seen even the ship makes pitching. The height of eye may be reduced up to 1600mm when approved by the administration
-84/88-
Progressive speed trial Continuous running test Crash astern & ahead Boiler accumulation test test (engine side) Zigzag test Main steering gear test Ship inertia test (different Turning test from stopping test)
Crash astern & ahead test (bridge side) Aux. steering gear test Windlass performance test
Speed Test
To confirm speed of ship defined in 2.1.8 of Part A of the Rules where test is carried out in full load condition speed at MCO (maximum continuous output) of the main engine where test is carried out in other condition speed at MCR (maximum continuous revolution, corresponding to MCO) of the main engine In addition, speed at 25%, 50%, 75%, normal continuous cruise power run (85%) and 100% of the engine is also to be confirmed The speed against ground is measured by running between two mileposts erected ashore, or by GPS (accuracy is 10m) or DGPS (accuracy is 5m) Measurement is taken on going and returning, in order to cancel the effect of current
-85/88-
Astern Test
An order for full astern* is issued while the ship is running ahead at the maximum speed. The test is continued until the speed against the water reaches 0** (Rudder is to be kept at the mid position during the test) Speed, heading angle and trace of running are to be measured at a constant interval (it is to be confirmed that machinery installations have normal functions while the ship is running astern) Track reach, Stopping distance and lateral deviation are to be measured
Note: * The rate of main engine is to be kept more than 70% of MCR ** Continuous running of engine in astern is required for more than 30 minutes for machinery part
Steering Test
Main steering gear: While ship is running ahead at maximum speed, put the rudder over from 35 on one side to 35 on the other side put the rudder from 35 on either side to 30 on the other side in not more than 28 seconds Aux. steering gear: While ship is running ahead at max (half of maximum speed, 7kt) put the rudder over from 15 on one side to 15 on the other side in not more than 60 seconds Hydraulic Change-over test cylinder During those, the power units, hydraulic fluid recharging system, emergency power supply, operation of controls, means of communication between bridge and engine room/ steering gear compartment, indicators for the alarm, rudder angle indicator, etc. are to be also tested.
Pump
Turning Test
The ship is steered to 35 while running ahead at the maximum speed, and the rudder angle is to be kept until the ship turns to 360 (turn to right and left) Ships speed and/or turning rate are measured at the heading angle reached at 0, 5, 15, 30, 60, 90, 120, 150, 180, 210, 240, 270, 300, 330, 360 and the elapsed time reached to each heading angle is also to be measured
-86/88-
steered to to p (s) side when the ships heading reaches to , the ship is steered to to s (p) side when the ships heading reaches to , the ship is steered again to to the p (s) side The test is continued until the ships heading reaches to the original course shall be taken as 10 and 20
-87/88-
Operation manuals for the loading computer Plans for means of access Operation manuals for stability computer Operating and maintenance instructions for ship machinery and equipment Manuals for water level detection and alarm systems Maintenance records of batteries Instruction manuals for the cargo tank venting systems Fire control plans, fire safety operational booklets, training manuals and maintenance plans Operation manuals for the helicopter facilities Instruction manuals for the inert gas systems
-88/88-