P133I Concrete
P133I Concrete
P133I Concrete
SAUDI ARAMCO
Inspection and Testing for Concrete Works
(QA/P133I.Doc)
0
Rev
QC Manager
Prepared By
QC Manager
Controlled By
20.04.2014
Date
Project Manager
Approved By
Table of Contents
1.
PROCEDURE NO.
2.
3.
APPLICABILITY
4.
RESPONSIBILITY
5.
GENERAL
6.
DEFINITIONS
7.
PROCEDURE
7.1.
Receiving Inspection
7.2.
7.3.
8.
RECORDS
9.
REFERENCES
10.
ATTACHMENTS
1.
PROCEDURE NO.
P133I
2.
3.
APPLICABILITY
All Concrete works.
4.
RESPONSIBILITY
5.
Project Manager
Discipline Engineer
Discipline Foreman
QA Manager
QC Personnel
Material Controller
GENERAL
The responsibility for the Inspection and Testing of the Concrete Works rests primarily
with the QC Inspector, the Discipline Engineer and the Discipline Foreman with audit
by the Senior QA/QC Personnel .
The Discipline Engineer and the Discipline Foreman shall ensure the required work
permits are available and in place on a daily basis. Similarly they shall ensure that
utilized drawings are latest revision
The Project QA & QC Managers shall verify compliance to this procedure by Audit,
and shall perform reviews on all Quality related contractual documentation
The QC Inspector shall be responsible for witnessing tests and inspections and
ensure appropriate documentation in accordance with relevant SATIP.
All forms and records shall be filled out in accordance with the relevant SATIP. Client
SATIP and records are referenced however should the need arise additional forms
shall be developed for specific activities and added as the project progresses
Concrete works shall comply fully with the applicable laws and Client requirements
and specifications.
3
6.
DEFINITIONS
SATIP:
SAIC:
SATR:
7.
PROCEDURE
7.1.
Receiving Inspection
The cement aggregates and water used shall be in accordance with SAES-Q001. The QC Inspector and Material Supervisor shall control, through the proper
SATIP and procedure that cement, raw materials and concrete reinforcement,
are in compliance.
The Quality Department shall submit to Client Representative, full details of all
materials to be used for the concrete works including, if required, the names of
suppliers or manufacturers and sources of supply, for his review and approval
In accordance with SATIP-Q-001-01.
The Quality Department shall ensure that materials or sources of materials are
not changed. Materials where required, shall be sampled and tested in an
approved laboratory. Results of tests shall be submitted to Client
Representative.
7.2.
The steel is clear of the forms and soil and held firmly in place
by the use of wires, chairs, or spacers.
Mud, oil, concrete and loose scale has been removed.
The steel has been installed in accordance with the foundation
drawings and bending schedule as to size, location and
spacing. The splicing and radius of bends conforms to the
project specifications.
The sleeves for anchor bolts must be checked for correct size
and material, and must be centered on the bolts.
d) Approval to Pour
Concrete foundations shall not be poured until the QC Inspector or
Client Inspector has completed pre-pour inspection.
Relevant SAIC/SATR shall be used to indicate acceptance to pour.
7.2.3. Concrete Placement (SATIP-Q-001-02)
Previous to, or during the placing of the concrete, the Discipline
Engineer shall check for the following:
a) Concrete surfaces to receive new concrete should have the
loosened particles of aggregate and dirt or mud removed.
b) The ground or existing concrete should be moistened with water.
c) The minimum mixing time should be sufficient to form the uniform
mass and not exceed the time limit for remaining in the mixer.
d)
Specimens for each set shall be obtained at the same time and from the
same batch of concrete. A standard slump test shall be made each time
compression test cylinders are taken.
Test cylinders shall be dated and numbered consecutively. Each
cylinder of each set shall also be given an identifying letter (A, B etc.)
At least four cylinders shall be made at one time and tested as follows:
1 Cylinder at 3 Days.
1 Cylinder at 7 Days.
2 Cylinders at 28 Days.
6
7.3.
The Discipline Foreman shall ensure that grouting is mixed and applied
in accordance with SAES-Q-010 and Manufacturers recommendations
and instructions.
Final Inspection and Testing (SATIP-Q-001-02)
The Saudi Aramco Approved Third Party Technician shall prepare, mark, store
and cure test cylinders as per the Client Requirements and specifications.
The results of the tests shall be submitted to client Representative in the period
required in the specifications.
Any defective concrete work shall, at the discretion of the Client
Representative, be demolished completely and rebuilt or cut and made good.
Such rectification shall be re-tested / Inspected in accordance with original
requirements
The Saudi Aramco Approved Third Party Technician shall use the Concrete
Cylinder Record Summary to keep records of the results of testing.
The documents relevant to inspection and testing shall be kept in the QA/QC
Office on Site.
8.
RECORDS
All Forms and records relevant to this procedure shall be kept in the site office by the
QA/QC Supervisor and following the finish of the project repatriated to the area head
office to be archived and kept for a period of Three years.
9.
REFERENCES
SAES-Q-001.
SAES-Q-010.
SAES-M-100.
SAES-H-101.
09-SAMSS-097.
SATIP-A-114-01
8
SATIP-S-070-01
SATIP-Q-001-02
SATIP-Q-010-01
10.
ATTACHMENTS
None