P143 Painting
P143 Painting
P143 Painting
SAUDI ARAMCO
INSPECTION AND TESTING FOR PAINTING WORKS
(QA/P143.DOC)
0
Rev
QC Manager
Prepared By
QC Manager
Controlled By
20.04.2014
Date
Project Manager
Approved By
Table of Contents
1.
PROCEDURE NO.
2.
3.
APPLICABILITY
4.
RESPONSIBILITY
5.
GENERAL
6.
DEFINITIONS
7.
PROCEDURE
7.1.
Material
7.2.
Surface Preparation
Primer Coat
Finish Coats
8.
RECORDS
9.
REFERENCES
10.
ATTACHMENTS
1.
PROCEDURE NO.
P143
2.
3.
APPLICABILITY
All Piping, Structural Steel and Concrete, Painting Works.
4.
RESPONSIBILITY
5.
Project Manager
Discipline Engineer
Discipline Foreman
QA Manager
QC Personnel
Material Controller
GENERAL
The responsibility for the Process Control of the Painting Works rests primarily with
the QC Inspectors, the Discipline Engineer and the Discipline Foreman with and
audit by the QA & QC Managers.
The discipline Engineer and the Discipline Foreman shall ensure the required work
permits are available and in place on a daily basis. Similarly they shall ensure that
utilized drawings are latest revision
Surface preparation shall conform to the project specifications.
Client specifications and drawings, manufacturer instructions / recommendations
shall supersede the techniques detailed in this procedure when they differ.
The following procedure is a basic outline of requirements and in all cases
the relevant SATIP (if available) shall be reviewed by QC Manager or QC
Supervisor to ensure Inspectors are fully aware of tests and documentation
requirements prior to start of work.
3
6.
DEFINITIONS
SATIP:
SAIC:
SATR:
7.
PROCEDURE
7.1.
Material
Material shall be in accordance with Client requirements and specifications,
material receiving inspection shall be in accordance with relevant SATIP and
SAIC.
7.2.
7.3.
When grating requires paint, the gratings and their supports should be
painted before installation.
Pipe flanges and other exposed surfaces on insulated pipe lines should
be cleaned and painted, in accordance with the specifications, before
insulating the line.
Electrical and instrument supports should be painted before the electrical
devices or instruments are mounted.
All other items which will be inaccessible after erection should be painted
prior to erection
The following items should be masked or otherwise protected when painting:
Equipment nameplates
Valve stems.
7.3.1.
7.3.2.
Surface Preparation
7.3.1.1.
7.3.1.2.
7.3.1.3.
Primer Coat
7.3.2.1.
7.3.2.2.
7.3.2.3.
7.3.2.4.
7.3.3.
Finish Coats
7.3.3.1.
8.
RECORDS
All records relevant to above procedure shall be kept by the QC Manager in the site
office for the duration of the project and transferred to the Area Head Office, at the
achievement of the Project, to be filed, archived and kept for a period of Three
years
9.
REFERENCES
Relevant APCS.
SAES-H-100.
SAES-H-101.
SAES-H-101V.
SAEP 316.
10.
ATTACHMENTS
None