Bridge Designs
Bridge Designs
Bridge Designs
HISTORICAL DEVELOPMENT
Pre British Colonial Period Prior to 1796 2 British Colonial Period 1796 to 1948 3 Post Colonial Period 1948 to date
1
Period
1796-1815
1815-1842
1842-1845 1846-1851 1851-1862 1863-1876 1877-1938 1938-1968 1968-1971 1971-1978 1978-1986
Civil Engineer and Surveyor Generals Department sometimes also referred to as colonial Engineer and land Surveyors Department
Civil Engineer and Surveyor generals Department Commissioner of Roads Civil engineers Department. Commissioner of Road Department Civil engineer and Commissioner of Roads Department Public works Department Public Works Department Public Works Department Highways Department Territorial Civil Engineering Organization and Highways Department Highways Department
Royal Engineers. Ceylon pioneer lascars later called the Military Corps of pioneers
Pioneer Corps Pioneer Corps Pioneer Corps and Government Factory (from 1858) Pioneer Corps. Government Factory Government Factory. (Pioneer Corps ceases to exit in 1877) Formation of a bridges Organization under C.E. (Bridges) in 1938 . Government Factory C.E. Bridges. Government Factory. State Development and Construction Corporation Newly formed Bridges Organization under a Deputy Director Bridges. S.D. & C.C., S.E.C. and some other private organizations RC&DC(Presently abolished),Maga Neguma SD&CC,SEC,CECB and some other private organizations
1986 to date
BACKGROUND
From the inception of the RDA in 1986, for over a period of about 12 years, the Engineering Services Division, has been responsible for the overall management of the execution of specialized functions namely:
Traffic Engineering and Road Planning Highway Designs Bridge Designs Bridge Inspection & Assessment Land Acquisition and Shifting of Utility Services for project implementation
For the execution of each of the above specialized functions, there were separate offices consisting of Engineers with supportive staff for both technical & administrative functions and each of them was managed by a Deputy Director. However at present, of the five offices, only the Bridge Designs office comes under the purview of the Director, Engineering Services.
Director (E/S)
DD (B/D)
SDE
SDE
SDE
SDE
DE
DE
DE
DE DOA
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
DE (T)
AA Dmans (10)
Supporting Staff
Preliminary investigations of bridges to identify the level of rehabilitation. Preparation of preliminary designs and cost estimates for bridge projects for project formulation and feasibility analysis and project appraisals. Developing optimal basic designs for bridge projects and deciding on the design standards to be adopted in the design. Finalization of detailed designs, drawings, BOQQ and estimates for bridge projects. Preparation and finalization of documents for land acquisition acquisition plans, tenement particulars etc.
Diagnosing problems in implementation of bridge projects and amending designs as required to suit the site conditions during construction. Providing advisory services and guidance in bridge designs to Provincial Directors and Chief Engineers. Providing advisory and support services to relevant Implementing Divisions in implementation of bridge projects.
Developing and updating of standard designs for bridge beams and other bridge components to satisfy requirements of current standards and code of practice and finalization of type plans for same. Implementation of design policy review of design standards and practices and recommending amendments/changes for updating them in keeping with recent developments and current trends and their adoption. Preparation of rates for items of works relevant for construction of bridges and updating of the same periodically.
Providing training for RDA Engineers in Bridge Designs to enable them to partially fulfill the requirements to obtain professional qualifications. Preparation of project proposals for the consideration of External Resources Department to seek foreign funds for implementation
at progress review meetings and providing advisory and support services where required for projects implemented by the Project Management Units under foreign funds. Participation at discussions with Foreign Mission /Expatriate Consultants in connection with bridge rehabilitation projects to be implemented under foreign funded programs.
Providing
counter part services to Foreign Missions, Expatriate Consultants etc. such as providing data/information, appraising of local conditions, reviewing of basic designs and detail engineering work, making observations and suggestions.
Monitoring, review and acceptance of detail engineering work executed by Consultants for bridge projects. Checking of alternative designs submitted by Contractors in the process of executing the bridge projects awarded to them to decide on adaptability of same.
oProviding consultancy services in bridge designs to outside Government Departments and Private Agencies. oExecution of structural assessments of bridges and providing designs & specifying repairs/strengthening needed for bridges for transport of abnormally or extra heavy loads such as Electric Generators, Gas Turbines and grant approval for the movement of those on specific trailer arrangements.
By
D.K. Rohitha Swarna Director (Engineering Services) Road Development Authority 08.12.2011
14
Historical Development of Bridges Important Old Bridges in Sri Lanka Investigation of Bridges Classification of Bridges Various types of Steel Bridges Bridge Loadings Bridge foundations Super Structure Various deck types
15
5.
Wrought Iron bars & cables Girders which can take tension
Later in 1820 the worlds first suspension bridge built with iron bars and cables known as Menai bridge with a span of 580ft which consist of timber decking and this has stood for 115 years. In 1832 1st Wrought iron girder bridge was built. Since the wrought iron was maleable ,ductile and much stronger in tension it could be riveted.
16
6. Open web girders, trusses with the advent of steel 7. Rfd concrete/Pre-stressed Concrete
First patent for reinforced concrete was published by England in 1808 and Portland cement concrete was invented in 1824. The first portland cement concrete bridge to be built was the Grand Maitre Aqueduct across river Vane in France built in 1874. Fressinet developed prestressing and the application was adopted in late 1930.
8.
Suspension Bridges, Cable Stayed with the advent of high strength steel
17
18
Old Victoria Bridge Over Kelani river in 1895 ( Replaced by Sri Lanka- Japan friendship bridge in 1992)
19
20
21
Old Steel Truss Bridge at Gampola Over Mahaweli River in 1926 (Replaced by 100 m long Post Tension Bridge in 2004)
22
71.6 m
23
Artistic Impression
25
Present Steel Arch Bridge at Peradeniya constructed in 1905 over Mahaweli River
68.4m
26
Investigation of Bridges
Topography Catchment area Hydrology Geo-Technical data Navigation Construction Resources Nearby Bridges Traffic Data
27
Abutment Pier
Foundation
28
Super structure
Foundation Abutment
Wing wall
29
Primary elements
structure form, spans, piers and abutments and their founding requirements and the physical context.
2.
Secondary elements
texture of finish, colour
It is very important to consider what visual impact the finished structure will have on the environment, on the people who use them & those who will be seeing them
30
Type of Material
Steel Concrete Timber
Type of construction
Arch Slab Beam
& Slab
Open
Structural Behavior
Simply Supported Continuous
Box
Girder Bridges
Purpose of construction
Permanent
Bridges High level Bridge (All weather Bridge) Submersible Bridge Temporary Bridges
Pontoon Bailey Timber
31
Contribution factors to the flood flow Rainfall intensity duration Terrain Characteristics Catchment area, shape, slope ,Nature of soil, Vegetation types Stream Characteristics Slope of the Stream nature of bed Since the occurrence of flood depends on combination of above factors its prediction becomes far from exact science.
32
(b)
More rational & a latest method which needs actual observations of the discharge at the site for same period and also the rainfall data spread over some years.
Slope and alignment of the natural stream Bed material of stream and flood plains Changes or potential changes in the prevailing conditions in the stream or the catchment, whether man-made or natural. Depth, velocity and alignment of flow through the constriction. Alignment and layout of the bridge and training works. Accumulation of debris. Size, shape, orientation and arrangement of piers, footings and piles. Amount of bed material in transport.
34
AFFLUX
This is another term to be familiar with design of bridges and it can be defined as a rise or heading up of water level on the upstream side of the bridge. It is caused when the effective linear waterway at the obstruction is less than the natural width of the stream immediately in the upstream side of the bridge. As such the afflux that can be produced by piers and projecting abutments has to be calculated in order to determine the finished road level of the bridge. The afflux should be kept minimum and limited as far as possible to 150mm in order to avoid upstream flooding and inundation.
In order to arrive the design flood discharge, it is recommended to use at least two of the above methods and arrive at a figure which is maximum of the two or 1.5 times the minimum whichever is less.
35
36
Bridges should be able to resist the effects of the loads & actions as listed below
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) Dead loads Live Loads Braking / Traction Centrifugal Force Skidding force Earth and Surcharge Pressure Floating Debris & Log Impact Wind Temperature Shrinkage & Creep Buoyancy Effect Seismic forces
37
380
38
Type HB Loading
HB is an abnormal loading which consists of 4 axles and each axle weighs 25 Tons 45 Tons
1.0 m 1.0 m 1.0 m 6.0 m 1.8m 1.8m 3.5 m wide
Direction of Travel
Contact Area:- Wheel load is assumed to be uniformly distributed over a circular contact area to give an effective pressure of 1.1 N/mm2
39
Classification of Soil
Cohesive soil Presence of clay minerals, eg; clays, plastic silt
Cohesionless soil composed of bulky grains, eg; non-plastic silts and gravel
40
When the soil is subjected to direct compression, shear stresses develop. Shear stresses will develop even in tension, but not relevant since soil fails in tension.
Failure in soil occurs by relative movement of particles and not by breaking of the particles. Shear strength is the principal engineering property which controls the stability of a soil mass under loads.
41
2. Stability of slopes
42
43
In order to design the retaining structure determination of following are needed. 1. The magnitude depends on - mode of movement of the wall - flexibility of the wall - properties of the soil - drainage conditions 2. The line of action of the earth pressure
Hence, this is a soil structure interaction problem & anyhow since it is Complicated to analyse it is assumed that retaining wall is rigid & soil structure Interaction is neglected.
44
Theories adopted
2.Active
3.Passive
compress horizontally
46
Basement slab
At rest pressure
No movement
Active pressure
Earth pressure
B
A
At rest Active Passive
Movement
No movement
48
Dead + Live
Traction / Breaking
V H
M e
H
49
H.F.L.
Traction / Braking
51
v2 P KW 2g
Lo ad
30
Cut Water
Calculate FOS for Stability and Stresses at all critical sections of the pier for all critical Load cases
Calculations are same done in Abutment Design
53
54
Wing wall design is almost same as Abutment Load for Wing wall Design
Restoring Loads All Vertical Loads
Dead Loads of the Wing wall Superimposed Dead Loads Weight of the Soil Backfill Surcharge Load
56
Allowable bearing Pressure has to be evaluated & settlement can be estimated using soil properties (C ,, values) In order to do the structural design of the foundation B.M. & S.F. need to be estimated. Two methods are used; Rigid Method of Analysis Flexible method of Analysis Soil is assumed to be of infinite no of springs Elastic const. of spring (coeff. Of sub grade rea) Settlement of the soil &
(B)
Assume the fdn to be rigid Find Soil pressure dis & it is a straight line Calculate B.M. & S.F. Soil structure interaction is not its influence Accounted.
Foundation is accounted.
57
Based on how the load is transferred, pile foundations are divided as; i. Bearing pile ii. Friction pile iii. Friction cum bearing pile End bearing piles are generally taken up to hard strata such as bed rock. Friction piles are suitable for cohesive soil not subjected to heavy scour. Friction cum bearing piles are used in mixed type of soils.
58
Well Foundation
TYPICAL SECTION OF WELL FOUNDATION
PIER CAP PIER
CYLINDER CAPPING BEAM TOP PLUG SAND FILL BOTTOM PLUG WELL STEINING WELL CURB CUTTING EDGE ROCK
Available in rectangular or circular sections. Rectangular sections are suitable for shallow depths and circular sections are suitable for larger depths. Can resist heavy vehicle loads and lateral loads. Only disadvantage is very time consuming process. Sufficient grip length is required after allowing for scour.
In the design, Three aspects to cover Depth of well Size(diameter) of the well Thickness of the well steining
59
Depth of scour There should be adequate grip length (to resist horizontal forces)
Size of the well is mainly governed by the allowable bearing pressure of the soil. Size of the steining depends on (i) Adequate working space (Minm 1.8 m is preferred) (ii) Steining will get subject to various stresses during sinking. (iii) Thickness of well steining should be such that it should be able to overcome the skin friction during sinking.
SOIL TYPE
SILT (Sandy/elayer) Clay (Soft) Clay (Stiff) Sand (Compact Coarse) (loose gravel) Gravel Sand mixture Saft Rock (Broken bedrock) Sedimentary Rock (Sandstone, limestone Siltstone) Medium AVERAGE BEARING TYPICALhard rock Hard Rock VARIOUS SOIL TYPES (Dolomite, gneiss, granite)
400
1000
2500
4000 CAPACITIES OF 8000
61
The superstructure design depend on the different types of bridges that is based on type of construction, floor arrangement (in case of steel bridges) and structural behavior
The design of a superstructure of a bridge is similar to that of any structure except that a bridge has to carry a moving load in combination with other loads like wind, temperature, seismic, longitudinal and lateral forces
62
63
64
100 m long Langer Truss (Modified Warren Truss) at Muwagama over Kalu Ganga
65
9800 Overall width 1200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x75 thick R.C.cover slabs with R/F T10 @ 100 crs. both ways. Pre cast kerb. Drg:No:T/B/106 -Rev. 1. Rain water catch pit. - Refer detail. 450 50mm 75 Chamfer 350 400 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 50 mm. 50 Thick wearing surface.
Slope 1 in 60
2 2 2 4 5
c L
Minimum 110
Wearing surface not shown for clarity. Infiller concrete in Grade : 40 (20) 32 R 6 . 2 . 300. 24 T 10 . 3 . 300.
24T10.4.300. 3 T10.6.200.
6 5 6
24 T 10 . 5 . 300. T10 Shear connectors at 600 crs. To be filled with cement mortar after fixing bolts.
10mm Fall
Service duct
570
100
Drip
50 mm dia. PVC drain pipe at 2300 crs. 610 100 50 610 110
15 nos. 7010 mm. (23'-0") long PSC beams Drg: No: T / B / 030. 6841
6 mm. dia. wire links to be provided to tie rods and top reinforcement along the groove. 20 dia. stainless steel dowels at fixed ends only.
610 110 50
610 100
GENERAL DETAILS
R. C. DETAILS
66
9800 Overall width. 1200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs. 425 75 50
Service duct.
7400 Carriageway.
1200 Foot walk. Foot walk in Grade : 25 (20) R.C. Ties at foot walk -Refer detail. 64 T10 . 3 . 150. 32 T10 . 2 33 T10 . 6 . 300. Lower kerb. Concrete: Grade 20(14) 33 T10 . 5 .300.
c L
10
350 500
425 10
18 Nos.9 500 mm long Pre cast kerb. Drg:No:T/B/106 -Rev. 1. (finished length) PSC. beams as per Drg:No: T/B/507 Rain water catch pit. -Refer detail. 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 75 mm. 50 Thick wearing surface. Slope 1:60. Minimum 135mm screed concrete
Wearing surface not shown for clarity. Infiller concrete in Grade : 40 (20)
230
745
340
Service duct.
9.5m. long.
200
5mm.fall.
300
380
100
50 50 100 80 75 500 25
100 110
500
GENERAL DETAILS.
REINFORCEMENT DETAILS.
67
9800 Overall width. 1200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs. 425 75 50 10 350 500 425 10 Pre cast kerb. Drg:No:T/B/106 -Rev. 1. Rain water catch pit. -Refer detail. 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 75 mm. 50 Thick wearing surface. Slope 1:60. Minimum 135mm screed concrete 7400 Carriageway. 1200 Foot walk. Foot walk in Grade : 25 (20) DETAILS REPEATS ABOUT CENTRE LINE. Wearing surface not shown for clarity. Infiller concrete in
Grade : 40 (20)
c L
R.C. Ties at footwalk-Refer detail. 77 T10 . 3 . 150. 32 T10 . 2 38 T10 . 6 . 300. Lower kerb. Concrete: Grade 20(14) 38 T10 . 5 .300.
230
11.5m. long.
Service duct.
815
340
200
5mm.fall.
300
100 110 dia. PVC. pipe rain water outlets at 3250 crs.. 50 dia. PVC. drain pipes at 3250 crs..
450
100
26 R 20 .1. 450. Tie bars. 20 dia. stainless steel dowels at fixed ends only. 7170
15 T12 . 7 500
500
205
500
110
GENERAL DETAILS.
REINFORCEMENT DETAILS.
68
9800 Overall width. 1200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs. 425 75 50 10 350 500
10 mm. fall
7400 Carriageway.
1200 Foot walk. DETAILS REPEATS ABOUT CENTRE LINE. Wearing surface not shown for clarity. 90 T10 . 3 . 150. Infiller concrete in Grade : 40 (19) 32 T10 . 2 Foot walk in Grade : 25 (19) R.C. Ties at footwalk 46 T10 . 6 . 300. Lower kerb. Concrete: Grade 20(14) 46 T10 . 5 .300.
13.5m. long.
200 195 50 100 80 75 500 25
425 10
18 Nos.13500 mm long (finished length) PSC. beams Pre cast kerb. Drg:No:T/B/106 -Rev. 1. as per Drg:No: T/B/505 Rain water catch pit. -Refer detail. 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 75 mm. 50 Thick wearing surface. Slope !:60. Minimum 135mm screed concrete
c L
Service duct.
230
890
5 mm. fall.
325
450
Service duct.
100 50 dia. PVC. drain pipes at 3250 crs.. 205 500 110
275
150 dia. displacers of polythene -tubes filled with light materials such as saw dust paddy husk etc. 7170
500
GENERAL DETAILS.
1:30.
REINFORCEMENT DETAILS.
525
100
69
1 200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs.
9 800 7 400
14.5m long.
1200 300 450 450 100 200 120 50 225 100 80 500 25
Drg: No: T/B/503/A.
CAST LENGTH = 14.42m. FINISHED LENGTH = 14.5m.
c L
Wearing surface not shown. Infiller concrete in Grade : 40 (19) 97 T 10 . 3 . 150. 44 T 10 . 2. 55 R.C. Ties at footwalk 49 T 10 . 6 . 300.
450 75 10
300 10
17 nos. 14 500 long PSC. Pre cast kerb. Drg:No:T/B/106 -Rev. 1. beams Drg:No: T/B/503/A. Rain water catch pit. -Refer detail. 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 75 mm. 50 Thick wearing surface.
Slope 1 : 60.
535
965
Service Duct.
300
225 dia. displacers of polythene -tubes filled with light materials such as saw dust paddy husk etc. 6680
32 R 20 . 1 . 450.
STAGE: 1. EDGE BEAM INFILLER CONCRETING HAS TO BE DONE IN THREE 49 T 10 . 4 . 300. STAGES. REFER NOTES. 20 T12 . 8. 500
325
100
160 1:30.
500
400
GENERAL DETAILS.
NOTES:
CONCRETING SEQUENCE OF EDGE BEAM.
REINFORCEMENT DETAILS.
STAGE- 3: SEVEN DAYS AFTER STAGE TWO: BALANCE(FOOT WALK) TO BE DONE WITH GRADE 25 (20) CONCRETE.
STAGE -2: SEVEN DAYS AFTER STAGE ONE : 500mm THICK GRADE 40 (20) CONCRETE UP TO TOP OF SCREED LEVEL.
600
STAGE: 3. STAGE: 2.
70
1 200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs. Pre cast kerb. Drg:No:T/B/106 -Rev. 1. Rain water catch pit. -Refer detail. 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 75 mm. 50 Thick wearing surface.
9 800 7 400
15.5m. long.
1200 300 450 450 100 200 170 50
650
Foot walk in Grade : 25 (19) Wearing surface not shown. 104 T 10 . 3 . 150. Minimum 135mm screed concrete Infiller concrete in Grade : 40 (19) 55 55 44 T 10 . 2. 53 T 10 . 5 . 300. 53 T 10 . 6 . 300. Lower kerb. Concrete: Grade 20(14) 53 T10 . 7 .300.
225
100 80 500 25
c L
75 50
450 10
450 600
10mm. fall.
300 10
1015
585
service Duct.
Slope 1 : 60.
STAGE: 3. STAGE: 2.
Service Duct.
STAGE: 1. EDGE BEAM INFILLER CONCRETING HAS TO BE DONE IN THREE STAGES. REFER NOTES.
5mm. fall.
325
100 50 dia. PVC. drain pipes at 4000 crs. 160 400 500
300
225 dia. displacers of polythene -tubes filled with light materials such as saw dust paddy husk etc. 6680
GENERAL DETAILS.
REINFORCEMENT DETAILS.
71
1 : 30. 1 200 Foot walk. Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs. Pre cast kerb. Drg:No:T/B/106 -Rev. 1. Rain water catch pit. -Refer detail. 150x50 insitu lower kerb. Conc:Grade 20(14). Minimum 75 mm. 50 Thick wearing surface.
Slope 1 : 60.
700
17 nos. 14 500 long PSC. beams Drg:No: T/B/503/A. Wearing surface not shown. Minimum 135mm screed concrete Infiller concrete in Grade : 40 (19)
Foot walk in Grade : 25 (19) 111 T 10 . 3 . 150. 44 T 10 . 2. 55 55 56 T 10 . 5 . 300. 56 T 10 . 7 . 300. 56 T 10 . 6 . 300. Lower kerb. Concrete: Grade 20(14)
225
100 80 500 25
c L
300
450
450 100
220
Drg: No: T/B/501/A.
9 800 7 400
16.5m. long.
1200 200 50
450 75 50
10
450 600
10mm. fall.
300 10
service Duct.
STAGE: 3. STAGE: 2.
Service Duct.
1065
635
STAGE: 1.
5mm. fall.
100 50 dia. PVC. drain pipes at 4000 crs.. 400 500 160
300
225 dia. displacers of polythene -tubes filled with light materials such as saw dust paddy husk etc. 6680 1 : 30.
36 R 20 . 1 . 450. 20 T12 . 8. 20 dia. stainless steel 160 dowels at fixed end only. 500 400 500
EDGE BEAM INFILLER CONCRETING HAS TO BE DONE IN THREE STAGES. 56 T 10 . 4 . 300. REFER NOTES.
325
GENERAL DETAILS.
NOTES: CONCRETING
SEQUENCE OF EDGE BEAM.
REINFORCEMENT DETAILS.
STAGE- 3: SEVEN DAYS AFTER STAGE TWO: BALANCE(FOOT WALK) TO BE DONE WITH GRADE 25 (20) CONCRETE.
STAGE -2: SEVEN DAYS AFTER STAGE ONE : 500mm THICK GRADE 40 (20) CONCRETE UP TO TOP OF SCREED LEVEL.
72
Type pre cast uprights and hand rails as per Drg:No:T/B/102 A&B. 500x450x100 thick pre cast R.C. slabs.
75 450
9 800 7 400
c L
1200
Rain water catch pit. - Refer detail. 150x50 Insitu lower kerb. 50 mm thick wearing surface. Conc.Grade: 20(14) Minimum 135 mm screed concrete. Minimum 75 mm.
111 T 10 . 3 . 150. 44 T 10 . 2.
635
75
1065
Service Duct.
300
200
450
825
100
345
50 6680 160 500 400 500 25 500
SECTION OF BEAM
SCALE:-1:5
100 160
500
GENERAL DETAILS.
1 :30.
REINFORCEMENT DETAILS.
73
25
225 dia. displacers of polythene -tubes filled with light materials such as saw dust paddy husk etc.
36 R 20 . 1 . 450.
56 T 10 . 4 . 300. 20 T12 . 8.
225
100 80 25
Type pre cast uprights & hand-rails. Drg: No: T/B/102 A&B. 500x450x75 thick pre cast RC. cover slab. 30mm Chamfer.
75
9800 Overall width of Deck. 1200 Foot walk. 7400 Carriage way 1200 Foot walk.
DETAILS REPEATS ABOUT CENTRE LINE. Wearing surface not shown for clarity. Concrete: Grade 40(20)
Clear cover 35 mm.
Rain water catch pit. - Refer detail. 150x50 Insitu lower kerb. Conc. Grade: 20(14)
200
Clear cover 50 mm
400 300
c L
50
510
50 dia. P.V.C. drain pipes at 3500 crs. 110 dia. PVC. pipe rainwater outlets at 3500 crs. 9 nos. 25000 long PSC.beams Drg:No: Top of Capping beam. Bearing plinth & pad to detail.
970 160 970
1120 440
570
280
50
1 3030 80
RC. deckslab.
10 315
80 120160120
30
910 970
30
970 30 30
970 30
970 9230 30
970 30
970 30
970
160
970
GENERAL DETAILS.
1 : 30
R C. DETAILS.
74
250
250
100
1040
550
1040
550
1040
550
1040
550
1040
550
1040 16940
550
1040
550
1040
550
1040
550
1040
550
1040
75
CARRIAGEWAY
620 520
150
225
725 65
455
55
95R10-14-300
2000
76
UP STREAM
1200
10400
DOWN STREAM
8000 1200
c L
450 460 290 50 Thick wearing surface 290 460 450
505
210
230
280
200 30 50
50
30
2500
c L
R. C. DETAILS OF DECK
575
77
c L
78
79
BACKGROUND
Initial Construction:
Has been carried out in 1965-1966 by PWD, using removed timber deck (Brotherhood truss) from Kalaoya Bridge Site at Anuradhapura Padeniya rd.(A028) supported at the other end.
Timber decked, old steel truss (Brotherhood truss) Supported on Abutment Founded on Bored piles Max. allowable load : 10 Ton Single load at the middle at a time
Bridge deck was repaired and opened back to the public in year1990
THE INCIDENT :
This was revealed by the experimental result been observed for the member no. 17 at the mid of the span
Present Condition
Construction of a new bridge of 3 spans, simply supported P S C Beam deck
Present Condition
Thank You