Industrial Losses
Industrial Losses
Industrial Losses
4. START-UP LOSS
Losses Description: Start - up: TIME Lost initially after switching on an equipment till it is ready for production. Example: Time required for the Sintering Furnace to reach the Set Temperature for Heat Treatment Process.
Losses Description: 8B PM Activity: TIME Lost due to PM activities done as per PM calendar
Example: Preventive Maintenance carried out in a Machine Losses Description: 8C Meetings: TIME Lost due to meetings held by stopping the machine
9. MANAGEMENT LOSS
Losses Description: 9A - Want of Tools: TIME Lost due to Non-availability of Tools. Example: Press Waiting for CV Inner Die from Tool Room.
Losses Description: 9B Awaiting Instruction: TIME Lost due to delay in giving Work order/Schedule/Instruction
Example: Wire Cut M/c waiting for CNC Programme / Work order Losses Description: 9C Want of RM: TIME Lost due to delay in giving RM to the machine
9. MANAGEMENT LOSS
Losses Description: 9D - Want of Men: TIME Lost due to Nonavailability of Men on a schedule machine Example: Operator Leave / Permission
Losses Description: 9E Want of Gas/Air/Oil: TIME Lost due to Non-availability of GAS (Air) supply to the machine
Example: Compressed Air not available for the press. Losses Description: 9F Want of Power: TIME Lost due to Non-availability of Electrical Power supply to the machine
Example: Electrical Power supply not available for the CNC M/c
9. MANAGEMENT LOSS
Losses Description: 9G - Awaiting Inspection: TIME Lost in waiting for first-off sample approving authority Example: Waiting for first product approval from Quality
Losses Description: 9H Want of Order: If machine cannot run due to Non-availability of orders
Example: No Market Order Losses Description: 9T Want of Containers :TIME Lost due to delay in giving tote box/trolley/half-drum/tray.
9. MANAGEMENT LOSS
Losses related to: Man