Aspects- technical , financial, commercial, economic, social, managerial, organizational. Components- physical (land, plant & equipments,
buildings etc.) and functional (design , engineering, procurement and construction)
Take care of increased requirements of the country population. Need for scientific management. Effectiveness of construction industry depends upon the individual staff, skill, style, The structure of organization, systems adopted, strategies followed and environment of the organization.
Face national, international compatibility & competition Function- planning , organizing ,directing and controlling
Pre- investment study Macro-economic and social analysis Sectional studies Need survey
Entrepreneurial private investment for profit Govt. planning for social and economic welfare, External pressures, Political commitments, critical economic and social bottlenecks Excess or idle resources and forward and backward linkage with existing or upcoming projects
Contract management
Notice inviting tenders Proposal form to be filled by the contractor GCC Special conditions Plans and drawings Specifications Detailed quantity and cost estimation. PQR Law of the land
ERECTION
Project tendering and ordering Project construction / installation. Project monitoring and control. Project evaluation. Project replan. Commissioning. Trail operation. P.G. Test. Closing of the contracts Settlement of arbitration and disputes
Project construction.
Accomplishment of defined objective Objective- time (schedule) & money (cost) Basic function- plan, organize, co-ordinate, leading, monitor and control activities. environment Plan manpower (skill & expertise), material, equipment, quality, time, cost, fund. Organize data base and project information system. Leading - effective & efficient management for technical ,financial and
schedule responsibility
Progress
Level of progress- monitoring Level-I progress chief executive level Level-II progress- O&M Head Level-III progress- DGM Level-IV progress Field engineer
Progress Report
Control diary- activity schedule, criticality, slippage Field report A- time aspect of activity Field report B- quantitative schedule Field report C- expenditure, actual / schedule Level-III report- work executing engineer report Level-II report senior executing engineer report Level-I report chief executing engineer report Manpower report- skill manpower requirement for the project Report of inter-related activities-
CONTROL DIARY
FOR SCHEDULE CONTROL OF ALL THE ACTIVITY
START
Schedule start date activity Latest start date
FINISH
Schedule activity finish date Schedule finish date
work detail
DURATION
START
Eve acti Sch Act Lik nt vity edu ual ely no le start star of star date t the t dat acti dat e vity e
Acti on by fiel d
10 11 12 13 14
Actual expenditure
10
Manpower report
Name of the project periodicity date of report
Reason for shortfall
Sl no Cate Recruitment gory of manp No. No. No. Impa ower req. sanct in ct on ion positi proj on.
training
No. to be traine d
TIME OVER-RUN
Losses Project escalation Liquidated damage Payment of extended escalation Output production delay Cost of project high Delayed return
LIQUIDATED DAMAGE
LD imposed when schedule not meet Delayed observed only between zero date and contractual trail run.
PRT
Project review team contracts, corporate engg., corporate monitoring group, quality, site concerned with the package. Monthly at cc & site
ZERO DATE
Agreement sighing date with contractor after award of the project
COMPLITION DATE
Contractual Trail operation date for LD purpose
WARANTY
12 month from date of contractual trail operation for manufacturing defect and bad workmanship.
Project evaluation
By monitoring and control system the progress of a project is being evaluated w. r .t. Time Cost Activity
Project re-plan
Based on evaluation the project is being re-planned the Schedule Activity Material procurement Contract amendment Engg. Regarding design.
Commissioning.
After erection the commissioning activity Pre trail run of each equipment. Monitoring of vibration. Temperature. Sustenance of the system
Trial operation.
After completion of the erection and commissioning trial run has to be made as per the contract provision. Hand over the project for further operation. Defect observed may be subsided. Guarantee / warrantee should be ensured.
P.G. Test.
P.G. test should be done as per the p.g. test procedure to ensure the garneted parameter. Witness by O&M representative. OS group should also evaluate the same. depending on class of erection
arbitration
Dispute settled through third intervention without court of law How to resolve disputes Mutual discussion Reconciliation. Civil court Arbitration Between two govt. body by a permanent arbitrator in the dept of public enterprise under MOI as per the arbitration law 1940
Coal handling system- mechanical electrical, track hoper crusher conveyor, idlers, TP ,trippers Ash handling system- bottom ash removal system, fly ash removal system, ash slurry disposal system, ash water facility, HP, LP, CMR Fuel oil handling system- pumps, steam heating, piping Water treatment plant- calflucarator, sludge disposal, DM plant, cation unit, anion unit PT plant, drinking water system Condenser cooling water system- pumps , cw duct & piping Compressed air system- compressor, piping, electrical Air conditioning- control tower area, ESP control room, WTP control room Fire protection system- hydrant system, high pressure water spray system, rate of rise of temperature detection system, sprinkler type protection system for coal conveyors, Foam injection & medium velocity spray system for oil tanks, Automatic Halon-1301 gas extinguishing system, fire water pumps
NTPC(SSTPS)
Formation of NTPC-7th nov 1975 CEA clearance may 1976 World bank appraisal team visit jan/feb 1976 World bank communicating govt. of India- 8th-april-1976 Approval from govt. of India. (SSTPS-ST-I) dec-1976 (600 MW) (SSTPS-ST-II) -July- 1979 (1400MW) Land acquisition (SSTPS) sept. 1977 Site leveling work started sept 1977 Issue of letter of award - feb - 1978 Main plant civil works started (zero date) feb -1978 Boiler erection started April 1978 Erection period of first unit of NTPC(SSTPS)- 48 months. Erection COST of NTPC(SSTPS)- 1190.69 crores Structure material 160000 MT Reinforcement steel -250000 MT Erection of mechanical / electrical 200000MT No. of major agency 60 nos No. of laborers - 20000 skilled & semiskilled
CIVIL- Power house -main plant layout, sub structure, superstructure, Reinforced concrete chimney, Ash disposal system, Water treatment plant, Circulating water system, Coal handling plant. MECHANICALSteam generator- pressure parts, super heater & re heater, fuel preparation & firing system, draft system, air heater, soot blowing system, refractory & insulation, E.S.P Turbo Generator- HP, IP, LP turbine, turbine governing system, turbine monitoring system, lubricating oil system, control fluid system, condenser, vacuum pumps, HP-LP steam turbine bypass system, BFPs &Drives, Condensate Extraction pumps, Heaters & Deaerators, Power cycle piping, EOT crane, Ash disposal system, Water treatment plant, Circulating water system, Coal handling plant, Fuel oil handling system , CW system, AIR COMPRESSOR, Fire protection system , Air conditioning system, ventilation system. ELECTRICAL Generators ,Excitation System, Auxiliary Power Distribution system, UNIT Auxiliary Power Distribution system, Station Auxiliary Power Distribution system, Plant lighting system , Grounding and Lightning protection system, Public Address system, 400KV system of SSTPS C&I Automatic control system , steam and water analysis , control panels and local instrument, Annunciation system , protection and interlocking system ,UPS,DAS.
DESIGN
Construction
CIVIL Piling and foundation Structure and steel works. Chimney Main power house Boiler Turbine Water treatment plant Cw system Fuel oil handling system Coal handling plant Ash handling plant Township
ERECTION
MECHANICAL Boilers and its auxiliaries-Structure- columns and bracing, girder beam, Assemblies of pressure parts components. Lifts Rotary machine- ID,FD,PA fans, Air preheaters, Bowl mills. Turbine generator- condenser, HP,IP,LP turbine, oil system, electro hydraulic governing system, generator, piping system, power cycle piping, boiler feed pump, condensate extraction system, Heaters and Deaerators, condensate polishing plant, EOT crane, elevator- TG hall Coal handling plant Ash handling plant- ash slurry disposal system, bottom ash system, fly ash system, ash slurry pumps. Water treatment plant chemical house, DM plant, cation unit, anion unit, PT plant, LP piping. Compressed Air system Air condition system Ventilation system D.G. set Fuel oil handling system Circulating water system. Fire protection system
ERECTION
ELECTRICAL Generator-Excitation system, Gas system, Seal oil system, Protection of generators Generator Transformer-Aux. power supply arrangement, LT, H.T. switchgear, 6.6kv bus duct, field test report of MCC module, Circuit Breaker testing, Relay testing Cabling cable tray, conduits, grounding, cable termination, Station lighting PA system, Battery Charger ,DC batteries, Float cum boost charger, 400/132 kv switchyard, control and relay panels C&I Instrument air system ,C&I package, TG& SG package, DAS
COMMISSIONING
Commissioning of CW pumps Commissioning of PT pumps Commissioning of BOILER FILL pumps Hydro test of boiler, fixing of orifice in lower ring header Commissioning of FD fan, Commissioning of ID fan, Commissioning of PA fan, Commissioning of CC Pumps Commissioning of motor driven boiler feed pump Commissioning of condensate extraction pump Acid cleaning First stage steam blowing TDBFP Commissioning Commissioning of coal mills Commissioning of ESP Commissioning completion of unit
PG TEST
P.G. test should be done as per the PG test procedure to ensure the garneted parameter. Witness by O&M & OS representative. OS group should also evaluate the same. depending on class of erection