Typical Procedure & Report Development Process Flow
Typical Procedure & Report Development Process Flow
3d
pWPS
21d
WPQT
7d
WPS
14d
Resources
1 Welding Engineer: 360hrs
1 Welder Foreman: 280hrs
1 Fitter Foreman: 280hrs
1 QC Supervisor: 336hrs
1 QC Inspector: 1344hrs
1 Production manager: 40hrs
WQT
Transportation
Study
8d
Analysis/Report
2d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Resources
1 Marine Engineer: 80hrs
1 Lead Engineer: 8hrs
1 Drafter: 80hrs
1 Lead Drafter: 8hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 10 days
2
Pipelay Analysis
21d
Analysis/Report
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Resources
1 Marine Engineer: 168hrs
1 Lead Engineer:24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 24 days
Resources
2 Field Engineer: 336hrs
1 Lead Engineer: 24hrs
1 Drafter: 80hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 24 days
Pipelay Procedure
21d
Constructability
Review
Analysis/Report
3d
Documentation/
First Rev.
Submission
10d
HAZID
Reviewed by
Company
7d
On-Bottom
Analysis
7d
Jacket Model
21d
Analysis/Report
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
3.5d
Resources
1 Structure Engineer: 248 hrs
1 Lead Engineer: 16hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 31 days
Structure (Upending)
Sample of Process Flow
AFC Drawings
Jacket Upending
Consultant Report
5d
Sling Confirmation
Single Block
WCR
Crane Barge
Confirmation
Jacket Main model
Double Block
8d
Analysis
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
Resources
1 Structure Engineer: 128hrs
1 Lead Engineer: 24hrs
1 Drafter: 40hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 16 days
7d
AFC Drawings
Consultant Report
General
Arrangement
Fabrication WCR
Jacket/Topside
Piles
15d
10d
Sea State
Analysis/Report
Analysis/Report
Barge Confirmation
Load-out Info
3d
2d Resources
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Conductor Hang-off
Analysis
15d
Report/Analysis
2d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Resources
1 Structure Engineer: 136hrs
1 Lead Engineer: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 17 days
Piles Drivability
Analysis
7d
Report/Analysis
2d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
3.5d
Resources
1 Structure Engineer: 72hrs
1 Lead Engineer: 16hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 9 days
Piles Upending
15d
Report/Analysis
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Resources
1 Marine Engineer: 144hrs
1 Lead Engineer: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 18 days
10
AFC Drawing
Rigging Calculation
Final WCR
Consultant Design
Report
14d
Info From
Fabricator
Loadout
Coordination
Manual
Rigging Calculation
3d
Documentation/
First Rev.
Submission
HAZID
Resources
2 Field Engineer: 448hrs
1 Lead Engineer: 24hrs
1 Drafter: 112hrs
1 Clerk/QA: 16hrs
14d
Installation
Procedure
10d
Reviewed by
Company
7d