Economics Towler
Economics Towler
Economics Towler
R. B. Eldridge
Course Outline
Industrial Design Process
Economic Analysis
Safety / Environmental / Ethics Issues
Nuts and Bolts Equipment Design
Process Simulation
Feasibility Level Design Problems
Course Objectives
Provide a real-world perspective on process design
Introduce design and selection of equipment
Give insight into practical constraints that govern design
decisions
Help you translate knowledge into practice & start
solving real problems
Using this understanding they can develop a plan of action and set
of detailed specifications, which if followed will lead to a predicted
financial outcome
XYZ Co.
Plan
Financial
outcome
Implementation
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Set Design
Specifications
Build Performance
Models
Generate Design
Concepts
R&D if Needed
Predict Fitness
For Service
Evaluate Economics
& Select Design
Customer
Approval
Procurement
& Construction
Begin Operation
Financial Outcome
If you had $10 million, how would you rather invest it?
1.
2.
3.
4.
5.
6.
Increased
Risk
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Industrial Process
Design
Set Design
Specifications
Build Performance
Models
Generate Design
Concepts
Customer
Approval
R&D if Needed
Predict Fitness
For Service
Evaluate Economics
& Select Design
Procurement
& Construction
Begin Operation
Business
Input
Project
Manager
Process
Engineer(s)
Technical
Specialists
R&D
Specialists
Control
Engineer
Mechanical
Engineer(s)
Cost Engineer
Civil
Engineers
Consultants
Contractors
Operating Companies
Own plants
Produce chemicals
High sales revenue
Margins & return on assets
(ROA) vary by sector
Technology Vendors
Own patents
Company Performance by
Sector
Notes:
Project
Sponsor
Business
Input
Project
Manager
Process
Engineer(s)
Technical
Specialists
R&D
Specialists
Technology
Vendor
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Control
Engineer
Mechanical
Engineer(s)
Cost Engineer
Civil
Engineers
Consultants
Contractors
E&C
Company
Current Approach
(For most companies, most sectors)
Project
Sponsor
Operating
Company
Business
Input
Project
Manager
Process
Engineer(s)
Technical
Specialists
R&D
Specialists
Technology
Vendor
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Control
Engineer
Mechanical
Engineer(s)
Cost Engineer
Civil
Engineers
Consultants
Contractors
E&C
Company
Implications
Task Name
Project KO Meeting
Process Commercialization
2
3
6
7
8
9
10
11
12
13
M-1
M1 M2
3/31
M3
M4
M5
M6
M7
M8
M9
M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23
74 days
Process Design/Optimization
Cold Flow Modeling
Design Sparger
Approve Sparger Design
Construction of Wedge
PP design/construction/shakedown
Cold Flow Testing
Catalyst Scale-up
14
Catalyst Scale-up
15
Demonstration Plant
16
17
18
Process Engineering
19
PFD Review
20
Basic Engineering
21
P&ID review
22
Detailed Engineering
23
Layout Review
24
Procurement
25
Fabrication
26
27
Begin Run
206 days
7/15
150 days
251 days
1/12
2/22
5/18
8/31
12/28
Set Design
Specifications
Build Performance
Models
These steps
have to
come first
Customer
Approval
Generate Design
Concepts
R&D if Needed
Predict Fitness
For Service
Evaluate Economics
& Select Design
Procurement
& Construction
Begin Operation
ID
Task Name
2
3
6
7
8
9
10
11
12
13
M-1
M1 M2
3/31
M3
M4
M5
M6
M7
M8
M9
M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23
74 days
Process Design/Optimization
Cold Flow Modeling
Design Sparger
Approve Sparger Design
Constru ction of Wedge
PP design/construction/shakedown
Cold Flow Testing
Catalyst Scale-up
14
Catalyst Scale-up
15
16
17
18
Process Engineering
19
PFD Review
20
Basic Engineering
21
P&ID re view
22
23
Layout Review
24
Procurement
25
Fabrication
26
27
Begin Run
206 days
7/15
150 days
251 days
1/12
2/22
5/18
8/31
12/28
List of tasks
Durations, start
and end dates
Predecessor
tasks
Resource
allocations
Gantt
chart
MS Project
SureTrak
Primavera Project Planner
Enterprise PM
Cobra
Set Design
Specifications
Build Performance
Models
Generate Design
Concepts
Customer
Approval
Predict Fitness
For Service
R&D if Needed
Evaluate Economics
& Select Design
Detailed Design &
Equipment Selection
We need to know:
What are we designing?
Where will it be built?
Procurement
& Construction
Begin Operation
Documentation of design
assumptions and boundary
conditions is very important
DATE
Sheet
BY
APVD
REV
DATE
1
BY
APVD
Contact information
Company name
Process unit name
Who to contact & where to reach them
Conventions followed
Units of measurement
Customer specific and may also depend on location
Design engineers have to be able to work with both metric and English units
Additional specifications
Feedstock grades
Safety information
Availability and pricing
Feed impurities and their concentrations
Name
ppmw
Site information
Methods and rules for designing processes and equipment are given in design
codes of practice
Standard sizes for piping & equipment, compositions, etc. are given in standards
Codes are set by national or international industry panels (e.g., ISO, ASME, API, ISA)
Codes are reviewed and reissued frequently
Codes specify practices for design, construction, testing and operation of equipment and processes, that are
expected to lead to a safe design, based on the experience of the code committee
Design in accordance with code is usually required by the company or by law
Tubing dimensions, valve sizes, exchanger layouts, screw threads, wire gauges, screens,
(Design Margins)
Equipment is usually sized for greater than the design
throughput
Allows for uncertainty in the design method and data
Leaves some room for expanding output
Ensures the plant can run at design capacity
Companies usually have a policy on design margins
Typically size equipment for 110% of design basis
Be careful to add design margin only once!
6. Design Documentation
Determine
Customer Needs
Set Design
Specifications
Generate Design
Concepts
Customer
Approval
Build Performance
Models
Predict Fitness
For Service
R&D if Needed
Evaluate Economics
& Select Design
Detailed Design &
Equipment Selection
Procurement
& Construction
Begin Operation
Design Documentation
The design documentation for a process usually includes a minimum of:
1. The design basis
2. A written description of the process
3. A process flow diagram
4. At least one mass & energy balance
5. Product specifications and properties
6. A list of major plant equipment
7. Equipment specification sheets
8. A piping and instrumentation diagram
9. A cost estimate
10.HS&E information (e.g., HAZAN, HAZOP, MSDS forms)
Additional information such as techno-economic analysis, market information,
analysis of competing technologies or alternative design options may also be
included if within the scope of the project
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Design Documentation
1. The design basis
2. A written description of the process
XYZ Co.
Design Documentation
1. The design basis
2. A written description of the process
3. Process flow diagram
4. At least one mass & energy balance
5. Product specifications and properties
6. A list of major plant equipment
7. Equipment specification sheets
8. A piping and instrumentation diagram
9. A cost estimate
10.HS&E information
XYZ Co.
Design Documentation
1. The design basis
2. A written description of the process
3. Process flow diagram
4. At least one mass & energy balance
5. Product specifications and properties
6. A list of major plant equipment
7. Equipment specification sheets
8. A piping and instrumentation diagram
9. A cost estimate
10.HS&E information
XYZ Co.
1
25C
120 kPa
kg/h
Hydrogen
Methane
Ethane
Ethylene
Propane
Propylene
Butanes
n-butylene
i-butylene
Water
Carbon dioxide
Total
kmol/h
wt%
mol%
Design Documentation
1.
2.
3.
4.
5.
Design Documentation
1.
2.
3.
4.
5.
7. Equipment specification
sheets
8. A piping and instrumentation
diagram
9. A cost estimate
10. HS&E information
Give detailed design information (stream properties, dimensions) for each major
piece of equipment
Design Documentation
1.
2.
3.
4.
5.
6.
7.
9. A cost estimate
10.HS&E information
XYZ Co.
Design Documentation
1.
2.
3.
4.
5.
6.
7.
8.
9. A cost estimate
10.HS&E information
Capital costs
Working capital
Installed capital cost
Royalty costs
Annual capital charge
Design Documentation
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.HS&E information
Market
Assessment
Detailed Design
$$
AFE
AFD
$$$$$
Preliminary
Design
Customer
Identification
Construction
~4000
A 2000 kMTA
ethylene cracker
~1200
A 90 kbd fluidized
catalytic cracking
plant
~1000
A typical fine
chemicals plant
~20
~100
A 60x8 distillation
column
2 to 10
A new
pharmaceutical plant
20 to 100
A pilot plant
1 to 20
A 2000ft2 heat
exchanger
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
~0.1
0.1 to 0.5
Laboratories, offices
Often approximated as 40%
of ISBL cost as first
approximation
ISBL
OSBL
ISBL
OSBL
Working Capital
To buy feedstocks
To get in business
ISBL
OSBL
E&C
WC
ISBL
OSBL
Contingency
To allow for the unexpected
E&C
ISBL Costs
Direct Field Costs
Major equipment
Furnaces, heat exchangers, coolers
Vessels, reactors, columns, tanks
Pumps, drivers, compressors, fans,
turbines
Refrigerators, driers, centrifuges
Bulk items
Electrics, instrumentation, computer
control
Piping, valves
Structures, insulation, paint
Lube oils, solvents, catalysts
Civil works
Roads, foundations
Piling, buildings
Construction equipment
Temporary construction
Temporary power and water
Construction workshops
Construction insurance
Labor benefits & burdens
Working Capital
Working capital is the money you need to get the plant running
Buy feedstocks, pay bills, etc., until product is sold & revenue begins
Days of RM storage
Days of product storage
Days accounts receivable less accounts payable
Inventories held (e.g. warehouse parts)
Cash on hand
Contingency
Contingency charges allow for variation
from the predicted cost estimate
Variation can be caused by
Scope change
Change in economic scenario
Currency fluctuations
Labor disputes, weather problems, subcontractor problems
Validity of cost estimate and vendor quotes
High
Project Cycle
Low
Cost
Design
Concept
Detailed
Design
Procurement
Construction
Start-up
High
Project Cycle
Low
Cost
Design Influence
Design
Concept
Detailed
Design
Procurement
Construction
Start-up
High
Project Cycle
Low
Cost
Design Influence
Design
Concept
Detailed
Design
Procurement
Construction
Start-up
Project Cycle
50
Accuracy %
40
Order of
Magnitude
30
20
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Study
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Study
Estimate Definitive
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Study
Estimate Definitive
Estimate
Detailed
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Study
Estimate Definitive
Estimate
Detailed
Estimate
Check
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
The check estimate (tender, Class 1 estimate) is prepared by the contractor after
negotiations with vendors and sub-contractors have been concluded
The cost of this estimate can be up to 5% of total project cost, particularly if most of the
engineering design has been completed
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Study
Estimate Definitive
Estimate
Detailed
Estimate
Check
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Exponential Estimating
The cost of most plant items varies with the equipment size in a
non-linear manner:
Log[Cost]
Cost
Size
Log[Size]
Size A
Size B
Exponential Estimating
Since the plant cost is built up from the sum of the equipment costs:
C Plant
C
i 1
equip i
Cost A
Cost B
Size A
Size B
0.6
Example
Cost A
Cost B
size A
size B
30
Cost 56
40
0.6
0.6
47 MM$
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Detailed
Estimate
Check
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Accuracy %
40
30
20
Order of
Magnitude
Detailed design
Vendor quotes
Detailed
Estimate
Check
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Size A
Size
B
(Holland, F.A., Watson, F.A. & Wilkinson, J.K., 1984, in Perrys Handbook, 6 th Edn., McGraw Hill, New York)
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Many of these are updates or derivatives of the work of Guthrie, and have to be used
with some caution
Guthrie, K.M. Capital Cost Estimating, Chem. Eng., 76(6), 114, 1969
Guthrie, K.M. Process Plant Estimating, Evaluation and Control, Craftsman
Co., Solana Beach, CA, 1974
Book
The IChemE and ACostE publish an excellent (& very cheap) guide to capital cost
estimating with recent cost correlations, but these need to be converted from U.K. to
U.S. basis.
Gerrard, A.M. Guide to Capital Cost Estimating, 4th Edn., Institute of Chemical
Engineers, Rugby, U.K., 2000
Many cost engineers collect data and keep their own correlations
Best practice in industry is to use costing software (see later)
Correlations given in Chapter 6 can be used as a first approximation if no software is
available
Gerrard, A.M. Guide to Capital Cost Estimating, 4th Edn., Institute of Chemical Engineers, Rugby, U.K., 2000
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Factorial Estimates
In addition to the purchased cost of the equipment itself, we need to
consider the costs of:
Installation Factors
F
2.5
4
2
3.5
4
2.5
4
4
Lang, H.J. Simplified approach to preliminary cost estimates. Chem. Eng., 55(6), 112, 1948
Hand, W.E. From flow sheet to cost estimate. Petrol. Refiner, 37(9), 331, 1958
2007 G.P. Towler / UOP. For educational use in conjunction with
Sinnott & Towler Chemical Engineering Design only. Do not copy
Chilton Method
Delivered Cost $
12 ft diameter tower
Trays and internals for tower
Accumulator drum
Receivers
Heat exchangers
Pumps and motors
Miscellaneous equipment
$ 200,000
350,000
150,000
400,000
600,000
165,000
135,000
Estimate the fixed capital cost using the Lang, Hand, and Chilton
methods. Assume 15 % contingency.
Installation Factor
F = (1 + fp)fm + fer + fi + fel + fc + fs + fl
Where:
fp
is the piping installation factor
fm is the material cost factor
fer is the site erection installation factor
fi
is the instrumentation installation factor
fel
is the electrical installation factor
fc
is the civil installation factor
fs
is the structure & buildings installation factor
fl
is the lagging, paint and fireproof installation
factor
All of these factors (except fm) vary with installation complexity and
equipment cost
Note that the factors are standardized on a plain carbon steel basis
Installation Factor
Cequipment
Cost information should also always state the cost year basis, e.g. $ 2004,
2000, 2002, etc.
For a new project we therefore have to update the cost basis to reflect
the correct location, local currency and current (or projected) time frame
This is done by applying indices:
CE Cost Index
CE Cost Index
Global Economy
Capital Investment Location Factors
US Gulf Coast
US west Coast
Western Europe
Mexico
Japan
Pacific Rim
India
1.00
1.25
1.20
0.95
1.15
1.00
0.85
Project Cycle
50
Accuracy %
40
30
20
Order of
Magnitude
Study
Estimate Definitive
Estimate
Detailed
Estimate
Check
Estimate
10
0
Design
Concept
Detailed
Design
Procurement
Construction
Right-click on main
area then select Add
Project Component
Enter a name
and select waste
heat boiler
Enter size
parameters and
click evaluate
Equipment cost
Installed cost
Cost
Manufacturing Costs
Labor Rates
Base Case
Q
Process Revision
Q
OVHD
PUMP
COLFEED
FEED
COLUMN
BOT
FEED
PUMP
HOT-OUT
C OLD-OU T
OVHD
COLUMN
Cash
Flow
Working Capital
Revenue / Sales
Expenses
Operations
Depreciation
Net Income
Taxes
Depreciation
IRS Definition
A reasonable allowance for exhaustion, wear and tear, and
normal obsolescence of a property used in the trade of business.
Such property must have a determinable useful life more than
one year.
Depreciation Methods
Straight Line
Declining Balance
Modified Accelerated Cost Recovery
System (MACRS)
MACRS
A chemical plant can be installed for $ 1,000,000.Operating income is estimated to be $ 600,000 annually this is
revenue minus annual expenses. Assume 10 yr straight line depreciation and a 50 percent tax rate. Land can be
purchased for $ 100,000. Plant construction will take two years and at start-up $ 100,000 of working capital will be
required. The plant salvage value is $ 50,000 and will be realized as income during the 10 th year of operation do not
include the salvage value in the depreciation calculation. Determine the cash flow for each year.
Period
Investment
Summary
Cash
Flow
Cash
Position
Start of
year -2
-100,000
-100,000
During
year -2
-500,000
-600,000
Start of
year -1
During
year -1
-500,000
-1,100,000
Time
zero
-100,000
-1,200,000
FCI
Land
Cash Flow ($ 350,000)
Working Capital
Year 1
350,000
-850,000
Year 2
350,000
-500,000
Year 3
350,000
-150,000
Year 4
350,000
200,000
Year 5
350,000
550,000
Year 6
350,000
900,000
Year 7
350,000
1,250,000
Year 8
350,000
1,600,000
Year 9
350,000
1,950,000
Year 10
350,000
2,300,000
End
Year 10
225,000
2,525,000
Revenue
Expenses
Operations
($ 500,000)
Net Income ($ 250,000)
Taxes ($ 250,000)
Future Sum
Discrete Interest
Continuous Interest
Annuity Payments
Present Worth
Future Worth
Manhattan Island was purchased in
1626 for $ 24.00 (P). Taxable real
estate value in 1984 = $ 24 billion
Who got the best deal assuming a 6 %
discrete yearly interest rate
Annuity (Loan)
R R R R
P
R R R R R
Capitalized Cost
An engineer buys equipment for $ 12,000 she wants a fund
set up so she can have $ 10,000 every 10 years to replace
the equipment (the salvage value for the unit is $ 2,000) How
much money should be put in the annuity and what is the
capitalized cost ?? The annual interest rate is 6 percent
Replacement Value
($ 10,000)
P
10 years
Gregory Tables
Investment
Summary
Cash
Flow
Cash
Position
Discount
Factor (15 % )
Discounted
Cash Flow
Discounted
Cash Position
Start of year
-2
-100,000
-100,000
1.350
-135,000
-135,000
During
year -2 to 0
-500,000
-600,000
1.166
-583,000
-718,000
Start of year
-1
During year
-1 to 0
-500,000
-1,100,000
1.079
-539,500
-1,257,500
Time zero
-100,000
-1,200,000
1.0
-100,000
-1,357,500
Year 1
350,000
-850,000
0.929
325,150
-1,032,350
Year 2
350,000
-500,000
0.799
279,650
-752,700
Year 3
350,000
-150,000
0.688
240,800
-511,900
Year 4
350,000
200,000
0.592
207,200
-304,700
Year 5
350,000
550,000
0.510
178,500
-126,200
Year 6
350,000
900,000
0.439
153,650
27,450
Year 7
350,000
1,250,000
0.378
132,300
159,750
Year 8
350,000
1,600,000
0.325
113,750
273,500
Year 9
350,000
1,950,000
0.280
98,000
371,500
Year 10
350,000
2,300,000
0.241
84,350
455,850
End
Year 10
225,000
2,525,000
0.223
50,175
506,025
Profitability Analysis
Payout Period (POP)
FCI (depreciable)
Cash flow / yr
Investment
Summary
Discount
Factor (15 % )
Discounted Cash
Flow
Start of year
-2
-100,000
1.350
-135,000
During
year -2 to 0
-500,000
1.166
-583,000
Start of year
-1
During year -1
to 0
-500,000
1.079
-539,500
Time zero
-100,000
1.0
-100,000
Year 1
0.929
325,150
Year 2
0.799
279,650
Year 3
0.688
240,800
Year 4
0.592
207,200
Year 5
0.510
178,500
Year 6
0.439
153,650
Year 7
0.378
132,300
Year 8
0.325
113,750
Year 9
0.280
98,000
Year 10
0.241
84,350
End
Year 10
0.223
50,175
Sensitivity Analysis
Change in Net Present Value, M USD
-10
-5
10
Price
Variable
Ethylene
Total Erected Cost
High
Ethylene Utilization
Low
Tornado Plot
Sensitivity Analysis
IRR
+10
Sales Price
+5
Sale Volume
% Change
-10
-5
-5
+5
+10
Investment
-10
Spider Plot
Uncertainty Analysis
Variable 1
Variable 2
Variable 3
0.2
0.4
0.25
0.35
0.15
0.2
0.3
0.1
0.25
0.15
0.2
0.05
0.1
0.15
0.1
0
0
0.05
0.05
10
0
-3
-2
-1
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
-3
-2
-1
Total Project
10
15
20