CFB Boiler Commissioning
CFB Boiler Commissioning
CFB Boiler Commissioning
LP Steam Slag
(16) (6)
Coal
(15) BOILER Ash
(7)
Diesel De-sox
(14) (8)
Cooling
Lime Stone
Water (9)
& Ash (13)
Mechanical Completion
Hydro test of the Boiler carried out.
Steam drum level glass gauges are installed
Boil out Process completed
PSV Testing done
Registration / legislation process completed.
Refractory dry out /Baking process completed
Primary, secondary & ID fan testing done
Power for Fans available
Interlocking, loop testing and trip testing checked.
Chemical dosing system complete.
Analyzers are in working condition
Fire suppression system on coal bunker is installed operative.
Screw feeders are ok, and power supply is available
Air supply to loop seals is available
Back filters are installed
Instrument air for all instruments available.
INSTRUMENT AIR
HP steam from boiler till boiler works is completed. (Isolation valves on steam trap lines
fitted)
HP steam line blowing is completed
Auto Vent valve fitted on HP steam Common Header at CFB area
LIME STONE STORAGE AND CONVEYING
Coal is available
Coal yard / coal shed is available
Power supply to Grab crane is available, Grab crane is operative.
Coal feeder, conveyors and one coal crusher is available
Coal bunker is available. Fire suppression system installed on coal bunkers.
Coal conveyor to coal bunker & coal bunker to boiler are available
Power is available to conveyors, crusher, Grab crane
Loader is available
Instrument supply is available
Dust collecting unit are ready
Interlock testing carried out.
Coal feeders to conveyors installed and ready to use.
LOW PRESSURE STEAM