Unit Sart Up 800mw
Unit Sart Up 800mw
Unit Sart Up 800mw
KTPS-800MW
(This piece of work is intended to create better insight of the existing procedures. This is
for informative use only. The assertions for the procedures were purely based on my
experience and the technical information available to me. I undertook lot of review for
preparing the document and I humbly accept and appreciate corrections/suggestions/reviews
from the readers)
Cooling system
1. All lube oil pumps of respective equipments into service.
2. CW pumps in service.
3. ACW pumps in service.
4. TGDMCW, SGDMCW in service.
5. Vaccum re-circulation pumps in service.
6. Primary water pump in service.
7. Generator Seal oil system in service.
Filling Process
o Maintain hot well level through condensate makeup valves.
o Ensure Air vents of HP/ LP heaters, feed water (at APRDS location), BFP
suction strainers, BP suction,MDBFP,TDBFPs open condition.
o Ensure Economiser air vents open.
o Take one CEP with min. recirculation open and start filling Deaerator.
o Close LP heater air vents when stream of water is observed
o Close air vents of MDBFP, TDBFPs till stream of water is observed.
o Close Economiser inlet header drain and also close Furnace inlet header drain.
o Open Deaerator pegging valve for initial heating from APRDS (charged with
Aux. Boiler). Heat the water in Deaerator storage tank till 90oC before feeding
to the Boiler.
o Charge the 30% feed line at feed control station by opening FDV-7, FDV-8,
FDV-9 and closing FDV-10(main line).
o Take FDV-8 control valve position to 30% for static water filling.
o Close air vent of feed water, BFP suction strainers, BP suction, HP heaters till
full stream of water is observed.
o Take MDBFP into service with minimum scoop position (5%-10%) and
recirculation valve open position.
o Adjust the MDBFP hydraulic scoop and control valve FDV-8 position for
controlling the flow (maintain <10% of BMCR flow till separator high level).
o After ensuring complete stream of water, close the economiser air vents.
o With SST level high, HWL-1 valve opens
(All the drains are directly or indirectly connected to the trench which is surrounded to the
service building. It is a good and easy practice to inspect around the trench of service
building to ensure no drain is left opened)
Before light-up
1. Once APRDS is charged through aux. Boiler, start heating HFO. Take HFO
pump in service (14kg/m2). Observe HFO header temperature is increasing if
not open manual re-circulation at location.
After reaching header temperature above 100◦C open HOTV and close the
same manual re circulation valve at location till the flow (re circulation) shows
3000kg/hr.
2. Take LDO pump into service with 14kg/m2 set point and above 10kg/m2 at
boiler.
3. Maintain service air pressure minimum 5.5kg/m2 for atomization.
4. Take APH-A and APH-B into service.
5. Take one FD fan and one ID fan into service and maintain air flow above
30 % (>893T/hr)
6. Take Scanner fan into service.
7. Complete the scavenging process of all the guns.
8. Ensure wind-box auxiliary air dampers are open or modulating and burner tilt
at horizontal position.
8. SCAPH inlet and outlet damper gates are opened and bypass damper are
closed.
9. Open ASS-10 valve (near coal feeder-D) to allow auxiliary steam to SCAPH
station.
10. Boiler side: SH drains open, SH vents open, startup vents open, separator
vents open, furnace riser vent open)
11. Turbine side: All unit flash tank drains open, all Mal drains to flash tank-A
open, CRH pot drain open.
12. SH and RH spray block valves close.
13. Check Open positions of Separator vents, SH vents, Furnace raiser vent,
Reheater vents.
14. Check Open positions of MS drains, SH drains.
15. Check Open positions of all Turbine drains related to unit flash tank and flash
tank-A.
Boiler light up
1. Ensure purge permissive are satisfied and then purge the boiler. Give LFO burner
start command 1&3 or 2&4 pair guns at AB elevation and check flame intensity.
Also ensure flame condition at location.
2. Once draft and LFO header pressure is normal, give start command to 2nd pair of
guns and checks flame intensity then ensure flame condition at location.
3. Adjust air-fuel ratio and maintain appropriate %O2.
4. Start APH soot blowing with aux. Steam or through air (open air valve at location).
(It is extremely important to have APH soot blowing system in service when firing is
carried with oil to avoid APH firing).
5. Set the MEFCV minimum position (28% to 32%) and take BCWP pump into
service.
6. Maintain SST level with feed water flow (MBFP)
Keep HWL-1 and HWL-2 valves in auto mode
(It is extremely important that minimum WW flow be maintained at all times when firing
the boiler to present tube damage due to overheating.
If WW flow falls below the low set point, all fuel must be automatically dropped with a
maximum time delay of 10sec.)
7. Start one PA fan and open cold air gates (5%) path for all the mills for coal nozzle
cooling.
8. For cold start ups , the fuel start up sequence is
AB(LDO)→CD(HFO)→EF(HFO)→AB(HFO)
9. At 2kg/cm2 of MS pressure,
Close Separator vents,
Close SH vents.
Close furnace raiser vent
I. (Air resists the heat 1500 times than that of steel. Its thermal conductivity is very
poor which decreases the heat transfer rate and results in short term failure of
tube.
2
II. We know that air exists at 1.03kg/cm2, closing air vents at 2kg/cm ensures that
air is completely removed from the system.)
10. Slowly increase firing rate as per Boiler startup curve.
11. At 5kg/cm2 of MS pressure,
Close all SH drains
(The condensate formed in the tubes is mainly due to following 2 reasons:
1. Formation of condensate due to previous shut down.
2. Formation of condensate due to initial start up steam.
Any blockage or restriction to the steam flow will cause heating of tube and results in
short term tube failure)
12. Arrange opening of Bypass system as per procedure (check below in Turbine
operations).
Open LP Bypass system as per procedure (check Bypass system steps).
Open HP Bypass valve minimum of 2% in order to warm up the MS pipe lines,
CRH/HRH pipe lines and RH coils.
(Make sure LP Bypass system is opened before opening HP Bypass valve).
13. At 7kg/cm2 of MS pressure,
Open MS bypass valves (left 2Nos. and right 2Nos.)
Close MS drains after opening MS bypass valves.
14. At 10kg/cm2 of MS pressure,
1. Open MS stop valves and then close MS bypass valves.
2. When steam passes through HPBP, ensure no hammering at 0-mtr. If
hammering observed, reduce the opening percentage.
(Sudden opening of HPBP during start-up must be avoided)
15. At 5kg/cm2 of CRH pressure,
Close Reheater vents.(Ensure steam path through LPBP before closing)
16. Increase firing rate 5%→7%→10% so on.
17. At 10% of firing rate,
If HP Bypass is not opened (minimum of 2%) at 10% of firing rate, then the
Boiler trips on Reheater protection.
18. Take warm fuel (H.F.O) into service at CD elevation. Minimum 5kg/cm2 of steam
is required for atomization.
19. Increase the HP Bypass valve position, which allows the steam to warm up RH
coils, MS stop valves, HP control valves, IP control valves as the steam passes
through RH drain and LP bypass system.
16. Slowly increase the firing rate to 20%.
Close RH outlet drain valve when CRH pressure reaches 5kg/cm2.
Close startup vents so that complete steam flow is established through HP/LP
Bypass system.
CRH pot drain crack open position.
Adjust HP Bypass valve position to maintain unit startup pressure of
100kg/cm2.
17. Take warm fuel (H.F.O) at EF elevation if startup pressure and temperature is not
sufficient.
18. Change over from LDO to HFO at AB elevation.
19. From the real time practice, minimum 23% of corrected fuel rate, 500TPH MS
flow is required to achieve start-up conditions.
20. Take 2nd set of ID and FD fans into service.
21. Ensure no water comes through CRH pot drain. If water is observed at CRH pot
drain, increase the HP bypass valve position to increase CRH temperature.
22. After synchronization,
Take mills one after the other into service as per pressure requirement.
nd
Take 2 set of PA fan into service.
23. Increase the loading of 2nd set of fans manually until equal currents with their
respective fans and put them in Auto.
24. Increase coal flow as per load demand.
25. Remove the Elevation oil guns when its corresponding coal feeders demand is
more than 50%.
26. Ensure all guns are out of service at 60% of load 480MW.
27. Adjust all feed rates equally and put it in AUTO or in CMC control.
Main Turbine Startup
Bypass system
15. After opening of MS stop valves at 10kg/cm2, arrange the bypass system.
16. Open LP Bypass stop valves by increasing the demand till 30 % in control PID
(manually).
17. Open LPBP control valves by giving set point in manual set point such that
minimum 25% of LPBP is opened till CRH reaches12kg/cm2
(Till synchronization, control valves follow fixed set point (manual set point) and after
synchronization control valves follows variable set point.)
18. Once CRH reaches 12kg/cm2, give LPBP fixed or manual set point as 12kg/cm2 till
synchronization.
19. Open HP Bypass valve greater than 2% in order to warm up the MS pipe lines,
CRH/HRH pipe lines and RH coils.
(Always make sure LP Bypass system is opened before opening HP Bypass valve).
20. At 20-25% BMCR firing rate,
Adjust HP bypass valve opening/closing to meet start up pressure 100kg/cm2.
Changeover APRDS from Auxiliary Boiler to Main steam line of minimum
30kg/cm2 pressure and 350oC temperature is required.
(While changeover pressure drop must be avoided as atomizing steam is in service
for HFO and temperature drop must be avoided as seal steam in service for
turbines).
46. Start increasing the load only when above step-42 is completed.