C
Construction Sequence for Section C-C
Construction Sequence for Section C-C
Possible Sequences:
1. B C A
2. A B C
3. A C B
Construction Sequence for Section C-C
5. Remove S1 Slab
6. Retrieve Kingpost
7. Backfill to Ground Level
8. Cut SBP wall 2.0m below final ground level and backfill
E
Construction Sequence for Section E-E
A
1. Cast inner walls, columns and external walls
2. Install steel bracing and cut kingpost above roof SSL
B 3. Cast 2.0m x 0.5m strengthening beam along GL 3-6
4. Cut kingpost between roof and concourse slab
5. Backfill 1.5m above roof level
Sequence:
A B
Construction Sequence for Section E-E
6. Remove S1 Slab
7. Retrieve Kingpost
8. Backfill to Ground Level
9. Cut SBP wall 2.0m below final ground level and backfill
Plan View
Stage 2 Kingpost transfer and cutting
1. Preload jack
2. Cut bottom part of King post
3. Finish up the water proofing
Stage 3 Casting of remaining footing