FTTH Project Implementation: PT. Confidential

The document outlines the steps for an FTTH project implementation, including: 1) Surveying and designing the fiber optic route and placements of ODPs, OLT, and ODCs; 2) Obtaining necessary permits; 3) Receiving and checking materials upon delivery; 4) Preparing for deployment by ensuring proper tools, manpower safety equipment are available; 5) Implementing by installing pole accessories, laying cables, and setting up ODPs, ODCs, and OLT.

Uploaded by

Lian
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
216 views

FTTH Project Implementation: PT. Confidential

The document outlines the steps for an FTTH project implementation, including: 1) Surveying and designing the fiber optic route and placements of ODPs, OLT, and ODCs; 2) Obtaining necessary permits; 3) Receiving and checking materials upon delivery; 4) Preparing for deployment by ensuring proper tools, manpower safety equipment are available; 5) Implementing by installing pole accessories, laying cables, and setting up ODPs, ODCs, and OLT.

Uploaded by

Lian
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 10

FTTH Project

Implementation

PT. Confidential
Survey and Design
• Define Fiber Optic Route on Electricity Pole
• Define ODP Placement on the Pole’s
• OLT Location & Cabling Requirement
• ODC Placement
• Provide As Plan Drawing, Core Management & Bill of Quantity
Permit Clearance
• Having co-ordination with RT/RW, inform for Project Deployment plan
• Handle Community Issue if any
• Get written permission from RT/RW of related cluster (usually in
Berita Acara form)
Material Receiving
• Check material quantity base on Delivery Note on receiving
• Check material condition and reject if any material damage during
delivery
• Report receiving Material on Site (MoS) result
• Performed along with subcon PIC as also become handover from LnS
to Subcon
• Keep materials in proper storage, especially active equipment must
be placed inside a room (indoor)
Deployment Preparation
• Check tools required, working in electricity pole need non metal
ladder to avoid electric hazardous
• Man Power must use isolator gloves, safety shoes/boots, Full Body
Harness
• Check cable work tools such as Cable Stripper, Cutter, Fusion Splicer,
Optical Time Domain Reflectometer (OTDR), Optical Power Meter
(OPM), pliers, screwdriver, etc.
• Check readiness of accessories materials
Implementation
• Install Pole Accessories
Implementation
• Cable Laying
Implementation
• Install ODP
Implementation
• Install ODC
Implementation
• Install OLT