Boiler Dantrubin Control Rembang Dan Pacitan
Boiler Dantrubin Control Rembang Dan Pacitan
Boiler Dantrubin Control Rembang Dan Pacitan
2) Furnace purge.
Before boiler ignition or after boiler shutdown, use proper air flow to clean out the
combustible matters which may accumulate in the furnace and flue gas duct in order to avoid
knocking combustion or blast. Usually use 30% of the rated air flow to purge for 5 min. The
purge can be carried out when all the requirements are satisfied, such as the tripping valve
of oil main pipe is closed, all primary air fans are stopped, all oil gun valves are closed, all
coal pulverizers are stopped, all coal feeder are stopped, furnace without flame, all dampers
in the purge channel are opened etc. The above requirements in fact are kind of entire
inspection for the fuel supplying equipments, flame detector indication, and air dampers; and
if all these requirements are met, take 5 min purge. Moreover, these factors combined
together can guarantee sufficient air flow to clean out the combustible matters which may
accumulate in the furnace and flue gas duct
3) Fuel oil and oil gun management.
It will help to carry out the oil leakage test, oil gun ignition and cutoff etc. The oil
gun can be put into operation when some requirements are satisfied, such as MFT
is reset, fuel pressure and fuel temperature are normal, etc. It can automatically run
the ignition sequence which controls the oil gun valve, atomized steam valve, high-
energy igniter etc.
4) Coal pulverizer management and main fuel (pulverized coal) in/out of service.
It assists to carry out the burner startup and shutdown. As for the direct-fired
system, it also manages the startup and shutdown of the coal pulverizer and coal
feeder. The conditions for feeding pulverized coal mainly include following parts:
enough ignition energy, normal primary air pressure, normal sealing air pressure
etc.
Fuel adjustment loop consists of fuel amount calculation loop, fuel regulator,
fuel control station and coal feeder bias M/A station. Fuel calculation loop
calculates the coal amount and oil amount and convert to the fuel variable
signal indicated by % or t/h according to calorific amount.
BTU calibration loop is set for adjustment system. Operator can manually set
the coal quality correction coefficiency via BTU calibration actuator, or can put
BTU as auto to automatically calibrate the fuel variable signal.
Boiler master control command is taken as the command signal of fuel
variable after limiting the air & coal ratio. Fuel bias signal is sent to M/A station
of A, B, C, D, E coal feeder as the command of control station via fuel control
M/A station after PID calculation.
Under manual mode, fuel control M/A station can operate 5 coal feeders
simultaneously(at least one coal feeder is in auto state). Fuel regulator outputs
the command that automatically track fuel control M/A station. When 5 coal
feeders are all in manual, switch the fuel control M/A station to manual and
tracing state to track the average rotation speed command of operating coal
feeders.
4) Adjustment principles of pulverizer inlet PA flow adjustment
system
The set point of pulverizer inlet PA air flow is got based on the coal
feeder command after function conversion. The function mainly gets
the needed PA flow based on coal amount (take coal as unit). The set
point has upper and lower limit (40% and 75%) to prevent pulverizer
tripping because of excessive low PA flow under auto conditions.
Operator can manually set the bias of set point in M/A station of
pulverizer PA flow adjustment.
When adjustment system is manual, regulator outputs auto signal to
track M/A station manual output. PA flow set point automatically tracks
measurement value. Therefore, the switch between manual and auto
of adjustment system is bumpless.
15)control
Coordinated
Coordinated control system is indirect energy balance control.
Boiler main controller has two PID regulators and one M/A station. The two regulators
are BF pressure regulator and boiler main regulator.
BF pressure regulator works under BF mode. It receives the pressure set point and
pressure signal front of turbine. Regulator output is the command of boiler main
control. In order to quicken the boiler side adjusting speed and reduce pressure
difference, turbine side energy signal PS*P1/PT is used to be feed forward.
Under coordinated mode, boiler main control regulator works. Main steam pressure
difference and power difference simultaneously function to boiler main control
regulator.
In order to quicken the load response speed, unit load command signal is taken as
feed forward signal, and quicken the adjust speed after dynamic processing.
Turbine main controller has two PID regulators and one M/A station. Two regulators
are TF pressure regulator and turbine main control regulator.
Under coordinated control mode, turbine main control regulator works. Main steam
pressure difference and power difference simultaneously function to turbine main
control regulator. The power signal practically sent by generator is taken as the
feedback signal to control the turbine and adjust steam valve opening, realizing the
closed loop control of power.
Under TF mode, TF pressure regulator receives the pressure set point and pressure
signal front of turbine to control the turbine and adjust steam valve opening, realizing
the closed loop control of power.
Boiler and turbine controller are both designed with relatively perfect tracing logic
which can realize the bumpless of manual/auto and operation modes.
7) Adjustment principles of PA pressure adjustment system
Turbine follow mode (TF): it is an assistant operating mode when the boiler has partial
fault or during large change of the working condition (coal pulverizer startup or shutdown
etc.). Under this mode, the boiler main control is in manual control mode, the operator sets
the fuel command manually, the turbine main control adjust the pressure before turbine
automatically. Under this mode, the pressure fluctuation of dynamic process is smaller, and
the unit runs normally, but the unit load response is slow.
The CCS system sends CCS REMOTE CONTROL DEH signal to DEH system,
after meeting DEH requirements and the operation of DEH operator, then
sent one DEH CHOOSE REMOTE signal to CCS system, which means that
the DEH system can accept CCS load increasing or decreasing pulsing
signal. The DEH POWER CONTROL/GOVERNING STAGE PRESSURE
CONTROL LOOP signal from DEH system to CCS system displays the DEH
control loop and working state.
4.2 Boiler main controller
The boiler controller is also called main control loop. It is mainly used to realize
the boiler control, fuel amount follow during load rejection when the auxiliary has
fault.
4.2.1 Main steam pressure control
When the unit is under the AUXILIARY FAULT RUN BACK operating condition,
the actual load command is also sent to the boiler main control loop as the
feedforward signal, which makes the boiler combustion rate changes as the
load command change. Under the coordinated operating mode, the unit load
command is the unit actual load command. Under boiler follow mode, the unit
load command is the unit actual power. The main steam pressure deviation
signal is calibrated by the ratio integral regulator and finally the main steam
pressure follows the main steam pressure set. After the comparison between
main steam pressure and its set value via subtracter, the boiler main control
command is sent to the boiler combustion control system to change the fuel
amount and air flow, thus the main steam pressure equals to the set value of
main steam pressure.
4.2.2 Boiler control during run back when the auxiliary has fault
When the unit has run back because of the faulty auxiliary, the unit actual load command
drops to the load target value according to certain run back rate. When cutting off the
calibration loop for main steam pressure, the boiler main command changes as the run
back command directly.
4.2.3 Fuel amount follow mode
The load is mainly determined by fuel amount. When the fuel control is in manual mode,
the boiler main control has lost boiler load control capability. So the boiler main control
command must follow the actual fuel amount signal.
4.2.4 Unit fix pressure/sliding pressure set value:
In order to satisfy the unit economic operation, the system sets fix pressure/sliding pressure
operating mode.
The unit withdraws the sliding pressure operation, that means it enters fix
pressure operation. During fix pressure operation, when the set value of the
main steam pressure is different from the target value, it will cause the set value
of main steam pressure increasing. The operator sets the increasing rate. Set
the increasing rate as zero in the following conditions.
Require to keep the main steam pressure set value increasing rate.
a. Enter basic mode
b. RB state
c. Bypass startup
DEHC
Turbine Control System
2.1.4 EH hydraulic pressure system includes oil feeding system, oil pipes,
and oil motor. EH oil feeding system also includes the emergency trip
system which controls the oil motor emergency shutdown and the
diaphragm valve. HP fire-resistant oil source is equipped with two
redundant sets of pressure oil pumps to ensure the continuous oil feeding.
2.1.5 The emergency trip system includes OPC solenoid valve, AST solenoid
valve and diaphragm valve.
The structure of OPC solenoid valves is two vales parallel connection. When
the OPC solenoid valve is energized, release OPC safety oil, and quickly
close the governing steam valve. The structure of AST solenoid valves is four
valves series/parallel connection. When AST solenoid valve is de-energized,
release AST safety oil and OPC safety oil, close all of the valves and shut
down. Connect the diaphragm valve with LP safety oil interface. When there
is no LP safety oil, releases AST safety oil by the diaphragm valve. Quickly
close the valve and shut down.
2.3 Main Functions of DEH Control System
2.3.1 Latch on
2.3.2 Set the static relationship of servo system
2.3.3 Control and start up before the startup
2.3.4 Automatically inspect the thermal state
2.3.5 Rotating speed control
2.3.6 Speed up: Set target, set speed-up rate, automatic passing the critical point, automatic turbine warming up,
and constant speed with 3000r/min.
2.3.7 Load control
2.3.8 Synchronization with initial load.
2.3.9 Pseudo - synchronization test of generator.
2.3.10 Automatic synchronization.
2.3.11 Run up: Set target, set loading rate, automatic turbine warming up.
2.3.12 Constant – sliding - constant run up.
2.3.13 Load feedback control.
2.3.14 Primary frequency regulation.
2.3.15 CCS control.
2.3.16 High load limit.
2.3.17 Low load limit.
2.3.18 Valve position limit.
2.3.19 Main steam pressure control.
2.3.20 Main steam pressure limit.
2.3.21 Run back.
2.3.22 Switchover of single valve and sequence valve
2.3.23 Over speed protection control
2.3.24 Load rejection over speed limit
2.3.25 103% over speed control
2.3.26 Acceleration protection
2.3.27 Over speed protection
2.3.28 On-line test
2.3.29 Oil spray test
2.3.30 Over speed test: electrical over speed test, mechanical over speed test
2.3.31 Valve opening and closing tests
2.3.32 HP trip solenoid valve test
2.3.33 Valve leakage test
2.3.34 Control mode switchover
2.3.35 Turbine auto/manual mode
2.3.36 Shutdown
2.5 DEH System Function Test
2.5.1 Valve test
DEH has two modes for testing: the valve test (full travel closing test) and the
valve looseness (movement) test. For the former one, close the full travel
during the test and for the latter close the valve for 10%-20% only on the
current position. In order to avoid the influence on the load, the fill travel test is
required to be carried out when unit load is 60%-80% of the rated load, and the
power loop should be put into service. The valve looseness test can be carried
out under full load condition.
For increasing the reliability, the HP trip solenoid valve use double redundant
structure which is two in parallel and two in serial. It ensures that the on-line
test can be carried out for the HP trip solenoid valve. The operator can do the
HP trip solenoid valve test on the display of OSI station, after switch the test
key-switch to the permitted position. During the test, the operator only can
select one solenoid valve to do the test each time.
Under the normal condition, if the electromagnets of the 6YV, 7YV, 8YV and
9YV HP trip solenoid valve carry the power, the 4PS and 5PS of pressure
switch doesn’t work. During the normal test, the electromagnet of 7YV or 9YV
loss the power and operate, the pressure switch 5PS operate. If the power
lose time of electromagnet is more than 15 seconds, and the signal of 5PS
pressure switch doesn’t correct, the test can be considered in fault. After the
test for electromagnet of 7YV and 9YV is finished, make the 7YV and 9YV
carry the power again. And then, the test for 6YV and 8YV can be performed,
the electromagnet of 6YV or 8YV lose the power and operate, the pressure
4PS operate. If the power lose time of electromagnet is more than 15
seconds, and the signal of 4PS doesn’t correct, the test can be considered in
fault. After the test for 6YV and 8YV is finished, make the 6YV and 8YV carry
the power again.
TERIMA KASIH