Effective Claims Management
Effective Claims Management
Effective Claims Management
This session will cover all conceptual issues related to claims in Constru
industry . Attendees will understand the various types of claims , delays
effects of delays as per the standard forms of FIDIC.
Effective Claims Management in Construction Pr
2] Douglas H. Yarn, ed. "Conflict" in Dictionary of Conflict Resolution, San Francisco: Jossey-Bass 1999. p
Effective Claims Management in Construction Pr
A “dispute” can only arise once the subject claim, issue or other matter
has been brought to the attention of the opposing party and that party
has had an opportunity of considering and admitting, modifying
or rejecting the claim or assertion.
So, what is
a claim?
ssertion of a right to money, property, or to a remedy
Extension of
Disruption Acceleration
Time (EOT)
Claims. Claims.
Claims
Types of delay
EOT Claims
• Extension of Time
• Time with Cost -
Employer’s delays
• Time without Cost -
Neutral Delays or
• Concurrent Delays by
Employer and Contractor
Effective Claims Management in Construction Pr
• Cost Escalation
• Claim Preparation Cost
Other Claims
• Acceleration Claim
Effective Claims Management in Construction Pr
Claims
Employer claiming monies from Contractor (2.5
Finish
Effective Claims Management in Construction Pr
Disruption Claim
This is basically a delay claim but delay may or may not affect the
project completion. Cost that are generally claimed are:
•Reduced Productivity
• Idle resources
Demobilization
• / Re-mobilization
•Unproductive Overtime.
Disruption is not the same as delay; disruption is an interference, disturbance,
hindrance or interruption to a Contractor’s intended method of works resulting in
out of sequence work and/or lower productivity.
Acceleration Claim
eration occurs when the Contractor attempts to mitigate
ays to the Contract programme by increasing his resou
king overtime etc. cceleration may be sub-divided into 2
ories:
Variation Vs Claim
Some variations may result in claims but not all variations result
claims.
Claim submission
Names of the parties; description of the works; details of tender and accep-
tance; the form of contract and any amendments thereto; the contract sum;
dates for commencement and completion; phased completion (if applica-
ble); liquidated damages for delay; the programme.
Summary of facts
73
Effective Claims Management in Construction Pr
Basis of claim
Contract provisions relied upon; common law provisions;
contractual
analy- sis and explanation of the basis of the claim.
Details of claim
Full details of every matter which is the subject of the claim. Each
separate issue should be carefully set out in a logical format. Key dates,
events, causes and effects, references to relevant documents and the
like should form the basis of a narrative which fully describes the history
of the project and the effects on progress, cost and completion. It is
important to distin- guish between the causes and effects of delay
(and/or disruption), exten- sions of time and the financial effects of
delay and/or disruption. Wherever possible, diagrams, programmes,
tables and the like should be included in the narrative (or in an
74
Effective Claims Management in Construction Pr
Statement of claim
A brief statement setting out the claimant's alleged entitlements and
relief sought, such as extensions of time; sums claimed; repayment of
liquidated and ascertained damages (if applicable).
Appendices
Copies of all documents referred to in the claim; programmes; diagrams;
schedules; financial data
Effective Claims Management in Construction Pr
1.Reject the claim on the grounds that the claimant has not proved his case.
Obviously the respondent has to provide and substantiate reasons for such a
rejection in his response.
duce a determination which is not only based upon the claim sub
but also on the respondent’s own knowledge of the matter and additional
records available to the respondent.
Effective Claims Management in Construction Pr
76
Effective Claims Management in Construction Pr
HTTP://WWW.CONTOSO.COM/