Power System Operation and Control-1
Power System Operation and Control-1
Power System Operation and Control-1
Unit 1 ~ Introduction
A power system consists of several generating stations, where
electrical energy is generated, and several consumers for whose use the
electrical energy is generated. The objective of any power system is to
generate electrical energy in sufficient quantities at the best-suited
locations and to transmit it to the various load centers and then
distribute it to the various consumers maintaining the quality and
reliability at an economic price
Quality implies that the frequency be maintained constant at the
specified value (50 Hz in our country; though 60-Hz systems are also
prevailing in some countries) and that the voltage be maintained
constant at the specified value. Further, the interruptions to the supply
of energy should be as minimum as possible.
Power System Operation and Control
Unit 1 ~ Introduction
One important characteristic of electric energy is that it should be
used as it is generated; otherwise it may be stated that the energy
generated must be sufficient to meet the requirements of the
consumers at all times. Because of the diversified nature of activities of
the consumers (e.g., domestic, industrial, agricultural, etc.), the load on
the system varies from instant to instant.
However, the generating station must be in a ‘state of readiness’ to
supply the load without any intimation from the consumer. This
‘variable load problem’ is to be tackled effectively ever since the
inception of a power system. This necessitates a thorough
understanding of the nature of the load to be supplied, which can be
readily obtained from the load curve, load–duration curve, etc.
Power System Operation and Control
Unit 1 ~ Introduction
Types of Load
• Domestic load
• Commercial Load
• Industrial Load
• Municipal Load
• Irrigation load
• Traction load
Power System Operation and Control
Unit 1 ~ Introduction
LOAD CURVE
A load curve is a plot of the load demand (on the y-axis) versus the time (on the
x-axis) in the chronological order.
From out of the load connected, a consumer uses different fractions of the total
load at various times of the day as per his/her requirements. Since a power system
has to supply load to all such consumers, the load to be supplied varies
continuously with time and does not remain constant. If the load is measured (in
units of power) at regular intervals of time, say, once in an hour (or half-an-hour)
and recorded, we can draw a curve known as the load curve.
Power System Operation and Control
Unit 1 ~ Introduction
A time period of only 24 hours is considered, and the resulting load curve, which
is called a ‘Daily load curve’, is shown in Fig. 1.1. However, to predict the annual
requirements of energy, the occurrence of load at different hours and days in a year
and in the power supply economics, ‘Annual load curves’ are used.
An annual load curve is a plot of the load demand of the consumer against time
in hours of the year (1 year = 8,760 hours).
Maximum demand:
It is the maximum load used by a consumer at any time. It can be less than or
equal to the connected load. The maximum demand is usually measured in units of
kilowatts (kW) or megawatts (MW) by a maximum demand indicator.
Demand factor:
The ratio of the maximum demand to the connected load is called the ‘demand
factor’.
Note: Maximum demand and the connected load are to be expressed in the same units (W, kW, or MW).
Power System Operation and Control
Unit 1 ~ Introduction
Average load:
If the number of kWh supplied by a station in one day is divided by 24 hours,
then the value obtained is known as the daily average load.
The load factor may be a daily load factor, a monthly load factor, or an annual load
factor, if the time period is considered in a day or a month or a year, respectively. Load
factor is always less than one because average load is smaller than the maximum
demand.
It plays a key role in determining the overall cost per unit generated. Higher the
load factor of the power station, lesser will be the cost per unit generated.
Power System Operation and Control
Unit 1 ~ Introduction
Diversity factor:
Diversity factor is the ratio of the sum of the maximum demands of a group of
consumers to the simultaneous maximum demand of the group of consumers.
A high diversity factor implied that with a smaller maximum demand on the station,
it is possible to cater to the needs of several consumers with varying maximum
demands occurring at different hours of the day. The lesser the maximum demand, the
lesser will be the capital investment on the generators. This helps in reducing the
overall cost of the units (kWh) generated.
Thus, a higher diversity factor and a higher load factor are the desirable
characteristics of the load on a power station. The load factor can be improved by
encouraging the consumers to use power during off-peak hours with certain incentives
like offering a reduction in the cost of energy consumed during off-peak hours.
Power System Operation and Control
Unit 1 ~ Introduction
Plant capacity:
It is the capacity or power for which a plant or station is designed. It should be
slightly more than the maximum demand. It is equal to the sum of the ratings of all the
generators in a power station.
Plant capacity factor:
It is the ratio of the average demand on the station to the maximum installed
capacity of the station.
Power System Operation and Control
Unit 1 ~ Introduction
Firm power: It is the power that should always be available even under emergency.
Prime power: It is the maximum power (may be thermal or hydraulic or mechanical)
continuously available for conversion into electric power.
Power System Operation and Control
Unit 1 ~ Introduction
Dump power: This is the term usually used in hydro-electric plants and it
represents the power in excess of the load requirements. It is made
available by surplus water.
Spill power: It is the power that is produced during floods in a hydro-power
station.
Cold reserve: It is the reserve-generating capacity that is not in operation, but can
be made available for service.
Hot reserve: It is the reserve-generating capacity that is in operation, but not in
service.
Spinning reserve: It is the reserve-generating capacity that is connected to bus bars
and is ready to take the load.
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.1:
A generating station has a maximum demand of 35 MW and has a connected load
of 60 MW. The annual generation of units is 24 × 107 kWh. Calculate the load factor and
the demand factor.
Solution:
No. of units generated annually = 24 × 107 kWh
No. of hours in a year (assuming 365 days in a year) = 365 × 24 = 8,760 hours
Power System Operation and Control
Unit 1 ~ Introduction
Load Factor
Demand factor
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.2:
A generating station supplies four feeders with the maximum demands (in MW) of
16, 10, 12, and 7 MW. The overall maximum demand on the station is 20 MW and the
annual load factor is 45%. Calculate the diversity factor and the number of units
generated annually.
Solution:
Sum of maximum demands = 16 + 10 + 12 + 7 = 45 MW
Simultaneous maximum demand = 20 MW
Power System Operation and Control
Unit 1 ~ Introduction
Diversity factor
Alternatively,
Annual load factor
i.e,
Example 1.3:
The yearly load–duration curve of a power plant is a straight line (Fig 1.4). The
maximum load is 30 MW and the minimum load is 20 MW. The capacity of the plant is
35 MW. Calculate the plant capacity factor, the load factor, and the utilization factor.
Solution:
No. of units generated per year = Area OACD = Area OBCD + Area BAC
Load factor
Power System Operation and Control
Unit 1 ~ Introduction
Utilization factor
Alternatively,
Utilization factor
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.4:
Calculate the total annual energy generated, if the maximum demand on a power
station is 120 MW and the annual load factor is 50 %.
Solution:
Maximum demand on a power station = 120 MW, Annual load factor = 50 %
Load factor
Example 1.5:
Determine the demand factor and the load factor of a generating station, which has
a connected load of 50 MW and a maximum demand of 25 MW, the units generated
being 40 × 106/annum.
Solution:
Connected load = 50 MW, Maximum demand = 25 MW
Units generated = 40 × 106/annum
Demand factor
Power System Operation and Control
Unit 1 ~ Introduction
Average demand
Load factor
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.6:
Calculate the annual load factor of a 120 MW power station, which delivers 110
MW for 4 hours, 60 MW for 10 hours, and is shut down for the rest of each day. For
general maintenance, it is shut down for 60 days per annum.
Solution:
Capacity of power station = 120 MW
Power delivered = 110 MW for 4 hours
= 60 MW for 10 hours
= 0 for the rest of each day
Power System Operation and Control
Unit 1 ~ Introduction
And for general maintenance, it is shut down for 60 days per annum.
Energy supplied in 1 day = (110 × 4) + (60 × 10) = 1,040 MWh
No. of working days in a year = 365 − 60 = 305
Energy supplied per year = 1,040 × 305 = 317,200 MWh
Annual load factor
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.7:
Customer-connected loads are 10 lamps of 60 W each and two heaters of 1,500 W
each. His/her maximum demand is 2 kW. On average, he/she uses 10 lamps, 7 hours a
day, and each heater for 5 hours a day. Determine his/her: (i) average load, (ii) monthly
energy consumption, and (iii) load factor.
Solution:
Maximum demand = 2 kW, Connected load = 10 × 60 + 2 × 1,500 = 3,600 W
Daily energy consumption = number of lamps used × wattage of each lamp ×
working hours per day + number of heaters × wattage of each heater × working hours
per day = 10 × 60 × 7 + 2 × 1,500 × 5 = 19.2 kWh
Power System Operation and Control
Unit 1 ~ Introduction
1. Average load
Example 1.8:
The maximum demand on a generating station is 20 MW, a load factor of 75%, a
plant capacity factor of 50%, and a plant-use factor of 80%. Calculate the following:
1. daily energy generated,
2. reserve capacity of the plant,
3. maximum energy that could be produced daily if the plant were in use all the
time.
Power System Operation and Control
Unit 1 ~ Introduction
Solution:
Maximum demand, MD = 20 MW
Load factor, LF = 75%
Power capacity factor = 50%
Plant-use factor = 80%
Average load = MD × LF
= 20 × 0.75 = 15 MW
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.9:
A certain power station’s annual load duration curve is a straight line from 25 to 5
MW (Fig 1.5). To meet this load, three turbine-generator units, two rated at 15 MW
each and one rated at 7.5 MW are installed. Calculate the following:
1. installed capacity;
2. plant factor;
3. units generated per annum;
4. Utilization factor.
4. Utilization factor
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.10:
A consumer has a connected load of 12 lamps each of 100 W at his/ her premises.
His/ her load demand is as follows:
From midnight to 5 AM : 200 W
5 AM to 6 PM : no load
6 PM to 7 PM. : 700 W
7 PM to 9 PM : 1,000 W
9 PM to midnight : 500 W
Draw the load curve and calculate the (i) energy consumption during 24 hours, (ii)
average load, (iii) demand factor, (iv) maximum demand, and (v) load factor.
Power System Operation and Control
Unit 1 ~ Introduction
Solution:
From Fig. 1.6,
1. Electrical energy consumption during the day = area of load curve
= 200 × 5 + 700 × 1 + 1,000 × 2 + 500 × 3 = 5,200 Wh = 5.2 kWh
2. Average load
3. Demand factor
4. Maximum demand = 1,000 W
5. Load factor
Fig 1.6: Load curve
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.11:
Calculate the diversity factor and the annual load factor of a generating station,
which supplies loads to various consumers as follows:
Industrial consumer = 2,000 kW;
Commercial establishment = 1,000 kW
Domestic power = 200 kW;
Domestic light = 500 kW
and assume that the maximum demand on the station is 3,000 kW, and the
number of units produced per year is 50×105.
Power System Operation and Control
Unit 1 ~ Introduction
Solution:
Average demand
Load factor
Power System Operation and Control
Unit 1 ~ Introduction
Example 1.12:
Calculate the reserve capacity of a generating station, which has a maximum
demand of 20,000 kW, the annual load factor is 65%, and the capacity factor is 45 %.
Solution:
Maximum demand = 20,000 kW
Annual load factor = 65%
Capacity factor = 45%
Energy generated/annum = maximum demand LF hours in a year
= (20,000) × (0.65) × (8,760) kWh = 113.88 × 106 kWh
Power System Operation and Control
Unit 1 ~ Introduction
Capacity factor
Hence,
Plant capacity
Example 1.13: The maximum demand on a power station is 600 MW, the annual load
factor is 60%, and the capacity factor is 45%. Find the reserve capacity of the plant.
Solution:
Example 1.14: A power station’s maximum demand is 50 MW, the capacity factor is 0.6,
and the utilization factor is 0.85. Calculate the following: (i) annual energy produced
and (ii) reserve capacity.
Solution:
Example 1.15: A power station is to feed four regions of load whose peak loads are 12,
7, 10, and 8 MW. The diversity factor at the station is 1.4 and the average annual load
factor is 65%. Determine the following: (i) maximum demand on the station, (ii) annual
energy supplied by the station, and (iii) suggest the installed capacity.
Solution:
Energy generated per annum = maximum demand × load factor × hours in a year
= 50 × 0.7058 × 8,760 = 309,228 MWh
Example 1.15: A power station is to feed four regions of load whose peak loads are 12, 7,
10, and 8 MW. The diversity factor at the station is 1.4 and the average annual load factor
is 65%. Determine the following: (i) maximum demand on the station, (ii) annual energy
supplied by the station, and (iii) suggest the installed capacity.
Solution:
(i)
(ii) Units generated/annum = max. demand × LF × hours (year) = 26.43 × 0.65 × 8,760 = 150,492.42 MWh
(iii) The installed capacity of the station should be 15% to 20% more than the maximum demand in order to
meet the future growth of load. Taking the installed capacity to be 20% more than the maximum
demand, suggested installed capacity = 1.2 × max. Demand = 1.2 × 26.43 = 31.716 ≅ 32 MW