01 Bldgconst1
01 Bldgconst1
01 Bldgconst1
Construction
BUILDING
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
Pavements
CONSTRUCTION
2. Measure the required side setback from one of the side lot lines
along the front building line. Drive stake A which will represent the
first corner of the building. From Stake A, measure the width of the
building and mark with stake B to obtain the other front corner.
4. Draw lines along the diagonals A-D and B-C and ensure that
these are equal.
Batter Boards – wood sticks or boards nailed horizontally at the stake which serve as the horizontal plane where the reference
point of the building measurements are established.
Preparation for
Construction 1.0
3. STEEL FORMS
• may be in the form of pans for concrete
joist construction or steel decking or
corrugated steel for concrete slabs and
slab-and-joist construction.
4. FIBER BOARDS
5. PHENOLIC BOARDS
Phenolic resin or phenol-formaldehyde resin –
is a thermosetting, waterproof, low-cost, mold-resistant, high
strength synthetic resin made from phenol and formaldehyde;
has good resistance to aging; used extensively in the
manufacture of adhesives, exterior and marine plywood,
laminated products, and molded articles.
Preparation for
Construction 1.0
Single Post
Wood Shore
Sills
Preparation for
Construction 1.0
COLUMN FORMS
Staking-Out the Building WOOD FORMWORKS
Laying the Batterboards
Formwork & Shoring 1.3
Reusable forms may have a
Construction Tools & square or rectangular cross
Equipment section
Major Parts of a Building
Foundation Bed YOKES are clamping devices
Site Investigation
Soil mechanics
for keeping column forms and
Excavation & Earthworking tops of wall forms from
Site Drainage spreading under the fluid
Slope Protection and pressure of newly placed
Retaining Structures
Pavements concrete
WALL FORMS
SPREADERS usually of wood,
space and keep the wall or
forms apart
FORM TIES
PLYWOOD SHEATHING
HORIZONTAL WALERS
WOOD STUDS
SILL PLATE
BRACING
Preparation for
Construction 1.0
Ledgers
Adjustable
Braces
Fixed Braces
Preparation for
Construction 1.0
4. Position scaffold boards and ladders. 5. Additional ledgers and braces 6. Once all levels are complete,
can now be added, with additional jacks and heads can now be
braces. positioned.
7. Jack head levels finalized and any jack 8. Primary beams can be 9. Secondary beams can be
bracing required is now fitted. positioned, clamped and levels positioned and clamped to primary
checked. beams, plywood decking to follow.
Preparation for
Construction 1.0
Concrete pump.
Water pump.
Preparation for
Construction 1.0 Concrete Mixer (Cement Mixer)
Staking-Out the Building
Laying the Batterboards A machine that mixes concrete
Formwork & Shoring ingredients by means of a rotating
Construction Tools &
Equipment 1.4 drum. Raw materials are introduced
Major Parts of a Building into the mixing drum through its open
Foundation Bed
Site Investigation
end and discharged by tilting the
Soil mechanics mixing drum to allow the concrete to
Excavation & Earthworking
Site Drainage pour out.
Slope Protection and
Retaining Structures
Pavements
Types of welding
machines are the b. Laser-powered welder is
following: used to weld material by
employing a laser to heat the
a. Arc welding metal.
machine is used
to weld materials
by melting portions
of the metal.
Bulldozer.
Front-end loader.
Preparation for
Construction 1.0
Highway construction equipment
Staking-Out the Building are:
Laying the Batterboards
Formwork & Shoring
Construction Tools & a. Scraper is a machine that loads,
Equipment 1.4
Major Parts of a Building hauls and dumps soil over medium
Foundation Bed to long distances.
Site Investigation Scraper.
Soil mechanics
Excavation & Earthworking b. Grader is an earthworking
Site Drainage
Slope Protection and
machine that grades or levels the
Retaining Structures ground.
Pavements
c. Compactor or roller is a
machine that compacts soil to
prepare for road paving. Grader.
Compactor
Preparation for
Construction 1.0
Foundation Bed 1.6 building foundation which forms the FOUNDATION WALLS
Site Investigation
Soil mechanics
permanent retaining wall of the
Excavation & Earthworking structure below grade.
Site Drainage
Slope Protection and CONCRETE MASONRY
Retaining Structures Foundation piers/columns – FOUNDATION WALLS
Pavements piers/columns below grade, to
distinguish them from similar
construction above grade
FOUNDATION WALL
Preparation for
Construction 1.0
1.6.1 TYPES OF FOUNDATION BEDS
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Foundation beds may be classified as follows:
Equipment
Major Parts of a Building
Foundation Bed 1.6
Site Investigation 1. Rock (solid rock, bedrock or ledge). Undisturbed rock masses forming an
Soil mechanics undisturbed part of the original rock-formation. Some examples of harder rocks
Excavation & Earthworking
Site Drainage are granite, slate, sandstone, and limestone which are all capable of carrying
Slope Protection and the load of any ordinary structure. Examples of softer rocks are shale, shaley
Retaining Structures slates and certain marley limestone and clay stones.
Pavements
2. Decayed rock (rotten rock). Sand, clays and other materials resulting from
the disintegration of rock masses, lacking the coherent qualities but occupying
the space formerly occupied by the original rock.
3. Loose rock. Rock masses detached from the ledge of which they originally
formed a part.
5. Boulders. Detached rock masses larger than gravel, generally rounded and
worn as a result of having been transported by water a considerable distance
from the ledges of which they originally formed a part.
Preparation for
Construction 1.0
10. Mud. Finely divided earthy material generally containing vegetable matter and
deposited from still or slowly moving water.
11. Mould. Earthy material containing a large proportion of humus or vegetable matter.
14. Filled Ground. All artificial fills and some natural fills are liable to a more or less
uniform but continuous settlement or shrinkage due to the gradual consolidation of the
material of which the fill is composed
Preparation for
Construction 1.0
B. Fine-grained soil –
consist of much smaller
particles, such as silt and clay.
Preparation for
Construction 1.0
WATER TABLE
AFTER PUMPING
Preparation for
Construction 1.0
A. SUB-SURFACE DRAINAGE –
consists of an underground network of piping for conveying groundwater
to a point of disposal, as a storm sewer system or a natural outfall at a
lower elevation on the site. Excess groundwater can reduce the load-
carrying capacity of a foundation soil and increase the hydrostatic
pressure on a building foundation. Waterproofing is required for basement
structures situated close to or below the water table of a site.
Preparation for
Construction 1.0 Components of the sub-surface drainage system are:
Staking-Out the Building
Laying the Batterboards Catch Basins
Formwork & Shoring receptacles for the runoff of SWALES
Construction Tools &
Equipment
surface water. They have a basin
Major Parts of a Building or sump that retains heavy
Foundation Bed
Site Investigation
sediment before it can pass into
Soil mechanics an underground drainpipe. AREA DRAIN
Excavation & Earthworking
Site Drainage 1.10
Slope Protection and Culverts
Retaining Structures are drains or channels passing under
Pavements
a road or walkway.
CATCH BASINS
Drainage tile
is a hollow tile, usually laid end to end
as piping (with open joints) in soil in
order to drain water saturated soil, or
CATCHMENTS
used to permit fluid in the hollow-tile
pipe to disperse into the ground (as in
an absorption field).
Preparation for
Construction 1.0
Swales
shallow depressions formed by the
intersection of two ground slopes,
designed to direct or divert the runoff
of surface water. Grass swales slope
1.5% to 2%; while paved swales, 4%
to 6%.
SWALES
Preparation for
Construction 1.0
0.5 H
Preparation for
Construction 1.0
b) T-type Cantilevered Retaining Wall – limited to a height of
Staking-Out the Building
Laying the Batterboards 20’ (6 M); beyond this height a counterfort wall is employed.
Formwork & Shoring
Construction Tools &
8” (205)
Equipment Batter refers to backward
Major Parts of a Building sloping face of a wall as it
Foundation Bed
Site Investigation
rises to offset illusion of face
Soil mechanics leaning forward
Excavation & Earthworking
Site Drainage Temperature steel for walls
Slope Protection and
Retaining Structures 1.11 more than 10” (255) thick
Pavements
Drainage mat w/ filter fabric
0.6H or porous gravel backfill
(0.9H w/ surcharge)
2” (51 mm) o weepholes @
4’-6’ (1220-1830mm) o.c. or
perforated drainpipe sloped
to outlet away from wall
2” (51) min
3” (75) min
Structural Steel
reinforcement
0.7H
(1.25 w/ surcharge)
0.6H
(1.0 w/ surcharge)
Preparation for
Construction 1.0
BUILDING
Staking-Out the Building
Laying the Batterboards
CONSTRUCTION
Formwork & Shoring
Construction Tools &
1 Equipment
Major Parts of a Building
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
Pavements
END