Coal Mill
Coal Mill
Coal Mill
• Coal Mills are used to grind the coal into fine particles before placing into a boiler, to ensure
efficient combustion. The coal is fed into the coal mill through a central inlet pipe where gravity is
used to lead the coal to the bottom of the mill, where the grinding table pulverizes the coal to
particles. The primary air flow to the furnace is fed through the mill, with the purpose of heating and
lift the coal particles into the funace. If the particles are too heavy they will drop to the bottom of the
mill and will be pulverized once more.
• Functions:
• The main functions of coal mill are as follows.
I. Pulverization
II. Drying
III. Classification
Bowl Mill
• Bowl mills are employed to pulverize the pre-crushed raw coal to the required fineness before it is
admitted into the boiler furnace for combustion. The mill output can be easily varied, as per the
turndown ratio from its minimum to maximum load and it will operate for long periods without
mechanical problems or stoppages for cleaning, oiling or adjusting. Crushed raw coal at a controlled
rate is fed into the revolving bowl of the Bowl Mill. Centrifugal force feeds the coal uniformly over the
replaceable grinding ring where independently spun rolls exert the required grinding pressure. The
rolls do not touch the grinding ring even when the mill is empty.
• This mill is designated as XRP 1003 Bowl Mill where
• X – 3 Phase, 50 Hz Supply,
• R – Raymond (Inventor of the mill),
• P – Pressurized,
• 100 – Nominal dia. of the Bowl (inches)
• 3 – Number of the Grinding Rolls.
PLANETARY GEAR BOX AND BOWL HUB ASSEMBLY
Oil Seal
Bearings
Seal air port
Page 11
MILL DISCHARGE VALVE ASSEMBLY
The mill discharge valve assembly consists of four
multiport outlet and mill discharge valves mounted
on the multiport outlet plate. Air cylinders operate
the flaps in the mill discharge valves. Solenoid
valves and limit switches are provided to effect
and indicate the open or close position of the flap.
This assembly does the distribution of pulverised
fuel into four pipes and also it isolates the mill from
boiler when required.
Animation
Coal Feeder
• Coal Feeder is one equipment that regulates the amount of coal to supplied into the coal mill.
• The amount of coal is regulated according to the needs in the boiler combustion
• The number regulation system in the coal feeder can be done in two ways based on the type,
namely by weight fraction(Gravimetric) or coal volume fraction(Volumetric)
Page 13
MILL INTERLOCKS AND PROTECTIONS
COAL MILL START PERMISSIVES:
A
No MFT N permit
D
Any Feeder Proven(A to F) O
Any oil in service(AB,CD,EF) R
back
Page 16
PLOS Healthy:
back
PA fan permit available or any mill on:
Pulveriser on
0
PA air permit available: R PA fan/mill on permit
PA Hdr pressure not v low 2/3, 500 mmwc A
N
5 sec
PA Hdr pressure not low 2/3, 625 mmwc D
back
18
Ignition permit available
A
N
Boiler Load > 30% D
19
Steam Inerting Completed or Disable
back
20
MILL TRIP CONDITIONS:
• MFT
• Trip From PLOS
• Pulveriser discharge vlv not open
• Ignition energy required not available
• Electrical trip
• Pulveriser Seal air Hdr pressure DP low < 200mmwc, 1min (1/2)
• Burner Isolation gate not open
• Loss of Primary air <625 mmwc 5 sec (or) < 500 mmwc (or) PA/FD trip
• Pulveriser start fail
• HAG closed / CAG not open
• Pulveriser Bearing temp v.high > 80 °C
• Pulveriser winding temp V.high > 85 °C
Coal Feeder
• Pulveriser trip from inerting
PLOS Fail
Both LOP Not On
LO Temp Aft CLR V Hi >65°C 1/2
GB/IP Shaft Temp V Hi >85°C 1/2 O
R
Any Pump On & Lo Pressure Aft CLR V LOW 0.5bar, 1 sec
Page 22
Trip from PLOS
back
23
Ignition Energy Required, not available
back
25
COAL FEEDER INTERLOCKS AND PROTECTIONS
No MFT
Feeder in remote
A Feeder start
Pulveriser on
N
FDR Seal air valve open D
Pulveriser off
No coal flow trip:
Pulveriser current low <52 amps A
FDR no coal on belt N
D
27
28
PRE OPERATIONAL CHECKS
Coal feeder line – up
• No PTW is pending.
• Feeder front and rear doors are closed.
• Check sufficient coal in bunker.
• Ensure Bunker outlet gate power supply on and gate open.
• Ensure bunker rod gate open
• Ensure feeder inlet gate open
• Bunker emptying pipe is dummied
• Ensure Feeder Seal air valve open condition
• Feeder module is ON and Feeder selection is in Remote (on feeder panel).
• Clean out conveyor is in ON position. (On feeder panel)
Coal Mill line – up
• No PTW is pending
• All inspection doors are closed
• Following are lined up with Instrument Air: MDV, HAG, HAD, CAG, CAD and Tramp iron valve
& Outlet Gate, Mill SAG
• Ensure PA Fan and Seal air fan are running normal.
• Open Mill seal air damper and ensure Seal air DP > 700mmWC
• Fire Fighting steam MOV power supply ON
• Ensure HAG,CAG,HAD,CAD is closed condition in Local and ensure closed feedback
received in DCS.
• Ensure burner inlet gates open (4Nos) and feedback showing in DCS
• Ensure Mill motor EPB released condition
• Line up any one of lube oil filter
• Open lube oil cooler DMCW inlet & outlet MIVs
• Ensure mill lube oil motor supply is healthy.
• Start Electric heater & ensure it automatically cut off at 40 C
• If lube oil temp > 30oC then start lube oil pump and ensure lube oil pressure > 2 kg/cm2 and
flow >120 Lpm
• Keep another LOP in standby mode
START UP PROCEDURE
• Ensure all Four MDV’s are opened
• Ensure lube oil flow(>120lpm) and pressure > 1.5 bar & second pump in interlock
• Give open command for CAG and ensure gate is opening in local.
• After CAG open feedback received open CAD gradually to 100 % by maintaining PA Header pressure.
Ensure CAD is fully opened in local.
• Ensure mill pyrite hopper inlet valve open and outlet valve is closed
• Ensure mill start permissive is available
• Ensure SADC fuel air damper in AUTO or else open manually > 20% for respective coal mill.
• Start Coal mill and monitor motor current, mill parameters are normal.
• Inform field operator to check for any abnormalities in local.
• Give open command for HAG and ensure gate is opening in local.
• Gradually open HAD and close CAD to maintain PA flow about 95 TPH and mill outlet temperature as 55⁰C.
• Open coal feeder Outlet gate and ensure gate is opening in local.
• Ensure mill outlet temp around 55⁰C before feeding coal
START UP PROCUDURE
Mill Fire
1. High Mill outlet Temperature - Do not exceed mill o/l temp. recommend as per
volatile matter content in coal.
2. Coal settlement in mill - Do not leave coal in idle mill. Remove the coal either
manually or taking the mill in service.
3. Rapid change in moisture content of coal - Keep a close watch at mill outlet temperature.
4. Putting burning coal in mill - Empty the bunker and remove smoldering coal.
Trouble Shooting
Mill Coal spillage High
1. Over feeding - Reduce feeder speed/ coal feed to mill
2. Insufficient primary air flow - Correct the primary air flow quantity.
3. Jamming of rolls - Service the bearings and oil seals
4. Low Mill outlet temperature - Reduce Cold air, increase hot air supply.
Reduce feeder s feed/coal feed to mill.
5. Worn grinding roll - Replace roll/or Ring and adjustment.
6. Classifier set for higher fineness - Reset classifier Blades towards open position.
Possible reason.
• Operator ensured steam quenching as per normal operation procedure (i.e., ensuring water leaving the
reject hopper). However ,it might be not enough to quench amount of combustible gases present in the
system.
Remedial measures for future
• Steam quenching time to be increased but at the same time operator should not allow roller
temperature/ mill outlet temperature to raise in addition to the normal practice of ensuring water leaving
the reject hopper.
• Keep the furnace pressure around -150pascal while taking mill
• HEI supplied CO monitoring system to be installed & commissioned with support of WOM.
Yo u
a n k
Th