Professional Documents
Culture Documents
Project Report
Project Report
MEDAK – 502110
A Project Report
On
“CONSTRUCTION OF 2BHK RESEDENTIAL BUILDING
(INDUSTRIAL TRAINING)”
Submitted for partial fulfilment of the requirements for the
award of students
DIPLOMA
IN
CIVIL ENGINEERING (FINAL YEAR)
BY
D.POOJA REDDY (18069-C-010)
S.ANUSHA (18069-C-033)
Under the guidance of
Mrs. M. VASANTHA
S .L. In civil
Department of Civil Engineering
GPW, Medak
CERTIFICATE
Internal Examiner
ACKNOWLEDGEMENTS
Disadvantages Of Formwork :
• Limited size or shape.
• Excessive loss of heat.
• A very smooth surface will be produced which would
give problems for finishing process.
5.5. Order and method of removing of formwork :
1.Shuttering forming vertical faces of walls, beams and
column sides which bear no load but are used only to
retain. The concrete should be removed first.
2.Shuttering forming soffit to slabs should
be removed next.
3.Shuttering forming soffit of beams, girders or other
heavily loaded shuttering should be removed in the
end.
6. Columns.
6.1. A column is a vertical member which effectively
takes load by compression. Column transfers the load
of the structure of slabs beams above to below, and
finally load is transferred to the soil. Position of the
columns should be so that there are no tensile stresses
developed at the cross section of the columns.
Columns location should be such that it hides in the
walls partially or fully.
6.2. RCC columns are mainly constructed in four
different stages. which are :
1. Column layouts
2. Column reinforcement work
3. Column formwork
4. Pouring of concrete
1. Column layouts : Column layout work In this stage
of works the location of columns are determined
practically in field. It is done by laying rope according to
grids shown in the drawing and then mark the location
of columns related to rope.
2. Column reinforcement work : After marking the
column locations, we then start to place reinforcement
as instructed in the structural drawing.