KOM For Instrumentation FOC
KOM For Instrumentation FOC
KOM For Instrumentation FOC
2
1. Kick-Off Meeting Purpose & Objectives
1.2 Objectives
The Objective is to describe the scope of work & provide the specific guidelines for
executing the works.
1.3 Scope
This Kick-off Meeting does covers only the Instrumentation and Process Control
System(PCS) Fiber Optic Cable Installation, Termination/Splicing and Testing, and
does not covers the FOC for Telecommunications and Electrical.
3
2. Introduction to Fiber Optic
12
4. Construction Plan
4.2 Mobilization
Foreman/Supervisor - 1 No.
Helper - 01 No.
13
5. Reference Standards & Drawings
5.1 Saudi Aramco Standards
Document No. Document Title
18-SAMSS-625 Outside Plant - Fiber Optic Cable Specifications (Single-Mode and Multi-Mode)
SAES-T-632 Telecommunications: Splicing Copper Cables, Fiber Optic Cables, and Types of Splice Closure
SAES-Z-020 Design and Installation of Fiber Optic Cable Systems for Process Control Network
14
5. Reference Standards& Drawings
5.2 International Standards
Document No. Document Title
ANSI American National Standard Institute
15
5. Reference Standards & Drawings
5.3 Reference Drawings
Document No. Document Title Remarks
Method Statement For Fiber Optic Cable Installation,
JUS&ICS-CI-PD-7010 Approved
Termination/Splicing and Testing For Instrumentation
16
6. Reference Quality Requirements & SATIP/SAIC/SATR
6.1 SCHEDULE Q Requirements
17
6. Reference Quality Requirements & SATIP/SAIC/SATR
6.2 Saudi Aramco Typical Inspection Plan(SATIP)
Document No. Document Title
SATIP-T-911-01 Underground Conduit System (Duct bank and Manhole)
SATIP-T-624-01
Fiber Optic Communications Cable (OSP/ISP/CO)
18
6. Reference Quality Requirements & SATIP/SAIC/SATR
6.3 Saudi Aramco Test Report (SATR)/Inspection Checklist(SAIC)
Document No. Document Title
SAIC-T-5501 Fiber Optic Cable and Accessories Storage, Handling, and Preservation
Visual Inspection
SAIC-T-5401 Fiber Optic Cable Material Receiving Visual Inspection
OSP Single-mode Fiber Optic Cable
SAIC-T-5405 Cable Splicing Accessories Material Receiving Visual Inspection
Fiber Optic Splicing Accessories
SAIC-T-5709 Jobsite Fabricated Duct banks, Manholes, and Handholes Initial Mandrel Test and
Visual Inspection Duct bank Initial T&I
SAIC-T-5506 Warning Tape Installation Visual Inspection, OSP Duct bank Backfilling
Testing and Visual Inspection
SAIC-T-5711 Innerduct Pulling Visual Inspection
SAIC-T-5712 Innerduct and Conduit Identification and Termination Visual Inspection
SAIC-J-6624 Cable Pulling Visual Inspection
SAIC-T-5408 Fiber Optic cable Underground and Direct buried installation, splicing, dressing,
identification and termination Visual inspection.
SATR-J-6621 Fiber Optic Cable Testing (Installed Cable)
19
7. Work Procedures & Requirements
20
7. Work Procedures & Requirements
7.1 General Requirements
1. All related design drawings must be stamped by the RCDD before the package can be issued for
Construction (IFC). (PCS only)
3. Conduits shall be single bore, plastic (PVC) NEMA TC 8, Type DB or EB. Same type of conduits
should be placed on any specific conduit section.
4. A maximum of equivalent two 90° bends are permitted in each section of the conduit runs. The
minimum bend radius of the conduits shall be 36˝. (PCS only)
5. All underground conduit systems in plant areas shall be concrete encased for mechanical
protection with non-structural concrete. (PCS only)
6. In plant areas, where vehicular traffic loads is expected, conduits should be located at least 760 mm
(30˝) below surface grade. Plant areas, where vehicular traffic load is unlikely, conduits should be
located at least 610 mm (24˝) below surface grade.
7. An “orange color” – detectable warning tape shall be placed above the conduit concrete
encasement to provide early warning. The tape shall be located at a minimum of 300 mm above the
upper surface of the conduit system.
21
7. Work Procedures & Requirements
7.2 Fiber Optic Cable Installation
1. When redundant data links are provided, the primary cable shall follow a different route
from the back up cable. (PCS only)
3. The pulling tension on fiber optic cables shall not exceed 600 pounds unless greater
pulling tensions are specifically approved by the cable manufacturer. When fiber optic
cable is pulled, it shall be pulled in a straight line. The cable shall never be bent or
wrapped around the hand or any other object as it is pulled. Only vendor-approved
equipment or methods shall be used.
5. Outdoor fiber optic cables (non-fire rated) shall not be run exposed for more than 15 m
(50.0 ft) within a building. If more than 15.2 m (50.0 ft) of cable is required between the
building entrance point and the cable termination point.
22
7. Work Procedures & Requirements
7.3 Fiber Optic Cable Termination / Splicing & Testing
1. Only approved FO Cable Splicer (with valid JCC) shall perform the termination or splicing of
Fiber Optic Cables
2. Only the ST and SC type connectors shall be used to terminate optical fiber cable.
(PCS only)
23
7. Work Procedures & Requirements
7.3 Fiber Optic Cable Termination & Testing
Testing Requirements
Acceptance testing requirements for fiber optic cables shall comply the requirements stated
in the table below, and three (3) basic tests
2 End-to-End Loss (typically 100% of fibers in both directions, and 100% of fiber splices and con-
conducted after completion of nections; (individual splice loss shall not exceed the following limits;
installation and splicing, also The maximum attenuation of each fiber within a cable, when normal-
before installation of terminal ized to a length of 1 km:
equipment’s using a) At wavelength = 1,300 nm, shall be 0.5 dB/km or less, and
OTDR). b) At wavelength = 1,550 nm, shall be 0.3 dB/km or less.
c) Individual splice insertion loss shall be 0.05 dB average link splice
loss with no single splice loss above 0.1 dB for fusion splices, and
0.1 dB average link splice loss with no single splice loss above
0.2 dB for mechanical splices;
d) Connectors shall have insertion losses of 0.5 dB or less).
3 Measuring Power (Power This measurement is the basis for loss measurements as well as
Meter Test) the power from a source or presented at a receiver.
24
7. Work Procedures & Requirements
7.3 Fiber Optic Cable Termination & Testing
25
8. Lessons and Learned
Outdoor fiber optic cables (non-fire rated) had been run exposed for
more than 15 m (50.0 ft) within a building. This is violation against
SAES-Z-020, para. 6.10.2
Cable Testing after Pulling Fails due to suspected Hard objects Hitting
the cable Area
26
9. Q & A
27
감사합니다 !
Thank you!
28