TRANSFORMER @ BPS1
PROJECT 2021-0395
June 15, 2023 – Weekly Meeting
Proposed Catch Basin in Bundwall
4-MVA TRANSFORMER BUNDWALL CONCERN
BUNDWALL CATCH BASIN
4-MVA TRANSFORMER PROJECT STATUS
SITE ACCEPTANCE TEST STATUS
1. MVSG (34.5KV) (VCB, CT, PT, LA, Protection Relay & Bus bar)
a. CT IR, Windings, Ratio Test – Done (Passed: March 8 & 28, 2023)
b. Lightning Arrester Insulation Resistance Test– Done (Passed: 3/28/23)
c. PT Insulation & Windings Test and Ratio Test – Done (Passed: 3/29/23)
d. Protection Relay Test (Software for Setting) – Done (Passed: May 5, 2023)
e. VCB IR, Contact Resistance, & Contact Timing Test – Done (Passed: May 4, 2023)
f. Bus bar Hi-pot Test – Done (Passed – May 10, 2023)
2. MVSG2 (2.4KV) (VCB, CT, PT, LA, Protection Relay & Busbar)
a. CT IR, Windings, Ratio Test – Done (Passed: March 8 & 28, 2023)
b. Lightning Arrester Insulation Resistance Test– Done (Passed: 3/28/23)
c. PT Insulation & Windings Test and Ratio Test – Done (Passed: 4/14/2023)
d. Protection Relay Test ((Software for Setting) - Done (Passed: May 18, 2023)
e. VCB IR, Contact Resistance, & Contact Timing Test - Done (Passed: May 4, 2023)
f. Bus bar Hi-pot Test (RAMP Needed for Testing)
3. Grounding Protection System Test – done (Passed: 3/29/23-Wed)
4. Cables Insulation Resistance Test & High Potential Test
a. Service Pole to 34.5kv MVSG1 Incoming Line – Done (Passed-3/28/23-Tuesday)
b. 34.5kv MVSG1 Outgoing Line to Transformer Primary Line – (IR Passed-4/26/23)
c. Transformer Secondary Line to 2.4kv MVSG2 Incoming Line - (IR Passed-4/26/23) Hi-pot (passed:
May 22, 2023)
d. 2.4kv MVSG Outgoing Line to MCC Panel Incoming Line - (IR Passed-4/26/23) Hi-pot (passed: May
18)
5. SF6 LBS – (April 26, 2023) Retest (Passed: May 18, 2023)
6. NGR Test – Done (Passed: May 4, 2023)
7. 4MVA Transformer – SAT Done – (Passed May 4&5, 2023)