HSE-BMS-011 Crane & Lifting Safety
HSE-BMS-011 Crane & Lifting Safety
HSE-BMS-011 Crane & Lifting Safety
• Overturns
• Falls
• Mechanical failures
2
How Do Accidents Occur?
• Lack of communication - the
point of operation is far
distance from the crane
operator or not in full view of
the operator
• Lack of training
• Inadequate maintenance or
inspection
3
Crane Hazards
• Improper load rating • Working too close to
power lines
• Excessive speeds
• Safety equipment not
• No proper hand functioning properly
signals
• Shattered windows
• Inadequate
inspection and • No steps/guardrails
maintenance walkways
• Unguarded parts • No / Damaged boom
angle indicator
• Unguarded swing
radius • Not using / improper
outriggers pad
4
Crane Hazards
5
Planning Before Start-Up
• Level the crane and ensure support surface is firm and
able to support the load
• Contact power line owners and determine precautions.
Know the location and voltage of overhead power lines.
• Know the basic crane capacities, limitations, and job site
restrictions, such as the location of power lines, unstable
soil, or high winds.
• Make other personnel aware of hoisting activities.
• Barricade areas within swing radius.
• Ensure proper maintenance and inspections.
• Determine safe areas to unload the materials or actual
place of erection.
6
Competent Person
Is a person capable of
assessing and planning a lift,
selecting, inspecting, installing
the lifting equipment and
accessories, and completing
the necessary documentation.
8
Crane and its Operator
All operators must be trained and conversant with the
following;
1. The safe operation of the machine
2. Location and operation of all safety back up systems
3. Reading and understanding of the load chart
4. Capabilities of the machine in all unusual circumstances
5. Any peculiarities pertaining to the machine
6. No operator will be permitted to operate a machine for
which he is not trained (Except he is giving adequate
training on the machine)
7. Crane key should not be left by the operator whenever he
leave the crane cabin
8. Operator should not leave the crane with the still load
hanging or not yet fixed
9
What to Inspect?
Correct air pressure and no
leaks
Tires properly inflated
Clearance for tail swing
Wire rope wear
Physical damage to crane
Loose or missing hardware,
nuts, or bolts
Fluid leaks
Others as per Crane Check
List
10
Damaged Wire Rope
Crushed Rope
Broken Strands
11
Damaged Web Sling
13
Load Moment Indicator
Refer to shipping ticket or
other documentation
Ensure lift calculations are
correct
Ensure load is within load
chart rating for boom length
and load radius of crane
Crane is rated by the
maximum weight it will lift at
a minimum radius and
minimum boom length – the
further from its centerpoint,
the less it will lift
14
Load Limiting Factors
Not level
Wind
Side loads
On its wheels
Lifting over the side
Use of extensions, jibs and
other attachments
Limits of wire rope, slings
and lifting devices
15
Cranes Lifting Principles
Center of Gravity
Leverage
Stability
Structural
Integrity
16
Load Example – 30 ton crane
Will lift 30tons at 3m from the center pin of the
crane
Based on level surface, no wind, and outriggers
fully extended
At 7.5m from the center pin with a 25m boom
length, the capacity is only 6.8tons
At 22.5m from the center pin, the capacity is
only 2tons
17
Improper Slinging/computation of load
20
Lifting Plan
Lifting plan must include as a minimum;
Position of item to be lifted and lifting equipment (Pick up and
set down)
Weight and configuration of item to be lifted
Radius of lift
Calculated capacity of lifting equipment at all stages (Load chart
attached)
Details of lifting equipment (shackles, lifting beams etc)
Lifting restrictions
Ground loads
21
Rigging Requirements
All sling or steel wire shall be
kept in good condition
Damage wire rope or any lifting
gears must be discarded
immediately
All rigging equipment must have
a valid test certificate
All rigging gear must be
inspected and records of
inspections kept (Competent
person and color code)
22
Quarterly Color Coding
JANUARY JULY
APRIL
AUGUST OCTOBER
FEBRUARY MAY
MARCH SEPTEMBER NOVEMBER
JUNE
DECEMBER
23
Hand Signal
An illustration of the
signals must be
posted at the job site.
This standard signal
shall be used by the
rigger and must be
clearly understood by
the crane operator
24
Barricade Affected Area
26
Rigging and Slinging
Use “Tag Lines” on
ALL lifts
27
Rigging and Slinging
Use “Choker Hitch”
on loose material
28
Rigging and Slinging
Use “Dunnage” and
“Wedges” for stacking
29
Rigging and Slinging
30
Rigging and Slinging
31
Rigging and Slinging
Secure the block to the
anchor point on the crane
Sheaves will
be damaged
32
Rigging and Slinging
Sling angle must
be <90
Max.90
90O
MAX
33
Rigging and Slinging
ALL hooks must have
safety latches
34
Rigging and Slinging
Use softener to
protect the slings
35
Rigging and Slinging
36
Rigging and Slinging
Do NOT overcrowd a
hook – use a shackle
37
Rigging and Slinging
39
Rigging and Slinging
Demarcate
affected
lifting areas
40
Rigging and Slinging
42
Rigging and Slinging
Required personnel
during Crane lifting:
-Crane Operator
-Rigger / Slinger
-Rigger /Signal man
43
Rigging and Slinging
44
Rigging and Slinging
45
Battening Down
It is sometimes imagined that
slings in choke hitch can be
made more secure by striking
the eye of a sling in an attempt
to force the bight into closer
contact with the load.
This dangerous
malpractice is often called
“battening down”.
The bight should be
allowed to assume its natural
angle which will be about 120° NATURAL ANGLE 120º
46
Man Basket Operation
Permit must be obtained prior to any
Man Basket Operation and the
following conditions must be met;
•Only approved Man basket is to be
used for lifting personnel by a crane
•Crane must have positive drive up
and down
•Crane must be equipped with a
functional anti two block device
•Crane must not operate outside of a
radius that reduces the cranes
capacity by more than 50%
•All shackle pins must be well secured
•Additional sling must attach to the
headache ball as a lifeline
47
Man Basket Operation
•The man-cage must not be
used to lift personnel and
material at the same time
•Only two persons are to be
lifted in the Man basket
•All personnel must wear full
body harness
•All signal must be given by a
qualified rigger identified by a
jacket
48
Man Basket Operation
• Man-basket permit will be
valid only for one operation
• A trial lift will be first
conducted prior to actual man
basket operation
• Once basket is lifted
personnel are not allowed to
climb in or out of it
49
Summary
An unstable load,
lack of
communication, lack
of training, and
inadequate
maintenance or
inspection are major
contributors to crane
accidents.
50
Summary
51