Super Critical Boiler Technology SKD
Super Critical Boiler Technology SKD
Super Critical Boiler Technology SKD
Necessity of Supercritical Boilers. Measures to improve plant efficiency. Necessity of higher temperatures. Material constraints and innovations. Advantages of forced circulation. Types of supercritical boiler construction.
Supercritical cycle 1-2 - Feedwater pumping/heating 2-3 - Feedwaterheating / superheating 3-4 - Turbine expansion
Subcritical cycle
3 2 2 1 1 4 6 4
1-2 - Feedwater pumping/heating 2-3 - Feedwater heating 3-4 - Evaporation ( Latent heat addition) 4-5 - Superheat
SUPERCRITICAL BOILER TECHNOLOGY THERE ARE TWO TYPES OF TECHNOLOGIES. 1)BENSON TECHNOLOGY-- ADOPTED BY SIEMENS GERMANY 2)SULZER TECHNOLOGY-- ADOPTED BY ABB SWITZERLAND, MHI, ALSTOM
I ) Higher cycle efficiency means Primarily less fuel consumption less per MW infrastructure investments, also less emission less auxiliary power consumption less water consumption II ) Operational flexibility Better temp. control and load change flexibility Shorter start-up time Suitable for variable pressure operation
COAL SAVING ( T/YR) CO2 REDUCTION (T/YR) SO2 REDUCTION ( T/YR) CYCLE EFFICIENCY (% )
Item
Generator Output Steam Pressure Steam Temperature Boiler Efficiency Plant efficiency Coal Consumption Coal Consumption difference Co2 Generation Co2 Generation difference
Supercritical
500 246 538/538 566/566 87.31 + 1.6 -13.7 87.31 + 3.8 -27.8
-11,033 -225,351
Description
Turbine Heat rate Boiler efficiency Plant heat rate Coal consumption Ash Generation CO2 SO2
Unit
kCal / kWh % kCal / kWh MM T/Annum MM T/Annum MM T/Annum MM T/Annum
Subcritical
1936 87 % 2225 4.068 1.627 7.371 0.0492
Supercritical
1835 87% 2109 3.856 1.542 6.986 0.0466
Reduction
101 (5.22%) 0 101 (5.22%) 0.212 0.085 0.385 0.003
INITIAL INVESTMENT (Rs Crores) : SUBCRITICAL : 2800 3000 SUPERCRITICAL : 33OO 3500 DIFFERENCE : 500.00 PAYBACK : 10 YEARS
Economiser
Lower Furnace
Hopper
Economiser
Lower furnace
Upper furnace
Separator
HP S/T
Condenser Blow
BFP
START UP CIRCUIT
Function: At low loads, once through flow is not sufficient to cool the furnace and water needs to be circulated. At low loads ( < 25% load), water/steam mix from the 2nd pass rear wall header enters into the separator and is recirculated through the drain tank and recirculation pump. Steam from the separator outlet enters the Pri SH inlet header At normal loads, steam from the 2nd pass rear wall header enters the separator and directly passes to the Pri SH inlet header. There is no recirculation.
CONTROL CONCEPT
Normally the drain flow from the separator is re-circulated via the BCP into the economizer, and control valve situated after the BCP is used for level control. The capacity of the BCP and the direct recirculation system is designed to accommodate the separator drain flow in normal low load operation. Especially during start-up larger amounts of water (swell flow) need be drained from the separator. For this purpose additional drain capacity is provided, dumping the excess water into the condenser flash tank. The respective control valves are situated near the condenser and open when the separator level exceeds a certain threshold lying above the normal set value applicable from normal re-circulation via BCP and control valve
Supercritical Sliding Pressure Boiler Water wall design Comparison of vertical wall and spiral wall
Vertical Water Wall (with Rifled Tube) Spiral Water Wall
Secondary superheater
Inlet header
Outlet header
Function: Second stage superheat. A first stage desuperheater is provided between the primary superheater and secondary superheater Configuration: Coils are arranged in pendant construction in parallel flow. The elements are widely spaced (approx 2 m) Material: SA 213 T22 / SA 213 T91/ SA 213 TP 347H
2ry SH Arrangement
2ry SH Arrangement
Primary Reheater
Outlet header
Function: First stage Reheater Configuration: Coils are arranged in multiple loops. Inlet banks are horizontal, while the outlet bank is vertical. Support: The horizontal coils are supported from economiser sling tubes emerging from the economiser intermediate header. Material: SA 210 Gr C / SA 213 T12 / SA 213 T11 / SA 213 T22
Inlet header
Final Reheater
Inlet header Outlet header
Function: Final Reheater. A desuperheater is provided between the primary Reheater and final Reheater Configuration: Coils are arranged in pendant construction in the passage behind the Final superheater in parallel flow. Material: SA 213 T91/ SA 213 TP 347H / CC 2328
Sling tubes from the economiser intermediate header act as sling tubes which support the primary superheater / primary reheater coils
SH / RH horizontal tubes
Buckstay
Role of Buckstay : Buckstays are structural members attached to furnaces to prevent implosion & explosion and are provided to retain the shape of Furnace / Secondary Pass. The tubes are connected to tie bars by welding & the tie bars are connected to buckstays by some sliding devices so that the tubes are free to expand along the diameter although the buckstay is not. The buckstays form a rigid frame through corner connections which are welded to corner tubes. The joint between corner plate & the buckstay beam is usually by links & pins to take care of the thermal movement of corner with respect to the buckstay.
Although a buckstay can readily take explosion as the beam is held at several places by tie bar connections ,its design becomes critical for implosion when the outer flange is under compressive load and no lateral torsional buckling reastarints are provided.
Materials
S. N o Composition ASME 1 Carbon Steel SA192 SA210 Gr A1 SA210 Gr C SA106 Gr B SA106 Gr C Specification DIN St 35.8 St 45.8 BS BS3059 Pt2 - S2-360, BS3059 Pt2-S2-440 BS3602 Pt1-360 BS3602 Pt1-430 Temperatur e Limit 427 C Waterwalls (nat. circ boilers), downcomers, risers, LTSH coils, Waterwall headers, economisers LTSH, RH coils SH/ RH Used in
2 3
C - 1/2 Mo 1 Cr 1/2 Mo
SA209 T1 SA213 T12 SA335 P12 SA213 T22 SA335 P22 CC 2199 / T23 SA213 T91 SA335 P91
15 Mo3 13 Cr Mo44 BS3059 Pt2 - S2 620 BS3604 Pt 2 620 440 BS3059 Pt2- S2 622490 BS3604 Pt1- 622 BS3059 Pt2 91
482 C 535 C
4 5 6
10 CrMo910
X10CrMoVNb 91
7 8 9
18 Cr 10 Ni Cb 18 Cr 9 Ni 3Cu Cb N
538
2 1/4 CrMo 18 Cr 2 1/4 CrMo 9 Cr
566
9 Cr
600
625
650
18 Cr
700
20~25 Cr 9 Cr 18 Cr 18 Cr 20~25 Cr
Ferritic Material
Austenitic Material
Coal
Coal Bunker
Burner
Coal Piping Primary Air Duct Hot Primary Air Fan Mill Cold Primary Air Fan Secondary Air Duct
Water Separator
2ry RH Tube
Rear Outlet Header Main Steam Pipe Hanger Inlet Passage Inlet Hanger & Header Passage Header Manifold
Pry RH Bank
Pry SH Bank
Pry RH Bank
Pry SH Bank 2nd Pass Inlet Pipe Pry SH Bank Eco Int. Header
Furnace Intermediate
Furnace Intermediate
Pry RH Bank
Pry RH Bank Eco Int. Header Pry RH Inlet Header Eco Bank 2nd Pass Inlet Ring Header Economizer Inlet Header
Eco Bank
Feed Water