PLAN RESEARCH DESIGN INTEGRATE AMEND
Version
1.0
DCOR
Model:
Quick
Reference
Design-Chain Operations
Reference-model
SCOR is a registered trademark in the United States and Europe
The
DCOR-model:
The Design Chain Operations
Reference-model (DCOR) is the
product of the Supply-Chain
Council (SCC), an independent,
not-for-profit, global corporation
with membership open to all
companies and organizations inter-
ested in applying and advancing
the state-of-the-art in supply and
design chain management systems
and practices. The newest model
from the SCC, the DCOR-model,
captures the SCC’s Technical
Development Steering Committee’s
consensus view of design chain
management. The Model’s
structure is inspired by that
of the Supply-Chain Operations
Reference Model (SCOR).
While much of the
underlying content of the
Model was originally developed by
practitioners, the DCOR-model
provides a unique framework that
links business process, metrics,
best practices and technology
features into a unified structure to
support communication among
design chain partners and to
improve the effectiveness of the
extended supply chain.
Top Level
(Process Types)
Configuration
Level
(Process
Categories)
Process Element
Level
(Decompose
Processes)
Implementation
Level
(Decompose
Process Elements)
Design-Chain
Operations
Reference-model
Not
in
Scope
PD1.1
Gather Design
Chain
Requirements
PD1.2
Gather Design
Chain
Resources
PD1.3
Balance Design Chain
Requirements with
Resources
PD1.4
Establish
Design-Chain Plans
Level
# Description Schematic
1
2
3
4
DCOR Contains Three
Levels of Process Detail
Amend
Research Design
Plan
Integrate
PLAN
PP
Plan
Design
Chain
PR
Plan
Research
PD
Plan
Design
RESEARCH
PI
Plan
Integrate
PA
Plan
Amend
PP.1:
Gather
Design Chain
Requirements
PP.2:
Gather
Design Chain
Resources
PP.3:
Balance
Design Chain
Resources with
Design Chain
Requirements
PP.4:
Establish &
Communicate
Design Chain
Plans
PR.1:
Gather
Reserch
Requirements
PR.2:
Gather
Research
Resources
PR.3:
Balance
Research
Resources with
Research
Requirements
PR.4
Establish
Research Plans
PD.1:
Gather
Design Chain
Requirements
PD.2:
Gather
Design Chain
Resources
PD.3:
Balance
Design Chain
Requirements
with Resources
PD.4:
Establish
Design Plans
PI.1:
Gather
Integrate
Requirements
PI.2:
Gather
Integrate
Resources
PI.3:
Balance
Integrate
Requirements
with Resources
PI.4:
Establish
Integrate Plans
PA.1:
Gather
Amend
Requirements
PA.2:
Gather
Amend
Resources
PA.3:
Balance
Amend
Requirements
with Resources
PA.4:
Establish &
Amend Plans
EP1:
Manage Plan
Business Rules
EP2:
Manage
Design Chain
Performance
EP3:
Manage Plan
Information
EP4:
Manage
Product
Lifecycle
EP5:
Manage Design
Chain Assets
R1
Research
Product
Refresh
R2
Research
New
Product
R3
Research
New
Technology
R1.1:
Schedule Research
Activites
R1.2:
Source Materials
R1.3:
Verify Materials
R1.4:
Transfer
Findings/Materials
R1.5:
Authorize Supplier
Payment (m-t-s)
R2.1:
Receive and
Validate Request
R2.2:
Schedule
Research Activities
R2.3:
Source Materials
R2.4:
Verify Materials
R2.5:
Transfer
Findings/Materials
R2.6:
Authorize
Supplier Payment
R3.1:
Receive and
Validate Request
R3.2:
Identify Sources
for Technology
R3.3:
Schedule
Research Activities
R3.4:
Source
Materials/Technology
Enable Plan
EP6:
Manage
Design Chain
Knowledge
Transfer
EP7:
Manage
Design Chain
Configuration
EP8:
Manage Plan
Regulatory
Compliance
EP9:
Align Design
Chain Unit
Plan with
Financial Plan
ER1:
Manage
Research
Business Rules
ER2:
Manage
Research
Performance
ER3:
Maintain
Research
Information
ER4:
Manage
Product
Lifecycle
ER5:
Manage
Research
Capital Assets
Enable Research
ER6:
Manage
Research
Knowledge
Transfer
ER7:
Manage
Research
Network
ER8:
Manage
Research
Regulatory
Requirements
DESIGN
D1
Design
Product
Refresh
D2
Design
New
Product
D3
Design
New
Technology
D1.1:
Schedule
Design Activities
D1.2:
Design Prototype
D1.3:
Build &
Test Prototype
D1.4:
Package Design
D1.5:
Release Design
to Integrate
D2.1:
Receive, Validate
& Decompose
Request
D2.2:
Schedule Design
Activities
D2.3:
Develop
Prototype
D2.4:
Build &
Test Prototype
D2.5:
Package Design
D2.6:
Release Design
to Integrate
D3.1:
Receive, Validate
& Decompose
Request
D3.2:
Schedule Design
Activities
D3.3:
Acquire
Knowledge
D3.4:
Develop
Prototype
D3.5:
Build &
Test Prototype
D3.6:
Package Design
D3.7:
Release Design
to Integrate
INTEGRATE
I1
Integrate
Product
Refresh
I2
Integrate
New
Product
I3
Integrate
New
Technology
I1.1:
Receive & Validate
Request
I1.2:
Integrate
New Product
I1.3:
Obtain &
Validate Design
I1.4:
Pilot Design
I1.5:
Package Product
I1.6:
Release Product
I2.1:
Receive & Validate
Request
I2.2:
Decompose
Request
I2.3:
Distribute
Requirements
I2.4:
Receive & Validate
Design
I2.5:
Pilot Design
I2.6:
Package
Product
I2.7:
Release
Product
I3.1:
Receive & Validate
Request
I3.2:
Decompose
Request
I3.3:
Distribute
Requirements
I3.4:
Receive & Validate
Design
I3.5:
Establish Execution
Processes
I3.6:
Pilot Design
I3.7:
Package Product
I3.8:
Release
Product
ED1:
Manage
Design
Business Rules
ED2:
Manage
Design
Performance
ED3:
Manage
Design
Information
ED4:
Manage
Product Life
Cycle
ED5:
Manage
Design Capital
Assets
Enable Design
ED6:
Manage
Design
Knowledge
Transfer
ED7:
Manage
Design
Network
ED8:
Manage
Design
Regulatory
Compliance
ED9:
Manage
Intellectual
Property
EI1:
Manage
Integrate
Business Rules
EI2:
Manage
Integrate
Performance
EI3:
Manage
Integrate
Information
EI4:
Manage
Product Life
Cycle
EI5:
Manage
Integrate
Capital Assets
Enable Integrate
EI6:
Manage
Integrate
Knowledge
Transfer
EI7:
Manage
Integrate
Network
EI8:
Manage
Integrate
Regulatory
Compliance
AMEND
Enable Amend
EA1:
Manage Amend
Business Rules
Processes
EA2:
Manage
Amend
Performance
EA3:
Manage
Amend
Information
EA4:
Manage
Product Life
Cycle
EA5:
Manage
Integrate
Capital Assets
EA6:
Manage
Amend
Knowledge
Transfer
EA7:
Manage
Amend
Network
EA8:
Manage
Amend
Regulatory
Compliance
A1
Amend
Product
Fallout
A2
Amend
Deficient
Product
A3
Amend
Product
Specs
A1.1:
Receive & Validate
Request
A1.2:
Decompose
New Product
A1.3:
Obtain &
Validate Design
A1.4:
Pilot Design
A1.5:
Package Product
A1.6:
Release Product
A2.1:
Obtain Deficiency
Information
A2.2:
Validate
Issue
A2.3:
Decompose
Issue
A2.4:
Distribute
Issue
A2.5:
Publish
Advisory
A3.1:
Obtain Specificaton
Information
A3.2:
Validate
Issue
A3.3:
Decompose
Issue
A3.4:
Distribute
Issue
A3.5:
Publish
SCO
For more information, please contact the
Council office:
In USA:
Supply Chain Council
1400 Eye Street, Suite 1050
Washington DC, 20005
Tel: +1 202-822-4660
Fax: +1 202-822-5286
Email: info@supply-chain.org
In Europe:
Supply Chain Council
287 Avenue Louise
2nd Floor
BE - 1050 Brussels
Tel: +32 2 627 0160
Fax: +32 2 645 2671
Email: Europe@supply-chain.org
www.supply-chain.org

More Related Content

DCOR.pdf

  • 1. PLAN RESEARCH DESIGN INTEGRATE AMEND Version 1.0 DCOR Model: Quick Reference Design-Chain Operations Reference-model SCOR is a registered trademark in the United States and Europe
  • 2. The DCOR-model: The Design Chain Operations Reference-model (DCOR) is the product of the Supply-Chain Council (SCC), an independent, not-for-profit, global corporation with membership open to all companies and organizations inter- ested in applying and advancing the state-of-the-art in supply and design chain management systems and practices. The newest model from the SCC, the DCOR-model, captures the SCC’s Technical Development Steering Committee’s consensus view of design chain management. The Model’s structure is inspired by that of the Supply-Chain Operations Reference Model (SCOR). While much of the underlying content of the Model was originally developed by practitioners, the DCOR-model provides a unique framework that links business process, metrics, best practices and technology features into a unified structure to support communication among design chain partners and to improve the effectiveness of the extended supply chain. Top Level (Process Types) Configuration Level (Process Categories) Process Element Level (Decompose Processes) Implementation Level (Decompose Process Elements) Design-Chain Operations Reference-model Not in Scope PD1.1 Gather Design Chain Requirements PD1.2 Gather Design Chain Resources PD1.3 Balance Design Chain Requirements with Resources PD1.4 Establish Design-Chain Plans Level # Description Schematic 1 2 3 4 DCOR Contains Three Levels of Process Detail Amend Research Design Plan Integrate
  • 3. PLAN PP Plan Design Chain PR Plan Research PD Plan Design RESEARCH PI Plan Integrate PA Plan Amend PP.1: Gather Design Chain Requirements PP.2: Gather Design Chain Resources PP.3: Balance Design Chain Resources with Design Chain Requirements PP.4: Establish & Communicate Design Chain Plans PR.1: Gather Reserch Requirements PR.2: Gather Research Resources PR.3: Balance Research Resources with Research Requirements PR.4 Establish Research Plans PD.1: Gather Design Chain Requirements PD.2: Gather Design Chain Resources PD.3: Balance Design Chain Requirements with Resources PD.4: Establish Design Plans PI.1: Gather Integrate Requirements PI.2: Gather Integrate Resources PI.3: Balance Integrate Requirements with Resources PI.4: Establish Integrate Plans PA.1: Gather Amend Requirements PA.2: Gather Amend Resources PA.3: Balance Amend Requirements with Resources PA.4: Establish & Amend Plans EP1: Manage Plan Business Rules EP2: Manage Design Chain Performance EP3: Manage Plan Information EP4: Manage Product Lifecycle EP5: Manage Design Chain Assets R1 Research Product Refresh R2 Research New Product R3 Research New Technology R1.1: Schedule Research Activites R1.2: Source Materials R1.3: Verify Materials R1.4: Transfer Findings/Materials R1.5: Authorize Supplier Payment (m-t-s) R2.1: Receive and Validate Request R2.2: Schedule Research Activities R2.3: Source Materials R2.4: Verify Materials R2.5: Transfer Findings/Materials R2.6: Authorize Supplier Payment R3.1: Receive and Validate Request R3.2: Identify Sources for Technology R3.3: Schedule Research Activities R3.4: Source Materials/Technology Enable Plan EP6: Manage Design Chain Knowledge Transfer EP7: Manage Design Chain Configuration EP8: Manage Plan Regulatory Compliance EP9: Align Design Chain Unit Plan with Financial Plan ER1: Manage Research Business Rules ER2: Manage Research Performance ER3: Maintain Research Information ER4: Manage Product Lifecycle ER5: Manage Research Capital Assets Enable Research ER6: Manage Research Knowledge Transfer ER7: Manage Research Network ER8: Manage Research Regulatory Requirements
  • 4. DESIGN D1 Design Product Refresh D2 Design New Product D3 Design New Technology D1.1: Schedule Design Activities D1.2: Design Prototype D1.3: Build & Test Prototype D1.4: Package Design D1.5: Release Design to Integrate D2.1: Receive, Validate & Decompose Request D2.2: Schedule Design Activities D2.3: Develop Prototype D2.4: Build & Test Prototype D2.5: Package Design D2.6: Release Design to Integrate D3.1: Receive, Validate & Decompose Request D3.2: Schedule Design Activities D3.3: Acquire Knowledge D3.4: Develop Prototype D3.5: Build & Test Prototype D3.6: Package Design D3.7: Release Design to Integrate INTEGRATE I1 Integrate Product Refresh I2 Integrate New Product I3 Integrate New Technology I1.1: Receive & Validate Request I1.2: Integrate New Product I1.3: Obtain & Validate Design I1.4: Pilot Design I1.5: Package Product I1.6: Release Product I2.1: Receive & Validate Request I2.2: Decompose Request I2.3: Distribute Requirements I2.4: Receive & Validate Design I2.5: Pilot Design I2.6: Package Product I2.7: Release Product I3.1: Receive & Validate Request I3.2: Decompose Request I3.3: Distribute Requirements I3.4: Receive & Validate Design I3.5: Establish Execution Processes I3.6: Pilot Design I3.7: Package Product I3.8: Release Product ED1: Manage Design Business Rules ED2: Manage Design Performance ED3: Manage Design Information ED4: Manage Product Life Cycle ED5: Manage Design Capital Assets Enable Design ED6: Manage Design Knowledge Transfer ED7: Manage Design Network ED8: Manage Design Regulatory Compliance ED9: Manage Intellectual Property EI1: Manage Integrate Business Rules EI2: Manage Integrate Performance EI3: Manage Integrate Information EI4: Manage Product Life Cycle EI5: Manage Integrate Capital Assets Enable Integrate EI6: Manage Integrate Knowledge Transfer EI7: Manage Integrate Network EI8: Manage Integrate Regulatory Compliance
  • 5. AMEND Enable Amend EA1: Manage Amend Business Rules Processes EA2: Manage Amend Performance EA3: Manage Amend Information EA4: Manage Product Life Cycle EA5: Manage Integrate Capital Assets EA6: Manage Amend Knowledge Transfer EA7: Manage Amend Network EA8: Manage Amend Regulatory Compliance A1 Amend Product Fallout A2 Amend Deficient Product A3 Amend Product Specs A1.1: Receive & Validate Request A1.2: Decompose New Product A1.3: Obtain & Validate Design A1.4: Pilot Design A1.5: Package Product A1.6: Release Product A2.1: Obtain Deficiency Information A2.2: Validate Issue A2.3: Decompose Issue A2.4: Distribute Issue A2.5: Publish Advisory A3.1: Obtain Specificaton Information A3.2: Validate Issue A3.3: Decompose Issue A3.4: Distribute Issue A3.5: Publish SCO For more information, please contact the Council office: In USA: Supply Chain Council 1400 Eye Street, Suite 1050 Washington DC, 20005 Tel: +1 202-822-4660 Fax: +1 202-822-5286 Email: info@supply-chain.org In Europe: Supply Chain Council 287 Avenue Louise 2nd Floor BE - 1050 Brussels Tel: +32 2 627 0160 Fax: +32 2 645 2671 Email: Europe@supply-chain.org www.supply-chain.org