Energy 35 (2010) 5217e5222
Contents lists available at ScienceDirect
Energy
journal homepage: www.elsevier.com/locate/energy
Adequacy evaluation of wind power generation systems
M. Carolin Mabel a, *, R. Edwin Raj b, E. Fernandez c
a
Department of Electrical and Electronics Engineering, St. Xavier’s Catholic College of Engineering, Chunkankadai, Tamilnadu 629003, India
Department of Mechanical Engineering, St. Xavier’s Catholic College of Engineering, Chunkankadai, Tamilnadu 629003, India
c
Department of Electrical Engineering, Indian Institute of Technology Roorkee, Roorkee, Uttranchal 247667, India
b
a r t i c l e i n f o
a b s t r a c t
Article history:
Received 11 December 2009
Received in revised form
8 July 2010
Accepted 27 July 2010
Available online 15 September 2010
This paper attempts to assess the adequacy of wind power generation systems using the data collected
from seven wind farms in Muppandal, Tamilnadu (India) with a total capacity of 37 MW. A Monte Carlo
model simulation is incorporated in the algorithm to obtain the hourly power output of wind farms,
which also takes into account the unavailability of wind turbines. A typical load demand profile is used to
examine the chronological hourly wind power generation for each month. The reliability index of LOLE
(loss of load expectation) is used to estimate the reliable contribution of wind farm power generation.
Ó 2010 Elsevier Ltd. All rights reserved.
Keywords:
Adequacy evaluation
Monte Carlo technique
Reliability
Wind power
1. Introduction
In the recent years, renewable energy applications are rapidly
increasing in power generation systems. Wind is one of the fastest
growing energy resource and their penetration levels in power
system are increasing worldwide. The benefit of wind power
generation is in providing clean energy and saving fossil fuels
thereby reducing emissions. Energy generation by wind power
plants is without fuel cost but nature dependent. This demands the
energy generated by wind is to be consumed fully in the grid to
reduce the overall generation cost. A wind turbine installed at
a potential site will generate electric power 70e85% of the time, but
not always at rated power output. The power output characteristics
of wind energy conversion system are different from that of any
conventional generation systems. A conventional power plant can
be considered as binary units, either fully available or not at all but
the wind power plant output vary between zero and its rated
capacity. When the power generation through wind is inadequate
or not available, the conventional sources must meet the load
demand during those quiescent periods. In spite of the intermittent
and variable nature of wind, the wind power generation system
contributes to a certain extent in meeting certain percentage of the
base loads of power system.
The analysis on reliability aspects of wind power finds more
significance compared to the conventional power generation
* Corresponding author. Tel.: þ91 9488073174; fax: þ91 4652259664.
E-mail address: carolin_mabel@yahoo.co.in (M.C. Mabel).
0360-5442/$ e see front matter Ó 2010 Elsevier Ltd. All rights reserved.
doi:10.1016/j.energy.2010.07.044
systems. Several studies have been reported on the modeling of
wind power generation and reliability of the power system incorporating wind energy [1e3]. Different reliability evaluation
methods such as probabilistic methods, chronological simulations
etc. have been applied [4e6]. The contribution of a wind plant to
the reliability performance of a generating system mainly depends
on wind energy penetration level and wind conditions [7,8].
An adequacy evaluation of wind farms is crucial in system
planning for certain base loads and to determine appropriate
generating resources to meet the expected total demand. For this
study, the real data are collected from seven wind farms in Muppandal, Tamilnadu (India) for a period of 3 years. The total capacity
of wind farms taken for study is 37 MW contributed by 137 wind
turbines. Tamilnadu is one of the Indian states having large wind
energy penetration with most of the wind farms located in Muppandal area. This paper presents a method to assess the reliability
of wind power generation systems. The Monte Carlo simulation
technique is incorporated in the method to obtain the hourly wind
power generation. The reliability index, LOLE (loss of load expectation) is used to evaluate the adequacy of wind energy.
2. Wind energy production and evaluation
2.1. Power output of a wind turbine
The power output of a wind energy conversion system depends
upon the stochastic nature and chronological variability of the wind
5218
M.C. Mabel et al. / Energy 35 (2010) 5217e5222
speed. Fig. 1 shows the variation in power output of a wind turbine
for different wind speeds [9].
The performance regions 1 and 2, shows the amount of power
that can be produced from a wind power generation system corresponding to wind speeds VIeVR and VReVO. VI is the cut-in speed,
VR is the rated speed and VO is the cut-out speed. The WECS power
output PT can be calculated as [10]:
Table 1
Wind potential of Muppandal station.
Station
Muppandal
8
0
>
>
<
A þ BV þ CV 2 PR
PT ¼
> PR
>
:
0
0 V VI
VI V VR
VR V VO
V VO
At 25m height
Annual
average
wind
speed (m/s)
Wind
power
density
(W/m2)
7.00
406
B ¼
C ¼
1
VR Þ2
ðVI
1
ðVI
VR Þ2
1
ðVI
VR Þ2
"
"
VI ðVI þ VR Þ
4ðVI VR Þ
VI þ VR
2VR
3 #
#
VI þ VR 3
4ðVI þ VR Þ
ð3VI þ VR Þ
2VR
2
Technical
potential
(MW)
712
2100
1600
demand in time period i, Pi(Ci < Li) is the probability that the load
demand exceeds the available power generation in time period i.
The percentage reliability (R) is calculated as given below:
ReliabilityðRÞ ¼
A ¼
Gross
potential
(MW)
(1)
The constants A, B and C are found out using the following
equations:
"
Wind
density
extrapolated
to 50m height
(W/m2)
#
VI þ VR 3
4
2VR
(2)
(3)
(4)
Generally, the cut-in speed of a wind turbine is in the range of
2.5e3.5 m/s and cut-out speed is in the range of 20e25 m/s.
1
LOLE
no: of hours
The reliability R value of 1 indicates that the wind generation
system is able to meet all of the load demand. On the other hand,
a lesser value of 1, for e.g., 0.4 represents that the wind energy
system supplies only forty percentage of the load demand. The
intermittent nature of wind and the constraints in the energy
available in wind can degrade the system reliability.
In a generation system study, the total system generation is
examined to determine its adequacy to meet the system load
requirement. Renewable energy systems like, wind power generation systems does contribute to the system reliability and reduces
the capacity requirement of utility system.
2.2. Evaluation of wind power using reliability index
3. Description of wind farms taken for study
The reliability index indicates the ability of wind generation
capacity to meet the system demand and it is used in the utility
industry in generation planning. The reliability index is defined by
the term, loss of load expectation. LOLE is the expected period
during which the load demand exceeds the available generation
capacity [11].
The LOLE is defined as:
The three-year data are collected from seven wind farms located
in Muppandal, Tamilnadu (India). These wind farms cover 137 wind
turbines with a total capacity of 37 MW. Tamilnadu is in the
southern region of India at north latitude between 8 50 and 13 350
and east longitude between 76 150 and 80 20’. This state is ahead
of other Indian states with more than 50% of the total wind energy
installed capacity of India. The Muppandal region in Tamilnadu has
the distinction of having one of the largest concentrations of wind
turbines at a single location with installed capacity of more than
1000 MW. Table 1 gives the potential of Muppandal station [12,13].
Significant variations in seasonal or monthly average wind
speed are common over most parts of the world. Fig. 2 shows the
pattern of monthly average wind speed variation for three
consecutive years and the average over the three years. In Muppandal, the wind speed is high during May to August and reaches
a maximum of 30 m/s because of South-West winds. During
December and January, the wind speed again increases because of
North-East winds.
The variation in energy output of wind farms depends upon the
variation in wind speed. Fig. 3 shows the variation of energy
LOLE ¼
n
X
Pi ðCi < Li Þ
(5)
i¼1
where i is the time step, an hour or a day, n is the no of hours, Ci is
the power generation available in time period i, Li is the load
Fig. 1. Variation in power output of a wind turbine for different wind speeds.
Fig. 2. Pattern of monthly average wind speed variation.
M.C. Mabel et al. / Energy 35 (2010) 5217e5222
5219
Fig. 3. Variation of energy generation per kW capacity with monthly average wind
speed.
generation per kW capacity with monthly average wind speed
taken over a period of three years. For reliable energy generation, it
is necessary to take into account the availability factor of the wind
turbine. The availability factor of a wind turbine is the percentage of
time, it is ready to generate power. Servicing, inspection, component failures and accidents, such as lightning strokes reduce the
availability of wind turbine. The availability of each wind turbine in
a wind farm may differ depending on the faults which occur. In this
study, grid breakdown and maintenance period are also included in
the calculation of availability factor since grid failure results in
stalling of wind turbine. Fig. 4 shows the availability of wind farms
for the three-year period. The availability is calculated using the
expression:
Availabilityð%Þ ¼
Uptime
100
Uptime þ Downtime
(6)
4. Adequacy evaluation of wind farms
Fig. 5. Algorithm for the evaluation of reliability index of wind farms.
4.1. Methodology
The methodology to evaluate the adequacy of wind power
generation systems uses Monte Carlo technique. Monte Carlo
algorithm is one of the realistic engineering tools that facilitate to
perform statistical analysis of the uncertainties involved in engineering problems [14,15]. The Monte Carlo simulation produces
a series of random numbers and these numbers will have the same
characteristics of the probability of their occurrences in the selected
domain between 0 and 1. Sufficient number of iterations is required
to arrive at statistically viable result and to approach the real value
of a parameter.
Fig. 5 gives the algorithm for the evaluation of reliability index,
LOLE of wind farms, where, NWG is the number of wind turbine
generators, WPGj is the power generation of jth wind turbine
generator in MW, PD is the power demand in MW, AVj is the
availability of the jth wind turbine generator, NWF is the number of
wind farms and PGT is the total wind power generation in MW.
Fig. 4. Availability of wind farms for the three-year period.
5220
M.C. Mabel et al. / Energy 35 (2010) 5217e5222
4.2. Analysis
Wind farm evaluation consists of two steps: (1) Availability
evaluation of each wind turbine and (2) the adequacy evaluation of
wind farms.
The hourly power output of the wind farms are obtained by the
model simulation. With the available data of hourly mean wind
speed and its standard deviation, normally distributed random
wind speeds for every second are generated using Monte Carlo
simulation. The generated wind speeds are used to calculate the
wind turbine generator power output of each wind turbine as given
by the Eq. (1), which gives the power output at any instant. At any
instant, the total power output of the wind farm is the sum of the
power output of each wind turbine. From the instant power output,
the hourly wind farm power output is evaluated.
In addition, the Monte Carlo technique generates random values
and compares with the availability of each wind turbine of the wind
farms to determine the inclusion of each wind turbine for determining power output of wind farms. The methodology is repeated
for number of iterations to obtain the LOLE.
The assessment of the reliability of wind farms in generation
systems is essential from the planning point of view. The chronological
Fig. 6. Load curve used for adequacy evaluation.
hourly generation data for each month of the seven wind farms are
used to match with a chronological hourly load demand model. The
total capacity of the seven wind farms from which the data are
collected is 37 MW. The maximum average hourly power generation is
Fig. 7. Profiles of the wind farm energy production and the load demand.
M.C. Mabel et al. / Energy 35 (2010) 5217e5222
5221
Fig. 7. (continued).
15 MW during the period taken for study. This power generation is
rather low in comparison with the rated capacity due to the nature of
wind, availability of wind turbines and grid etc. Therefore, the rated
capacity of a wind turbine or a farm cannot be interpreted in the same
way as that of a conventional generation system. The capacity value of
any wind farm can be considered as the capacity factor multiplied by
its rated capacity [8].
The wind farms taken for study are connected to the southern
grid of India. The following assumptions are made to evaluate the
adequacy of wind power generation systems:
1) It is considered that wind power generation systems alone
meet the load demand.
2) The load demand curve pattern is the same throughout the
year since the seasonal demand variation is negligible owing to
the weather condition of the site.
3) In the scaled load curve, the peak load demand is taken as 90%
of the maximum hourly average power generation in a year.
For the adequacy evaluation, a suitable load model is essential.
This load curve is derived from a typical load curve of southern
region grid of India by scaling down the actual load demand curve
pattern. The peak load demand is taken as 13.5 MW which is 90% of
the maximum hourly average power generation. The obtained load
curve for the study is of the similar pattern of typical load curve
with difference in magnitude. Fig. 6 shows the derived load curve
for the adequacy evaluation. The LOLE index is obtained by
comparing hourly average generation of each month with the
corresponding hourly load demand.
The LOLE is obtained as 164.87 h per year. This means the wind
farm reliability contribution is 42.75% in meeting the load demand.
Fig. 7(a)e(l) shows the comparison of monthly hourly average daily
generation curve with the load demand profile.
It can be seen from Fig. 7(b)e(e), during the months of May to
August the power generated from wind farms can meet the load
demand for maximum number of hours. In Fig. 7(l) for the month of
March, the power generation is too low and the load demand is not
even met once. This shows how the seasonal variation of wind
speed affects the wind power generation and thereby its reliability.
From the Fig. 7(a)e(l) it can be noted that throughout the year,
a base power generation of 2 MW is available from the wind farms
taken for study.
5222
M.C. Mabel et al. / Energy 35 (2010) 5217e5222
Another feature of wind energy to be noted from this study is
that during off peak hours, the wind power generation is high and
during peak hours the power generation is low. This signifies that
the wind energy must be considered only for the base load while
integrating with the power systems. During the months of June,
July and August in Fig. 7(c)e(e), the maximum power generation
from the wind farms is higher than the peak load demand, but the
time of the day does not match with peak demand. The adequacy
analysis shows the hours during which the power generation is
high and low, and accordingly the energy planners must handle the
reserves in power system.
5. Conclusions
A case study with respect to the reliability assessment of wind
farms is carried out using the real data collected from Muppandal,
Tamilnadu (India). It is seen that the reliability contribution of wind
farms is 42.75% to meet the load demand pattern assumed for the
evaluation. In addition, the study depicts that the maximum wind
power generation period does not match with the peak load period.
This signifies that in a power system, wind generated power must
be utilized to the maximum to meet the base load demands to
conserve conventional fuels and to reduce emissions. However, the
total energy contribution by the wind farms to the power system is
significant. While operating wind energy conversion systems with
the other sources, it is necessary to know when and how much
power will be available from wind in order to satisfy the load
demand. This adequacy evaluation study is helpful to energy
planners and operators in planning and decision-making.
References
[1] Billinton R, Chen Hua, Ghajar R. A sequential simulation technique for
adequacy evaluation of generating systems including wind energy. IEEE
Transactions on Energy Conversion 1996;11(4):728e34.
[2] Wang Peng, Billinton Roy. Reliability benefit analysis of adding WTG to a distribution system. IEEE Transactions on Energy Conversion 2001;16(2):134e9.
[3] Ubeda JR, Rodriguez Garcia MAR. Reliability and production assessment of
wind energy production connected to the electric network supply. IEE
Proceedings-Generation, Transmission & Distribution 1999;146(2):169e75.
[4] Karaki SH, Chedid RB, Ramadan R. Probabilistic performance assessment of
wind energy conversion systems. IEEE Transactions on Energy Conversion
1999;14(3):217e24.
[5] Kris Voorspools R, William D’haeseleer D. Critical evaluation of methods for windpower appraisal. Renewable and Sustainable Energy Reviews 2007;11(1):78e97.
[6] Tina G, Gagliano S, Raiti S. Hybrid solar/wind power system probabilistic
modeling for long-term performance assessment. Solar Energy 2006;80:
578e88.
[7] Billinton Roy, Bai Guang. Generating capacity adequacy associated with wind
energy. IEEE Transactions on Energy Conversion 2004;19(3):641e6.
[8] Billinton Roy, Karki Rajesh. Cost effective wind energy utilization for reliable
power supply. IEEE Transactions on Energy Conversion 2004;19(2):435e40.
[9] Mathew Sathyajith. Wind energy fundamentals, resource analysis and
economics. New York: Springer; 2006.
[10] Giorsetto Paul, Utsurogi Kent F. Development of a new procedure for reliability modelling of wind turbine generators. IEEE Transactions on Power
Apparatus and Systems 1983;102(1):134e43.
[11] Endrenyi J. Reliability modeling in electric power systems. New York: John
Wiley & Sons; 1978.
[12] MNRE. Wind power programme. Ministry of New and Renewable Energy,
Govt. of India. See also, http://mnes.nic.in/wp10.htm; 2003.
[13] Non-conventional sources of energy. Annual plan. Chennai: State Planning
Commission; 2004e2005.
[14] Zio E, Marella M, Podofillini LA. Monte Carlo simulation approach to the
availability assessment of multi-state systems with operational dependencies.
Reliability Engineering and System Safety 2007;92(7):871e82.
[15] Billinton R, Lian G. Station reliability evaluation using a Monte Carlo approach.
IEEE Transactions on Power Delivery 1993;8(3):1239e45.