Sample of ECA
Sample of ECA
Sample of ECA
ELEMENTAL COST ANALYSIS - FORM 1 JOB TITLE : Cadangan Membina dan Menyiapkan Sebuah Dewan Serbaguna, Asrama dan CLIENT : Pejabat Serta Kerja-kerja Berkaitan Dengannya di Kompleks Perhutanan Bukit Bakar, Jajahan Machang, Kelantan. (Dewan Serbaguna) LOCATION : Machang, Kelantan Darul Naim TENDER DATE : 3 - Administrative Buildings A - 2 - 1089 Government
October/05
INFORMATION TOTAL PROJECT Project and Contract Information Project Details and Site Condition : Contract : Proposed two storey multiple-purpose hall comprising office at first floor, including associated Standard PWD Form203A (Rev. 10/83) external works within lot boundries. Other specialist works are included under Provisional Sums. No problem in accessibility and the site condition generally is flat and slightly sloping. Market Conditions : Contract particulars : Type of Contract : Basis of Tender : Bills of Quantities COMPETITIVE Competitive Tender List RM Standard PWD Form203A (Rev. 10/83) Cost Fluctuation: Yes No / Open / Selected Competition Negotiated / Government Private 3,899,071.45 Provisional Sums Schedule of rates / Spec. & Drawings Contract Period Stipulated by Client: Contract Period Offered by Builders: Numbers of Tenders Issued : Numbers of Tenders Received : Serials Prime Cost Sums 28 weeks 28 weeks 32 25 Preliminaries Contigencies Contract Sum RM RM RM RM 177,157.15 3,931,663.80 RM 350,000.00 3,789,000.00 L L / 1,997,464.55 Bills of Appr. Quant. L 4,280,494.30 L / 4,546,550.87 L Int (JV)/L
ANALYSIS OF SINGLE BUILDING Design/Shape Information Accomodation and Design Features: The rectangular shape multi-purpose hall comprising of 2 storey with hall area, VIP room, office, meeting room, audio room, toilet and changing room. Areas : Functional unit: Lower Ground Floor Ground floor Upper Floors Gross Floor Area Usable Area Circulation Area Ancillary Area Internal Division Gross Floor Area Floor Spaces NOT Enclosed: Roof Area : (Structural and Plant Rooms) 92 760 237 1089 612 173 291 14 1089 m m m m m m m m m 612 m Design / Shapes Percentage of Gross Floor Area (a) Below Ground Floor (b) Single-Storey Construction (c) Two-storey Construction 1.52 m 3.05 m 3.96 m (e) 20-storey Construction N/A (d) 3-storey Construction % %
100
N/A
Brief Cost Contract sum Provisional Sums Prime Cost Sums Preliminaries Contigencies Contract Sum less Contingencies
RM RM RM RM RM RM
1,997,464.55 350,000.00 177,157.15 1,997,464.55 being being 9.73 % of remainder % Contract Sum
RM
2,508.64 per m2
e Buildings
Int (JV)/L L L L L L
per m2
118,016.30
108.37
759
m2
155.49
0.70
242.38
7,113.00
118,016.30
108.37
242.38
7,113.00
m m m m m m m
152.13
14,910.00
m m m
P.C.Sums Allowed
(RM)
5. Services 5A Sanitary Appliances 5B Plumbing Installation 5C Refuse Disposal 5D Air-conditioning & Ventilation System 5E Electrical Installation 5F Fire Protection Installation 5G Lift & Conveyor Installation 5H Communication Installation 5J Special Installation 5K Builder's Profit & Attendance on Services 5L Builder's Work in Connection With Services Group Element Total : Sub-total excluding External Works, Preliminaries and Contingencies
83
Nos
145.66
0.08
582,374.95 1,356,893.85
534.78 1,198.61
6. External Works 6A Site Work 6B Drainage 6C External Services 6D Ancillary Buildings 6E Recreational Facilities Group Element Total : Preliminaries TOTAL ( less Contigencies )
trative Buildings 9
704.20
704.20
1,364.40
Reinforced concrete for pad footings, ground beams, column stumps and groud slab. Also reinforced concrete for apron and walkaway.
2E 2F
2G 2H
Reinforced concrete column, mezzanine and roof beam. Use decorative column base including plastering and painting. Reinforced concrete suspended floor slab construction. Steel roof structure system on prefabricated timber roof trusses with a layer of double sided aluminium foil, uPVC rain water down pipes and PVC ballon grating to top of it. Reinforced concrete stair construction finished with cement and sand plaster with an approved plasticier finished smooth with a wood float. Homogenous floor tiles at landing slab. Generally 115mm thick brickwall. Natural anodised aluminium top hung window and casement window with fixed panels. "Formaframe" Zincaneal panel door (inclusive for fixed glass panel on top) 1 hour fire rated door to the instruction and recommendation by Jabatan Perkhidmatan Bomba Malaysia. Generally 115mm thick reinforced with and including a layer of "Exmet" at every fourt course. "Formaframe" Zincaneal panel door with local range ironmongeries. PVC door with aluminium frame and ironmongeries.
3 3A 3B 3C 3D
Finishes Internal Wall finishes Internal Floor Finishes Internal Ceiling Finishes External Finishes
Alkali resisting primer and emulsion paint with glazed ceramic tiles finished to wall and columns. Homogenous tiles to floor and non-slip homogenous tiles to toilets. "Ekowood" solid laminated timber boarding to the hall area including skirting. Skim coating to concrete soffit. UAC Superflex asbestos free ceiling and emulsion paint to the asbestos ceiling sheet. Cement and sand to apron and homogenous tiles to walkaway slab. Cement and sand plaster with weathershield paint to external wall and column. UAC Superflex asbestos free ceiling with weathershield paint. Lecture chair sittings, rectangular banquet table, moveable magnetic white board, velvet notice board for hall area. Rectangular 4 sides curved confrenced table and moveable magnetic white board for meeting room. 4-seater and 3-seater waiting chairs, media tower, newspaper rack, velvet notice board and Lshaped one side curved information counter at lobby area. Double sides workstation, executive table, full leather chair and cabinet at office. For VIP room both sides curved showcase.
5 5A 5B 5C 5D 5E 5F 5G 5H 5J 5K 5L
Services Sanitary Appliances Plumbing Installation Refuse disposal Air-Conditioning & Ventilation System Electrical Installation Fire Protection Installation Lift & Conveyor Installation Communication Installation Special Installation Builders's Profit & Attendance on Services Builders's Work in Connection With Services External Works Site Works Drainage External Services Ancillary Building Recreation Facilities
Generally, "Johnson Suisse" glazed vitreous china of sanitary wares, 3 tap-hole counter top vanity basin and "DOE" range of tap fittings. Cold water and sanitary plumbing. Air cooled split unit system, air cooled packaged, electrical wiring and mechanical ventilation system. Complete electrical services, telephone, sound reinforcement system, stage curtain system, visual projection system and stage lighting system. Hose reel system, fire alarm system and portable fire extinguisher system.
6 6A 6B 6C 6D 6E
Site preparation and earthworks and all slope protection works including turfing. Roadworks and car parks, fencing and gates, stainless steel sliding gate and bridgeworks. Stormwater drainage systems, foul drainage system and water reticulation system which include all the fittings and accessories. Pump House, Guard House and Water Tanks.
ITEM
Location
Nos
Length
Width
Sub Total
Total
5.31
17.26
91.72
91.72
TOTAL :
91.72
Ground Floor
ITEM
Location
Nos
Length
Width
Sub Total
Total
576.70 2 ANCILLARY AREA AHU Room TOILET (Female) WC Near Door Sink Opening VIP Toilet WC Sink Opening TOILET (Male) WC Sink Near Door Opening CHANGING ROOM Male & Female 4 1 1 1 0.95 3.09 0.95 1.22 1.71 2.32 2.32 0.12 6.52 7.17 2.21 0.14 1 1 1 0.95 0.95 0.91 1.71 2.32 0.12 1.63 2.21 0.11 3 1 1 1 0.95 0.95 2.02 1.22 1.71 2.32 2.32 0.12 4.89 2.21 4.69 0.14 1 1.54 3.92 6.05
2.32
2.63
12.21
VIP Room
4.09
4.15
17.00
67.19
1 1
4.15 13.30
4.15 4.27
17.24 56.74
1 1 2
Ground Floor
ITEM Location Nos Length Width Sub Total Total
INTERNAL DIVISION Backstage 2 2 1 1.83 0.91 8.11 0.12 0.12 0.12 0.42 0.21 0.93
2 1 1 2 3 1 2 3 1 1 1 1 1 1
2.32 4.15 4.27 4.15 1.71 1.22 4.15 1.71 2.32 1.16 4.09 4.27 1.54 4.15
0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.23 0.23
0.53 0.48 0.49 0.96 0.59 0.14 0.96 0.59 0.27 0.13 0.47 0.49 0.35 0.95 8.97
Toilet (Male)
Toilet (Female)
VIP room
AHU room
TOTAL :
759.83
REF : 1 ' = 0.3048m 1 " = 0.0254m Brickwall A = 4 1/2" thk brickwall Brickwall B = 9" thk brickwall Brickwall A = 0.1143 Brickwall B = 0.2286
Upper Floor
GFA
ITEM
Location
Nos
Length
Width
Sub Total
Total
ANCILLARY AREA MEETING ROOM AUDIO ROOM PANTRY & TOILET Pantry Toilet A Toilet B
1 1
12.08 3.54
9.03 2.93
109.04 10.39
1 2 1
131.70
CIRULATION AREA LOBBY AREA 1 A B C Opening LOBBY AREA 2 1 1 1 1 1 8.42 5.98 2.93 0.91 4.15 3.05 1.52 4.57 0.12 4.15 25.66 9.12 13.41 0.11 17.24
65.53
INTERNAL DIVISION Office Area 1 1 1 1 3 1 1 1 5.98 6.10 2.93 12.08 2.93 4.69 1.71 2.32 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.69 0.70 0.34 1.39 1.01 0.54 0.20 0.27
5.13
TOTAL :
237.18
Upper Floor
GFA
Not Enclosed
GFA
ITEM
Location
Nos
Length
Width
Sub Total
Total
Less 1 1 1 1 1 1 1 2 35.47 1.22 2.44 1.83 34.25 5.49 1.83 1.10 1.83 4.27 3.05 22.67 1.83 1.83 2.74 0.91 64.87 5.20 7.43 41.46 62.64 10.03 5.02 2.02
Left C
TOTAL :
198.68
Not Enclosed
GFA
Roof
GFA
ITEM
Location
Nos
Length
Width
Sub Total
Total
ROOF Overall A B C D
Less 1 3.66 3.66 15.85 4.27 4.57 4.27 1.83 0.61 1 1 1 2 41.45 29.87 1,238.21 16.72 15.61 28.99 5.20 66.52 1,238.21
TOTAL :
1,171.69
Pitch 12 25 30 45
Pitch 30
1.149425
1,172.00
= =
1,347.13 1347
Roof
GFA
Door / Window
GFA
ITEM
Location
Nos
Length
Width
Sub Total
Less 4 10 1 2 1 2 2.13 2.13 2.44 2.13 2.13 2.13 0.91 0.76 3.96 0.91 1.52 1.52 7.80 16.26 9.66 3.90 3.25 6.50
TOTAL :
Door / Window
GFA
ITEM
Location
Nos
Length
Width
Sub Total
Less 19 5 1 2.44 2.44 2.13 1.52 0.91 1.52 70.61 11.15 3.25
WINDOW Type W1 Type TH1 Type TH2 Type TH3 Type FG1 2 1 5 14 1 1.52 0.91 0.61 0.91 1.83 2.44 1.22 1.22 1.83 2.44 7.43 1.11 3.72 23.41 4.46
TOTAL :
Door / Window
GFA
Total
47.38
Door / Window
GFA
Total
85.01
40.13
125.14
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA, ASRAMA DAN PEJABAT SERTA KERJA-KERJA BERKAINTAN DENGANNYA DI KOMPLEKS PERHUTANAN BUKIT BAKAR, JAJAHAN MACHANG, KELANTAN DARUL NAIM. SUMMARY OF TENDER
DESCRIPTION
b) DEWAN SERBAGUNA & PEJABAT 3 4 5 6 FITTINGS & FURNISHING EXTERNAL WORKS MECHANICAL & ELECTRICAL WORKS PROVISIONAL SUMS
TOTAL AMOUNT