Elemental Cost Analysis
Elemental Cost Analysis
Elemental Cost Analysis
A-1-822.08
JOB TITLE : Cadangan Membina dan Menyiapkan Sekolah Vokasional Kuala CLIENT : Kementerian Pendidikan Malaysia
Berang serta Kerja-Kerja Infrastruktur yang berkaitan di atas Lot
10062 (H.S.D 1188), Kampung Tajin, Mukim Kuala Berang,
Terengganu Darul Iman.
LOCATION : Kampung Tajin, Mukim Kuala Berang, Terengganu Darul Iman TENDER DATE : November-13
Floor Space NOT Enclosed 28.08 m2 At Ground Floor 3.60 m (d) 3-Storey
-
Roof Area 1,056.06 m2 Above Ground Floor - Construction
(Measured Flat On Plan) m (e) 4-Storey
-
Construction
Brief Cost Information
Contract Sums RM 37,499,500.00 Functional Unit Cost But
Provisional Sums RM 3,540,000.00 Excluding External Works : RM 1,091
Prime Cost Sums RM -
Preliminaries RM 1,170,649.94 being 3.12% of Remainder of Contract
Sum Contingencies RM 0.00 being 0.00% of Remainder of Contract
Sum
/m2
APPENDIX 2
ELEMENT COST ANALYSIS - Form 2 7-Educational Building
A-1-822.08
SUMMARY OF ELEMENT COSTS
A-1-822.08
BRIEF SPECIFICATION
GROSS FLOOR AREA : 864 M2 TENDER DATE : November-13
ELEMENT SPECIFICATION
1 Substructure
1A Piling
1B Work Below Lowest Floor Finish R.C Grade 30 as raft foundation, apron slab, ramp bed.
2 Superstructure
2A Frame R.C Gr. 30 columns, isolated columns and roof beams construction.
2B Upper Floor Not applicable
Metal deck on steel roof trusses with double sided wooven , Aluminium insulation foil, one layer
2C Roof
chicken wire mesh, and metal fascia board.
2D Staircase Not applicable
2E External Walls 114mm thk clay brickwall
Aluminium frame fixed casement glass window, fixed aluminium louvres & fixed glass louvres
2F Windows
window.
2G Internal Walls & Partition Generally 114mm thick claybricks wall
Generally single leaf plywood flush doors including ironmongeries for internal doors and double
2H Doors
leaf aluminium glass door including ironmongeries for external doors.
3 Finishes
Cement and sand plastering and emulsion paint to walls and columns. Ceramic wall tiles finishes
3A Internal Wall Finishes
to walls and columns.
3B Internal Floor Finishes Generally homogeneous tiles, non-slip homogeneous tiles.
3C Internal Ceiling Finishes Generally emulsion paint to general surfaces of asbestos free
Cement & sand plaster & weathershield paint to external wall & column, and concrete coping
4 Fittings and Furnishings Not applicable
5 Services
Pedestal w.c, wash hand basin, kitchen sink, mirror, liquid soap dispenser, floor trap, bib tap,and
5A Sanitary Appliance
tap.
5B Plumbing Installation Not applicable
5C Refuse Disposal Not applicable
Air-conditioning & Ventilation Not applicable
5D System
5E Electrical Installation Not applicable
5F Fire Protection Installation Not applicable
5G Lift & Conveyor Installation Not applicable
5H Communication Installation Not applicable
5J Special Installation Not applicable
Builder's Profit & Attendance on Not applicable
5K Services
Builder's Work in Connection with R.C Grade 30 in counter top.
5L Services
6 External Works
6A Site Work Not applicable
6B Drainage Precast concrete Grade 20 perimeter drain
6C External Services Not applicable
6D Ancillary Buildings Not applicable
6E Recreational Facilities Not applicable