Method Statement
Method Statement
Method Statement
SAUDI OGER
electrical cable
PURPOSE
The purpose of this Method Statement is to describe the system to be taken for achieving the
specified requirements for structural system of suspending the electrical cables at segments
25, 7.
SCOPE
This Method Statement is to provide a detailed description for the execution of all works related
to structural elements under the scope of structural system of suspending the electrical cables
cross with segments 7,25 .
Method statement
1- Locate and set out of grid lines and axes of foundations
2- Establish the test foundation pits to determine the exact level of existing cable duct
bank and hand tool shall be used for excavation that approach the existing duct bank.
3- Check the limits of tunnel excavation and be sure that safe distance for requires
foundation is available
4- Execute the foundation pits up to the required levels.
5- Establish the plain concrete up to the required level
6- Establish and Form work.
7- Establish the steel reinforcements
8- Erect the anchor bolts in the right location as per structural drawings.
9- Concreting of foundations
10- Erect the base plates and steel columns
11- Backfilling around foundation with compacted sand to >= 95 % of dry density.
12- Establish the horizontal strand cable and use the tension equipment provided with dial
gauge to adopt the tension force to max 5 tons
13- Establish the inclined strand wire and tied to the Hal strand cable in the specified
locations.
14- Repeat the same procedures to adopt the tension force to max 2.00 ton to keep the sag
deflection of strand wire cable max to 30 cm.
15- Start to excavate up to the duct bank of electrical cable.
16- Duct bank shall be free from any working electrical cable during excavation or
demolishing process.
17- Duct bank will be cut from both end closed to the limit of tunnel excavation, and then
during the excavation of tunnel it will be broken.
18- The cable tray can be installed to the appropriate level to compensate the increasing
of electrical cable length .
SURVEY AND SETTING OUT
The construction site shall be surveyed and set out by establishing grid lines and levels of the
work. The limits and elevations shall be in accordance with the approved construction
drawings.
EXCAVATION
1- Foundation pits shall be excavated to the extents indicated in the approved construction
drawings and the excavation slopes not less than 1.5 horizontal to 1 vertical.
Structural system of suspending
SAUDI OGER
electrical cable
2- Any excess excavation shall be backfilled with an approved fill material and compacted to
>95% of its maximum dry density (or as specified). If the compaction is not achievable, over
excavated area shall be replaced with mass concrete - Grade C15, if and when so required.
3- Hand tools shall be used for excavation that approaches existing pipes, conduits, cables or
other underground facilities. Temporary support shall be provided to the existing utilities to
prevent damage during operation.
4- The excavated material shall be moved to an approved dumping area
BACKFILLING
Materials
Materials to be used for backfilling works shall be approved