Method Statement
Method Statement
Method Statement
MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR
MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR
2 Compaction of all road 1112 m2 2 roller compactor 2 operator Labour constant: 12 days
formation levels as 0.17hr (10min) /
described before the 1 m2
commencement of any
construction thereon. 10min x 1112 m2
= 23day 1hr 22min
for 1 roller
compactor
23 ½ day / 2 roller
compactor
= 11.75 days
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
exceloneconstruct@gmail.com
MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR
35day / 2 excavator
= 17day 4hrs
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
exceloneconstruct@gmail.com
MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR
Labour constant:
Roller compactor
0.08hr (5min) /
1 m2
5min x 1112 m2
= 11day 4hr 39min
for 1 roller
compactor
Total = 23days
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
exceloneconstruct@gmail.com
MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR
5 Construct and complete 1112 m2 1 bucket 1 skill labour Labour constant: 12 days
115mm thick brickwall 1 shovel 4 general labour 0.08hr (5min) /
with concrete base 1 trowel 1 m2
including all necessary
excavation, formwork 5min x 1112 m2
and reinforcement. = 11day 4hr 39min