Quality Control Questioner
Quality Control Questioner
Quality Control Questioner
BASIC
QA/QC QUESTIONS & ANSWERS
QA/QC Questionnaires
A Fundamental Handbook for Interview
QA/QC & Instrumentation Inspection
ABU ZARRAR QUAISI
2009
AL‐QAMAR
QA/QC Questionnaires
Instrumentation Inspection and Quality Control Questioner
Q. What is QA/QC?
) QA/QC means, “Quality Assurance/Quality Control” the purpose of this (QA/QC) is to establish
the sequence of requirement for the quality of material, quality of works, its inspection and
records.
Q. What are basic responsibilities of QA/QC personals?
) To ensure execution of works and comply fully as per standard and approved specs.
Q. What are the basic required documents for a QA/QC personal?
) The basic required documents QA/QC personal are as following:
ITP: to conduct the Quality check (inspection/witness/surveillance) etc.
WP: standard procedure to execute the works. (Work Procedure)
P&ID: as a reference to ensure that the work is as per standard drawing.
MTC: To ensure that the material complies the PES standard specs.
PP: To ensure that the Instruments are installed as per P&ID and PP as per convenience.
IDS/ISS: To ensure that the instrument comply with the basic requirement.
RFI: To conduct the inspection of completed works. (Request for Inspection)
QR: To maintain the quality records of completed works etc.
QCO: To issue a warning in case of little violation and observation
NCR: To issue a warning in case of serious violation of standard. (Non Compliance Report)
Calibration Report: To ensure parameters are function checked as per IDS.
Hook Up: To ensure that the remote connection of pneumatic is done correctly.
Wiring Diagrams: To ensure that the wiring is done correctly.
Q. What are QA/QC’s ITP’s and QCP? Give a brief.
) ITP: This procedure informs about the kinds of quality check (surveillance, inspection,
witness or hold points) means quality of work being done in proper sequences.
QCP: This procedure address the activities and requirement in details
Q. What is NCR? Why does it need for a QA/QC personal?
) NCR means Non‐Compliance Report, QA/QC personal has reserve the right to issue a warning if
the contractor doesn’t comply or violate with the standard procedure.
Q. What are common PPE required? Give a brief.
) Following are the common PPE for a safe and quality works‐standard procedure:
Qualification : Awareness about all kinds of safety standard/codes and work
procedure.
Experience : Qualified for the works execution.
Use (PPE) : Proper equipments and tools shall be used to avoid injuries/loss.
Safety Shoes, Helmet, Glass, Gloves, Earplugs, Harness proper
tools and certified equipments.
Q. What is redlining? Brief its color coding.
) In case of any change occur to the standard approved drawing while the project is being
constructed or tested the relevant drawing will be “redlined”. Following color coding shall be
used for this purpose:
Red : If any addition required in the drawing.
Green : If any deletion is required from the drawing.
Blue : if any comment is added.
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 3
QA/QC Questionnaires
Q. What is difference between Hazardous and NonHazardous area?
) Hazardous: A Hazardous location is defined as an area where a potential for fire or
explosion exist due to the presence of flammable gases, liquid or vapors,
combustible dusts or fibers and flying in sufficient quantities to produce a
n explosion or ignitable mixture.
Non‐Hazardous: An area where no risk of presence of any kinds exposition.
Q. What are different kinds of certification?
) i) Weather Proof
ii) Dust Proof
iii) Water Tight
iv) Explosion Proof
v) Flame Proof
vi) Intrinsic Safety Proof
Q. What is ISO? Explain some of its standards?
) ISO means International Standard Organization; some of them are as below:
ISO: 9001, ISO: 9002, ISO: 9003 etc.
Q. What are Zone classifications? Give a brief.
) Zone classification is defining the area of hazards, they are as below;
Zone – 0: A zone in which explosions gas/air mixture is continuously present or
present for extended periods, during normal operation.
Zone – 1: A zone in which explosions gas/air mixture is likely to occur in normal
operation.
Zone – 2: A zone in which explosions gas/air mixture is not likely to occur in the
normal operation and if it occurs, it will only exist for a short time.
Zone – 10: A zone in which explosive dust atmosphere is present continuously or for
extended periods of time.
Zone – 11: A zone in which there is likelihood that explosive atmosphere may occur
for short periods due to unsettled dust layers.
Q. What are the standard heights to install the instruments?
) A standard height to install the instruments is 1‐4 meters, but it can vary less or more as per
location’s convenience.
Q. What is Loop – Check?
) To ensure that the system wiring from field to control console functioning.
Q. Explain tuning of controller; (a) Closed Loop Method, (b) Open Loop Method.
Tuning basically involves adjustment of α+I+D parameters to achieve good control. The gain,
time, constants & dead time around the loop will dictate the settings of various parameters of
controllers.
a) Closed Loop Method : Ultimate gain method
b) Open Loop Method : process reaction curve
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 4
QA/QC Questionnaires
Q. What are area classifications? Give a brief.
) As per NEC and NACA, following are the hazard classification;
Class I : Location in which flammable gases or vapors may be present in the atmosphere
in quantities sufficient to produce explosive or ignitable mixture.
Class I gases/vapors are divided into four following groups
Group A: Presence of Acetylene
Group B: Presence of Hydrogen, Butadiene, Ethylene Oxide etc.
Group C: Presence of Ethylene, Cyclo‐Propane, Carbon‐Mono Oxide etc.
Group D: Presence of Gasoline, Acetone, Butane, Propane, Alcohol, natural gas
(Methane) etc.
Class II : Location in which the presence of combustible dust are in the air in sufficient
quantity to ignite or explode.
Class II conductive/non‐conductive dust is divided into three as below:
Group E: Presence of metal dusts (Aluminum, Magnesium and chemical dusts etc).
Group F: Presence of black carbon, charcoal, coal or coke dusts etc.
Group G: Presence of non‐conductive dust (foam, starch, combustible plastic etc).
Class III : Location in which easily ignitable fibers or flying are present but are not likely to
be in suspension in air in quantities sufficient to produce ignitable mixture.
Division – 1 : The Hazards are present continuously or periodically under
normal operation condition.
Division – 2 : The Hazards are only presents during accidental or abnormal
conditions.
Q. Why is flow measured in square root?
) Flow varies directly as the square root of D.P (Differential Pressure) since this flow varies as the
square root of the D.P the pen does not directly indicate flow. The flow can be determined by
taking the square root of the pen.
Say the pen reads 50% of chart.
Q. What is the diameter of the transmitter nozzle?
) 0.030”
Q. How will you work/remove on a control valve which is in line?
) Inlet and outlet discharge manual valve to be
1 1
closed by the operator and tagged.
The valve No. 1 to be closed first. Control valve
should be in fully open condition. Valve No. 2
closed. Secondly the line has to be drained and
depressurized before removing. Figure BY PASS VALVE
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 5
QA/QC Questionnaires
Q. What are the standard nozzles orientations for process control systems?
)
Q. What is different between Open Loop and Close Loop?
) Open Loop : A Loop System which operates direct without any feedback and
generates the output in response to an input signal.
Close Loop : A loop system which uses a measurement of the output signal through
feedback and a companion with the desired output to generate an error
signal that is applied to the actuator.
Q. What is feedforward and feedbackward control system?
)
Figure 1. Feed Forward Control Figure 2. Feed Backward
Feed‐forward control is a system in which corrective action is based on measurement of
disturbance inputs into the process.
Feed backward control involves the detection of the controlled variable & counter acting of
changes in its value relative to setpoint by adjustment of the manipulated variable.
Q. What is Logic Gate?
) A Digital logic circuit with one or more input voltage but only one output voltage.
Q. What does a transmitter O/P signal start from 315 or 420 m.a.?
) Linear and can check up weather its “live zero” or “dead zero”
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 6
QA/QC Questionnaires
Q. Why is M.A. signal preferred for signal transmission?
) Noise reduction and no current drop for long transmission lines.
Q. Explain Cascade control (To prevent outside dist.
) TT
TIC
REMOTE POINT
STEAM
PT
PIC SLAVE
FEED WATER
PV FUEL GAS
Figure. Cascade control
Cascade means two controllers in series, one of them is a matter of primary & the second is the
secondary or slave. The O/P of the slave controller operates the final control.
Q. Explain three element feed water control system.
P2 P3 = R(P2‐P1‐
COMPUTING
RELAY K)+P4+K0
P1 P4 R = GAIN
KI = Adj. Suppression
R0 = Adj. Bras
P3
Figure. FEED WATER CONTROL SYSTEM
Q. What is Foundation Field bus system?
) A fully digital control system is called Foundation Field bus system.
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 7
QA/QC Questionnaires
Q. What are meant FAT, SAT, RAT?
) FAT : Factory Acceptance Test
SAT : Site Acceptance Test
RAT : Run Acceptance Test
Q. What is Microprocessor Control System? Give a brief of PLC, DCS and SCADA?
) Computer based control system is called Microprocessor control system.
The brief of PLC, DCS and SCADA are as following:
PLC : Program Logic Control system
PLC’s are used in practice with the aim of achieving higher degree of availability
or fault tolerance. The types are as follow:
Fault Tolerant: 1 out of 2 objective systems objective: Reduce the probability of
losses of production by switching to a standby system.
Fail Safe: 2 out of 2 system objective: Protect life, the environment and
investment by safely disconnecting to a secure “off” position.
DCS : Distributed Control System.
SCADA : Supervisory Control And Data Acquisition.
Q. What are inspection points for a cable tray installation?
) Material check as per approved spec, size and type, trays hook‐up, proper distance structure,
tray to tray i.e. power/control/signal/low voltage and high voltage, support and fixed strong not
shaking.
Q. What are inspection points for field instruments with impulse tubing?
) Material inspection as per approved spec material, type and size, installation as per Hook‐up,
check line route to avoid any obstruction, check tube bending and check tube support,
compression fitting of ferrules and then test (Hydro‐static test) shall be done.
Q. What are inspection points for cable laying?
) Material inspection as per approved materials, type and size, meggering, cable routing drawing,
completion of cable route (tray, conduit or trench etc) and cable numbering (tags), cable
bending, use of proper tools and equipment for cable pulling.
Q. What are inspection points for Junction Box and Marshalling Cabinets?
) Material inspection, type size as per approved specification, installation hook‐up for frame,
bracket or stands, fixed properly means shaking free, Name Plate and Tag No.
Q. What are standard methods of Ferrules addressing to and from a Junction Box?
) For to side only Terminal’s Address required which shall be close to terminal either side and
complete information shall be off from side after or before as per left and right side.
Q. What are standards of installing a DP Transmitter in gas service and why?
) Inst. (DP Transmitter) in gas service shall be above the process to avoid the malfunctioning and
drain the liquid (condensate) into the process line easily.
MAIN STEAM
PRC
FT
FRC FRC FV
PRIMARY
SECONDARY
FT
RR
FUEL GAS Figure RATIO CONTROL OF FURNACE DIAGRAM
Q. Analogue integrator & analogue differentiator?
)
ANALOGUE INTEGRATOR ANALOGUE DIFFERENTIATOR
C
R
R C
AV V OUT AV V OUT
+ +
∫
V out = 1/RC Vin dt
V out = Rcd/dt Vin
Q. What is absolute pressure?
Absolute pressure is the total pressure present in the system?
Absolute Pressure = Gauge Pressure + Atm. Pressure
Q. What is absolute zero pressure?
Absolute zero = 760 mm Hg.
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 11
QA/QC Questionnaires
Q. What is maximum vacuum?
The maxmm. Vacuum = 760 mm Hg.
Q. What is Vacuum?
) Any pressure blow atmospheric pressure is Vacuum.
Atm. = 760 mm. 0 Vacuums Zero Gauge
Maxm. Vacuum 760 mm Hg
Zero Absolute
Q. What are the primary elements for measuring pressure?
) The primary elements for measuring pressure are:
1. Bourdon Tube
2. Diaphragm
3. Capsule
4. Bellows
5. Pressure Spring
The above are known as elastic deformation pressure elements.
1. Types of Bourdon Tubes.
1) ‘C’ Type.
2) Spiral
3) Helix
2. Diaphragm : The diaphragm is best suited for low pressure measurement
3. Capsules : Two circular diaphragm are welded together to form a pressure
capsule.
Material used: PHOSPHER BRONZE, NI‐SPONGE, STAINLESS STEEL
4. Bellows : Bellows is a one‐piece, collapsible, seamless metallic unit with
deep folds formed from very thin walled tubing.
5. Pressure Spring : Pressure springs of helical or spiral shape are used for measuring
high pressures.
Q. How will you change the action of a control valve?
) If the control valve is without bottom flange the actuator needs to be charged. If the bottom
flange is provided, disconnect stem, separate body from bonnet. Remove the bottom flange
and the plug from body. Detach the plug from the stem by removing the pin, fix the stem at the
other end of the plug and fix the pin back. Turn the body upside down. Connect it back to the
bonnet after inserting the plug and stem. Connect back the stem and couple it. Fix back the
bottom flange. Calibrate the Valve.
Q. On electrical equipment being used in hazardous area you may see the letter UL or
C.S.A, what do these abbreviations stand for?
UL – Under Writer Laboratories
C.S.A –Canadian Standard Association
Q. A 3 phase system has phase to phase 480V AC , what is the phase to earth/neutral
voltage? Show calculation.
480/√3 =277V Line current = √3 phase voltage (√3 = 1.732)
Q. Per NEC , what are the instances where seals fittings are needed?
When a conduct run is crossing hazardous boundaries below ground requires boundary seal,
side, electrical equipment, junction box & conduit. Any breaking, sparking & heat producing
device must be required fittings.
Q. How to minimize the effect of breathing in conduit installation?
Low point drain and breather shall be provided.
Q. Name type of cables suitable for class 1, division 1 and division 2 locations?
Class1, division 1 ,and division2 locations suitable cable is XLPE , Polyethylene , EPR , Armored
cable .
Q. In which NEC article number for the grounding, wiring, conduit & area classification?
Q. Name at least 5 Saudi Aramco Eng’g. Standard which is commonly used for
Instrumentation. Installation and inspection.
Q. What are a closed loop control and its example?
Q. What are the procedure of installing a Gas service, Liquid service & steam service
transmitter?
Q. What is the safety factor for impulse tubing pressure test?
Q. What are the contents of the loop folder?
Grounding (J902)
17.1 General
17.1.1 Electrical systems must be connected to ground for the protection of personnel and
equipment from fault currents (AC safety ground) and to minimize electrical
interference in signal transmission circuits (Instrument circuit ground).
17.1.2 Two grounding systems are required for instrumentation systems:
a) safety ground for personal safety.
b) Instrumentation Safety Ground.
17.2.2 Enclosure for field instruments shall be grounded as follows: (J‐902)
17.2.2.1 Instruments Operating at greater than 50 Volts
The enclosure for Instrument devices operating at 120 V AC or
125 VDC shall be grounded per SAES‐P‐111.
Instrument Circuit Ground (J902)
17.3.1 The purpose of instrument circuit grounding is to reduce the effect of electrical
interference upon the signal being transmitted. An instrument circuit ground
bus shall be provided for consolidating instrument signal commons and cable
shield drain wires. This ground bus shall be isolated from the safety ground
system except at a single tie point as described below.
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 23
QA/QC Questionnaires
Tubing Installation
PPPFL‐001
PIP 4.2.8.1 Interconnecting instrument piping (tubing) between the primary metering
element and the measuring instrument shall be 0.5 inch AISI Series 300 stainless
steel tubing minimum. Tubing wall thickness shall be 0.89 mm (0.035 inch)
minimum. Applicable piping code and process requirements shall prevail.
PIP 4.2.8.2 Interconnecting piping shall be limited to a maximum length of 6 m (20 ft) for
meters in control loops. Interconnecting impulse tubing between a differential
flow element and a transmitter in compressor suction service shall be kept as
close as possible or close coupled.
PIP 4.2.8.3 Interconnecting Seal liquid to protect flow meter impulse tubing and secondary
measurement instrumentation from corrosive fluids or to provide a stable
hydraulic measuring medium shall be free flowing but not volatile under normal
process and external ambient conditions. Seal liquids shall not be miscible with
nor react with the process fluid being measured. Seal liquids shall be selected so
that their potential for contamination of the process fluid is acceptable.
PIP 4.2.8.4 (Addition) PIP PCIDP000 "Differential Pressure Installation Details" shall be used
for interconnecting the flow Differential Pressure Instruments to the root valves
of the differential producers.
PIP 4.6.2.c (Addition) Purging of impulse lines shall be considered only if other methods
have failed to eliminate problems of condensation, vaporization, corrosion or
plugging.
34SAMSS831
Installation
8.1.1 Pressure and D/P instruments in liquid or condensable vapor service shall be self‐
venting (i.e., mounted below the process connections) with all impulse lines
sloping downward approximately 1:10 minimum toward the instrument.
Pressure and D/P instruments in gas service shall be self‐draining (i.e., mounted
above the process connections) with all lines sloping downward approximately
1:10 minimum toward the process connection.
9.2.2 Tubing and Fittings
4.1 General
4.1.1 Instrument air supply systems shall provide dry, oil‐free air to pneumatic
instrumentation, valve actuators, and other services requiring instrument‐quality
air.
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 25
QA/QC Questionnaires
4.8 Instrument Air Distribution System
4.8.1 General Requirements
4.8.1.4 Each branch header shall connect to the top of the main header through
a branch‐line‐size, full‐bore isolation valve.
4.8.1.5 Where there is a general distribution system for more than one
plant, the piping shall be connected in a loop to provide two directions of
supply to each plant. Isolation valves shall be provided to enable
isolation of each plant.
4.8.1.6 Supply takeoffs to individual instruments (a line serving up to a maximum
of four devices) shall connect to the top of the branch header through a
takeoff‐line‐size, full‐bore isolation valve.
4.8.1.6.1 The minimum size of supply takeoffs is ½‐inch.
4.8.1.6.2 Twenty percent (20%) spare takeoff fittings and block
valves shall be installed on the branch header.
4.8.1.7 Instrument air piping shall not be pocketed (i.e., shall not contain, U‐
sections). Instrument air piping shall not be installed underground.
Exception:
Instrument air branch connections may be buried to cross beneath roadways or
fences where there is no existing overhead rack and where the aboveground
support would interfere with crane or emergency vehicle movement. Prior
approval from the General Supervisor, Process Instrumentation Division, P&CSD
is required. Buried branch lines shall have low point drains, stainless steel
construction and external coating per SAES‐H‐002.
4.8.2.1 The pressure drop for piping between the dryer after filter outlet and the
most remotely located user shall not exceed 35 kPa (5 psi) under
maximum service flow rate.
Table 2
Number of Users Pipe Size
1 ‐ 4 ½ inch
5 ‐ 9 ¾ inch
10 ‐ 15 1 inch
16 ‐ 80 1½ inch
81 ‐ 150 2 inch
151 ‐ 300 3 inch
5 Testing (J-901)
Pressure testing of supply system and distribution system per SAES‐L‐056, using
dry instrument air or inert gas is required. Hydrostatic testing of instrument air
piping is not permitted.
1. Design and Selection of Process Control & Instrumentation System should include: Suitability,
Reliability, Quality, Accuracy, and Repeatability.
a) True
b) False
c) None
2. Sour Gas can be used in lieu of Instrument Air.
a) True
b) False
c) None
3. Accepted Field Signals are:
a) 3 – 15 psi, 4 – 20 mA, Hart & any Vendor Protocol.
b) 0 – 12 psi, 0 – 16 mA, 0 – 5V.
c) 0 – 30 psi, 0 – 20 mA, Hart.
4. Instrument & Control system (outdoor, unsheltered) shall be rated for operation for Outdoor
Temperature of:
a) 10 deg. C – 35 deg. C.
b) 0 deg. C – 30 deg. C
c) 0 deg. C – 55 deg. C
d) 10 deg. C – 55 deg. C
e) 0 deg. C – 65 deg. C
5. Downstream edge of orifice shall be Square & Sharp so they will not show a Beam of Light when
checked with an Orifice Edge Gauge.
a) True
b) False
c) None
6. Orifice Bore BETA is ratio of pipe ID and pipe OD.
a) True
b) False
c) None.
7. At what temperature is Degree Centigrade = Degree Fahrenheit
a) 32
b) 0
c) –40
d) 40
8. For temperature compensation in flow measurement with orifice, Thermowell shall be located
not less than 2 and no more than 30 pipe dia. downstream.
a) True
b) False
c) None.
CORRECT ANSWERS:
1 (a); 2 (b); 3 (a); 4 (e); 5 (b); 6 (b); 7 (c); 8 (b); 9 (b); 10 (b); 11 (c); 12 (a); 13 (b); 14 (a); 15 (b); 16 (c); 17
(b); 18 (b); 19 (a); 20 (b); 21 (a); 22 (a); 23 (b); 24 (d); 25 (b); 26 (b); 27 (d); 28 (b); 29 (b); 30 (b).
Basic QA/QC Questions & Answers |Compiled & prepared by Abu Zarrar Quaisi |AL‐Qamar| 31