Condition Monitoring of Steam Turbines by Performance Analysis - R Beebe
Condition Monitoring of Steam Turbines by Performance Analysis - R Beebe
JQME
9,2
Condition monitoring of steam
turbines by performance
analysis
102 Ray Beebe
Gippsland School of Engineering, Monash University, Churchill,
Victoria, Australia
Keywords Turbines, Testing, Condition monitoring, Preventive maintenance,
Performance measurement
Abstract Many power generation steam turbine generators today are required in service well
beyond their intended lifetimes. Dismantling for inspection is expensive, and owners need to
consider all relevant information in making the decision. Application of condition monitoring in all
the applicable methods is justified, with each showing different degradation modes. Performance
analysis is less well publicised, yet unlike vibration analysis and oil debris analysis, it will show
conditions which reduce machine efficiency and output, such as deposits on blades and erosion of
internal clearances. Data obtained from tests before and after overhaul also reveal whether any
restorative work achieved the expected improvements in performance. The paper outlines, with
examples, some condition monitoring techniques that have contributed to retaining some large
fossil machines in service for up to 17 years without opening high-pressure sections.
Practical implications
The condition monitoring technique of performance analysis is less well known
that the other methods, yet it is the only way of detecting and monitoring some
modes of machine degradation. Large steam turbines are expensive machines
of critical importance, and also expensive to maintain. Maintenance decision
makers, therefore, need to take into account the needs of their business,
recommendations from the original equipment manufacturer, their own
experience and that of other users of similar plant, and information on
condition available from the plant.
This paper contains examples of condition monitoring by performance
analysis on large steam turbines that are intended to help engineers working in
power generation in the application of condition monitoring. Although their
effect can be significant, many changes are small and detection requires special
test instrumentation. Much useful work can, however, be done with plant
instruments. The overall aim is to assist in making the decision to take these
machines from service only when justified technically and economically.
Introduction
Steam turbines are the mainstay of electricity production worldwide. Today’s
Journal of Quality in Maintenance
Engineering competitive electricity generation market has increased the pressure to keep
Vol. 9 No. 2, 2003
pp. 102-112
power generation plant online as and when required.
# MCB UP Limited
1355-2511
A contributing factor in providing ongoing assurance of acceptable plant
DOI 10.1108/13552510310482361 condition is the use of condition monitoring. Methods should be applied
according to the modes of degradation expected. Vibration analysis provides Condition
much of this assurance, and has developed such that access to on line vibration monitoring of
data is available to experts who may be located remote from the plant. Damage steam turbines
to blading should be detectable by vibration analysis, but other problems such
as deposition, erosion of blading and internal steam leakages require
performance analysis.
As other degradation modes can only be detected by visual inspection or 103
non-destructive testing, eventually casings do require to be opened for
inspection. This is particularly so for the many large power generation
machines continuing in service beyond their intended design life.
Performance analysis can be applied to most plant, rotating and stationary.
It is the one condition monitoring technique, which allows the optimum time for
restorative maintenance to be determined, where the deterioration results in
increased fuel consumption, or in reduced output, or both (Beebe, 1998a).
It should be accepted that a turbine outage after a long time in service would
probably take longer than if scheduled more frequently, as internal distortion is
likely to have occurred. Also, parts such as casing studs will probably need
replacement (Coade and Nowak, 1993). Once a casing is opened and clearance
measurements made, it is possible to estimate the performance improvements
achievable by refurbishment and so justify the expenditure (Kuehn, 1993;
Sanders, 2002). However, it is clearly preferable to try to determine the internal
condition first by testing.
The overhaul decision should not be made unless there is a compelling
technical or economic reason for opening a casing. A current EPRI project is
aimed at extending the accepted interval between overhauls (McCloskey et al.,
1995; Roemera et al., 1998; Roemer et al., 2000a, b). Condition monitoring by
performance testing has been used to extend time between opening of casings
to up to 17 years, making its cost/benefits very favourable (Beebe, 1995; Vetter
and Schwiemler, 1989).
Condition monitoring can also be used to evaluate the effect of maintenance
or modification work on the steam path. This is of great benefit when justifying
future work.
Table I gives some main degradation problems with steam turbine-
generators, together with an outline of how condition monitoring can detect
them.
The temperatures of main inlet and hot reheat steam are set as close to
datum as can be achieved. This is usually the same as the rated values.
The inlet pressure is set to the datum value. As most turbines have
capacity beyond their nameplate rating, the standard inlet steam
pressure may need to be below the rated value if undesirably high
outputs would result (Beebe, 1998c).
Condenser pressure is largely a function of seasonal conditions and
weather, and is usually taken at the best attainable on the day.
Extractions to feedwater heaters should be all fully open. If feedwater
heater unreliability means that some heaters are out of service for long
periods, that condition may have to be used as datum, unless a method
of allowing for this effect on turbine output can be derived.
Test readings a test run of an hour or so during steady conditions are carefully
made using calibrated test instruments, with two separate measurements of
each point. Readings of test transducers can be made manually, but it is now
usual to use a data logger coupled with a computer. With the exception of some
minor flows read from plant instruments and used only in correction factors,
test measurements of flow are not required. This simplifies the test
considerably and minimises the cost considerably compared with the full heat
rate test used for the acceptance tests.
The generator MW output is corrected for any variations from the datum
terminal conditions. For example, if the condenser pressure on the test is higher
than the datum, then the turbine output will be less that expected at datum
condenser pressure. Correction data are usually provided by the manufacturer
for use in the acceptance tests but can be obtained using cycle modelling
programs or from special tests (Beebe, 1998c). With the instrument calibration
information available, the calculations can be performed immediately following
the tests.
JQME For some plant items, it is possible to use the normal plant instruments and
9,2 data processing system to determine condition parameters (Beebe, 1998b). In
the case of steam turbines, a more refined method using test quality
instruments is needed to give warning well in advance of changes evident from
permanent instrumentation systems (Groves, 1996). This may be possible with
highly stable transducers of recent design, or with adequate calibration
106 arrangements.
Correction Correction
Test data Test A factor Test B factor
Test A
High pressure casing (from main stop valve inlet) 85.5 per cent.
Intermediate pressure casing (from reheat stop valve inlet) 88.2 per cent.
Text B
High pressure casing (from main stop valve inlet) 83.8 per cent.
Intermediate pressure casing (from reheat stop valve inlet) 88.3 per cent.
A relative deterioration in the HP casing is evident. Further study would be
made of any other parameters available in this area.
JQME Parameter Comments
9,2
Steam strainer pressure drop Best measured with a differential pressure transducer
rather than an upstream and a downstream pair. An
increase indicates blockage, possibly from metal
particles from boiler tubing, or welding repairs
108 Corrected first stage pressure At VWO, proportional to steam flow through the
turbine, indicates first stage condition. An increase
points to upstream erosion, or downstream blockage,
and vice versa
Section enthalpy drop efficiency Calculated using steam tables computer program. A
(superheated steam sections) drop indicates blade fouling, or erosion damage
Section pressure ratios Stage pressures can be corrected to standard inlet
pressure (ASME, 1985), but any error in measuring it
is applied to all the stage pressures. Ratios use only
the outlet and inlet pressures of each section. Changes
show up erosion or deposition
Extraction temperatures to According to design, a higher than expected steam
feedheaters in superheated sections inlet temperature may indicate relative internal
bypassing leakage in the turbine upstream of the
extraction point
Extraction temperatures to Temperatures above saturation temperature indicate
feedheaters in saturated steam leakage of steam from a stage upstream of the
sections extraction point
Drain line temperatures from Where available, these may indicate relative leakage,
casings, or from shaft seal (gland, according to design. A similar approach can be used
packing) sections for points before and after pipe junctions of two
streams of different temperatures. Pipe surface
temperatures are often sufficient for repeatable
assessment
Table III.
Some parameters Estimated N2 packing leakage (on Test by varying relative inlet steam temperatures and
showing condition of turbines with combined HP-IP observing effect on IP enthalpy drop efficiency (Cotton,
turbine sections casings) 1993)
109
Figure 1.
Section of Mollier chart
showing expansion line
Figure 2.
Stage pressures along
turbine
Application of all paremeters Condition
A 350MW turbine as shown earlier above showed a significant reduction in monitoring of
corrected VWO output. As this was only the second series of tests on this new steam turbines
machine, further investigation proceeded (Beebe, 1978, 2001).
Calculation of enthalpy drop efficiency and pressure ratio for each section
localised the cause of the reduction as the intermediate pressure section. As this
base load machine had been in continuous service for six months, it was 111
postulated that blade deposition had occurred.
During coming off line for the next planned outage, a steam forced cool was
conducted. Here the steam temperatures at main inlet and reheat inlet are
reduced in steps as load is reduced over a few hours, taking care to observe
operating limits such as the margin above saturation temperature. This
practice is common where prompt access is required to the turbine, as it can
save many hours over cooling at the natural rate.
Tests repeated after the outage revealed that the corrected VWO output had
returned to its original value, and the section parameters had also reverted.
Learnt here is that steam forced cooling should be standard practice before
outages on machines which have long steady load service. The condensate
should be sampled and tested for signs of deposits from the blading.
Comparative tests
Where steam flows through blading sections can be found, further parameters
of condition are available.
Measurement of cycle flow is expensive, often requiring several flow
measurements in the cycle. Some plants have a high accuracy flow element for
final feedwater flow, with some having a removable inspection port, but these
are not common. In some situations, a comparative flow measurement is useful,
even without a high accuracy element.
Blades of a new design were installed in the last stage sections of a turbine.
Significant improvements in efficiency and output were promised.
Testing at VWO was run immediately before and after the outage. Flow was
calculated using the permanent feed flow element, which is welded in the line.
Test quality transducers were installed to measure its differential pressure
output. The condition of the flow element was assumed to be unchanged during
the outage period.
Test results showed that VWO output and efficiency had increased in the
order predicted, however, some of this may have been due to other work done
during the outage. Some casing joint distortion was found and the joint was
remachined on one casing. Some changes in section parameters in this casing
were observed (Beebe, 2000).
This case does highlight the difficulty of distinguishing between the effects
of two or more maintenance/modification jobs, both of which should have an
impact on performance. However, in the future, similar deterioration in this
area should be detectable in advance of proposed work, and the improvements
in performance used to justify maintenance action.
JQME Conclusion
9,2 From the cases described, it is concluded that condition monitoring by
performance analysis is a most valuable input in assuring continued operation,
and when deciding and justifying major maintenance actions.
References
112 ASME (1985), ``Simplified procedures for routine performance tests of steam turbines’’, ANSI
PTC 6S report 1974, reaffirmed 1985.
Beebe, R. (1978), ``Recent experience with condition monitoring of steam turbines by performance
analysis’’, Transactions of Mechanical Engineering, Institution of Engineers, Australia.
Beebe, R. (1998a), ``Condition monitoring by performance analysis to optimise time for overhaul
of centrifugal pumps’’, Proceedings of 52nd Meeting of Society for Machinery Failure
Prevention Technology, Virginia Beach, VA.
Beebe, R (1998b), ``Predictive maintenance by performance monitoring of plant’’, Proceedings of
52nd Meeting of Society for Machinery Failure Prevention Technology, Virginia Beach, VA.
Beebe, R. (1998c), ``Steam turbine generator condition monitoring by performance analysis:
derivation of correction factors by test’’, Proceedings of 11th COMADEM 98, Tasmania,
Vol. 1, pp. 87-92.
Beebe, R. (2000), ``Case studies in condition monitoring of low pressure steam turbines by
performance analysis’’, Proceedings of 13th COMADEM, Houston, TX.
Beebe, R. (2001), Machine Condition Monitoring, MCM Consultants.
Coade, R. and Nowak, S. (1993), ``Remaining life study of a 350MW HP/IP turbine’’, Conference on
Pressure Vessels and Pipework, Sydney.
Cotton, K.C. (1993), Evaluating and Improving Steam Turbine Performance, Cotton Fact Inc.
Groves, K. (1996), ``Turbine steam path monitoring using plant DPA system’’, unpublished
degree major project, Monash University, Melbourne.
Kuehn, S.E. (1993), ``Steam turbine technology keeps pace with demands’’, Power Engineering,
March, available at: www.encotech.com/software/eSTPE.html
McCloskey, T.H., Pollard, M.A. and Schimmels, J.N. (1995), ``Development and implementation of
a turbine-generator outage interval extension strategy’’, PWR-Vol 28 ASME/IEEE
International Joint Power Generation Conference, pp. 485-91.
Roemer, M.J., Kacprzynski, G.J. and McCloskey, T. (2000b), ``Advanced steam turbine-generator
maintenance planning using prognostic models’’, Proceedings of 54th Meeting of the
Society for Machinery Failure Prevention Technology.
Roemer, M.J., Orsagh, R. and Hesler, S. (2000a), ``Turbine-generator asset management using
EPRI’s Turbo-X program’’, EPRI Welding Conference, May.
Roemer, M.J., Dewey, R.P., Atkinson, B., Mauney, D.A. and McCloskey, T.H. (1998), ``Turbine-
generator maintenance outage optimisation: probability/risk assessment of net present
value’’, Proceedings of 52nd Meeting of Society for Machinery Failure Prevention
Technology, Virginia Beach, VA.
Sanders, W.P. (2002), Turbine Steam Path Maintenance and Repair, Vol. 1, PennWell, Tulsa, OK.
Vetter, H. and Schwiemler, G. (1989), ``First turbine inspection after a 15-year operating period’’,
VGB KRAFTWERKSTECHNIK, Vol. 69 No. 10, October, pp. 835-45.