Technical Seminar

HULL BLOCK INSPECTION

TUNGLINH 27th Feb, 2012

1.PREPERATION
Standards (acceptance criteria): Yard Quality Standard, IACS Rec.47 List of WPS, Material Certificates Approved Drawing + Letter, Fire divisions (superstructure) NDT condition QC Inspection Record

2.SAFETY FIRST
Our work is never so urgent or important that one cannot take time to do it safely.

CHECK LIST: Personal Protective Equipment (PPE) Scaffold, ladder, harness Ventilation Protected opening

3.EXECUSION
1. 2. 3. 4. 5. 6. 7. Surveyor equipments Deformation & Straightness Misalignment, Missing of structure Thickness, Material grade Criteria areas Continuous of structure Welding sequence & Welding defects

3.1 Surveyor Equipments


Weld Gauges Hammer Ruler Taper Gauge Gap Thickness Feeler Gauge Caliper Camera Light

3.2 Deformation & Straightness


IACS Rec.47, Table 6.10, 6.11

3.3 Misalignment

3.4 Material & Thickness


Base on Expansion Drawing to define Grade of Material & Thickness of Plating and Stiffeners

3.5 Criteria Areas


Approved Drawing List of criteria areas + NDT areas Marked defects of QC High grade material Curved form plating WT, OT bulkhead (prevent leaking of water)

3.5 Criteria Areas


Beside that: High stress, high corrosion areas

High stress areas


Side shell, Strong member (girder, stringer) Conner Toe of brackets

High stress areas

High corrosion areas


Ballast tanks PSPC Stern, Fore of ship

High corrosion areas

High corrosion areas

3.6 Continuous of structure

3.7 Welding sequence & Welding defects


Welding plan IACS Rec.47

4.REPORT
Clearly writing in English (simple and easy to understand) Save to system (NPS)

Technical Seminar

THANK YOU!