Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Pertmaster

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

Pertmaster Risk Analysis Software

Project Risk Analysis (with Pertmaster)


AACE Toronto Section October 2, 2008
Brought to you by:

Emerald Associates 2007

Presenter

Ian Nicholson, P.Eng. VP Solutions, Emerald Associates


Mechanical Engineer Primavera Systems Authorized Trainer, Consultant Pertmaster Authorized Trainer, Consultant iann@emerald-associates.com (403) 686-8957

Emerald Associates 2007

Page 1

Pertmaster Risk Analysis Software

My Company
Emerald Associates Calgary - Edmonton - Toronto Primavera Authorized Reseller for AB, SK, MB, ON Primavera Premier Solution Provider Pertmaster Solutions Partner for Canada Common Point Certified Partner On-Time Systems Reseller

Emerald Associates 2007

Emerald Associates Our Clients


Oil & Gas Suncor Energy Shell Canada & US British Petroleum Husky Petro-Canada Encana Trident Exploration CNRL Nexen Petro-Chemical Agrium Nova Chemicals Electrical Bruce Power OPG Connecticut Light & Power Manitoba Hydro Transalta ENMAX Government Milwaukee Metropolitan Sewerage District Capital Health Authority Transportation CPRail Contractors Ledcor Flint Stuart Olson Redpath Genivar Engineering Wardrop VECO Bantrel Fluor Jacobs Worley Parsons/Colt

Emerald Associates 2007

Page 2

Pertmaster Risk Analysis Software

Agenda
Why & How to Conduct Risk Analysis Risk Theory Pertmaster Application Real World Case Study

The advantage of not planning is that failure is not preceded by long periods of depression, worry and anxiety. - Anonymous

Emerald Associates 2007

Why is Schedule Risk Analysis Suddenly So Popular?

Because Common Platforms Common Coding Central Databases Have now made it possible to produce meaningful roll-ups and powerful, useable results But really because of -

Emerald Associates 2007

Page 3

Pertmaster Risk Analysis Software

Results like these

Emerald Associates 2007

Uncertain spend curves by period

Emerald Associates 2007

Page 4

Pertmaster Risk Analysis Software

Confident Prediction of Project Completion

Emerald Associates 2007

Why is this Suddenly so Important?


Because new US (SOx) and Canadian (MI-52-109) legislation means CEOs and CFOs must sign off personally that: All controls are in place and working That there are no known, unstated, factors that could affect the financial position of the company. And accounting methods are poor at predicting future risks from current commitments that could reflect on the financial statements.

Emerald Associates 2007

Page 5

Pertmaster Risk Analysis Software

How Does Risk Analysis Answer the Need?

1. Most existing software does static spreadsheet analysis without the dimension of time. 2. These spreadsheets are often created by accountants who tend to be focused on actual records. Even Earned Value is backward focused. 3. Pertmaster starts from the resource loaded schedule created by the project staff. 4. Schedules start from current actuals and look forward. 5. Such a schedule is rolling forward & constantly evolving as new events occur, exposures are evaluated and actual results received. 6. Thus the source data is the actual detailed data created and used by the people closest to the project.

But.

Emerald Associates 2007

The Other Side of the Coin


1. This is schedule based analysis so a weak schedule means an even weaker risk analysis. 2. However, it should reflect time, productivity & costs. 3. Perfect schedules are rare so it is a matter of deciding if the weaknesses are critical. 4. The risk process is fundamentally qualitative so dont get too hung up on theoretical quantitative procedures. 5. A slick report based on garbage is just toxic garbage.

Emerald Associates 2007

Page 6

Pertmaster Risk Analysis Software

So how do we get meaningful results?

Emerald Associates 2007

Pertmaster Risk Methodology


Schedule Review Risk Ready State Risk Risk Planning Reporting Review for logic & errors Risk Identification Estimate Uncertainty Risk Events: Risk Register Risk Develop Risk Model Management Map Risks to Activities Process Risk Risk Preliminary Analysis & Review Response Identification Impacted Risk Plan Monte Carlo simulation Final Model & Report Risk Assessment Risk Event plan Mitigation planning Based on: PMBOK Chapter 11, APM PRAM Guide, AS/NZ S4360
Emerald Associates 2007

Page 7

Pertmaster Risk Analysis Software

1 Interviews
Prepare Focus on critical or near critical sequences. Think about things not scheduled but impacting. Identify people to interview in each sector. Prepare a bullet point check list for each. Interview One-on-one is most effective Dont lead them, listen and prompt from the bullet points. Most important to them is what affects them most; it may not be important to the project

Emerald Associates 2007

2 Interviews
A Recent Example From Interview Sheets, Write up Interviews

Catch the essence only Identify risk categories Sort comments

Emerald Associates 2007

Page 8

Pertmaster Risk Analysis Software

3. Quantify the Risks


Take the risks identified and relate them to the schedule and quantify the impact Determine whether these risks are uncertainty or risk event

Emerald Associates 2007

4. Build the Model


Build the risk model

Emerald Associates 2007

Page 9

Pertmaster Risk Analysis Software

5. Review & Understand the Results

Emerald Associates 2007

6. Develop Mitigation Strategies

Emerald Associates 2007

Page 10

Pertmaster Risk Analysis Software

7. Implement Changes

Emerald Associates 2007

8. Repeat
A risk model is a living document It is important to update the risks and models frequently to obtain best results Make this part of your project management methodolgy Dont be a seagull!

Emerald Associates 2007

Page 11

Pertmaster Risk Analysis Software

An introduction to schedule risk analysis theory

Emerald Associates 2007

Overview of traditional CPM

10d

--/--/--

Predicts single completion date and cost Uses single values for activity durations and costs Does not take uncertainty into account
Emerald Associates 2007

Page 12

Pertmaster Risk Analysis Software

CPM with schedule risk analysis

10d

--/--/-8d 10d 15d

Quantifies probability of completing project on time and budget Uses estimates for durations and costs Takes uncertainty into account to predict a realistic end date
Emerald Associates 2007

Monte Carlo (Latin Hypercube) Simulation Triangle divided up into equal segments One segment randomly selected for each iteration Skew impacts distribution of results Reveal hidden critical paths
20 19 12 18 11 17 10 16 9 15 8 14 7 13 27 26 25 24 23 22 21

10 days 9 days 14 days 17 days 10 days

2 1

6 5 4 3

33 32 31 30 29 28

14 days
38 37 36 35 34

13 days
42 41 45 40 44 47 39 43 46 48

7 days 10 days 12 days

Min

Likely

Max

10 days

Emerald Associates 2007

Page 13

Pertmaster Risk Analysis Software

Better estimates for completion dates


Single-Path Schedule CPM schedule finishes on December 10, relies on combinations of durations that equal 70 days

Likelihood of the 10th December?

Emerald Associates 2007

Exercise: Find out chance of meeting 10th December

Emerald Associates 2007

Page 14

Pertmaster Risk Analysis Software

Why is there only a 18% chance?


Distributions are skewed most likely is nearer to minimum than maximum

There is a greater chance an activity will take more time rather than less time to complete.

Emerald Associates 2007

Effect of skewed distributions


What would be the chance of completing the project on time if each distribution was symmetrical?

50%

Therefore: With skewed distributions the chance of hitting a schedule end date will be less than 50%

Emerald Associates 2007

Page 15

Pertmaster Risk Analysis Software

Effect of parallel paths


This project also completes on December 10 Is it more or less risky than single path? Likelihood of December 10th finish?

Emerald Associates 2007

More riskyMerge Bias Effect

Emerald Associates 2007

Page 16

Pertmaster Risk Analysis Software

Combined effect of skew and parallel paths

Skewed Distributions

+
Parallel Paths

=
Typically less than 20% chance of hitting completion date

Emerald Associates 2007

Why run a quantitative analysis?


To help create more realistic schedules

To improve awareness of project risk and uncertainty

To identify schedule assumptions

Communication: Develop a better understanding of the schedule amongst the project team

Emerald Associates 2007

Page 17

Pertmaster Risk Analysis Software

Running a quantitative risk analysis

Emerald Associates 2007

Checking the schedule


Before considering a risk analysis, check the quality of the schedule Reports | Schedule Check Report Produces a report in your browser Can be summary or full report Content can be customized Can be badged

Emerald Associates 2007

Page 18

Pertmaster Risk Analysis Software

Schedule Checker
Checks schedule quality Constraints

Open-ended tasks Start to Finish links Negative lags Positive lags Long lags Broken logic Calendars on lags Link on summary tasks (MS Project) Aim: Reflect reality
Emerald Associates 2007

Run Analysis
What is the chance of completing our project on time?

Emerald Associates 2007

Page 19

Pertmaster Risk Analysis Software

Understanding Project Drivers

Emerald Associates 2007

Identify High Risk Activities


The critical path is useful Determines the earliest the project can finish Delay on the critical path delays the project The path that most deserves risk management Duration Sensitivity Shows how closely correlated changes in one activity are to changes in the overall project Criticality Index During the risk analysis, the number of times an activity was critical is recorded The percentage of iterations each activity was critical = Criticality Index Cruciality Product of Sensitivity and Criticality

Emerald Associates 2007

Page 20

Pertmaster Risk Analysis Software

Exercise: Criticality Index (1 of 1)

Unit 1 no longer critical but has more uncertainty (company has not made this unit type before)

Unit 2 given less uncertainty (company has made similar units before)

Unit 2 is on the Traditional Critical Path should we concentrate on Unit 2?

Emerald Associates 2007

Criticality Index Shows Unit 1 more risky!


Risk | Run Risk Analysis CPM shows we should focus on Unit 2?

Risk Analysis shows we should focus on Unit 1 Traditional CPM can Mask Risks!

Emerald Associates 2007

Page 21

Pertmaster Risk Analysis Software

Criticality/Sensitivity/Cruciality
Criticality identifies activities that are likely to be on the critical path given the uncertainty in the schedule. Sensitivity relates activity changes to overall schedule changes Therefore Reduce durations and/or uncertainty on activities with a high sensitivity/cruciality to improve the chance of completing the project on time. High Cruciality: If task is delayed, project is delayed. Focus on the tasks with high cruciality index first.

Emerald Associates 2007

Revising Estimates
If the contract has already been signed, we need to improve chances of meeting the contracted date The tornado helps us: Risk | Tornado Graph

Emerald Associates 2007

Page 22

Pertmaster Risk Analysis Software

Revising Estimates
As Refurbish Premises is the biggest driver to the project duration, this is the best place to mitigate the risk We can reduce its worst case by obtaining a guarantee from the contractor Change Maximum Duration

Emerald Associates 2007

Revising Estimates
Analysis now shows new top driver

Emerald Associates 2007

Page 23

Pertmaster Risk Analysis Software

Questions..
Questions? Time Check Real Life Example

Emerald Associates 2007

Page 24

You might also like