Energy Optimization
Energy Optimization
Energy Efficiency $80 billion per year $80 bn/year global capex through 2020, to capture energy efficiency savings, with >10% IRR Refining & chemical industry annually spends $50-100M on energy per plant 70% of oil companies rank energy efficiency as the best method to meet CO2 caps
GHG Mitigation $680 billion per year $680bn/year incremental investment by 2020, to achieve IPCC* target of 35% below 1990 emissions levels $5-10bn/year estimated market for CCS (carbon capture & storage) in 2030 Process industries account for 36% of global GHG emissions
Alternative Energy $20 trillion total $20 trillion total global investment through 2030 in alternatives Alternative energy accounts for 13% of global energy supply, and is growing 2-3 times faster than traditional sources 53% of oil companies currently involved in some type of renewable energy project
*Intergovernmental Panel on Climate Change, whose reports drive initiatives like the Kyoto Protocol Sources: McKinsey Investing In Energy Productivity, Global GHG abatement study; Daily Telegraph A clean sweep for coal; International Energy Agency reports; WRI 2005 report; Hydrocarbon Publishing 2010 report 2010 Aspen Technology, Inc. All rights reserved |
100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
92%
53%
Energy Efficiency
GHG Mitigation*
Renewable Energy
Refinery energy costs: $75 -140M p.a. Global spend on energy: $57 108B p.a.
Chemicals energy costs: $75 -125M p.a. Global spend on energy: $20B p.a.
Lifecycle
|
5-20%
3-5%
2-10%
2-10%
100%
aspenONE Energy Efficiency Solutions
70-90%
Design
Plant Design
Challenge How to identify and screen the best design options How to balance equipment, costs & energy usage Energy/yield trade-off Technology selection Utility system design
Impact Challenge Sub-optimal decisions Takes longer to develop alternatives Retrofits more costly than needed Higher Capital & Energy Costs Identify best design alternatives including equipment, capital costs & energy efficiency Solution
Technology Services
Process Synthesis Pinch analysis Process Consulting Process improvement Energy & emissions reduction Debottlenecking Steady state modeling Column analysis Distillation systems Column sequencing Heat/mass exchange Conceptual Design Economic analysis Industry Sectors Refining Chemicals Energy
Conceptual Engineering
Select Process Technology
Basic Engineering
Detailed Engineering
Plant Operations
Identify Plant Capital Projects
Maintain Equipment
FEED
Procure and Control Equipment, Materials and Services
10
Refining
11
12
13
Independent design consultancy. Leveraged by full use of AspenTechs engineering, simulation and design tools. Optimise the process then design the utility system to best supply the process demands. Process / Utility system interface can often be improved.
Optimal Heat Exchanger Network design (Pinch Analysis) Optimal site wide utility system design accounting for process heating and power demands Comparative capital & operating cost assessment of design options. Identification of most cost effective design. Feasibility study level of detail New design and retrofit
14
Identify:
Utility requirements Operating margin for alternative configurations
Using industry standard linear modelling LP vectors updated using Heat and Mass balanced kinetic models for FCC, CCR, ISOM, HCU or from licensor data Independent of Licensor Independent of EPC contractors Experienced personnel in LP Optimisation, refinery configuration studies and refinery unit design
15
16
300.0
TEMPERATURE C
250.0
200.0
150.0
100.0
50.0
0.0 0.0 20.0 40.0 60.0 80.0 100.0 HOT 120.0 COLD 140.0
ENTHALPY X10 3 kW
19
20
Data Extraction
21
Condenser Condenser
H
22
Process with low temperature source that cannot generate steam Indirect Heat
Integration thru a local steam header
AIR/CW
Process A
Process B
CW
Process A
Process B
Direct inter-unit integration by changing the rundown temperature Transfer product from Process A to Process B so temperature of product is below Process A pinch and above Process B pinch
2010 Aspen Technology, Inc. All rights reserved |
23
Cold utilities
24
Fue HP l
HP MP
MP LP
LP
Smaller boilers!
Reduction in fuel consumption
+
Fuel
HP MP
+ +
HP MP IP
LP
Smaller CW towers!
LP LLP LLP
25
27
28
A002 19167 kW
46.0 C
A001 5268 kW
20.0 bar 48.8 C
E005 1960 kW
40.9 C
101 69 57
E008 650 kW
40.0 C
E001 329 kW
35
64.7 C
76.3 C
C001 Depropanizer
33
C002 Deethanizer
100
59 1 1
C003 C3 Splitter
67.0 C
107 C
E002 5414 kW
70.2 C
29
100.0
TEMPERATURE C
80.0
Ideal Profile Block C002: Column Grand Composite Curve (T-H) Actual Profile
95
Temperature C 70 75 80 85
90
60.0
70
75
58
40.0
65
56
57
Temperature C 55 60
20.0
60
55
10.0
15.0
ENTHALPY MW
0.25
0.5
0.75
45
1.25
1.5
Temperature C 51 52 53
50
50
1.75
50
54
65
55
2.25
3.25
3.5
3.75
4.25
4.5
4.75
5.25
47
48
-0.2
-0.1
0.1
0.2
0.3
49
0.4
0.5
0.6
0.7
0.8
0.9
1.4
1.5
1.6
1.7
1.8
1.9
2.1
2.2
2.3
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 10.5 11 11.5 12 12.5 13 13.5 14 14.5 15 15.5 16 16.5 17 17.5 18 18 Enthalpy Deficit MW
30
A002 17528 kW
41.2 C
A001 4076 kW
19.3 bar 48.2 C
E005 2039 kW
40.5 C
101 69 57
E008 650 kW
40.0 C 64.7 C
E001 0 kW
35 34
42
C001 Depropanizer
33
C002 Deethanizer
100
59 1 1
C003 C3 Splitter
63.0 C
105.9 C
E002 4642 kW
Feed tray optimization Column resequence - Requires lower depropanizer pressure & Save one exchanger vapor feed to C3 Splitter Both hot/cold utility savings are 2.4 MW each
31
Heat Balance
DTMIN =20.00
300.0
250.0
MPGEN
TEMPERATURE C
Base GCC
200.0
150.0
100.0
HW1
50.0
BFW
COLD
0.0 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0
UTIL
DTMIN =20.00
300.0
250.0
MPGEN
TEMPERATURE C
200.0
Target GCC
LLP
Debutanizer
Indirect integration
Deisobutanizer Depropaniser
150.0
100.0
HW1
Deethanizer
50.0
BFW
C3Splitter
COLD
0.0 0.0
FCC GCC
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
UTIL
Potential to increase MPS gen by 13.7 t/h by increasing LLPS use by 7.7 t/h Potential to increase hot water gen by 7.7 MW
32
40oC
E305
48oC
308 C
C202B
E303B
70oC
330oC
To reactor
275oC
117oC
Proposed flowsheet
Remove feed heater from slurry pumparound and increase heat duty of steam generator Switch LCO pumparound from stripper reboiler and hot water heating into MP BFW heating and into feed heating Increase heat duty on the stripper reboiler and switch the other stripper reboiler from LCO pumparound into LLP steam.
2010 Aspen Technology, Inc. All rights reserved |
33
34
Energy efficiency can be addressed in all phases of plant life cycle Design efficiency into your plant (new or existing) Include energy and GHG in planning and scheduling solution Employ an energy performance management system to operate utility system better, manage contracts, improve decisions APC strategy should include energy and GHG AspenTech offers a comprehensive suite of products and expert services to help reduce energy in all these areas
Optimize Energy & Emissions lower costs & meet environmental requirements
38
Questions?
39
Additional slides
40
41
Water
Petronas, Melaka Marathon Ashland, Robinson Phillips, Texas Crown , Texas Engen, Durban
Capital cost reduction - hydrogen Energy reduction Yield and capacity Energy reduction
42
43
44
45