T 36
T 36
T 36
36
OCT-DEC 2010
section 1 was 427 m, section 2 was 53 m and section 3 was 1135 m. (See Figure2) 2) Hold back (Dead Man Anchor) DMA system Hold back DMA system designed to assist dummy pipeline laying and pulling. The system consisted of two anchors (DMA anchor and piggyback anchor) and an anchor wire named DMA wire. The system should be installed prior to dummy pipe lay and the load test should be performed on the dead man anchor (DMA) prior pipe lay to ensure its capacity.
Figure 2 Dummy pipeline start laying location
The DMA wire was divided into 6 pieces in order to be fit on small pipe-lay vessel. For each piece DMA wire there were open and closed sockets attached at both ends. 3) Suction Anchor The suction anchor rigging arrangement provided accurate positioning for the dummy pipe, a connection cable was used to connect the dummy pipe termination head and suction anchor. The length of connection cable should be accurately calculated. The suction anchor was designed with 105 ton pulling resist.
installation operation also faces the problems of protecting existing pipelines and cables as the new pipeline cross them. During installation, the new pipelines must be accurately positioned to allow their connection to PLET and platforms. All of the challenges need to be carefully evaluated and planned prior installation.
4) The Existing Facilities Protector Steel protection structures for existing cable and pipeline were installed prior to wire and pipe laying and pulling operations. Mud mat and tyre girdle structures designed to prevent sinking or slipping occur. Figure 3 shows the protection system.
OCT-DEC 2010
37
2) Dummy pipe installation a) Dummy pipe laying outside FPSO safety zone b) Dummy pipe pulling through underneath FPSO c) Dummy pipe positioning 3) Normal pipeline laying Three types of vessel were used in installation. a) Anchor Handling Tugs (AHT) used for deployment of DMA wire and pipelines which are identified as AHT #1 and AHT #2. b) ROV Support Vessel (RSV) used for the pre and post lay survey and monitor layback and the transfer of the DMA cable under the FPSO. c) Positioning tugs used for holding FPSO and keep it perpendicular to DMA wire during installation operation.
Step 1 - Deploy anchors at target position_and with DMA wire section 1 Once Anchor Handling Tug (AHT) #2 at the target anchor position, it lowered piggyback anchor down to the seabed, AHT#2 picked up the 3" anchor wire attached at the anchor and paid out to 250 m and then connected the end of 3" anchor wire to 90mm chain attached to DMA anchor at AHT#2 stern. AHT#2 moved forward to make tension of anchor wire and continued to precede the DMA anchor deployment. Figure 4 shows the deployment of piggyback anchor and DMA anchor. After anchor deployment was completed_AHT#2 continued the deployment of DMA wire section 1 by 400m. AHT#1 inspected the DMA wire with ROV once its deployment was completed. AHT#2 abandoned the wire at the location. Pennant buoy was attached to the abandoned wire for future recovery. Step 2 - Laying DMA wire section 2.1, section 2.2 & section 2.3 AHT#2 recovered the abandoned wire and performed socket to socket connection. Then AHT#2 moved forward to make a tension to ensure the straightness of the 400m DMA wire AHT#2, kept paying out 400m DMA wire #2.1. The laying of DMA wire #2.2 and #2.3 followed the same steps. Then AHT#2 abandoned the wire at the design location. Pennant buoy was attached to the abandoned wire for future recovery of AHT#1. During the laying procedures while the DMA wire will cross over the pipeline protection frame_operation will be slow with ROV monitoring the wire passage over the frame.
38
OCT-DEC 2010
Figure 10 AHT#2 moving away from FPSO to put the DMA wire in tension
Step 3 - Laying messenger line AHT#1 recovered the end of DMA wire #2.3 and kept 30m distance from FPSO_AHT#2 was located on the other side of FPSO and also with 30 m distance as shown in Figure 6. The Messenger line were lowered down from both vessels. There were hook and master link preinstalled at the end of messenger lines for connection. The connection of messenger lines was via ROV as shown in Figure 7. During the process, ROV always monitored the messenger lines to ensure it does not touch FPSO mooring lines/risers. Step 4 - Deployment of DMA wire section 3 under FPSO Once the completion of the messenger lines connection_AHT#2 attached the DMA wire section 3 to the messenger line and started to pay out while AHT#1 retrieved the messenger line accordingly. The DMA wire section 3 reached the AHT #1 as shown in Figure 8. During the process, ROV always monitored the messenger lines to ensure it does not touch FPSO mooring lines/risers. AHT #1 started to lay down DMA wire section 3 to the seabed, and AHT #2 paid in DMA wire to keep tension on the seabed.
Figure 8 DMA wire connection underneath FPSO_before starting of lower down the DMA wire
Step 5 Deployment of DMA wire section 4 After completed the deployment of DMA wire section 3, AHT#1 moved to the other side of the FPSO and retrieved the pennant which was abandoned by AHT#2, connected the DMA wire section 3 to the DMA wire section 4 and continued DMA wire section 4 laying up to target location,. Then completed the entire 2536 meters DMA wire deployment procedures.
OCT-DEC 2010
39
Pipe pulling operation SEMAC1 was positioned at DMA anchor location (pipe pulling position). SEMAC1 recovered both DMA and the DMA wire section 1, and then connected the DMA wire section 2 on board and started pulling operation. SEMAC1 pulled the dummy pipe with approximately 201 ton pulling force. The pulling continues until the first 400 meters was completed. The section 2 of DMA wire was disconnected and section 3 was then connected to the winch and started the second 400 meters pulling. Same operation repeated, and SEMAC1 continued to the third pulling until the first dummy pipe section was 10 meters away from the center of the target location, the third pulling distance was 609 meters. During the entire pulling operation, DSV monitored the progress of the pipe movement at initiation head location and other location as per SEMAC1 instruction.
c) Dummy pipe positioning Once the 1st flange of 53 m dummy spool was 10 meters away from the center of target location, SEMAC1 stopped movement, checked the position of the flange and confirmed the alignment of the pipe. DSV repositioned at the dummy pipe termination head and installed the suction anchor 20 meters away from the end. The dummy pipe termination head should be tied to suction anchor by a hold back wire with the length precisely fit the dummy pipe final location. DSV was stationed on the suction anchor and performed survey of dummy pipe
located 2536 meters away from the DMA after completion of DMA wire development. Recovered the DMA wire by using ROV and transferred it to SEMAC1, and then connected it to dummy pipe which was on SEMAC1. The dummy pipe laying started after the DMA wire had been connected to pipe string. The 1615 meters long dummy pipe was laid in line with DMA wire and started from its terminal point (see Figure 12). The dummy pipe was abandoned from SEMAC1 after it had been laid. During the whole process, ROV launched from DSV to monitor the touch down point (TDP) and its initiation, pipe laying and termination. To facilitate the pipeline to the target located inside the FPSO safety zone, the dummy pipe must be bottom towed (pull) through underneath the FPSO. The DSV closely supported the operation by providing essential ROV monitoring and survey support to AHT s. The sequence of activity was as follows:
40
OCT-DEC 2010
flanges movement until it reached the designated target location and the hold back wire of the suction anchor was under tension. The dummy pipe installation was completed.
References:
1. 2. 3. 4. 5. 6. 7. 8. DNV 1981 Rules for Submarine Pipeline System DNV-OS-F101, 2005 Submarine Pipeline Systems API SPEC 5L, 2004 Specification for Line Pipe, 2004 API 1104 20th Edition Welding of pipeline & Related Facilities ASTM E-94 Standard Guide for Radiographic Examination ASME V:2005 Boiler and Pressure Vessel Code-NDE SPC-SP-SP-0005,Rev.0 Specification for Welding & Inspection API RP 2A-WSD 21st Edition Recommended Practice for Planning, Designing, and Construction of Fixed Offshore Platforms - Working Stress Design AISC-ASD 9th Edition American Institute of Steel Construction - Allowable Stress Design ISO 9001, 2000 Quality Management System PP
6.0 Conclusions
This paper summarized the installation methodology and successful operations of pipeline laying underneath a operating FPSO with all mooring and risers connected. The details of the operation procedures are outlined herein. This project is an important example of successful experiences and a sound starting point for future improvements in pipeline pulling through oil tanker and mooring system. The technologies developed and adopted in the project lead to the success of the pipeline laying. We have the following key findings * Protection structure system designed to avoid any damage to existing pipeline and cable is proved necessary and efficient, there is no exciting pipeline or cable damage observed; * Pipeline laying and pulling procedures adopted Dead Man Anchor and Piggy-Back Anchor locating method which simplify operation and reduce cost effectively * Segmental DMA wire and dummy pipe designed to suit small pipe-laying vessel which reduce project cost and offshore operation time * Suction anchor provided an accurate positioning bench mark.
9. 10.
OCT-DEC 2010
41