2012 PTQ q3
2012 PTQ q3
2012 PTQ q3
DN-3651.
A DN-3651 technical paper will be presented at the 244th American Chemical Society (ACS) meeting in August 2012.
Leading minds. Advanced technologies.
Meet Alexei Gabrielov:
Outdoor Enthusiast, CRITERION Scientist.
criterion.indd 1 1/6/12 11:33:38
Q
Which would you say is the preferred scheme for enhanced
distillate production: increase diesel yield from FCC pretreat
in mild hydrocracking mode; or extend the endpoint of the
feed to a diesel unit and convert the heavy fraction?
A
Stefano Melis, Senior Hydroprocessing Specialist,
Albemarle Corporation, Stefano.Melis@albemarle.com
It is extremely diffcult to provide recommendations on
this subject. Indeed, the choice strongly depends upon
the confguration of the refnery and on the characteris-
tics of the available FCC pretreat and diesel units, with
particular reference to unit volume and hydrogen
partial pressure.
In general, upgrade of FCC pretreat to mild hydro-
cracking seems to be the easiest solution. Such an
option simply corresponds to an increase in operation
severity, where average conversion levels around 20%
are achieved at the expense of cycle length. Higher
conversion levels (in the order of 30%) might also be
achieved, but this can be done only in units with suff-
cient pressure (for instance, 100 bar) and would likely
also require signifcant throughput reduction or invest-
ment in additional reactor volume.
On the other hand, extending the end point of the
diesel feed requires much more attention. A typical
diesel unit provides a T95 boiling point shift of around
5C. High-pressure operations combined with highly
active hydrogenation catalyst can raise the T95 shift to
10-15C, but the conversion of the heavy fraction also
requires a signifcant increase in operating severity
(because of the nature and the amount of sulphur and
nitrogen present in the heavy fraction). Processing of
even heavier diesel (requiring a >15C boiling point
shift) is also possible, but requires the use of cracking
catalysts at the bottom of the reactor and shifting the
operation from hydrotreatment to HGO/LVGO hydro-
cracking. This solution can be done only in units that are
equipped with a suitable quenching system and will
also require a reduction in throughput and cycle length.
Since the fnal objective is obviously margin improve-
ment, the choice between the two potential solutions
depends on the net increase of diesel yield compared
to the increased costs associated with production loss
(from lower throughput reduction and/or increased
turnarounds/downtime, for example), increased cata-
lyst expense and increased hydrogen consumption. Of
course, capital expenditure must also be taken into
account for those scenarios requiring a unit revamp.
Finally, in addition to the hydroprocessing economic
factors described above, the refner must estimate the
effects these hydrotreating options will have on FCC
unit operations, yields and product qualities in order
to project the overall refnery impacts.
Q
Is there a control option that will ensure the right oxygen
feed to our sulphur recovery unit in all operating conditions
upstream of the unit, and so avoid emissions peaks?
A
Eric Roisin, Sulfur Recovery Technical Manager, Axens,
Eric.Roisin@Axens.com
I would recommend you contact the suppliers of detec-
tors to inquire if their acid gas detectors are able to
quantify both sulphur and hydrocarbons species. I know
ABB and Ametek do supply such pieces of equipment.
The integration of such equipment within the SRU
control can also be done by engineering companies that
revamp existing units. I have heard about the success
story of Suncors Simonette gas plant in Canada, the
control system of which was revamped by Jacobs.
Q
What is the best approach with current catalyst systems
for shifting between maximum gasoline and maximum diesel
from the FCC unit: catalyst change-out or a blending option?
A
Yen Yung, Global Technical Specialist, Albemarle
Corporation, Yen.Yung @albemarle.com
Shifting between maximum gasoline mode and maxi-
mum diesel in the FCC unit is very unit specifc. The
main determining factors include the time needed for a
catalyst change-out, maximum regenerator temperature
and wet gas capacity.
Albemarle has a full line of MD catalysts (for instance,
Amber MD for gas oil feedstocks and Upgrader MD for
residual feedstocks) featuring high accessibility and
bottoms conversion for maximising diesel production.
Albemarle has also developed catalysts for maximum
gasoline yield and high bottoms conversion. These cata-
lysts include Go-Ultra for gas oil feedstocks, and
Upgrader and Coral SMR for residual feedstocks.
When maximum fexibility is required, our bottoms
conversion additive, referred to as BCMT-MD, is
recommended for a multitude of feedstock types. This
provides an immediate mechanism for boosting
bottoms cracking and increasing the yield of middle
distillates. This is accomplished by increasing the equil-
ibrated accessibility index of the base catalyst and
providing additional bottoms cracking power and
selectivity towards diesel. Rather than waiting weeks
or months, the selectivity towards diesel can be quickly
accomplished by using BCMT-MD.
www.eptq.com PTQ Q3 2012 5
ptq&a
Additional Q&A can be found at www.eptq.com/QandA
Q&A copy 11.indd 1 2/6/12 17:25:43
A
Jason Smith, BASF Refning Additives Manager, Jason.
k.smith@basf.com
Rapid changes in fuels supply and demand can move
the relative pricing of a refners products quickly. As a
result, a refner may fnd themselves with a non-
optimal catalyst and non-optimal unit performance.
Operational changes can be made, but will only result
in incremental performance changes. For high turnover
units, changes in catalyst formulation might be able to
keep up these rapidly changing product goals.
However, most units would be more likely to beneft
from the use of co-catalysts offered by BASF.
Co-catalysts are a standalone product category
providing the refner with the fexibility to change the
product slate of the FCC without changing the FCC
catalyst. These products are added at rates of 10-40%
of the catalyst feed and fundamentally change the
performance of the FCC unit in a short period of time.
LCO production could be increased through opera-
tional changes: decreased riser outlet temperature,
decreased catalyst activity, increased feed preheat and
increased HCO recycle. However, these changes do not
necessarily improve the proftability of the FCC due to
the resultant increase in bottoms product and loss of
product volume. Only a change in catalytic performance
can defnitely increase FCC proftability for LCO maxi-
misation. Changing the catalytic performance allows for
increased LCO selectivity lower bottoms make and
can maintain proftable product volume and value. A
catalyst reformulation could provide this change in cata-
lytic performance, but this takes too long to capture the
advantage of the rapidly changing economics.
Similarly, gasoline production can be infuenced
quickly and most effectively using a maximum conver-
sion co-catalyst as opposed to operational adjustments
and base catalyst changes. Gasoline yield is maximised
while maintaining high throughput and coke selectivity.
In one commercial example, HD Ultra, BASFs maxi-
mum LCO co-catalyst, replaced 30% of the catalyst
feed, increasing matrix activity and stability. The resul-
tant product slate saw a 2% increase in LCO and a 2%
reduction in slurry. In another commercial example,
Converter, BASFs maximum gasoline co-catalyst,
replaced 20% of the catalyst feed. Slurry oil decreased
by 4.5%, while conversion jumped by 5.2%, gasoline
grew by 3.5% and LPG increased by 2.1%. Co-catalysts
quickly changed the product slate at these refneries to
maximise proftability. Further examples can be found
in the 2010 NPRA paper AM-10-110: Co-catalysts Provide
Refners with FCC Operational Flexibility.
While operational changes are quick, they have
limited ability to change unit performance and may
have undesirable trade-offs. Base catalyst formulation
can provide fundamental unit performance changes,
but they often take too long to be of use in a changing
market. Usage of either a maximum gasoline co-
catalyst or a maximum LCO co-catalyst allows refners
to rapidly change unit performance and capture the
most favourable economics at all times, maximising
FCC proftability.
Q
We are targeting maximum propylene production from
the FCC unit for obvious economic reasons, but are there any
negative effects of this policy on the quality of other product
streams?
A
Eric Roisin, Sulfur Recovery Technical Manager, Axens,
Eric.Roisin@Axens.com
When increasing the propylene yield, the gasoline
production will reduce. The gasoline properties will
change as follows:
Olefn content will stay relatively constant
Aromatic content will increase signifcantly and
could be a constraint in the gasoline pool
RON will increase; with conventional maximum
gasoline operation, FCC gasoline will reach around 92
RON. When the propylene yield is at 10 wt%, 94-95 is
very common. As a consequence, the gasoline pool will
require less reformate or lower severity reformate. It
will have a positive effect on the aromatic content in
the pool and could compensate the additional aroma-
ticity of the FCC gasoline
RVP will increase slightly because the content of C
5
in the gasoline will increase.
In order to address the last point on RVP, Axens
advises considering adding a TAME unit or an oligom-
erisation unit on the C
5
cut downstream Prime-G+ frst
step, which constitutes an ideal feed pretreatment
6 PTQ Q3 2012 www.eptq.com
MINIVAP ON- LINE
P h o n e +4 3 1 2 8 2 1 6 2 7 -0 | F a x +4 3 1 2 8 0 7 3 3 4
i n fo . g ra b n e r-i n s tru m e n t s @ a m e te k . a t | w w w. g ra b n e r-i n s tru m e n t s . co m
VAPOR PRESSURE
PROCESS ANALYZER
VP o f G a so li n e , C ru d e O i l a n d L P G
Acco rd i n g to S ta n d a rd s
R VP , D VP , T VP a n d V/L = 2 0
H i g h e st P re ci si o n
U p to 2 S a m p le S tre a m s
Ad ju sta b le Te m p e ra tu re
R a n g e : 2 0 -6 0 C
Ad ju sta b le V/L R a ti o
Au to m a ti c C a li b ra ti o n
F a st a n d E a s y M a i n te n a n ce
Au to m a ti c L u b ri ca ti o n
MINIVAP ON-LINE.indd 1 29.02.2012 13:19:08
Q&A copy 11.indd 2 1/6/12 12:56:11
cbi.indd 1 1/6/12 12:08:30
8 PTQ Q3 2012 www.eptq.com
before etherifcation. A TAME unit is an opportunity to
reach a higher RON pool. Oligomerisation of C
5
into
distillate (PolyFuel process) is an opportunity to switch
gasoline into diesel, particularly in Europe, where
refners face surplus gasoline production.
Q
What arrangement of trays and packing designs will
give me the best effciency of fractionation in my crude and
vacuum distillation units?
A
Celso Pajaro, Manager of Refnery Applications, Sulzer
Chemtech USA, Celso.Pajaro@sulzer.com
There is no specifc arrangement of packing and trays
for getting the best effciency of fractionation. The choice
in column internals is a function of the type of crude
being processed and the column diameter available.
Structured packing has been used in every section of
crude columns, often to substantially increase effciency.
In many cases, the effciency within a given section can
be increased by two to three theoretical stages each.
However, its use in the top section can be a challenge
with particularly corrosive crudes. Monel and AL6XN
materials have been used successfully in these applica-
tions, but care needs to be taken to properly match the
correct material with the level and type of corrosivity.
In such corrosive sections, trays have an innate
advantage due to their higher thickness. Some heavy,
high-sulphur crudes also have issues with chloride salt
deposition, which can plug packing and trays, so
specially designed fouling-resistant trays such as
Sulzers VG AF have been used to increase column run
length and maintain tray performance.
If corrosion is not an issue, entrainment-resistant
trays, such as Sulzers Umbrella Floating Mini (UFM)
valve trays will give the highest effciency over the
widest operating range. The downward vapour fow
from these valves improves mixing at the tray deck
level and minimises entrainment, maintaining the high-
est possible effciency from turndown to full capacity.
For the kero through diesel fractionation sections, the
UFM valve trays are the best economical option. Also,
structured packing can be used to improve diesel-
AGO fractionation.
The wash oil section is characterised by low liquid
rates coupled with high vapour rates. This is ideal for
structured packings. With its high effciency, a well-
designed structured packing wash section can produce
high yields of high-quality AGO under a wide variety
of conditions. Sulzer MellapakPlus high-performance
structured packing provides a high combination of eff-
ciency and capacity.
The stripping section is typically designed with trays
with a variable open area to maximise their effciency.
Structured packing has been used in this section with
some success; its low pressure drop allows for better
stripping. However, plugging has been experienced
with some diffcult crude types.
For vacuum columns, structured packing is the clear
choice due to its lower pressure drop that allows mini-
mum pressure at the fash zone and maximum feed
vapourisation. For columns with a steam stripping
section, trays are the typical solution, although struc-
tured packing has also been used due to the lower
pressure drop that maximises stripping. There are
several vacuum columns successfully operating with
structured packing in their stripping section. As is the
case with crude columns, structured packing can be
subject to fouling when processing diffcult crudes.
Q
Is there a case for hydrogen production via coke
gasifcation over steam methane reforming?
A
Girish K Chitnis, Licensing Director, Technology Sales
and Licensing, ExxonMobil Research and Engineering
Company, girish.k.chitnis@exxonmobil.com
Hydrogen demand in modern refneries continues to
increase, with additional hydrotreating and hydro-
cracking units being deployed to meet the various
clean fuels mandates and product demands with
heavier crudes and additional conversion capacity.
Historically in low-conversion refneries, byproduct
hydrogen from catalytic reforming of naphtha for motor
gasoline production was principally used to meet hydro-
gen demand. Although catalytic reforming technology
has advanced over the years, resulting in increased
hydrogen yield due to lower operating
pressures,
1,2
it does not produce enough hydrogen to
want to keep the FCC at full feed rate. An option would be to
add partial conversion hydrocracking before the FCC. The
feed rate to the hydrocracker (HC) can be fixed so that the
FCC can be kept full, but there is substantial additional diesel
produced. Of course, some additional VGO is required, either
purchased or through additional crude runs.
The pressure of the partial-conversion HC needs to be
optimised. A high-pressure unit will be able to make ultra-
low-sulphur diesel (ULSD) directly. However, capital cost is
high. A less capital-intensive option is to use a lower-pressure
HC, with some additional post-treat of the diesel integrated
with the HC. If there are other difficult diesel stocks that need
to be treated in the refinery, such as FCC light cycle oil (LCO),
it may also be possible to economically utilise the post-treat
unit for them.
With regard to FCC LCO, this stream is an inferior
potential diesel component with its low cetane value, even
after hydrotreating. Partial hydrocracking of LCO (at
moderate pressure) can be considered to upgrade the
material. While some diesel molecules will be lost to lighter
material, the diesel retained is upgraded to a higher-quality
diesel blending stock.
Ncn-intrusive cw
measurement up tc 00C
FieId-Prcven at Pehneries
Trouble Iree operation at
extreme pipe temperatures
No clogging, no pressure losses
nstallation and maintenance
without process interruption
ndependent oI uid or pressure
Hazardous area approved
suits
and measuring true unit per-
formance in Northern Alberta.
Shouldnt this be kept in mind
by those considering long term
supply agreements?
Oil Sands Crude
Profits and
Problems?
Canadian bitumen production
currently runs about 1 MMbpd,
with some being sold as Synbit
and Dilbit. Over the next 10-12
years output is expected to
increase to 3.5 MMbpd and more
refiners will begin investing to
process it and come to depend
on the Synbit and Dilbit for a
significant part of their supply.
Few today, however, have ever
processed these feeds at high
blend ratios, and are unaware
that conventional process and
equipment designs are not up
to the job. Canadian oil sands
feedstocks are extremely hard
to desalt, difficult to vaporize,
thermally unstable, corrosive, and
produce high di-olefin product
from the coker. If you intend to
lock into a long-term supply,
therefore, it is imperative that you
consider reliability and run length
from a particular design.
Too low tube velocity in the
vacuum heater tubes will lead to
precipitation of asphaltenes. Too
fast a flow rate will erode the
tube bends. If coil layout, burner
configuration and steam rate are
not correct, run length will be
measured in months, not years.
Diluent recovery unit designs
must take into account possible
For a discussion of factors
involved in designing refinery units
to process difficult oil sands feed-
stocks, ask for Technical Papers
#234 and 238.
10 PTQ 01:10 01 PC PTQ 0107 ADF 10/19/07 4:42 PM Page 1
pcs 2.indd 1 1/6/12 21:05:28
For more information, visit www.uop.com/uniex.
2012 Honeywell I nternational, I nc. All rights reserved.
refinement redefined
UOP Unihox rosiduo-upgrading toonnology yiolds 25% moro
oloan uol, turning "bottom o tno barrol" into "top o tno lino."
Got tno most rom ovory barrol. Tno UOP Unihox Proooss oan doublo tno diosol yiold
o otnor rosiduo-upgrading toonnologios, turning tno "bottom o tno barrol" into moro
blaok on your bottom lino. Tno Unihox Proooss is a nign-oonvorsion, oommoroially
provon toonnology tnat prooossos low-quality rosiduo stroams liko vaouum rosiduo into
nign-quality distillato produots loading to rohnory margin inoroasos o up to 100%.
Simply put, witn tno Unihox Proooss rom UOP, you'll maximizo produotion and prohts
rom ovory barrol.
SPM-UOP-30 Uniflex Ad_Comp_v6.indd 1 3/8/12 2:35 PM
uop.indd 1 9/3/12 12:31:44
Process and catalysis factors to maximise
propylene output
T
he fuid catalytic cracking
(FCC) unit has been the
primary source when it comes
to meeting the growing market
demand for propylene. This has led
to a signifcant challenge for licen-
sors to develop new process
technology and for refners to opti-
mise cracking severity. Achieving
maximum propylene yield and
conversion from a wide range of
feed qualities also presents consid-
erable challenges to catalyst
designers. The impact of feed
composition and process variables
on the yields and heat balance is
signifcant and therefore requires a
good understanding of the chemis-
try to design the right FCC catalyst
for individual FCC units.
This article describes the most
important elements of chemistry
and catalyst design considerations
for maximising propylene make
from the FCC unit.
Maximising propylene in the
FCC unit
In the refning industry, several
cracking processes are applied to
cleave carbon-carbon bonds, includ-
ing non-catalytic thermal coking
and visbreaking, as well as catalytic
hydrocracking and, most impor-
tantly, FCC. Coking, visbreaking
and hydrocracking will not be
discussed further, as there is essen-
tially no production of propylene
from these processes. While FCC is
predominantly a catalytic process,
the reaction temperature is high
enough to initiate some thermal
cracking.
Thermal cracking reactions
proceed through a non-selective
free radical chain mechanism that
Catalyst selection and process design enable a new RFCC unit to maximise
propylene production from a range of feeds
Takuya aMano, JaCk WilCox and CaRel PouWels Albemarle Corporation
Takakazu MaTsuuRa Taiyo Oil Co
involves three primary steps: initia-
tion, which involves the formation
of the highly reactive, electrically
neutral free radical ion; propaga-
tion, which is essentially the
cracking step plus the generation of
another radical; and termination, as
the radicals are eventually reduced
to methane, olefnic C
2
and C
2
frac-
tions, butadiene and small amounts
of isobutene and isobutylene. While
the thermal cracking reactions
occurring in the FCC reactor do
produce some olefnic C
2
, indicating
some hydrogen transfer, the contri-
bution to the overall propylene
yield is relatively small. The degree
of branching is minimal, indicating
very little isomerisation.
The predominant cracking mecha-
nism utilised in the FCC process is
driven by the use of a highly selec-
tive acid-catalysed system. Catalytic
cracking involves the formation of
carbo-cation intermediates as
follows: a carbonium ion is initially
formed either by abstraction of a
hydride ion from a paraffn or from
the acid site provided by the cata-
lyst. The highly selective cracking
reaction, referred to as -scission,
plus the formation of another
carbonium ion, then occurs.
Catalytic cracking produces highly
olefnic liquid products and essen-
tially no C
2
and lighter products. In
addition, secondary reactions, such
as hydrogen transfer and isomerisa-
tion occur, which impacts LPG and
gasoline olefnicity, as well as the
degree of paraffn branching. Figure
1 illustrates the differences in selec-
tivity by comparing the products
derived from thermal and catalytic
cracking of n-hexadecane at 500C.
1
A leap in FCC technology
occurred when zeolites were incor-
porated into the catalyst
formulation, signifcantly upgrad-
ing catalytic cracking. This change
produced a much more intrinsically
active catalyst, which resulted in
not only increased unit conversion
but also signifcantly better product
selectivities, as well as reduced
delta coke and dry gas production.
www.eptq.com PTQ Q3 2012 17
1 2 0
1 4 0
1 0 0
8 0
6 0
4 0
2 0
C 1 C 2 C 3 C 4 C 5 C 6 C 7 C 8 C 9 C 1 0 C 1 1 C 1 2 C 1 3 C 1 4
m
o
l
e
s
p
r
o
d
u
c
t
1
0
0
m
o
l
e
s
c
r
a
c
k
e
d
C-number
0
C a ta lytic c ra c k in g , a m o rp h o u s S i0 2 /A 1 2 0 3
T h e rm a l c ra c k in g , q u a rtz c h ip s
Figure 1 Thermal and catalytic cracking of n-hexadecane at 500C
albemarle.indd 1 4/6/12 15:15:06
18 PTQ Q3 2012 www.eptq.com
of branched and cyclic hydrocar-
bons to the active sites and only
allow straight-chain and mono
methyl paraffns and olefns to
enter. These molecules are essen-
tially centre-cracked, generating
predominantly propylene and small
amounts of butylene and ethylene.
The primary reactants are in the C
6
and C
7
range, but other gasoline
molecules with a carbon atom
number between 5 and 10 can be
converted by ZSM-5 to some extent.
Figure 2 shows the effect of ZSM-5
on product selectivity shifts, giving
clear evidence of the increase in the
production of C
3
, C
4
and C
2
olefns,
with a corresponding reduction in
C
6
and C
7
components.
FCC gasoline can be typically
classifed into fve types of hydro-
carbons: paraffns (P), iso-paraffns
(iP), olefns (O), naphthenes (N)
and aromatics (A). Based on these
hydrocarbon types, conversion of
the most easily cracked C
6
and C
7
atoms by ZSM-5 is shown in Figure
3. An olefn is cracked by ZSM-5
and produces two smaller olefns.
As such, in order to maximise the
light olefn yield, the cracking
mechanism generating the C
6
and
C
7
olefns produced in the riser
during the primary cracking with
the FCC catalyst must be carefully
managed.
The numbers on the bars in
Figure 3 show a reduction in the
specifc hydrocarbon type. The
decrease in light isoparaffns is the
largest. This is attributed to the
reduced formation of light isoparaf-
fns in the presence of ZSM-5 and
other reactions, including cracking
to light olefns. The light olefns,
however, contribute the most to
propylene make, as olefns are more
reactive and crack to form two
smaller olefn molecules. In general,
gasoline-range olefns are the
primary reactants for propylene.
The molecules that can be readily
cracked by ZSM-5 are in the gaso-
line boiling range and often referred
to as gasoline precursors. Although
iso-paraffns are good gasoline
precursors, the small pores of ZSM-
5 restrict access primarily to
straight-chain paraffns or those
with a methyl branch. Larger
branched or multiple-branched
However, at equivalent conversion,
the gasoline research octane
decreased, refecting the reduced
olefnicity. The reduced gasoline, as
well as LPG olefnicity, is a direct
result of the hydrogen transfer reac-
tions. These reactions dictate the
hydrogen redistribution through
the entire product slate. Hydrogen
transfer is refected by increased
iso/normal paraffns, reduced gaso-
line and LPG olefnicity, reduced
over-cracking to LPG, and more
hydrogen-defcient heavy products
as hydrogen is shifted to lighter
products (see Table 1).
Maximising propylene yield from
the FCC unit is typically accom-
plished by combining a low rare
earth catalyst system with severe
reaction conditions. Signifcant
quantities of incremental propylene
may be generated by augmenting
the catalyst inventory with the
shape-selective zeolite ZSM-5.
(Albemarles AFX catalyst and tech-
nology, with its unique zeolite
system discussed later, maximises
propylene without augmenting the
catalyst inventory with ZSM-5 addi-
tive.) This zeolite utilises pore
openings smaller than Y-zeolite,
driving different catalytic reactions.
The smaller pores restrict the access
Conversion Gasoline, vol% Propylene, vol%
Silica-alumina gel 75.5 47.5 8.5
REHY 85.5 61.0 5.9
Zeolite vs amorphous cracking
Table 1
1 2
1 8
1 6
1 4
1 0
8
6
4
2
C 1 C 2 C 3 C 4 C 5 C 6 C 7 C 8 C 9 C 1 0 C 1 1 C 1 2
Y
i
e
l
d
,
w
t
%
C-number
0
F C C c a ta lyst +Z S M -5
F C C c a ta lyst
Figure 2 Component selectivity shifts with ZSM-5
3
5
4
2
1
iP 6 O 6 iP 5 iP 7 O 7 A 7 A 6
Y
i
e
l
d
,
w
t
%
o
n
f
e
e
d
C-numbers and component t ype
0
F C C c a ta lyst +Z S M -5
F C C c a ta lyst
-2 .8 -2 .1 -2 .0 -1 .7 -1 .5 0 . 3 0 . 5
Figure 3 Gasoline components impacted by ZSM-5
albemarle.indd 2 1/6/12 13:14:41
www.eptq.com PTQ Q3 2012 19
molecules are consequently not
desirable. Since Y-zeolite catalyses
isomerisation reactions, the catalyst
must be formulated to minimise
these reactions.
As Figure 3 shows, there is a
small increase in the gasoline
benzene and methyl-benzene with
the use of ZSM-5.
FCC manufacturers have a vari-
ety of tools available for designing
the optimal catalyst system to
maximise the propylene yield from
the FCC unit. The impact of these
various parameters on catalyst
performance in general and on light
olefn selectivity in particular
follows (see Table 2).
Type Y-zeolite is the primary
cracking component incorporated
into modern FCC catalysts. Y-
zeolite contains a high degree of
acidity, which contributes to a high
intrinsic activity. Despite the vari-
ous treatments performed on the
as-produced Y-zeolite to modify its
performance, the hydrogen transfer
function remains relatively high
while maintaining some isomerisa-
tion activity.
ZSM-5 zeolite also contains a high
level of acidity, which produces a
very active component, although
the effective cracking rate is limited
by the molecular diameter and
shape of the reactants. The inher-
ently high silica to alumina of this
particular zeolite promotes limited
isomerisation. In addition, ZSM-5
has oligomerisation activity, which
consumes propylene.
The catalyst matrix has evolved
into more than just an amorphous
support for the active zeolite
component. Albemarle Developed
Matrix (ADM) technology (also
employed in Albemarles AFX cata-
lysts) incorporates catalytically
active components, providing a
wide range of functionalities,
including heavy oil upgrading and
heavy metal contaminant tolerance.
The acid sites utilised with the
matrix are less dense and not as
strong as the acid sites in the Y-
zeolite. The matrix cracking activity
can be varied from low to high,
although the hydrogen transfer
(HT) and isomerisation activity are
lower than that of Y-zeolite. As
Figure 4 shows, reducing the hydro-
gen transfer activity contribution
Acidity Cracking Hydrogen transfer Isomerisation
ZSM5-zeolite Very High High* - High
Y- zeolite High High High Moderate
Matrices Low-moderate Low-high Low to moderate Low
* Size and shape of molecules determines cracking rate
Impact of FCC catalyst components
Table 2
MOBILE COOLING FOR INCREASED
PETROCHEMI CAL PRODUCTI ON
Chillers
Water Pumps
Heat Exchangers
Power Generators
Cooling Towers
Aggreko employs over 4,500 people operating from 165 locations in about 100 countries.
Aggreko has a successful track record in commissioning engineered mobile
solutions that eliminate process bottlenecks and improve production as well as
unit bottom lines.
We can help you meet your objectives:
Provide temporary cooling to increase the distillation capacity in the summer
Improve your Vacuum unit cut quality in summer by improving steam ejectors
capacities
Clean in operation your heat exchangers without unit stoppage
Continue to run your units during cooling tower maintenance
Cool your rundowns and hydrocarbons streams to meet product quality requirement
Set-up contingency plans to secure your utilities
We Rent :
France : 0825 008 007
Germany : 0800 2447356
Spain : 902 22 11 01
Italy : 02 48 40 491
Benelux : (0)3 825 02 71
Netherlands : (0)88 644 1441
Poland : 00800 3311395
www.aggreko.com
albemarle.indd 3 1/6/12 13:15:00
can be optimised to the units
constraints.
Reaction temperature
Increasing the riser outlet tempera-
ture to the limit of the wet gas
compressor and/or the main air
blower increases conversion, total
LPG yield and propylene
production.
Increasing the cracking tempera-
ture not only enhances the thermal
cracking reactions, but also
increases the catalytic reactions due
to the increased catalyst circulation.
A common parameter used to
monitor the level of catalytic to
thermal cracking occurring in the
FCC reaction zone is the ratio of
total C
4
to LPG (C
4
/(C
3
+C
4
). A ratio
of 0.68 denotes a high degree of
catalytic cracking
3
, whereas values
near 0.50 indicate increased thermal
cracking. These values are applica-
ble for typical FCC catalysts without
the use of ZSM-5, as the latter
zeolite increases C
3
selectively. In
general, cracking reactions have
higher effective activation energy
than bimolecular hydrogen transfer
reactions, so increasing the reaction
temperature increases the tendency
for gasoline olefns to crack to light
olefns rather than to undergo
hydrogen transfer.
4
Increasing the cracking tempera-
ture about 10C will increase the
propylene yield by about 0.8-0.9
wt% (see Table 3).
Hydrocarbon partial pressure
Minimising the hydrocarbon partial
pressure in the reaction zone direc-
tionally increases the light olefn
yield. Bimolecular reaction rates,
primarily hydrogen transfer, are
signifcantly slower at a low hydro-
carbon partial pressure,
4
preserving
the precursors for propylene
production in the gasoline boiling
20 PTQ Q3 2012 www.eptq.com
from the matrix increases the
propylene yield.
In addition to hydrogen transfer,
several other secondary reactions
occur, such as cyclisation, aromati-
sation and oligomerisation. As the
catalyst/hydrocarbon in the reac-
tion zone increases, the
oligomerisation reaction rate
increases, consuming propylene
and leading to a loss of propylene
yield.
2
From a catalytic standpoint, the
following parameters must be care-
fully optimised to maximise the
propylene yield:
Maximise generation of C
6
and C
7
olefns and iso-paraffn precursors
in the gasoline boiling range
Minimise the hydrogen transfer
function
Limit isomerisation to maximise
methyl branches
Minimise undesirable secondary
reactions, including cyclisation,
aromatisation and oligomerisation
Selectively crack precursors to
propylene.
Optimising unit conditions
The inherent fexibility and versatil-
ity of the FCC process allows the
refner to adjust the units operating
severity to rapidly respond to chang-
ing market demands. Maximising
the yield of light olefns, such as
propylene, requires the cracking
severity to be carefully tuned.
Specifcally, operating parameters,
including reaction temperature, cata-
lyst circulation rate and hydrocarbon
partial pressure in the reaction zone,
Unit 1 Unit 2
RxT, C 522 543 519 530
C
3
=, wt% Base +1.6 Base +1.0
C
4
/(C
3
+C
4
) 0.58 0.56 0.59 0.57
* FCC catalyst with high ZSM-5 content
Effect of reaction temperature on propylene yield
Table 3
RxT, C 553 551
RxP, barg 2.1 2.8
Steam, mol% on feed 71 60
C
3
=, wt% on feed 11.6 9.9
Hydrocarbon partial pressure effect
on propylene yield sample
Table 4
Feed properties Operations
Type FT-Wax Unit Pilot plant
API 43.1 RxT, C 538
S.G. 0.81 CTO 4
S, ppmw 2.5 Catalyst Zoom
Sim Dist, 5% ,C 368 Conv, wt% 92
Sim Dist, 95%, C 474 C
3
=, wt% 18
Cracking FT-Wax in FCC pilot plant
Table 5
1 5
1 7
1 3
1 1
4 0 5 0 6 0 7 0 8 0 9 0
C
3
=
y
i
e
l
d
,
w
t
%
Conversi on, wt %
9
0 . 3
0 . 4
0 . 2
0 . 1
H
y
d
r
o
g
e
n
t
r
a
n
s
f
e
r
i
n
d
e
x
0 . 0
H T I : m a trix 2
H T I : m a trix 1
C 3 = m a trix 1
C 3 = m a trix 2
Figure 4 Effect of different matrices on hydrogen transfer and propylene yield
albemarle.indd 4 1/6/12 13:15:10
range. In addition, the oligomerisa-
tion reaction rate is much slower at
a lower hydrocarbon partial pres-
sure, thus preserving propylene.
Optimising the reactor/regenerator
pressure balance (to minimise the
reactor pressure) and using riser
diluents (steam) minimises the
hydrocarbon partial pressure in the
reaction zone. Grassroots units
intended to maximise the light
olefn yield are being designed for
a very low operating pressure and
high riser diluent injection. Table 4
shows an example of the impact of
reactor pressure and effective
hydrocarbon partial pressure.
Catalyst circulation rate
Optimising the reactor/regenerator
heat balance to maximise catalyst
circulation rates and resulting
catalyst-to-oil ratios contributes to
increased cracking severity, conver-
sion and light olefn yield. The
increased cracking and resulting
conversion far outweigh the nega-
tive impact of the increased
hydrogen transfer.
FCC feed quality
In order to maximise the yield of
light olefns, cracking severity must
be optimised for a given feed qual-
ity. In general, more propylene can
potentially be derived from feed
sources that are hydrogen rich and
low in contaminants (that is, easy to
convert). Feed sources rich in
aromatic components produce fewer
precursors in the gasoline boiling
range, resulting in potentially less
propylene yield. Commercial data
presented by Axens indicate as
much as 1.5-2.0 wt% incremental
propylene may be produced for
every 0.5 wt% increase in feed
hydrogen content.
5
A processing
option being integrated in some of
the new unit confgurations takes
advantage of co-processing hydro-
gen-rich streams, such as light
naphtha, C
4
saturates or oligomer-
ised C
4
/C
5
products.
Research presented by CPERI6
demonstrates the potential propyl-
ene yielded from cracking an
extremely hydrogen-rich feed
source (a wax derived from the
Fisher-Tropsch process). Utilising
various blends of commercial
equilibrium catalysts and
Albemarles ZSM-5 additive Zoom,
this feed was cracked in a pilot
plant. As Table 5 shows, with ZSM-
5 additive, a conversion level above
90 wt% was obtained with a propyl-
ene yield of 18 wt%.
Increasing the hydrogen content
of the feed by hydrotreating actu-
ally results in fewer precursors for
propylene production due to the
reduced olefn and corresponding
increased naphthene content of the
feed.
Catalyst design considerations
FCC catalyst
As the unit operating severity is
limited by mechanical constraints
and the choice of feed is typically
fxed by the refnerys crude oil
source, the selection of the optimum
catalyst system becomes crucial to
maximise both the desired yield
distribution and unit proftability.
This requires a complete under-
standing of the unit constraints and
limitations, as well as the feed qual-
ity and yield objectives.
www.eptq.com PTQ Q3 2012 21
albemarle.indd 5 1/6/12 13:15:26
As previously indicated, the opti-
mum catalyst system will maximise
both propylene selectivity and
gasoline olefnicity, while minimis-
ing hydrogen transfer, isomerisation,
oligomerisation and aromatisation
reactions. Albemarle has applied
several techniques limiting these
secondary reactions, while enhanc-
ing the primary cracking reaction.
Minimising rare earth has long been
used as a way to reduce hydrogen
transfer. The Albemarle Developed
Zeolites (ADZ) for this application
not only minimise hydrogen trans-
fer by low rare earth exchange but
also employ a very low unit cell
size and disperse the acid sites as
far as possible while retaining
acceptable intrinsic activity.
Additionally, hydrogen transfer is
minimised by producing catalyst
particles with a high accessibility,
allowing the olefnic products to
more rapidly diffuse from the
catalyst particle. Classical hydrogen
transfer is a bimolecular reaction
requiring reactants to be close to a
pair of acid sites. Reducing olefn
contact time by increasing accessi-
bility reduces hydrogen transfer.
2
Augmenting the base catalyst
addition and unit inventory with
ZSM-5 additive is an effective solu-
tion for increasing propylene yield
in the FCC unit. This approach
gives the refner a great deal of fex-
ibility, as additive usage can be
adjusted to respond to propylene
demand and to optimise operations
within unit constraints while
maximising unit proftability.
As previously mentioned, ZSM-5
generates propylene by selectively
cracking olefns in the gasoline boil-
ing range. As the concentration of
ZSM-5 additive in the catalyst
inventory increases, the incremental
yield of propylene produced per
percentage of additive decreases.
Propylene yield tends to plateau
with about 10% ZSM-5 crystal
concentration in the catalyst inven-
tory. The diminishing effectiveness
of ZSM-5 at higher concentrations
occurs primarily due to the deple-
tion of the gasoline olefn
precursors.
The base catalyst formulation and
technology dictate the maximum
potential propylene yield from the
FCC unit. Figure 5 shows the maxi-
mum propylene yield that may be
produced by four different host
FCC catalysts augmented with a
variety of ZSM-5 additives. The
yield response of the ZSM-5 varies
with the properties of the base cata-
lyst; the maximum propylene yield
is dependent on the base catalyst
properties.
The average 7.5 angstrom pore
opening of the Y-zeolite is too small
to allow the access of high molecu-
lar diameter feed molecules.
Catalysts commonly incorporate
larger (>100 angstrom) pore open-
ings and some cracking activity in
the matrix design to pre-crack the
large feed molecules into smaller
components. The relatively weak
acid site cracking provided by the
matrix produces olefnic precursors,
which can be further cracked to
lighter olefns with special zeolites.
Impact of hydrogen transfer
We can estimate the relative activ-
ity of FCC catalysts for generating
secondary reactions using the
hydrogen transfer index (HTI) for
catalysts tested under constant
conditions with the same feed. The
HTI can be defned in several ways,
including the ratio of iso-butane
over total C
4
s.
Catalysts with a lower HTI gener-
ate fewer secondary reactions,
preserving a greater quantity of the
gasoline boiling range olefns,
which can be subsequently cracked
to lighter olefns.
The four base catalysts tested (see
Figure 5) demonstrate the effect of
HTI on propylene generation. As
seen in the fgure, the propylene
yield increases as the HTI of the
base catalyst is reduced.
Further testing under constant
conditions demonstrates that
suppressing hydrogen transfer by
22 PTQ Q3 2012 www.eptq.com
6
9
8
7
5
4
3
2
1
0 2 4 6 8 1 0 1 2 1 4 1 6 1 8 2 0
P
r
o
p
y
l
e
n
e
y
i
e
l
d
,
w
t
%
ZSM-5 cryst al , wt %
0
D e c re a sin g b a se c a ta lyst
h yd ro g e n tra n sfe r in d e x
Figure 5 Effect of base catalyst technology on propylene
2 . 5
3 . 5
3 . 0
2 . 0
1 . 5
0 . 2 6 0 . 2 8 0 . 3 0 0 . 3 2 0 . 3 4 0 . 3 6 0 . 3 8 0 . 4 0
Base cat al yst HTI at 72 wt % conversi on
1 . 0
S C T-R T te st d a ta . R e sid .
R
2
= 0 . 9 5
C
3
=
l
o
g
(
1
+
%
Z
S
M
-
5
)
Figure 6 Base catalyst HTI infuences propylene yield potential
albemarle.indd 6 1/6/12 13:15:46
maximising the availability of olefn
precursors is the key to maximising
propylene. Multiple catalysts were
mixed with varying amounts of
ZSM-5 additive (see Figure 6). The
relative propylene yield shows a
strong correlation with the HTI of
the base catalyst.
Catalyst properties can be modi-
fed by several techniques to
suppress hydrogen transfer reac-
tions. Controlling the zeolite acid
site density and optimum disper-
sion of these acid sites is crucial in
minimising hydrogen transfer.
Reducing the number of acid sites
may be accomplished by minimis-
ing the zeolite unit cell size (UCS).
The zeolite UCS may be reduced by
several techniques; as the alumina
ions are removed, the intrinsic
activity of the zeolite decreases.
Minimising rare earth exchange
also produces a reduced UCS.
Hydrogen transfer activity may
also be mitigated by producing a
zeolite with a highly accessible pore
structure, which enhances diffusion.
A catalyst designed with high
accessibility allows the olefnic
produced from primary cracking to
rapidly diffuse from the catalyst
particle. Since hydrogen transfer is
a bimolecular reaction requiring the
reactants to be in close proximity to
a pair of acid sites, reducing the
residence time of olefns within the
catalyst particle reduces the rate of
hydrogen transfer.
Increasing the preservation of the
olefns initially results in reduced
LPG selectivity but increased LPG
and gasoline olefnicity. This results
in more precursors for the subse-
quent generation of propylene.
Albemarles worldwide equilib-
rium catalyst database shows a
clear example of how high catalyst
accessibility technology affects
HTI. Albemarle routinely tests
equilibrium catalysts collected
from FCC units all over the world
in a standard micro reactor test
called the fuid simulation test
(FST). This test is conducted with
constant feed quality and reaction
conditions, allowing direct compar-
isons of various catalyst yield
selectivities. Albemarles catalyst
technology exhibits a lower
HTI compared to two major
competitive catalyst technologies
(see Figure 7).
Based on these principles (low
hydrogen transfer, high accessibil-
ity, proprietary selective cracking
technology), Albemarle developed
the AFX family of catalysts. This
new FCC catalyst design was
specifcally developed to provide
maximum propylene selectivity
while cracking feeds ranging from
relatively clean gas oil to highly
contaminated resids. Furthermore,
it does not require the use of a
separate ZSM-5 additive. AFX cata-
lysts combine a high accessibility
structure with the optimum rare
earth level required to meet the
desired yield objectives. The FST
test data shown in Figure 8 illus-
trate the reduction in HTI that is
achieved with a high accessibility
catalyst structure.
For gas oil feed applications, the
additional reduction in hydrogen
transfer provided by the AFX cata-
lyst allows for maximum
preservation of olefn precursors
that can be cracked to propylene.
Maximisation of propylene poses
additional catalyst challenges when
processing heavy, contaminated
feeds. In addition to including the
features referred to above, the cata-
lyst must incorporate exceptional
metals tolerance and hydrothermal
stability. In part to provide these
features, a target level of rare earth
is exchanged into the zeolite struc-
ture. The reduction in hydrogen
transfer obtained from high catalyst
accessibility allows a somewhat
higher rare earth content, providing
an activity maintenance advantage
relative to low accessibility product.
When applied to a resid FCC opera-
tion, the AFX system is formulated
to minimise hydrogen transfer while
retaining maximum tolerance for
heavy metals and activity retention.
www.eptq.com PTQ Q3 2012 23
0 . 3 0
0 . 4 0
0 . 3 5
0 . 2 5
0 . 2 0
6 0 6 2 6 4 6 6 6 8 7 0 7 2 7 4 7 6 7 8 8 0
E
c
a
t
H
-
t
r
a
n
s
f
e
r
i
n
d
e
x
Ecat FST conversi on, wt %
0 . 1 5
A lb e m a rle s h ig h A A I te c h n o lo g y
re su lts in lo we r H T I
C o m p e tito r A
A lb e m a rle h ig h A A I
C o m p e tito r B
Figure 7 HTI for various catalyst technology platforms
0 . 3 0
0 . 2 5
0 . 2 0
0 . 1 5
M a x
H
T
I
Rare eart h on zeol i t e
0 . 1 0
H ig h a c c e ssib ility A F X
L o w a c c e ssib ility
Figure 8 High accessibility reduces hydrogen transfer index
albemarle.indd 7 1/6/12 13:15:56
Your 8ingle 8ource for New or Retroht nternals
Why wait 10, 15 or 20 weeks for your delivery! Ask ACS-AMISTCO,
INC. about our Fast Track delivery for trays and a complete range
of tower internals. With complete in-house engineering and
fabrication, we can use your existing drawings or modify them to
improve your process.
Trays (numerous options)
Sieve or perforated
Bubble cap trays
Cartridge trays
DuaI ow
Bafe
Valve
www.acs-amistco.com 24hr EMERGENCY 8ERVCE 1-800-231-0077
Mesh-numerous alloys-plastics
Vane (Chevron)
Double Pocket Vane
Candle or Fiberbed
Insertion Misthx
MIST ELIMINATORS
DISTRIBUTORS & SUPPORTS
Manufactured to customer
specihcations or engineered to
meet performance requirements.
COALESCERS
Oil water separations Haze removal
from fuels Removal of tower wet
rehux Caustic treater applications
STRUCTURED PACKING
Woven, sheet metal, and knitted
structured packing. Built to spec
or performance requirement.
RANDOM PACKING
Catalyst bed supports
Basket strainers
Nozzles Outlet/Inlet baskets
Distributors
Hub and header laterals
WEDGE WIRE SCREEN
Wide variety of random packing
types, sizes and materials in
stock! Ask us how our patented
SuperBlend 2-Pac can increase
your capacity and efhciency.
amistco.indd 1 1/6/12 11:38:54
Since the maximum propylene
yield is closely correlated with the
inherent hydrogen transfer activity,
catalysts designed to achieve an
equal target propylene yield have
the same base HTI. Zeolite stability
and activity begin to decline more
rapidly than the HTI as the zeolite
rare earth content approaches zero.
The activity advantage provided by
high catalyst accessibility increases,
since the target propylene yield also
increases, as additional zeolite can
be added to the catalyst particle.
For maximum propylene applica-
tions requiring the lowest HTI, the
activity advantage provided by a
high accessibility structure rapidly
increases (see Figure 9).
Commercial application
AFX catalysts have been thoroughly
evaluated and approved for
commercial application by several
third-party testing facilities. Various
grades of the AFX catalysts have
been tested on both a bench and
pilot scale, with feed qualities rang-
ing from relatively light, clean gas
oil to heavy, contaminated residual
sources. Figure 10 shows one exam-
ple of AFX catalyst testing results
compared with competitive cata-
lysts specifcally formulated to
maximise propylene while process-
ing a relatively clean gas oil quality
feed.
While laboratory testing demon-
strates the value of AFX catalysts,
their performance in FCC units that
target maximum propylene is even
more important and more impres-
sive. Due to its performance in FCC
units, AFX is widely recognised as
a leading catalyst for maximum
propylene.
7
It has been successful in
challenging applications at or close
to the plateau level of propylene, in
high-pressure FCC unit operations,
and in resid fuid catalytic cracking
(RFCC) units processing heavy resi-
due. It is also the preferred catalyst
for grassroots modern FCC units,
which are all in some way operat-
ing on the edge of what it possible.
There are many FCC units using
AFX catalysts to maximise propyl-
ene. The remainder of this article
focuses on a recent application of
the AFX catalyst to a newly
commissioned RFCC unit.
The multi-functional AFX catalyst
system provided this refner with
the capability to not only maximise
propylene yield but also the fexibil-
ity to maintain the most proftable
yield distribution while processing
highly contaminated feedstocks.
The excellent propylene selectivity
provided with this catalyst has led
to reduced ZSM-5 additive being
added to the catalyst inventory,
signifcantly reducing the activity
dilution impact on the circulating
catalyst inventory.
Taiyo Oil Company has recently
brought on stream a grassroots
RFCC unit at its Kikuma refnery in
Ehime, Japan. This unit has been
designed to process 25 000 b/d of
untreated atmospheric tower
bottoms derived from a variety of
crude oils from the Middle East and
Asia Pacifc regions. This unit is a
UOP design incorporating the latest
technology, including the high-
severity RxCat reactor confguration.
To meet its stringent yield require-
ments, Taiyo selected Albemarles
AFX catalyst augmented with low
levels of DuraZoom additive to
trim the propylene yield. This
catalyst system, combined with the
high-severity cracking environment
provided by the unit, has met the
high propylene yield goals set by
the refner.
This RFCC confguration has been
designed to provide the operating
fexibility necessary to maximise the
light olefn yield while processing a
variety of feed qualities. State-of-
the-art technology components,
including the Optimix feed injec-
tion, VSS riser termination device,
AF spent catalyst stripping and
fow-through catalyst coolers, have
been included in this unit design to
provide operating fexibility while
processing the heavy, contaminated
feedstocks. The reaction zone has
www.eptq.com PTQ Q3 2012 25
0 . 8
1 . 0
0 . 9
0 . 7
0 . 6
0 . 5
0 . 4
0 . 3
0 . 1 2 0 . 1 6 0 . 2 0 0 . 2 4 0 . 2 8 0 . 3 2
R
e
l
a
t
i
v
e
z
e
o
l
i
t
e
a
c
t
i
v
i
t
y
Hydrogen t ransf er i ndex
0 . 2
I n c re a sin g p ro p yle n e
H ig h a c c e ssib ility A F X
L o w a c c e ssib ility
8 1 % h ig h e r
re la tive a c tivity
2 4 % h ig h e r
re la tive a c tivity
Figure 9 Activity advantage of AFX catalysts (high accessibility)
1 4
1 3
1 2
1 1
1 0
9
7 4 7 6 7 8 8 0 8 2 8 4 8 6
P
r
o
p
y
l
e
n
e
,
w
t
%
Conversi on, wt %
8
O th e r A lb e m a rle te c h n o lo g y
C o m p e titive te c h n o lo g ie s
A F X te c h n o lo g y
Figure 10 Third-party testing of AFX catalyst technology
albemarle.indd 8 1/6/12 13:16:07
incorporated RxCat technology,
which is intended to provide
increased conversion as well as
light olefn and coke selectivity
advantages by mixing regenerated
catalyst with a recycled carbonised
catalyst back to the riser prior to
introducing the feed. This allows
the catalyst density in the riser to
be varied without generating incre-
mental coke, as well as effectively
increasing the catalyst-to-oil ratio
and resulting conversion and
increased light olefn, primarily
propylene, selectivity.
8
Following the successful start-up
of this RFCC unit in October 2010,
the unit has been continuously
processing untreated residual feed
from various crude sources. The
AFX catalyst system allowed Taiyo
to maximise propylene and main-
tain a proftable yield distribution
while processing highly contami-
nated feedstocks. The propylene
selectivity provided by this system
has reduced the need for ZSM-5
additive, signifcantly decreasing
the activity dilution impact on the
circulating catalyst inventory. The
feedstock for this unit includes a
signifcant level of non-distillable
material, with high Conradson
carbon and sulphur levels (see
Table 6).
Despite the relatively poor qual-
ity feed being processed in this
unit, the combination of effective
reaction zone design, catalyst cool-
ers and a very coke-selective AFX
catalyst system has resulted in a
low delta coke. As Table 7 shows,
the cracking conditions have been
optimised. The resulting high cata-
lyst circulation rate combined with
the high cracking temperature and
highly effective catalyst activity
RFCC feed Heavy case ATB + VTB
Specifc gravity @15C 0.931
UOP K/MW 12.0/400
H
2
, wt% 12.5
S, wt% 0.80
Con carbon, wt% 5.77
N, total, wt ppm 867
Ni, wppm 7.7
V, wppm 5.2
Taiyo Oil Co RFCC feed quality
Table 6
Operating conditions
Reactor temperature, C 536
Reactor pressure, kg/cm
2
1.8
Regenerator temperature, C 735
Catalyst (from regen)-to-oil 8.1
Catalyst activity 67.5
Catalyst Ni, wppm 5300
Catalyst V, wppm 1950
CRC, wt% 0.03
Taiyo Oil Co optimised operating
conditions
Table 7
Yields Wt%
C
2
- 3.25
C
3
2.05
C
3
= 10.27
Saturate C
4
6.40
Total C
4
= 9.65
Gasoline 40.35
LCO 13.25
MCB 6.50
Conversion, vol% 80.25
C
c
recovery, wt% 97.1
C
3
=/total C
3
0.834
Gasoline (R+M)/2 92.15
LCO/MCB 2.04
Taiyo Oil Co average yield distribution
Table 8
facilitated the reactions necessary to
optimise the yield distribution.
Despite the varying feed quality,
the operating fexibility provided
by the units design and the AFX
catalyst have allowed the propylene
yield to be maintained at the 10
wt% target level (see Table 8).
Propylene recovery and olefnicity
have remained excellent despite the
varying feed quality.
Upgrading the heaviest feed
components into lighter, more valu-
able liquid products was an
important objective for Taiyo Oil.
While the relatively severe reaction
conditions contribute to cracking a
portion of these heavy feed compo-
nents, the selectivity is to upgrade
the high molecular weight fraction
to a lighter boiling range. This
provides more valuable products
by maximising the precursors for
propylene production.
Since the initial start-up, the Taiyo
unit has been processing a blend of
untreated atmospheric and vacuum
tower bottoms derived from vari-
ous Middle East and Asia Pacifc
crude oils. The high nickel-to-vana-
dium ratio and low sulphur content
in the combined feed refect the
predominant level of the indige-
nous Asia Pacifc crude in the feed
blend. While the hydrogen content
of the feed blend would seem to
indicate a moderately crackable
feed, the high carbon residue, heavy
metals and non-distillable content
would typically constrain the oper-
ating severity, limiting the potential
propylene production.
The operating conditions are
closely monitored and adjusted to
optimise the yield distribution,
typically maximising propylene, for
varying feed qualities. In order to
meet the maximum propylene
26 PTQ Q3 2012 www.eptq.com
demand, the cracking temperature
and catalyst circulation rate (includ-
ing recycled spent catalyst) were
maximised by optimising the reac-
tor/regenerator heat balance, with
the fow through catalyst coolers.
One of the design objectives was to
minimise hydrogen transfer by
incorporating a short contact time
riser reactor plus a state-of-the-art
riser termination device, the VSS
system. The hydrocarbon/catalyst
contact time in the riser could be
further minimised with the use of
riser diluents. Once the operating
conditions have been set, the key
variable becomes optimising the
catalyst system; in this case,
Albemarles AFX catalyst. This cata-
lyst system allows Taiyo to
successfully process heavy contami-
nated feed components by
combining excellent dry gas and
coke selectivity, metals tolerance,
particularly effective for the high
nickel loading, and bottoms upgrad-
ing to lighter, more valuable
products. In addition to the excel-
lent propylene selectivity, this
catalyst is very selective to
gasoline.
Table 8 summarises the average
yield distribution while processing
the feed blend described in Table 6
at the cracking severity shown in
Table 7. The propylene yield repre-
sents record-high production
derived from cracking untreated
residual feed. The high C
3
olefnic-
ity and resulting propylene yield
refect the low hydrogen transfer
activity provided by the fexibility
of a state-of-the-art reactor design
utilising the appropriate catalyst
albemarle.indd 9 4/6/12 15:15:58
system. The AFX catalyst incorpo-
rates a commercially proven
bottoms cracking function reected
by the excellent LCO-to-main-
column-bottoms (MCB) ratio. This
was important to Taiyo, requiring
that the MCB solids or ash content
be very low. In order to meet this
requirement, the MCB passes
through a solids separation device
with a limited capacity. Excessive
MCB yield could potentially
constrain the RFCC units feed rate.
Summary
Achieving record-high propylene
and conversion from a wide range
of feed qualities offers considerable
challenges to the catalyst design.
The impact of feed composition and
process variables on the yields and
heat balance is signicant and thus
requires a good understanding of
the chemistry to design the right
FCC catalyst for a unit. AFX cata-
lysts, with their low hydrogen
transfer, high accessibility and
powerful matrix technology, are
proven catalysts for maximum
propylene.
Upgrading the heaviest feed
components to lighter, more valua-
ble liquid products was an
important objective for Taiyo Oil.
While the relatively severe reaction
conditions contribute to cracking a
portion of these heavy feed compo-
nents, the selectivity to upgrade the
high molecular weight fraction to
lighter boiling range, more valuable
products, as well as maximise the
precursors for propylene produc-
tion, was provided by the AFX
catalyst. This operation demon-
strates the performance that can be
obtained by applying the appropri-
ate catalyst system to meet reners
goals while remaining within unit
constraints. This particular opera-
tion shows how AFX catalyst
technology can be applied to take
maximum advantage of a unique,
advanced reactor design with oper-
ational excellence.
Acknowledgment
The authors would like to thank Alan Kramer,
FCC Additives Specialist with Albemarle
Corporation, for his valuable contributions to
this article.
References
1 Greensfelder B S, Voge H H, Good G M, Ind.
Eng. Chem., 1949, 41, 2573.
2 Feugnet F, Echard M, Gauthier T, Pilot Plant
Testing for Resid to Propylene, 2009, 8th FCC
Forum, 17.
3 Nieskens M J P C, Maxwell I E, Heinerman
J J L, The assessment of Carbenium-ion and
Radical Cracking in Fluid Catalytic Cracking,
Akzo-workshop The MON of FCC naphtha,
1987, 2.
4 Venuto P B, Habib E T, Fluid Catalytic Cracking
with Zeolite Catalysts, Marcel Dekker, New York,
1979.
5 Plain C, Hyvahl -R2R (RDS-RFCC) The Ideal
Partnership, BBTC Barcelona 2008, 22.
6 Lappas A A, Iatridis D K, Vasalos I A,
Production of Liquid Biofuels in an FCC Pilot
Plant using Waxes produced from Biomass to
Liquid Process (BtL).
7 Pouwels A C, The quintessence of FCC
catalyst design to maximize propylene, ME
Tech 2011, 13.
8 www.uop.com, Rening, Process Technology
and Equipment, RxCatTM FCC Technology,
Process Description.
Jack R Wilcox is the Fluid Catalytic Cracking
Process Specialist in the Applications
Technology group of Albemarle Corporation.
He has over 40 years experience providing
FCC technical services, process development
and design engineering for Rening Process
Services, Akzo-Nobel, Filtrol Catalysts and UOP
Inc. He holds a BS in chemical engineering from
the University of Illinois and is a registered
Professional Engineer in Illinois.
Takuya Amano is a Technical Service
Specialist in the Asia Pacic Renery Catalysts
Technology group of Albemarle Corporation.
He has 14 years experience providing HPC
catalyst production technology and technical
services for Nippon Mining and Japan Energy
Corporation, and six years experience
providing FCC technical services for Albemarle
Corporation. He holds a BS in chemistry from
the Gakushuin University.
Carel Pouwels is the Global FCC Resid
Specialist in the Applications Technology group
of Albemarle Corporation. He has 25 years
experience at Albemarle, predominantly in the
eld of FCC catalysts. His experience includes
the development and application of novel FCC
catalyst technologies and testing equipment.
He holds a degree in chemical engineering
from Delft University of Technology.
Takakazu Matsuura is the General Manager in
Rening Department 2 of Taiyo Oil Co., Ltd and
is responsible for the operation of the resid uid
catalytic cracking (RFCC) complex in Shikoku
Operations. He has over 10 years experience
in process design engineering and seven years
experience in plant operations. Takakazu also
has experience in the construction of RFCC
complexes.
www.eptq.com PTQ Q3 2012 27
Our new clean-fuels
plant is straining the
auxiliary units!
How can we boost their capacity
without major construction?
Read more on this topic at
www.amistco.com
TO MEET CLEAN FUELS require-
ments for gasoline, a medium-sized
Midwestern renery added a low-
sulfur fuels technology plant. Gasoline
throughput was unchanged. However,
the sharp increase in sulfur removal
required more hydrogen from the
hydrogen unit and sent more sulfur
gases to the amine treaters and
downstream sulfur units. These
auxiliary units became bottlenecks,
overdriven at the cost of product
purity and amine consumption.
On studying the hydrogen, amine, and
sulfur units, ACS-Amistco found many
opportunities for improving separation
efciency and capacity. The problems
were solved without major construction
by applying modern technology to mist
eliminators, liquid-liquid separators,
and tower trays and packing. Results
included haze-free product and
reduced amine consumption. Now a
diesel clean-fuels plant is being added.
Prore: 281-331-595 Fax: 281-585-1Z80
amistco@amistco.com
21-rr Erergercy 3erv|ce: 800-839-3Z1
ACS-AMISTCO
albemarle.indd 10 1/6/12 13:16:31
Ai m for More Di esel , Better Di esel
ExxonMobils MIDW
TM
*
technology is a commercially
proven process using an advanced proprietary
catalyst for the production of ultra-low sulfur and
low cloud-point diesel.
Benefits include:
Low-pressure, xed bed process |mproves product
y|e|d and qua||ty
Increased su|fur remova| and reduced naphtha y|e|ds
Propr|etary cata|yst** |somer|zes waxy n-parafns |n
gas o||, to|erant to H
2
S, ammon|a, and organ|c S and N
Stand-a|one or |ntegrate w|th others
* MIDW is a trademark of ExxonMobil Research and Engineering Company
**Available from ExxonMobil Catalyst Technologies LLC
ExxonMob|| Research and Eng|neer|ng
Company's MIDW* Techno|ogy
Improves Product Y|e|d and Qua||ty
3225 Gallows Road, Fairfax, Virginia 22037-0001, USA
www.exxonmobil.com/refningtechnologies +1-703-846-2568 fax +1-703-846-3872 tsl.email@exxonmobil.com
exxonmobil.indd 1 1/6/12 11:46:09
Challenges and opportunities of 10 ppm
sulphur gasoline: part 1
T
he worldwide rening indus-
try has undergone a major
transformation in the last
decade due to changes in regula-
tory and market forces, such as
uctuating crude prices, tighter
regulation on product quality and
renery emissions, shifting crude
quality and fundamental changes in
fuel demands. These forces can be
seen clearly in the North American
market, where crude quality has
become heavier due to increasing
amounts of lower-cost heavy, sour
Canadian bitumen and where regu-
lations have become more severe
by limiting the sulphur level in
fuels to 15 wppm in diesel and 30
wppm in gasoline. In addition to
these feed and product quality
changes, the overall demand for
transportation fuels is shifting from
a traditionally gasoline-oriented to
an increasingly diesel-oriented
market.
Regulatory specications for the
gasoline and diesel pool, which are
constantly evolving, have been in
the forefront of reners challenges
in the last 10 years. In particular, the
gasoline sulphur and benzene regu-
lations have been the main drivers
for the recent remodelling of the
renery conguration. This transfor-
mation has been seen all around the
world, but particularly in Europe,
Asia and North America. Other
countries are following the trend
and a common worldwide gasoline
sulphur specication is on the hori-
zon. Indeed, the overall gasoline
sulphur content is likely to level off
at 10 ppm across the globe. As a
consequence, most reners will face
renewed challenges to be able to
meet the new ultra-low-sulphur
Prospect of a worldwide standard for ULSG and the challenges of increased heavy
crude supplies demand careful consideration and selection of renery conguration
DELPHINE LARGETEAU, JAY ROSS, MARC LABORDE and LARRY WISDOM
Axens
gasoline (ULSG) specications.
However, in view of other market
forces, there may also be new oppor-
tunities for reners.
This article will identify these
new opportunities by reviewing the
processing options and conse-
quences of such regulation, focusing
mainly on North American rener-
ies and drawing on the European
and Asian experience of meeting
the 10 ppm ULSG regulations. The
issues, challenges and opportunities
of each option will be presented
and discussed. In a second article, a
detailed economic assessment of
each conguration will be applied
in a case study.
Gasoline sulphur regulation
There has been a steady downward
trend in the sulphur content of fuels
to reduce emissions from cars and
trucks. Many countries mandated
the production of low-sulphur
gasoline (LSG) some time ago, but
in recent years regulations in
Western Europe, some Asian coun-
tries and California in the US have
brought in even tighter specica-
tions to lower the gasoline sulphur
to 10 ppm.
The different regional approaches
to the gasoline sulphur specication
www.eptq.com PTQ Q3 2012 29
C o u n trie s m a y a p p ly lo we r lim its fo r d iffe re n t g ra d e s, re g io n s/c itie s, o r b a se d o n a ve ra g e c o n te n t.
D iffe re n t in fo rm a tio n o n lim its a n d re g u la tio n s c a n b e fo u n d a t www. ifq c . o rg
Figure 1 Maximum gasoline sulphur limit around the world
Source: International Fuel Quality Center
Region Gasoline sulphur, wppm
Europe: EU 2005 specication 50
EU 2009 specication 10
USA: Tier 2 (2004-2006) 30
CARB 3 (California) 10
2010+ CARB 4 (California) 5
Japan: 2007 specication 10
Current gasoline sulphur specication
Table 1
axens.indd 1 2/6/12 17:26:28
30 PTQ Q3 2012 www.eptq.com
compliance with gasoline sulphur
regulations.
FCC pretreatment vs post-treatment
When the Tier 2 regulations were
proposed, many were convinced
that CFHT would be the solution of
choice due to the resulting large
improvement in FCC performance.
However, the high capital cost
requirement for the FCC pretreat-
ment option coupled with low
refnery margins resulted in the
wide application of FCC post-treat-
ment to reduce gasoline sulphur.
Another factor that can infuence
the decision between pretreatment
and post-treatment is FCC fue gas
emissions. Limits on refnery emis-
sions and in particular those from
the FCC have led to refnery-specifc
regulation via consent decrees with
the EPA, resulting in much lower
SO
x
and NO
x
emissions. The
preferred refnery confguration
may well have been different had
the limits on emissions and product
sulphur been regulated in concert.
More recently, there has been an
important trend towards the process-
ing of increasingly heavier crudes,
in particular heavy Canadian crude
or bitumen. By 2015, there is an
expected increase of about 2 million
b/d of Canadian bitumen, which
will be largely exported to the US as
raw bitumen (DilBit) or synthetic
bitumen (SynBit) after partial
upgrading at the production site.
These very heavy crudes are a chal-
lenge for processing in existing
refnery assets due to a high acid
content (TAN), high aromaticity and
low hydrogen content, along with
very high contaminant content:
sulphur, nitrogen, Conradson carbon
and metals. A sampling of heavy
crude components, which may be
considered potential FCC feed, are
show in Table 2 to highlight the
challenges of processing bitumen-
derived materials.
As a result of these feedstock
trends and a renewed focus on
cleaner fuels, lower emissions and
even a shift in gasoline/diesel
production, the topic of pretreat-
ment versus post-treatment is upon
us again. More specifcally, we will
focus on the pretreat and post-treat
issues around the FCC as it relates
set out in Table 1 show a clear trend
towards ULSG. Other countries are
following the same path to either
meet their domestic regulatory
specifcations or be able to export
and sell on the international ULSG
market (see Figure 1).
Although the majority of coun-
tries still have gasoline sulphur
specifcations well above 10 ppm,
the overall trend clearly shows that
in the near future ULSG production
will become the norm worldwide.
Current refnery confguration
Refnery confgurations vary widely,
depending on crude availability,
local demand, export markets and
regulatory constraints. In the same
way, each market has its own set of
dynamics and means of complying
with the new fuel regulations.
In Europe, regulations for ULSG
were adopted early and somewhat
infuenced by a market demand,
which is more heavily skewed
toward diesel than gasoline. The
options for ULSG compliance were
infuenced by:
Processing of relatively light and
low-sulphur crude oil
Relatively good-quality FCC feed
(little cracked gas oil such as heavy
coker gas oil)
Undercutting of FCC gasoline to
maximise diesel production.
The EUs 10 ppm ULSG is
produced mainly by using moder-
ate severity FCC post-treatment.
Many catalytic feed hydrotreater
(CFHT) units installed in Asian
refneries were designed to meet
modern fuels and emission regula-
tions. As such, many are designed
for high desulphurisation levels to
meet refnery and SO
x
regulations
from the FCC fue gas, resulting
in low-sulphur FCC gasoline.
Consequently, most refneries in
Japan have met the new ULSG limit
of 10 ppm by adding low-severity
post-treatment units.
In the US, the refnery confgura-
tion was infuenced by a large
demand for gasoline coupled with
limited fuel oil outlets, resulting in
the installation of bottom-of-the
barrel conversion units and high
FCC feed sulphur. The US Tier 2
gasoline sulphur and California Air
Resources Board (CARB) regula-
tions led to a sharp increase in the
number of FCC feed pretreatment
and FCC gasoline post-treatment
units over a short period of time
(see Figure 2). Essentially, all of the
US refneries now have pre- and/or
post-treatment units to ensure
2001 2010
P re -tre a t o n ly
P o st-tre a t o n ly
P re - a n d p o st-tre a tm e n t
Figure 2 FCC pretreatment and gasoline post-treatment trend in US refneries
Canadian bitumen Coker HCGO Syn. bitumen Mexican Blend Arabian Light
VGO
API gravity 13 13 18 22 26
Sulphur, wt% 3.3 4-5 1.7 2.2 2.2
Nitrogen, ppm 2100 4000 1500 1000 700
Hydrogen, wt% 10.7 10.5 11.5 11.7 12.4
ATB
API gravity 5.7 9 6 17
Sulphur, wt% 4.9 3.6 3.6 3.1
Nitrogen, ppm 5000 3500 3000 1900
Hydrogen, wt% 9.2 10.8 9.8 11.4
Concarbon, wt% 15.3 11.2 11.6 8.1
Ni + V, ppm 325 200 258 49
FCC feed quality from heavy feeds
Table 2
axens.indd 2 2/6/12 11:36:00
www.eptq.com PTQ Q3 2012 31
to FCC performance, emissions and
the level of product gasoline post-
treatment required.
FCC pretreatment options
The benefts of FCC feed pretreat-
ment in a CFHT are well known
and extend beyond simply reduc-
ing the sulphur level in the FCC
feed. The reduction in sulphur and
other contaminants is helpful in
terms of reducing the FCC product
sulphur level and lowering the fue
gas emissions from the FCC, but
the interaction with improved feed
quality and increased FCC perform-
ance is also very important.
Environmental regulations, and in
particular the need to produce very
low-sulphur gasoline, have put
increased emphasis on CFHT
performance and reliability.
Concurrently, a lower demand
for fuel oil coupled with the
processing of heavier crudes has
resulted in the installation of resi-
due conversion units such as
delayed cokers. These conversion
units produce signifcant amounts
of hydrogen-defcient, heteroatom-
rich (N and S) vacuum gas oils
(VGO, HCGO), which need to be
deeply hydrotreated prior to
conversion in the FCC unit.
As a result, modern CFHT units
need to process increasingly more
refractory feedstocks while achiev-
ing high desulphurisation levels to
meet gasoline sulphur specifca-
tions. The increased contaminants
also make it more diffcult for the
CFHT to upgrade the quality of the
FCC feed to maintain the required
yield of gasoline and LPG. In addi-
tion to the objective of
hydrodesulphurisation, hydrodeni-
trogenation and polynuclear
aromatics (PNA) saturation, the
processing of cracked stocks in a
CFHT, often with high end-point to
maximise refnery economics,
requires a careful selection of the
catalytic system to take into account
the potential for higher metals
(nickel, vanadium, arsenic, silicon)
and asphaltenes, along with the
higher fouling propensity of these
aromatic-rich feeds.
On the other hand, this problem
can turn into an opportunity to
increase the severity of the CFHT,
not only to meet sulphur targets
but also to change the diesel-to-
gasoline ratio by operating in mild
hydrocracking (MHC) mode and
taking advantage of low-cost natu-
ral gas to further increase volume
swell. These adjustments will
require some modifcations to the
operating conditions, selection of
the optimum catalytic system and
distributor internals, increased
hydrogen consumption and likely
upgrades throughout the unit. One
of the challenges of operating in the
MHC mode is the ability to meet
ultra-low-sulphur diesel (ULSD)
specifcations throughout the MHC
cycle. Moderate-pressure MHC
units generally do not meet the
required diesel specifcations, there-
fore post-treatment is required. One
option to meet this challenge is the
HyC-10 technology developed by
Axens to integrate diesel upgrading
within the MHC high-pressure loop
while decoupling operating condi-
tions.
1,2
Another important factor in
MHC/CFHT design is the ability to
maintain desulphurisation targets
while meeting optimum VGO qual-
ity throughout the cycle length.
In conclusion, a deep understand-
ing of the feedstock type and the
chemical reactions involved in a
CFHT (kinetics, thermodynamics,
contamination/poisoning) coupled
with their impact on the FCC oper-
ation is paramount to selecting
optimum CFHT operating condi-
tions and design of the optimum
catalyst system. The following
section will examine the infuence
of the CFHT operation on the FCC
units performance.
Impact of CFHT on FCC performance
The FCC unit has long been the
workhorse in the refnery to achieve
relatively low-cost conversion of
heavy crude components (VGO,
HCGO and some atmospheric resi-
due) into gasoline, butenes for
high-octane alkylate production,
propylene and LCO diesel blend
components. Although the chemis-
try and catalyst systems can be
complex, generally speaking the
FCC unit is a hydrogen redistribu-
tion system with some carbon
rejection as coke, which is consumed
in the process. The performance of
the FCC unit and the yield of valua-
ble products is therefore linked to
the hydrogen content of the feed.
This trend is shown in Figure 3,
where the conversion potential and
gasoline yield increase sharply with
the hydrogen content of the feed.
The CFHT therefore plays a vital
role in improving the FCC feed
quality to enhance the yield and
overall refnery proftability. As the
feed contaminants of sulphur and
nitrogen are reduced to improve
product quality and reduce FCC
emissions, multi-ring aromatics are
saturated and the crackability of the
feed increases. Sharp gains in
conversion and gasoline yield result
from the frst incremental increase
in hydrogen and there is some
degree of diminishing returns (see
Figure 3). When propylene yield is
of interest, the increased hydrogen
6 5
8 5
8 0
7 5
7 0
6 0
5 5
5 0
4 5
4 0
1 0 . 5 1 1 . 0 1 1 . 5 1 2 . 0 1 2 . 5 1 3 . 0 1 3 . 5
w
t
%
Feed hydrogen, wt %
3 5
1 2
2 0
1 8
1 6
1 4
1 0
8
6
4
2
w
t
%
0
P
r
o
p
y
le
n
e
p
o
t
e
n
t
ia
l
F u e l o il
C o n ve rsio n
G a so lin e
Figure 3 FCC yield vs feed hydrogen content
axens.indd 3 2/6/12 11:36:13
The art of recovering maximum value from
your precious metal bearing materials.
The sc ienc e of recovering maximum value from
your precious metal bearing materials begins with
the most techni cal l y advanced anal yti cal ,
research, and sampling equipment, systems, and
procedures. The art of recovering maximum value is
a different story; thats based on seven decades of
experience and success serving thousands of organi-
zations around the world.
At Sabin Metal we combine science and art to
maximize your returns, speed process turnaround
times, and comply with environmental regulations
for safety, security, and peace of mind. If these
advantages are important to you, we'd like to
explain how we fit into your precious metals asset
recovery program. Let us hear from you today.
At Sabin Metal
weve turned science into art:
Learn more at sabinmetal.com
Sabin-ScienceToArt.indd 1 2/27/12 1:50 PM sabin.indd 1 1/6/12 12:12:48
signifcantly help control the
sulphur level when producing
ULSG, as is done in Europe.
Considering the dependence of
FCC gasoline on both CFHT
performance and precise fractiona-
tion of the gasoline product,
meeting ULSG targets through
CFHT alone is possible but chal-
lenging. There will be little room
for error or deterioration in CFHT
performance over the course of a
production run or cycle.
www.eptq.com PTQ Q3 2012 33
input is always benefcial, and in
many cases high hydrogen input
can be justifed, particularly when
hydrogen is relatively inexpensive.
3
As the severity of the CFHT
increases, there is also the opportu-
nity for co-produced diesel in the
CFHT via mild hydrocracking to
shift the overall refnery balance
between gasoline and diesel.
Defning the optimal balance
between severity, hydrogen input,
cracking and FCC mode of opera-
tion within the existing constraints
of a refnery confguration is there-
fore very complex.
Within the context of ULSG, the
more traditional role of the CFHT
to consider is that of desulphurisa-
tion and the impact on the FCC
gasoline produced. As the sulphur
content in the FCC unit feed
decreases and the extent of feed
hydrotreating increases, the types
of sulphur left in the FCC feed alter
and the amount of sulphur found
in the gasoline decreases. Figure 4
shows this general trend for feeds
that are hydrotreated and for non-
hydrotreated feeds of varying
sulphur content.
If one were to target the new
ULSG pool sulphur level of 10 ppm,
the CFHT must reduce the feed
sulphur to about 200-300 ppm,
considering a ratio of between 20:1
and 30:1 of the hydrotreated feed
sulphur to the gasoline sulphur.
This will be true even if we consider
that the FCC gasoline is only about
one-third of the pool and the other
blend stocks are nearly sulphur-
free, as refners will leave some
margin below 10 ppm to ensure
compliance.
When looking at the sulphur in
FCC gasoline, one needs to be very
clear about the gasoline cut point
and the distillation tail on the
produced gasoline product. In
Figure 5, we can see a carefully
analysed commercial FCC gasoline
and the cumulative full-range gaso-
line sulphur versus true boiling
point (TBP).
Figure 5 clearly demonstrates the
importance of defning the gasoline
boiling range when discussing the
sulphur level. In the US market,
gasoline has been traditionally
over-cut relative to the standard
430F (220C) cut and often
extended to 450-480F (230-250C),
thereby including not only benzo-
thiophene but also some
methyl-benzothiophenes in the
gasoline. These compounds enter
the gasoline cut just at the standard
cut point and complicate accurate
measurement of gasoline sulphur
from non-ideal industrial samples.
With the increased interest in distil-
late production, undercutting the
gasoline to less than 430F will
Table 5
6 0
1 0 0
8 0
4 0
2 0
2 5 5 0 7 5 1 0 0 1 2 5 1 5 0 1 7 5 2 0 0 2 2 5 2 5 0
C
u
m
u
l
a
t
i
v
e
s
u
l
p
h
u
r
,
%
Temperat ure, C
0
T h io p h e n e
C 1 -T h io p h e n e
C 2 -T h io p h e n e
B e n zo -
T h io p h e n e
A lk yl-B e n zo -
T h io p h e n e
S
S
M e rc a p ta n s
Figure 5 FCC gasoline sulphur profle
Typical Feed sulphur, wppm Product sulphur, wppm
Western Europe 200-1000 10-20
North America 500-2000 30-50
California 100-300 10-20
South America 500-2000 30-100
Japan/Korea 50-200 10
FCC gasoline post-treatment unit design
Table 3
1 0 0 0
1 0 0 0 0
1 0 0
1 0
0 . 0 1 0 . 1 1 1 0
G
a
s
o
l
i
n
e
S
,
w
t
p
p
m
Feed sul phur, wt %
1
H yd ro tre a te d
S tra ig h t ru n
Figure 4 FCC gasoline sulphur vs feed sulphur and treatment
axens.indd 4 2/6/12 17:27:18
FCC post-treatment options to
meet ULSG
In order to comply with low-
sulphur gasoline regulations, a
majority of refners across the world
have already invested in a FCC
post-treatment unit. However,
processing schemes vary greatly
from one site to another, depending
on sulphur specifcation, overall
refnery confguration and crude
diet (see Table 3).
Most refneries in California and
Japan are equipped with FCC feed
pretreaters, which explains the low
sulphur level in FCC naphtha.
Conversely, FCC naphtha sulphur
tends to be high in the Americas,
and high-severity post-treaters will
be required to meet the 10 ppm
gasoline sulphur target.
The Prime-G+ process selectively
desulphurises FCC full-range naph-
tha (FRCN) while ensuring minimal
octane loss. It is a widely used
cracked gasoline desulphurisation
technology, with over 190 licensed
units throughout the world.
4
The
technology has proven to be highly
fexible, with several Prime-G+
processing schemes offered accord-
ing to the targeted severity of the
unit (see Figure 6).
Exploiting existing Prime-G+ units
Depending on the existing Prime-
G+ confguration, meeting new
ULSG regulations at 10 ppm while
using the existing assets could be
achieved in different ways. First,
one potential solution that does not
require any additional investment
would be to simply increase sever-
ity (essentially reactor temperature)
to lower the existing Prime-G+
product sulphur. The increased
HDS level would lead to a higher
octane loss and hydrogen consump-
tion, coupled with a potential cycle
length reduction. Switching to
higher selectivity and activity
Prime-G+ catalysts may help miti-
gate these drawbacks, but could
prove insuffcient in many cases.
Another solution would involve
the co-processing of other sulphur-
rich streams in the Prime-G+ unit
that previously did not require any
treatment to meet the earlier
sulphur specifcations. The streams
could be light such as light coker
naphtha or visbroken naphtha that
can be handled in the frst step
(selective hydrogenation unit
SHU and splitter section). Light,
straight-run naphtha, natural gaso-
line could also be co-processed
either in the SHU upstream of the
splitter or directly in the HDS
section. One of the drawbacks of
co-processing is possible hydraulics
limitations in the unit. In addition,
34 PTQ Q3 2012 www.eptq.com
SHU HDT
ULSG
FCC
FRN
Low/moderate HDS
P rim e -G +1 -sta g e H D S
Moderate/high HDS
SHU
HDT
1&2
ULSG
FCC
FRN
P rim e -G +2 -sta g e H D S
SHU
HDT
ULSG
FCC
FRN
P rim e -G +1 st ste p S H U & sp litte r / 1 -sta g e H D S
Very high HDS
SHU
HDT
1&2
ULSG
FCC
FRN
P rim e -G +1 st ste p S H U & sp litte r / 2 -sta g e H D S
Figure 6 Prime-G+ processing schemes
axens.indd 5 2/6/12 11:36:41
adding sulphur-rich streams could
lead to a higher HDS level coupled
with a higher octane loss and,
again, the potential for a reduced
cycle length.
An alternative option would be to
decrease the Prime-G+ feed sulphur
to maintain a similar HDS level
across the unit to ensure constant
octane loss and cycle length.
Lowering the feed sulphur could be
achieved in different ways. The
short-term solutions would be to
use sulphur reduction additives in
the FCC unit or to process low-
sulphur crudes. Both of these
options have limitations and are
generally not practical for a signif-
cant sulphur reduction without a
heavy penalty on refnery fexibil-
ity. More realistically, a reduction
in the FCC naphtha end-point or
changes in the CFHT could be envi-
sioned to reduce the sulphur in the
FCC naphtha. In Western Europe, it
is common to reduce the FCC naph-
tha end-point, as it also maximises
diesel production to meet market
demand.
Revamping FCC post-treatment
units
As most refneries are equipped
with a FCC post-treatment unit to
control gasoline sulphur, it is
instructive to take a closer look at
the revamping options around the
selective FCC naphtha desulphuri-
sation unit to meet the new ULSG
requirements. There are a number
of ways to revamp an existing
selective FCC naphtha desulphuri-
sation unit to meet tighter sulphur
specifcations, which display differ-
ent levels of complexity and
associated cost:
Option 1: Install a Prime-G+ frst
step if not existing
Option 2: Add a SHU (selective
hydrogenation unit) or HDS reactor
if the cycle length is a limitation for
the new product sulphur target
Option 3: Route the medium cata-
lytic naphtha (MCN) cut to the
NHT/reformer
Option 4: Process the medium
catalytic naphtha (MCN) and the
heavy catalytic naphtha (HCN)
streams separately
Option 5: Install a second-stage
HDS section.
In option 1, the installation of a
FCC naphtha splitter downstream
of the existing (or new) SHU is the
Prime-G+ frst step. The SHU oper-
ating conditions and catalyst design
allow for the selective hydrogena-
tion of diolefns, which may foul
the desulphurisation section, and
also the conversion of light sulphur
species such as mercaptans to heavy
boiling sulphur compounds. As a
result of the chemical reactions
taking place in the SHU, the down-
stream splitter produces a sweet,
low-sulphur, light catalytic naphtha
(LCN) stream rich in olefns and a
heavy FCC naphtha (HCN), which
is routed to the HDS section. Such
a HCN stream with its lower olefns
content can be selectively desul-
phurised through the use of tailored
catalysts to meet the ULSG target
while controlling olefns saturation
and thus octane loss. Addition of
the splitter reduces the throughput
to the HDS section and hydrogen
consumption. This solution also
allows the co-processing of other
streams containing sulphur, such as
coker naphtha, visbroken naphtha,
straight-run naphtha or natural
gasoline.
For option 2, the addition of a
SHU upstream of an existing split-
ter will produce a sweet
low-sulphur LCN stream and
provide benefts similar to those
described in option 1. In case cycle
length becomes limited, implemen-
tation of an additional HDS reactor
in series with the existing one can
be envisioned. Options 1 and 2 are
easy to implement and lead to
moderate capital expenditure. The
typical block fow diagram of
Option 3 is shown in Figure 7.
This option involves revamping
the existing splitter into a three-cut
column in order to withdraw a
heart cut (MCN) rich in olefns that
contains some sulphur and exhibits
a moderate octane number (espe-
cially MON). The MCN is then
mixed with the normal feed to the
NHT unit and reformer unit.
Sending the MCN to the reformer
will lead to a gasoline octane gain.
However, there may be limitations
in terms of capacity for both NHT
and reformer sections that need to
be carefully assessed and taken into
account for the evaluation of the
overall revamp cost. In addition,
potential increased benzene produc-
tion in the reformer could lead to
issues in meeting the MSAT II gaso-
line benzene specifcations. The
addition of an integrated reformate
splitter/benzene hydrogenation
(Benfree) resolves this issue.
5
While this solution offers some
advantages in terms of octane, the
decreased gasoline yield should
also be considered. Overall, this
option may be attractive, but has
more implications than just making
modifcations to the existing FCC
post-treatment section.
www.eptq.com PTQ Q3 2012 35
NHT
Prime-G+
Reformer
S R N
H C N
F R C N
L C N
M C N
H C N
C o k e r N
Isom
Splitter
Splitter
Benfree
MoGas
pool
Figure 7 FCC naphtha heart cut (MCN) to reformer
axens.indd 6 2/6/12 11:36:54
Decoupling of the MCN and
HCN can also be utilised to treat
these streams in two separate selec-
tive HDS sections. This is option 4
and is illustrated in Figure 8.
This innovative and patented
scheme by Axens has the additional
advantage of offering greater exi-
bility to route the desulphurised
HCN either to the MoGas or diesel
pool, according to the economics of
the renery.
6
Both MCN and HCN
selective HDS sections are designed
to minimise octane loss while
achieving 10 ppm product sulphur.
Compared to the previous option,
option 4 incurs more revamping
costs, as a new MCN HDS section
needs to be installed. But the addi-
tional cost could be easily offset by
the improved octane retention
compared to treating the combined
MCN and HCN in a single one-
stage selective HDS section at ULSG
levels and by the additional exibil-
ity that this option offers.
The last option explored here,
option 5, is the inclusion of a
second-stage HDS section to mini-
mise octane loss and maintain or
even increase the catalyst cycle
length. The typical block ow
diagram is shown in Figure 9.
Although the splitter is shown here
upstream of the HDS section, Axens
also has experience of designing a
two-stage HDS section on full-range
FCC naphtha with no upstream
splitter.
In a typical one-stage HDS cong-
uration, olens saturation, and thus
octane loss, increases rapidly above
98% HDS. At a high HDS level, the
addition of a second-stage HDS
section helps improve octane reten-
tion and minimise hydrogen
consumption.
Several Prime-G+ units have been
designed for two-stage operation
and many are in operation.
Although this option requires addi-
tional capital investment, there is a
real incentive to pursue this solu-
tion when the renery is octane
tight or hydrogen constrained.
These options provide commer-
cially proven solutions for reners
to meet new ULSG specications
with existing or modied post-
treatment units. In view of the low
renery margins and octane-long
position resulting from the ethanol
mandate, the debottlenecking of a
selective FCC naphtha desulphuri-
sation unit will likely be the
preferred solution for many ren-
ers, assuming no signicant changes
in their crude diet.
A number of reners are,
however, envisioning the process-
ing of heavy crudes such as those
derived from Canadian oil sands
due to their lower cost coupled
with geopolitical reasons. Processing
of these heavy crudes requires a
complete renery reconguration
with bottom-of-the-barrel conver-
sion units such as coking or
ebullated-bed hydrocracking. As
was discussed earlier, the resulting
VGO and HCGO streams are very
refractory with high levels of
sulphur and nitrogen and a very
low hydrogen content. Such feeds
require deep pretreatment prior to
feeding the FCC unit to maintain
acceptable yields. Since FCC
pretreatment (CFHT) is mandatory
in those cases, one may wonder
whether a post-treatment unit is
required or not. In a second article,
an economic evaluation will illus-
trate the pros and cons of FCC
pretreatment only or in combina-
tion with post-treatment.
Conclusion
North American reneries need to
adapt to tightening sulphur speci-
cations and the prospect of ULSG
at 10 ppm. This challenge will be
exacerbated by the increased
proportion of heavy crudes and the
gasoline/diesel imbalance. This
article has presented commercially
proven congurations that are
available to meet these constraints
and maintain protability. A combi-
nation of pre- and post-treatment
36 PTQ Q3 2012 www.eptq.com
Prime-G+
selective
hydrogenation
SHU
Splitter
F R C N
H
2
m a k e -u p
H C N
1 5 0 F +
U ltra -lo w-su lp h u r
g a so lin e to M o G a s
H
2
S
1st stage
HDS
2nd stage
HDS
U ltra -lo w S L C N to P o o l,
TA M E o r A lk y U n it
Prime-G+
selective
hydrogenation
SHU
Splitter
F R C N
MCN
HDS
HCN
HDS
Process
integration
U ltra -lo w S L C N to P o o l,
TA M E o r A lk y U n it
U L S M C N :
1 5 0 -3 0 0 F to M o G a s
U L S H C N :
3 0 0 F -F B P to
M o G a s o r d ie se l
Figure 8 Decoupling MCN and HCN processing
Figure 9 Revamp of Prime-G+ HDS into two-stage conguration
axens.indd 7 2/6/12 11:37:12
may be necessary, depending on the initial refnery
confguration, local market demands, emissions regula-
tions and the crudes processed.
A second article will present a detailed economic
evaluation to allow comparison of the costs and returns
between the FCC feed pretreatment alone and post-
treatment options, as well as the optimum
desulphurisation and cycle length for the CFHT when
considered in combination with a post-treatment.
These confgurations will be applied in the context of a
refnery being revamped to process heavy Canadian
crudes and maintaining its FCC unit. The VGO feed-
stock considered for this economic evaluation will be a
55 000 b/d blend of straight-run VGO and heavy coker
gas oil with 4.2 wt% sulphur.
Acknowledgement
The paper was frst presented at the 2011 AFPM (or NPRA) Annual
Meeting.
References
1 Bonnardot J, et al, Direct Production of Euro-IV Diesel at 10 pm Sulphur
via the HyC-10 Process, ERTC 9th Annual Meeting, Nov 2004.
2 Sarrazin P, et al, New mild hydrocracking route produces 10-ppm-
sulphur diesel, Hydrocarbon Processing, Feb 2005.
3 Roux R, et al, Resid to Petrochemicals Technology, ERTC 13th Annual
Meeting, Nov 2008.
4 Debuisschert Q, Prime-G+ Commercial Performance of FCC Naphtha
Desulphurization Technology, AM-03-26, NPRA Annual Meeting, Mar
2006.
5 Largeteau D, et al, Benzene Management in a MSAT 2 Environment,
AM-08-11, NPRA Annual Meeting, Mar 2008.
6 Debuisschert Q, et al, Technology Solutions addressing gasoline and
diesel imbalances, Platts European Refning Market 4th Annual Meeting,
Sept 2010.
Delphine Largeteau is Technology Manager for Olefns & Light Oil
Hydroprocessing, Axens. She joined Axens in 1998 as Process Engineer
and moved to the North American offce in November 2001, where
she served as Proposal & Technology Engineer, focusing on light ends
and Prime-G+ technologies, before attaining her current position. She
holds a degree in chemical engineering from Universit Technologique
de Compigne (UTC) in France and a masters in refning, engineering
and gas from the IFP School.
Jay Ross is a Technology and Marketing Manager covering the feld of
transportation fuels, including FCC, catalytic reforming, isomerisation
and biodiesel production. He has over 30 years of experience in the
refning and petrochemical industry, including process engineering
design, R&D, licensing and technical assistance. He holds a degree in
chemical engineering from Princeton University. He has served on the
NPRA and ERTC expert panels, and has authored several patents and
numerous technical papers and articles. He is currently stationed in
Singapore.
Marc Laborde is Strategic Marketing Engineer in Axens Marketing
Department. After a frst experience with ExxonMobil, he joined
Axens in 2010 at his current position. He holds a degree in chemical
engineering from Ecole Nationale Suprieure de Chimie in Caen and a
masters in refning, engineering and gas from the IFP School.
www.eptq.com
BORSIG ZM Compression
GmbH
Seiferitzer Allee 26
D-08393 Meerane / Germany
Phone: +49 (0) 3764 / 5390-0
Fax: +49 (0) 3764 / 5390-5092
E-mail: info@zm.borsig.de
www.borsig.de/zm
Commitment for Life
BORSIG ZM CompressionGmbH, a member of the
BORSIG Group, offers flexible, innovative and high-quality
solutions for compressors. Our products stand for high
quality, competence and reliability.
RECIPROCATING COMPRESSORS
for Process Gases
Our reciprocating compressor series is of modular design
and complies with the API 618 design standards. The series
has been developed for the heaviest continuous operation.
Today BORSIG ZM is able to offer reciprocating compres-
sors in vertical and horizontal design with up to a maximum
of 6 axes.
Discharge pressure: ... 1,000 bara
Capacity/flow: ... 115,000 m/h
Power: ... 16,000 kW
CENTRIFUGAL COMPRESSORS
for Process Gases
The BORSIG ZM T-Jet-series comprises multistage inte-
grally geared centrifugal compressors which comply with
the corresponding API design standards, such as API 617.
Discharge pressure: up to 80 bar
Capacity/flow: 1,100 ... 40,000 m/h
Power: 100 ... 12,000 kW
Additional products and services of BORSIG ZM Compres-
sion GmbH:
Reciprocating Compressors for CNG Filling Stations,
Compressor Parts, Services
ACHEM
A, 9.1-B42
NEFTEGAZ, 21C17
axens.indd 8 5/6/12 10:09:43
Selas Fluid has supplied innovative heater and furnace technologies to reneries and
petrochemical plants worldwide for more than six decades.
As an approved supplier of renery heaters, petrochemical furnaces and incineration technologies to major oil and
gas companies, Selas Fluid is prepared to surpass your expectations. We have built a history of proven results, with
thousands of installations, by providing continuous innovation, quality products and reliable customer support.
Selas Fluid is a full-service partner to the rening, petrochemical, and chemical industries worldwide.
Equipment supply
Process design and engineering
Modular construction
Erection services
Revamp, retrot and upgrade
Consultation and feasibility studies
Start-up and operator training
Spare parts and technical services
Selas Fluid
Subsidiary of The Linde Group
Headquarters:
Five Sentry Parkway East
Blue Bell, PA 19422 USA
Telephone: 610-834-0300
Texas Ofce:
16225 Park Ten Place
Suite 250
Houston, TX 77084 USA
Telephone: 281-717-9090
Al-Khobar:
Linde Arabian Contracting
Telephone: +966-3-887-0133
www.lindeus-engineering.com
selas.indd 1 1/6/12 12:13:56
Natural gas fuels the integration of
refning and petrochemicals
R
ising oil prices and weak fuel
demand in the recent past
have had a signifcant impact
on gross refnery margin (GRM).
Historical data show that refneries
with bottom-of-the-barrel process-
ing facilities and an integrated
petrochemicals complex have
performed well to stay ahead of the
competition because of their greater
fexibility to maintain a healthy
GRM. A robust refnery confgura-
tion that is fexible enough to
process a variety of crudes, includ-
ing diffcult opportunity crudes,
along with an integrated petro-
chemicals complex is key to
sustaining a healthy GRM.
However, simple integration of a
refnery and a petrochemicals
complex may not be enough.
Integration should be smart enough
to address volatility in the market
by ensuring a healthy GRM and
minimising environmental impact
by reducing carbon footprint. Use
of natural gas fuel addresses this
issue to some extent by enabling
the recovery of valuable compo-
nents from refnery off-gases and
facilitating the release of a good
quantity of naphtha for the genera-
tion of a valuable petrochemicals
feedstock. It also enables the
production of more middle distil-
late from bottom-of-the-barrel
processing and helps reduce the
carbon footprint of the overall
complex. The price differential
between crude and natural gas,
especially in countries where natu-
ral gas is readily available, makes
the use of gas a hugely proftable
proposition. Even in countries
where both natural gas and crude
are imported, there is a case for gas
Maximising the use of natural gas in a refnery-petrochemicals complex offers
higher margins and lower carbon emissions
TanMay TaRaphdaR, pRaveen yadav and M K e pRasad
Technip KT India
that needs to be looked into. This
article aims to explore various
options available to refners to
enhance their GRM and reduce
their carbon footprint through the
use of natural gas.
Refnery fuel consumption and
generation
A refnery consumes fuel gas and
fuel oil produced from various
refnery processes. No supplemen-
tary fuel is required for refnery
operation. Generally, naphtha is
used as feed and fuel for the hydro-
gen generation unit and gas
turbines. A typical fuel consump-
tion pattern in a refnery is shown
in Figure 1.
Fired heaters in various process
units consume about 40-50% of fuel.
The utility system, including boilers
and gas turbines, consumes about
30-40% of fuel and the hydrogen
generation unit consumes about 15-
20% of fuel. The contribution of the
hydrogen generation unit includes
both feed and fuel. Typically, a
refnery with secondary processing
facilities such as fuid catalytic
cracking (FCC) and hydrocracking
consumes about 8-10 wt% of crude
throughput as fuel, including naph-
tha used in the hydrogen generation
unit and gas turbines. If the refnery
is integrated with a petrochemicals
complex, which is highly energy
consuming, fuel consumption is
signifcantly higher. This fuel
requirement is satisfed by fuel oil
and fuel gas generated from vari-
ous process units.
Fuel oil is mainly generated from
the vacuum distillation unit and the
FCC units main fractionator
bottoms in the absence of bottom-
of-the-barrel processing facilities in
the refnery. Vacuum residue is
generally taken through a
visbreaker unit to produce fuel oil.
Generation of fuel oil can vary
between 5 and 50% of feed to the
vacuum distillation unit, depending
upon the type of crude processed,
while fuel oil from the FCC units
main fractionator bottoms can vary
between 4 and 6 wt% of the FCC
units feed.
www.eptq.com PTQ Q3 2012 39
H yd ro g e n p la n t
U tilitie s
P ro c e ss h e a te rs
Figure 1 Fuel consumption pattern in a refnery
technip.indd 1 1/6/12 14:19:33
40 PTQ Q3 2012 www.eptq.com
distillate from the refnery.
Additional naphtha generated from
the delayed coker can be used as
feedstock for the naphtha cracker.
Moreover, off-gas from the delayed
coker contains good amounts of
ethylene, ethane and propylene.
Ethylene and propylene can be
recovered and used as petrochemi-
cals feedstock after suitable
treatment for the removal of impu-
rities, while ethane can be sent to a
steam cracker for the production of
petrochemicals feedstocks. Thus,
replacing fuel oil with natural gas
not only eliminates low-value fuel
oil generation, but also enhances
refnery and petrochemicals integra-
tion along with high-value middle
distillate production. This changeo-
ver, replacing fuel oil by natural
gas in the existing fred heaters,
requires careful evaluation of the
thermal, mechanical and hydraulic
adequacy of existing hardware,
particularly with respect to burners,
tube metallurgy, refractory, air
preheater systems and so on.
Natural gas as feed and fuel for
steam reforming
Hydrogen is one of the most impor-
tant utilities in the refnery. It is
required to remove impurities,
including sulphur and nitrogen,
from various refnery products and
intermediate streams. Hydrogen is
produced mainly by the steam
reforming of naphtha. The hydro-
gen requirement varies widely,
depending on the crude processed
and the refnerys product
specifcations.
Typically, four tons of naphtha
are required as feed and fuel to
produce one ton of hydrogen, while
about 3.5 tons of natural gas are
required to produce one ton of
hydrogen. Use of natural gas as
feed and fuel for the hydrogen
plant will release a good quantity
of naphtha. This naphtha can be
utilised further for producing value-
added petrochemical feedstocks. A
switch from naphtha to natural gas
requires certain modifcations in
various sections of the hydrogen
generation unit:
Feed pumping/compression and
preheating Naphtha pumps, naph-
tha vaporisers and superheaters are
A typical contribution of fuel gas
generation from various process
units of a refnery using Arabian
Heavy and Arabian Light crude
mix is shown in Figure 2. Delayed
coker, FCC unit, gasoline block
(catalytic reforming unit with isom-
erisation or alkylation), crude
distillation unit and hydrocracker/
hydrotreaters (naphtha, kerosene,
diesel and VGO) contribute typi-
cally about 40%, 16%, 17%, 2% and
25% respectively towards fuel gas
generation from the refnery.
Many modern refneries have an
integrated petrochemicals complex
to improve proftability. A signif-
cant amount of fuel gas is also
generated from the naphtha cracker
complex, while a small amount of
fuel gas is generated from the
aromatics complex (excluding the
catalytic reforming unit). Typically,
about 16-17 wt% of feed is
converted into fuel gas in the
ethane cracker, while about 17-18
wt% of feed is converted into fuel
gas in the naphtha cracker. Fuel oil
generation from the ethane cracker
is negligible, but it can be as high
as 10 wt% of feed for the naphtha
cracker.
A petrochemicals complex is also
a major energy consumer. A steam
cracker consumes lot of power in
its cracked gas compressors and
refrigeration compressors. Typically,
600-620 kWh of power is required
for one ton of ethylene production.
Generally, a naphtha cracker is a
net exporter of fuel gas and fuel oil,
while an ethane cracker is a net
consumer of fuel gas. A paraxylene
complex is a net consumer of fuel
gas/fuel oil and power. About 0.3
tons of fuel gas and 320-360 kWh of
power are required for one ton of
paraxylene production. Refnery
products such as fuel gas, fuel oil,
naphtha and diesel are used to
satisfy the fuel and power require-
ment of the steam cracker and
aromatics complex. Natural gas can
be utilised as fuel for an integrated
r ef i ner y- cum- pet r ochemi cal s
complex while maintaining fexible
product objectives.
Use of natural gas in the refnery
Natural gas or regasifed liquid
natural gas can be used in a refn-
ery for various purposes:
Fuel for process and utility heat-
ers, replacing fuel oil
Feed and fuel for the hydrogen
generation unit, replacing naphtha
Fuel for gas turbines, replacing
naphtha
Fuel for process heaters, replacing
fuel gas.
Each of these cases will be
discussed in detail.
Natural gas as fuel for process and
utility heaters, replacing fuel oil
Use of natural gas as a fuel to
replace fuel oil provides the oppor-
tunity to either reduce or eliminate
fuel oil generation from the refnery
by utilising bottom-of-the-barrel
processing technology. So far, the
delayed coker unit is one of the
most economical options for this
type of processing. Other technolo-
gies that are available and used
presently offer lower yields of
distillates and do not eliminate fuel
oil generation completely. New
technology such as slurry hydroc-
racking, which is on the verge of
commercialisation, promises to offer
a better distillate yield and mini-
mum residue generation. However,
our discussion is restricted to the
delayed coker, since it has a proven
operational track record. Typically,
a distillate yield (combining naph-
tha and diesel) of about 65% is
obtained from the delayed coker,
which may result in 10-12% more
M S b lo c k , 1 7 %
D C U , 4 0 %
F C C U , 1 6 %
C D U , 2 %
H C U & H D Ts, 2 5 %
Figure 2 Fuel gas generation in a refnery
technip.indd 2 1/6/12 14:19:45
Boots on the Ground. Eyes on the Horizon.
Enersul has been putting boots on the ground designing, operating, and innovating industry leading
sulphur processing and handling solutions for over 60 years. We are continuously improving our
. e c n e i r e p x e l a n o i t a r e p o e v i s n e t x e r u o h g u o r h t d e n i a g e g d e l w o n k e h t g n i y l p p a , s n o i t u l o s l a c i n h c e t f o e g n a r e d i w
It is this rich history that enables us to keep our eyes on the horizon, always looking forward to ensure
we are providing the best possible technical and operational solutions for today and tomorrow.
When it needs to be done right, rely on
7210 Blackfoot Trail SE Calgary, Canada T2H 1M5 | +1 403 253 5969 | enersul@enersul.com| enersul.com
trusted experience. proven excellence.
enersul.indd 1 1/6/12 11:43:29
42 PTQ Q3 2012 www.eptq.com
not required, while a natural gas
compressor may be required
Hydrodesulphurisation If regasi-
fed liquid natural gas is used as
feedstock, pre-desulphurisation is
not required due to the very low
sulphur content of the feed.
Additionally, natural gas is olefn
free, so there will be no threat from
olefns to the reformer catalyst
Reformer fring The stoichiometric
air requirement will be changed due
to the change in the hydrogen-to-
carbon ratio of the fuel, which will
call for burner tip modifcations
High-temperature shift reaction,
steam generation and pressure swing
adsorption A lower load on the
high-temperature shift reactor and
lower steam generation due to less
fring are to be expected. Pressure
swing adsorption is generally not
affected by this change-over.
Replacing naphtha with natural
gas as feed and fuel for the hydro-
gen plant not only helps the refners
to produce more valuable products
but also helps to reduce the carbon
footprint of the refnery. Typically,
the changeover from naphtha to
natural gas will help refners to
reduce CO
2
emissions from the
hydrogen generation unit by 25%.
Natural gas as fuel for gas turbines
The gas turbine is the main work-
horse for power generation in the
refnery. A part of the power
requirement of the refnery is satis-
fed by steam turbines utilising the
cogeneration potential to generate
various levels of steam required in
the refnery. The balance part of
the power requirement is satisfed
by gas turbines. Generally, naph-
tha is used as fuel for gas turbines.
Typically, 0.25 tons of naphtha is
required to generate 1 MWh of
power from a gas turbine. When
naphtha is replaced by natural gas
as fuel for a gas turbine, it releases
a signifcant amount of naphtha
which can further be utilised for
valuable product generation.
About 0.2 tons of natural gas are
required for 1 MWh of power
generation. This switchover also
helps refners to reduce CO
2
emis-
sions from a gas turbine by
25-30%.
Natural gas as fuel for fred heaters,
replacing fuel gas
Fuel gas is mainly generated from
the following refnery sources:
Saturated gas from the crude
distillation unit
Off-gases from hydrodesulphuri-
sation/hydrotreating units: naphtha
hydrotreater, kerosene hydrotreater,
diesel hydrotreater and vacuum gas
oil hydrotreater
Off-gas from the catalytic reform-
ing unit
Off-gas from the FCC unit
Off-gas from the hydrocracking
unit
Off-gas from the delayed coker
unit
Aromatics complex
Naphtha cracker complex.
Typical off-gas yields from vari-
ous refnery units, the aromatics
complex and the naphtha cracker
complex are shown in Figure 3.
Total fuel gas generation from the
refnery accounts for about 8-10
wt% of crude throughput, whereas
on integration with a naphtha
cracker and aromatics complex it
can be as high as 15 wt% of crude
throughput.
Table 1 shows the valuable
components present in off-gases
from various refnery process units,
an aromatics complex and a steam
cracker complex.
A refnery that is processing
crudes with light ends typically has
a saturated gas unit to recover LPG.
Figure 3 Units producing refnery off-gases
CDU
NHT
CRU
Cracker
Aromatics
HCU
FCCU
KHT
DHT
VDU
DCU
VGO
HDT
C ru d e
o il
0 -2
Yie ld ,
wt% o f fe e d 0 . 5 1 2 3 4 -5 1 0 -1 2 2 -3 3 -4 1 6 -1 8 5
Fuel gas pool
technip.indd 3 2/6/12 17:31:34
sation of the C
5
naphtha stream.
However, if we use the C
5
stream
to produce valuable products (such
as ethylene and propylene) in a
steam cracker, an alkylation unit
can be considered for octane boost-
ing. Isobutane reacts with olefns
such as propylene and iso-butylene
to produce alkylates in the presence
of solid or liquid catalyst in an
alkylation unit. Generally, FCC C
4
cut is a good feedstock to produce
alkylates with a RON of 92 and
above.
A signifcant quantity of ethylene
and propylene can be recovered
from FCC and coker off-gases. In
addition, ethane and propane
recovered from saturated gases
from the crude distillation unit and
from FCC and coker off-gases can
be utilised to produce ethylene and
propylene by processing in a steam
cracker. Hence, the steam cracker
can be designed as a dual feed
cracker (both liquid and gas) to
take advantage of off-gases and
any surplus naphtha, leading to
more fexibility of operation. A
Technip-designed steam cracker is
capable of taking any feed, from
ethane to gas oil, providing a great
deal of fexibility. Spyro from
Technip is frst principle-based
software capable of predicting
yield and run length accurately for
any feed. It is used by ethylene
producers worldwide to monitor
and control cracking furnace
performance.
A great deal of synergy exists
between the refnery, aromatics
complex and steam cracker
complex. Off-gases from the FCC
www.eptq.com PTQ Q3 2012 43
However, saturated off-gas from
this unit, primarily consisting of
methane and ethane, still contains
some propane. Ethane and propane
from saturated gas unit off-gas can
be recovered in a cryogenic separa-
tion unit after suitable purifcation
and can be fed to the steam cracker
for the production of ethylene and
propylene.
Hydrogen recovery from refnery
off-gases is an important factor in
reducing the size of an on-purpose
hydrogen generation unit. This can
be achieved by developing a hydro-
gen balance model across the
refnery, identifying the constraints/
fexibility of hydrogen usage, and
hydrogen pinch analysis for possi-
ble alternatives of hydrogen reuse
from off-gases. It should be noted
that a careful techno-economic
evaluation is required before imple-
menting any project for hydrogen
recovery from off-gases. The reason
behind is that, on the one hand, it
reduces the size of the hydrogen
generation unit and thus CO
2
emis-
sions, while, on the other hand, it
degrades the quality of off-gases in
terms of calorifc value and reduces
the opportunity to burn hydrogen
to reduce CO
2
emissions. However,
for a larger hydrogen contributor, a
dedicated recovery system is justi-
fed. A catalytic reformer is one
such source for hydrogen recovery.
Technip has developed a dedicated
tool called HyN.DT for hydrogen
management to help refners opti-
mise hydrogen recovery and the
size of on-purpose hydrogen gener-
ation units.
Off-gas from the FCC unit and
delayed coking units contains a
good quantity of ethane, ethylene,
propylene and some propane.
Separate recovery of ethylene and
propylene through cryogenic sepa-
ration after suitable treatment may
be economical if the quantity of gas
is signifcant. Otherwise, a
combined recovery section with a
cracker complex may be considered.
Ethane and propane separated from
off-gases are sent to the cracker for
further production of ethylene and
propylene.
Recovery of valuable components
such as hydrogen, ethylene and
ethane from off-gases signifcantly
reduces the available fuel gas in the
refnery, leading to a requirement
for an external fuel such as natural
gas. In other words, the use of
natural gas as fuel for the refnery
will help to recover valuable
components from off-gases, leading
to enhanced refnery proftability. A
changeover from fuel gas to natural
gas needs careful evaluation of
existing hardware, especially fred
heaters, with respect to thermal,
mechanical and hydraulic
adequacy.
Synergies between refning and
petrochemicals production
Use of natural gas as refnery fuel
unleashes a host of opportunities in
terms of synergies between a refn-
ery and petrochemicals complex.
The availability of full-range naph-
tha (C
5
-165C cut) as a result of
utilising natural gas for steam
reforming and gas turbines can be
fruitfully used as feedstock for a
petrochemicals complex. From this
full-range naphtha, a portion of
naphtha (light naphtha, mainly C
5
)
can be utilised in a steam cracker
for the production of ethylene and
propylene, while C
7
-C
9
cut naphtha
can be utilised for the production of
aromatics such as benzene, toluene
and paraxylene. The middle cut can
be blended in the gasoline pool.
Recent specifcations of gasoline
limit the aromatics content in gaso-
line, thus restricting the blending of
reformate in the gasoline pool and
leading to the use of alternate
octane boosters such as isomerate
and alkylate. Octane booster
isomerate is produced by isomeri-
Source Yield, wt% of feed
CDU 0-2 Depending on presence of light ends in crude, source
for ethane
CRU 10-12 Source for hydrogen
FCCU 3-4 Source for ethane and ethylene
DCU 4-5 Source for ethane and ethylene
HCU 2-3 Used as fuel gas primarily
NHT 0.5 Used as fuel gas primarily
KHT 1 Used as fuel gas primarily
DHDT 2 Used as fuel gas primarily
VGO HDT 3 Used as fuel gas primarily
Aromatics complex
(excluding catalytic reforming) 5 Used as fuel gas primarily
Steam cracker complex 16-18 Source for hydrogen
Refnery off-gases with valuable components
Table 1
technip.indd 4 2/6/12 17:31:48
roMax process slmulauon soware by 8ryan 8esearch & Lnglneerlng, lnc.
oqloeetloq 5olouoos fot tbe Oll, Cos, kefoloq & cbemlcol loJosttles.
sales[bre.com www.bre.com 979 776-3220 uS 800 776-3220
Process
Optimizing CO
2
Capture,
Dehydration and
Compression Facilities
Insight:
The removal of CO
2
by liquid absorbents is widely implemented in the
le|d ol gas process|rg, crer|ca| producl|or, ard coa| gas|lcal|or. Vary poWer p|arls
are |oo||rg al posl-corousl|or C0
2
recovery lo reel erv|rorrerla| regu|al|ors ard
lo produce C0
2
lor errarced o|| recovery app||cal|ors. Tre lgure oe|oW |||uslrales
aclua| dala ol lue| corsurpl|or |r 2005 ard ar esl|rale ol erergy derard lor
var|ous lue|s lror 2010 lo 2030. Tre Wor|d erergy derard W||| |||e|y |rcrease
al rales ol 10-15 every 10 years. Tr|s |rcrease cou|d ra|se lre C0
2
emissions
oy aooul 50 oy 2030 as corpared W|lr lre currerl |eve| ol C0
2
er|ss|ors. Tre
|rduslr|a| courlr|es (Norlr Arer|ca, weslerr Europe ard 0EC0 Pac|lc) corlr|oule
lo lr|s jurp |r er|ss|ors oy Z0 corpared lo lre resl ol lre Wor|d, ard rore lrar
0 ol lrese er|ss|ors W||| core lror poWer gereral|or ard |rduslr|a| seclors.
0esp|le lre slrorg recorrerdal|ors lror cerla|r goverrrerls, lrere
are very leW aclua| |rveslrerls |r C0
2
caplure lac|||l|es geared loWard reduc|rg
greerrouse gas er|ss|ors ra|r|y oecause ol lre r|gr cosl ol C0
2
recovery lror
lue gas. C0
2
caplure cosls car oe r|r|r|zed, roWever, oy des|gr|rg ar erergy
ellc|erl gas aosorpl|or process. 8ased or lre lrd|rgs ol recerl corceplua|
erg|reer|rg slud|es, lTC Purerergy esl|raled lre producl|or cosl lo oe u3S 19/lor
CO
2
(u3S 51/ lorre C0
2
) lor 90 C0
2
recovery ol 1 ro|e C0
2
corlerl |r lre lue
gas ol N0CC poWer p|arls. A separale sludy sroWed lre cosl lor 90 C0
2
recovery
ol 12 ro|e C0
2
lror a coa| lred poWer p|arl lo oe u3S 30/lor C0
2
(u3S 33/lorre
CO
2
). Tre cosl ol C0
2
recovery lror coa| poWer p|arl lue gas |s suoslarl|a||y |ess
lrar lral ol N0CC poWer p|arl lue gas due lo lre r|grer C0
2
corlerl |r lre leed.
Tre erergy ellc|ercy ol a C0
2
caplure p|arl deperds pr|rar||y or
lre perlorrarce ol lre so|verl ard opl|r|zal|or ol lre p|arl. lr lrad|l|ora| lue
gas p|arl des|grs, VEA Was lre pr|rary so|verl ard Was ||r|led lo 20 Wl lo
r|r|r|ze equ|prerl corros|or. Recerl deve|oprerls |r corlro|||rg corros|or ard
degradal|or ras a||oWed ar |rcrease |r lre so|verl corcerlral|or lo aooul 30 Wl
lrus decreas|rg lre requ|red c|rcu|al|or ard suosequerl slear derard. A recerl
00E sludy sroWs lre slear corsurpl|or lor ar ex|sl|rg C0
2
p|arl us|rg 18 Wl
VEA (Kerr Vc0ee Process) |s 3.15 |o ol slear per |o ol C0
2
lor ar|re regereral|or.
A roderr process lral uses 30 Wl VEA |s expecled lo use 1.Z |o ol slear per |o
of CO
2
lor ar|re regereral|or. Tre lTC lorru|aled so|verl |s a propr|elary o|erd
ol ar|res ard ras a |oWer slear usage lrar lre corverl|ora| VEA so|verl. 8ased
or lre raler|a| ard erergy oa|arces lor lre p|arl des|gred |r lre recerl sludy, lre
reoo||er slear corsurpl|or |s esl|raled al aooul 1.1Z |o slear/|o C0
2
us|rg lre
proposed lorru|aled so|verl W|lroul |rp|ererl|rg ary sp||l loW corlgural|ors. Tr|s
|s rucr |ess lrar lre reporled slear usage lor lre VEA so|verl.
Tre des|gr ol a lac|||ly lo caplure 90 ol lre C0
2
lror lre lue gas ol
a coa| lred poWer p|arl |s oased or lre spec|led lue gas cord|l|ors, C0
2
producl
spec|lcal|ors, ard corslra|rls. us|rg lre ProVax process s|ru|al|or sollWare lror
8ryar Researcr & Erg|reer|rg, C0
2
caplure ur|ls car oe des|gred ard opl|r|zed
for the required CO
2
recovery us|rg a var|ely ol ar|re so|verls. Tre lo||oW|rg lgure
represerls a s|rp||led process loW d|agrar lor lre proposed C0
2
Caplure P|arl.
Tre lao|e oe|oW preserls lre ra|r lrd|rgs lor C0
2
caplure lror lre
coa| lred poWer p|arl ard lre N0CC poWer p|arl, eacr des|gred lo produce aooul
330Z lor per day (3,000 TP0 relr|c). To produce lre sare capac|ly ol C0
2
, or|y
ore lra|r W|lr sra||er co|urr d|arelers |s requ|red |r lre case ol lre coa| poWer
p|arl ard lWo lra|rs W|lr |arger co|urr d|arelers are requ|red |r lre N0CC PoWer
P|arl case. Tr|s |s ra|r|y due lo process|rg a |arger lue gas W|lr |oWer C0
2
corlerl
|r lre N0CC poWer p|arl. Corsequerl|y, a suoslarl|a| reducl|or |r lre cap|la| ard
producl|or cosl Was reporled lor lre coa| lred poWer p|arl C0
2
recovery lac|||ly.
For rore |rlorral|or aooul lr|s sludy, see lre lu|| arl|c|e al
www.bre.com/support/technical-articles/gas-treating.aspx.
bre.indd 1 1/6/12 11:59:52
unit and coker containing ethylene
and propylene can be integrated
with the cold section of the steam
cracker. On the other hand, pyroly-
sis gasoline produced from the
steam cracker contains a good
quantity of xylenes and can be inte-
grated with the aromatics complex.
Propylene produced from the steam
cracker complex and benzene
produced from the aromatics
complex are feedstocks for the
production of cumene and phenol
for producing bis-phenol and poly-
carbonates. Figures 4 and 5 show
enhanced integration between a
refnery and a petrochemicals
complex when natural gas is used
as fuel.
Reducing carbon footprint: a bonus
In addition to achieving good
synergy between a refnery and a
petrochemicals complex, the use of
natural gas as refnery fuel helps in
reducing the carbon footprint of the
refnery, especially when fuel oil is
replaced by natural gas. Typically,
the replacement of fuel oil with
natural gas gives about a 30%
reduction in CO
2
emissions and *
the replacement of fuel gas with
natural gas gives about a 5-10%
reduction in CO
2
emissions from
fred heaters. This is in addition to
a reduction of 25% in CO
2
emis-
sions from the hydrogen generation
unit and 25-30% from gas turbines,
which can be achieved by replacing
naphtha with natural gas.
Case study
This study concerns a base case of a
refnery complex of 15 million t/y
capacity with a steam cracker and
aromatics complex. The refnery
consists of a CDU/VDU primary
unit, a catalytic reforming unit and
alkylation for gasoline production,
an FCC unit and once-through
hydrocracker unit as secondary
units, and a delayed coker is
considered for bottom-of-the-barrel
processing. Hydrotreating of all
products such as kerosene, diesel,
naphtha and VGO is considered to
meet the product specifcations
required for downstream units and
to meet environmental regulations.
Since light naphtha (mainly C
5
cut),
which is fed into the naphtha
cracker, is not available for isomeri-
sation for boosting the octane
number of gasoline, an alkylation
unit is considered for the purpose.
C
4
cut from the FCC unit is the feed
to the alkylation unit. Light naph-
tha (C
5
cut) from a naphtha
hydrotreater and hydrocracker,
along with hydrocracker bottoms,
is the main feed to the naphtha
cracker. Pyrolysis gasoline gener-
ated from the naphtha cracker goes
through an aromatics separation
unit, the aromatics are fed into a
paraxylene complex and raffnate is
recycled back to the naphtha
cracker. A butadiene extraction unit
is considered within the naphtha
cracker complex. Hydrogen is
recovered from catalytic reformer
and naphtha cracker off-gases
through pressure swing adsorption.
The sulphur block includes an
amine treating unit, sour water
stripper, amine regenerator unit
and sulphur recovery unit. A block
fow diagram for the base case
refnery confguration is shown in
Figure 6. A linear programming
model was developed based on this
confguration, with maximisation of
GRM as the objective on the follow-
ing basis:
Capacity: 15 million t/y (300 000
b/d)
Crude: 50% Arab Heavy and 50%
Arab Light
Desired products: ethylene,
propylene, LPG, butadiene, gaso-
line, aviation turbine fuel, diesel,
benzene and paraxylene
A base case (without supplemen-
tary fuel such as natural gas)
material balance is performed using
this model and product yields are
shown in Table 2 under base case.
With the same confguration, the
model was rerun with natural gas
as fuel, replacing off-gases and
naphtha as feed and fuel for hydro-
gen generation and gas turbines.
Integration between a refnery
and a petrochemicals complex is
maximised by optimising the
www.eptq.com PTQ Q3 2012 45
Sat gas released
from fuel gas pool
FCC and coker off
gases released from
fuel gas pool
M o re e th yle n e
p ro d u c tio n
M o re p ro p yle n e
p ro d u c tio n
Cracker
E th a n e
E th yle n e
a n d
p ro p yle n e
E th yle n e a n d p ro p yle n e
E th a n e
E n h a n c e d e th yle n e
p ro d u c tio n
E n h a n c e d p ro p yle n e
p ro d u c tio n
E n h a n c e d p ro p yle n e
p ro d u c tio n
Light naphtha to
steam cracking
M o re P X p ro d u c tio n
M o re b e n ze n e
p ro d u c tio n
6. Can a process
engineering model be used?
D yn a m ic ; ste a d y sta te ; m a y b e E x c e l b a se d .
S te a d y sta te c a n p ro vid e g a in s a n d p ro c e ss
e n g in e e rin g in sig h t.
7. Combination of
approaches.
P rim a ry o b je c tive : p ro te c t a g a in st c o n stra in ts.
Ta rg e t o b je c tive : m e e t fin a l d e p lo ym e n t
re q u ire m e n ts.
Figure 1 Seven steps to fnding a seed model
honeywell.indd 4 1/6/12 14:28:12
Were Not Exaggerating. Our Boilers
are something to brag about.
We custom design and custom build boilers to perform efciently, safely and cleanly.
Your RENTECH boiler will lower operating costs, reduce emissions, and provide faster start-up
and cool-down. You ll nd satised customers on six continents with specialty boilers, HRSGs,
wasteheat boilers and red packaged watertube boilers from RENTECH. We ve been designing
and building boilers for people who know and care since 1996.
WWW.RENTECHBOILERS.COM
rentech.indd 1 1/6/12 13:22:29
Seizing the opportunities
The objective dened earlier is to
identify a seed model that is at least
sufcient for constraint control
during closed loop control model
identication for a control project.
Figure 1 shows six separate potential
strategies for achieving this goal. A
nal practical strategy combines
these six strategies. Knowledge
management is deployed within
steps 3 and 5, while process models
are deployed within step 6.
But actually the practitioner is
especially interested in a seed model
that is sufcient for nal deploy-
ment, rather than just for constraint
control during closed-loop control
model identication. This is where
process models offer further
potential. And it is also worth noting
that process models are not limited
to process simulators. The following
example describes the use of a proc-
ess model developed within a
spreadsheet.
The actual application is simpli-
ed for this discussion and is shown
in Figure 2. It basically consists of a
surge drum with three ows into
and one ow from a drum. The
control application has two MVs,
two CVs and two DVs. The ow out
of the drum is MV1. One of the
ows into the drum is MV2. The
two other ows into the drum are
DV1 and DV2. The drum level is
CV1 and the ratio of DV1/(DV1
+MV2+DV2) is CV2.
Vessel dimensions and level tap
information from the unit process
and instrumentation diagrams
(P&IDs) enable the process gains
between CV1 and each of the MVs
and DVs to be calculated by spread-
sheet formula. Spreadsheet formula
can also be used to calculate the
process gains between ratio CV2 and
DV1, MV2 and DV2. Here, the gains
depend on operating conditions, but
it is relatively trivial to calculate the
variability of the gains across the
operating region planned for the
controller and to then select reason-
able gains. (Alternately, the
controller design could be revisited
by looking to replace or transform
CV2 or by deciding to dynamically
update controller gains for CV2
online; ie, while the control applica-
tion is in service.) The control
models identied from this spread-
sheet analysis were found to be
consistent with control models
obtained by conventional identica-
tion that used a few days of data
mined from the DCS historian as
input data. Based on this validation,
the control models identied from
spreadsheet analysis were used for
commissioning of the multivariable
controller without step testing. Here,
the process model (spreadsheet
formulae in this case) provided
insight into gain non-linearity across
the process operating conditions that
is not typically available from
conventional identication.
More signicant examples have
also been discussed in the literature.
One such example involved the
design, test and installation of multi-
variable controllers during the
engineering and construction phase
of a 1300 mmscfd gas plant shown
in Figure 3.
1
Multivariable controllers
were applied to the units for (a) feed
gas separation and condensate stabi-
lisation; (b) dehydration and feed
liquid separation; and (c) NGL recov-
ery. Dynamic process models
developed during engineering design
were enhanced for the multivariable
control application development. In
particular, multivariable process
controllers were incorporated
directly into the process models as
unit operations. This has the advan-
tage that the controller performs
consistent with design intent at high
model real-time factors.
54 PTQ Q3 2012 www.eptq.com
F C
R e c yc le
M V2
F C
P rim a ry
fe e d
D V1
C V1
F C
S e c o n d a ry
fe e d
D V2
L I
F C
M V1
Feed
drum
C V2 =
D V1
D V1 +M V2 +D V2
C V2 =
D V1
D V1 +M V2 +D V2
Figure 2 Simplied surge drum controller application
Feed gas
separation and
condensate
stabilisation
Gas treating
NGL recovery
Gas rejection
or sale
Dehydration and
feed liquid
separation
C o n d e n sa te
p ro d u c t
C o n d e n sa te o r
N G L p ro d u c t
N G L
p ro d u c t
Figure 3 Gas plant facility
honeywell.indd 5 2/6/12 17:38:01
In the NGL unit, one enhancement
arising from the evaluation of regu-
latory control loop interactions
within the process model was the
addition of ratio controllers that
were also used as MVs for the multi-
variable controller. The NGL unit
process model also demonstrated
that deployment of the multivariable
controller application increased
ethane recovery by 1.37% in ethane
recovery mode, which has the poten-
tial benet of $ millions per annum.
The controller commissioned on the
virtual plant was designed consist-
ent with the KISS (Keep It Simple,
Sir) principle. However, the NGL
unit process model could also be
used to demonstrate additional
potential benets through expand-
ing the controller scope (MVs and
CVs).
In this example, the applicability
of the control models identied
from the process engineering model
to the real plant was judged in part
by comparing with control models
identied by a more traditional
approach for a different application
of the same gas plant process
technology.
Conclusion
As has been discussed, the maturing
of closed-loop step testing and iden-
tication technology for advanced
control reduces the effort required
for testing and identication for an
advanced control project. However,
it requires a seed model and, as
such, the interim milestone of
providing this seed model will
receive more focus. And, naturally,
there will also be the desire for the
seed model to be more than just a
seed model it should basically be
suitable for control deployment
without step testing. This will lead
to the adaption of control project
engineering work processes, on an
opportunity basis, to move towards
meeting these desires. As the future
evolves, work processes are likely to
more widely incorporate the use of:
Latest features of data-centric
modelling and efciency tools
Steady-state process engineering
model analysis
Dynamic process models
Organisationally supported knowl-
edge management deployment
Virtual platforms standardised for
the organisation.
Of course, tools with proven
historic value, such as process model
engineering toolkits for control, will
continue to be deployed where
appropriate.
Reference
1 Sakizlis V, Coward A, Vakamudi K,
Mermans I, Advanced process control in the
plant engineering and construction phase,
Hydrocarbon Processing, Oct 2010.
Ken Allsford is a Simulation Discipline Lead
based in Houston, Texas, with the Advanced
Solutions group of Honeywell International. He
holds a PhD in chemical engineering from the
University of Birmingham, UK.
Email: Ken.Allsford@Honeywell.com
Bhaskar Iyer is a Control Discipline Lead based
in Houston, Texas, with the Advanced Solutions
group of Honeywell International. He holds a
BTech in chemical technology from Nagpur
University, India.
Email: Bhaskar.Iyer@Honeywell.com
Aric Tomlins is a Control Discipline Lead based
in Houston, Texas, with the Advanced Solutions
group of Honeywell International. He holds a
BSc in chemical engineering from Rensselaer
Polytechnic Institute, USA.
Email: Aric.Tomlins@Honeywell.com
A e r z e n - o n e s t e p a h e a d
Oi l -f ree gas c ompressi on!
Chemical and petro-chemical processes handle a wide variety
of gases. Dry compression is preferable in the case of con-
taminated and aggressive gas applications for which Aerzen
offers a complete spectrum of solutions involving positive dis-
placement blowers, boosters, and oil-free screw compressors.
Decades of experience in the f eld of custom engineered gas
compression equipment packages ensure maximum up-time
and minimal life cycle cost.
Challenge us and draw upon our know-how.
Please pick up our leaf ets A1-004, G1-151 and V1-067 for fur-
ther information or visit us on Internet at www.aerzen.com
Aerzener Maschinenfabrik GmbH
Reherweg 28
.
31855 Aerzen /Germany
.
Phone: +49 51 54 /8 10
Fax: +49 51 54 /81 91 91
.
info@ aerzener.de
.
www.aerzen.com
B l o we r s . . . . C o mp r e s s o r s . . . . G a s me t e r s B l o we r s . . . . C o mp r e s s o r s . . . . G a s me t e r s
Hall 8.0
.
Stand D 38
120 x 190_PTQ.indd 2 22.05.2012 19:52:38 Uhr
www.eptq.com PTQ Q3 2012 55
honeywell.indd 6 4/6/12 15:19:30
High pressure. Extreme temperatures. volatile products. lt's all part of the job in
hydrocarbon processing. But so is the goal of maximizing safety integrity. We make
the process more secure with our innovative valves and controls, which is why the
industry relies on us to keep their workers safe and their plants running smoothly.
/ea|n mo|e aoo0t o0| o|ant oe|fo|mance so|0t|ons at CWFC.com
Eng|nee||ng t|ansfo|mat|on.
R|sk has
a|ways been
part of
th|s job.
A part we can do without.
c wright.indd 1 1/6/12 21:16:30
APC2: aligning people with control
A
dvanced process control
(APC) can take on many
avours and levels of sophis-
tication. With regard to digital
control systems (DCS), advanced
regulatory controls can create value
using property predictions cascaded
to DCS controllers, or feed forward
or decoupling signals can be added
to improve stability and robustness
of controls. In order to take on
entire units of control, medium to
large multivariable controllers have
been developed to handle process
interactions and to drive the unit to
the most economical combination
of constraints. Multi-unit control
and optimisation in the form of a
larger linear program provides a
A lead practitioner explains how renery-wide involvement of people underpins a
major advanced process control programme
RAYMOND COKER
BP Texas City renery
tool to coordinate ows and opti-
mal targets across the renery.
More detailed effects can be
modelled and included in the linear
program solution as new knowl-
edge is incorporated into the
solution. Fuel gas, steam, hydrogen,
amine, cooling water, tanks, ship-
ments, electricity and process
line-ups create opportunities to
synergise across multiple units.
Aligning people with control
(APC2) provides the mechanism to
design controllers, commission
controllers and sustain value long
term. Critical resources include
advanced control engineers, unit
control engineers, process engi-
neers, operations personnel, and
economics and planning personnel.
Economics and planning provide
the big picture view of the renery
and help identify the gold nuggets
for control personnel. Advanced
control personnel help planning by
adding greater delity to the
models and trade-offs between
quality and production, as well as
by commissioning model-based
controllers to coordinate moves
across each unit and to reach the
targets set by planning. Unit control
personnel help with control system
congurations, regulatory controls
and advanced controls. Process and
operations provide critical process
and constraint information.
The extended team includes
www.eptq.com PTQ Q3 2012 57
P ip e still F e e d 4 3 2 4 % 4 9 0 %
Rate
MBPD
Margin
Profit/B
%
Improvement
Stream Unit APC annual
benefits %
profit/year
1 6
APC project %
costs
1 . 4 2
C a t c ra c k e r F e e d 8 6 4 % 1 6 9 0 % 1 6 1 . 1 4
Benefit/cost % on APC
D ie se l h yd ro tre a te r D ie se l 8 6 4 % 1 6 9 0 % 8 2 . 2 7
A ro m a tic s F e e d 4 3 4 % 3 2 9 0 % 2 0 0 . 9 1
C o k e r F e e d 8 6 4 % 8 9 0 % 1 2 0 . 7 6
R e fo rm e r G a so lin e 8 6 4 % 4 9 0 % 1 2 0 . 3 8
H yd ro c ra c k e r F e e d 4 3 4 % 1 6 9 0 % 1 6 0 . 5 7
To ta ls 1 0 0
2 3
1 8
1 8
1 8
9
5
9
1 0 0
R e fo rm e r
H yd ro c ra c k e r
D ie se l h yd ro tre a te r
C o k e r
A ro m a tic s
C a t c ra c k e r
P ip e still
APC project % costs
R e fo rm e r
H yd ro c ra c k e r
D ie se l h yd ro tre a te r
C o k e r
A ro m a tic s
C a t c ra c k e r
P ip e still
APC annual benefits % profit/year
Figure 1 Estimated benets of an APC programme
bp.indd 1 1/6/12 14:31:53
58 PTQ Q3 2012 www.eptq.com
and stakeholders required to dene
scope, schedule, cost, benets and
infrastructure
APC pretest report Control, proc-
ess, operations and maintenance
resources required to update
design, transform, calculate, repair
instruments, modify regulatory
controls and prepare for test
Inferential calculations Control,
process and analyser maintenance
resources to develop and imple-
ment inferential calculations with
updates from lab, analyser or rigor-
ous calculations
Dynamic models Control, process
and operations resources to test,
develop and verify dynamics and
steady-state gains
Controller performance Control,
process, planning and operations
resources to commission controller
economics, speed and priorities
As-built documentation Control,
process, operations and training to
document nal solution in sufcient
detail to train operators and support
applications.
Benets drive APC
Once the APC projects are ordered
by year, the estimates can be further
rened to improve the scope, costs,
schedule and benets (see Figure 2).
These costs reect only the project
costs. The maintenance costs for
APC range from 15-20% of the orig-
inal project effort per year. The
largest factor in the maintenance
costs is how often and how much
the unit changes over time.
Start with the end in mind: the
benet mechanisms drive the APC
solutions. APC studies are an excel-
lent way to leverage the knowledge
of operations, process engineers,
process consultants and modellers,
control engineers, instrument and
analyser maintenance, environmen-
tal engineers and safety personnel.
There are many gold nuggets
(benet opportunities) in the minds
of these people working on the
units or supporting the units. By
asking leading questions and
understanding the process and
constraints, the APC leader can
discern the most important benet
mechanisms to go after and develop
the control objectives.
The APC design will grow as new
management sponsors, instrument
and analyser personnel, environ-
mental personnel, laboratory
personnel, corporate technical lead-
ers and sponsors, commercial
managers, upstream suppliers and
downstream customers.
Create the vision
In order to get an APC programme
off the ground, there must be a
credible story to initiate interest and
support from management at multi-
ple layers. Using rules of thumb
(3-5% improvement, 90% utilisation,
average stream margin and average
stream ow rate) for APC benets
for each unit, a table of estimated
benets can be calculated (see
Figure 1). The priority or order of
execution of the projects depends
on the benet-to-cost ratio (plan-
ning and economics and project
management), condition of unit,
condition of instruments, condition
of systems, TAR schedule, other
project schedules and availability of
key resources (operations, process
engineering, control engineering,
instrument and analyser mainte-
nance, and system support).
It is very important to build good
alignment with your management
team early in the APC programme.
Without their initial support, it will
be difcult to drive through the
obstacles ahead. The following
people are critical to the success of
the programme:
Management Supports resources,
projects and funds
APC engineers Lead APC studies
and projects
Unit control engineers and digital
control personnel APC design, regu-
latory controls, database points,
displays
Planning and economics Stream
values and utility costs, quality and
production targets
Process engineers Equipment and
process limits, process models
Instrument and analyser staff
Support valve, instrument and
analyser repairs
Operations staff APC design,
operating objectives, dynamic and
steady-state concerns
Environmental engineers Environ-
mental limits and permits,
compliance requirements
Safety personnel Ensure manage-
ment of change provides proper
communication and approvals,
compliance
Information and network technol-
ogy personnel Develop and maintain
system and network architecture.
The following are important for
the proper execution of the APC
studies and projects:
APC study report All disciplines
P ip e still F e e d 2 0 1 1
Stream Unit APC annual
benefits %
profit/year
1 6
APC project %
costs
1 . 4 2
C a t c ra c k e r F e e d 2 0 1 2 1 6 1 . 1 4
Benefit/cost Year
D ie se l h yd ro tre a te r D ie se l 2 0 1 1 8 2 . 2 7
A ro m a tic s F e e d 2 0 1 2 2 0 0 . 9 1
C o k e r F e e d 2 0 1 3 1 2 0 . 7 6
R e fo rm e r G a so lin e 2 0 1 4 1 2 0 . 3 8
H yd ro c ra c k e r F e e d 2 0 1 3 1 6 0 . 5 7
To ta ls 1 0 0
2 3
1 8
1 8
1 8
9
5
9
1 0 0
1 2 0
1 0 0
8 0
6 0
4 0
2 0
2 0 1 0 2 0 1 1 2 0 1 2 2 0 1 3 2 0 1 4 2 0 1 5 2 0 1 6 2 0 1 7
A
c
c
u
m
u
l
a
t
e
d
c
o
s
t
s
,
%
Year
0
3 0 0
2 5 0
2 0 0
4 5 0
4 0 0
3 5 0
1 5 0
1 0 0
5 0
2 0 1 0 2 0 1 1 2 0 1 2 2 0 1 3 2 0 1 4 2 0 1 5 2 0 1 6 2 0 1 7
A
n
n
u
a
l
b
e
n
e
f
i
t
s
,
%
Year
0
Figure 2 Rened estimates improve the scope, costs, schedule and benets of an APC
programme
bp.indd 2 1/6/12 14:32:05
www.eptq.com PTQ Q3 2012 59
mechanisms are identied. The
product of the study is an APC
design that includes the manipu-
lated, disturbance (or feed forward)
and controlled variables.
Build relationships
Seek out the right people to help
grow and support the APC
programme. It is important to focus
on the relationships in the organisa-
tion that will gain you a broader
understanding of the site economics
while the details of each project are
being developed. Good resources
are planning and economics, senior
process engineers, commercial
managers and business leaders.
These meetings can be spread out
from weekly to quarterly for short
periods of time such as 30 minutes
to an hour. Select topics that will
enhance your current projects or
ones in the next year.
Sometimes gold nuggets (value
opportunities) are identied
through these discussions as the big
picture person understands more of
your details and as the detailed
person understands the big picture
of how the various units or streams
work together.
Furthermore, the organisation of
DCS, consoles and networks can be
further improved by looking at how
the various process units relate to
each other through streams
and energy connections. This
opportunity engages information
technology, systems personnel and
DCS administrators.
Control and optimisation technol-
ogy is available to complete large
unit or multi-unit control and opti-
misation systems. The right DCS
and system architecture can acceler-
ate this development. Too many
breaks in the network or too many
DCS will make it more difcult and
more costly to implement control
and optimisation strategies across
the site. Examples of gold nuggets
are as follows:
Maximise gasoline on the reactor
this does not necessarily equate
to maximising gasoline overall
Utilise APC gains to understand
the cost of quality shifts for
commercial decisions
Utilise plant linear program
economic information, needed for
APC benets, for studies and
post-audits
Set quality targets close to the
limit, reducing giveaway, and align
APC targets with planning targets
Use third-party resources to expe-
dite benets
Use corporate and other site
resources to expedite benets, build
win-win relationships and leverage
lessons learned
Develop calculations or inferen-
tials that connect downstream
constraints to upstream controllers
(open loop or closed loop).
Kick-off and pretest
The purpose of the APC project
kick-off is to establish roles and
responsibilities. In addition, it is
another great opportunity to build
support for the preliminary testing
and instrument review (pretest).
During the pretest, the team
reviews or changes instrument
measurements, valves, tuning,
lters, regulatory structure, identi-
es move sizes and time to steady
state for independent variables
(manipulated or disturbance), iden-
ties and installs calculations and
inferential calculations, installs
computer hardware and software,
starts data collection, and updates
the control design and objectives.
The regulatory controls and meas-
urements are the foundations of
APC. By reviewing the current and
historical data with the unit control
engineers and the process engi-
neers, the best regulatory control
structure can be assessed and
improved. The analyser technicians
and engineers can provide insight
into the reliability and accuracy of
the analyser systems and measure-
ments. Frequently, these analyser
systems limit the reliability of APC.
The issues can be identied in the
sample or analyser systems. It is
important to identify all of the proc-
ess, control, instrument and
analyser shortcomings as early as
possible and to then put together a
plan to push through these
obstacles.
In order to reduce the time to
steady state for a controlled varia-
ble based on an analyser, an
inferential calculation is used to
reduce the dead time and lag in the
analyser measurement. The inferen-
tial shown in Figure 3 reduces the
dead time by 45 minutes and lag
time by 30 minutes.
Inferential calculations are also
useful for predicting quality
between analyser updates. Figure 4
0 . 6
1 . 0
0 . 9
0 . 8
0 . 7
0 . 5
0 . 4
0 . 3
0 . 2
0 . 1
0 2 0 4 0 6 0 8 0 1 0 0 1 2 0 1 4 0 1 6 0 1 8 0 2 0 0 2 2 0 2 4 0
0 . 0
Figure 3 Inferential calculation reduces the time to steady state for a controlled variable
based on an analyser
It is important
to identify all
of the process,
control, instrument
and analyser
shortcomings as
early as possible
bp.indd 3 1/6/12 14:32:14
Test and model
The purpose of the APC project test
is to identify dynamic and steady-
state models for the process. Plant
is tested to identify dynamic rela-
tionships between independent and
dependent variables (controlled).
Typically, the test time is 10 times
the number of independent test
variables times the average time to
steady state. This time can be short-
ened by parallel testing or by
utilising automated testing soft-
ware. Data collection must be
uncompressed, reliable and contain
a list of instruments and calcula-
tions necessary for present and
future APC needs. Modelling
includes transforming variables,
calculating variables, identifying
dynamic models, building a model
for the multivariable controller and
correcting conditioning problems
with steady-state gains. Simulating
includes determining costs for each
manipulated variable, tuning inde-
pendent and dependent variables,
applying transforms, establishing
limits for variables and simulating
the controller using different oper-
ating scenarios to observe controller
behaviour.
Most process units have operators
that have been on the unit for many
years. Sometimes these seasoned
veterans have moved into other
positions in the organisation. It is
worthwhile fnding out who they
are and building a relationship with
these key individuals. Their experi-
ence goes well beyond anything
that will be observed on a single
APC project, no matter how
detailed the lead APC engineer may
be. They will likely know where the
process cliffs or edges are and what
to stay away from. They may or
may not know why the process
behaves the way it does, but their
experience will give insight into
where are the safest and most relia-
ble areas to operate a step test.
Unless you enjoy falling off cliffs,
carefully consider the wisdom of
the operators and experienced proc-
ess engineers.
During the step test, the dynamic
models are continuously improved
with each day of new data. The
models are reviewed with the team
in order to make adjustments to
60 PTQ Q3 2012 www.eptq.com
shows how well the inferential
calculation predicts the analyser
updates. The inferential calculations
are based on process measurements.
The selection of inputs to the infer-
ential calculations can be discerned
by reviewing the data with the unit
control engineer and the process
engineer. The fat lines are the time
between analyser updates.
Use of off-line rigorous process
models assists in defning process
gains, non-linearities, transforms or
inferential calculations. Rigorous
spreadsheet calculations can be
used for pressure-compensated
temperatures, energy balances or
physical properties. Explicit deriva-
tives of calculations may be used to
calculate model gains in the APC,
while custom calculations can be
used to update the model gains or
controller gains every control cycle
based on engineering principles.
In order to create a simpler online
calculation for the reactor section,
the following concepts were used:
Energy of activation is needed to
get the right relationship between
temperature and conversion or
quality
Effect of feed rate or residence
time must be well understood
Reactor pressure and mole frac-
tion gains and exponents are
needed
Effect of poisons on reaction
needs to be understood
A more rigorous model can be
used to create data to make a
simpler model to be used online as
a controlled variable:
Reaction = A * (Exp(-Ea/RT)^B * (F)^C * (P)^D
* (Mi)^Ei * ...
Where A, B, C, D, Ei are coeff-
cients, R is the Ideal Gas Law
constant, T is temperature in abso-
lute scale, F is fow, P is pressure in
absolute scale and Mi is mole frac-
tion or %.
The data needed to create this
relationship can be generated from
rigorous kinetic models developed
by process engineers, or from
simplifed reactor equations devel-
oped by the site linear program
engineer.
All of the methods require infor-
mation from a number of resources
such as process engineers, planning
personnel and the site linear
program developer. It is critical to
the success of the APC project to
identify and leverage the resources
that can help with key calculations
and relationships (frst and second
derivatives over process operation).
Table 5
9 6 0 1 0 8 0 1 2 0 0 1 3 2 0 1 4 4 0 1 5 6 0 1 3 8 0 1 8 0 0 1 9 2 0
0 . 1 5 0 0
0 . 1 5 4 2
0 . 1 5 8 3
0 . 1 6 2 5
0 . 1 6 6 7
0 . 1 7 0 8
0 . 1 7 5 0
0 . 1 7 9 2
0 . 1 8 3 3
0 . 1 8 7 5
0 . 1 9 1 7
0 . 1 9 5 8
0 . 2 0 0 0
Figure 4 Inferential calculation predicts analyser updates
Rigorous spreadsheet
calculations can be
used for pressure-
compensated
temperatures, energy
balances or physical
properties
bp.indd 4 1/6/12 14:32:35
Nalco Downstream Energy Services is the global leader in Rening Process
Treatments, Fuel Additives, Petrochemical Processes and Water Treatments.
For more than 80 years, we have worked to build an unrivaled level of experience and expertise with
over 1,200 employees operating in more than 350 reneries and 400 petrochemical plants across
six continents. Our comprehensive global network of onsite experts, industry technical consultants,
manufacturing plants, supply facilities and research centers enables us to consistently deliver a high
level of value to our local, regional and multinational customers.
Delivering Essential Expertise
2012 NALCO All rights reserved. 05/2012
nalco.indd 1 1/6/12 11:53:45
move sizes and to times between
the moves to improve the models.
After the models are completed by
the APC team, they are reviewed
with operations and process engi-
neers for accuracy and consistency.
Next, the models are adjusted to
improve the conditioning of the
model matrix based on variable
gains that are proportional with
respect to independent variables or
dependent variables, or both. This
step requires a good understanding
of the process. The value of each
manipulated variable can be deter-
mined from information from the
process gains as well as from the
stream values and utility costs
collected from the economics and
planning department. Controlled
variable priorities, control objectives
and operating strategies are deter-
mined from conversations with the
process engineers, unit control engi-
neers, planning personnel and
operations personnel. Finally, the
controller is simulated to ensure
that the priorities, objectives and
strategies are met. At this point, all
of the ideas, lessons and wisdom
from the key stakeholders have
been considered and implemented
into the simulated controller.
Commission and audit
The purpose of project training
and commissioning is to deliver a
successful APC solution with a full
explanation of objectives, design
and use to the operating staff.
Operators need training on the use
of multivariable control, control
design, objectives, dynamic models,
calculations and priorities.
Engineer training is completed on
a mentoring basis for all of the
project steps.
An interface needs to be installed
for the multivariable controller,
manipulated and controlled varia-
bles turned on, the controller tuned
and models adjusted to meet
controller objectives, as well as the
design changed as new constraints
become active or old constraints are
eliminated. As-built documentation
needs to be provided for the multi-
variable controller, including details
necessary to understand what is
needed and why it is there. Finally,
data must be collected and it is
important to ensure all control
objectives have been met, to esti-
mate benefts and to issue a
post-audit report. Figure 5 shows
the growth of benefts in 2012 by
month.
Alternatively, the APCs perfor-
mance can be shown as incremental
benefts each month compared to
its potential performance. The ratio
of actual benefts to potential bene-
fts is an indication of the APCs
effectiveness. It is important to
report to all stakeholders the APCs
performance, success stories and
challenges. If the right people know
what the challenges are for lower
utilisation, they can take appropri-
ate action to solve the problems.
For example, low analyser utilisa-
tion can be resolved by the analyser
group, and tight manipulated vari-
able limits can be adjusted by the
process engineer in conjunction
with the operations management.
As new information is gathered
from studies, projects, meetings and
informal discussions, the APC
programme can be adjusted on a
monthly or quarterly basis.
Conclusion
In order to create and maintain an
APC programme, the following key
steps are critical to success and
necessary to get good organisa-
tional alignment:
Develop an APC plan with suff-
cient detail to provide costs and
benefts by year
Prioritise work based on avail-
ability of DCS, unit and personnel
and cost-to-beneft ratio
Establish a solid front-end load-
ing of projects via studies or by
leveraging existing controllers
Rally the right team and stake-
holders around each APC project
and study
Communicate study reports, proj-
ect progress and APC results to
project stakeholders and the leader-
ship team.
Raymond Coker is Advanced Control Team
Lead with BP Texas City refnery, USA. He has
32 years experience in process and process
control, completed his frst DMC application
in 1985 and his last DMCplus 7.2 application
in 2012, and has led multivariable predictive
control projects on a wide range of refning and
petrochemical units. He holds a BS in chemical
engineering from the University of Texas at
Austin, and is a professional engineer and a
project management professional.
62 PTQ Q3 2012 www.eptq.com
1 2
1 6
1 4
1 0
8
6
4
2
0 1 2 3 4 5
B
e
n
e
f
i
t
s
,
%
o
f
m
a
x
y
e
a
r
Mont hs
0
P o te n tia l
A c tu a l
Figure 5 Growth of benefts by month for an APC project
Communicate study
reports, project
progress and APC
results to project
stakeholders and the
leadership team
bp.indd 5 1/6/12 14:32:48
www.metso.com/oilandgas
Focusing on your safety
We of er peace of mind when it comesto your processsafety and productivity.
Metso isa single source for all your processcontrol needs, from automation systems
to intelligent f ow control solutionsthat are proven in the toughest conditions.
Our 30,000 professionalsbased in over 50 countriesdeliver sustainability and
prof tability to customersworldwide.
metso.indd 1 1/6/12 11:44:48
Grand Ameri ca Hot el
Sal t Lake Ci t y, UT
Oct ober 1-3, 2012
AFPMs Q&A and Technology
Forum is the industrys most
comprehensive meeting on
renery operations and process
technology. This event assembles
representatives from throughout
the industry including reners,
petrochemical producers, catalyst
and chemicals suppliers, plant
automation specialists and
engineering rms and gives
them the opportunity to address
real problems reners face today.
PROVIDING
SOLUTIONS
THE 2012 AFPM (NPRA)
Q&A AND TECHNOLOGY FORUM
Attendees will gain from the
chance to discuss their challenges
and nd solutions from the expert
Q&A panelists and other attendees.
Todays competitive rening
environment requires attention to
plant s afety, superior technology,
innovation and excellence in
operations. Benet from the shared
knowledge of experts throughout
the industry the Q&A and
Technology Forum will keep you
moving in the right direction as you
optimize your plants operation.
Register today at www.afpm.org.
afpm.org
afpm.indd 1 1/6/12 13:20:03
Alarm foods and plant incidents
M
ost of the incident investiga-
tions performed by the US
Chemical Safety Board
(CSB) cite alarm foods as being a
signifcant contributing cause to
industrial incidents. In fact, alarm
management has become identifed
as one of the key issues listed on the
cover of recent CSB investigation
reports. The British-based organisa-
tion Engineering Equipment &
Materials Users Association
(EEMUA) came to the same fnding
in its report from 1999 when it
analysed major incidents around the
world, including Three Mile Island,
Bhopal and Texaco Milford Haven.
1
Therefore, the connection of alarm
foods to incidents has been well
documented for over 12 years. On
the whole, industrial progress
controlling foods in those 12 years
has been nil. Many corporations and
plant locations are attempting to do
so, but many engineers, including
alarm management vendors, do not
know what it takes to control foods
under all operating conditions. This
article shows examples of good
alarm management programmes
and how they successfully control
alarm foods under all operating
conditions.
Defnition and impact of an
alarm food
An alarm food has been defned by
ANSI/ISA 18.2 as being 10 or more
annunciated alarms in any 10-
minute period per operator.
2
Since
ISA issued the 18.2 standard over
two years ago, recent OSHA audits
have reported that questions on the
subject came up during inspections
of the plant. An attorney presenting
on the topic at the Global
Alarm foods and their contribution to industrial incidents can be controlled
successfully through all process states
DUSTIN BEEBE, STEVE FERRER and DARWIN LOGEROT
ProSys Inc
Conference on Process Safety 2012
stated that alarms and alarm
management were now frequently
coming up in audits. It is obvious
that OSHA considers the ISA 18.2
standard to be recognised and
generally accepted good engineer-
ing practices (RAGAGEP). As a
result, plant managers should be
ready to have their alarm perform-
ance scrutinised.
Obviously, plants that do not
currently meet the ISA 18.2 guide-
lines under all operating conditions
must remediate or face the conse-
quences. The consequences that
occur are not only when OSHA
audits come to the plant. Consider
these items:
It is commonly reported that 70%
of plant incidents occur on startup
or shutdown. Shutdown periods
are where many alarm foods occur
because of the sudden changes from
the run state. Could the occurrence
of these incidents be caused by one
or more critical alarms being
hidden under the food of
hundreds of alarms typical during
shutdown? What about startup
after a shutdown where alarm
foods have occurred? Until the
alarms have cleared, the operators
are fying blind without alarms
until reactivated. What are the odds
of an incident occurring when start-
ing up your plant without alarms
to annunciate?
Are your safety-critical alarms
immune to infuence by alarm
foods? Even special-sounding
alarms can be missed when a
cacophony of hundreds of fooding
alarms are sounding
What about product quality, plant
proftability or equipment damage
have any of these issues suffered
when an alarm food was a signif-
cant distraction for the operator
while operating the process?
Has your plant ever performed an
incident review to fnd that a criti-
cal alarm was missed? Was
personnel action taken against the
board operator for poor perform-
ance? Was the food of alarms even
considered as a distraction for the
board operator?
Does your plant have any data on
how many alarms are missed due
to distractions? How many redun-
dant alarms annunciate alarms
with little or no meaning at your
plant? How many loss of contain-
ment incidents, injuries or worse
can be tracked back to an alarm
food?
From the beginning
Over the last 30 years, the number
and frequency of alarms have
changed with technology. In the old
days of pneumatic controls, install-
ing a new process alarm had
signifcant costs. Since the use of
computer-based control systems,
new alarms cost nothing. As a
result, the number and frequency of
alarms has increased signifcantly
over the years. This phenomenon
has reached a point where a term
was needed to defne the experi-
ence when numerous alarms are
annunciating in a stream an
alarm food.
Alarms are typically confgured
for a single operational state run.
Alarm foods typically occur upon
a change of state in the process.
This could be from run to shut-
down or run to upset, or can even
include a change from state 1 to
www.eptq.com PTQ Q3 2012 65
prosy.indd 1 1/6/12 14:43:26
66 PTQ Q3 2012 www.eptq.com
Consistent and reliable reporting
of alarm metrics
Improvements in alarm philoso-
phy document
Improving the quality of alarms
Dynamic alarm management.
Reduction in operator errors
Honeywell, in its paper presented
to the AIChE 1996 Safety
Conference, estimated that the total
loss due to operator error is $10
billion per year in the US alone.
3
Also, it has been commonly
reported that 70% of process inci-
dents occur during startup or
shutdown. Therefore, when the
process is changing from one state
to another and alarm foods have
the greatest propensity to occur, it
makes sense that lots of errors
would occur during alarm foods.
Proper alarm management is just
the beginning of minimising opera-
tor errors. The priority of
minimising errors during critical
changes in operating mode must be
the highest priority because of what
an error can mean during these
critical process transition periods.
The signifcance of errors and the
consequence of a mistake during
these periods while at an increased
risk of error during an alarm food
is justifcation alone for aggressive
investment to eliminate alarm
fooding.
Consistent and reliable reporting of
alarm metrics
Many plants have reported having
alarm management systems that
report results but require a signif-
cant amount of an engineers time
to routinely produce and send these
reports. Since the metrics are some-
what limited, some have even
resorted to augmenting the
system with several spreadsheets,
taking even more time from
productive assignments.
Since so many of the alarm
reporting tools contain manual
intervention, some managers have
allowed process upsets or shut-
downs with associated foods to be
fltered out of reports. Although
this makes the results look better,
fltering these results can hinder
actually resolving the problem
because those results are removed
state 2. This is because operating
parameters change upon a change
of state in the process and those
changes cause the foods. This
phenomenon can affect hundreds
or even thousands of alarms.
Therefore, upon process state
changes, many alarms can sound in
a short period of time. The frst
alarm or two indicate the initiating
event, alerting the operator to the
change. After this, many unneces-
sary and redundant alarms resulting
from the same root cause are
annunciated and displayed to the
operator. If another situation devel-
ops, those alarms would be added
to the existing food of alarms with-
out any differentiation between the
two root causes for the operator.
The operator is faced with evaluat-
ing these alarms for any process
information they might provide,
then acknowledging them. So many
alarms can show up at once that
this job can become very diffcult.
In fact, the observation has been
made that so many alarms are
going off that, by cause and effect,
acknowledging alarms becomes the
only response of the operator.
What is the problem?
The EEMUA, when speaking about
the impact of alarm foods on cata-
strophic incidents, said they were
a major contributor, and the loss
incidents frequently involved the
operator being overloaded with
alarm foods.
1
EEMUA Publication 191 provides
several high-profle examples where
poor alarm system performance
(foods) contributed to fnancial loss,
environmental damage, injuries or
death. Based on this information,
the following equality has been
proposed to emphasise proper
thinking and priority of alarm
management projects for corporate
managers, operations managers, and
managers of industrial health, safety
and environmental departments:
Floods = incidents = loss
Conversely, the control of alarm
foods will result in fewer incidents,
less loss and, as a result, lower risk.
Industrial plants have reported
lower insurance rates as a result of
lower risk attributed to superior
alarm management performance.
Process state changes are critical
periods where operators need their
alarm system to be fully functional.
Unfortunately, these periods are
exactly when alarm foods occur.
The fact that alarm foods can occur
in a process control room is prob-
lematic for four reasons:
A deluge of alarms can cause the
operator to miss critical alarms
Floods of alarms can be a signif-
cant distraction while the operator
is trying to deal with upsets in the
plant. At times, the operator is
forced to acknowledge alarms with-
out review to silence alarms in
order to think
Floods can be an indication of
larger systemic safety issues
With ISA 18.2 becoming
RAGAGEP, plant managers can
expect to be asked by OSHA to
show documentation that they meet
the ISA 18.2 guidelines under all
operating conditions. Now that
foods are recognised to be a major
contributor to plant incidents,
OSHA will defnitely be seeking
actual plant metrics for peak rates
(or foods). The fltering of upset
conditions and shutdowns from the
results will not be acceptable. The
General Duty Clause allows OSHA
to investigate anything including
an alarm food during an inspection
or as a result of hearing about one
in an operator interview.
What are the opportunities
in industry?
The reduction in alarm foods when
the process is running and stable is
relatively easy and not a factor for
most plants. The key to alarm
management is the ability to
perform under all operating condi-
tions, including startup, shutdown
and any other operating mode
change the process might experi-
ence. The opportunity in industry is
to implement an alarm manage-
ment programme that properly
manages and reports alarms under
all operating conditions.
Several key opportunities for
industry will be examined as they
relate to successful alarm
management:
Reduction in operator errors
prosy.indd 2 1/6/12 14:43:36
www.eptq.com
from the discussion. Many managers take these steps
because they do not believe they can achieve better
results or they cannot justify the investment to get
better results. The frst belief is false because the means
for producing results that meet ISA 18.2 metrics under
all operating results does exist today and has for many
years. In the second case, if the alarm management
solution is not getting the job done then management
needs to see the results to be aware that investment
will be necessary to achieve the desired results.
Consider the reaction OSHA inspectors would have
once they discover negative results (alarm foods) were
fltered by manual intervention of an engineer at the
plant. This situation might be uncovered through an
operator interview and review of the fltered alarm
metric results.
Unfortunately, many plants are inconsistent in their
collection of data and production of reports because of
the man-hours of effort required for the reports. Also,
the priority of alarm reporting projects are typically
low and the engineer assigned to the task is often
pulled to take on a more important project. Many
times, the project dies when the engineer never goes
back to it.
Recent advancements in alarm reporting software
tools now allow the data collection and email or
SharePoint reporting process to be completely auto-
mated for an enterprise. These enterprises can be made
up of multiple distributed control systems (DCS) of
different manufacturers and versions in a given plant
location, several plants in a specifc country or even a
worldwide enterprise. The key is that the entire proc-
ess can gather, process and report versus ISA 18.2
metrics without the need for human intervention.
Once the actual alarm performance results versus a
standard are known, corrective action can be justifed.
In addition to funding, these engineering projects must
be appropriately prioritised with the commitment
necessary to get the project done. Unfortunately, with-
out proper funding for these projects, priority and
commitment will not follow.
Improve alarm philosophy document
Some sites have not yet developed an alarm philoso-
phy document that contains the specifcs necessary to
eliminate debate and disagreement during the rational-
isation process. As a result, the time requirement for
the rationalisation process goes up, as do expenses for
the project.
Another reason to revise the alarm philosophy docu-
ment is that many companies have not yet updated
their alarm rate targets to the most recent ISA 18.2-
2009 Standard. As a result, plant managers do not have
the means to justify expenditures to achieve better
performing alarm rates, particularly alarm foods,
because the targets set do not require improvement
from the less than adequate results currently attained.
Improve the quality of alarms
A common misconception in industry is that the objec-
tive of alarm management is to reduce the number of
SAMSON AG MESS- UND REGELTECHNIK
Weismllerstrae 3
60314 Frankfurt am Main Germany
Phone: +49 69 4009-0 Fax: +49 69 4009-1507
E-mail: samson@samson.de
Internet: www.samson.de
SAMSON GROUP www.samsongroup.net
A
0
1
1
2
0
E
N
Partner with
the Best
With over 50 independent subsidiar-
ies and more than 220 engineering
and sales ofces spread across the
world, SAMSON ensures the safety
and environmental compatibility of
your plants on any continent.
To offer the full range of high-quality
control equipment used in industrial
processes, SAMSON has brought
together highly specialized compa-
nies to form the SAMSON GROUP.
prosy.indd 3 1/6/12 14:43:47
alarms annunciated to the operator. While the reduc-
tion in alarm rates will almost always be a result of a
well-designed and implemented alarm management
project, it is not the primary objective. The objective of
alarm management is to improve the quality of alarms.
Additionally, the goal is to provide operators with a
consistent and reliable alarm interface that supports
their efforts to safely, reliably and effciently operate
the process.
Every alarm should:
Be clear and relevant to the operator
Indicate an abnormal process condition or event
Have consequences of inaction
Have a defned response
Be unique.
In short, a quality alarm is an annunciated process
condition or event to which the operator can and
should take corrective action in order to return the
process to stable and safe operation. Another way of
stating these objectives is to provide the operator with
alarms that are necessary and meaningful, but not those
that are unnecessary, confusing or redundant.
The way alarm quality is improved is through a
complete and systematic alarm rationalisation. Every
plant is divided into systems and subsystems. Plant
operating procedures, P&IDs, PHA documentation, and
interviews with operations and engineering personnel
are all important parts of the overall process. The qual-
ity of this process rises and falls with the quality of the
facilitator. The facilitator should be an experienced,
professional engineer with extensive process and alarm
management experience. This position should not be a
note taker but one that can challenge the participants
where necessary, guide the discussion to avoid rabbit
trails, and keep the process on track to meet the overall
objectives.
Alarm rationalisation is the most important element
of alarm management, and the approach used in ration-
alisation will be a prime determinant in the success or
failure of the overall effort. A number of practices have
emerged with the intent to reduce alarm rates. Most
only affect average alarm rates. In fact, the ASM
Consortium reported that after evaluating 37 consoles
and over 90 months of data peak alarm rate is not
closely correlated with the degree of rationalisation.
4
Only one process, dynamic alarm management, has
proven to control alarm foods.
Dynamic rationalisation is alarm rationalisation for
more than one process state. Static rationalisations can
become dynamic when the question when is added
to the discussion for each point. As a result, the
increased cost for performing a dynamic rationalisation
versus a static one is not as signifcant as one might
think. Additionally, using the answers generated from
the when questions allows engineers to properly
confgure alarm management software to enable and
deactivate alarms appropriately for whatever the
current state is for the process.
Answering the when question involves using oper-
ating experience and process knowledge to determine
the detectable operating states of each section of the
68 PTQ Q3 2012 www.eptq.com
Table 5
distributor design and its installation as the potential
root cause of high radial temperature spread in the bed
outlet.
Details related to the distributor tray selection and
tray installation have been previously addressed.
Improving hydrocracker re|iabi|ity
Reactor quench zone design and thermometry selec-
tion are critical for a hydrocracker units reliability. A
fast-response multipoint device for the thermometry
provides early warning of potential temperature excur-
sions. If temperature wave propagation from bed to
bed is not corrected, bed inlet temperature spread will
translate into excessive bed outlet temperature spread,
resulting in poor temperature control, premature shut-
down for catalyst change-out, or temperature
excursions.
remature unit shutdown for cata|yst change-out and
unit re|iabi|ity
Hydrocracker reactors are generally designed for a
high hydrogen partial pressure. Consequently, the
catalyst deactivation rate is often less than 2F (1C)
per month. A high radial temperature spread at the
bed outlet may cause the reactor shell to reach its
metallurgical temperature limit, while the actual
weighted average bed temperature of the catalyst is
lower than the estimated end-of-run temperature,
resulting in a premature unit shutdown. It is also
important to recognise that the number of skin ther-
mocouples may be limited. Consequently, the actual
highest metal temperature may be higher than the
measured highest temperature reading, leading to
reactor reliability issues.
Conc|usions
Both optimised distributor and quench box design can
improve catalyst utilisation (or catalyst cycle length)
and unit reliability. An optimised mixing chamber
using swirling action alleviates concerns when an
increase in the quench gas rate is required for reactor
excursion control. A compact quench zone design with
a reduced number of manways can reduce capital costs
while shortening unit turnaround time. Reactor ther-
mometry selection is critical to provide a fast response
and reliable radial temperature reading for improving
unit reliability.
keferences
1 H2Advunce US luLenL 7,112,212 26, SepL 2006.
2 US luLenL 2,S02,44S 24, Mur 1970.
3 US luLenL S,690,896, 2S Nov 1997.
4 US luLenL S,62S,14S, 2 ]un 1997.
5 US luLenL 4,826,989, 6 ]un 1989.
6 Chou 1 S, Hydrocrucker rellublllLy lmprovemenL, /!Q, Q2 200S.
1ai-Sheng Chou ls u Hydroprocesslng SpeclullsL wlLh H2Advunce,
HousLon, 1exus, und hus 22 yeurs' reInlng experlence, speclullslng ln
hydroprocesslng reucLor lnLernuls deslgn. He hus deslgned 82 dlsLrlbuLors
und 49 quench zones Ior hydroprocesslng reucLors und holds u lhu ln
chemlcul englneerlng Irom Lhe UnlverslLy oI HousLon.
/ma||. ta|s|eaqcao|.com
www.eptq.com 119
achieved using the metal-based additive at one-fourth
the dosage of the incumbent product. Through the use
of the scavenger programme, this refner was able to
S
alarms reported (see Figure 7). This programme has
been in commercial use for more than fve years. It has
also resulted in fewer environmental incidents and
greater peace of mind for the refner, workers and
-
eration because there is a signifcant risk of exposure to
people, equipment and the environment. Asphalt is
generally transferred at loading racks, where personnel
manning the loading rack may be exposed to toxic
vapours. Transport to terminals and application of the
fnal product are also situations where exposure to
S may
occur. The viscous nature of asphalt and the high
temperatures needed to work with this material make
for a dangerous combination when even low levels of
S
from asphalt can be accomplished through the proper
application of a chemical scavenger. An additive
-
ogy and test methods can optimise additive dosage,
improve scavenger response and allow refners to meet
A thorough understanding of the asphalt blending
confguration, tank residence times, available mixing
equipment and injection points is critical to designing a
programme that produces the desired results while
ensuring an optimised chemical programme. Diffculties
-
bly can also be an issue. With the proper additive,
-
eries to increase employee safety, comply with
environmental regulations and minimise capital
ls Munuger oI Lhe 1echnology SupporL Group Ior luel
AddlLlves wlLh uker Hughes und hus 12 yeurs oI Iuel uddlLlves lndusLry
S
scuvengers, dlsLllluLe cold ow lmprovers und mercupLun scuvengers. She
ls ulrecLor oI Lhe leLroleum AddlLlves Group wlLh uker
Hughes, hls prevlous roles wlLh Lhe compuny lnclude Senlor SynLheLlc
ChemlsL Ior Lhe keInery lrocess Group, Munuger Ior AnLlIoulunLs und
Corroslon Groups, und Munuger oI k&u Ior Lhe OllIeld Chemlculs Group.
He hus u lhu ln lnorgunlc chemlsLry Irom Kunsus SLuLe UnlverslLy und
to increase emp|oyee safety and
TruePeak Tuneable Diode
Laser (TDL) Analyser
Our TruePeak Process Laser Analyzer uses
a tunable diode laser and measures across
an infrared absorbance region. This means
you can make measurements in the most
demanding applications.
Rapid measurement (as fast as 1 second)
Process temperature up to 1500 Celsius
Optical measurement no sensor contact
with process
Aggressive applications high particulate,
corrosives, and more
Flexible installation options
TruePeak measurement
In situ analysis
Interference free
The Process TDL Solution
Features:
please visit us at www.yokogawa.com/eu
h2a.indd 7 9/3/12 12:56:05
prosy.indd 4 1/6/12 14:43:59
plant. The team determines key
operating data and a logic struc-
ture, which will be utilised to
identify the current state. Once the
states and logic are determined, it
is a straightforward exercise to
determine when (during which
operating states) each alarm is to be
active and inactive.
Other rationalisation methods
Other common rationalisation
methodologies do not improve the
quality of alarms. In fact, some do
just the opposite. Most of these
approaches are pursued as a means
to reduce the cost of the project.
Unfortunately, in every case they
insure the plant will not reduce
foods to the levels required by ISA
18.2:
Bad actor management This meth-
odology focuses on the handful of
alarms with the highest annuncia-
tion rates. The process typically
repeats over and over again. The
risk is that legitimate alarms have
been disabled without considera-
tion for the overall process. This
process can reduce average alarm
rates but does nothing to impact
alarm foods
Partial rationalisation Partial
rationalisation focuses the effort on
the alarms that annunciated over
the last three to six months. Much
like bad actor management, this
methodology is focused on a subset
of the total alarms and is not
considering the process as a whole
system
Static rationalisation This is an
alarm rationalisation for a single
process state usually the run
state. Most processes have several
states, therefore, when non-run
states are current, lots of alarms can
sound. This is because system read-
ings do not match the run state set
points. This rationalisation method
can usually result in a reduction in
average alarm rates, but has been
proven not to have an impact on
foods (see ASM Consortium report
comment above).
4
Dynamic alarm management
Most alarm management practices
and procedures only produce
desired results in the area of aver-
age alarm rates. Certainly, reducing
average alarm counts is positive;
however, reducing foods (peak
rates) is vastly more important for
everyone operators, managers
and the community. The reason this
is true is that peak rates are respon-
sible for operators missing critical
alarms and average rates are not.
Disastrous incidents affecting lives,
property and the environment can
begin when an operator misses a
single alarm.
Dynamic alarming is not state-
based alarming, although many
practitioners use these terms inter-
changeably. The difference between
the two is subtle but exceedingly
important:
State-based alarming This is
where the operator authorises a
change or the control system auto-
matically changes alarm settings to
appropriate set points upon a
change of state. Unfortunately, this
change can be abrupt because there
is little to no transition manage-
ment. Also, without managing this
transition of set points from one set
to another, the change can actually
create a food of its own. The time
when a process is changing state is
very critical and the worst possible
time for the operator to deal with a
food. Many software vendors are
limited in the number of points that
their software can handle. As a
result, they limit the number of
total points to about 30 for state-
based alarming
Dynamic alarming Although simi-
lar to state-based alarming, the key
distinction is that the automatic
alarm settings go through a transi-
tion manager when changing from
one setting to another. This allows
each alarm a far smoother, custom-
ised transition and eliminates the
causation of foods. True dynamic
alarm management software is able
to handle over 700 dynamic points
per operator.
Dynamic alarm management is
the most effective form of alarm
management and, as a result, many
claim it, but few companies actually
have the ability. Alarm foods are
reduced to the lowest possible
levels, and plants using dynamic
alarm management have no prob-
lem meeting and exceeding alarm
metrics set by ISA 18.2.
Results of dynamic alarm
management
The results produced by well-
conceived, planned and implemented
dynamic alarm management systems
are nothing short of exceptional.
These differences are reported by
some operators to be amazing or
unbelievable.
The following narrative is a
specifc case that illustrates several
key differences dynamic alarm
management can make in a work-
ing control room. At the central
control room of a large US refnery,
a trip of the compressed air supply
for the plant caused a complete
shutdown of the refnery.
Fortunately, about half of this
centralised control room had just
implemented a comprehensive
dynamic alarm management
program. Within a few minutes of
the shutdown, this side of the
control room complex was rela-
tively calm, operators were going
about the necessary shutdown
activities, and the group was well
aware of where they were and
knew what actions needed to be
taken. They did not experience any
alarm foods.
The other side of the control room
was in disarray. Alarms were
annunciating by the hundreds,
someone was assigned the role of
acknowledging alarms so the others
could fnd out where they were and
what actions were necessary.
Alarms were continuing to annun-
ciate so fast that the alarm summary
screen could not keep up. In fact, a
number of alarms were completely
lost and never found. The senior
operator had a very diffcult time
assessing the situation. In time, he
was fnally able to piece together
what state the plant was in even
though he still had a number of
unknowns.
The operations manager for the
plant happened to be in the control
room complex when the plant shut-
down occurred. This manager was
able to experience both sides of
the control room under the same
shutdown conditions. After seeing
the difference dynamic alarm
management made under those
real-life conditions, he insisted on
implementing it in the other half as
www.eptq.com PTQ Q3 2012 69
prosy.indd 5 2/6/12 17:56:03
soon as possible instead of waiting
for the next year.
Comparison of alarm rationalisation
methodologies
The data in Table 1 were acquired
from three different sites using vari-
ous rationalisation methodologies.
Shutdowns and upsets occurred for
each of the units during the time
period.
The actual results generated from
bad actor management show very
little improvement of either average
or peak alarm rates. None of the
bad actor management readings
were even close to the requirements
for meeting the ISA 18.2 guidelines.
Static rationalisation improves aver-
age alarm rates to where they can
often meet ISA 18.2 metrics, but
peak alarm rates (foods) show very
little improvement at all before and
after static rationalisation. Dynamic
rationalisation is the only successful
means of controlling both average
and peak alarm rates to levels that
meet or exceed ISA 18.2 metrics.
The results shown in Table 1 indi-
cate how signifcant dynamic
rationalisation can be for a process.
Plant results
The results that can be obtained
using dynamic rationalisation can
eliminate a signifcant number of
redundant alarms, thereby reducing
distractions, load and potentially
errors for the operators. Figure 1
shows a comparison of alarm data
for the same time period in the
same process, the only difference
being that the green line was gener-
ated after the system was
dynamically rationalised. The red
line was recreated from the exact
same event and timeline, showing
alarms that would have occurred
had dynamic alarming not been
implemented.
In Figure 1, the red line indicates
that without dynamic alarming a
food of about 150 alarms would
have occurred between 8:48 and 9:03
or over about fve minutes. Within
that same fve-minute period, the
green line shows the actual alarm
rate. Note that at about 8:58, three
alarms sounded, one of which was a
critical alarm, not related to the orig-
inal event, which could have led to
a signifcant incident if it were
missed by operators. The critical
alarm was a fuel gas fail to close the
alarm from the SIS system. As a
result of so few unnecessary alarms
annunciating, the plant manager felt
dynamic alarm management played
a major role in helping to avert a
signifcant, potentially catastrophic
event from occurring.
Figure 2 shows about one month
of alarm rate data in 12-hour
segments. Near the end of the
month, the unit tripped and was
completely shut down as a result.
This process state change would
generally trigger hundreds and, in
some cases, thousands of alarms in
a very short period of time.
Eliminating the redundant or stand-
ard shutdown alarms accomplished
many goals, including improving
the effectiveness of the operator. In
this case, the frst 12-hour period
containing the trip experiences only
50 alarms. This signifcant reduction
in alarms during a shutdown
improved the ability to spot critical
alarms by making them more obvi-
ous to the operator. Also, reduced
distractions provide time for the
operator to think ahead of the proc-
ess and avoid potential problems
before they develop.
Figure 3 is a close-up of the shut-
down period highlighted in Figure
2. Please note that the actual peak
rates never approached the ISA 18.2
peak alarm limit of 60 alarms per
hour.
Practical steps to control alarm
foods
The items listed below are some
keys to begin the process of obtain-
ing the results that meet or exceed
ISA 18.2 metrics:
Management commitment is an
important key to success. Without
this commitment, resources for the
project will not be available. Keep
them appraised of progress by
communication about your
progress. Develop a metric report
with the right level of details that
they want to see regularly. If your
70 PTQ Q3 2012 www.eptq.com
Point summary ISA 18.2 Dynamic Static Bad actor
Metrics[2] rationalisation rationalisation management
Number of areas 2 2 2
Points 3641 3327 2552
Q3 2010 avg. alarm rate per hour 6 4 5 12
Q4 2010 avg. alarm rate per hour 6 4 6 26
Q3 2010 peak alarm rate per hour <=60 39 1266 402
Q4 2010 peak alarm rate per hour <=60 42 702 954
Note: fgures shown in red do not meet ISA 18.2 Metrics
Comparison of results by rationalisation method
Table 1
Figure 1 Comparison of dynamic versus typical alarm management
120
200
160
80
40
8.45 9.00 9.15 9.13
14
0
Static
Dynamic
176
prosy.indd 6 1/6/12 14:44:20
|h-0PTh Sh08T 0008SS
S0L0T|0h-8AS0 0AS ST00|S
|hh0VAT|V 0|S00SS|0h
6800PS
hAh0S-0h T0T08|ALS
P|0h8|h6 L0T08S
00TSTAh0|h6 Xh|8|T FL008
&
GeorgeR. Brown Convention Center, Houston, Tx
USERS SYMPOSIUM
SYMPOSIUM
28
th
Our Technical Sessions are the best value for your training dollar and are taught by
leading industry experts!
xh|b|ts 0peo Free to the P0b||c
Tuesday & Wednesday 2:30 p.m. - 7:00 p.m.
Thursday 9:30 a.m. - 12:00 p.m.
http:llt0rbo|ab.tam0.ed0
For more |oIormat|oo
Call 979.845.7417 or email at inquiry@turbo- lab.edu
Sponsored by: The Turbomachinery Laboratory
Texas A&N Universit] College 8tation
turbo.indd 1 1/6/12 16:52:40
alarm metric reporting tool is not
getting the job done, identify
one that does and ask for manage-
ments support to get the necessary
resources. Without automatic and
reliable reporting on a plant-wide
basis, an
OSHA audit might be a very
unpleasant event for your boss
The alarm reporting tool should
have the following capabilities:
Automatic data gathering and
72 PTQ Q3 2012 www.eptq.com
Figure 2 Example of ood control using dynamically managed alarm rates upon unit trip
and shutdown: data in 12-hour segments
Figure 3 Example of ood control using dynamically managed alarm rates upon unit trip
and shutdown: data in hourly segments
60
80
ISA 18.2 target average. 6 a|arms/hour
70
50
40
30
20
10
m
a
2
1
0
1
0
2
/
2
1
/
2
m
p
2
1
0
1
0
2
/
2
1
/
3
m
a
2
1
0
1
0
2
/
2
1
/
5
m
p
2
1
0
1
0
2
/
2
1
/
6
m
a
2
1
0
1
0
2
/
2
1
/
8
m
p
2
1
0
1
0
2
/
2
1
/
9
m
a
2
1
0
1
0
2
/
2
1
/
1
1
m
p
2
1
0
1
0
2
/
2
1
/
2
1
m
a
2
1
0
1
0
2
/
2
1
/
4
1
m
p
2
1
0
1
0
2
/
2
1
/
5
1
m
a
2
1
0
1
0
2
/
2
1
/
7
1
m
p
2
1
0
1
0
2
/
2
1
/
8
1
m
a
2
1
0
1
0
2
/
2
1
/
0
2
m
p
2
1
0
1
0
2
/
2
1
/
1
2
m
a
2
1
0
1
0
2
/
2
1
/
3
2
m
p
2
1
0
1
0
2
/
2
1
/
4
2
m
a
2
1
0
1
0
2
/
2
1
/
6
2
m
p
2
1
0
1
0
2
/
2
1
/
7
2
m
a
2
1
0
1
0
2
/
2
1
/
9
2
m
p
2
1
0
1
0
2
/
2
1
/
0
3
m
a
2
1
1
1
0
2
/
1
/
1
m
p
2
1
1
1
0
2
/
1
/
2
t
n
u
o
c
m
r
a
l
A
Date and time
0
Tota| unit
shutdown
60
ISA 18.2 peak a|arm target. 60 a|arms/hour
70
50
40
30
20
10
m
a
3
0
1
0
2
/
2
1
/
8
2
m
a
0
0
0
1
0
2
/
2
1
/
8
2
m
a
0
0
0
1
0
2
/
2
1
/
9
2
m
a
6
0
1
0
2
/
2
1
/
8
2
m
a
9
0
1
0
2
/
2
1
/
8
2
m
p
2
1
0
1
0
2
/
2
1
/
8
2
m
p
3
0
1
0
2
/
2
1
/
8
2
m
p
6
0
1
0
2
/
2
1
/
8
2
m
p
9
0
1
0
2
/
2
1
/
8
2
m
a
3
0
1
0
2
/
2
1
/
1
3
m
a
0
0
0
1
0
2
/
2
1
/
1
3
m
a
6
0
1
0
2
/
2
1
/
1
3
m
a
9
0
1
0
2
/
2
1
/
1
3
m
a
3
0
1
0
2
/
2
1
/
0
3
m
a
0
0
0
1
0
2
/
2
1
/
0
3
m
a
6
0
1
0
2
/
2
1
/
0
3
m
a
9
0
1
0
2
/
2
1
/
0
3
m
p
2
1
0
1
0
2
/
2
1
/
0
3
m
p
3
0
1
0
2
/
2
1
/
0
3
m
p
6
0
1
0
2
/
2
1
/
0
3
m
p
9
0
1
0
2
/
2
1
/
0
3
m
a
3
0
1
0
2
/
2
1
/
9
2
m
a
6
0
1
0
2
/
2
1
/
9
2
m
a
9
0
1
0
2
/
2
1
/
9
2
m
p
2
1
0
1
0
2
/
2
1
/
9
2
m
p
3
0
1
0
2
/
2
1
/
9
2
m
p
6
0
1
0
2
/
2
1
/
9
2
m
p
9
0
1
0
2
/
2
1
/
9
2
t
n
u
o
c
m
r
a
l
A
Date and time
0
Tota| unit
shutdown
reporting for multiple control
systems of different manufacturers
and versions
Alarm results compared directly
with ISA 18.2 targets
Routine alarm reports to be
emailed to appropriate users
Management reports to be
emailed as a routine to managers
The alarm reporting tool is
pivotal to the justication of further
investment of resources in this
project. This data is important;
make sure an engineer is not work-
ing him or herself to death to get it
Hire a consultant with process
and alarm management experience
to guide the plant through the proc-
ess of upgrading your alarm
philosophy document. This docu-
ment must have the specicity to
handle issues that might be points
of disagreement during the next
phase. Addressing those issues in
this document simplies and
minimises the cost of the next step
dynamic rationalisation
Do not be tempted to save money
during the rationalisation phase by
only doing some subset of total
points and leave the rationalisation
incomplete and open to oods. The
end result is the rationalisation will
need to be repeated, requiring addi-
tional investment of resources and
time
The rationalisation team should
be made up of operations, process
engineering and controls engineer-
ing along with an experienced
rationalisation facilitator
The facilitator for the dynamic
rationalisation process should be a
professional engineer with exten-
sive process and alarm management
experience. Hiring an outside
consultant is usually helpful to
minimise political issues with
operators
The selection of a dynamic alarm
management solution is very
important to the success of the
project. Before any purchase is
made, a designate should talk to at
least three references of other plants
with PSM processes that are now
meeting or exceeding ISA 18.2
guidelines under all operating
conditions. The alarm management
software should add to the capabili-
ties of the control system, not
replace anything. One of the
features critical to achieving
dynamic alarm management is
proper management of transitions
from one state to another. This
process should be customisable by
point and not require multiple
alarms to be activated at once. The
logic tool within the software
should be congurable to allow
majority voting (for example: 2 of 3,
3 of 5) to change process states
prosy.indd 7 1/6/12 14:44:31
The alarm shelving tool furnished
with the software should be confg-
urable with automatic re-enabling.
One popular alarm shelving tool
also has intelligent re-enabling that
re-enables the alarm automatically
when it is no longer having an
issue.
Conclusion
Although progress has been reported
in the reduction of average alarm
rates, only very few locations have
seen the necessary improvement in
alarm foods. Incident investigations
reported over the last 12 years have
indicated loss incidents frequently
involving the operator being over-
loaded with alarm foods.
1
Therefore,
if this is true, the equation foods =
incidents = loss is true. As a result,
it is fair to state that the control of
alarm foods will lead to fewer loss
incidents and, as a result, fewer
health, safety and environmental
incidents and their associated losses
and expenses.
Several cases have shown that
alarm foods can be controlled
successfully through all process
states. Managers must emphasise
the importance of controlling foods
and provide resources in order to
achieve results that meet the ISA
18.2 metrics for alarm foods. When
plants are able to consistently
achieve the metric for alarm foods,
the risk of incident and loss will be
better controlled.
References
1 Appendix 16 - The Cost of Poor Alarm
Performance, Alarm Systems, A Guide to
Design, Management and Procurement EEMUA
Publication 191, Edition 2, 2007, ISBN 0 85931
155 4, Imprint Reference 7-2007.
2 ANSI/ISA 18.2 - 2009, Management of Alarm
Systems for the Process Industries.
3 Cochran E, Bullemer P, Abnormal Situation
Management: Not by New Technology Alone,
AIChE 1996 Safety Conference.
4 Andow P, Zapata B, Reducing Alarm Flood
Severity, Highlights from the ASM Consortium
2008.
Additional reference not cited:
5 US Chemical Safety Board (CSB)
Investigations, www.CSB.gov/investigations/
default.aspx.
Dustin Beebe is the CEO of ProSys, Baton Rouge,
LA. He holds a BS in chemical engineering from
the University of Arkansas and is a registered
Professional Engineer. He is a member of the
ISA 106 committee and employs members of
the ISA 18.2, 101 and 106 committees, is a
member of the Chemical Engineering Advisory
Boards for both the University of Arkansas
and Louisiana State University, and frequently
presents on alarm management and human
machine interface (HMI) and on other process
control subjects.
Steve Ferrer is Business Development Manager
at ProSys. Prior to joining ProSys, he spent 25
years in consulting sales and service to the
chemical, refning, paper and textile industries.
He holds a BS in microbiology from Louisiana
State University and is a member of AIChE, ISA
and LCIA.
Darwin Logerot is a Senior Consulting Engineer
at ProSys and is one of the companys leaders
in the areas of model predictive control and
alarm management. He has more than 35
years experience in the process chemical
industry, holds a BS in chemical engineering
from Louisiana State University and is a
registered Professional Engineer in Louisiana
and is a member of AIChE and ISA.
www.eptq.com PTQ Q3 2012 73
Adding value to the oil,
gas and petrochemical
industries?
Absolutely.
ABB C onsulting provides technical and engineering services to improve
performance in the areas of compliance, operations and engineering. We offer
expertise in the following areas: environmental services; industrial energy
efficiency; inspection; integrity management; maintenance & reliability; pressure
relief; process safety; project services; technical software and technical training.
w w w . a b b . c o m /c o n s u lti n g
A B B C o n s u lti n g
Tel: +44 (0)1925 741111
E-mail: contact@ gb. abb. com
PTQ Q2 2012 (125x178) Feb 2012.indd 1 01/03/2012 10:34:03
prosy.indd 8 2/6/12 17:39:07
What you can do
with a
touch of blue.
Improve your renery protability by maximizing the production of clean
transportation fuels with our leading residue upgrading technologies.
Deliver the best in renery hydrogen production while reducing
your operating costs with our unique Terrace Wall reformer design.
Enhance the efciency of your overall sulfur recovery to achieve peak
operating and environmental performance with our SRU technology.
You can
And these are just the technology options. There is so much more
you can do with a touch of blue. Visit www.fwc.com/touchofblue
fw.indd 1 7/3/12 13:55:37
Minimise corrosion while maximising
distillate
S
ustained growth in the demand
for jet fuel, diesel and other
middle distillate products is
expected to have a continuing
impact on unit operations, product
pricing, product selection and refn-
ing margins into the foreseeable
future. As more and more new
facilities come online to supply the
demand for tighter product sulphur
specifcations, refners will continue
to maximise distillate production in
their atmospheric distillation units
to take advantage of favourable
product pricing. However, maximis-
ing the production of these fuel
streams requires a continual assess-
ment of the entire processing system
beyond the mechanical capability of
pumps, piping and valves to ensure
reliable operation of the unit in a
market environment that favours
distillate production. As refneries
continue to lower tower top temper-
atures in an effort to increase
product draws in the distillate
sections of the column, the condi-
tions for introducing salt fouling
and corrosion mechanisms into
areas that previously were not
affected come to the forefront.
Refners must address the hazards
of unmonitored distillate maximisa-
tion on corrosion in the crude
distillation column top section and
overhead system. In this article,
overhead corrosion control strate-
gies and guidelines are discussed to
help refners maintain reliable unit
operation while maximising distil-
late production.
Overhead salt point and lower tower
top temperatures
Crude unit overhead corrosion
deals with corrosion affecting the
Reducing atmospheric fractionator overhead temperatures to maximise middle
distillate production requires a full understanding of resulting corrosion mechanisms
BRandOn Payne
GE Water & Process Technologies
upper sections of the crude unit
atmospheric fractionation column,
including the top tower trays, over-
head condenser system and top
pumparound circuits. Corrosion in
the crude unit overhead system is
primarily due to acid attack at the
initial water condensation point
(ICP), resulting in low pH condi-
tions and the associated aggressive
corrosion of the systems metal
surfaces. Secondary corrosion
mechanisms in the tower top and
overhead are typically due to
amine-chloride salt deposition driv-
ing under-deposit corrosion.
Neutralisers are used to control
the pH of condensing overhead
waters within an optimal range to
maximise the reduction of corrosion
rates while minimising the tendency
for salt deposition caused by the
neutralisation reaction with the
acidic species. The type of neutral-
iser used in an overhead system is
selected based on three primary
factors: neutralisation capacity (the
strength of the neutraliser), the
water partition coeffcient (the rate
at which it will enter the frst water
droplets formed in the overhead
system) and the neutralisers salt
point.
The salt point is defned as the
temperature at which the frst
neutralisation salts begin to precipi-
tate from the vapour phase. These
salts can be very corrosive them-
selves and can also give rise to
under-deposit corrosion at certain
points in the system. In order to
control the deposition and corrosiv-
ity of these salts, a water wash is
often used to provide a means of
diluting and washing the corrosive
salts from the overhead system. In
these cases, the salts are scrubbed
from the overhead vapour, washed
from the overhead piping and
condenser system, and fow into the
overhead receiver. However, as the
overhead process temperature is
lowered in an effort to force addi-
tional material into the distillate
draw section of the column, the
location of the salt point tempera-
ture moves further upstream into
the overhead line, pumparound
circuits and tower top internals
where there is no water wash.
Without the means of removing
deposited salts in these areas, corro-
sion can be severe and equipment
failure rapid. Therefore, it is critical
to continuously re-evaluate the
neutraliser being used to determine
if it is still appropriate for changes
in overhead and operating condi-
tions. The ideal neutraliser for the
system will form its amine chloride
salt at a temperature that is 15F
(8C) lower than the water dew
point in the system. To protect
against the deposition of precipi-
tated amine-chloride salts inside of
the distillation column, the neutral-
iser salt point temperature must
also be 25F (14C) lower than the
tower top temperature.
www.eptq.com PTQ Q3 2012 75
Corrosion in the
crude unit overhead
system is primarily
due to acid attack
at the initial water
condensation point
ge.indd 1 1/6/12 16:22:41
76 PTQ Q3 2012 www.eptq.com
effects. While chloride control is a
relatively direct and straightfor-
ward effort, lowering levels of
tramp amines can be much more
diffcult. This is often because oper-
ational practices prevailing in the
refnery will give rise to high levels
of tramp amines cycling up in the
crude unit overhead. These prac-
tices are often caused by units
outside the crude unit boundary.
Four primary sources of tramp
amine entry are the sour water
stripper, steam production,
alkanolamine scrubbing units, and
amines entering the refnery with
the incoming crude oil. An overall
understanding of tramp amine
backgrounds, surges and sources is
necessary to enable targets and
intervention for control of these
species. Levels as low as 5 ppm of
certain tramp amines can have a
dramatic impact on salt points and
associated corrosion. Figure 1 illus-
trates typical tramp amine cycles.
The tendency for all these amines
to cycle up in the system is largely
driven by overhead receiver pH
and desalter effuent brine pH. As
the pH rises above 5.5, the tendency
for these species to cycle up is
substantially increased. This is
because the partitioning rate at
which amines migrate from the
hydrocarbon to the water phase are
strongly infuenced by pH. Once
cycled up, the rate at which amines
will blow down is dependent on
the pH of both the desalter effuent
brine and the overhead receiver
waters, as well as the relative rate
of amine input. A lower pH will
cause a faster blow-down at a
constant input of amines to the
recycling system. The dynamic
aspects of amines having reduced
partitioning rates, reduced recycling
rates and increased blow-down
rates as pH is lowered has impor-
tant consequences.
GE Water & Process Technologies
(GE) has developed a comprehen-
sive methodology to address the
drivers of system salt points, salt
deposition rates and subsequent
corrosion rates in systems with
signifcant salt fouling problems
through a systematic review of
amine inputs. By properly control-
ling these inputs and system pH,
Role of excess chlorides and
tramp amines
Chloride control in the overhead
system is one of the most important
aspects of a good corrosion control
programme. This is because altering
chloride levels has the largest over-
all impact on the corrosion potential
by dramatically affecting both pH
and the salt point deposition
temperatures. The lower chloride
levels entering the distillation
column are, the greater the degree
of corrosion control that is possible
from a treatment programme.
Therefore, with the desalter having
the greatest impact on the condition
of the charge to the distillation
tower, all efforts should be made to
ensure optimal desalter perform-
ance, reducing desalted crude
chlorides to the lowest possible
levels. However, maintaining low
chlorides alone is not suffcient to
guarantee good overhead corrosion
control. The amines present in the
system are equally important to the
overhead systems fouling and
corrosion potential.
Neutralising amines that are
intentionally added to control over-
head pH conditions are not the only
amine species that play a role in
overhead salt formation. The pres-
ence of tramp amines may play a
larger role in undesired salt forma-
tion in the overhead and tower top
than the injected neutraliser amines.
Tramp amines are broadly defned
as any amines, other than the
appropriate neutraliser being used,
found cycling in the system. Tramp
amines that are entering and recy-
cling in the system will strongly
affect overhead pH and typically
have very high salt points. Sources
of these tramp amines include
incoming crude and slop oils, steam
neutralisers, alkanol amine units,
sour water strippers, H
2
S scav-
angers and cold wet refux. Such
amines can make it virtually impos-
sible to either keep salt points
below the water dew point or to
drop pH to desirable levels. The
most desirable condition is to have
overall tramp amines in the system
low enough to enable the usage of
a quality neutraliser with a low salt
point. If tramp amine levels are
high enough, the net system salt
point can negate the impact of a
quality neutraliser. This situation
can cause salt point temperatures to
exceed the tower top temperature
and cause various deposition prob-
lems that can become quite severe
and affect tower operation and
charge rates. Efforts should always
be taken to understand total amine
loading.
Both elevated chloride levels and
amine levels will negatively impact
overhead corrosion due to salt point
Tank
farm
Fractionation
column
Desalter
Accumulator
Wa sh
w a te r
S trip p in g
ste a m
To w e r to p re flu x
A m in e
re c yc le
A m in e
re c yc le
N e u tra lise r
A m in e
Wa te r w a sh
Figure 1 Typical amine recycle loops
ge.indd 2 1/6/12 16:23:12
For mission-critical equipment, trust the #1 online monitoring system
Who monitors the most reciprocating compressors?
When you look at the numbers, it all addsup to PROGNOST Systems:
|..gost |rst.||oJ b.so c| cr||ro J|.grcst|c systons cr .oc|p.cc.t|rg ccnp.ossc.s
|o .c.|Js tcp .o|ro.s .rJ ||| p.cJJco.s t.Jst ||OC|OS
systems
Ovo. 20 yo..s c| oxpo.|orco |r ncr|tc.|rg .oc|p.cc.t|rg n.c||ro.y
||OC|OS |.s cro |ccJs .oc|p.cc.t|rg n.c||ro.y
OJ. JoJ|c.t|cr orsJ.os t|.t ycJ. syston .on.|rs bost|rc|.ss
reply@prognost.com www.prognost.com
prognost.indd 1 1/6/12 11:42:08
*ad copy 2.indt 1 1/6/12 14:52:43
www.eptq.com PTQ Q3 2012 79
the most rapid reduction in deposi-
tion and corrosion potential can be
achieved. Although lowering pH
offers positive benefts, as described
above, iron should be monitored in
the overhead waters. The effective
minimum pH will be dictated by
the onset of increased iron produc-
tion due to ICP corrosion at the
water dew point. The pH should
never be lowered beyond this level
in order to keep ICP corrosion
under control.
Overhead water wash systems
Water washing is used as a means
of forcing the water dew point
temperature to higher levels and to
physically dilute and wash salts.
This is accomplished by raising the
amount of free liquid water in the
system. This free water will then
dilute corrosive species at the ICP
and also wash away any neutralisa-
tion salts formed at temperatures
below the wash water injection
temperature, or mixed exit temper-
ature. However, it should be noted
that an inadequate water wash can
be worse than no water wash.
Water wash should be injected in
two stages using high-effciency
nozzles in a co-current confgura-
tion to provide a small droplet size
with a large surface area and
dispersal pattern. This will impact
both the wall wetting capability of
the spray, as well as the vapour
scrubbing effciency.
The frst injection stage should be
a single point injected into the over-
head vapour line near the top of the
column, while the second stage
needs to be multiple points injected
in parallel just prior to the
exchanger inlets. In a well-
controlled unit, the frst-stage wash
injection should provide just
enough water to form 20% of total
liquid water and primarily saturate
the overhead vapour. The second
injection stage should then inject
the remainder of the total water
needed to achieve the wash water
target. Enough water should be
added to achieve a minimum of 5%
free water. While 5% is a minimum
value, 10-15% water wash can be
even more effective. However, care
must be taken to make sure that the
overhead receiver can handle the
additional amount of water fux
and still provide acceptable water
separation. Water carry-over in the
overhead refux can be a very
signifcant problem, as high levels
of water-soluble amine salts will be
carried back to the tower. This can
lead to a large cycling effect that
will dramatically increase salt
points, as well as place salts directly
on tower internals. Additionally,
the water can cause wetting of
already existing salts and increase
their corrosion potential considera-
bly. Care should also be taken to
ensure that overhead vapour veloc-
ity stays within a range of
30-80 ft/s.
Caustic usage
A target of <15 ppm chlorides, with
<5 ppm upside variation, is an ideal
target. While effective programmes
can be maintained with higher
levels of chlorides, it generally
becomes more diffcult and expen-
sive if either chlorides or variation
increase. A large variation in chlo-
ride levels can be very detrimental,
as either low pH acid attack or high
pH salt deposition can occur.
Therefore, efforts should be priori-
tised to maintain effective chloride
control within control ranges. The
injection of caustic (NaOH) into the
desalted crude oil can be used as a
polisher to further reduce chlorides
after the best performance is
obtained from the desalters.
However, caustic usage must be
carefully evaluated and monitored
to determine accurately the down-
stream impacts and the critical
threshold concentrations. It should
not be used as a replacement for
optimising desalter operation.
Proper selection of flming corrosion
inhibitors and neutralisers
In order to properly control corro-
sion in a crude unit overhead
system, a three-pronged strategy
comprised of an organic neutralis-
ing amine, a flming inhibitor and a
water wash should be implemented.
Every corrosion control programme
will utilise these three elements to
varying degrees, based upon the
unit design, crude diet and operat-
ing envelope. Therefore, the
selection of the proper treatment
chemistry is critical to the
programmes success and the units
equipment reliability.
Under normal conditions, the
ideal neutraliser utilised will form
its amine-chloride salt at a tempera-
ture that is at least 15F (8C) lower
than the water dew point in the
system. Calculating the ICP and salt
point are critical to controlling
corrosion. The use of modelling
software, such as GE Water &
Figure 2 LoSalt ionic equilibrium model input
Selection of the
proper treatment
chemistry is critical
to the programmes
success and the units
equipment reliability
ge.indd 3 1/6/12 16:23:24
As such, they help reduce the risks
associated with salt fouling due to
amine-based neutralisers or tramp
amines present in the system.
Filmers have been used with
success in the dispersion of depos-
ited salts in areas where no water
wash is present, such as pumpa-
round circuits and tower trays.
Unlike neutralisers, flming inhib-
itors will not vaporise in the
overhead system and will remain
liquid. Therefore, flmers must be
atomised into the overhead at the
point of injection. Nozzles and dilu-
tion streams must be used to
achieve proper distribution. Since
the flmer injection exists as an
entrained droplet distribution in the
overhead vapour stream, it follows
a two-phase fow profle. Liquid
droplets will impact with and coat
the wall through direct interaction.
Both the choice of application point
and the droplet size distribution of
the injected liquid play a large role
in the overall effectiveness of a
flmer. Larger droplets in the fow
feld have a tendency to impinge
onto the outside wall of any bends
or turns in the line. A loss of flmer
coverage can be caused by 90-
80 PTQ Q3 2012 www.eptq.com
Process Technologies proprietary
LoSalt Ionic Equilibrium model (see
Figures 2 and 3), allows for the
rapid and effcient prediction of the
overhead system salt point. These
modelling tools can be used to
quickly determine the best neutral-
ising amine and/or operating
parameters by predicting salt points
for various amines and the ICP for
various operating conditions.
The LoSalt Ionic Equilibrium
model has been effectively used to
assist refners in optimising tower
top temperatures by establishing
the operating limits they must not
exceed in order to prevent salt
formation and deposition in the
system. In one case, the operational
changes made, based on the infor-
mation provided by the ionic
modelling analysis, allowed the
refnery to decrease average over-
head corrosion rates by 80% to a
corrosion rate of <5 mpy (verifed
by consecutive UT thickness
readings).
Filming inhibitor chemistries are
the mainstay of the overhead corro-
sion inhibitor programme. Filmers
work by coating the metal surface
with a hydrophobic barrier, which
prevents corrosive species from
reaching and reacting with the
metal surface. While a neutraliser
has a maximum theoretical limit to
the overall reduction of corrosion
rates, flmer chemistries are not
constrained by such a limit. The
level of corrosion protection from a
flming corrosion inhibitor can
approach 100%, given adequate
dosage and the proper conditions.
However, the practical aspects of
the flmer application generally do
not allow such a degree of protec-
tion. It is, however, relatively easy
to realise 90-95% protection for
coated surfaces at reasonable
dosages. Traditional flmers require
a pH above 4 to maintain optimal
flm stability. The newest flmers in
the GE Water & Process
Technologies pHilmPlus line can
offer flm stability down to a pH of
2. This is especially important
during desalter upsets and high-
chloride events, which can drive
overhead system pH to very low
levels. In addition to providing a
signifcant further reduction in
corrosion rates, over and above that
available with a neutraliser, certain
flmers can act as salt dispersants.
2 3 0
1 8 0
1 3 0
8 0
1 0 3 0
1 . 7
5 . 0
8 . 3
1 1 . 5
5 0 7 0 9 0 1 1 0
S
a
l
t
p
o
i
n
t
s
N
e
u
t
r
a
l
i
s
e
r
r
a
t
e
Chl ori des i n boot , ppm
3 0 1 . 7
3 . 7
5 . 7
7 . 7
9 . 7
1 1 . 7
1 3 . 7
1 7 . 7
1 5 . 7
1 9 . 7
2 1 . 4
O p e ra tin g p o in t
Wa te r d e w p o in t
To p te m p e ra tu re
A m in e
A m m o n ia
G P D
6
5
4
3
2
1
0 1 0 2 0 3 0 4 0 5 0
O p e ra tin g p o in t a t in te rse c tio n o f p H p ro file a n d re d lin e
6 0 7 0 8 0 9 0 1 0 0
p
H
a
t
2
5
C
Wat er condensed, %
0
1 4 . 8
1 8 . 1
Figure 3 LoSalt ionic equilibrium model output
ge.indd 4 1/6/12 16:23:36
degree elbows or U-bends due to
the momentum of the travelling
droplets forcing them to move to
the outside wall of the curves via
centripetal forces. Also, vapour-
liquid route preferencing and
maldistribution can cause poor
flmer coverage downstream of
splits, T-s and in manifolds. Droplet
sizes larger than 50 microns will
have a greater tendency to be lost
prematurely to the wall for systems
with complex bends. For this
reason, high-quality hydraulic
nozzles that are properly designed
for the system fows and pressures
should be utilised to achieve a
minimum droplet size distribution.
Also, at least two stages of flmer
distribution are recommended for
most systems, similar to a water
wash system.
The frst stage should be near the
beginning of the overhead vapour
line, preferable into the 90-degree
elbow pointing down the vertical
pipe near the side of the tower.
The second stage should be distrib-
uted over parallel legs, just
upstream of the individual
exchangers. The injection direction
should be co-current with the fow,
and each injection point should use
its own carrier stream that is
metered and controlled. Filmer
injection points should be at least
10 pipe diameters away from
other injection points. The frst
flmer injection is preferred
downstream of the neutraliser
injection point, and both should
be signifcantly upstream of the
water dew point and salt point
locations.
Conclusion
As refners reduce atmospheric
tower top temperatures to maxim-
ise diesel and middle distillate
production, a thorough understand-
ing of the ICP, salt point and
control of amine recycle loops is
critical to maintaining plant reliabil-
ity in changing plant operational
conditions. By practising good
operational diligence, treatment
programme stewardship and utilis-
ing predictive diagnostic tools, such
as GEs proprietary LoSalt Ionic
Equilibrium model to predict amine
salt points, refners can establish
safe operating regimes for diesel
and middle distillate maximisation
and ensure the long-term safety
and proftability of refnery assets.
LoSALT and pHilmPLUS are trademarks
of General Electric Company and may be
registered in one than one country.
Brandon Payne is a Product Applications
Specialist with GE Water & Process
Technologies Refnery Corrosion Center of
Excellence. He is responsible for global support
of refnery corrosion treatment programmes,
and has over 14 years of refnery engineering
and process treatment experience.
www.eptq.com PTQ Q3 2012 81
Determination of Sulfur and other elements
at-line and in the laboratory
El ement al Anal ysi s
of Fuel s
To keep pace with the demanding quality requirements of
modern fuels, advanced, precise and easy to use analytical
technology is required. With a complete range of XRF and
ICP spectrometers, SPECTROs unique solutions for at-line
and laboratory elemental analysis are capable of meeting
the most demanding product specification testing
requirements.
Measure your fuels
- at sub 10-15 ppm levels of sulfur t o ensure federal
government agency compliance
- at t race ppm levels for met al element s such as Cu, Ca, Mg,
Na, K, and P, t o ensure low engine emissions as well as
t rouble-free mot oring
- wit h reliabilit y, speed and accuracy for any part icular applicat ion
- manually or fully aut omat ically
Discover more exciting details at
www.spectro.com/fuels
Visi t us at
digitalrefining.com
ge.indd 5 2/6/12 17:39:51
zyemeflow.indd 1 1/6/12 14:55:17
Reliable design of sour water strippers
O
il refning always generates
sour water, and within a
refnery there are numerous
sources. Most refnery sour water
systems contain very little CO
2
. The
H
2
S content makes water sour,
and H
2
S levels can become very
high. The capacity of ammonia
solutions for H
2
S is a direct result
of ammonias alkalinity, which
neutralises the hydrogen ion liber-
ated by H
2
S dissociation when it
dissolves into the solution.
Although not the usual case, in
principle, and with enough H
2
S
partial pressure, there can even be
more H
2
S than ammonia. The
potentially very high H
2
S content
can make sour water extremely foul
and, if the H
2
S is not recovered,
pollution levels would be
completely out of hand. Many sour
4
water sources have been noted.
1
Sources include the following:
Many refning units use live
steam and heat for fractionation,
and live steam for velocity assist
and temperature control in fred
heaters. Nitrogen in the presence of
heat and a hydrogen source (such
as a hydrocarbon) forms ammonia.
The steam is condensed and recov-
ered in the overhead circuit of the
crude unit, FCC unit or coker unit
In the case of refnery hydrotreat-
ing, hydrogen gas and a metal
catalyst are used to saturate olefns.
Hydrotreating also converts
sulphur-containing hydrocarbons to
H
2
S, and nitrogen-bearing hydro-
carbons to ammonia
Although ammonia is considera-
bly more volatile than most
alkanolamines, it has a high affnity
for water. Ammonia is removed
from hydrocarbon products by
A simulation model aims to raise confdence in the reliability of sour water
stripper design
NAthAN hAtcher and rAlph WeilANd
Optimized Gas Treating
injecting wash water into the gas
and cooling the mixture at an
elevated pressure to condense the
water. This provides an irresistible
invitation for ammonia to enter the
aqueous phase
Wash water prevents the accu-
mulation of salts and the corrosion
of heat exchange surfaces, espe-
cially in areas where there are gas
liquid interfaces and where there
are sudden temperature changes on
heat transfer surfaces, such as when
heat transfer is controlled by liquid
level in an exchanger
Amine regenerator refux water
purges can also be a signifcant
source of ammonia.
The sour water generated in refn-
eries is generally classifed as being
either phenolic or non-phenolic.
Non-phenolic water contains almost
exclusively NH
3
, H
2
S and possibly
a trace of CO
2
; it is generated by
refnery hydrotreating (hydrodesul-
phurisation, or HDS) units. When
stripped of contaminants, non-
phenolic water can typically be
recycled for reuse in the HDS as
wash water, or it can be used as
make-up water to the crude desalt-
ing process. This article considers
only non-phenolic water. Phenolic
(or, more broadly, non-HDS) water
contains compounds that can harm
upstream units if used as wash
water in them. Typical contami-
nants include salts, phenols and
caustic. However, make-up water
to processing units must frst be
treated, so maximising water reuse
is desirable to minimise attendant
operating costs. Other sources of
water to sour water stripping units
are process drums, crude desalting
units, scrubbing of hydrocarbons
following caustic treatment for
mercaptans, COS and fnal H
2
S
removal, TGU quench columns, and
various effuent drains for remov-
ing the water used to prevent salt
deposition in equipment.
1
It may be useful to point out that
ammonia and hydrogen sulphide
have almost unlimited solubility in
water when they are present
together. This is a possibly interest-
ing consequence of the fact that the
reactive component of the solvent,
ammonia, is volatile and, if present
in the gas phase, it will continue to
absorb as long as it becomes proto-
nated as a result of H
2
S
co-absorption. Thus, it is conceiva-
ble that a particular sour water
stream may be a lot more concen-
trated in both ammonia and
hydrogen sulphide than the solubil-
ity of either component alone
would suggest.
Basic sour water stripping process
At frst glance, sour water stripping
is a simple process in which either
external steam, steam generated by
a reboiler, or even a hot hydrocar-
bon stripping vapour is used to
shift chemical reaction equilibria by
heating the sour water. Stripping
vapour is the gaseous solvent
used to remove and carry the
ammonia and H
2
S out of the
system. In other words, the applica-
tion of heat generates internal
stripping steam (equivalently, live
steam injection or stripping gas can
be used) and removes ammonia,
H
2
S and CO
2
from the water by:
Heating the sour water feed to
boiling point
Reversing chemical reactions
Diluting the partial pressure of
www.eptq.com PTQ Q3 2012 83
ogrt.indd 1 1/6/12 16:46:21
84 PTQ Q3 2012 www.eptq.com
Chemistry of ammonia with
acid gases
Ammonia is a relatively weak base
capable of being mono-protonated.
For example, in aqueous solution, it
forms ammonium ion (protonated
ammonia) to a limited extent:
NH
3
+ H
+
NH
+
4
(1)
This reaction is in perfect parallel
with amine protonation, so in this
sense ammonia can be thought of
as nothing more than just another
reactive amine. There is a great deal
of nonsense written in various
books and other publications
concerning the reactions of H
2
S and
CO
2
with ammonia. All reactions
involve ionic species and all reac-
tion products are ions. Ions do not
form ionic compounds except possi-
bly when materials begin to
precipitate. As long as all species
are in solution, they exist as indi-
vidual ions and are not associated
with each other. All ions are freely
foating and the only associations
are ones that result in solution non-
ideality. Thus, there is no such
thing as ammonium carbonate,
ammonium bicarbonate, ammo-
nium bisulphide or diammonium
sulphide in solution. It is very hard
to make sense of reaction equilibria
unless one discards the existence of
such compounds.
The reactions that occur when
H
2
S and CO
2
dissolve in solution
are the same as in any other aque-
ous, primary or secondary amine
system. The reactions are:
H
2
O H
+
+ OH
-
(2)
H
2
S H
+
+ HS
-
(3)
HS
-
H
+
+ S
=
(4)
CO
2
+ H
2
O H
+
+ HCO
-
3
(5)
HCO
-
3
H
+
+ CO
=
3
(6)
NH
3
+ CO
2
NH
2
COO
-
+ H
+
(7)
Ammonia drives all these reac-
tions to the right by serving as a
proton sink per reaction (1).
Understanding sour water strip-
pers, understanding the way
ammonia behaves as a solvent for
acid gases, and understanding what
the gases stripped by furnishing
excess steam.
The process is very similar to
amine regeneration. Figure 1 shows
a typical sour water stripper column
with heating by the injection of live
steam. Since a sour water stripper
does not form a closed loop in the
same sense that an amine regenera-
tor does, maintaining a water
balance is unnecessary. This means
that live steam can be used as a
stripping agent either alone or in
conjunction with a conventional
reboiler, and the additional water
added by the condensate is simply
added to the refnerys water inven-
tory. Typical energy usage in the
stripping process is in the range
1.0-1.5 lb of 50 psig equivalent satu-
rated steam per gallon of sour
water.
When an external reboiler is used,
steam pressure can often be higher
than in an amine regenerator to
minimise the heat exchange surface.
In an amine regenerator, amine
degradation limits temperatures. In
a sour water stripper, there is little
or no ammonia in the stripped
water in the reboiler, so these
concerns do not exist. However,
there is a practical limit of 400-
450F, where coking heavy
hydrocarbons can lead to fouling
and solids deposition in the
reboiler. Corrosion is always a
concern.
Higher NH
3
and H
2
S concentra-
tions require more stripping energy.
Since H
2
S solubility relies on the
presence of ammonia, the molar
concentration of H
2
S very rarely
exceeds that of ammonia, and then
usually only in dilute systems. A
typical molar ratio of H
2
S to ammo-
nia is 0.5-0.8 in the combined sour
water stripper feed water of a typi-
cal refnery. Ammonia levels in the
water are often determined by
upstream process conditions, and
they can be highly specifc to the
process licensor and crude slate in
operation. Obviously, higher
concentrations of NH
3
and H
2
S are
preferred from a water consump-
tion perspective. However, there is
a practical limit of between one and
several weight per cent ammonium
bisulphide equivalent in the sour
water feed before metallurgy must
be upgraded.
Trays have historically been used
in sour water strippers, but random
packing is beginning to see use in
units processing relatively clean
water. Trays with directional, fxed
valves have been reported to be
more resistant to fouling, because
the horizontal velocity imparted as
the gas leaves each valve tends to
sweep clean the area near the
valves.
2
Stripped sour water specifcations
for NH
3
and H
2
S can be highly
dependent upon the locale where
the unit is installed and the fnal
discharge requirements. NH
3
is
harder to strip than H
2
S, and typi-
cal targets for NH
3
are 30-80 ppmw
in the stripped water versus unde-
tectable to less than 0.1 ppmw for
H
2
S. Typical recent installations
3,4
involve 35-45 actual trays, with
overall tray effciencies quoted
anywhere from 25 to 45%.
S o u r
w a te r
F e e d /
b o tto m s
L ive
ste a m
S trip p e d
w a te r
S WS
A G
1 1
7
1 2
1 0
SWS
Pump-1
Cooler
3 5
4
8
9
Figure 1 Sour water stripper with live steam injection
ogrt.indd 2 1/6/12 17:27:11
dupont.indd 1 23/2/12 15:04:26
86 PTQ Q3 2012 www.eptq.com
happens to ammonia in amine
regenerators depends on knowl-
edge of:
Vapour-liquid equilibria
Kinetics of the carbamate-forming
reaction, Equation 7
An appreciation for mass transfer
as a rate process where Henrys
Law applies.
The thermodynamic framework
on which the vapour-liquid calcula-
tions are based involves a model
for the activity coeffcients via
extended Debye-Hckel theory.
Thus, the basic modelling approach
for ammonia is the same as for any
other amine, with one exception:
ammonia is highly volatile and this
leads to different distributions in
absorption and especially regenera-
tion equipment compared with
amines. Its volatility is often respon-
sible for it getting into the sour
water system in the frst place
(through condenser water blow-
down, for example), but volatility
also allows it to be recovered rela-
tively easily from the same sour
water. Heat stable salts and alkali
salt contaminants also affect the
distribution of ionic species in solu-
tion and their presence must be
considered, too, and is the subject
of a future article.
Simulating sour water strippers
Traditionally, sour water strippers
have been modelled as a series of
equilibrium stages, with overall
stage effciencies quoted anywhere
in the range of 15% to 45%; that is,
ranging over a factor of three.
However, the mass transfer rate-
based approach to the simulation of
amine contactors and such hard-to-
model distillation processes as
extractive, azeotropic and reactive
distillation have been in commercial
use since the mid- to late 1980s.
Their extension to sour water strip-
ping is a natural progression and,
in December, 2011 a commercial
mass transfer rate-based sour water
stripper model became available as
part of the ProTreat simulation
package. The remainder of this arti-
cle uses the ProTreat simulators
sour water stripper model to reveal
some rather surprising facts and
behaviours of sour water strippers.
Phase equilibrium
The vapour pressure of ammonia
and acid gases above sour water
plays a key (but by no means the
only) role in determining the extent
to which a given column and proc-
ess confguration will purify sour
water and how the process operat-
ing conditions affect the separation.
We have developed an activity
coeffcient model for phase behav-
iour for sour water that uses the
Deshmukh-Mather approach
10
for
activity coeffcients, and the Peng-
Robinson equation of state for the
vapour. The thermodynamic model
has been ftted to all public-domain-
phase equilibrium data for the
CO
2
-H
2
S-NH
3
-H
2
O system, a total
of some 550 separate experiments,
most involving ammonia and either
one or both of the acid gases H
2
S
and CO
2
. Figure 2 is a set of parity
plots indicating partial pressure
H
N
d
e
t
a
l
u
c
l
a
C
l
a
i
t
r
a
p
a
P
,
e
r
u
s
s
e
r
p
Measured NH
3
partial pressure, Pa
H
d
e
t
a
l
u
c
l
a
C
2
l
a
i
t
r
a
p
S
a
P
,
e
r
u
s
s
e
r
p
Measured H
2
S partial pressure, Pa
O
C
d
e
t
a
l
u
c
l
a
C
2
l
a
i
t
r
a
p
a
P
,
e
r
u
s
s
e
r
p
Measured CO
2
partial pressure, Pa
Figure 2 Parity plots of VLE data for the system NH
3
-H
2
S-CO
2
-H
2
O
ogrt.indd 3 2/6/12 17:43:16
It should be noted that this is not
an overall tray effciency. Tray
overall effciencies are based on
ideal stage calculations to deter-
mine the number of theoretical
(ideal) stages. ProTreat studiously
avoids such calculations because,
when combined with the averaging
that is done through overall eff-
ciencies, and the possible use of
thermal effciencies to force-match
measured temperature profles,
they completely obscure what is
really going on in SWSs. The inter-
esting behaviours that occur in sour
water strippers are caused by mass
transfer effects; ideal stage approxi-
mations ignore tower internals as
mass transfer devices and smooth
out most of the physics of the real
mass transfer device by considering
only vapour-liquid equilibrium. The
missing physics cannot be recov-
ered by an overall tray effciency
for the column. Consequently, an
ideal stage stripper model is, at
best, only as good as its guessed
effciencies. The Murphree vapour
effciency, on the other hand,
provides a quantitative measure of
how close to perfect equilibrium
each real tray actually operates.
Unfortunately, a mass transfer rate
model is needed to predict the
Murphree effciencies, so one might
as well use a mass transfer model
in the frst place and avoid effcien-
cies altogether. The real value of the
Murphree vapour effciency is to
show how far from equilibrium real
trays perform and how radically
performance can vary from tray to
tray. It is worth emphasising that
there is absolutely no relationship
between Murphree vapour and
overall tray effciencies.
As can be seen from Figure 3, H
2
S
effciency varies enormously
throughout the tower and is also a
very sensitive function of the steam-
to-sour-water ratio, especially when
steam rates are relatively high.
Generalising the Murphree vapour
effciency for H
2
S is utterly impossi-
ble because it varies from a few per
cent to 50%. Trays become
extremely ineffcient when the last
vestiges of H
2
S are being removed
from the water. Obviously, the tray
count and the steam required
depend heavily on the treated water
www.eptq.com PTQ Q3 2012 87
ranges in Pascals, and the goodness
of ft.
Mass transfer rate model
The sour water stripper model in
ProTreat deals with the separation
of ammonia, the acid gases and
water as governed by the particular
mass transfer rate of each individ-
ual component. Ammonia is treated
as reactive towards CO
2
in the same
sense that any other primary or
secondary amine is reactive, and
transfer rates are determined by
individual (vapour and liquid)
phase mass transfer coeffcients,
interfacial areas and concentration
difference driving forces. The
details of mass transfer rate model-
ling have been described at length
elsewhere
5,6
and will not be
repeated here. Suffce it to say, the
kinetics of the NH
3
-CO
2
reaction
(see Equation 7) have been properly
accounted for using known kinetic
parameters and the usual enhance-
ment factor approach. The resulting
process model is a virtual plant on
a computer in which all the funda-
mental physical and chemical
processes occurring are properly
accounted for. The computer simu-
lation is a direct one-for-one
prediction of both column and
process performance completely
without recourse to user estimates
of any parameters whatsoever. All
that is required is the actual process
fow sheet confguration, tower
internals details and values for
process parameters corresponding
to such operating conditions as sour
water fow and composition, tower
pressures and imposed heat loads.
The sour water stripper model
itself has been validated against at
least a half dozen sets of stripper
performance data by two refning
companies and an engineering frm,
with what were reported by them
as excellent results. Using a virtual
plant in the form of a precise
computer model, the remainder of
this article examines the effect of
the steam-to-water ratio and strip-
per operating pressure on sour
water stripper performance, as
measured by such parameters as
Murphree vapour effciency and
residual ammonia and H
2
S in the
stripped water. The simulation
cases use live steam injection as the
source of stripping vapour because
this tends to be the most effective
way of providing thermal energy
for stripping; however, reboiled
strippers add less make-up water
and can be simulated just as easily.
Exploring strippers
Figure 1 shows the simplest possi-
ble confguration of a sour water
stripper. For this exercise, the strip-
per contained 40 one-pass valve
trays on 2ft spacing with 2in weirs.
Sour water was fed to Tray 6 (from
the top), live 50 psig saturated
steam entered below the bottom
tray and, in all cases, the column
was sized for 70% of jet and down-
comer food. Except for the case
study involving stripper pressure,
where a fxed temperature approach
of 20F was used, the sour water
feed to the stripper was kept at
235F. Table 1 gives the conditions
of the sour water used for this case
study.
Ratio of steam to sour water
Four steam rates were used 0.78,
0.92, 1.20 and 1.48 lb/USgal
covering the range normally used
in sour water stripping. (Gantz
7
shows performance data for steam
rates from 0.6 to 4.0 lb/USgal,
although, commercially, rates at
and above 1 lb/USgal are more
usual.) One of the performance
parameters of interest is the
computed Murphree (1925) vapour-
phase effciency.
8
Taylor and
Kooijman
9
defne the Murphree
vapour effciency, E
mw
i,n
, for compo-
nent i on tray n (from the top) as:
E
MV
=
y
i,n
- y
i,n + 1
(8)
i,n y
i,n
- y
i,n + 1
where y is the mole fraction
Total fow, lb/h 150 000
Temperature, F 235
Pressure, psia 70
Water, mol% 96.4
Hydrogen sulphide, mol% 1.5
Carbon dioxide, mol% 0.1
Ammonia, mol% 2.0
Sour water feed conditions
Table 1
ogrt.indd 4 1/6/12 17:27:37
Theres a lot to think about these days. W orldw ide energy dem and w ill continue to rise. The environ-
ment needs to be protected. Hea|thy econom|es and hea|thy compan|es need so|ut|ons for effc|ent
and environm entally com patible pow er generation. G etting there requires forw ard thinking and
technological advancem ent to protect our health and our prosperity. This is w hat drives us every
day, when we deve|op compress|on so|ut|ons for carbon capture, transport and storage. We fnd the
answers and create the products that empower you to run your bus|ness proftab|y, wh||e operat|ng
in an environm entally sound m anner. Thats one less thing for you to think about. Find out m ore at
w w w .m andieselturbo.com
Mari ne Power Pl ant s Turbomachi ner y Pri meSer v
Forward Thi nki ng
Advanced CO
2
compression solutions
Forward Thinking_210x297mm.indd 1 01.06.12 12:49 man.indd 1 1/6/12 16:09:35
specifcations to be met. Thus, the
designer is faced with a diffcult
decision, because more trays and
more stripping energy lead to lower
effciency. These effects cannot be
modelled or accounted for with an
ideal stage model, even when a
guessed overall tray effciency is
used. Providing optimal, cost-
effective designs using theoretical
stages is a rather seat-of-the-pants
enterprise.
Before tackling corresponding
effciencies for ammonia, it is
revealing to look at the vapour- and
liquid-phase concentration profles
of ammonia, as well as the simu-
lated vapour profle compared
directly with the equilibrium
vapour composition. Figure 4 shows
tray-by-tray profles of the liquid-
and vapour-phase mole percentages
of ammonia. The surprising thing is
the bulge, or maximum, displayed
at boil-up rates at the low end of
the range.
We have observed and reported
the existence of similar maxima in
ammonia concentration in the
context of ammonia control in refn-
ery amine units.
11
Indeed, it was
found that in an amine regenerator
only the bottom few trays were
effective in stripping ammonia. In
the present case of a sour water
stripper, ammonia stripped in the
lower part of the column is actually
reabsorbed in the upper part
because the H
2
S is high enough
there to react with and fx a signif-
cant part of the ammonia back into
the liquid. When the steam-to-sour
water ratio is high enough,
however, the H
2
S concentration is
too low everywhere to remove
enough ammonia to result in a
maximum in the ammonia concen-
tration. We note in passing that
there is a strictly monotonic
decrease in H
2
S concentration as the
sour water moves down the
column.
When the boil-up rate is at the
lower end of the spectrum and a
maximum in ammonia concentra-
tion occurs away from the ends of
the stripper, the Murphree vapour
effciency for ammonia exhibits
seemingly odd behaviour. Figure 5
shows very surprising effciency
trends from tray to tray at stripping
steam rates of 0.78 and 0.92 lb
steam/USgal. At the lowest steam
rate, the apparent effciency ranges
from -100% to +120%, and at 0.92
lb/USgal the apparent effciency
reaches +200%. The reason is that
the lines corresponding to actual
and equilibrium vapour-phase mole
fractions cross (as they must do
because a bulge implies that strip-
ping gives way to absorption at
some point in the column) and they
have a maximum on immediately
adjacent trays rather than on the
same tray. Figure 6 shows the
actual (y) and equilibrium (y*) lines
for the steam rate of 0.92 lb/USgal,
from which it can be seen that both
exhibit a maximum, the lines cross,
and they have peak values on
different trays. Referring to
Equation 8 (defnition of effciency),
it is easy to see that if the numera-
tor or denominator changes sign, or
the concentration difference in the
denominator becomes very small,
apparent effciencies can become
not only large but negative.
At frst glance, much of this odd
effciency behaviour may seem a
little academic; however, when a
constant effciency is applied to an
equilibrium-stage model, the maxi-
mum in ammonia concentration in
the interior of the column, well
away from the ends, will not be
revealed and simulation results will
tend to be quite optimistic in terms
of sour water quality and stripped
gas ammonia levels. This may go
some way to explaining the wide
variations reported in tray effcien-
cies (15% to 45%) in this application.
It is worth noting that when strip-
ping steam rates are moderate to
high, the Murphree effciency turns
out to be between 35% and 40%,
with variations of only one or two
1 0
0
5
1 5
2 0
2 5
3 0
3 5
0 1 0 2 0 3 0 4 0 5 0 6 0
T
r
a
y
f
r
o
m
t
o
p
H
2
S eff i ci ency, %
4 0
F e e d tra y
0 . 9 2
0 . 7 8
1 . 2 0
1 . 4 8
1 0
0
5
1 5
2 0
2 5
3 0
3 5
0 5 1 0 1 5 2 0 2 5 3 0
T
r
a
y
f
r
o
m
t
o
p
NH
3
i n vapour, mol %
4 0
F e e d tra y
0 . 9 2
0 . 7 8
1 . 2 0
1 . 4 8
Figure 3 Calculated Murphree vapour effciencies for H
2
S
Figure 4 Ammonia concentration profles in the SWS
www.eptq.com PTQ Q3 2012 89
ogrt.indd 5 1/6/12 17:27:49
percentage points across the whole
column.
Effect of stripper pressure
From time to time, one hears it
stated that higher stripper pressures
favour sour water stripping, so we
decided to put this old wives tale
to the test. Table 2 shows the effect
of column head pressure in residual
ammonia and H
2
S levels in stripped
water for the same process confgu-
ration and sour water composition
shown in Figure 1 and Table 1,
respectively. The simulated
performance corresponds to a steam
rate of 25 000 lb/h of 50 psig steam
(1.40 lb/USgal) with the cross
exchanger set to a temperature
approach of 20F to minimise the
effect of temperature differences
across the stripping section. The
table shows that, contrary to anec-
dote, higher pressure has a negative
(albeit relatively small) effect on
water quality with respect to
ammonia, but can cause an 80-fold
increase in residual H
2
S content of
the stripped water under these
conditions. Higher pressures do not
seem to favour ammonia stripping,
and they certainly have a negative
effect on stripped water quality vis-
-vis H
2
S.
Summary
Perhaps the most important
message of this article is that genu-
ine mass transfer rate-based
modelling allows the construction
of a virtual plant on a computer.
There is no reliance on what might
be termed fudge factors to
achieve agreement between calcula-
tions and reality.
A mass transfer rate-based sour
water stripper model provides a
virtual sour water stripper on a
computer. Engineers can now
design sour water stripper units
with unprecedented accuracy and
reliability. Plant operations person-
nel can answer a wide range of
what-if questions to troubleshoot
operations and to optimise existing
units with complete confdence in
the results.
After overall tray effciencies,
Murphree vapour effciencies are
probably the most commonly used
type of effciency for tray calcula-
tions. Overall effciencies are an
invention of the 1920s, developed
to allow ideal stage distillation
calculations to approximate reality
more closely, and as 90-year-old
technology they have served the
distillation business well. However,
the whole equilibrium-stage
approach was superseded by mass
transfer rate calculation methods in
the mid- to late 1980s, already more
than 25 years ago. The gas treating
industry deals with far more
complex separations processes than
1 5
0
5
1 0
2 0
2 5
3 0
3 5
4 0
1 0 0 5 0 0 5 0 1 0 0 1 5 0
T
r
a
y
n
u
m
b
e
r
f
r
o
m
t
o
p
NH
3
eff i ci ency
0 . 7 8 lb ste a m / U S g a l.
F e e d tra y
1 5
0
5
1 0
2 0
2 5
3 0
3 5
4 0
5 2 0 4 0 6 0 8 0 1 0 0
T
r
a
y
f
r
o
m
t
o
p
NH
3
eff i ci ency
0 . 9 2 lb ste a m / U S g a l.
F e e d tra y
Figure 5 Murphree vapour effciencies for ammonia at low steam rates
1 0
5
1 5
2 0
2 5
3 0
3 5
0 5 1 0 1 5 2 0 2 5 3 0
T
r
a
y
n
u
m
b
e
r
f
r
o
m
t
o
p
Ammoni a i n vapour, mol e%
4 0
y* n )
y n )
M a x im u m a t y 1 2 )
M a x im u m a t y* 1 3 )
F e e d tra y
Figure 6 Actual and equilibrium ammonia concentrations in the vapour phase at low
steam rates
90 PTQ Q3 2012 www.eptq.com
ogrt.indd 6 1/6/12 17:28:05
distillation, but, unfortunately, it
has been remarkably slow to catch
on to the new technology. Genuine
mass transfer rate-based simulation
is an extremely powerful tool in gas
treating.
There are several other messages
that pertain directly to sour water
stripping:
H
2
S effciency varies enormously
from tray to tray throughout a sour
water stripper, and the Murphree
effciency is a very sensitive func-
tion of the steam-to-sour-water
fow rate ratio. Any attempt to
generalise H
2
S component eff-
ciency is utterly futile because of
its huge variation from only a few
per cent to 50% across a column
and its dependency on the particu-
lar operating conditions of each
unique situation
With respect to effciencies perti-
nent to H
2
S stripping, the tray count
and the steam required depend
heavily on the treated water specif-
cations to be met. Thus, the designer
is faced with really quite a diffcult
decision more trays and more
stripping energy lead to lower eff-
ciency. What and where is the
balance? Should one use more or
less steam, and more or fewer
trays? These effects cannot be
accounted for with an ideal stage
model, even when it uses effciency.
The process appears to be too
complex to generalise into rules of
thumb
At stripping steam rates in the
lower half of the normal range used
in practice, it is quite possible for
the ammonia concentration in a
sour water stripper to show an
enormous bulge or maximum in
some part of the stripping section
well away from the ends. At this
bulge, the sour water stripper
changes from acting as an ammonia
stripper to an ammonia absorber.
When (and where) the bulge occurs,
there is a high enough H
2
S concen-
tration in the liquid to attract
ammonia into the water phase and
hold it there chemically. Again,
ideal stage models even with eff-
ciency do not show this kind of
behaviour, and they can lead to
either gross overdesign or to a
complete mis-design, depending on
the relative H
2
S and ammonia
concentrations in the sour water
feed
Murphree vapour effciencies for
ammonia in sour water strippers
operating at low to moderate strip-
ping steam rates can vary from
large negative values to positive
values well over 100%. At high
stream rates, on the other hand,
Murphree vapour effciencies for
ammonia stripping are typically
35% to 40%. This huge variation
depending on steam rate and H
2
S-
to-NH
3
ratio may go a long way
towards explaining the wide range
of 15% to 45% overall effciency
often quoted by practitioners
Contrary to a commonly repeated
anecdote, higher stripper pressures
do not favour better ammonia strip-
ping, and they certainly do not
favour H
2
S stripping where a factor
of 80 loss in performance was
predicted, even for the setup in this
study.
In conclusion, this article has
pointed out several aspects of sour
water stripping that either do not
seem to have been recognised here-
tofore, or that offer solid scientifc
explanations for previously observed
and reported characteristics.
ProTreat is a registered mark of Optimized Gas
Treating Inc.
References
1 Stevens D Mosher A, Ogg D, Fundamentals
of sour water stripping, Brimstone Sulfur
Recovery Symposium, Vail, CO, Sept 2007.
2 Hauser R, Kirkey R T, Refnery tests
demonstrate fxed valve trays improve
performance in sour water stripper, AIChE
Spring National Meeting, 31 Mar 2003, New
Orleans, LA T1-2E.
3 Quinlan M P, Hati A A, Processing NH
3
acid
gas in a sulphur recovery unit, Proceedings
of the 2010 Laurance Reid Gas Conditioning
Conference, Norman, OK.
4 Asquith J, Moore A, sour water processing
balancing needs, Proceedings of the 2000
Brimstone Sulphur Recovery Symposium, Vail,
CO.
5 Weiland R H, Sivasubramanian M S, Dingman
J C, Effective amine technology: controlling
selectivity, increasing slip and reducing sulphur,
Laurence Reid Gas Conditioning Conference,
Norman, OK, 2003.
6 Weiland R H, Dingman J C, Column design
using mass transfer rate simulation, Laurence
Reid Gas Conditioning Conference, Norman,
OK, 2001.
7 Gantz R G, Sour water stripper operations,
API Special Report, Hydrocarbon Processing,
May 1975, 83.
8 Murphree E V, Graphical rectifying column
calculations, Ind. Eng. Chem., 17, 1925, 747-
750 and 960-964.
9 Taylor R, Kooijman H, ChemSep Tutorial:
Effciencies, www.chemsep.com/downloads/
docs/ChemSepTutori al_Effi ci enci es. pdf,
downloaded 4 Jan 2012.
10 Deshmukh R D, Mather A E, A Mathematical
model for equilibrium solubility of hydrogen
sulphide and carbon dioxide in aqueous
alkanolamine solutions, Chem. Eng. Sci., 36,
1981, 355-362.
11 Hatcher N A, Weiland R H, Special
treatment, Hydrocarbon Engineering, Jan 2012.
Ralph Weiland began working in gas treating
as a graduate student in 1965 and has been
an active researcher in this feld ever since.
He received BASc, MASc and PhD degrees in
chemical engineering from the University of
Toronto. He taught chemical engineering for
30 years at universities in Canada, Australia
and the US, and spent 10 years doing mass
transfer tray development with Koch-Glitsch
LP in Dallas, TX. He established Optimized Gas
Treating in 1992.
Email: ralph.weiland@ogtrt.com
Nathan Hatcher joined Optimized Gas
Treating, Buda, Texas, as Vice-President,
Technology Development, in 2009. He has
spent almost his entire career in amine
treating and sulphur recovery, and has
extensive experience in the practical
application of process simulation to
operations, troubleshooting and training.
He holds a BS in chemical engineering from
the University of Kansas and is currently a
member of the Amine Best Practices Group.
Email: nate.hatcher@ogtrt.com
Stripper head pressure, psig Treated water
Ammonia, ppmw H
2
S, ppmw
10 17.2 0.00002
15 21.1 0.00013
20 26.0 0.00058
25 31.5 0.00197
Effect of stripper pressure on residual NH
3
and H
2
S levels in stripped water
Table 2
www.eptq.com PTQ Q3 2012 91
ogrt.indd 7 1/6/12 17:28:21
sulzer.indd 1 1/6/12 16:12:23
Monitoring and treatment to maximise
light cycle oil
C
urrent global trends in prod-
uct demand favour the
increasing production of
diesel fuel over motor gasoline
because the demand growth for
middle distillate fuels has exceeded
the demand growth for gasoline for
some time.
2
In fact, the US is now a
net exporter of refned petroleum
products (mostly middle distillates)
for the frst time since 1949.
3
Furthermore, the demand for gaso-
line from refneries has declined
due to increases in the average fuel
economy and the use of renewable
fuels.
5
Decline in gasoline demand
5
in
the US resulted in a reduction in
refnery capacity, particularly in
PADD I (East Coast), which
increased cost sensitivities through-
out the US refning market. US
demand for propylene continues to
rise at a rapid pace because steam
crackers are switching to ethane
feeds, and propylene and diesel
continue to command a price
premium over most other refned
products.
8
These changes in product
demand mix and market over-
capacity have resulted in refners
focusing on increasing middle
distillate production with minimal
additional capital and operational
costs.
The question many refners are
now facing is how can existing refn-
ery assets be used to economically
increase diesel and propylene
production. Refners have many
options to increase middle distillate
and propylene production.
Unfortunately, many of the options
have signifcant negative conse-
quences or additional capital costs.
Changes in operation are often
Fouling control, simulation software and tower scanning can improve operations
and reliability when maximising middle distillate and propylene production
GREG SAVAGE
Nalco
constrained by existing equipment
limitations, and changing the prod-
uct mix can reveal new bottlenecks.
2
Capital investment options
Crude distillation units and delayed
coker units have some fexibility to
increase distillate production, but
are constrained by feed slate and
mechanical limitations. Most US
refneries only have two to fve
trays between the fash zone and
the distillate draw, which results in
less precise distillate cuts. In
contrast, European refneries that
are historically optimised for diesel
production may have 10 to 14 trays
in the same zone to ensure good
separation. Some US refners are
now adding distillate draws on
vacuum towers to maximise distil-
late production and limit the
amount of distillate sent to the FCC
unit, which is chiefy designed for
the production of gasoline and will
convert middle distillate-range feed
to lighter products.
2
Most US refners have invested in
a FCC unit as their main conversion
technology. Changes in operation,
catalyst and feed can optimise the
FCC unit for distillate production.
Increasing diesel in a FCC unit is
challenging, in part because FCC
light cycle oil (LCO) has limited
value as a blend stock for diesel
fuel due to its aromatic, sulphurous
character and because it requires
further hydrotreating before
blending.
6
Construction of new hydrocrack-
ers, which provide increased
fexibility over FCC units and
better-quality gasoline and distillate
products, is ongoing but slow due
to relatively high capital costs and
the resulting increased hydrogen
demand. Tighter sulphur specifca-
tions along with the increased
processing of higher-sulphur feeds
and the rise in production of high-
sulphur intermediate products such
as LCO are increasing the demand
on hydrodesulphurisation units
www.eptq.com PTQ Q3 2012 93
3 0 0 0
5 0 0 0
4 0 0 0
2 0 0 0
1 0 0 0
0 1 0 2 0 3 0 4 0 5 0
N
H
3
i
n
a
c
c
u
m
u
l
a
t
o
r
,
p
p
m
Chl ori de i n accumul at or, ppm
0
2 5 5 C
2 3 5 C
C u rre n t sa lt 2 6 5 . 5 C
2 4 5 C
Figure 1 NH
4
CI salt formation isotherms
nalco.indd 1 1/6/12 20:58:32
94 PTQ Q3 2012 www.eptq.com
main fractionator towers are partic-
ularly sensitive to salt fouling
because of low temperature and
relatively high concentration of
ammonia (NH
3
) and hydrogen chlo-
ride (HCl) in the overhead system.
An increase in P at the main frac-
tionator at both units can reduce
wet gas compressor capacity and
therefore limit the throughput. An
increase in P across the FCC units
main fractionator increases the
pressure in the reactor and in the
regenerator, which can limit air
blower capacity and coke burn, as
well as the production of propyl-
ene.
1
Therefore, the control of
chlorides into the distillation
columns as well as frequent model-
ling of the salt potential and salt
formation temperature are essential
in adjusting distillation column cut
points. Control of chlorides into the
distillation columns can be accom-
plished through good desalting at
the crude distillation unit and the
injection of caustic downstream of
the desalter. Optimisation of caustic
and neutraliser injections through
automation can reduce the chloride
levels in the crude atmospheric
columns and overhead systems
while minimising the risk of down-
stream impacts such as sodium
poisoning of the FCC catalyst.
Continuous use of salt-dispersant
technologies, controlled on the basis
of salt formation potential, normal-
ised P across the top section of
distillation columns and the heat
transfer modelling of pumparound
exchangers, minimises the risk of
salt fouling by moving deposits out
of the column into the heavy naph-
tha or middle distillate streams.
1
Distillation column scanning
Straight-run middle distillates left
in the FCC gas oil feed are
converted to lower-valued products
during FCC processing. Also, carry-
over of heavy gas oil into the
straight-run middle distillate prod-
uct draw will impact the cold-fow
properties of the eventual distillate
blend.
2
Consequently, exact control
and excellent operation of the distil-
lation columns are necessary for
optimising the production of high-
quality diesel while minimising
downstream impacts. Distillation
(HDS).
4
Moreover, increasing olefn
production at the FCC unit
increases the fouling potential for
downstream HDS units, which can
be controlled with appropriate anti-
foulant additives. HDS capacity is
often a bottleneck for the refnery,
particularly when optimising for
distillate and propylene production.
Therefore, there is a greater poten-
tial for HDS preheat fouling and a
larger associated economic penalty.
Changing cut points
The most common strategy for
increasing diesel production is to
adjust cut points between the naph-
tha and middle distillate draws in
the crude, FCC and coker units.
Often, changes in the cut points are
accomplished by reducing fraction-
ator tower top temperatures. This
reduction will increase ammonium
chloride (NH
4
Cl) salting potential.
Figure 1 shows a plot of ammo-
nium chloride salt deposition
isotherms from a typical FCC unit
on the Gulf Coast, which was
generated using Nalco Pathfnder
simulation software. The plot
demonstrates that the lower the
temperature, the less ammonia and
chloride are necessary to create salt.
Similarly, Figure 2 shows a plot of
overhead temperature versus salt
formation temperature and salting
potential from a typical Gulf Coast
FCC unit, but with constant ammo-
nia and chloride levels. This plot
shows that a 6F reduction in over-
head temperatures can result in
nearly three times the salting poten-
tial. Changes in tower pressure,
overhead temperature or concentra-
tion of amines, ammonia and
chloride alter partial pressures and
therefore salt potential.
Salt deposits in towers and pump-
arounds can result in under-deposit
corrosion and the generation of
corrosion by-product deposits. These
deposits may plug trays in the top
and mid-sections of the tower,
partially or completely block the
heavy naphtha and middle distillate
product draws, as well as severely
limit the pumparound rates and
heat removal from the tower.
Performance of pumparound
exchangers can be modelled using
heat transfer simulation software.
The build-up of salt deposits in trays
can increase the P across the top
section of the tower. Uncontrolled
fouling has resulted in tray fooding,
evidenced by a rapid and signifcant
increase in P, which can have a
negative impact on the fractionation
effciency between gasoline and
middle distillate.
1
The FCC unit and delayed coker
Figure 2 NH
4
CI deposition potential
6 0
5 0
4 0
3 0
2 0
1 0
2 7 8 2 8 0 2 8 2 2 8 4 2 8 6 2 8 8 2 9 0 2 9 2 2 9 4
D
e
p
o
s
i
t
i
o
n
p
o
t
e
n
t
i
a
l
,
p
o
u
n
d
s
p
e
r
d
a
y
3 0 6
3 0 8
3 0 4
3 0 2
3 0 0
2 9 8
2 9 6
2 9 4
F
o
r
m
a
t
i
o
n
t
e
m
p
e
r
a
t
u
r
e
,
F
Fract i onat or overhead t emperat ure, F
0
N H
4
C
1
fo rm a tio n te m p e ra tu re
N H
4
C
1
fo rm a tio n p o te n tia l
Salt deposits in towers
and pumparounds
can result in under-
deposit corrosion
and the generation of
corrosion by-product
deposits
nalco.indd 2 2/6/12 17:56:40
EUROPE - MIDDLE EAST - AFRICA
TEL: +33 5 4902 1600
saleseurope@johnsonscreens.com
AUSTRALIA - ASIA PACIFIC
TEL: +61 7 3867 5555
salesasiapacifc@johnsonscreens.com
www.johnsonscreens.com
JAPAN
TEL: +81 55 997 8511
sales.jpn@johnsonscreens.co.jp
NORTH, SOUTH & CENTRAL AMERICA
TEL: +1 651 636 3900
hpisalesnsa@johnsonscreens.com
J ohnson Screens
Scallop
OptiMiser
Scallop
CONTACT US!
Catalytic Reforming
Styrene Monomer
Dehydrogenation
Ammonia Conversion
Mercury Removal
Sulphur Units
Gas Treatment...
Many low pressure processes use Johnson Screens
Find relevant industry events worldwide.
Read news items focusing on contracts,
company news and new products.
dig ref.indd 1 24/2/12 13:30:07
The winning catalyst combination
for your hydrocracker
Single source lSC 9001 lSC 14001 CHSAS 18001
www.axens.net
HRK, HDK, HK series: the expert trio to maximize
cycle length, activity and middle distillates selectivity
Hydro_cats_ad_fin.indd 1 26/7/11 12:35:06
axens.indd 1 8/3/12 10:17:04
International Conference: 18 20 September, 2012, Amsterdam
Best-in-Class Operations and Maintenance
Strategies for Chemicals and Petrochemicals
Regi st er o n l i n e at :
www.tacook.com/amsterdam
Featuring leading
experts from:
BASF
Bayer Technol ogy
Servi ces
BP Chemi cal s
Ce c
Cl ariant Produkt e
INEOS
Manuf act uri ng
Nat i onal Ski l l s
Academy f or
Process Indust ri es
SABIC
Manuf act uri ng
T.A. Cook
Consul t ant s
Pre-conference workshop, 18th September, 2012
Successf ul ly Managi ng your Operat ions and Mai nt enance Programme t o Enhance
Overal l Pl ant Per f ormance and Product ivit y
Featuring Best Practices on Executing World Class Operations and Maintenance:
Id e n t i f y i n g a l o n g t e r m m ai n t e n an ce st r at egy t o su ccessf u l l y m an age m at u r e asse t s an d e n su r e o p e r at i o n al e f ci e n c y
Im p l e m e n t i n g a r i sk b ase d i n sp e c t i o n p r o gr am m e i n o r d e r t o r e d u ce m ai n t e n an ce ex p e n d i t u r e w h i l st m ai n t ai n i n g
r e l i ab i l i t y an d av ai l ab i l i t y at agei n g p l an t s
A n al y si n g t h e co st i m p ac t o f ad o p t i n g n ew m ai n t e n an ce ap p r o ac h e s an d st r at egi e s
Bu i l d i n g a r o b u st an d e e c t i v e co n t r ac t o r m an age m e n t st r at egy
O p t i m i si n g t h e t u r n ar o u n d p r o ce ss t o d e c r ease d o w n t i m e, i n c r ease sh u t d o w n i n t e r v al s an d e n h an ce o v e r al l p l an t
p e r f o r m an ce
Maximising your Operational Ef ciency, Reliability & Availability
Supported By:
Who Should Attend?
Th i s e v e n t w i l l e n su r e t h at y o u h av e acce ss t o ex t e n si v e c ase st u d i e s b y m aj o r i n d u st r y p l ay e r s, p r o m p t d i sc u ssi o n o n co m m e r c i al l y
r e l e v an t t o p i c s, an d p r o v i d e y o u w i t h t h e o p p o r t u n i t y t o exc h an ge an d b e n c h m ar k b e st p r ac t i c e w i t h f e l l o w at t e n d e e s. Th e
e v e n t w i l l b e o f i n t e r e st t o o r gan i sat i o n al l ead e r s w i t h i n t h e ar eas o f :
Pl an t / Si t e M an age m e n t
O p e r at i o n s an d M ai n t e n an c e
En gi n e e r i n g an d Pr o d u c t i o n
A sse t an d Re l i ab i l i t y M an age m e n t
Tu r n ar o u n d / Tu r n ar o u n d St r at e g y
Pr o j e c t M an age m e n t
Th i s e v e n t i s al so d e si gn e d f o r t h e O EM & t h i r d p ar t y m ar ke t s an d w i l l b e o f i n t e r e st t o t h o se w i t h i n t h e ar eas o f :
O p e r at i o n s an d M ai n t e n an c e
St r at e g y an d M an age m e n t
Pr o j e c t s an d Te c h n i c al Pe r f o r m an c e
Sal e s, M ar ke t i n g an d Bu si n e ss D e v e l o p m e n t
Te c h n i c al Sal e s an d M ar ke t i n g
Supported By:
O p e r at o r s o f c h e m i c al an d p e t r o c h e m i c al p l an t s i n
Eu r o p e n o w n d t h e m se l v e s u n d e r c o n si d e r ab l e p r e s-
su r e t o m ai n t ai n c o m m e r c i al l y su c c e ssf u l o p e r at i o n s.
Gi v e n t h e e c o n o m i c u n c e r t ai n t y i n t h e Eu r o zo n e, r i si n g
e n e r g y c o st s, d e m an d sh i f t t o A si a, an d t h e e m e r ge n c e
o f m o r e co m p e t i t i v e f e e d st o c k r e gi o n s, i t i s m o r e i m p o r-
t an t t h an e v e r f o r p r o d u c e r s t o i m p l e m e n t an e f c i e n t
an d co st e e c t i v e o p e r at i o n s an d m ai n t e n an c e st r at e g y.
W e ar e d e l i gh t e d t o i n v i t e y o u t o t h i s t i m e l y co n f e r e n c e
o n Best-in-Class Operations & Maintenance Strategies
for Chemicals and Petrochemicals. O u r t w o d ay age n d a
i s d e si gn e d t o gi v e y o u t h e o p p o r t u n i t y t o l ear n r st - h an d
f r o m p l an t o p e r at o r s, w h o w i l l sh ar e t h e i r ex p e r i e n c e s
i n i m p l e m e n t i n g b e st - i n - c l ass O & M st r at e gi e s an d t h e i r
ap p r o ac h e s t o m axi m i se o p e r at i o n al e f ci e n c y. In ad d i t i o n ,
h ear f r o m i n d u st r y t h o u gh t l ead e r s t o gai n an u n d e r st an d -
i n g o f m ar ke t u c t u at i o n s an d t r e n d s t o e n ab l e y o u t o
r e m ai n c o m p e t i t i v e an d st ay ah e ad o f t h e c u r v e . Take
ad v an t age o f t h e n e t w o r k i n g o p p o r t u n i t i e s b u i l t i n t o t h i s
ev e n t , t o m ake u sef u l co n t ac t s an d b u i l d l ast i n g co n n e c t i o n s.
Feat u r i n g b e st p r ac t i c e s o n :
M ap p i n g o u t e e c t i v e st r at e gi e s t o st r eam l i n e y o u r
o p e r at i o n s an d d e v e l o p a su st ai n ab l e m ai n t e n an c e
p r o gr am m e
Gai n i n g v al u ab l e t i p s o n i m p l e m e n t i n g an i n t e gr at e d
m ai n t e n an c e m e t h o d o l o g y ac r o ss y o u r p r o d u c t i o n
e e t
U si n g p l an t d o w n t i m e s e e c t i v e l y t o e x t e n d p l an t
l i f e an d p r o t e c t age i n g asse t s
A n al y si n g t h e n an c i al i m p ac t o f y o u r m ai n t e n an c e
ap p r o ac h i d e n t i f y i n g h o w y o u c an c o n t r o l y o u r
co st s, w i t h o u t a e c t i n g p e r f o r m an c e
Em b e d d i n g r o b u st KPIs t o al l o w y o u t o e e c t i v e l y
m easu r e an d m o n i t o r p e r f o r m an c e
D e v e l o p i n g an d r o l l i n g o u t an e e c t i v e c o n t r ac t o r
m an age m e n t st r at e g y
Pl u s j o i n t h e d i sc u ssi o n ! Take ad v an t age o f o u r i n t e r ac-
t i v e p an e l d i sc u ssi o n t o w e i gh u p t h e p r o s an d c o n s o f
o u t so u r c i n g m ai n t e n an c e ac t i v i t i e s.
En su r e t h at y o u ar e i n t h e b e st p o ssi b l e p o si t i o n t o ex-
e c u t e e f c i e n t , r e l i ab l e an d c o st e e c t i v e f u t u r e p l an t
o p e r at i o n s b y at t e n d i n g t h i s e v e n t . W e l o o k f o r w ar d
t o w e l co m i n g y o u an d y o u r co l l eagu e s t o A m st e r d am .
Yo u r s si n c e r e l y,
Thomas Cook
M an agi n g D i r e c t o r
T.A . Co o k Co n f e r e n c e s
P.S. Jo i n u s o n W e d n e sd ay 19 t h Se p t e m b e r, af t e r
t h e r st d ay o f t h e c o n f e r e n c e f o r o u r e v e n i n g e v e n t .
N e t w o r k i n a r e l axe d at m o sp h e r e an d sh ar e y o u r t h o u gh t s
f r o m t h e d ay s p r e se n t at i o n s w i t h y o u r i n d u st r y co l l eagu e s.
Fo r m o r e i n f o r m at i o n p l e ase v i si t w w w .t ac o o k .c o m /
am st e r d am
Dear Colleague
Workshop Leaders:
David Fleming, Senior Consultant,
T.A. Cook Consultants
Af t e r i n i t i al l y sp e n d i n g t i m e as an e n gi n e e r i n t h e st e e l i n d u st r y,
Dav i d m ad e t h e t r an si t i o n i n t o e l e c t r o n i c s i n t h e 19 9 0 s w o r k i n g
f o r a n u m b e r o f b l u e c h i p o r gan i sat i o n s, as an En gi n e e r, W o r k
Pr o c e ss Sp e c i al i st , an d as an I n t e r n al Co n su l t an t . H i s f o c u s w as
v e r y m u c h t o w ar d s t h e m an age m e n t o f p r o j e c t s t h at i m p r o v e d
p r o d u c t i v i t y an d r e d u c e d u n i t c o st s, w h i l st e n su r i n g a c o n t i -
n u o u s i m p r o v e m e n t , e n v i r o n m e n t an d c u l t u r e.
Si n ce Dav i d e n t e r e d co n su l t an c y, h e h as b e e n i n v o l v e d i n p e r f o r m an ce i m p r o v e m e n t
p r o j e c t s p ar t i c u l ar l y f o c u si n g o n d ay t o d ay m ai n t e n an c e, i n sp e c t i o n an d t u r n a-
r o u n d s, w h e r e h i s r e sp o n si b i l i t i e s h av e r an ge d f r o m sp e c i c w o r k ar eas, t o o v e r al l
p r o j e c t m an age m e n t . Th i s h as t ake n h i m ac r o ss Eu r o p e an d N o r t h A m e r i c a, an d h e
h as ex p e r i e n ce d b o t h t h e u p st r eam an d d o w n st r eam si d e o f t h e o i l an d gas i n d u st r y.
Successfully Managing your Operations and
Maintenance Programme to Enhance Overall
Plant Performance and Productivity
Th i s f u l l - d ay i n t e r ac t i v e w o r k sh o p w i l l p r o v i d e y o u w i t h a co m p r e h e n si v e r ev i ew i n t o
o p t i m i si n g t h e m ai n t e n an c e an d o p e r at i o n s p r o c e ss. I d e n t i f y an d d e n e t h e go al s
o f a su cc e ssf u l O & M p r o gr am m e, d i sco v e r h o w e e c t i v e y o u r o w n m ai n t e n an c e
st r at e g y i s an d l ear n t h e i m p o r t an c e o f d e v e l o p i n g a h eal t h y o n - si t e c u st o m e r-
c o n t r ac t o r r e l at i o n sh i p . Yo u w i l l h av e t h e o p p o r t u n i t y t o sh ar e l e sso n s l ear n e d
w i t h f e l l o w d e l e gat e s i n an i n t i m at e e n v i r o n m e n t t o e n su r e t h e saf e, r e l i ab l e an d
e f c i e n t o p e r at i o n s o f y o u r p r o d u c t i o n f ac i l i t y.
Gai n f u r t h e r i n si gh t s i n t o :
Est ab l i sh i n g y o u r o w n go al s w h e n i t co m e s t o su cc e ssf u l O & M m an age m e n t
D e n i n g w h at c an m ake m ai n t e n an c e e e c t i v e an d w h e r e i m p r o v e m e n t s
ar e co n t i n u o u s , as w e l l as su st ai n ab l e
D i sco v e r i n g h o w t h e su cc e ssf u l m an age m e n t o f O & M r e so u r c e s an d t ask s c an
h e l p i m p r o v e o v e r al l p e r f o r m an c e an d p r o d u c t i v i t y
D e v e l o p i n g an d m ai n t ai n a h eal t h y o n si t e c u st o m e r- co n t r ac t o r r e l at i o n sh i p t o
ac h i e v e O & M exc e l l e n c e
U n d e r st an d i n g w h y ac t i v e su p e r v i si o n c an i m p r o v e y o u r p r o d u c t i v i t y
I d e n t i f y i n g t h e i m p o r t an c e o f i m p l e m e n t i n g an e e c t i v e l ead e r sh i p an d
m an age m e n t p r o gr am m e
Th e w o r k sh o p o e r s an exce l l e n t o p p o r t u n i t y f o r p r o f e ssi o n al s w i t h a b ac k gr o u n d
i n o p e r at i o n s, m ai n t e n an c e o r e n gi n e e r i n g t o m e e t w i t h f e l l o w i n d u st r y ex p e r t s
Pre-conference Workshop
Tuesday, 18 September, 2012
This full-day workshop will run from 9:30 a.m. to 4:30 p.m. with refreshments and lunch
provided
t o ad d r e ss y o u r o w n O & M i ssu e s, b r ai n st o r m n e w ap p r o ac h e s as w e l l as sh ar e
y o u r o w n ex p e r i e n c e s an d b e st p r ac t i c e s. Take aw ay n e w i d eas an d ap p r o ac h e s i n
o r d e r t o e st ab l i sh y o u r o w n h i gh l y e e c t i v e O & M st r at e g y, t o e n su r e f u l l b u si n e ss
o p t i m i sat i o n .
Workshop Agenda:
Identifying the goal of successful O&M management
W h at i s o p e r at i o n s & m ai n t e n an c e m an age m e n t ?
W h at ar e y o u l o o k i n g t o ac h i e v e?
How efective is your maintenance strategy?
W h at m ake s an e e c t i v e m ai n t e n an c e p h i l o so p h y?
M ai n t ai n i n g e q u i p m e n t r e l i ab i l i t y - t h e co n t i n u o u s c y c l e
The successful tendering and management of contractors on-site
D e v e l o p i n g an d m ai n t ai n i n g a h eal t h y c u st o m e r- co n t r ac t r e l at i o n sh i p
I m p l e m e n t i n g a sh ar e d ap p r o ac h t o O & M exc e l l e n c e
The process of managing resources and tasks
E e c t i v e w o r k p r e p ar at i o n an d f o r w ar d p l an n i n g
Pl an t h e w o r k , w o r k t h e p l an
Active supervision is key to productivity improvement
W h at m ake s an e e c t i v e su p e r v i so r?
W h at ar e t h e i r ke y ar eas o f f o c u s, d u r i n g a t y p i c al d ay?
O&M: Leadership, management and motivation
Th e i m p o r t an c e o f m an age m e n t sy st e m s an d co n t r o l
W h at ar e t h e Ke y Pe r f o r m an c e I n d i c at o r s?
David Woods, Senior Consultant,
T.A. Cook Consultants
Dav i d st ar t e d h i s c ar e e r as a M e r c h an t N av y O f c e r, p r i o r
t o w o r k i n g as a Q u an t i t y Su r v e y o r i n t h e c o n st r u c t i o n
i n d u st r y. H e e n t e r e d c o n su l t i n g i n t h e e ar l y 19 9 0 s an d
h as b e e n i n v o l v e d i n p e r f o r m an c e i m p r o v e m e n t p r o j e c t s
ac r o ss Eu r o p e i n i n d u st r i e s as d i v e r se as i gh t c at e r i n g ,
sh i p b u i l d i n g an d f ac i l i t i e s m an age m e n t .
H i s r e sp o n si b i l i t i e s h av e r an ge d f r o m Pr o j e c t M an age m e n t t o Exe c u t i v e D ev e l o p -
m e n t an d h e h as h e l d se n i o r m an age m e n t p o si t i o n s w i t h l ead i n g co n su l t an c i e s
i n t h e U S an d Eu r o p e . Si n c e j o i n i n g T.A . Co o k i n 20 0 6 , Dav i d h as sp e c i al i se d
i n t h e ar e as o f t u r n ar o u n d an d asse t m an age m e n t . H i s r e sp o n si b i l i t i e s as a
Pr o j e c t M an age r an d Tu r n ar o u n d Tr ai n e r h av e m ai n l y f o c u se d o n m ai n t e n an ce
an d sh u t d o w n m an age m e n t .
Registration and Refreshments
Chairmans Opening Remarks
Dav i d W o o d s, Se n i o r Co n su l t an t , T.A . Co o k Co n su l t an t s
Adapting to a Fluctuating Global Chemical and Petrochemicals Market Short Term Prospects and Long Term Predictions
Ev al u at i n g h o w t h e c u r r e n t co m m e r c i al c l i m at e h as i m p ac t e d an d i s i m p ac t i n g t h e c h e m i c al an d p e t r o c h e m i c al i n d u st r y
A n al y si n g t h e i n u e n c e o f n e w co m p e t i t i v e m ar ke t s t h e M i d d l e East & A si a
Su p p l y an d d e m an d m o v e m e n t s asse ssi n g t h e c u r r e n t p r o d u c t i o n c ap ac i t y i n Eu r o p e
M ar ke t t r e n d s, c h al l e n ge s an d f u t u r e gr o w t h o p p o r t u n i t i e s
Re gu l at o r y t r e n d s an d f u t u r e p r e d i c t i o n s f o r Eu r o p e
Pi e r r e D e Ke t t e n i s, Exe c u t i v e D i r e c t o r, CEFI C Pe t r o c h e m i st r y Pr o gr am m e (A PPE)
BASF Antwerps Journey Towards Achieving On-Site O&M Excellence
Su cc e ssf u l l y m o n i t o r i n g O & M p e r f o r m an c e an d p r o c e sse s at o u r f ac i l i t y i m p l e m e n t i n g O & M KPI s
A cc u r at e l y m easu r i n g t h e e e c t i v e n e ss o f l ead i n g p e r f o r m an c e i n d i c at o r s
En su r i n g a co st co m p e t i t i v e ap p r o ac h t o si t e O & M
Ri sk Base d M ai n t e n an c e (RBM ) e st ab l i sh i n g co st e e c t i v e n e ss an d m ac h i n e u p t i m e
H e r m an Bae t s, Te c h n i c al Go v e r n an c e M an age r, BA SF A n t w e r p
Morning Refreshments
Ensuring the Successful Management and Reliability of Ageing Components within Day-to-Day Plant Operations
Fac i n g t h e i n c r ease d m ai n t e n an c e b u r d e n o f age i n g p l an t s i m p l e m e n t i n g a l o n g- t e r m m ai n t e n an c e st r at e g y
D e gr ad at i o n o f m ac h i n e r y co r r o si o n u n d e r i n st al l at i o n (p i p e s, p u m p s an d f u r n ac e p ar t s)
M e c h an i c al an d asse t i n t e gr i t y m an age m e n t
M ai n t ai n i n g o p e r at i o n al e f c i e n c y an d ke e p i n g co st s d o w n KPI s
Ri sk Base d M ai n t e n an c e (RBM ) co m p o n e n t r e l i ab i l i t y an d h eal t h & saf e t y co n si d e r at i o n s (CO M A H )
O r gan i sat i o n al m an age m e n t o f c h an ge i n m ai n t e n an c e
Ge o r ge s M ad e ssi s, Li l l o Si t e M an age r, I N EO S M an u f ac t u r i n g
Networking Lunch
Asset Life Cycle Management and Risk Based Inspection (RBI) Achieving Reliability & Availability, Reduced Shutdowns
and Increased Turnaround Intervals at Bayer
Fac i n g t h e i n c r ease d i n sp e c t i o n c h al l e n ge o f age i n g asse t s q u al i t at i v e v s. q u an t i t at i v e r i sk an al y si s
H o w RBI l ead s t o t ar ge t e d , sp e c i c i n sp e c t i o n p l an s, an al y si n g t h e p o t e n t i al d am age m e c h an i sm s
Co r r o si o n st u d y an d r i sk b ase d i n sp e c t i o n f o r xe d e q u i p m e n t , p i p i n g an d saf e t y v al v e s
Th e i m p ac t o f RBI t o t u r n ar o u n d d u r at i o n , i n t e r v al s, o r gan i sat i o n an d co st
Ch r i st o s Ch r i st o gl o u , H ead o f Ri sk Base d I n sp e c t i o n A sse ssm e n t (RBIA ) G r o u p , Bay e r Te c h n o l o g y Se r v i c e s
A Fleet Overview Implementing Best-in-Class Operations & Maintenance (O&M) Strategies and the Ef ective Management of
Mature Assets
A n i n t r o d u c t i o n t o o u r e e t
W o r k i n g t o w ar d s ac h i e v i n g b e st - i n - c l ass O & M st r at e gi e s, c h al l e n ge s an d O & M p h i l o so p h y
Est ab l i sh i n g a r e l i ab l e ap p r o ac h t o t h e m an age m e n t o f age i n g p r o d u c t i o n f ac i l i t i e s
I n t e gr at i n g m ai n t e n an c e m e t h o d o l o gi e s ac r o ss t h e p e t r o c h e m i c al s e e t as a w h o l e e n su r i n g o p e n l i n e s o f co m m u n i c at i o n
Co n t r ac t i n g st r at e gi e s i n t h e c u r r e n t co m m e r c i al c l i m at e t h e r i sk s an d r e w ar d s o f O EM v s t h i r d p ar t y v s i n - h o u se m ai n t e n an c e
Sp eake r t o b e co n r m e d
Afternoon Refreshments
Closing Speaker Panel - Analysing New Maintenance Approaches and Strategies for the Chemicals and Petrochemicals
Industry: In-House Operations and Maintenance Teams vs Outsourcing
W h at i s o n o e r at t h e m o m e n t i n t e r m s o f m ai n t e n an c e st r at e gi e s an d ap p r o ac h e s?
D e t e r m i n i n g t h e st r e n g t h s an d w eak n e sse s o f i n - h o u se m ai n t e n an c e p r o gr am m e s:
Re gai n i n g co n t r o l o v e r v i t al sy st e m s an d p r o c e sse s
Fl ex i b i l i t y, av ai l ab i l i t y an d q u al i t y o f w o r k
D o i n - h o u se m ai n t e n an c e t eam s h e l p p r o d u c e r s e st ab l i sh l o n g- t e r m su cc e ss, as w e l l as a co m p e t i t i v e e d ge?
E e c t i v e m an age m e n t o f p r o b l e m at i c co n t r ac t o r s
Th e n an c i al i m p ac t s o f i n so u r c i n g an d o u t so u r c i n g
Feat u r i n g ke y sp eake r s f r o m ac r o ss t h e co n f e r e n c e
Chairmans Closing Remarks and Close of Day One
9.00
9.30
9.45
10.45
1 1.35
12.00
12.50
14.00
14.50
15.50
16.20
17.15
Day One
Wednesday, 19 September, 2012
8.30
9.00
9.10
10.00
10.50
11.20
12.10
13.20
14.10
14.30
15.15
16.00
Registration and Refreshments
Chairmans Opening Remarks and Welcome Back
Dav i d W o o d s, Se n i o r Co n su l t an t , T.A . Co o k Co n su l t an t s
Executing an Ef ective Maintenance Strategy to Maximise Operational Output Decreasing Downtime, Improving Reliability and
Reducing Costs
Re o r gan i sat i o n o f t h e si t e an d co m p an y m ai n t e n an c e st r at e g y : i n so u r c i n g & / o r o u t so u r c i n g b ase d o n c r i t i c al i t y o f sk i l l s an d k n o w - h o w
D e n i n g & i m p l e m e n t i n g an e e c t i v e m ai n t e n an c e p r o c e ss:
N o t i c at i o n an d gat e ke e p i n g
Pl an n i n g , exe c u t i o n an d w o r k o r d e r c l o su r e
Est ab l i sh i n g su cc e ssf u l p e r f o r m an c e m an age m e n t i n c r easi n g t h e p r o d u c t i v i t y o f t h e m ai n t e n an c e t eam , sc h e d u l e o p t i m i sat i o n an d r e d u c i n g co st s
I n t r o d u c i n g a r e l i ab i l i t y f o c u s gr o u p
Ph i l i p M o r e l , T.A . Co o k Co n su l t an t s
Implementing an Holistic Energy Ef ciency Programme on a Global Level to Achieve Sustainable Operations
Bu i l d i n g a co m p r e h e n si v e e n e r g y e f c i e n c y p r o gr am m e f r o m sc r at c h an d ac h i e v i n g su cc e ssf u l o n - si t e i m p l e m e n t at i o n
A p p l y i n g an i n t e gr at e d ap p r o ac h t o su st ai n ab i l i t y an d o p e r at i o n al exc e l l e n c e
En su r i n g su cc e ss b y e m b e d d i n g e n e r g y e f c i e n c y i n t o t h e o p e r at i o n s an d m i n d se t o f t h e co m p an y
Pr o j e c t r e v i e w m easu r ab l e r e su l t s an d c h al l e n ge s
D r. H e r b e r t M ai e r, H ead o f G l o b al Co m p e t e n c e Ce n t r e En e r g y & U t i l i t i e s, Cl ar i an t Pr o d u k t e
Morning Refreshments
Accurately Identifying the Scope of Turnarounds and Routine Maintenance Activity: Achieving Financial Optimisation and
Sustaining Ef cient Operations
Se l e c t i n g a su cc e ssf u l m ai n t e n an c e ap p r o ac h co r r e c t i v e, p r e d i c t i v e an d p r e v e n t i v e m ai n t e n an c e :
Pl an n i n g an d sc h e d u l i n g t e c h n i q u e s: Pr i m av e r a/ SA P p l an n i n g t o o l s an d i m p l e m e n t i n g a l o n g- t e r m ap p r o ac h t o m ai n t e n an c e sc h e d u l i n g
Co n si d e r i n g t h e n an c i al i m p ac t o f m ai n t e n an c e d e c i si o n s u n d e r st an d i n g / m i n i m i si n g t h e n an c i al i m p ac t o f m ai n t e n an c e st r at e gi e s:
A cc u r at e l y i d e n t i f y i n g k n o w n / e st i m at e d co st s an d t h e m o n e t ar y i m p ac t o f r i sk
Re n i n g t h e f r e q u e n c y, sco p e an d d u r at i o n o f t u r n ar o u n d s d e v e l o p i n g t h e o p t i m u m co m b i n at i o n
Ke v i n M c Q u i l l an , Sp e c i al Pr o j e c t s D i r e c t o r, SA BI C M an u f ac t u r i n g
Networking Lunch
Optimising Turnarounds to Strategically Combat the Challenge of Ageing Assets and to Enhance Future Plant Operations
A n i n t r o d u c t i o n t o t h e sh u t d o w n ke y i n t e gr i t y & r e l i ab i l i t y d r i v e r s
Sh u t d o w n exc e l l e n c e an d su cc e sse s d e l i v e r i n g t h e p r o j e c t o n t i m e an d t o b u d ge t :
Fr o n t e n d l o ad i n g t o c u t p l an t d o w n t i m e
H o w sh u t d o w n s c an b e u se d st r at e gi c al l y t o ex t e n d p l an t l i f e
Tu r n ar o u n d m an age m e n t st a & co n t r ac t o r s
Tar i q M i r za, Eu r o p ean A c e t y l Tu r n ar o u n d M an age r, BP Ch e m i c al s
Afternoon Refreshments
Building a Robust and Ef ective Contractor Management Strategy to Achieve Overall O&M Success
H o w d o y o u m ai n t ai n a se c u r e an d h eal t h y r e l at i o n sh i p w i t h y o u r co n t r ac t o r?
En su r i n g st r i n ge n t q u al i t y m easu r e s ar e p u t i n p l ac e an d m e t b y co n t r ac t o r s se r v i c e l ab e l agr e e m e n t s (SLA )
I m p l e m e n t i n g an i n t e gr at e d ap p r o ac h t o O & M exc e l l e n c e
En f o r c i n g a r o b u st saf e t y c u l t u r e w i t h i n t h e O & M o f p e t r o c h e m i c al si t e s m ai n t ai n i n g co n t r ac t o r saf e t y o n si t e
Sp eake r t o b e co n r m e d
Implications of an Ageing Workforce Attracting and Securing Future Generations of O&M Professionals
Th e r e c l i n i n g r e so u r c e p o o l h o w i s t h e i n d u st r y b e i n g a e c t e d ?
W h at i s b e h i n d t h e gr o w i n g d e c l i n e i n n e w o p e r at i o n s an d m ai n t e n an c e st a ?
H o w ar e w e w o r k i n g t o w ar d s se c u r i n g a sk i l l e d l ab o u r f o r c e?
Li v e ex am p l e s o f e e c t i v e so l u t i o n s
Fu t u r e p r e d i c t i o n s f o r t h e c h e m i c al an d p e t r o c h e m i c al i n d u st r i e s
Cl i n t o n D e v i n e, D o w n st r eam A cco u n t M an age r, N at i o n al Sk i l l s A c ad e m y f o r Pr o c e ss I n d u st r i e s
Chairmans Closing Remarks and Close of Conference
Day Two
Thursday, 20 September, 2012
Co m p an y
A d d r e ss
Po st co d e
Co u n t r y
I n v o i c e A d d r e ss (i f d i e r e n t f r o m ab o v e):
P.O . N o . (i f ap p l i c ab l e)
Po st co d e
Co u n t r y
M ai n co n t ac t f o r t h i s b o o k i n g
Te l e p h o n e
Em ai l
Si gn at u r e
Fu l l n am e
Jo b Ti t l e
Te l e p h o n e
Em ai l
Fu l l n am e
Jo b Ti t l e
Te l e p h o n e
Em ai l
Pr i c e i n c l u d e s e l e c t r o n i c d o c u m e n t at i o n , l u n c h , r e f r e sh m e n t s an d an e v e n i n g
e v e n t f o r c o n f e r e n c e p ar t i c i p an t s. Pl e ase n o t e t h at ac c o m m o d at i o n an d t r av e l
ar e n o t i n c l u d e d i n t h e r e gi st r at i o n f e e.
Plant owners and petrochemical producers:
Early Bird* * Standard Fee
Conference: 975 * 1190*
Full day workshop: 590* 690*
Service providers and consultancies:
Early Bird* * Standard Fee
Conference: 1190* 1490*
Full day workshop: 590* 690*
* p l u s 19 % D u t c h VAT
* * Ear l y Bi r d d i sc o u n t v al i d u n t i l 27t h Ju l y , 20 12
D i sco u n t s ar e av ai l ab l e f o r p e t r o c h e m i c al an d c h e m i c al p l an t o p e r at o r s an d gr o u p
b o o k i n gs. Pl ease co n t ac t u s f o r f u r t h e r d e t ai l s.
Fax: +44 (0) 121 212 1623
O r r e gi st e r o n l i n e at :
www.tacook.com/amsterdam
Pre - Conference Workshop 18 September, 2012
Two day conference 19 - 20 September, 2012
Pre - Conference Workshop 18 September, 2012
Two day conference 19 - 20 September, 2012
I will attend
U n f o r t u n at e l y I am u n ab l e t o at t e n d t h e e v e n t .
Pl ease se n d m e t h e e v e n t d o c u m e n t at i o n at 350 (n o VAT )
To r e gi st e r f o r t h i s e v e n t p l ease f ax t h i s r e gi st r at i o n f o r m t o :
Fees & Payments
Methods of Payment
Venue & Accommodation
How To Get There
Conference Organisers
Cr e d i t Car d . Pl ease d e b i t m y : M ast e r c ar d V i sa A m ex
Car d N o :
Ex p i r y Dat e : Se c u r i t y N o :
Car d h o l d e r s N am e :
Si gn at u r e :
Ch e q u e Ban k Tr an sf e r Pay m e n t u p o n r e ce i p t o f t h e i n v o i ce
Pay m e n t m u st b e r e c e i v e d BEFO RE t h e co n f e r e n c e
Dorint Hotel
A m st e r d am A i r p o r t , St at i o n sp l e i n , ZW 9 51
A m st e r d am , N L- 1117 - CE Sc h i p h o l O o st
Th e N e t h e r l an d s
Te l : +31 (0 )20 5 4 0 0 7 7 70
Fr o m A m st e r d am Sc h i p o l I n t e r n at i o n al A i r p o r t , t h e h o t e l i s a 10 m i n u t e t ax i r i d e
aw ay. Th e r e i s al so a f r e e sh u t t l e b u s av ai l ab l e, d e p ar t i n g e v e r y 10 m i n u t e s t o t h e
h o t e l b e t w e e n 0 6 .0 0 - 23.45. If y o u ar e d r i v i n g p l ease u se t h e f o l l o w i n g ad d r e ss f o r
y o u r sat e l l i t e n av i gat i o n sy st e m : St at i o n sp l e i n ZW 9 51, H aar l e m m e r m e e r.
T.A. Cook Conferences Ph o n e +4 4 (0 ) 121 20 0 38 10
4t h Fl o o r, M c Lar e n Bu i l d i n gs Fax +4 4 (0 ) 121 212 1623
4 6 Th e Pr i o r y Q u e e n sw ay Em ai l i n f o @t aco o k .co m
Bi r m i n gh am W e b w w w .t aco o k .co m
B4 7LR
Pl ease t i c k t h e b o x i f y o u w i sh t o b e r e m o v e d f r o m o u r m ai l i n g l i st .
(w h e n d o i n g so p l ease w r i t e y o u r n am e ab o v e)
Best-in-Class Operations and Main-
tenance Strategies for Chemicals and
Petrochemicals
Maximising your Operational Ef ciency, Reliability and Availability
18-20 September, 2012, Amsterdam, Netherlands
T.A . Co o k Co n su l t an t s Lt d . VAT r e gi st e r e d i n En gl an d , N o . 78 149 578 8
D at a Pr o t e c t i o n : Pe r so n al d at a i s gat h e r e d i n ac c o r d an c e w i t h t h e D at a Pr o t e c t i o n A c t 19 9 8 . Can -
c e l l at i o n s A l l c an c e l l at i o n s h av e t o b e c o n r m e d i n w r i t i n g. Can c e l l at i o n s t w o w e e k s p r i o r t o t h e
b e gi n n i n g o f t h e c o n f e r e n c e w i l l e n t i t l e y o u t o a r e f u n d l e ss 20 0 ad m i n i st r at i o n f e e . Re gr e t t ab l y ,
n o r e f u n d s c an b e m ad e f o r c an c e l l at i o n s r e c e i v e d l e ss t h an t w o w e e k s p r i o r t o t h e e v e n t . Sh o u l d
t h e r e gi st e r e d p e r so n n o t b e ab l e t o at t e n d t h e e v e n t y o u m ay e asi l y assi gn an o t h e r p e r so n as a
r e p l ac e m e n t . O r gan i se r s Ch an ge s: W e r e se r v e t h e r i gh t t o m ake al t e r at i o n s t o t h e p r o gr am m e
i f n e c e ssar y . I t m ay b e n e c e ssar y f o r r e aso n s b e y o n d t h e c o n t r o l o f t h e o r gan i se r s t o al t e r t h e
c o n t e n t s an d t h e t i m i n g o f t h e p r o gr am m e o r t h e i d e n t i t y o f t h e sp e ake r s. Th e o r gan i se r r e se r v e s
t h e r i gh t t o c an c e l i n t h e e v e n t o f an i n su f c i e n t n u m b e r o f d e l e gat e s.
C
o
n
f
e
r
e
n
c
e
C
o
d
e
:
P
e
t
1
_
1
2