Gantt Chart and Project Management
Gantt Chart and Project Management
The assignment
Your team is expected to produce a Gantt chart and to keep it up to date for use in managing your project.
Gantt charts are an effective planning tool for organizing your effort and intelligently allocating resources
and personnel. Use MS Project (available in ME computer studio) to produce your chart. Why MS
Project? Because it is the most widely used project planning package in industry and you should be
learning how to use "real world" tools.
Tasks are activities that must be completed to achieve the project goal. Break the project into small tasks
and subtasks. Tasks have start and end points, are short relative to the project and are significant (not
"going to library", but rather, "search literature"). Shorter tasks are easier to track and manage than long
tasks. For our 14 week project, no individual task should be longer than one week. Use verb-noun form
for naming tasks, e.g. "create drawings" or "build prototype". Use action verbs such as "create", "define"
and "gather" rather than "will be made". Each task has a time duration. It can be very difficult to estimate
durations accurately. Doubling your best guess usually works well. Allow some contingency time for
unexpected events (10-25%).
Milestones are important checkpoints or interim goals for a project. They can be used to catch scheduling
problems early. Name by noun-verb form, e.g. "report due", "parts ordered", "prototype complete". Your
plan will evolve so be flexible and update on a regular basis. It also helps to identify risk areas for project,
for example, things you don't know how to do but will have to learn. These are risky because you may not
have a good sense for how long the task will take. Or, you may not know how long it will take to receive
components you purchased for a project.
Est
WBS Task
Person Who Resources M&S
# Description
-Hrs
5 Profile motor power
5.1 Design test stand 20 SE, JM Pro/E
5.2 Build test stand 15 SE, JM Frame & brake parts $35
5.3 Test 3 motors 3 SE, JM Stroboscope $75
5.4 Plot torque vs. speed 2 JM Excel
In a Gantt chart, each task takes up one row. Dates run along the top in increments of days, weeks or
months, depending on the total length of the project. The expected time for each task is represented by a
horizontal bar whose left end marks the expected beginning of the task and whose right end marks the
expected completion date. Tasks may run sequentially, in parallel or overlapping.
As the project progresses, the chart is updated by filling in the bars to a length proportional to the fraction
of work that has been accomplished on the task. This way, one can get a quick reading of project progress
by drawing a vertical line through the chart at the current date. Completed tasks lie to the left of the line
and are completely filled in. Current tasks cross the line and are behind schedule if their filled-in section
is to the left of the line and ahead of schedule if the filled-in section stops to the right of the line. Future
tasks lie completely to the right of the line.
In constructing a Gantt chart, keep the tasks to a manageable number (no more than 15 or 20) so that the
chart fits on a single page. More complex projects may require subordinate charts which detail the timing
of all the subtasks that make up one of the main tasks. For team projects, it often helps to have an
additional column containing numbers or initials which identify who on the team is responsible for the
task. Group the tasks under major headings that correspond to the steps in the design process, such as:
Problem Definition, Project Planning, Gathering Information, Conceptual Design, Concept Selection, Detail
Design, Implementation, Testing, Documentation, etc.
Often the project has important events that you would like to appear on the project timeline, but which are
not tasks. For example, you may wish to highlight when a prototype is complete or the date of a design
review. You enter these on a Gantt chart as "milestone" events and mark them with a special symbol,
often an upside-down triangle.
Gantt charts made with Excel are easy to update and maintain. Here's how to do it.
On a piece of scrap paper or a chalk board, make a list of tasks and assign each task tentative start and
stop dates (or durations) and the people responsible for the task. Also list important milestones and their
dates. If you have more than 15 or 20 tasks, split your project into main tasks and subtasks, then make an
overall Gantt chart for the main tasks and separate Gantt charts for the subtasks which make up each main
task.
Decide what resolution to use in the timeline. For projects of three months or less, use days, for longer
projects use weeks or months, and for very short project use hours. For these instructions, we will assume
you have chosen a resolution of days.
Set up the cells. You can use the sample (found elsewhere on this web page) as a guide. Use the border
command to draw boxes around the appropriate cells. Enter your scheduling data. To make the gray bars
which indicate length of task, select the appropriate cells, then the fill command (one of the buttons near
the top).
As the project progresses, fill in the gray bars with black to denote the fraction of a task that is complete.
To embed a Project Gantt chart into a Word document, get the chart showing on the screen, then Edit >
Copy Picture... > to GIF file. From there you can import the gif file into Word. You may have to rotate it
90 degrees in MS Paint to get it to fit and be readable.