Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

TP9

Download as pdf or txt
Download as pdf or txt
You are on page 1of 53

Construction and testing of marine

bridge foundation
By
Sing-lok CHIU, AECOM
Zheng-ru Fang, CHEC Construction (M) Sdn Bhd (CHEC)

Shi-jing, LIU, China Habour Engineering Company Ltd (CHEC)

Presented by Dr SL Chiu
AECOM, Hong Kong

29 November 2012

Page 1

Contents
Background of bored pile foundation
Construction bored pile foundation
Quality assurance testing of production piles
Loading tests on the trial and production piles
Test results
Conclusion

29 November 2012

Page 2

Background of Bored pile foundation


Main Bridge over navigation channel- supported on 4
piers- P24 to P27- by 66 bored piles , 2m in diameter,
socketted 2 to 6m in (Granite) bedrock
Approach bridge at eastern end- supported on 10
piers- P283 to P292- by 80 bored piles, 1.5m in
diameter, socketted 5 to 8m in (SHALE) bedrock

29 November 2012

Page 3

2nd Penang Bridge under construction

P24 TO P27

P283 TO P292

29 November 2012

Page 4

Main Span: Cablestayed bridge


117.5m

117.5m

240 m

150m x 30m

Pier P24

12-pile group

29 November 2012

Pier P26

Pier P25

21-pile group

21-pile group

Page 5

Pier P27

12-pile group

Approach bridge

55m

2x 4-pile group

29 November 2012

2x 4-pile group

Page 6

2x 4-pile group

Geological conditions

29 November 2012

Page 7

Layout of bored piles


Main span piers

Approach bridge piers

(117.5 m + 240+117.5 m )

7000 mm

15, 240 mm

8 x 1.5m bored piles


117,500 mm

12 2.0m
bored piles
29 November 2012

21 2.0m
bored piles
Page 8

(55m apart)

Construction of bored piles


Approach bridge piers

Main span piers

2.3 m

40 m

Protective casing in soft


marine mud

20 m

Slurry-supported bored hole


2.0 m

2 to 6 m

Toe-socketted in Grade
III or better bedrock

Grade III Granite

29 November 2012

1.8 m

1.5 m

5 to 8 m

Grade III Shale

Page 9

Engineering properties of slurry for the bore pile works


Slurry Density

<1.25g/cm3

PH-Value

7 to 12

Viscosity in Marsh
32 to 60 s
Funnel seconds
<4% (during drilling)
Sand content
<2% (after drilling)

29 November 2012

Page 10

Reinforcement details
Pier numbers

Main Bridge

Approach bridge

Steel Cage

P24-P27

P283-P292

Top Section

36m (L)
44T32 (M)
T16x150 (B)

34m (L)
36T32 (M)
T12x 150(B)

Middle section

36m (L)
44T32 (M)
T16x150 (B)

24m (L)
18T32 (M)
T12x200 (B)

Bottom section

Various (L)
22T32 (M)
T16x300 (B)

Various (L)
9T32 (M)
T12x 300 (B)

(L) Length, (M) Main reinforcements,


(B) Spiral binder

29 November 2012

Page 11

Concreting to marine bored piles


Cement grout to cleanse
sediments at the pile base
prior to concreting

Concrete batching plants to


produce Grade 40/20 concrete
for bored piles

Concrete mixing plant on site and a temporary platform for piling works

29 November 2012

Page 12

Quality assurance testing of bored piles


Interface coring
Cross hole sonic logging
Load testing
Maintained load test (MLT)
Statnamic test

29 November 2012

Page 13

Interface coring
To carry out on every production bored pile

To verify the workmanship of piling work


To take core sample through the pile base
To inspect the concrete quality
To measure the core length against the core run for
any missing material

29 November 2012

Page 14

4 x 50mm
Access tubes

2 x 100mm access tubes

Access tubesinterface coring


sonic logging

4 x 50mm
Access
tubes

29 November 2012

Page 15

200 mm

Perforated section
250 mm

2 x 100mm
access
tubes

Interface coring (contd)

Typical core sample from interface


coring through a production pile

29 November 2012

Page 16

Interface coring (contd)


Minor imperfection at
the interface

29 November 2012

Page 17

Cross-hole Sonic logging (CSL)


The quality of the shaft concrete
of the bored pile was checked
using CSL to the ASTM D6760.
6 access tubes in total provided
to each of the production bored
piles, 4 of them 50 mm in
diameter and the other two 100
mm
2 x 100mm
access tubes

Extracted from FHWA report


FHWA-CFL/TD-05-007 on Drilled shaft
foundation defects, October 2005

4 x 50mm
Access tubes

29 November 2012

Page 18

Cross-hole Sonic logging (CSL), contd


Cross Hole AnalyzerTM (CHA) systemthe equipment employed for CSL in
this project

Typical site set up for CSL


testing

29 November, 2012

Page 19

Defects identification by CSL


Principlesound wave velocity and
energy may change as it
traverses through
material of different
densities
MeasurementsFirst arrival time (FAT)
Energy reduction (ER)

Typical CSL results- Water fall diagram


29 November, 2012

Page 20

Defects identification by CSL, contd

29 November, 2012

Page 21

CSL field operation


- with CHA system

Transmission
probe
Receiver
probe

29 November, 2012

Page 22

CSL- Results interpretation, contd


Class

Characteristics

Good Pile
First Arrival Time (FAT) and Energy Profiles are regular. Pile is good

Minor Anomaly
Some delay in FAT on the test profiles. Still within acceptable limits. Pile is
questionable

Major Anomaly
Two or more test profiles indicate major delay in FAT at similar depths.
Corresponding low energy curves observed. Pile is poor quality or flawed.

Defective Pile
Two or more test profiles having a total loss in FAT and corresponding
loss in energy curves. Pile is defective

The acceptance criteria for production bored piles subjected to CSL tests

29 November, 2012

Page 23

Repair to defects in Class III and IV


Two methods were proposed by contractor:

Method A- suitable for defected areas at shallow or


intermediate depths
involving use of reverse circulation drill to form access
hole to the defective area and hack off the defects in
concrete and re-cast the defected areas with sound
concrete.
Method B- suitable for defected areas at all depths
involving sinking of a series of drillholes to the defective
areas and cleansing of the defected areas by high
pressure water jet and filling out the affected areas with
high strength grout.
29 November, 2012

Page 24

RCD to form access to


defected areas in pile

Method A

High pressure (40 MPa


max) water jet blasting to
hack off the defective
concrete

29 November, 2012

Page 25

Repair to defects in Class III and IV

High pressure water


jet blasting to hack off
the defective concrete

Fill out the


cleansed area
with sound
concrete

RCD to form access to


defected areas in pile

29 November, 2012

Page 26

Method B

125 mm @ 300 mm c/cspaced access holes are


sunk to defected areas

29 November, 2012

Concrete cutting nozzle to


deliver high pressure water jet to
hack off the defective concrete

Page 27

CCTV to inspect the


cleansed area before
grouting

Loading Tests
Pile- pier No

L2P285

BHT 12P292

BHT9P25

Trial pileP25

diameter

1.5M

1.5m

2.0m

2.0m

Pile length (m)

106.4

89.5

125.1

115.07

Socket length (m)

6.3 m

2.06 m

8m

4.32 m

Rock Type

MD
SHALE

HD SHALE

S to MD S to MD
GRANITE GRANITE

Type of load test

ST

MLTtop
ST
loaded

MLT with O-cell in


socket

20MN

38MN

maximum test load 23MN

29 November, 2012

Page 28

50 MN

Testing methods

pile head

Maintained Load test


O-cell method

-8.50m
-9.95msea bed

2.3m

Trial pile at Pier 25


Pile dimensions:
Diameter: 2.3m to 2.0m
Length: 115.07m
Socket: 4.32m in M to S DG

115.07m

2.0m

112.75m

-38.50m

Upper plate of load cell

Loading method- embedded load cell

0.44m

Load cell
1.88m

lower plate of load cell

-121.69m

-123.57m
level of pile toe

29 November, 2012

Page 29

O-cell method

data
displacement transducers
acquisition
reference beam
system
hydraulic pump with
pressure gauge

oil pipe
shaft
side
shear

steel telltale rods


telltale casings
load cell

shaft end bearing

29 November, 2012

Page 30

Instrumentation of the test bored pile


5 hydraulic jacks of
a maximum stroke
of 200mm

Type

YG56510025

Access of tell-tale rods


to bottom plate

Outer
Diameter of Upper plate Lower plate
diameter
Cylinder
thickness
thickness
(mm)
(mm)
(mm)
(mm)
1800

29 November, 2012

500

40

Page 31

40

Height
(mm)

max. stroke
(mm)

440

220

Instrumentation of the test bored pile

TGCL-1
Vibrating wire type strain
gauge
Operational range: 2500
Resolution: 0.4 ~ 1
Waterproof 150m under
water
Temperature: -20 to 80
29 November, 2012

WDL-50TZ
Linear Variable
Differential
Transformer (LVDT)
displacement
transducers

Page 32

19

20

21

refrence pile 1

Layout of testing platform


refrence beam

P25 test pile

Reference pile 2

Unitmm

29 November, 2012

Page 33

Instrumentation of the test bored pile

6 LVDT displacement transducers were installed,


namely
2 for upward movements of the top plate of load cell
2 for downward movements of the bottom plate of
load cell
2 for upward movements of the pile head.
29 November, 2012

Page 34

Vibrating wire type


strain gauges
Tell tale access

O-Cell

29 November, 2012

Page 35

Test Results

29 November, 2012

Page 36

Test results (contd)

38101 kN

32.24 mm

Equivalent load settlement curve for the test pile


subjected to equivalent head down loading
29 November 2012

Page 37

Test results (contd)

Shaft friction of P25

Axial forcekN
0

10000

20000

30000

20

-20

50

100

estimated

measured

60

6689
8332
9974
11617
13260
14902
16545
18187
19830

-40

Depth in m

depthm

40

-60

80

-80

100

-100

120

-120

29 November 2012

Page 38

Max shaft resistance, fs in kPa

150

Maintained Load Test

0.0m

1.8m

-top-loaded method

SPT-N Value

Marine Clay
-22.4m

Test pile No. BHT12 @ Pier 292


Pile dimensions:
Diameter: 1.8m to 1.5m
Length: 89.5m
Socket: 2.06m in HD SHALE
The test pile was equipped with strain
gauges and extensometers thus the
settlement of the pile base and
shortening the pile shaft as well as
the load transfer along the pile shaft
could be measured

Alluvial silty sand

Grade V Shale
Grade IV Shale
-88.8m
1.5m

29 November, 2012

Page 39

Maintained load test- set up

Top-loaded method

29 November, 2012

Page 40

Maintained load testset up


7 x 5000kN
hydraulic jacks
Pressure
synchroniser

29 November, 2012

Page 41

Test results of MLT on the Bored Pile BHT12 @ Pier 292

Pile base settlement vs Load

Pile top settlement vs Load

29 November, 2012

Page 42

Test results of MLT on the Bored Pile BHT12 @ Pier 292, contd

Cycle 1

Cycle 2 End of test

Test load, kN

16001

19943

S top (mm)

81.42

113.92

94.27

S base(mm)

59.78

86.89

84.65

Shaft
shortened, mm

21.64

27.03

9.62

Load distribution along pile shaft


29 November, 2012

Page 43

Statnamic load test


Test pile No. L2 @ Pier 285
Pile dimensions:
Diameter: 1.8m to 1.5m
Length: 106.4m
Socket: 6.3 m in MD SHALE

Test pile No. BHT9 @ Pier 25


Pile dimensions:
Diameter: 2.3m to 2.0m
Length: 125.1m
Socket: 8.0 m in SD GRANITE

29 November, 2012

Page 44

Statnamic Test set-up


Testing cylinder

silencer

Gravel container
Cylinder

Reaction masses

Load cell and laser


sensor housing

piston

Piston mounting
frame

Test pile

29 November, 2012

Extracted from the test report on pile L2-P285 by


Geonamic for CHEC on 29 July 2011 ( ref: DIR 11810)

Page 45

Statnamic Test set-up

Extracted from the test report on pile L2-P285 by Geonamic for CHEC on 29 July 2011 ( ref: DIR 11810)

29 November, 2012

Page 46

Statnamic load test

Extracted from the test report on pile L2-P285 by Geonamic for CHEC on 29 July 2011 (ref: DIR 11810)

29 November, 2012

Page 47

Typical output of test results of Statnamic load test

29 November, 2012

Page 48

Test results of Statnamic load test on the tested bored piles

29 November, 2012

Page 49

Test results of Statnamic load test on the tested bored Pples

Load vs Displacement (top)


Load vs Time (bottom)

29 November, 2012

Load vs Time (top)


Load vs Displacement (bottom)

Page 50

Force, displacement, velocity and


acceleration against time plots

Summary of test results


Ratio
fs/v

of

Clay

P292BHT12
MLT

P25-9
Statnamic

P25- Trial
O-cell

0.08

0.14

0.074

Medium
dense silty 0.09
Sand

P25-9
Statnamic

0.04-0.05
0.145

Dense silty
0.11
Sand

0.03-0.05

CD Granite

0.04

CD Shale

0.12

Remarks

Top-loaded tests- pile pile pushed up by


head moving Downward
o-cell from below

29 November, 2012

P25-Trial
O-cell

Page 51

Maximum
mobilised
920 kPa
skin friction
in SDG

941 kPa

Concluding Remarks
1. The works were fraught with difficulties and challenges given the
soft clay layer below seabed underlain by subsequent layers of
medium dense to dense silty sand above the rock head at a great
depth over 100 m.
2. The production piles were subjected to various types of quality
assurance checks:
a) Interface coring for existence of any imperfections at pile base
b) CSL for scanning the integrity of the shaft concrete
3. For those piles that were found containing imperfections, high
pressure water jet and subsequent backfilling of pressurised
cement grout were applied to rectify the defects and imperfections
in the piles
4. Different types of load tests were carried out on trial piles and
production piles for determination of design parameters and for
quality insurance check of the quality of the bridge foundation.
29 November, 2012

Page 52

Thank You

29 November, 2012

Page 53

You might also like