TP9
TP9
TP9
bridge foundation
By
Sing-lok CHIU, AECOM
Zheng-ru Fang, CHEC Construction (M) Sdn Bhd (CHEC)
Presented by Dr SL Chiu
AECOM, Hong Kong
29 November 2012
Page 1
Contents
Background of bored pile foundation
Construction bored pile foundation
Quality assurance testing of production piles
Loading tests on the trial and production piles
Test results
Conclusion
29 November 2012
Page 2
29 November 2012
Page 3
P24 TO P27
P283 TO P292
29 November 2012
Page 4
117.5m
240 m
150m x 30m
Pier P24
12-pile group
29 November 2012
Pier P26
Pier P25
21-pile group
21-pile group
Page 5
Pier P27
12-pile group
Approach bridge
55m
2x 4-pile group
29 November 2012
2x 4-pile group
Page 6
2x 4-pile group
Geological conditions
29 November 2012
Page 7
(117.5 m + 240+117.5 m )
7000 mm
15, 240 mm
12 2.0m
bored piles
29 November 2012
21 2.0m
bored piles
Page 8
(55m apart)
2.3 m
40 m
20 m
2 to 6 m
Toe-socketted in Grade
III or better bedrock
29 November 2012
1.8 m
1.5 m
5 to 8 m
Page 9
<1.25g/cm3
PH-Value
7 to 12
Viscosity in Marsh
32 to 60 s
Funnel seconds
<4% (during drilling)
Sand content
<2% (after drilling)
29 November 2012
Page 10
Reinforcement details
Pier numbers
Main Bridge
Approach bridge
Steel Cage
P24-P27
P283-P292
Top Section
36m (L)
44T32 (M)
T16x150 (B)
34m (L)
36T32 (M)
T12x 150(B)
Middle section
36m (L)
44T32 (M)
T16x150 (B)
24m (L)
18T32 (M)
T12x200 (B)
Bottom section
Various (L)
22T32 (M)
T16x300 (B)
Various (L)
9T32 (M)
T12x 300 (B)
29 November 2012
Page 11
Concrete mixing plant on site and a temporary platform for piling works
29 November 2012
Page 12
29 November 2012
Page 13
Interface coring
To carry out on every production bored pile
29 November 2012
Page 14
4 x 50mm
Access tubes
4 x 50mm
Access
tubes
29 November 2012
Page 15
200 mm
Perforated section
250 mm
2 x 100mm
access
tubes
29 November 2012
Page 16
29 November 2012
Page 17
4 x 50mm
Access tubes
29 November 2012
Page 18
29 November, 2012
Page 19
Page 20
29 November, 2012
Page 21
Transmission
probe
Receiver
probe
29 November, 2012
Page 22
Characteristics
Good Pile
First Arrival Time (FAT) and Energy Profiles are regular. Pile is good
Minor Anomaly
Some delay in FAT on the test profiles. Still within acceptable limits. Pile is
questionable
Major Anomaly
Two or more test profiles indicate major delay in FAT at similar depths.
Corresponding low energy curves observed. Pile is poor quality or flawed.
Defective Pile
Two or more test profiles having a total loss in FAT and corresponding
loss in energy curves. Pile is defective
The acceptance criteria for production bored piles subjected to CSL tests
29 November, 2012
Page 23
Page 24
Method A
29 November, 2012
Page 25
29 November, 2012
Page 26
Method B
29 November, 2012
Page 27
Loading Tests
Pile- pier No
L2P285
BHT 12P292
BHT9P25
Trial pileP25
diameter
1.5M
1.5m
2.0m
2.0m
106.4
89.5
125.1
115.07
6.3 m
2.06 m
8m
4.32 m
Rock Type
MD
SHALE
HD SHALE
S to MD S to MD
GRANITE GRANITE
ST
MLTtop
ST
loaded
20MN
38MN
29 November, 2012
Page 28
50 MN
Testing methods
pile head
-8.50m
-9.95msea bed
2.3m
115.07m
2.0m
112.75m
-38.50m
0.44m
Load cell
1.88m
-121.69m
-123.57m
level of pile toe
29 November, 2012
Page 29
O-cell method
data
displacement transducers
acquisition
reference beam
system
hydraulic pump with
pressure gauge
oil pipe
shaft
side
shear
29 November, 2012
Page 30
Type
YG56510025
Outer
Diameter of Upper plate Lower plate
diameter
Cylinder
thickness
thickness
(mm)
(mm)
(mm)
(mm)
1800
29 November, 2012
500
40
Page 31
40
Height
(mm)
max. stroke
(mm)
440
220
TGCL-1
Vibrating wire type strain
gauge
Operational range: 2500
Resolution: 0.4 ~ 1
Waterproof 150m under
water
Temperature: -20 to 80
29 November, 2012
WDL-50TZ
Linear Variable
Differential
Transformer (LVDT)
displacement
transducers
Page 32
19
20
21
refrence pile 1
Reference pile 2
Unitmm
29 November, 2012
Page 33
Page 34
O-Cell
29 November, 2012
Page 35
Test Results
29 November, 2012
Page 36
38101 kN
32.24 mm
Page 37
Axial forcekN
0
10000
20000
30000
20
-20
50
100
estimated
measured
60
6689
8332
9974
11617
13260
14902
16545
18187
19830
-40
Depth in m
depthm
40
-60
80
-80
100
-100
120
-120
29 November 2012
Page 38
150
0.0m
1.8m
-top-loaded method
SPT-N Value
Marine Clay
-22.4m
Grade V Shale
Grade IV Shale
-88.8m
1.5m
29 November, 2012
Page 39
Top-loaded method
29 November, 2012
Page 40
29 November, 2012
Page 41
29 November, 2012
Page 42
Test results of MLT on the Bored Pile BHT12 @ Pier 292, contd
Cycle 1
Test load, kN
16001
19943
S top (mm)
81.42
113.92
94.27
S base(mm)
59.78
86.89
84.65
Shaft
shortened, mm
21.64
27.03
9.62
Page 43
29 November, 2012
Page 44
silencer
Gravel container
Cylinder
Reaction masses
piston
Piston mounting
frame
Test pile
29 November, 2012
Page 45
Extracted from the test report on pile L2-P285 by Geonamic for CHEC on 29 July 2011 ( ref: DIR 11810)
29 November, 2012
Page 46
Extracted from the test report on pile L2-P285 by Geonamic for CHEC on 29 July 2011 (ref: DIR 11810)
29 November, 2012
Page 47
29 November, 2012
Page 48
29 November, 2012
Page 49
29 November, 2012
Page 50
of
Clay
P292BHT12
MLT
P25-9
Statnamic
P25- Trial
O-cell
0.08
0.14
0.074
Medium
dense silty 0.09
Sand
P25-9
Statnamic
0.04-0.05
0.145
Dense silty
0.11
Sand
0.03-0.05
CD Granite
0.04
CD Shale
0.12
Remarks
29 November, 2012
P25-Trial
O-cell
Page 51
Maximum
mobilised
920 kPa
skin friction
in SDG
941 kPa
Concluding Remarks
1. The works were fraught with difficulties and challenges given the
soft clay layer below seabed underlain by subsequent layers of
medium dense to dense silty sand above the rock head at a great
depth over 100 m.
2. The production piles were subjected to various types of quality
assurance checks:
a) Interface coring for existence of any imperfections at pile base
b) CSL for scanning the integrity of the shaft concrete
3. For those piles that were found containing imperfections, high
pressure water jet and subsequent backfilling of pressurised
cement grout were applied to rectify the defects and imperfections
in the piles
4. Different types of load tests were carried out on trial piles and
production piles for determination of design parameters and for
quality insurance check of the quality of the bridge foundation.
29 November, 2012
Page 52
Thank You
29 November, 2012
Page 53