EA in Biscuit MFG With Photo PDF
EA in Biscuit MFG With Photo PDF
EA in Biscuit MFG With Photo PDF
A..Shajahan
Formerly with National Productivity Council as Deputy Director (Environment)
Email : alishajahan@gmail.com
Background
NPC conducted a detailed waste audit in a biscuit manufacturing unit with a
production level of 50T/d and making 24 different soft and hard biscuit varieties.
The major raw materials used were wheat flour, sugar, hydrogenated vegetable
oil (HVO), water, skimmed milk powder, butter etc. Specified quantities of raw
materials are fed to a dough mixer where kneading of raw materials is carried
out. The dough thus prepared is taken to the baking line where it is made into
sheets by a pair of rollers and then passed through a moulder/cutter. The raw
biscuits are taken by a conveyor into the baking oven, fired by LDO through a set
of six burners. The baking is carried out in 6 stages with different temperature
regimes. The products of combustion from each burner pass through radiant
heat transfer tubes and finally exit through individual chimneys. The defective
biscuits are drawn out of the conveyor and collected in a tray. The good biscuits
are mostly packed in wrappers and the rest in cardboard boxes and bins. All the
packed biscuits are sent to storage and forwarding area (S&F).
The major water consumption areas are process (9m3/d), cooling tower make up
(23m3/d), canteen (16m3/d) and toilets/urinals (52m3/d).
The process wastewater (4m3/d) emanates from periodic cleaning of dough
mixers, moulders, cutters, dough trucks, vats and floors.
Resource Conservation and Pollution Abatement Measures
Mould and Cutter Cleaning
The unit had a practice of cleaning the moulder and cutter first with compressed
air followed by water wash thereby discharging the residual dough into the drain.
The company had a contract demand of 750 KVA which was recently enhanced
to 1200 KVA in view of the expansion plans. The MD had varied from 560 715
KVA during the last 12 months.
The analysis of the KVA demand data for a 24-hour cycle shows that 63% of the
time, the load had remained between 500-600 KVA. On seven occasions the
load remained between 500-600 KVA. Only twice in the cycle the load has
approached 700 KVA.
The peaks (700 KVA) had occurred due to simultaneous operation of many high
capacity loads such as mixers. The MD can be controlled between 400-500 KVA
by judicious operation of equipments and segregation of essential and nonessential loads so that the later can be shed during peak load periods.
Baking Oven
The average LDO consumption per day for both the ovens is 3250 liters.
To determine the fuel efficiency, an emission from each stack was monitored.
The result of the gas analysis showed very high excess air (200-300%) being
used in the burners indicating excessive heat loss in the flue gas equivalent to
30% of the heat input in the fuel. It was recommended to use an excess air of
30%, which is normally used for oil firing purposes. This measure resulted in
20% of oil saving amounting to an annual savings of Rs.12.5 lacs.
Other Recommendations for Energy Conservation
Since the refrigeration system contributes a major share of the electrical load, the
plan can utilize the exhaust heat from baking ovens by installing a vapor
absorption system thereby reducing the electrical energy consumed.
The compressed air system has to be repaired for leaks regularly to minimize the
cost of compressed air.
The butter requirement for the plant is around 600 kg/d only. However an
inventory of 18 T is maintained at 0 to 4oC. This consumes sizable energy and
hence a lower inventory should be carried taking into account the energy costs.
Optimized Operation of ETP
A schematic flow diagram of the ETP is given in Fig.1. The ETP receives
process, canteen and domestic wastewater. The system consists of
-
ETP has been designed for a basis of 150 m 3/day and a daily BOD load of
225kg.
DOMESTIC
W.W.
PROCESS
W.W.
S.C.
S.C.
O/G
TRAP
JUNCTION
CHAMBER
O/G
TRAP
R&D
AERATION
TANK - II
RECIRCULATION
COLLECTION
SUMP
DOMESTIC
W.W.FROM
ADMN.
P
GRIT
CHANNEL
AERATION
TANK -I
TREATED
WATER
COLLECTION
SUMP
P
S.T
S.T
EXCESS
SLUDGE
SDB
EXCESS
SLUDGE
that treatment system has been excessively over designed and the treated
effluent was not conforming to the standards in terms of BOD & TSS.
Process
15.8m3/day
Canteen
51.6 m3/day
Process
4m3/day
The BOD & COD removals were satisfactory in the first stage biological
treatment. But there is a carryover of solids from the settling tank to the
second stage. This carry over was due to poor sludge compaction achieved
in the circular settling tank. The operating MLSS level, vis-a-vis 14TSS in the
return sludge, is too low.
A high D.O. level is maintained in the aeration tank and this causes pin-flock
formation of microbial mass. With this intensive mixing, agglomeration of
biomass is difficult to achieve.
The operating problems and process deficiencies for second stage biological
treatment are also similar to first stage system. Additional problems were:
i.
The F/M ratio is 0.028 due to primarily low organic loading rate. The
MLSS level in the aeration tank is 956 mg/1 as against a design value of
4000 mg/1. Due to low organic loading rate and carryover of suspended
solids in the clarified effluent, the overall treatment efficiency is low.
ii.
Low hydraulic loading rate and high detention time in the setting tank II
causes the problem of rising sludge.
It was recommended to eliminate the first stage activated sludge system and
continue with second stage aeration with only a 5 H.P aerator, thereby
resulting in a power saving of 15 H.P.
The sedimentation tank has to be modified with improved hopper bottom and
overflow weir arrangement.
It was recommended to maintain optimum D.O level (1-2 mg/1), high return
sludge concentration for consistent BOD and COD removal.
1.
2.
Equipment Description
Pumps
Collection sump to grit channel
Return sludge to A.T.I
H.P. Rating
Existing
Necessary
2
1
2
3.
1.
2.
5
15
26
Savings in power