DPWH Year End Report (Final)
DPWH Year End Report (Final)
DPWH Year End Report (Final)
EXECUTIVE SUMMARY
The national road network is the most important infrastructure asset of the government.
An
indicative estimate of the national road network asset is valued at P1.2 Trillion. The road network
provides the connectivity to all Filipinos for their economic and social activities. As such, the
President has directed DPWH to ensure that the quality and safety of our national road network is
upgraded and maintained properly. The funding of DPWH for our national roads and bridges is
being increased substantially to ensure continued growth nationwide.
In support of the key priorities of the Aquino Administration, the main societal goal of the DPWH is
to contribute to the sustainable economic growth and poverty reduction and improve the countrys
global competitiveness.
THRU :
Our target outcomes until 2016 and budgetary support is intended to achieve these targets:
Pave all existing unpaved national arterial roads (15,872 Kms) by 2014;
Pave all existing unpaved national secondary roads (15,370 Kms) by 2016;
Make all national bridges permanent by 2016;
Implement Flood Master Plans for the countrys major and principal rivers by 2016.
To achieve these goals and desired outcomes, the DPWH has adopted the following five strategic
programs as follows:
1.
2.
3.
4.
5.
Page 1
PMO Implemented
Projects (LFP/FAP)
P 1.261 Billion
Total
(Savings) *
P 15.45 Billion
* The P15 Billion is only the savings between ABC vs. Awarded Contract and does not
include the variance between the Appropriation vs. ABC.
Also, improved monitoring of projects has resulted in the completion of several infrastructure
projects (e.g., C-3 Road/Quezon Avenue Interchange Project, Plaridel By Pass Project
(Contract Package No. 2)) ahead of schedule.
Comparison of the Plaridel Bypass Project-Phase I, CP-I and CP-II and the C-3 Road (G.
Araneta)/Quezon Avenue Interchange Project
Date of Bidding
Project Cost
Approved budget cost (ABC)
Total Amount as Bid
Variance (ABC-Bid Amt.)
P706.5 million
P543.3 million
P163.2 million
C-3 Road
Interchange
Nov 2010
P534.6 million
P430.0 million
P104.6 million
P264.2 million {variance:
Appropriation (P694.2 m)
Bid Amount}
Implementation Schedule
Original/target
Actual
Variance
Remarks
Bidding irregularities in DPWH Region 4-B. The District Engineering Office (DEO) in
Mamburao, Occidental Mindoro began a project worth P473.457 million, well beyond the
P50 million that district engineers can sign off on their own. To bypass clearance from
regional and central offices, they cut the project into components that would not breach the
said limit. DPWH cancelled the bidding of these projects, clustered them into six projects,
and rebid these in September 2011.
Total approved budget for the contract (ABC) for the six clustered projects was P463.8
Million. Through public bidding, the DPWH was able to save P46.6 Million as the total
awarded contract amounted to only P417.2 Million.
DPWH subsequenlty improved its percentage index from (-) 65% in 2009 to (-) 21% in 2012
based on the Surveys of Enterprises on Corruption conducted by the Social Weather
Stations (SWS). DPWH is targeting to futher improve its standing and be in the neutral
territory before the end of 2016.
Page 2
The National Capital Region (NCR)/Central Office, where the biddings for projects above
P150 Million are conducted, improved its percentage index from a (-) 71% in 2009 to (-) 8%
in 2012 which was the result of transparent/competitive biddings and reforms which DPWH
has been implementing. The other regions recorded some improvements buts not as
significant as in NCR, but the DPWH is continuing to work in improving the procurement
practices in the Regional and District Offices.
2. Enhanced Citizens Participation in Governance
Road projects are now being implemented according to approved plans and specifications
by better equipped and qualified contractors with closer project inspection and monitoring
including the monitoring and participation of a network of Civil Society Organizations
(CSOs), Non-Government Organizations (NGOs), Church and private sector organizations.
As of February 2012, DPWH accredited 52 Civil Society Organizations (CSOs) as
partners/observers in all stages of project development cycle (identification, preparation,
budgeting, procurement, implementation, operation and post evaluation) and in other areas
of mutual interest.
3. Intensified Infrastructure Development
Convergence Program
DPWH has a convergence program with the Department of Tourism to provide good road
access to our designated priority tourism destinations under the DOT Master Plan. A total
amount of P4.31 Billion (P1.39 Billion-2011, P2.92 Billion-2012) has been allocated from
2011 to 2012 and an additional budget of P5 Billion in 2012 out of savings and unutilized
funds and an additional P11.95 Billion is included in 2013 for tourism road infrastructure
projects.
These tourism road projects which support the National Tourism Development Plan (NTDP)
were identified through a selection process jointly undertaken by DOT and DPWH from
Regional Consultations based on the Tourism Road Infrastructure Program Criteria.
Public-Private Partnership Program
DPWH will continue to pursue infrastructure investments with the private sector to augment
the countrys much needed infrastructure development. Aside from the Daang Hari-SLEx
Link which was successfully bid out last December 2011, three (3) proposed expressways
are in the pipeline for 2013, namely NLEx-SLEx Connector, NAIA Expressway Phase 2,
Central Luzon Link Expressway Phase 1 and possibly the fourth, the Cavite Laguna
Expressway Project.
The three (3) Skyway Projects [NAIA Expressway, NLEx-SLEx Link Connector Road
(MPTDC), Metro Manila Skyway Stage 3 (CMMTC) ] will create an integrated elevated road
network (skyways) for Metro Manila. This skyway network will be President Aquinos legacy
project.
Page 3
Quality of Roads.
According to the World Economic Forums Global Competitiveness Report, the Philippines
global ranking in terms of quality of roads improved from 114th in 2010-2011 to 87th in 20122013. Also, the quality of road index improved from 2.8 to 3.4 at par with Indonesia and
targeting to be in the 4 to 5 territory in 2016.
4. In 2012, out of the total allotment of P194 Billion, 82% (P159 Billion) were already obligated.
Out of the P159 Billion, 90% (P143 Billion) were disbursed, this is 35% (P37 Billion) higher than
the P106 Billion total disbursement for full year 2011.
Of The P194 Billion total allotment received by DPWH, P109 Billion is from the DPWH Regular
GAA Budget.
5. The DPWH Budget (Capital Outlays) significantly increased by 45% (P45 Billion) from P99
Billion in 2012 to P144 Billion in 2013. Excluding the inter-regional and nationwide projects, the
total regional allocation for 2013 is P108 Billion, of which an initial 26% or P28 Billion is
programmed for Mindanao. The P 28 Billion allocation for Mindanao is 97% (P13.6 Billion)
higher from the P14 Billion in 2011.
As of February 28, 2013, DPWH already bid out more than 80% of the 2013 Regular GAA
projects and will be awarded before the election ban which starts March 28.
Page 4
OUTLINE
A. Strategic Policies and Programs
1. Good Governance and Anti-Corruption Program
a. Right Project
b. Right Cost
c. Right Quality
d. Right on Time
e. Right People
2. Better Quality and Safer National Roads and Bridges Program
3. Strategic Convergence Program
a. Tourism Convergence Program
b. Water Convergence Program
c. Integrated Transport System
d. Metro Manila Flood Management Program
e. Community Based Employment Program
f. Peace and Prosperity Program
g. School Building Program
h. Rural Road Development Program
4. Public Private Partnership (PPP) Program
a. On-going PPP projects
b. Proposed PPP projects
5. Effective Flood Control Program
B. State of Infrastructure in the Philippines based on Global Competitiveness Report
C. State of Philippine Road Network
D. 2010-2016 Target Outcomes
1. National Arterial Road (100% paved by 2014)
2. National Secondary Road (100% paved by 2016)
3. National Bridges (100% permanent by 2016)
E.
F.
G.
H.
I.
Page 5
DPWH ACCOMPLISHMENTS
The Department of Public Works and Highways (DPWH) envisions to be an effective and efficient
government agency, improving the life of every Filipino through quality infrastructure. Its mission is
to provide and manage quality infrastructure facilities and services responsive to the needs of the
Filipino people in the pursuit of national development objectives.
Rooted on the core values and in pursuit of the mission to reach the vision, DPWH has adopted as
its management philosophy Doing the right projects at the right cost and right quality and
accomplished right on time with the right people.
DPWH PHILOSOPHY:
Right Projects
jjppjjj
Right Cost
Right Quality
Right on Time
Right People
The outcome perspectives of social impact and external stakeholders concretize the quality
infrastructure DPWH envisions for the Filipinos. In order to achieve the outcomes, the organization
has to strengthen its resource stewardship, people and processes which are the drivers to attain the
outcomes. Hence, to achieve its vision, DPWH optimizes government resources to meet its goals
and improve its processes and efficiency. All in all, these will lead to social and economical impact
to provide safe and integrated infrastructure and improve the lives of Filipino.
A. DPWH STRATEGIC POLICIES AND PROGRAMS:
Pursuant to Presidents Aquinos Program of sustained economic growth and poverty reduction, the
Department has adopted the following strategic policies and priorities which will have clear social
outcomes based on prudent and efficient selection of projects (national and local) with measurable
social and economic benefits specially to the marginalized:
1. Good Governance Reform and Anti-Corruption Program
2. Upgrade Quality and Safer National Roads and Bridges Program
3. Strategic Convergence Program
4. Public Private Partnership (PPP) Program
5. Effective Flood Control Program
Page 6
2006
2008
2007
2009
2012
-21
-55
-63
-66
-65
-66
The National Capital Region (NCR)/Central Office, where the biddings for projects above
P150 Million are conducted, improved its percentage index from a (-) 71% in 2009 to (-) 8%
in 2012 which was the result of transparent/competitive biddings and reforms which DPWH
has been implementing. The other regions recorded some improvements buts not as
significant as in NCR, but the DPWH is continuing to work in improving the procurement
practices in the Regional and District Offices.
All Areas
NCR
ANG
CLB
ILO
CEB
DAV
CDO-I
-8
-20
-21
-24
-30
-30
-32
-36
-56
-65
-71
-71
-52
-70
Page 7
Implementation of the Governance Reform and Anti-Corruption Program was given priority in
DPWH in line Presidents Aquino Anti-Corruption Policy. The Transformation Program has
achieved the following major positive results:
]
MAJOR POLICIES
RIGHT COST
RIGHT QUALITY
RIGHT ON TIME
RIGHT PEOPLE
Page 8
MAJOR POLICIES
SAFETY
Page 9
CONVERGENCE PROGRAM
TOURISM CONVERGENCE PROGRAM:
Support to designated strategic Tourism
Destinations is included in the DPWH Budget;
Objective selection of projects using the Tourism
Road Infrastructure Project Prioritization Criteria
based on the Tourism Master Plan;
A total amount of P21 Billion were already invested
for various tourism infrastructure projects from
2011 to 2013, and an estimated P13 to P15 Billion
annual investment for tourism projects is proposed
in 2014 and succeeding years.
Department of Agriculture
Department of Agrarian Reform
Department of Environment and Natural
Resources
Page 10
Department of Education
Department of Agriculture
Department of Agrarian Reform
Page 11
Length (km)
Subic-Clark-Tarlac Expressway
93.77
82.62
2.34
9.30
SLEX (Magallanes-Alabang)
13.43
6.75
36.03
7.00
42.00
6.86
Length (km)
88.85
4.00
Length (km)
NAIA Expressway
7.15
13.53
47.00
30.70
19.74
59.50
43.60
14.70
Page 12
Page 13
Proposed:
1. NAIA Expressway
Project
Cost
Schedule
Status/Remarks
P 11.59 B
P 5.55 B
P 1.38 B
P 3.87 B
P 0.79 B
P 2.01 B
P 15.52 B
July 2010-May
2013
March. 2013May 2014
Jan. 2014-Jan.
2016
April 2012-June
2014
(Design and
Const.)
On-going, 81.89%
ROW acquisition and advance
work for the Agno Viaduct for
Section 2 is on-going.
Feasibility Study for the realignment of Section 3 is being
finalized.
On-going, 29.57%
DED for Segment II has been
finalized
2. NLEX-SLEX Link
Connector Road
P 11.73 B
Oct. 2014-Dec.
2016
(Construction)
Page 14
Name of Project
3. Cavite-Laguna (CALA)
Expressway
Project
Cost
P 35.58 B
Schedule
Status/Remarks
Jan. 2015-Dec.
2017
(Construction)
P 14.94 B
P 14.20 B
TBD
P 1.96 B
March 2013
March 2015
(Construction)
Procurement of Project
Management Consultant (PMC)
has been completed. TCGI
Engineers is the PMC.
Procurement of contractor/s by
STAR Infrastructure
Development Corporation
(SIDC) is on-going.
P 44.59 B
P 42.38 B
P 9.45 B
2014-2017
(Design and
Construction)
2014-2017
(Design and
Construction)
2014-2017
(Design and
Construction)
TBD - To Be Determined
Page 15
with
Other
B. Flood Management Master Plan for Metro Manila and Surrounding Areas
OBJECTIVE:
After the flood events of Ondoy and Pepeng in September and October 2009, respectively that
caused severe damages in Metro Manila and Surrounding Areas, the World Bank has provided
a Technical Grant in the amount of $1.5 Million under the Global Facility for Disaster Reduction
and Recovery Trust Fund of the Australian Agency for International Development (AusAID).
A flood risk assessment study for the entire Metro Manila and Surrounding Basin Area was
undertaken from February 2011 to February 2012, to prepare a comprehensive flood risk
management plan for the same and to determine a set of priority structural measures, which will
still undergo individual feasibility studies and detailed design prior to implementation, including
non-structural measures that will provide sustainable flood management up to a designated
safety level and serve as the roadmap/vision of the Government until 2035 (23 years from now).
BOUNDARY OF STUDY AREA AND THE RIVER BASINS:
Page 16
The Study Area covers the entire Metro Manila and Surrounding Areas, particularly, provinces of
Rizal, Laguna and parts of Bulacan with a total area of 4,354 sq. km. or 435,400 hectares, which
is 7 times the size of Metro Manila and 2/3 that of Singapore.
It also encompasses the Pasig-Marikina River Basin, Malabon-Tullahan, Meycauayan, South
Paraaque-Las Pias and Laguna Lake Basins, including drainage basins. Administration Areas
in and around the Study Area include sixteen (16) cities and one (1) municipality in the National
Capital Region (NCR), sixty three (63) cities/municipalities in the CALABARZON Area and eight
(8) cities/municipalities in Bulacan with a population of 20,433,722 in and around the Study Area
and estimated population of 17,147,658 in the Study Area.
GUIDING PRINCIPLES FOR MASTER PLAN DEVELOPMENT:
1. Adopt Integrated Water Resources Management Principles and River Basin Approach
2. Develop safe society with resiliency to floods through:
a. Structural measures for the river basins and waterways
b. Structural measures for Laguna Lakeshore, and
c. Improvement of urban drainage system
3. Improvement of the Flood Information and Warning System (FIWS)
4. Establish integrated and consistent Flood Risk Management (FRM) institutional system
5. Strengthen community-based flood risk management Land Use and Solid Waste
6. Utilization of runoff waters as water resources, etc.
7. Reforestation and watershed management
THREE MAJOR FLOODING OCCURENCES:
1. Huge volume of water coming from Sierra Madre
2. Drainage capacity constraints in core area of Metro Manila
3. Low-lying communities around Manila Bay & Laguna Lake
Page 17
Name of Project
1. Pasig-Marikina River Improvement and Dam Construction
2. Meycauayan River Improvement
3. Malabon-Tullahan River Improvement
4. South Paraaque-Las Pias River Improvement
5. East Mangahan Floodway (Cainta & Taytay River Improvement)
6. West Laguna Lakeshore Land Raising
7. Land Raising for Small Cities around Laguna Lakeshore
8. Improvement of the Inflow Rivers to Laguna Lake
9.
Each of the above projects is independent, but they form integral measures for mitigating floods
in Metro Manila and Surrounding areas. Hence, considering the need for immediate
interventions to ease the flooding problems in these areas, several high-impact flood control
projects amounting to P5 Billion were identified for immediate implementation, to wit:
Page 18
Name of Project
National Capital Region (NCR):
1. Valenzuela-Obando-Meycauayan (VOM)
Project
Total Cost
Released
Amount
820.0 M
820.0 M
2.
700.0 M
380.0 M
3.
700.6 M
211.0 M
4.
222.5 M
222.5 M
5.
50.0 M
50.0 M
6.
100.0 M
100.0 M
7.
8.
250.0 M
190.0 M
190.0 M
9.
Additional Projects
50.9 M
50.9 M
100.0 M
100.0 M
139.0 M
139.0 M
637.0 M
637.0 M
30.0 M
30.0 M
50.0 M
50.0 M
400.0 M
400.0 M
Region III:
1. Dredging of Labangan Channel, Hagonoy,
Bulacan
2. San Fernando-Sto. Tomas-Minalin Tail Dike
3.
4.
5.
Region IV-A:
1. Sta. Maria-Mabitac River
2.
180.0 M
180.0 M
3.
100.0 M
100.0 M
4.
Bian River
100.0 M
100.0 M
136.5 M
136.5 M
43.5 M
43.5 M
5,000.0 M
3,940.4 M
Nationwide:
1. Various Dredging Equipment
2.
SARO No.
A-12-01110
dated 11/22/12
A-12-01111
dated 11/22/12
A-12-01112
dated 11/22/12
A-13-00684
dated 03/14/13
A-12-01111
dated 11/22/12
A-12-01112
dated 11/22/12
A-12-01125
dated 11/23/12
A-13-00684
dated 03/14/13
A-12-01112
dated 11/22/12
A-12-01113
dated 11/22/12
A-13-00684
dated 03/14/13
A-12-01111
dated 11/22/12
A-12-01112
dated 11/22/12
A-12-01112
dated 11/22/12
A-12-01112
dated 11/22/12
A-13-00117
dated 01/15/13
A-12-01113
dated 11/22/12
A-13-00684
dated 03/14/13
A-13-00684
dated 03/14/13
A-12-01112
dated 11/22/12
A-12-01125
dated 11/23/12
A-13-00141
dated 01/15/13
A-13-00141
dated 01/15/13
A-13-00141
dated 01/15/13
A-13-00141
dated 01/15/13
A-12-01111
dated 11/22/12
A-12-01111
dated 11/22/12
Page 19
Out of the P5 Billion, P3.940 Billion was already released for various flood control projects.
Attached is the detailed list of the High Impact Flood Control Projects with the corresponding
status.
In addition to the above, rehabilitation/improvement of twelve (12) existing pumping stations in
Metro Manila amounting to P1.600 Billion was likewise approved and released to MMDA.
Clearing of eight (8) major waterways in Metro Manila with an estimated 20,000 informal settlers
that will be provided decent resettlements is also part of an inter-agency efforts being
undertaken by the government.
NON-STRUCTURAL MEASURES:
1. Strengthening of the Flood Information and Warning System (FIWS)
Effective Flood Control Operation and Warning System (EFCOS) improvement
New telemetric rainfall and water level gauging stations
2. Capacity Building for Strengthening Community-based FRM
Update and implement Information and Education Campaign (IEC) programs
Rainfall and water level monitoring by Barangay Disaster Risk Reduction and
Management Councils (BDRRMCs)
Construction of evacuation routes and temporary evacuation centers
3. Improvement of Management Information System (MIS) for Disaster Risk Management
Improvement and development of MIS
Capacity building
4. Reforestation and Watershed Management
Page 20
Quality of Roads. According to the World Economic Forums Global Competitiveness Report,
the Philippines global ranking in terms of quality of roads improved from 114th in 2010-2011 to
87th in 2012-2013. Also, the quality of road index improved from 2.8 to 3.4 at par with
Indonesia and targeting to be in the 4 to 5 territory in 2016.
Quality of Roads Index
Page 21
Legend
Road Classification
National Arterial
National Secondary
DPWH MANDATE:
PLAN, DESIGN, CONSTRUCT AND MAINTAIN NATIONAL ROADS AND BRIDGES AND
FLOOD CONTROL SYSTEMS IN MAJOR AND PRINCIPAL RIVERS
ROAD CLASSIFICATION:
National Arterial Road (NAR):
The main trunkline from northernmost Luzon down to Southern Mindanao interconnecting
major islands and those traversing backbone and across the islands and those that provides
direct access to important centers and areas vital for regional development and
emergencies.
National Secondary Road (NSR):
Other roads which complement national arterial roads to provide access to other main
population and production centers
The National Roads covered by the Autonomous Region for Muslim Mindanao (Maguindanao,
Lanao del Sur, Sulu, Tawi-Tawi and Basilan except the capital Isabela City) are not included in the
DPWH national road data base.
Page 22
Note: Figures may not add up due to rounding. The annual targets are subject to change based on
actual accomplishment of upgrading (gravel to paved) projects.
Page 23
Year
Note: The annual bridge targets/prioritization are still subject to change based on the actual accomplishments
and due to the occurrence of calamity (floods and earthquake) and other unforeseen circumstances that
causes damage to the bridge structures.
Page 24
+ 45%
Year
Page 25
Page 26
Page 27
An additional P7.32 Billion was requested for release to the Department of Budget and
Management per letter dated January 24, 2013 for the implementation of the TISP-ARMM, Phase II.
Hereunder is the detailed status of the eleven (11) road infrastructure projects covering twenty-two
(22) contract packages under ISP-ARMM which involves the rehabilitation/upgrading of an
estimated length of 128 kms:
Hereunder is the status of the five (5) bridge infrastructure projects under ISP-ARMM:
Note - Bato-Bato and Kiaokaran Bridges were implemented as one contract package.
Page 28
In 2012, out of the total allotment of P194 Billion, 82% (P159 Billion) were already obligated.
Out of the P159 Billion, 90% (P143 Billion) were disbursed, this is 35% (P37 Billion) higher than
the P106 Billion total disbursement for full year 2011.
Of The P194 Billion total allotment received by DPWH, P109 Billion is from the DPWH Regular
GAA Budget.
193.65 B
57.66B
(Extended/
Cont.)
159.41 B
142.92 B
55.37B
(Extended/
Cont.)
135.99B
(Current)
104.04B
(Current)
*
(NCA/LDDAP/WA/TRA)
Page 29
171.50 B
41.22B
(Extended/
Cont.)
130.28B
(Current)
49.64 B
P10.96B
(Extended/Cont.)
17.81 B
38.68B
(Current)
(NCA/LDDAP/WA/TRA)
Page 30
Project Cost
(Civil Works)
Implementation
Schedule
Status/Remarks
Completed:
Highway Projects:
Central Mindanao Road Project, 26th Yen JICA
Loan Package, PH-P237
a. Contract Package 2, North UpiMaguindanao/Sultan Kudarat Bdry. Road
b. Contract Package 3, Maguindanao/Sultan
Kudarat Bdry.-Lebak-Kalamansig Road
* Excluding CP1implemented using local funds.
2. Arterial Road Bypass Project (Phase I), Plaridel
Bypass Road Project, JICA PH-P236
a. Contract Package 1, (Sta. 32+970 Sta.
39+625)
b. Contract Package 2,(Sta. 39+625 Sta.
47+700)
3. Austrian-Assisted DPWH Bridge Construction
Acceleration Project for Calamity-Stricken
Areas
Flood Control Projects:
4. Iloilo Flood Control Project II, JICA PH-P230
a. Contract Package 1,Const. of Jaro
Floodway and Improvement of Tigum &
Aganan Rivers
b. Contract Package 2,Improvement of Iloilo
River, Upper Ingore Creek & Jaro River
Mouth Section
c. Contract Package 3, Development of
Relocation Site for Stage 1
1.
P 1.009 B
Completed
P 0.897 B
Completed
P 1.559 B
Completed
P 0.594 B
Completed
P 1.615 B
Completed- 19 Bridges
P 2.229 B
Completed
P 1.182 B
Completed
P 0.029 B
Completed
P 2.942 B
P 0.713 B
P 0.213 B
Completed 17 Bridges
On-going 1 Bridge
Suspended effective
P 0.440 B
P 2.917 B
P 2.372 B
P 7.045 B
P 1.862 B
Completed
P 1.833 B
Completed-4 Bridges,
On-going:
Highway Projects:
5. Urgent Bridges Construction Project for Rural
Development (UBCPRD), JICA PH-P231
a. Contract Package I
b. Contract Package II-A *
c. Contract Package II-B *
6.
7.
P 1.275 B
On-going, 4 Flyovers
and 43 Unibridges (50
spans) are already
completed
On-going-35 Bridges,
Under-Preconst.-8
Bridges
Proposed restructuring
contract of Centunion
using loan proceeds is
deferred due to the
on-going Senate Blue
Ribbon Committees
investigation on the
Page 31
implementation of the
Presidents Bridge
Program.
8.
9.
On-going
Bidding on Feb. 2013
On-going
Bidding on Jan. 2013
P 0.802 B
P 2.456 B
-
P 29.394 B
(Total Cost)
On-going
P16.194 B
Consultancy Services
for Upgrading/
Improvement (UI)
Component and Asset
Preservation (AP)
Component on-going.
P 0.709 B
On-going
P 0.422 B
600 c.d.
Resolution Award
P 0.420 B
600 c.d.
Resolution Award
600 c.d.
Contract Agreement
P 0.415 B
600 c.d.
Contract Agreement
P 0.112 B
On-going
P 0.112 B
On-going
P 0.231 B
P 0.681 B
Completed
Completed
P 0.141 B
On-going
P 0.420 B
Completed
P 0.910 B
Completed
P 4.914 B
Completed- 111
Bridges; On-going-2
Bridges
under process
under process
Page 32
P 1.199 B
Completed
P 0.691 B
On-going
P 0.401 B
On-going
P 1.269 B
P 0.846 B
June 2012-March
2013
P 0.147 B
P 1.668 B
Contract Agreement
for Concurrence of
JICA.
Completed
P 0.168 B
Completed
P 0.509 B
On-going
P 0.924 B
On-going
P 0.045 B
On-going
P 0.196 B
Completed
CP 7, Excavation/Dredging of Local
Drainage Channels, Road Raising and
Const. of Bridges
P 0.336 B
P 1.155 B
P 0.894 B
b.
Supplemental
e.
f.
g.
h.
Supplemental
Pre-Qualification
Results for JICA
Concurrence
Page 33
P 2.943 B
P 1.824 B
On-going
Completed
P 6.241 B
(Total Cost)
Under Pre-Const.
P 1.167 B
P 0.659 B
P 1.253 B
2014-2016
Approved by the
NEDA-ICC on March
22, 2012. Advance
procurement of
consulting services ongoing.
P 1.092 B
2014-2016
P 14.940 B
Dec. 2014-March
2017
Proposed:
Highway Projects:
19. Road Improvement and Institutional
Development Project (ADB-Assisted)
20. Arterial Road Bypass Project, (Phase II),
Plaridel Bypass Road Project, JICA PH-P250
a. Contract Package III, (Sta. 047+400 Sta.
049+625)
b.
concurrence of PQ and
Bidding Documents by
JICA prior to
advertisement
Waiting for the
concurrence of PQ and
Bidding Documents by
JICA prior to
advertisement
The construction of
this project will be
financed through ODA
while the Operation
and Maintenance (O &
M) will be under PPP.
Flood Control Projects:
24. Flood Risk Management Project (FRIMP) in
Cagayan, Tagoloan and Imus Rivers (JICAAssisted)
P 2.980 B
Procurement of
Consultancy Services
for Detailed
Engineering Design is
on-going.
The request for
proposals is under
review by DPWH
based on JICA
comments on the
same.
Page 34
P 7.545 B
P 2.956 B
To be determined
Approved by the
NEDA-ICC on March
22, 2012.
Technical assistance
was requested from
EDCF for the conduct
of a full-scale
Environmental and
Social Impact
Assessment.
Several high-impact
flood control projects
will be implemented as
immediate
interventions to ease
the flooding problems
at priority areas.
P 351.718 B
(estimate)
For eleven
(11) Flood
Control
Projects
P 5.0 B for
critical areas
based on the
Master Plan
Page 35
I.
Page 36
4. Bio-Engineering Technology
The DPWH is now taking steps to support the usage of indigenous products and
technologies in the implementation of infrastructure projects to help the governments
effort in promoting green engineering and minimizing the effects of climate change. A
Department Order No. 41, series of 2010, was issued to prioritize the usage of coconut
bio-engineering products/solutions in all DPWH projects/activities especially those
projects involving slope stabilization, soil conditioning, soil erosion prevention and/or
hydroseeding.
The usage of the coco-fiber products in the engineering industry will not only beneficial
for the environment but it will also provide employment opportunities for the coconut
farmers in rural areas.
Page 37