Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

EXECUTIVE SUMMARY
The national road network is the most important infrastructure asset of the government.
An
indicative estimate of the national road network asset is valued at P1.2 Trillion. The road network
provides the connectivity to all Filipinos for their economic and social activities. As such, the
President has directed DPWH to ensure that the quality and safety of our national road network is
upgraded and maintained properly. The funding of DPWH for our national roads and bridges is
being increased substantially to ensure continued growth nationwide.
In support of the key priorities of the Aquino Administration, the main societal goal of the DPWH is
to contribute to the sustainable economic growth and poverty reduction and improve the countrys
global competitiveness.
THRU :

Construction and proper maintenance of the countrys national roads, bridges


and public works to provide access to major airports, seaports/RORO ports,
markets, production areas, strategic tourist destinations and economic centers
throughout the country.

Our target outcomes until 2016 and budgetary support is intended to achieve these targets:

Pave all existing unpaved national arterial roads (15,872 Kms) by 2014;
Pave all existing unpaved national secondary roads (15,370 Kms) by 2016;
Make all national bridges permanent by 2016;
Implement Flood Master Plans for the countrys major and principal rivers by 2016.

To achieve these goals and desired outcomes, the DPWH has adopted the following five strategic
programs as follows:

1.
2.
3.
4.
5.

Good Governance Reform and Anti-Corruption Program


Better Quality and Safer National Roads and Bridges Program
Strategic Convergence Program
Public Private Partnership Program
Effective Flood Control Program

Key Outcomes and Actual Accomplishments:


1. Institutionalized Accountability
 Reformed public works processes resulted in the elimination of wastes and the curbing of
corruption, a more prudent and objective selection of projects and the strict adherence to the
policy requiring the preparation of Program of Work with detailed estimates for each capital
outlay instead of indiscriminate releasing of project funds.
Improved procurement procedures, as well as competitive and transparent bidding, have
resulted in P15.45 Billion savings which can be utilized for additional infrastructure projects
like funding the site development for the relocation sites for typhoon victims, rehabilitation of
damaged infrastructure projects, etc.

Page 1

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Savings Generated (Locally Funded and Foreign Assisted Projects)


Region/District Implemented Projects (LFP)
FY 2011 Budget
FY 2012 Budget
FY 2013 Budget
P 6.191 Billion
P 4.187 Billion
P 3.810 Billion

PMO Implemented
Projects (LFP/FAP)
P 1.261 Billion

Total
(Savings) *
P 15.45 Billion

* The P15 Billion is only the savings between ABC vs. Awarded Contract and does not
include the variance between the Appropriation vs. ABC.
 Also, improved monitoring of projects has resulted in the completion of several infrastructure
projects (e.g., C-3 Road/Quezon Avenue Interchange Project, Plaridel By Pass Project
(Contract Package No. 2)) ahead of schedule.
Comparison of the Plaridel Bypass Project-Phase I, CP-I and CP-II and the C-3 Road (G.
Araneta)/Quezon Avenue Interchange Project

Date of Bidding
Project Cost
Approved budget cost (ABC)
Total Amount as Bid
Variance (ABC-Bid Amt.)

Plaridel Bypass Project-Phase I


CP-I
CP-II
Jul 2008
Sep 2010
P1,447.5 million
P1,570.7 million
- P123.2 million

P706.5 million
P543.3 million
P163.2 million

C-3 Road
Interchange
Nov 2010
P534.6 million
P430.0 million
P104.6 million
P264.2 million {variance:
Appropriation (P694.2 m)
Bid Amount}

Implementation Schedule
Original/target
Actual
Variance
Remarks

Jan 2009-May 2011


Jan 2009-Nov 2011
6 months delayed from
original schedule
The project was delayed
due to ROW problems (1.
Delayed in the
relocation/raising of power
transmission line by
National Grid Corporation,
2. Delayed issuance of
NTP for works at NLEX
area by MNTC) and
adverse weather condition.

May 2011-Feb 2013


May 2011-Nov 2012
3 months ahead of
schedule
The project was ahead of
schedule to due to
simultaneous work of the
3 contractors under joint
venture.

Jun 2011-Dec 2012


Jun 2011-Sep 2012
3 months ahead of schedule
The project was ahead of
schedule due to 24/7
continuous work.

 Bidding irregularities in DPWH Region 4-B. The District Engineering Office (DEO) in
Mamburao, Occidental Mindoro began a project worth P473.457 million, well beyond the
P50 million that district engineers can sign off on their own. To bypass clearance from
regional and central offices, they cut the project into components that would not breach the
said limit. DPWH cancelled the bidding of these projects, clustered them into six projects,
and rebid these in September 2011.
Total approved budget for the contract (ABC) for the six clustered projects was P463.8
Million. Through public bidding, the DPWH was able to save P46.6 Million as the total
awarded contract amounted to only P417.2 Million.
 DPWH subsequenlty improved its percentage index from (-) 65% in 2009 to (-) 21% in 2012
based on the Surveys of Enterprises on Corruption conducted by the Social Weather
Stations (SWS). DPWH is targeting to futher improve its standing and be in the neutral
territory before the end of 2016.
Page 2

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

The National Capital Region (NCR)/Central Office, where the biddings for projects above
P150 Million are conducted, improved its percentage index from a (-) 71% in 2009 to (-) 8%
in 2012 which was the result of transparent/competitive biddings and reforms which DPWH
has been implementing. The other regions recorded some improvements buts not as
significant as in NCR, but the DPWH is continuing to work in improving the procurement
practices in the Regional and District Offices.
2. Enhanced Citizens Participation in Governance
Road projects are now being implemented according to approved plans and specifications
by better equipped and qualified contractors with closer project inspection and monitoring
including the monitoring and participation of a network of Civil Society Organizations
(CSOs), Non-Government Organizations (NGOs), Church and private sector organizations.
As of February 2012, DPWH accredited 52 Civil Society Organizations (CSOs) as
partners/observers in all stages of project development cycle (identification, preparation,
budgeting, procurement, implementation, operation and post evaluation) and in other areas
of mutual interest.
3. Intensified Infrastructure Development
 Convergence Program
DPWH has a convergence program with the Department of Tourism to provide good road
access to our designated priority tourism destinations under the DOT Master Plan. A total
amount of P4.31 Billion (P1.39 Billion-2011, P2.92 Billion-2012) has been allocated from
2011 to 2012 and an additional budget of P5 Billion in 2012 out of savings and unutilized
funds and an additional P11.95 Billion is included in 2013 for tourism road infrastructure
projects.
These tourism road projects which support the National Tourism Development Plan (NTDP)
were identified through a selection process jointly undertaken by DOT and DPWH from
Regional Consultations based on the Tourism Road Infrastructure Program Criteria.
 Public-Private Partnership Program
DPWH will continue to pursue infrastructure investments with the private sector to augment
the countrys much needed infrastructure development. Aside from the Daang Hari-SLEx
Link which was successfully bid out last December 2011, three (3) proposed expressways
are in the pipeline for 2013, namely NLEx-SLEx Connector, NAIA Expressway Phase 2,
Central Luzon Link Expressway Phase 1 and possibly the fourth, the Cavite Laguna
Expressway Project.
The three (3) Skyway Projects [NAIA Expressway, NLEx-SLEx Link Connector Road
(MPTDC), Metro Manila Skyway Stage 3 (CMMTC) ] will create an integrated elevated road
network (skyways) for Metro Manila. This skyway network will be President Aquinos legacy
project.

Page 3

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

 Quality of Roads.
According to the World Economic Forums Global Competitiveness Report, the Philippines
global ranking in terms of quality of roads improved from 114th in 2010-2011 to 87th in 20122013. Also, the quality of road index improved from 2.8 to 3.4 at par with Indonesia and
targeting to be in the 4 to 5 territory in 2016.
4. In 2012, out of the total allotment of P194 Billion, 82% (P159 Billion) were already obligated.
Out of the P159 Billion, 90% (P143 Billion) were disbursed, this is 35% (P37 Billion) higher than
the P106 Billion total disbursement for full year 2011.
Of The P194 Billion total allotment received by DPWH, P109 Billion is from the DPWH Regular
GAA Budget.
5. The DPWH Budget (Capital Outlays) significantly increased by 45% (P45 Billion) from P99
Billion in 2012 to P144 Billion in 2013. Excluding the inter-regional and nationwide projects, the
total regional allocation for 2013 is P108 Billion, of which an initial 26% or P28 Billion is
programmed for Mindanao. The P 28 Billion allocation for Mindanao is 97% (P13.6 Billion)
higher from the P14 Billion in 2011.
As of February 28, 2013, DPWH already bid out more than 80% of the 2013 Regular GAA
projects and will be awarded before the election ban which starts March 28.

Page 4

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

OUTLINE
A. Strategic Policies and Programs
1. Good Governance and Anti-Corruption Program
a. Right Project
b. Right Cost
c. Right Quality
d. Right on Time
e. Right People
2. Better Quality and Safer National Roads and Bridges Program
3. Strategic Convergence Program
a. Tourism Convergence Program
b. Water Convergence Program
c. Integrated Transport System
d. Metro Manila Flood Management Program
e. Community Based Employment Program
f. Peace and Prosperity Program
g. School Building Program
h. Rural Road Development Program
4. Public Private Partnership (PPP) Program
a. On-going PPP projects
b. Proposed PPP projects
5. Effective Flood Control Program
B. State of Infrastructure in the Philippines based on Global Competitiveness Report
C. State of Philippine Road Network
D. 2010-2016 Target Outcomes
1. National Arterial Road (100% paved by 2014)
2. National Secondary Road (100% paved by 2016)
3. National Bridges (100% permanent by 2016)
E.
F.
G.
H.

Public Investment Program


Infrastructure Program for Mindanao
Status of Fund Utilization
Priority Overseas Development Assistance (ODA) Projects
1. On-going and Completed ODA projects
2. Proposed ODA projects

I.

Climate Change Adaptation and Strategies

Page 5

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

DPWH ACCOMPLISHMENTS
The Department of Public Works and Highways (DPWH) envisions to be an effective and efficient
government agency, improving the life of every Filipino through quality infrastructure. Its mission is
to provide and manage quality infrastructure facilities and services responsive to the needs of the
Filipino people in the pursuit of national development objectives.
Rooted on the core values and in pursuit of the mission to reach the vision, DPWH has adopted as
its management philosophy Doing the right projects at the right cost and right quality and
accomplished right on time with the right people.

DPWH PHILOSOPHY:
Right Projects
jjppjjj

Right Cost
Right Quality
Right on Time
Right People

8% reduction of Indirect Cost of


project
Streamlined bidding process
P15.45 Billion actual savings
from competitive bidding
Cost reduction in Motor Vehicle
User Charge (MVUC) projects

The outcome perspectives of social impact and external stakeholders concretize the quality
infrastructure DPWH envisions for the Filipinos. In order to achieve the outcomes, the organization
has to strengthen its resource stewardship, people and processes which are the drivers to attain the
outcomes. Hence, to achieve its vision, DPWH optimizes government resources to meet its goals
and improve its processes and efficiency. All in all, these will lead to social and economical impact
to provide safe and integrated infrastructure and improve the lives of Filipino.
A. DPWH STRATEGIC POLICIES AND PROGRAMS:
Pursuant to Presidents Aquinos Program of sustained economic growth and poverty reduction, the
Department has adopted the following strategic policies and priorities which will have clear social
outcomes based on prudent and efficient selection of projects (national and local) with measurable
social and economic benefits specially to the marginalized:
1. Good Governance Reform and Anti-Corruption Program
2. Upgrade Quality and Safer National Roads and Bridges Program
3. Strategic Convergence Program
4. Public Private Partnership (PPP) Program
5. Effective Flood Control Program
Page 6

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

1. GOVERNANCE REFORM AND ANTI-CORRUPTION PROGRAM:


DPWH subsequenlty improved its percentage index from (-) 65% in 2009 to (-) 21% in 2012
based on the Surveys of Enterprises on Corruption conducted by the Social Weather
Stations (SWS). DPWH is targeting to futher improve its standing and be in the neutral
territory before the end of 2016.
Surveys of Enterprises on Corruption (DPWH)
By Social Weather Stations (SWS)
2005

2006

2008

2007

2009

2012

-21

-55
-63
-66

-65

-66

The National Capital Region (NCR)/Central Office, where the biddings for projects above
P150 Million are conducted, improved its percentage index from a (-) 71% in 2009 to (-) 8%
in 2012 which was the result of transparent/competitive biddings and reforms which DPWH
has been implementing. The other regions recorded some improvements buts not as
significant as in NCR, but the DPWH is continuing to work in improving the procurement
practices in the Regional and District Offices.
All Areas

NCR

ANG

CLB

ILO

CEB

DAV

CDO-I

-8
-20

-21

-24
-30

-30

-32

-36

-56
-65
-71

-71

-52

-70

Page 7

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Implementation of the Governance Reform and Anti-Corruption Program was given priority in
DPWH in line Presidents Aquino Anti-Corruption Policy. The Transformation Program has
achieved the following major positive results:
]

KEY REFORM AREAS


 RIGHT PROJECT

MAJOR POLICIES

 RIGHT COST

 RIGHT QUALITY

 RIGHT ON TIME

 RIGHT PEOPLE

Objective programming and project selection criteria based


on planning applications (i.e. PMS-HDM 4);
Project Status available on the DPWH Website;
Public consultation and full disclosure on public expenditure
and project status.
Detailed Design, Program of Work and Detailed
Cost/Estimates prepared/evaluated based on restructured
Indirect/Direct Costs;
A more transparent and simplified bidding process has
resulted to bidders submitting only 5 documents instead of
20 documents in the past;
Open, Transparent and Competitive Bidding which resulted
in P15.45 Billion savings (as of February 2013);
For the same amount of budget, what used to be cost of
concrete road for 230 mm thickness is now good for 280
mm thickness.
Eliminated submission of Letter of Intent to achieve the right
cost
24/7 DPWH Call Center (165-02) to address queries and
complaints;
Outsourced project inspection and quality assurance;
Undertaking ISO Certification of 17 DPWH Offices;
Clustering of projects to ensure that these will be
implemented by competent contractors with appropriate
equipment.
As of Feb. 2013, Accredited 52 Civil Society Organizations
(CSOs) partners for monitoring;
Bantay Lansangan Road Sector Report Card Rating;
Close monitoring of project implementation.
Professionalize DPWH Organizations and its employees
Promotional Examination for Assistant District Engineers
and up
Cadet Engineering Program
Accreditation of DPWH Materials Engineer

Page 8

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

2. BETTER QUALITY AND SAFER NATIONAL ROADS AND BRIDGES PROGRAM:


KEY REFORM AREAS
 UPGRADE QUALITY

MAJOR POLICIES

 SAFETY

Adopted new standards for concrete pavement


thickness from 230mm to 280mm where
appropriate;
Outsourced project inspection and quality
assurance;
Developed new construction design standards
and specifications upgrade drainage
specifications, slope protection & soil erosion
control, widening of national roads;
Strengthening/retrofitting of national bridges to
comply with international seismic standards;
Implement Design-Build Bridges.

Construct loading and unloading bays for road


safety;
Improve road safety using Traffic Accident
Recording and Analysis System (TARAS) and
International Road Assessment Program
(iRAP);
Enforce anti-overloading provision of the law;
Upgrading of temporary bridges to permanent
structures;
Clearing of road hazards, illegal structures and
obstructions along national roads right of way.

Page 9

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

3. STRATEGIC CONVERGENCE PROGRAM:


AGENCY PARTNER
Department of Tourism

CONVERGENCE PROGRAM
TOURISM CONVERGENCE PROGRAM:
Support to designated strategic Tourism
Destinations is included in the DPWH Budget;
Objective selection of projects using the Tourism
Road Infrastructure Project Prioritization Criteria
based on the Tourism Master Plan;
A total amount of P21 Billion were already invested
for various tourism infrastructure projects from
2011 to 2013, and an estimated P13 to P15 Billion
annual investment for tourism projects is proposed
in 2014 and succeeding years.

Department of Agriculture
Department of Agrarian Reform
Department of Environment and Natural
Resources

WATER CONVERGENCE PROGRAM:


Adopted a River Basin Approach to Flood
Management and Water Resource Utilization
Implemented an Integrated Water Resource
Management Approach in Coordination with DA,
NIA, DENR
Undertake projects consistent with the Flood
Management Master Plan for Metro Manila and
surrounding Areas

Department of Transportation and


Communication

INTEGRATED TRANSPORT SYSTEM:


Support for access to major airports and RORO
ports is included in the DPWH Budget.
Infrastructure support in preparation for APEC
2015 by improving access to designated airports,
convention sites, tourism destinations.

Metropolitan Manila Development


Authority

FLOOD MANAGEMENT PROGRAM:


Coordinate flood control measures and needed
infrastructure in flood prone areas of Metro Manila

Page 10

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Department of Labor and Employment


Department of Social Welfare and
Development

COMMUNITY BASED EMPLOYMENT PROGRAM


(DOLE):
DPWH is the lead steward for infrastructure sector
TRABAHONG LANSANGAN FOR CCT BENEFICIARIES
(DSWD):
Prioritize CCT Beneficiaries for Labor Employment
on DPWH projects

Department of National Defense


Armed Forces of the Philippines

Department of Education

Department of Agriculture
Department of Agrarian Reform

PEACE AND PROSPERITY PROGRAM:


Peace and Prosperity Program in Mindanao and
other Conflict-Affected Areas
Support for infrastructure development in
Mindanao is included in the DPWH Budget .

SCHOOL BUILDING PROGRAM:


Assist DepEd in developing PPP School Building
Program
An amount of P14.11 Billion for Basic Education
Facilities is included in the DPWH FY 2013 Budget.

RURAL ROAD DEVELOPMENT PROGRAM:


Farm to Market Roads Development supporting
Agrarian Reform Communities (ARC) and key
agricultural production areas.

Page 11

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

4. PUBLIC PRIVATE PARTNERSHIP (PPP) PROGRAM:

Public Private Partnership Program to augment Regular GAA Budget


Implement the High Standard Highway Master Plan for Metro Manila and 200km radius to
develop priority expressway projects thru PPP;
Identified various modes of undertaking these priority expressways;
Develop long term road maintenance program for national roads under PPP;

PROPOSED HIGH STANDARD HIGHWAY NETWORK IN METRO MANILA


AND ITS 200 KM SPHERE
EXISTING: 300 Km.
Project Name

Length (km)

Subic-Clark-Tarlac Expressway

93.77

North Luzon Tollway

82.62

C-5 Expressway (Segment 8.1)

2.34

Metro Manila Skyway, Stage 1

9.30

SLEX (Magallanes-Alabang)

13.43

Manila Cavite Toll Expressway

6.75

South Luzon Tollway

36.03

Manila-Cavite Toll Expressway (R-1


Extension)
Metro Manila Skyway, Stage 2

7.00

Southern Tagalog Arterial Road (STAR)

42.00

6.86

ON-GOING CONSTRUCTION: 92.85 Km.


Project Name
Tarlac-Pangasinan-La Union Toll
Expressway
Daang Hari-SLEx Link

Length (km)
88.85
4.00

PROPOSED (PRIORITY): 235.92 Km.


Project Name

Length (km)

NAIA Expressway

7.15

NLEx-SLEx Connector Road (MPTDC)

13.53

CALA Expressway (Cavite and Laguna


Side)
Central Luzon Expressway (CLLEx),
Phase I
Southern Tagalog Arterial Road (STAR),
Lipa City-Batangas City, Phase II
C-6 Expressway and Global Link (South
Section)
C-6 Extension (Flood Control Dike
Expressway)
Calamba-Los Banos Expressway

47.00
30.70
19.74
59.50
43.60
14.70

Page 12

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

PROPOSED HIGH STANDARD HIGHWAY (HSH) NETWORK IN CEBU

Highly Urbanized Area:


Extension of Cebu Coastal Road up to Liloan
Construction of Cebu Hillside Road and its
Connector Roads
Flyover construction along Cebu North Road,
Cebu South Roads and Coastal Road
Northern Area:
Widening of Cebu North Road
Construction of Cebu North Parallel Road
Southern Area:
Widening of Cebu South Road from Naga to
Carcar
Construction of Cebu South Parallel Road
Mactan Island:
Improvement of Mactan Circumferential Road
Widening of First Mandaue-Mactan Bridge and
its Approach Roads
Construction of 3rd Bridge and its Approach
Road

PROPOSED HSH NETWORK IN TAGUM-DAVAO-GEN. SANTOS CORRIDOR


Inter-City Transport Axes:
Davao-Tagum Transport Axis together with
Davao- Tagum Parallel Transport Axis is formed
Davao-Digos-General Santos Transport Axis
together with Davao-General Santos Parallel
Transport Axis
Davao-Cagayan De Oro Transport Axis

Inter-City Transport Axes:


Davao City Diversion Road
Second Diversion Road to be formed
Mac Arthur Highway-E. Quirino Avenue
Quimpo Blvd.-Quezon Blvd.-Leon Garcia
Avenue- R. Castillo Avenue
C.M. Recto Avenue-J.P. Laurel Avenue
Ma-a Road
D. Quinones Road-Dacudao Avenue
General Santos City Circumferential Road

Page 13

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Status as of February 2013:


Name of Project
On-going:
1. Tarlac-Pangasinan-La
Union Expressway
(TPLEX) Project
a. Tarlac to Carmen,
Rosales, Section 1
b. Rosales to Urdaneta,
Pangasinan, Section 2
c. Urdaneta, Pangasinan
to Rosario, La Union,
Section 3
ROW
2. Daang Hari-SLEX Link
Road Project

Proposed:
1. NAIA Expressway

Project
Cost

Schedule

Status/Remarks

P 11.59 B
P 5.55 B
P 1.38 B
P 3.87 B

P 0.79 B
P 2.01 B

P 15.52 B

July 2010-May
2013
March. 2013May 2014
Jan. 2014-Jan.
2016

April 2012-June
2014
(Design and
Const.)

March 2014March 2016


(Construction)

On-going, 81.89%
ROW acquisition and advance
work for the Agno Viaduct for
Section 2 is on-going.
Feasibility Study for the realignment of Section 3 is being
finalized.
On-going, 29.57%
DED for Segment II has been
finalized

Approved by NEDA Board on


May 30, 2012.
Undergoing bidder due diligence
(4 prospective bidders
prequalified).
Bid submission is on 08 April
2013.

2. NLEX-SLEX Link
Connector Road

P 11.73 B

Oct. 2014-Dec.
2016
(Construction)

Approved by NEDA Board on


Nov. 29, 2012.
Approved by the NEDA Board
on 18 January 2013.
MPTDC and CITRA agreed the
terms and conditions in relation
to their respective rights and
obligations on the design,
construction, operation and
maintenance of the 5.5 km
common alignment.
Award project contract to
winning bidder in Dec. 2013
after the Swiss challenge
process

Page 14

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Name of Project
3. Cavite-Laguna (CALA)
Expressway

Project
Cost
P 35.58 B

Schedule

Status/Remarks

Jan. 2015-Dec.
2017
(Construction)

Approved by NEDA Board on


Jan. 18, 2013.

Loan Agreement was signed last


March 30, 2012. Procurement
of DE Consultant on-going.
The construction of this project
will be financed through ODA
while the Operation and
Maintenance (O & M) will be
under PPP.
Business Case Study to start by
March 2013 to Aug. 2013.

4. Central Luzon Link


Expressway (CLLEx),
Phase I, TarlacCabanatuan, Nueva Ecija
(ODA)

P 14.94 B

Dec. 2014March 2017


(Construction)

5. Central Luzon Link


Expressway (CLLEx),
Phase II, CabanatuanSan Jose, Nueva Ecija
6. Southern Tagalog Arterial
Road (STAR) Project,
Stage 2 (Phase II), Lipa to
Batangas City

P 14.20 B

TBD

P 1.96 B

March 2013
March 2015
(Construction)

Procurement of Project
Management Consultant (PMC)
has been completed. TCGI
Engineers is the PMC.
Procurement of contractor/s by
STAR Infrastructure
Development Corporation
(SIDC) is on-going.

7. C-6 Expressway and


Global Link (South
Section)

8. C-6 Extension (Flood


Control Dike Expressway)

9. Calamba-Los Baos Toll


Expressway

P 44.59 B

P 42.38 B

P 9.45 B

2014-2017
(Design and
Construction)

Supplemental Feasibility Study


completed by KOICA Study
Team in December 2012.

2014-2017
(Design and
Construction)

Requested Transaction Advisory


Services under PDMF of PPP
Center.
Draft Final Report for the
Business Case Study already
completed

2014-2017
(Design and
Construction)

Requested Transaction Advisory


Services under PDMF of PPP
Center
Draft Final Report for the
Business Case Study already
completed
Requested Transaction Advisory
Services under PDMF of PPP
Center

TBD - To Be Determined

Page 15

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

5. EFFECTIVE FLOOD CONTROL PROGRAM:


A. Strategic Policies:

River Basin Approach to Flood Management and Water Resource Utilization


Integrated Water Resource Management Approach in Coordination
Department/Agencies

with

Other

B. Flood Management Master Plan for Metro Manila and Surrounding Areas
OBJECTIVE:
After the flood events of Ondoy and Pepeng in September and October 2009, respectively that
caused severe damages in Metro Manila and Surrounding Areas, the World Bank has provided
a Technical Grant in the amount of $1.5 Million under the Global Facility for Disaster Reduction
and Recovery Trust Fund of the Australian Agency for International Development (AusAID).
A flood risk assessment study for the entire Metro Manila and Surrounding Basin Area was
undertaken from February 2011 to February 2012, to prepare a comprehensive flood risk
management plan for the same and to determine a set of priority structural measures, which will
still undergo individual feasibility studies and detailed design prior to implementation, including
non-structural measures that will provide sustainable flood management up to a designated
safety level and serve as the roadmap/vision of the Government until 2035 (23 years from now).
BOUNDARY OF STUDY AREA AND THE RIVER BASINS:

Page 16

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

The Study Area covers the entire Metro Manila and Surrounding Areas, particularly, provinces of
Rizal, Laguna and parts of Bulacan with a total area of 4,354 sq. km. or 435,400 hectares, which
is 7 times the size of Metro Manila and 2/3 that of Singapore.
It also encompasses the Pasig-Marikina River Basin, Malabon-Tullahan, Meycauayan, South
Paraaque-Las Pias and Laguna Lake Basins, including drainage basins. Administration Areas
in and around the Study Area include sixteen (16) cities and one (1) municipality in the National
Capital Region (NCR), sixty three (63) cities/municipalities in the CALABARZON Area and eight
(8) cities/municipalities in Bulacan with a population of 20,433,722 in and around the Study Area
and estimated population of 17,147,658 in the Study Area.
GUIDING PRINCIPLES FOR MASTER PLAN DEVELOPMENT:
1. Adopt Integrated Water Resources Management Principles and River Basin Approach
2. Develop safe society with resiliency to floods through:
a. Structural measures for the river basins and waterways
b. Structural measures for Laguna Lakeshore, and
c. Improvement of urban drainage system
3. Improvement of the Flood Information and Warning System (FIWS)
4. Establish integrated and consistent Flood Risk Management (FRM) institutional system
5. Strengthen community-based flood risk management Land Use and Solid Waste
6. Utilization of runoff waters as water resources, etc.
7. Reforestation and watershed management
THREE MAJOR FLOODING OCCURENCES:
1. Huge volume of water coming from Sierra Madre
2. Drainage capacity constraints in core area of Metro Manila
3. Low-lying communities around Manila Bay & Laguna Lake

Page 17

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

STRUCTURAL MITIGATION MEASURES:


There are eleven (11) recommended short-listed structural mitigation measures under the
Flood Management Master Plan for Metro Manila and Surrounding Areas that will serve as the
roadmap of the Government, which is envisioned to be implemented from today until 2035 (23
years).
These projects were prioritized according to: 1) severity of floods based on flood risk, flood area,
duration of floods and flood damage, 2) technical viability, 3) social and environmental viability in
preliminary level, and 4) aerial distribution of putting priority for the flood mitigation measures for
the rivers and Laguna Lake.
Hereunder are the 11 long-term projects with an estimated cost of around P351.72 Billion but is
still subject to validation of individual projects via comprehensive feasibility study and detailed
design that can either be financed using GOP funds or requested under ODA assistance.

Name of Project
1. Pasig-Marikina River Improvement and Dam Construction
2. Meycauayan River Improvement
3. Malabon-Tullahan River Improvement
4. South Paraaque-Las Pias River Improvement
5. East Mangahan Floodway (Cainta & Taytay River Improvement)
6. West Laguna Lakeshore Land Raising
7. Land Raising for Small Cities around Laguna Lakeshore
8. Improvement of the Inflow Rivers to Laguna Lake
9.

Manila Core Area Drainage Improvement

10. West Mangahan Area Drainage Improvement


11. Valenzuela-Obando-Meycauayan (VOM) Improvement (to be studied
further)
Total:

Est. Cost (PB)


198.435
B
14.040 B
21.635 B
17.335 B
25.901 B
25.185 B
7.158 B
0.637 B
27.257 B
5.522 B
8.613 B
P 351.718 B

Each of the above projects is independent, but they form integral measures for mitigating floods
in Metro Manila and Surrounding areas. Hence, considering the need for immediate
interventions to ease the flooding problems in these areas, several high-impact flood control
projects amounting to P5 Billion were identified for immediate implementation, to wit:

Page 18

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Name of Project
National Capital Region (NCR):
1. Valenzuela-Obando-Meycauayan (VOM)
Project

Total Cost

Released
Amount

820.0 M

820.0 M

2.

KAMANAVA Project, Phase I (KalookanMalabon-Navotas Area)

700.0 M

380.0 M

3.

Manila Bay Seawall Project

700.6 M

211.0 M

4.

Upper Marikina River Improvement Project


(Nangka River)

222.5 M

222.5 M

5.

Marikina River Dredging

50.0 M

50.0 M

6.

Mangahan Floodway Dredging

100.0 M

100.0 M

7.
8.

West Side of Mangahan Floodway Project


East Side of Mangahan Floodway Project

250.0 M
190.0 M

190.0 M

9.

Additional Projects

50.9 M

50.9 M

100.0 M

100.0 M

139.0 M

139.0 M

637.0 M

637.0 M

30.0 M

30.0 M

50.0 M

50.0 M

400.0 M

400.0 M

Region III:
1. Dredging of Labangan Channel, Hagonoy,
Bulacan
2. San Fernando-Sto. Tomas-Minalin Tail Dike
3.
4.
5.

Mitigation Measures for Breaches in the San


Fernando-Sto. Tomas-Minalin Tail Dike
Del Carmen-Balimbing Creek, City of San
Fernando, Pampanga
Orani Channel, Bataan

Region IV-A:
1. Sta. Maria-Mabitac River
2.

Sta. Cruz River

180.0 M

180.0 M

3.

San Pedro River

100.0 M

100.0 M

4.

Bian River

100.0 M

100.0 M

136.5 M

136.5 M

43.5 M

43.5 M

5,000.0 M

3,940.4 M

Nationwide:
1. Various Dredging Equipment
2.

Operation and Maintenance of Dredging


Equipment for Pasac-Delta Waterway,
Guagua and Sasmuan, Pampanga
Grand Total:

SARO No.
A-12-01110
dated 11/22/12
A-12-01111
dated 11/22/12
A-12-01112
dated 11/22/12
A-13-00684
dated 03/14/13
A-12-01111
dated 11/22/12
A-12-01112
dated 11/22/12
A-12-01125
dated 11/23/12
A-13-00684
dated 03/14/13
A-12-01112
dated 11/22/12
A-12-01113
dated 11/22/12
A-13-00684
dated 03/14/13
A-12-01111
dated 11/22/12
A-12-01112
dated 11/22/12
A-12-01112
dated 11/22/12
A-12-01112
dated 11/22/12
A-13-00117
dated 01/15/13
A-12-01113
dated 11/22/12
A-13-00684
dated 03/14/13
A-13-00684
dated 03/14/13
A-12-01112
dated 11/22/12
A-12-01125
dated 11/23/12
A-13-00141
dated 01/15/13
A-13-00141
dated 01/15/13
A-13-00141
dated 01/15/13
A-13-00141
dated 01/15/13
A-12-01111
dated 11/22/12
A-12-01111
dated 11/22/12

Page 19

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

Out of the P5 Billion, P3.940 Billion was already released for various flood control projects.
Attached is the detailed list of the High Impact Flood Control Projects with the corresponding
status.
In addition to the above, rehabilitation/improvement of twelve (12) existing pumping stations in
Metro Manila amounting to P1.600 Billion was likewise approved and released to MMDA.
Clearing of eight (8) major waterways in Metro Manila with an estimated 20,000 informal settlers
that will be provided decent resettlements is also part of an inter-agency efforts being
undertaken by the government.
NON-STRUCTURAL MEASURES:
1. Strengthening of the Flood Information and Warning System (FIWS)
Effective Flood Control Operation and Warning System (EFCOS) improvement
New telemetric rainfall and water level gauging stations
2. Capacity Building for Strengthening Community-based FRM
Update and implement Information and Education Campaign (IEC) programs
Rainfall and water level monitoring by Barangay Disaster Risk Reduction and
Management Councils (BDRRMCs)
Construction of evacuation routes and temporary evacuation centers
3. Improvement of Management Information System (MIS) for Disaster Risk Management
Improvement and development of MIS
Capacity building
4. Reforestation and Watershed Management

Page 20

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

B. STATE OF ROAD INFRASTRUCTURE IN THE PHILIPPINES:

Quality of Roads. According to the World Economic Forums Global Competitiveness Report,
the Philippines global ranking in terms of quality of roads improved from 114th in 2010-2011 to
87th in 2012-2013. Also, the quality of road index improved from 2.8 to 3.4 at par with
Indonesia and targeting to be in the 4 to 5 territory in 2016.
Quality of Roads Index

Legend: 1 = extremely underdeveloped; 7 = extensive and efficient by international standards


Source: World Economic Forum, The Global Competitiveness Report

Quality of Roads Ranking

Page 21

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

C. STATE OF PHILIPPINE ROAD NETWORK:

Legend
Road Classification
National Arterial
National Secondary

DPWH MANDATE:
PLAN, DESIGN, CONSTRUCT AND MAINTAIN NATIONAL ROADS AND BRIDGES AND
FLOOD CONTROL SYSTEMS IN MAJOR AND PRINCIPAL RIVERS
ROAD CLASSIFICATION:
National Arterial Road (NAR):
The main trunkline from northernmost Luzon down to Southern Mindanao interconnecting
major islands and those traversing backbone and across the islands and those that provides
direct access to important centers and areas vital for regional development and
emergencies.
National Secondary Road (NSR):
Other roads which complement national arterial roads to provide access to other main
population and production centers
The National Roads covered by the Autonomous Region for Muslim Mindanao (Maguindanao,
Lanao del Sur, Sulu, Tawi-Tawi and Basilan except the capital Isabela City) are not included in the
DPWH national road data base.

Page 22

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

D. 2010-2016 TARGET VS. ACTUAL OUTCOMES:


ROAD UPGRADING (GRAVEL TO PAVED):
The government targets to completely pave by 2016 the 31,242 km national road network (i.e.,
7,256 km unpaved sections of the national arterial and secondary road network). To achieve this,
the government (DPWH) has allocated P50 Billion from 2010 to 2012 for the paving of about 2,320
kms and a total of an estimated P125 Billion is still needed for the paving of the remaining 4,937
kms.

Note: Figures may not add up due to rounding. The annual targets are subject to change based on
actual accomplishment of upgrading (gravel to paved) projects.

Note: Original target is based on the 2012 SONA inputs.


Out of the 2,320 kms of national road targeted to be paved from January 2010 to December 2012,
86.5% (based on revised targets) or 2,006 kms were accomplished as of December 31, 2012. The
2,006 kms represents an accomplishment of 27.6% vs. the target of 7,256 kms to be paved by end
of 2016.

Page 23

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

NATIONAL BRIDGES TARGET OUTCOMES

Bridge Length (Lineal Meters)

(In Lineal Meters)

Year

Note: The annual bridge targets/prioritization are still subject to change based on the actual accomplishments
and due to the occurrence of calamity (floods and earthquake) and other unforeseen circumstances that
causes damage to the bridge structures.

Page 24

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

E. PUBLIC INVESTMENT PROGRAM:

Amount (Billion Pesos)

2005-2013 DPWH Capital Outlays (Projects)


Based on GAA

+ 45%

Year

- - - - with PDAF (Pork Barrel)

Page 25

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

FY 2012 vs. FY 2013 DPWH BUDGETS (Based on GAA)


Amount in Billion Pesos

DWPH FY 2013 CAPITAL OUTLAYS (PROJECTS)


P 144.34 Billion
Of the P144.34 Billion total investment requirement in 2013, P100.93 Billion (69.93%) is earmarked
for the highways sector, P15.85 Billion (10.98%) for flood control works and P27.57 Billion (19.09%)
for other projects, as shown below:

Page 26

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

F. INFRASTRUCTURE PROGRAM FOR MINDANAO:


The DPWH Budget (Capital Outlays) significantly increased by 45% (P45 Billion) from P99 Billion in
2012 to P144 Billion in 2013. Excluding the inter-regional and nationwide projects, the total regional
allocation for 2013 is P108 Billion, of which an initial 26% or P28 Billion is programmed for
Mindanao. The P 28 Billion allocation for Mindanao is 97% (P13.6 Billion) higher from the P14
Billion in 2011. Hereunder is the breakdown of the nationwide regional infrastructure program:
2011-2013 DPWH BUDGETS (CAPITAL OUTLAYS)
REGIONAL ALLOCATION
(In Billion Pesos)

TRANSITION INVESTMENT SUPPORT PROGRAM FOR ARMM (ISP-ARMM):


The National Government has prepared a Stimulus Development Plan (SDP) for Autonomous
Region for Muslim Mindanao (ARMM) to implement the reform roadmap towards economic recovery
and development. Under the plan, the Government will fund priority and strategic projects
promoting basic services, basic infrastructure and livelihood development that have been identified
by various national agencies. The development of national road infrastructure is one of the
highlights of the Plan.
The Department of Public Works and Highways (DPWH), which has been designated as the lead
agency to implement these projects, has created a Task Force to oversee its implementation. The
amount of P2.851 Billion has been approved by the President and released by the Department of
Budget and Management under SARO No. A-11-01651 dated 04 November 2011 for the
rehabilitation, upgrading and improvement of various national roads and bridges in the following
provinces covered by ARMM:
ISP-ARMM OVERALL STATUS
As of January 31, 2013

Page 27

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

An additional P7.32 Billion was requested for release to the Department of Budget and
Management per letter dated January 24, 2013 for the implementation of the TISP-ARMM, Phase II.
Hereunder is the detailed status of the eleven (11) road infrastructure projects covering twenty-two
(22) contract packages under ISP-ARMM which involves the rehabilitation/upgrading of an
estimated length of 128 kms:

Hereunder is the status of the five (5) bridge infrastructure projects under ISP-ARMM:

Note - Bato-Bato and Kiaokaran Bridges were implemented as one contract package.

Page 28

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

G. STATUS OF FUND UTILIZATION:


FY 2011 vs. FY 2012 FUND UTILIZATION
As of February 25, 2013

In 2012, out of the total allotment of P194 Billion, 82% (P159 Billion) were already obligated.
Out of the P159 Billion, 90% (P143 Billion) were disbursed, this is 35% (P37 Billion) higher than
the P106 Billion total disbursement for full year 2011.

Amount (Billion Pesos)

Of The P194 Billion total allotment received by DPWH, P109 Billion is from the DPWH Regular
GAA Budget.

FY 2012 FUND UTILIZATION


As of February 25, 2013

Amount (Billion Pesos)

193.65 B
57.66B
(Extended/
Cont.)

159.41 B
142.92 B
55.37B
(Extended/
Cont.)

135.99B
(Current)

104.04B
(Current)

*
(NCA/LDDAP/WA/TRA)

Page 29

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

FY 2013 FUND UTILIZATION


As of February 28, 2013

Amount (Billion Pesos)

171.50 B
41.22B
(Extended/
Cont.)

130.28B
(Current)

49.64 B
P10.96B
(Extended/Cont.)

17.81 B

38.68B
(Current)
(NCA/LDDAP/WA/TRA)

Page 30

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

H. PRIORITY OVERSEAS DEVELOPMENT ASSISTANCE (ODA) PROJECTS:


Name of Project

Project Cost
(Civil Works)

Implementation
Schedule

Status/Remarks

Completed:
Highway Projects:
Central Mindanao Road Project, 26th Yen JICA
Loan Package, PH-P237
a. Contract Package 2, North UpiMaguindanao/Sultan Kudarat Bdry. Road
b. Contract Package 3, Maguindanao/Sultan
Kudarat Bdry.-Lebak-Kalamansig Road
* Excluding CP1implemented using local funds.
2. Arterial Road Bypass Project (Phase I), Plaridel
Bypass Road Project, JICA PH-P236
a. Contract Package 1, (Sta. 32+970 Sta.
39+625)
b. Contract Package 2,(Sta. 39+625 Sta.
47+700)
3. Austrian-Assisted DPWH Bridge Construction
Acceleration Project for Calamity-Stricken
Areas
Flood Control Projects:
4. Iloilo Flood Control Project II, JICA PH-P230
a. Contract Package 1,Const. of Jaro
Floodway and Improvement of Tigum &
Aganan Rivers
b. Contract Package 2,Improvement of Iloilo
River, Upper Ingore Creek & Jaro River
Mouth Section
c. Contract Package 3, Development of
Relocation Site for Stage 1
1.

P 1.009 B

June 2009-Nov. 2011

Completed

P 0.897 B

Jan. 2009-Dec. 2011

Completed

P 1.559 B

Jan. 2009-Nov. 2011

Completed

P 0.594 B

May 2011-Feb. 2013

Completed

P 1.615 B

July 2008-July 2011

Completed- 19 Bridges

P 2.229 B

April 2006-April 2012

Completed

P 1.182 B

March 2006-Sep. 2009

Completed

P 0.029 B

Feb. 2003-July 2004

Completed

P 2.942 B
P 0.713 B
P 0.213 B

Dec. 2007-Feb. 2010


June 2011-Oct. 2013
May 2011-Nov. 2012

Completed 17 Bridges
On-going 1 Bridge
Suspended effective

P 0.440 B
P 2.917 B
P 2.372 B

May 2012-April 2014


March 2006-June 2009
Jan 2009-March 2012

May 2012 due to


revision of the design
and ROW problem
On-going 6 Bridges
Completed 64 Bridges
Completed 42 Bridges

P 7.045 B

Nov. 2009-Dec. 2013

P 1.862 B

March 2010-Sep. 2012

Completed

P 1.833 B

Nov. 2011-Nov. 2014

Completed-4 Bridges,

On-going:
Highway Projects:
5. Urgent Bridges Construction Project for Rural
Development (UBCPRD), JICA PH-P231
a. Contract Package I
b. Contract Package II-A *
c. Contract Package II-B *

6.

7.

d. Contract Package II-C *


e. Contract Package III
f. Contract Package IV
* Implemented using local funds
Mega Bridges for Urban and Rural
Development Project (MBURDP), French
Government Assisted
Spanish Assisted-Bridge
Construction/Replacement project
a. Supply and Services (91 Bridges) including
const. of 1 Pilot Bridge (Mompong Bridge)
b. Construction (47 Bridges) by DPWH using
local funds.
c.

Construction of (43 Bridges) by Centunion


using Loan Proceeds

P 1.275 B

Jan. 2013-Dec. 2015


(If implementation will
continue as planned)

On-going, 4 Flyovers
and 43 Unibridges (50
spans) are already
completed

On-going-35 Bridges,
Under-Preconst.-8
Bridges
Proposed restructuring
contract of Centunion
using loan proceeds is
deferred due to the
on-going Senate Blue
Ribbon Committees
investigation on the
Page 31

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

implementation of the
Presidents Bridge
Program.
8.

9.

Millennium Challenge Corporation (MMC)


Assisted Secondary National Roads
Development Program (SNRDP) Wright-TaftBorongan-Guiuan Road Project
a. CP 1, Buray - Tinani Road
b. CP 2, Tinani-Taft-Sulat Road
c. CP 3, San Julian-Borongan-Balangkayan Rd
d. CP 4, Llorente - Guiuan Road
National Roads Improvement and Management
Program, Phase II, NRIMP 2 (World BankAssisted)

10. Road Upgrading and Preservation Project,


RUPP (JICA-Assisted)

11. Mindanao Roads Improvement Project, Saudi


Fund for Development, Loan No. 1/433
a. Cotabato City East Diversion Road Project
b. Lake Lanao Circumferential Road Project
Contract Package 2A-New, MarawiMasiu-Bayang Section
Contract Package 2B-New, BayangGanassi-Pualas Section
c. Basilan Circumferential Road Project
Contract Package 3A-New, IsabelaLamitan-Tipo-tipo-Tumahubong Section
Contract Package 3B-New, IsabelaMaluso-Sumisip-Tumahubong Section
Contract Package 3A-1, Tipo-tipoSumisip-Tumahubong Section
Contract Package 3B-1, MalusoSumisip-Tumahubong Section
12. Rural Roads Network Development Project,
Phase III, JICA, 24th YCP, PH-P220
a. CP III, Libon-Marocmoc-Pantao Road,
Albay
b. CP IV, Looc-Odiongan-San Andres Road,
Romblon
c. CP IV-A, Six (6) Bridges and Approaches
along Looc-Odiongan-San Andres Road
d. CP VIII, Prosperidad-Lianga Road, Agusan
del Sur / Surigao del Sur
e. CP IX, Bdry. Iloilo/Antique-Anini-y-V.
Jimenez Road, Antique

On-going
Bidding on Feb. 2013
On-going
Bidding on Jan. 2013

P 0.802 B
P 2.456 B
-

Oct. 2012-April 2014


Jul. 2013-Aug. 2015
Sept. 2012-Sept. 2015
Mar. 2013-Aug. 2015

P 29.394 B
(Total Cost)

April 2009-Dec. 2014


(Loan Effectivity)

On-going

P16.194 B

Dec. 2012-July 2018

Consultancy Services
for Upgrading/
Improvement (UI)
Component and Asset
Preservation (AP)
Component on-going.

P 0.709 B

Nov. 2012-May 2014

On-going

P 0.422 B

600 c.d.

Resolution Award

P 0.420 B

600 c.d.

Resolution Award

dated Dec 11, 2012


dated Dec 14, 2012
P 0.415 B

600 c.d.

Contract Agreement

P 0.415 B

600 c.d.

Contract Agreement

P 0.112 B

Aug. 2012-Jan. 2014

On-going

P 0.112 B

Sep. 2012-Feb. 2014

On-going

P 0.231 B
P 0.681 B

Dec. 2007-Sep. 2009


July 2007-June 2010

Completed
Completed

P 0.141 B

Jan. 2012-Jan. 2013*

On-going

P 0.420 B

March 2009-Nov. 2010

Completed

P 0.910 B

July 2009-March 2012

Completed

P 4.914 B

Feb. 2004-Dec. 2012

Completed- 111
Bridges; On-going-2
Bridges

under process
under process

* Request for Time Extension with the revised


completion date of January 2013 is under
process.
Excludes sub-projects under RRNDP Program
implemented using local funds.

13. Austrian-Assisted DPWH Bridge Construction /


Replacement Project

Page 32

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS


14. Korean Economic Development Cooperation
Fund
a. Gapan-San Fernando-Olangapo Road,
Phase I, Loan No. PHL-8
b. Gapan-San Fernando-Olangapo Road,
Phase II, Loan No. PHL-10
c. Bacolod (Silay) Airport Access Road,
Negros Occidental, Loan No. PHL-09

P 1.199 B

Oct. 2008-June 2011

Completed

P 0.691 B

Feb. 2012-Oct. 2014

On-going

P 0.401 B

Feb. 2012-April 2013

On-going

P 1.269 B

May 2010-June 2013

Out of the 31 Contract


Packages, 21 CPsCompleted, 9 CPs-Ongoing and 1 CP-for
termination.

P 0.846 B

June 2012-March
2013

Out of the 11 Contract


Packages, 7 CPsUnder Preconst.
Activities, 4 CPs-Ongoing

P 0.147 B

Jan. 2013 Feb. 2014

CP 2, Lower Porac-Gumain River


Diversion Channel
CP 3A, City of San Fernando Flood
Control Works (San Fernando River)
CP 3B, City of San Fernando Flood
Control Works (Outlet Channel and
Bridges)
CP 4, Excavation/Dredging of Major Rivers

P 1.668 B

May 2010-Aug. 2012

Contract Agreement
for Concurrence of
JICA.
Completed

P 0.168 B

Aug. 2009-May 2011

Completed

P 0.509 B

March 2011-Feb. 2013

On-going

P 0.924 B

Feb. 2010-Jan. 2013

On-going

CP 5, Raising of Roads and Construction


of Side Drainage
CP 6, Flood Mitigation Works in Guagua

P 0.045 B

Nov. 2012-May 2013

On-going

P 0.196 B

Dec. 2009-Sep. 2011

Completed

CP 7, Excavation/Dredging of Local
Drainage Channels, Road Raising and
Const. of Bridges

P 0.336 B

Jun. 2013-Sep. 2014

P 1.155 B

Dec 2011-March 2013

Out of the 48 Contract


Packages, 46 CPsCompleted, 1 CPSuspended, 1 CP
Cancelled

P 0.894 B

June 2012-Dec. 2012

Out of the 14 Contract


Packages, 10 CPsOn-going, 4 CPUnder Pre-Const.
Activities

15. Post Ondoy and Pepeng Short-Term


Infrastructure Rehabilitation Project, JICAAssisted (Road and Bridge Component)
a. Original

b.

Supplemental

Flood Control Projects:


16. Mt. Pinatubo Hazard Urgent Mitigation Project,
Phase III, JICA, PH-P241
a. CP 1, Excavation/Dredging of Local
Drainage Channels and Const. Bridges
b.
c.
d.

e.
f.
g.
h.

17. Post Ondoy and Pepeng Short-Term


Infrastructure Rehabilitation Project, JICAAssisted (Flood Control Component)
a. Original

* Includes the 1 Contract Package


amounting to P7.83 Million that was
cancelled
b.

Supplemental

Pre-Qualification
Results for JICA
Concurrence

Page 33

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS


18. Pasig-Marikina River Channel Improvement
Project (PMRCIP), Phase II, JICA PH-P239
a. Contract Package 1A-Lower Pasig River
b. Contract Package 1B-Upper Pasig River

P 2.943 B
P 1.824 B

July 2009-May 2013


July 2009-June 2012

On-going
Completed

P 6.241 B
(Total Cost)

July 2012-June 2016


(Loan Effectivity)

Under Pre-Const.

P 1.167 B

June 2013-June 2016

Waiting for the

P 0.659 B

May 2013-July 2015

21. Samar Pacific Coastal Road, PalapagMapanas-Lapinig-Jipapad-Arteche-San


Policarpo (KEDCF)

P 1.253 B

2014-2016

Approved by the
NEDA-ICC on March
22, 2012. Advance
procurement of
consulting services ongoing.

22. Baler-Casiguran Road, Aurora (KEDCF)

P 1.092 B

2014-2016

Project Appraisal was


conducted by the
EDCF Mission on
November 12-16,
2012.
Advance procurement
of consulting services
on-going.

P 14.940 B

Dec. 2014-March
2017

Loan Agreement was


signed last March 30,
2012. Procurement of
DE Consultant ongoing.

Proposed:
Highway Projects:
19. Road Improvement and Institutional
Development Project (ADB-Assisted)
20. Arterial Road Bypass Project, (Phase II),
Plaridel Bypass Road Project, JICA PH-P250
a. Contract Package III, (Sta. 047+400 Sta.
049+625)

b.

Contract Package IV, (Sta. 049+625 Sta.


057+362.35)

23. Central Luzon Link Expressway (CLLEx),


Phase I, Tarlac-Cabanatuan, Nueva Ecija

concurrence of PQ and
Bidding Documents by
JICA prior to
advertisement
Waiting for the
concurrence of PQ and
Bidding Documents by
JICA prior to
advertisement

The construction of
this project will be
financed through ODA
while the Operation
and Maintenance (O &
M) will be under PPP.
Flood Control Projects:
24. Flood Risk Management Project (FRIMP) in
Cagayan, Tagoloan and Imus Rivers (JICAAssisted)

P 2.980 B

March 2015-Feb. 2018

Procurement of
Consultancy Services
for Detailed
Engineering Design is
on-going.
The request for
proposals is under
review by DPWH
based on JICA
comments on the
same.
Page 34

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS


25. Pasig-Marikina River Channel Improvement
Project (PMRCIP), Phase III, JICA PH-P252

P 7.545 B

Sept. 2013-Aug. 2016

Detailed Design is ongoing.


Procurement of
Consultant for
Construction
Supervision is ongoing.

26. Integrated Disaster Risk Reduction and Climate


Change Adaptation Measures in the Low Lying
Areas of Pampanga Bay (KEDCF)

P 2.956 B

To be determined

Approved by the
NEDA-ICC on March
22, 2012.
Technical assistance
was requested from
EDCF for the conduct
of a full-scale
Environmental and
Social Impact
Assessment.

Out of the P5Billion,


P3.94 Billion was
already released for
various flood control
projects.

Several high-impact
flood control projects
will be implemented as
immediate
interventions to ease
the flooding problems
at priority areas.

27. Flood Management Master Plan for Metro


Manila and Surrounding Areas

P 351.718 B
(estimate)
For eleven
(11) Flood
Control
Projects
P 5.0 B for
critical areas
based on the
Master Plan

Note: ODA Project Status as of December 2012

Page 35

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

I.

CLIMATE CHANGE ADAPTATION STRATEGIES:


1. Water Sector Restructuring Principles
Current Status and Problems:
 Limited water availability when and where needed for various uses;
 Fragmented institutions with water related functions
 Floods is happening in many parts of the country urban and rural areas;
 Droughts and water scarcity happening in some parts of the country
 Water quality is poor and polluted;
 Ecosystems are in danger;
 Lack of scientific decision support systems and reliable updated data
Restructuring Guiding Principles:
 Good water governance for water security
 Integrated water resources management (including irrigation, domestic water supply
and sanitation, integrated flood management, hydropower, tourism and other
competing uses of water)
 River basin approach (priority on major rivers)
 Integrated and accurate data collection and analysis
 Use of scientific decision support systems for water resources management including
flood modelling and warning system
 Development of water resources include mitigation of water-related hazards
2. Rainwater Collection Systems/Retarding Basins
 The amount of P38.4 Million (2011) and P39.6 Million (2012) was released to various
ROs and DEOs for the installation of RWCS
 627 RWCS installed in various ROs and DEOs, public schools and other public
buildings as of December 2012.
 P50 Million is included in the DPWH FY 2013 Budget for the construction of
additional units of RWCS
 MOA created between DPWH and DILG on the construction of RWCS
 Proposed MOA with the DepEd to incorporate RWCS in the standard design of
schools thru its PPP School Building Program
 Working with the MMDA to recommend the enactment of an ordinance to require
business/commercial establishments to provide programs that would reduce/control
flooding in Metro Manila.
 The provision of underground detention tanks as part of storm water management
system, particularly in flood prone urban areas to temporarily store flood water shall
be a consideration in the design of the drainage system.
3. Clearing of Waterways
Clearing and Cleaning along Manila Bay:
 Continuous Clean-up of the Manila Bay and identification of Informal Settlers (IS)
along waterways and esteros in Compliance to the Supreme Court Decision dated
May 18, 2009 and February 15, 2010 on the continuing mandamus for the
sustainable development of the Manila Bay
 As of December 2012, a total of 15,510 structures and 230 fish pens identified in
Region III and IV-A along rivers, waterways and esteros of the Manila Bay.
Clearing of Rivers and other waterways nationwide:
 A total of 612.72 km covering 220 Rivers and 194 sections of drainage canals were
cleared/cleaned and desilted as of 1st quarter of 2012. Further, a total of 422 illegal
structures along rivers under the bridges in Region II were dismantled.

Page 36

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

2012 STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMS

4. Bio-Engineering Technology
The DPWH is now taking steps to support the usage of indigenous products and
technologies in the implementation of infrastructure projects to help the governments
effort in promoting green engineering and minimizing the effects of climate change. A
Department Order No. 41, series of 2010, was issued to prioritize the usage of coconut
bio-engineering products/solutions in all DPWH projects/activities especially those
projects involving slope stabilization, soil conditioning, soil erosion prevention and/or
hydroseeding.
The usage of the coco-fiber products in the engineering industry will not only beneficial
for the environment but it will also provide employment opportunities for the coconut
farmers in rural areas.