Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 72

Project : CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg.

2), LIBERTAD
CENTRAL ELEMENTARY SCHOOL

Location : Butuan City, Agusan del Norte

Computation of the Estimated Project Duration

1,500,000.00 28,792,843.61 (<---APPROPRIATION)


60 1,151.71
1 REDUCTION FACTOR
1,151.71

143 25.5 number of weeks/6


10 Mobilization
21 Sundays
26 rainy days
5 26 Holidays
205 days 52 Total Calendar Days
207 days
6.9 months
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
Office of the District Engineer
Butuan City District Engineering Office
R. Palma St., Butuan City

EXECUTIVE SUMMARY
(Detailed Program of Works)

FOR : The District Engineer


This Office

THRU: Assistant District Engineer

1.)   SUBJECT : CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL


Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City,
(Project Title/Location) Agusan del Norte

2.)  ACTION RECOMMENDED FOR APPROVAL

3.)  IMPLEMENTING OFFICE : DPWH – Butuan City District Engineering Office

4.)  PREPARED BY : ENGR. GINALYN L. CULTURA

5.)  DESIGN DATA

5.1) Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (with
parapet, stairwall 5m width, steel casement windowat rear portion with
security grills for the front jalousie windows, fire protection system,
overhead tank and cistern)
( 9.5m x 55.00m )

5.2) Appropriation : ₱28,792,843.61

5.3) Source of Funds : BEFF 2020

5.4) Classification : BUILDING

5.5) Limits :

5.6) Net Length :

5.7) No. of Calendar Days : 205 Calendar Days

6.)   REMARKS

6.1) Prices and Unit Costs used in the Detailed Unit Price Analysis (DUPA) were Based
on the approved Price Monitoring Committee for the 3rd Quarter C.Y. 2019

6.2) The authority to approved this program of work is in accordance with the provision
and guidelines of D.O. # 20 series of 2018.

In view of the foregoing, this program of work is respectfully recommended for your
Consideration and Approval.

LEOPOLDO A. LOMONSOD
Engineer III
Chief, Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII ANNEX A
*
Butuan City District Engineering Office
Butuan City
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Project : ELEMENTARY SCHOOL Appropriation : 28,792,843.61
( 9.5m x 55.00m ) Source of Fund : BEFF 2020
Project ID : Target Start Date : Upon Availability of Funds
Location : Butuan City, Agusan del Norte Total Project Duration : 205 C.D
Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (with parapet, stairwall 5m width, steel casement window No. of Pre-determined : 26 C.D
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern) Unworkable Days

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 176,800.00
Part II Other General Requirements 1.99% 448,089.64
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.83% 637,712.75
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 42.85% 9,645,903.72
PART C FINISHING WORKS 36.80% 8,283,898.31
PART D PLUMBING/SANITARY WORKS 7.53% 1,694,636.90
PART E ELECTRICAL WORKS 2.64% 594,613.32
PART F MECHANICAL WORKS 4.57% 1,029,386.21

Total 100% 22,511,040.85


EQUIPMENT: BREAKDOWN OF EXPENDITURES:
DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
Plate Compactor 1 1. Labor 3,565,812.19 A. Total Direct Cost 22,511,040.85
Concrete Vibrator 1 2. Materials 17,152,932.98 B. OCM and Profit 4,842,187.53
One Bagger Mixer 1 3. Rental of Equipment 1,810,123.59 C. Value Added Tax (5%) 1,367,661.43
Bar Cutter 1 4. Provisional Sum / Daywork D. Total Construction Cost 28,720,889.81
Bar Bender 1 5. OCM and Profit 4,842,187.53 E. Eng'g & Administrative Overhead 71,802.60
Welding Machine 2 6. Value Added Tax (5%) 1,367,661.43 F. RROW Acquisition
Cutting Outfit 1 7. EAO, 0.5% 71,802.60 G. Physical Reserved (Contingency)
Set of Minimum Material Testing Equipment 1 8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 28,792,692.41 H. TOTAL ESTIMATED COST 28,792,692.41
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

GINALYN L. CULTURA RONELO ANTHONY P. SARCEDA LEOPOLDO A. LOMONSOD ERVIN P. SALANG JOSE CAESAR A. RADAZA
Engineer II Engineer II Engineer III Asst. District Engineer District Engineer
Planning & Design Section Planning & Design Section Planning & Design Section
Concurred:

MARILOU B. DEDUMO, PhD., CESO V


School Division Superintendent
Butuan City
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING Appropriation :


Source of Fund :
Project ID : Target Start Date :
Location : Total Project Duration :
Project Description :

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 176,800.00
Part II Other General Requirements 448,089.64
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 637,712.75
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 9,645,903.72
PART C FINISHING WORKS 8,283,898.31
PART D PLUMBING/SANITARY WORKS 1,694,636.90
PART E ELECTRICAL WORKS 594,613.32

Total

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 3,565,812.19 A. Total Direct Cost 22,511,040.85
2. Materials 17,152,932.98 B. OCM and Profit 4,842,187.53
3. Rental of Equipment 1,810,123.59 C. Value Added Tax 1,367,661.43
4. Provisional Sum / Daywork D. Total Construction Cost 28,720,889.81
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 4,842,187.53 E. Eng'g & Administrative Overhead, % 1,041,690.30
6. Value Added Tax 1,367,661.43 F. RROW Acquisition
7. EAO, % G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST H. TOTAL ESTIMATED COST 29,762,580.11

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

PART I FACILITIES FOR THE ENGINEER

A.1.1 Offices and Laboratory for the Engineer

A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) 6.80 mo 176,800.00 26,000.00 30,030.00 0.79

TOTAL OF PART A 176,800.00

PART II OTHER GENERAL REQUIREMENTS

B.3 Permits and Clearances 1.00 l.s. 139,150.65 139,150.65 146,108.18 0.62

B.5 Project Billboard/ Sign Board 1.00 ea 4,553.88 4,553.88 5,833.52 0.02

B.7 (2) Occupational Safety and Health Program 1.00 l.s. 85,523.92 85,523.92 98,780.13 0.38

B.9 Mobilization/Demobilization 1.00 l.s. 218,861.19 218,861.19 229,804.25 0.97

TOTAL OF PART II 448,089.64

Project ID

(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

PART A EARTHWORKS

801(1) Removal of Structure and Obstruction 1.00 l.s. 106,452.50 106,452.50 136,365.65 0.47

803(1)a Structure Excavation (Common Soil) 469.24 m3 108,776.68 231.81 296.95 0.48

804(1)a Embankment from Structure Excavation 383.40 m3 58,612.35 152.88 195.83 0.26

804(1)b Embankment (Borrow) 240.04 m3 220,326.76 917.88 1,175.80 0.98

804(4) Gravel Fill 98.95 m3 143,544.46 1,450.68 1,858.32 0.64

TOTAL OF PART A 637,712.75

PART B PLAIN AND REINFORCED CONCRETE WORKS

900(1)c1 Structural Concrete, Class A, 28 days (4000 psi) 391.83 m3 2,521,055.99 6,434.06 8,242.03 11.20

900(1)c2 Structural Concrete, Class A, 28 days (Slab on Fill, 2500 psi) 56.28 m3 319,723.83 5,680.95 7,277.30 1.42

902(1)a Reinforcing Steel, Grade 40 34,876.10 kg 2,022,022.13 57.98 74.27 8.98

902(1)b Reinforcing Steel, Grade 60 70,518.00 kg 4,088,443.28 57.98 74.27 18.16

903(2) Formworks and Falseworks 1.00 l.s. 694,658.49 694,658.49 889,857.53 3.09

TOTAL OF PART B 9,645,903.72


CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

PART C FINISHING

C.1 Termite Control Works

1000(1) Soil Poisoning 170.17 L 64,832.91 380.99 488.05 0.29

Sub-Total C.1 64,832.91

C.2. Masonry Works

1046(2)a1 CHB Non Load Bearing Wall (including Reinforcing Steel), 100 mm 219.20 m2 135,361.64 617.53 791.05 0.60

1046(2)a2 CHB Non Load Bearing Wall (including Reinforcing Steel), 150 mm 1,073.91 m2 1,036,363.81 965.04 1,236.21 4.60

Sub-Total C.2 1,171,725.45

C.3 Fabricated Materials

1003(17) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 38,879.52 38,879.52 49,804.66 0.17

1004(2) Finishing Hardware 1.00 l.s 54,600.00 54,600.00 69,942.60 0.24

1005(1) Casement Steel Window 108.00 m2 384,630.60 3,561.39 4,562.15 1.71

1005(5) Steel Window (Window Grills) 1.00 l.s 56,735.57 56,735.57 72,678.27 0.25

1006(6) Steel Doors and Frames 1.00 l.s. 23,819.77 23,819.77 30,513.13 0.11

1008(1)c Aluminum Glass Window (Awning Type) 2.16 m2 6,041.59 2,797.03 3,583.00 0.03

1009(1)a Jalousie Window (Glass) 48.00 m2 72,947.38 1,519.74 1,946.78 0.32

1010(4) Wooden Doors 1.00 l.s. 366,311.72 366,311.72 469,245.32 1.63

Sub-Total C.3 1,003,966.15

C.4 Finishing Works

1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame) 649.00 m2 547,199.99 843.14 1,080.07 2.43

1003(15)c Moulding (Pre-cast) 265.60 m. 62,568.19 235.57 301.77 0.28

1016(1)a Waterproofing (Cement-Base) 183.00 m. 103,790.04 567.16 726.53 0.46

1018(1) Glazed Tiles and Trims 118.51 m2 144,670.10 1,220.74 1,563.77 0.64

1018(2) Unglazed Tiles 49.28 m2 51,669.50 1,048.49 1,343.11 0.23

1027(1) Cement Plaster Finish 2,443.24 m2 442,560.46 181.14 232.04 1.97

1038(1) Reflective Insulation 516.15 m2 98,724.92 191.27 245.02 0.44

1051(6) Railings 1.00 l.s. 221,970.90 221,970.90 284,344.73 0.99

Sub-Total C.4 1,673,154.10


CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

C.5 Painting Works

1032(1)a Painting Works (Masonry/Concrete) 3,446.00 m2 1,065,934.03 309.33 396.25 4.74

1032(1)b Painting Works (Wood) 209.08 m2 55,316.63 264.57 338.92 0.25

1032(1)c Painting Works (Steel) 143.65 m2 43,066.77 299.80 384.05 0.19

Sub-Total C.5 1,164,317.43

C.6 Roof Framing and Roofing Works

1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.4 mm thk 572.00 m2 407,974.16 713.24 913.66 1.81

1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.5 mm thk.) 55.80 l.m. 17,959.35 321.85 412.29 0.08

1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk.) 22.80 l.m. 10,913.67 478.67 613.18 0.05

1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk.) 10.00 l.m. 6,114.31 611.43 783.24 0.03

1047(2)a Structural Steel, Trusses 10,076.43 kg 928,597.08 92.16 118.05 4.13

1047(2)b Structural Steel, Purlins 17,209.50 kg 1,637,828.31 95.17 121.91 7.28

1047(3)a Bolts 107.10 kg 18,161.97 169.58 217.23 0.08

1047(6) Metal Structure Accessories (Steel Plates) 1,678.59 kg 119,345.31 71.10 91.08 0.53

1047(7)b Metal Structure Accessories (Sagrods) 235.00 kg 15,104.28 64.27 82.33 0.07

1047(4) Metal Structure Accessories (Cross Bracing) 520.85 kg 34,215.18 65.69 84.15 0.15

1047(3)c Metal Structure Accessories (Turnbuckle) 44.00 ea. 9,688.65 220.20 282.07 0.04

Sub-Total C.6 3,205,902.27 - -

TOTAL OF PART C 8,283,898.31

PART D PLUMBING/SANITARY WORKS

1001(5)a Catch Basin 28.00 ea 62,823.35 2,243.69 2,874.17 0.28

1001(8) Sewer Line Works 1.00 l.s. 137,752.26 137,752.26 176,460.65 0.61

1001(9) Storm Drainage and Downspout 1.00 l.s. 237,258.38 237,258.38 303,927.98 1.05

1001(11) Septic Vault 1.00 l.s. 194,420.25 194,420.25 249,052.35 0.86

1002(4) Plumbing Fixtures 1.00 l.s. 236,991.68 236,991.68 303,586.34 1.05

1002(24) Cold Water Lines 1.00 l.s. 65,128.16 65,128.16 83,429.18 0.29

1002(26) Cistern 1.00 l.s 760,262.82 760,262.82 973,896.67 3.38

TOTAL OF PART D 1,694,636.90


CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

PART E ELECTRICAL

1100(10) Conduits, Boxes, and Fittings 1.00 l.s. 88,354.64 88,354.64 113,182.29 0.39

1101(33) Wires and Wiring Devices 1.00 l.s. 307,416.21 307,416.21 393,800.17 1.37

1102(1) Panel Boards with Main and Branch Breakers 1.00 l.s. 99,407.50 99,407.50 127,341.01 0.44

1103(1) Lighting Fixtures and Lamps 1.00 l.s. 99,434.97 99,434.97 127,376.19 0.44

TOTAL OF PART E 594,613.32

PART F MECHANICAL - - - - - -

1202(1) Fire Protection System 1.00 l.s. 329,752.83 329,752.83 422,413.37 1.46

1201(1) Water Pumping System 1.00 l.s. 451,002.09 451,002.09 577,733.68 2.00

1200(14) Ventilation 1.00 l.s. 248,631.29 248,631.29 318,496.68 1.10

TOTAL OF PART F - - 1,029,386.21 - -

TOTAL OF PART III 21,886,151.21

TOTAL OF (Project ID) 21,886,151.21

GRAND TOTAL 22,511,040.85 100.00


CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Dump Truck 12 yd3 2 20
2 Plate Compactor 5 hp 1 21
3 Concrete Vibrator 5 amp 1 22
4 One Bagger Mixer 4 - 6 ft3/min 1 23
5 Bar Cutter 1 24
6 Bar Bender 1 25
7 Welding Machine 500 amp 2 26
8 Cutting Outfit 1 27
9 Set of Minimum Material Testing Equipment 1 28
10 29
11 30
12 31
13 32
14 33
15 34
16 35
17 36
18 37
19 38
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
A.1.1 Offices and Laboratory for the Engineer
Provision of Field Office for the Engineer As Submitted 0.79 6.80 mo - - 176,800.00 26,000.00 176,800.00 10% 17,680.00 9,724.00 204,204.00
A.1.1 (8)
(Rental Basis) As Evaluated
As Submitted - - 176,800.00 176,800.00 17,680.00 9,724.00 204,204.00
TOTAL OF PART A
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.62 1.00 l.s. 139,150.65 - - 139,150.65 139,150.65 0% - 6,957.53 146,108.18
B.3 Permits and Clearances
As Evaluated
As Submitted 0.02 1.00 ea 3,669.00 804.44 80.44 4,553.88 4,553.88 22% 1,001.85 277.79 5,833.52
B.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.38 1.00 l.s. 78,379.44 7,144.48 - 85,523.92 85,523.92 10% 8,552.39 4,703.82 98,780.13
B.7 (2) Occupational Safety and Health Program
As Evaluated
As Submitted 0.97 1.00 l.s. - - 218,861.19 218,861.19 218,861.19 0% - 10,943.06 229,804.25
B.9 Mobilization/Demobilization
As Evaluated
As Submitted 229,148.01 7,948.92 218,941.63 448,089.64 9,554.24 22,882.20 480,526.08
TOTAL OF PART B
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.47 1.00 l.s. 2,374.40 5,595.60 98,482.50 106,452.50 106,452.50 22% 23,419.55 6,493.60 136,365.65
801(1) Removal of Structure and Obstruction
As Evaluated
As Submitted 0.48 469.24 m3 - 5,530.46 103,246.22 231.81 108,776.68 22% 23,930.87 6,635.38 139,342.93
803(1)a Structure Excavation (Common Soil)
As Evaluated
As Submitted 0.26 383.40 m3 - 9,184.46 49,427.90 152.88 58,612.35 22% 12,894.72 3,575.35 75,082.42
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.98 240.04 m3 183,630.60 5,750.23 30,945.94 917.88 220,326.76 22% 48,471.89 13,439.93 282,238.58
804(1)b Embankment (Borrow)
As Evaluated
As Submitted 0.64 98.95 m3 117,092.48 19,437.08 7,014.90 1,450.68 143,544.46 22% 31,579.78 8,756.21 183,880.45
804(4) Gravel Fill
As Evaluated
As Submitted 303,097.48 45,497.82 289,117.45 637,712.75 140,296.81 38,900.47 816,910.03
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WO
As Submitted 11.20 391.83 m3 1,765,390.07 506,055.70 249,610.22 6,434.06 2,521,055.99 22% 554,632.32 153,784.42 3,229,472.73
900(1)c1 Structural Concrete, Class A, 28 days (4000 psi)
As Evaluated
Structural Concrete, Class A, 28 days (Slab on As Submitted 1.42 56.28 m3 232,138.12 54,973.11 32,612.60 5,680.95 319,723.83 22% 70,339.24 19,503.15 409,566.22
900(1)c2
Fill, 2500 psi) As Evaluated
As Submitted 8.98 34,876.10 kg 1,686,346.63 235,009.92 100,665.59 57.98 2,022,022.13 22% 444,844.87 123,343.35 2,590,210.35
902(1)a Reinforcing Steel, Grade 40
As Evaluated
As Submitted 18.16 70,518.00 kg 3,409,721.60 475,180.12 203,541.56 57.98 4,088,443.28 22% 899,457.52 249,395.04 5,237,295.84
902(1)b Reinforcing Steel, Grade 60
As Evaluated
As Submitted 3.09 1.00 l.s. 325,201.80 332,907.37 36,549.31 694,658.49 694,658.49 22% 152,824.87 42,374.17 889,857.53
903(2) Formworks and Falseworks
As Evaluated
As Submitted 7,418,798.20 1,604,126.23 622,979.28 9,645,903.72 2,122,098.82 588,400.13 12,356,402.67
TOTAL OF PART B
As Evaluated
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.29 170.17 L 56,156.10 7,888.01 788.80 380.99 64,832.91 22% 14,263.24 3,954.81 83,050.96
1000(1) Soil Poisoning
As Evaluated
As Submitted 56,156.10 7,888.01 788.80 64,832.91 14,263.24 3,954.81 83,050.96
Sub - Total C.1
As Evaluated
C.2. Masonry Works
CHB Non Load Bearing Wall (including As Submitted 0.60 219.20 m2 102,603.14 20,819.70 11,938.81 617.53 135,361.64 22% 29,779.56 8,257.06 173,398.26
1046(2)a1
Reinforcing Steel), 100 mm As Evaluated
CHB Non Load Bearing Wall (including As Submitted 4.60 1,073.91 m2 843,320.04 122,689.15 70,354.61 965.04 1,036,363.81 22% 228,000.04 63,218.19 1,327,582.04
1046(2)a2
Reinforcing Steel), 150 mm As Evaluated
As Submitted 945,923.18 143,508.85 82,293.42 1,171,725.45 257,779.60 71,475.25 1,500,980.30
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 0.17 1.00 l.s. 31,000.00 7,163.20 716.32 38,879.52 38,879.52 22% 8,553.49 2,371.65 49,804.66
1003(17) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 0.24 1.00 l.s 54,600.00 - - 54,600.00 54,600.00 22% 12,012.00 3,330.60 69,942.60
1004(2) Finishing Hardware
As Evaluated
As Submitted 1.71 108.00 m2 212,058.00 103,566.00 69,006.60 3,561.39 384,630.60 22% 84,618.73 23,462.47 492,711.80
1005(1) Casement Steel Window
As Evaluated
As Submitted 0.25 1.00 l.s 44,534.93 7,692.46 4,508.18 56,735.57 56,735.57 22% 12,481.83 3,460.87 72,678.27
1005(5) Steel Window (Window Grills)
As Evaluated
As Submitted 0.11 1.00 l.s. 22,050.00 1,608.88 160.89 23,819.77 23,819.77 22% 5,240.35 1,453.01 30,513.13
1006(6) Steel Doors and Frames
As Evaluated
As Submitted 0.03 2.16 m2 4,127.76 1,206.66 707.17 2,797.03 6,041.59 22% 1,329.15 368.54 7,739.28
1008(1)c Aluminum Glass Window (Awning Type)
As Evaluated
As Submitted 0.32 48.00 m2 33,619.20 35,752.89 3,575.29 1,519.74 72,947.38 22% 16,048.42 4,449.79 93,445.59
1009(1)a Jalousie Window (Glass)
As Evaluated
As Submitted 1.63 1.00 l.s. 295,521.00 64,355.20 6,435.52 366,311.72 366,311.72 22% 80,588.58 22,345.02 469,245.32
1010(4) Wooden Doors
As Evaluated
As Submitted 697,510.89 221,345.29 85,109.97 1,003,966.15 220,872.55 61,241.95 1,286,080.65
Sub-Total C.3
As Evaluated
C.4 Finishing Works
Ceiling (4.5mm Fiber Cement Board on Metal As Submitted 2.43 649.00 m2 403,437.87 130,692.83 13,069.28 843.14 547,199.99 22% 120,384.00 33,379.20 700,963.19
1003(1)a1
Frame) As Evaluated
As Submitted 0.28 265.60 m. 50,464.00 12,104.19 - 235.57 62,568.19 22% 13,765.00 3,816.66 80,149.85
1003(15)c Moulding (Pre-cast)
As Evaluated
As Submitted 0.46 183.00 m. 84,161.70 19,628.34 - 567.16 103,790.04 22% 22,833.81 6,331.19 132,955.04
1016(1)a Waterproofing (Cement-Base)
As Evaluated
As Submitted 0.64 118.51 m2 82,300.24 56,699.87 5,669.99 1,220.74 144,670.10 22% 31,827.42 8,824.88 185,322.40
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.23 49.28 m2 33,514.82 16,504.25 1,650.43 1,048.49 51,669.50 22% 11,367.29 3,151.84 66,188.63
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1.97 2,443.24 m2 286,964.65 141,450.74 14,145.07 181.14 442,560.46 22% 97,363.30 26,996.19 566,919.95
1027(1) Cement Plaster Finish
As Evaluated
As Submitted 0.44 516.15 m2 73,164.26 23,236.96 2,323.70 191.27 98,724.92 22% 21,719.48 6,022.22 126,466.62
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.99 1.00 l.s. 203,697.43 7,887.27 10,386.20 221,970.90 221,970.90 22% 48,833.60 13,540.23 284,344.73
1051(6) Railings
As Evaluated
As Submitted 1,217,704.97 408,204.45 47,244.67 1,673,154.10 368,093.90 102,062.41 2,143,310.41
Sub-Total C.4
As Evaluated
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.5 Painting Works
As Submitted 4.74 3,446.00 m2 587,776.91 434,688.29 43,468.83 309.33 1,065,934.03 22% 234,505.49 65,021.98 1,365,461.50
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated
As Submitted 0.25 209.08 m2 23,081.80 29,304.39 2,930.44 264.57 55,316.63 22% 12,169.66 3,374.31 70,860.60
1032(1)b Painting Works (Wood)
As Evaluated
As Submitted 0.19 143.65 m2 22,137.69 19,026.44 1,902.64 299.80 43,066.77 22% 9,474.69 2,627.07 55,168.53
1032(1)c Painting Works (Steel)
As Evaluated
As Submitted 632,996.41 483,019.12 48,301.91 1,164,317.43 256,149.84 71,023.36 1,491,490.63
Sub-Total C.5
As Evaluated

C.6 Roof Framing and Roofing Works

Prepainted Metal Sheets, Long Span, As Submitted 1.81 572.00 m2 332,109.49 68,967.88 6,896.79 713.24 407,974.16 22% 89,754.32 24,886.42 522,614.90
1014(1)b1
Corrugated, 0.4 mm thk As Evaluated
Fabricated Metal Roofing Accessory (Ridge As Submitted 0.08 55.80 l.m. 16,724.93 1,122.19 112.22 321.85 17,959.35 22% 3,951.06 1,095.52 23,005.93
1013(2)a1
Roll, 0.5 mm thk.) As Evaluated
Fabricated Metal Roofing Accessory (Flashing, As Submitted 0.05 22.80 l.m. 10,409.28 458.53 45.85 478.67 10,913.67 22% 2,401.01 665.73 13,980.41
1013(2)a2
0.6 mm thk.) As Evaluated
Fabricated Metal Roofing Accessory (Gutter, As Submitted 0.03 10.00 l.m. 5,953.40 146.28 14.63 611.43 6,114.31 22% 1,345.15 372.97 7,832.43
1013(2)b1
0.6 mm thk.) As Evaluated
As Submitted 4.13 10,076.43 kg 831,204.71 57,327.18 40,065.19 92.16 928,597.08 22% 204,291.36 56,644.42 1,189,532.86
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 7.28 17,209.50 kg 1,410,318.53 78,484.45 149,025.33 95.17 1,637,828.31 22% 360,322.23 99,907.53 2,098,058.07
1047(2)b Structural Steel Purlins
As Evaluated
As Submitted 0.08 107.10 kg 15,422.40 2,736.83 2.74 169.58 18,161.97 22% 3,995.63 1,107.88 23,265.48
1047(3)a Bolts
As Evaluated
As Submitted 0.53 1,678.59 kg 90,769.75 25,977.78 2,597.78 71.10 119,345.31 22% 26,255.97 7,280.06 152,881.34
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated
As Submitted 0.07 235.00 kg 11,103.75 3,636.85 363.68 64.27 15,104.28 22% 3,322.94 921.36 19,348.58
1047(7)b Metal Structure Accessories (Sagrods)
As Evaluated
As Submitted 0.15 520.85 kg 25,348.47 8,060.65 806.06 65.69 34,215.18 22% 7,527.34 2,087.13 43,829.65
1047(4) Metal Structure Accessories (Cross Bracing)
As Evaluated
As Submitted 0.04 44.00 ea. 8,360.00 1,327.33 1.33 220.20 9,688.65 22% 2,131.50 591.01 12,411.16
1047(3)c Metal Structure Accessories (Turnbuckle)
As Evaluated
As Submitted 2,757,724.72 248,245.96 199,931.60 3,205,902.27 705,298.51 195,560.03 4,106,760.81
Sub-Total C.6
As Evaluated
As Submitted 6,308,016.26 1,512,211.67 463,670.36 8,283,898.31 1,822,457.64 505,317.81 10,611,673.76
TOTAL OF PART C
As Evaluated
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART D PLUMBING/SANITARY WORKS
As Submitted 0.28 28.00 ea 55,576.15 6,588.36 658.84 2,243.69 62,823.35 22% 13,821.14 3,832.22 80,476.71
1001(5)a Catch Basin
As Evaluated
As Submitted 0.61 1.00 l.s. 120,681.12 15,519.22 1,551.92 137,752.26 137,752.26 22% 30,305.50 8,402.89 176,460.65
1001(8) Sewer Line Works
As Evaluated
As Submitted 1.05 1.00 l.s. 182,354.63 49,912.50 4,991.25 237,258.38 237,258.38 22% 52,196.84 14,472.76 303,927.98
1001(9) Storm Drainage and Downspout
As Evaluated
As Submitted 0.86 1.00 l.s. 140,829.14 48,719.19 4,871.92 194,420.25 194,420.25 22% 42,772.46 11,859.64 249,052.35
1001(11) Septic Vault
As Evaluated
As Submitted 1.05 1.00 l.s. 200,877.35 32,831.21 3,283.12 236,991.68 236,991.68 22% 52,138.17 14,456.49 303,586.34
1002(4) Plumbing Fixtures
As Evaluated
As Submitted 0.29 1.00 l.s. 53,013.16 11,013.64 1,101.36 65,128.16 65,128.16 22% 14,328.20 3,972.82 83,429.18
1002(24) Cold Water Lines
As Evaluated
As Submitted 3.38 1.00 l.s 669,413.99 82,589.84 8,258.98 760,262.82 760,262.82 22% 167,257.82 46,376.03 973,896.67
1002(26) Cistern
As Evaluated
As Submitted 1,422,745.52 247,173.97 24,717.40 1,694,636.90 372,820.13 103,372.85 2,170,829.88
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.39 1.00 l.s. 79,504.10 8,045.94 804.59 88,354.64 88,354.64 22% 19,438.02 5,389.63 113,182.29
1100(10) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 1.37 1.00 l.s. 289,348.50 16,425.19 1,642.52 307,416.21 307,416.21 22% 67,631.57 18,752.39 393,800.17
1101(33) Wires and Wiring Devices
As Evaluated
As Submitted 0.44 1.00 l.s. 93,350.00 5,506.82 550.68 99,407.50 99,407.50 22% 21,869.65 6,063.86 127,341.01
1102(1) Panel Boards with Main and Branch Breakers
As Evaluated
As Submitted 0.44 1.00 l.s. 88,208.00 10,206.33 1,020.63 99,434.97 99,434.97 22% 21,875.69 6,065.53 127,376.19
1103(1) Lighting Fixtures and Lamps
As Evaluated
As Submitted 550,410.60 40,184.28 4,018.43 594,613.32 130,814.93 36,271.41 761,699.66
TOTAL OF PART E
As Evaluated
PART F MECHANICAL
As Submitted 1.46 1.00 l.s. 282,957.90 42,540.84 4,254.08 329,752.83 329,752.83 22% 72,545.62 20,114.92 422,413.37
1202(1) Fire Protection System
As Evaluated
As Submitted 2.00 1.00 l.s. 429,599.00 19,457.35 1,945.74 451,002.09 451,002.09 22% 99,220.46 27,511.13 577,733.68
1201(1) Water Pumping System
As Evaluated
As Submitted 1.10 1.00 l.s. 208,160.00 36,792.08 3,679.21 248,631.29 248,631.29 22% 54,698.88 15,166.51 318,496.68
1200(14) Ventilation
As Evaluated
As Submitted 920,716.90 108,669.30 9,879.03 1,029,386.21 226,464.96 62,792.56 1,318,643.73
TOTAL OF PART F
As Evaluated
As Submitted 16,923,784.97 3,557,863.27 1,414,381.95 21,886,151.21 4,814,953.29 1,335,055.23 28,036,159.73
TOTAL OF PART III
As Evaluated
As Submitted 16,923,784.97 3,557,863.27 1,414,381.95 21,886,151.21 4,814,953.29 1,335,055.23 28,036,159.73
TOTAL OF (Project ID)
As Evaluated
As Submitted 17,152,932.98 3,565,812.19 1,810,123.59 22,511,040.85 4,842,187.53 1,367,661.43 28,720,889.81
GRAND TOTAL
As Evaluated
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City
FORM ABC-2015-02-00

CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 205
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED 176,800.00 10.00% 17,680.00 9,724.00 27,404.00 204,204.00
PART I FACILITIES FOR THE ENGINEER
AS EVALUATED

AS SUBMITTED 448,089.64 2.13% 9,554.24 22,881.22 32,435.46 480,525.10


PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED

(Project ID)
(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

AS SUBMITTED 637,712.75 22.00% 140,296.81 38,499.92 178,796.73 816,509.48


PART A EARTHWORKS
AS EVALUATED

AS SUBMITTED 9,645,903.72 22.00% 2,122,098.82 574,133.88 2,696,232.70 12,342,136.42


PART B PLAIN AND REINFORCED CONCRETE WORKS
AS EVALUATED

AS SUBMITTED 8,283,898.31 22.00% 1,822,457.64 486,564.83 2,309,022.47 10,592,920.78


PART C FINISHING
AS EVALUATED

AS SUBMITTED 1,694,636.90 22.00% 372,820.13 103,367.77 476,187.90 2,170,824.80


PART D PLUMBING/SANITARY WORKS
AS EVALUATED

AS SUBMITTED 594,613.32 22.00% 130,814.93 36,270.75 167,085.68 761,699.00


PART E ELECTRICAL
AS EVALUATED

AS SUBMITTED 1,029,386.21 22.00% 226,464.96 62,790.83 289,255.79 1,318,642.00


PART F MECHANICAL
AS EVALUATED

AS SUBMITTED 21,886,151.21 22.00% 4,814,953.29 1,301,627.98 6,116,581.27 28,002,732.48


TOTAL OF PART III
AS EVALUATED

AS SUBMITTED 21,886,151.21 22.00% 4,814,953.29 1,301,627.98 6,116,581.27 28,002,732.48


TOTAL OF (Project ID)
AS EVALUATED

AS SUBMITTED 22,511,040.85 21.51% 4,842,187.53 1,334,233.20 6,176,420.73 28,687,461.58


TOTAL
AS EVALUATED

Preparation by: ESTIMATING COMMITTEE Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

RYAN JOY L. BASCO LAARNI D. DE LOS SANTOS TERESITA D. LOON ERVIN P. SALANG JOSE CAESAR A, RADAZA
Engineer II Engineer II Engineer III Asst. District Engineer District Engineer
Planning & Design Section Quality Assurance Section Chief, Construction Section Chairman
Member Member
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City

FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 205
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART I FACILITIES FOR THE ENGINEER
AS SUBMITTED 6.80 mo 176,800.00 10% 17,680.00 9,724.00 27,404.00 204,204.00 30,030.00
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis)
AS EVALUATED

AS SUBMITTED 176,800.00 17,680.00 9,724.00 27,404.00 204,204.00


TOTAL OF PART I
AS EVALUATED

PART II OTHER GENERAL REQUIREMENTS


AS SUBMITTED 1.00 l.s. 139,150.65 0% - 6,957.35 6,957.35 146,108.00 146,108.00
B.3 Permits and Clearances
AS EVALUATED

AS SUBMITTED 1.00 ea 4,553.88 22% 1,001.85 277.27 1,279.12 5,833.00 5,833.00


B.5 Project Billboard/ Sign Board
AS EVALUATED

AS SUBMITTED 1.00 l.s. 85,523.92 10% 8,552.39 4,703.79 13,256.18 98,780.10 98,780.10
B.7 (2) Occupational Safety and Health Program
AS EVALUATED

AS SUBMITTED 1.00 l.s. 218,861.19 0% - 10,942.81 10,942.81 229,804.00 229,804.00


B.9 Mobilization/Demobilization
AS EVALUATED

AS SUBMITTED 448,089.64 9,554.24 22,881.22 32,435.46 480,525.10


TOTAL OF PART II
AS EVALUATED

(Project ID)
(Project Component ID - Description)

CIVIL, MECHANICAL, ELECTRICAL AND


PART III
SANITARY/PLUMBING WORKS

PART A EARTHWORKS
AS SUBMITTED 1.00 l.s. 106,452.50 22% 23,419.55 6,492.95 29,912.50 136,365.00 136,365.00
801(1) Removal of Structure and Obstruction
AS EVALUATED

AS SUBMITTED 469.24 m3 108,776.68 22% 23,930.87 6,609.81 30,540.68 139,317.36 296.90


803(1)a Structure Excavation (Common Soil)
AS EVALUATED

AS SUBMITTED 383.40 m3 58,612.35 22% 12,894.72 3,255.93 16,150.65 74,763.00 195.00


804(1)a Embankment from Structure Excavation
AS EVALUATED

AS SUBMITTED 240.04 m3 220,326.76 22% 48,471.89 13,416.38 61,888.27 282,215.03 1,175.70


804(1)b Embankment (Borrow)
AS EVALUATED

AS SUBMITTED 98.95 m3 143,544.46 22% 31,579.78 8,724.86 40,304.64 183,849.10 1,858.00


804(4) Gravel Fill
AS EVALUATED

AS SUBMITTED 637,712.75 140,296.81 38,499.92 178,796.73 816,509.48


TOTAL OF PART A
AS EVALUATED
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City

FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 205
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART B PLAIN AND REINFORCED CONCRETE WORKS
AS SUBMITTED 391.83 m3 2,521,055.99 22% 554,632.32 153,774.55 708,406.87 3,229,462.86 8,242.00
900(1)c1 Structural Concrete, Class A, 28 days (4000 psi)
AS EVALUATED

AS SUBMITTED 56.28 m3 319,723.83 22% 70,339.24 19,486.49 89,825.73 409,549.56 7,277.00


900(1)c2 Structural Concrete, Class A, 28 days (Slab on Fill, 2500 psi)
AS EVALUATED

AS SUBMITTED 34,876.10 kg 2,022,022.13 22% 444,844.87 113,964.40 558,809.27 2,580,831.40 74.00


902(1)a Reinforcing Steel, Grade 40
AS EVALUATED

AS SUBMITTED 70,518.00 kg 4,088,443.28 22% 899,457.52 244,534.80 1,143,992.32 5,232,435.60 74.20


902(1)b Reinforcing Steel, Grade 60
AS EVALUATED

AS SUBMITTED 1.00 l.s. 694,658.49 22% 152,824.87 42,373.64 195,198.51 889,857.00 889,857.00
903(2) Formworks and Falseworks
AS EVALUATED

AS SUBMITTED 9,645,903.72 2,122,098.82 574,133.88 2,696,232.70 12,342,136.42


TOTAL OF PART B
AS EVALUATED

PART C FINISHING WORKS


AS SUBMITTED 170.17 L 64,832.91 22% 14,263.24 3,946.81 18,210.05 83,042.96 488.00
1000(1) Soil Poisoning
AS EVALUATED

CHB Non Load Bearing Wall (including Reinforcing Steel), AS SUBMITTED 219.20 m2 135,361.64 22% 29,779.56 8,246.00 38,025.56 173,387.20 791.00
1046(2)a1
100 mm AS EVALUATED

CHB Non Load Bearing Wall (including Reinforcing Steel), AS SUBMITTED 1,073.91 m2 1,036,363.81 22% 228,000.04 62,988.91 290,988.95 1,327,352.76 1,236.00
1046(2)a2
150 mm AS EVALUATED

AS SUBMITTED 1.00 l.s. 38,879.52 22% 8,553.49 2,370.99 10,924.48 49,804.00 49,804.00
1003(17) Carpentry and Joinery Works (Blackboard)
AS EVALUATED

AS SUBMITTED 1.00 l.s 54,600.00 22% 12,012.00 3,330.00 15,342.00 69,942.00 69,942.00
1004(2) Finishing Hardware
AS EVALUATED

AS SUBMITTED 108.00 m2 384,630.60 22% 84,618.73 23,446.67 108,065.40 492,696.00 4,562.00


1005(1) Casement Steel Window
AS EVALUATED

AS SUBMITTED 1.00 l.s 56,735.57 22% 12,481.83 3,460.60 15,942.43 72,678.00 72,678.00
1005(5) Steel Window (Window Grills)
AS EVALUATED

AS SUBMITTED 1.00 l.s. 23,819.77 22% 5,240.35 1,453.01 6,693.36 30,513.13 30,513.13
1006(6) Steel Doors and Frames
AS EVALUATED

AS SUBMITTED 2.16 m2 6,041.59 22% 1,329.15 368.54 1,697.69 7,739.28 3,583.00


1008(1)c Aluminum Glass Window (Awning Type)
AS EVALUATED

AS SUBMITTED 48.00 m2 72,947.38 22% 16,048.42 4,412.20 20,460.62 93,408.00 1,946.00


1009(1)a Jalousie Window (Glass)
AS EVALUATED
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City

FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 205
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
AS SUBMITTED 1.00 l.s. 366,311.72 22% 80,588.58 22,344.70 102,933.28 469,245.00 469,245.00
1010(4) Wooden Doors
AS EVALUATED

AS SUBMITTED 649.00 m2 547,199.99 22% 120,384.00 33,336.01 153,720.01 700,920.00 1,080.00


1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame)
AS EVALUATED

AS SUBMITTED 265.60 m. 62,568.19 22% 13,765.00 3,612.41 17,377.41 79,945.60 301.00


1003(15)c Moulding (Pre-cast)
AS EVALUATED

AS SUBMITTED 183.00 m. 103,790.04 22% 22,833.81 6,234.15 29,067.96 132,858.00 726.00


1016(1)a Waterproofing (Cement-Base)
AS EVALUATED

AS SUBMITTED 118.51 m2 144,670.10 22% 31,827.42 8,733.61 40,561.03 185,231.13 1,563.00


1018(1) Glazed Tiles and Trims
AS EVALUATED

AS SUBMITTED 49.28 m2 51,669.50 22% 11,367.29 3,146.25 14,513.54 66,183.04 1,343.00


1018(2) Unglazed Tiles
AS EVALUATED

AS SUBMITTED 2,443.24 m2 442,560.46 22% 97,363.30 26,907.92 124,271.22 566,831.68 232.00


1027(1) Cement Plaster Finish
AS EVALUATED

AS SUBMITTED 516.15 m2 98,724.92 22% 21,719.48 6,012.35 27,731.83 126,456.75 245.00


1038(1) Reflective Insulation
AS EVALUATED

AS SUBMITTED 1.00 l.s. 221,970.90 22% 48,833.60 13,539.50 62,373.10 284,344.00 284,344.00
1051(6) Railings
AS EVALUATED

AS SUBMITTED 3,446.00 m2 1,065,934.03 22% 234,505.49 64,176.48 298,681.97 1,364,616.00 396.00


1032(1)a Painting Works (Masonry/Concrete)
AS EVALUATED

AS SUBMITTED 209.08 m2 55,316.63 22% 12,169.66 3,182.75 15,352.41 70,669.04 338.00


1032(1)b Painting Works (Wood)
AS EVALUATED

AS SUBMITTED 143.65 m2 43,066.77 22% 9,474.69 2,620.14 12,094.83 55,161.60 384.00


1032(1)c Painting Works (Steel)
AS EVALUATED

AS SUBMITTED 572.00 m2 407,974.16 22% 89,754.32 24,507.52 114,261.84 522,236.00 913.00


1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.4 mm thk
AS EVALUATED

AS SUBMITTED 55.80 l.m. 17,959.35 22% 3,951.06 1,079.19 5,030.25 22,989.60 412.00
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.5 mm thk.)
AS EVALUATED

AS SUBMITTED 22.80 l.m. 10,913.67 22% 2,401.01 661.72 3,062.73 13,976.40 613.00
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk.)
AS EVALUATED

AS SUBMITTED 10.00 l.m. 6,114.31 22% 1,345.15 370.54 1,715.69 7,830.00 783.00
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk.)
AS EVALUATED

AS SUBMITTED 10,076.43 kg 928,597.08 22% 204,291.36 56,130.30 260,421.66 1,189,018.74 118.00


1047(2)a Structural Steel, Trusses
AS EVALUATED
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City

FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 205
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
AS SUBMITTED 17,209.50 kg 1,637,828.31 22% 360,322.23 84,198.96 444,521.19 2,082,349.50 121.00
1047(2)b Structural Steel Purlins
AS EVALUATED

AS SUBMITTED 107.10 kg 18,161.97 22% 3,995.63 1,083.10 5,078.73 23,240.70 217.00


1047(3)a Bolts
AS EVALUATED

AS SUBMITTED 1,678.59 kg 119,345.31 22% 26,255.97 7,150.41 33,406.38 152,751.69 91.00


1047(6) Metal Structure Accessories (Steel Plates)
AS EVALUATED

AS SUBMITTED 235.00 kg 15,104.28 22% 3,322.94 913.28 4,236.22 19,340.50 82.30


1047(7)b Metal Structure Accessories (Sagrods)
AS EVALUATED

AS SUBMITTED 520.85 kg 34,215.18 22% 7,527.34 2,008.88 9,536.22 43,751.40 84.00


1047(4) Metal Structure Accessories (Cross Bracing)
AS EVALUATED

AS SUBMITTED 44.00 ea. 9,688.65 22% 2,131.50 590.93 2,722.43 12,411.08 282.07
1047(3)c Metal Structure Accessories (Turnbuckle)
AS EVALUATED

AS SUBMITTED 8,283,898.31 1,822,457.64 486,564.83 2,309,022.47 10,592,920.78


TOTAL OF PART C
AS EVALUATED

PART D PLUMBING/SANITARY WORKS


AS SUBMITTED 28.00 ea 62,823.35 22% 13,821.14 3,830.31 17,651.45 80,474.80 2,874.10
1001(5)a Catch Basin
AS EVALUATED
AS SUBMITTED 1.00 l.s. 137,752.26 22% 30,305.50 8,402.24 38,707.74 176,460.00 176,460.00
1001(8) Sewer Line Works
AS EVALUATED
AS SUBMITTED 1.00 l.s. 237,258.38 22% 52,196.84 14,471.78 66,668.62 303,927.00 303,927.00
1001(9) Storm Drainage and Downspout
AS EVALUATED
AS SUBMITTED 1.00 l.s. 194,420.25 22% 42,772.46 11,859.29 54,631.75 249,052.00 249,052.00
1001(11) Septic Vault
AS EVALUATED

AS SUBMITTED 1.00 l.s. 236,991.68 22% 52,138.17 14,456.15 66,594.32 303,586.00 303,586.00
1002(4) Plumbing Fixtures
AS EVALUATED

AS SUBMITTED 1.00 l.s. 65,128.16 22% 14,328.20 3,972.64 18,300.84 83,429.00 83,429.00
1002(24) Cold Water Lines
AS EVALUATED

AS SUBMITTED 1.00 l.s 760,262.82 22% 167,257.82 46,375.36 213,633.18 973,896.00 973,896.00
1002(26) Cistern
AS EVALUATED

AS SUBMITTED 1,694,636.90 372,820.13 103,367.77 476,187.90 2,170,824.80


TOTAL OF PART D
AS EVALUATED
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City

FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 205
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART E ELECTRICAL WORKS
AS SUBMITTED 1.00 l.s. 88,354.64 22% 19,438.02 5,389.34 24,827.36 113,182.00 113,182.00
1100(10) Conduits, Boxes, and Fittings
AS EVALUATED
AS SUBMITTED 1.00 l.s. 307,416.21 22% 67,631.57 18,752.22 86,383.79 393,800.00 393,800.00
1101(33) Wires and Wiring Devices
AS EVALUATED
AS SUBMITTED 1.00 l.s. 99,407.50 22% 21,869.65 6,063.85 27,933.50 127,341.00 127,341.00
1102(1) Panel Boards with Main and Branch Breakers
AS EVALUATED
AS SUBMITTED 1.00 l.s. 99,434.97 22% 21,875.69 6,065.34 27,941.03 127,376.00 127,376.00
1103(1) Lighting Fixtures and Lamps
AS EVALUATED
AS SUBMITTED 594,613.32 130,814.93 36,270.75 167,085.68 761,699.00
TOTAL OF PART E
AS EVALUATED
PART F MECHANICAL WORKS
AS SUBMITTED 1.00 l.s. 329,752.83 22% 72,545.62 20,114.55 92,660.17 422,413.00 422,413.00
1202(1) Fire Protection System
AS EVALUATED
AS SUBMITTED 1.00 l.s. 451,002.09 22% 99,220.46 27,510.45 126,730.91 577,733.00 577,733.00
1201(1) Water Pumping System
AS EVALUATED
AS SUBMITTED 1.00 l.s. 248,631.29 22% 54,698.88 15,165.83 69,864.71 318,496.00 318,496.00
1200(14) Ventilation
AS EVALUATED
AS SUBMITTED 1,029,386.21 226,464.96 62,790.83 289,255.79 1,318,642.00
TOTAL OF PART F
AS EVALUATED
AS SUBMITTED 21,886,151.21 4,814,953.29 1,301,627.98 6,116,581.27 28,002,732.48
TOTAL OF PART III
AS EVALUATED
AS SUBMITTED 21,886,151.21 4,814,953.29 1,301,627.98 6,116,581.27 28,002,732.48
TOTAL OF (Project ID)
AS EVALUATED
AS SUBMITTED 22,511,040.85 4,842,187.53 1,334,233.20 6,176,420.73 28,687,461.58
GRAND TOTAL
AS EVALUATED

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

LAARNI D. DE LOS SANTOS


RYAN JOY L. BASCO TERESITA D. LOON
Engineer II Engineer II Engineer II
Planning & Design Section Quality Assurance Section Chief, Construction Section
Member Member
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------
SUMMARY OF BID PRICES
(All Parts of Bill of Quantities)

Instructions for completing the Summary of Bid Prices:

1.    Part No. – Enter the “Part No.” for each section of the BOQ where unit prices are entered.

2.    Part Description – Enter the “Part Description” corresponding to the “Part No.”

3. Total Amount – Enter the “Total Amount” in Pesos for all pages having the same “Part Description”

Part No. Total Amount


Part Description
(Item No.) (Total Item Cost)

Part I Facilities for the Engineer


Part II Other General Requirements
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS
PART B PLAIN AND REINFORCED CONCRETE WORKS
PART C FINISHING WORKS
PART D PLUMBING/SANITARY WORKS
PART E ELECTRICAL WORKS
PART F MECHANICAL WORKS

Total of Amounts
Total of All Amounts in words
Pesos
_____________________________________________________________________________________
________
and ___________________________________ centavos__________________________

Name ___________________________ in the capacity of __________________________

Signed __________________________ Date ____________________________________

Duly authorized to sign the Bid for and on behalf of _______________________________


--------------------------------------------------------
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

PART I FACILITIES FOR THE ENGINEER


In words: Pesos ___ In words: Pesos ___
___________________ ___________________
Provision of Field Office for the Engineer ___________________ ___________________
A.1.1 (8) mo 6.80
(Rental Basis) _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

PART II OTHER GENERAL REQUIREMENTS


In words: Pesos ___ In words: Pesos ___
___________________ ___________________
___________________ ___________________
B.3 Permits and Clearances l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
B.5 Project Billboard/ Sign Board ea 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
B.7 (2) Occupational Safety and Health Program l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
B.9 Mobilization/Demobilization l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


PART A EARTHWORKS
In words: Pesos ___ In words: Pesos ___
___________________ ___________________
___________________ ___________________
801(1) Removal of Structure and Obstruction l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
803(1)a Structure Excavation (Common Soil) m3 469.24 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
804(1)a Embankment from Structure Excavation m3 383.40 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:


Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

Php

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
804(1)b Embankment (Borrow) m3 240.04 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
804(4) Gravel Fill m3 98.95 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

PART B PLAIN AND REINFORCED CONCRETE WORKS


In words: Pesos ___ In words: Pesos ___
___________________ ___________________
Structural Concrete, Class A, 28 days (4000 ___________________ ___________________
900(1)c1 m3 391.83 _____________ _____________
psi)
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
Structural Concrete, Class A, 28 days (Slab on ___________________ ___________________
900(1)c2 m3 56.28
Fill, 2500 psi) _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
902(1)a Reinforcing Steel, Grade 40 kg 34,876.10 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
902(1)b Reinforcing Steel, Grade 60 kg 70,518.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
903(2) Formworks and Falseworks l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:

Php
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

PART C FINISHING WORKS


In words: Pesos ___ In words: Pesos ___
___________________ ___________________
___________________ ___________________
1000(1) Soil Poisoning L 170.17 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
CHB Non Load Bearing Wall (including ___________________ ___________________
1046(2)a1 m2 219.20 _____________ _____________
Reinforcing Steel), 100 mm
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
CHB Non Load Bearing Wall (including ___________________ ___________________
1046(2)a2 m2 1,073.91 _____________ _____________
Reinforcing Steel), 150 mm
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1003(17) Carpentry and Joinery Works (Blackboard) l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1004(2) Finishing Hardware l.s 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1005(1) Casement Steel Window m2 108.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1005(5) Steel Window (Window Grills) l.s 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1006(6) Steel Doors and Frames l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:

Php
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1008(1)c Aluminum Glass Window (Awning Type) m2 2.16 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1009(1)a Jalousie Window (Glass) m2 48.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1010(4) Wooden Doors l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
Ceiling (4.5mm Fiber Cement Board on Metal ___________________ ___________________
1003(1)a1 m2 649.00 _____________ _____________
Frame)
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1003(15)c Moulding (Pre-cast) m. 265.60 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1016(1)a Waterproofing (Cement-Base) m. 183.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1018(1) Glazed Tiles and Trims m2 118.51 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1018(2) Unglazed Tiles m2 49.28 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1027(1) Cement Plaster Finish m2 2,443.24 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:


Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

Php

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1038(1) Reflective Insulation m2 516.15 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1051(6) Railings l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1032(1)a Painting Works (Masonry/Concrete) m2 3,446.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1032(1)b Painting Works (Wood) m2 209.08 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1032(1)c Painting Works (Steel) m2 143.65 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
Prepainted Metal Sheets, Long Span, ___________________ ___________________
1014(1)b1 m2 572.00 _____________ _____________
Corrugated, 0.4 mm thk
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
Fabricated Metal Roofing Accessory (Ridge ___________________ ___________________
1013(2)a1 l.m. 55.80
Roll, 0.5 mm thk.) _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:

Php
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
Fabricated Metal Roofing Accessory (Flashing, ___________________ ___________________
1013(2)a2 l.m. 22.80 _____________ _____________
0.6 mm thk.)
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
Fabricated Metal Roofing Accessory (Gutter, ___________________ ___________________
1013(2)b1 l.m. 10.00
0.6 mm thk.) _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(2)a Structural Steel, Trusses kg 10,076.43 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(2)b Structural Steel Purlins kg 17,209.50 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(3)a Bolts kg 107.10 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(6) Metal Structure Accessories (Steel Plates) kg 1,678.59 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(7)b Metal Structure Accessories (Sagrods) kg 235.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(4) Metal Structure Accessories (Cross Bracing) kg 520.85 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1047(3)c Metal Structure Accessories (Turnbuckle) ea. 44.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:


Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

Php
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

PART D PLUMBING/SANITARY WORKS

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1001(5)a Catch Basin ea 28.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1001(8) Sewer Line Works l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1001(9) Storm Drainage and Downspout l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1001(11) Septic Vault l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1002(4) Plumbing Fixtures l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1002(24) Cold Water Lines l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1002(26) Cistern l.s 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

PART E ELECTRICAL WORKS

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1100(10) Conduits, Boxes, and Fittings l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1101(33) Wires and Wiring Devices l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________
Department of Public Works and Highways (DPWH)

Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------

BILL OF QUANTITIES

Pay Description Unit Quantity Unit Price Amount


Item No. (Pesos) (Pesos)
-1 -2 -3 -4 -5 -6

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1102(1) Panel Boards with Main and Branch Breakers l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1103(1) Lighting Fixtures and Lamps l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

PART F MECHANICAL WORKS

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1202(1) Fire Protection System l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1201(1) Water Pumping System l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

In words: Pesos ___ In words: Pesos ___


___________________ ___________________
___________________ ___________________
1200(14) Ventilation l.s. 1.00 _____________ _____________
In figures: Php ____ In figures: Php ____
_________________ _________________

Sub-total Bid Price in Words: In figures:

Php

Total Bid Price in Words: In figures:

Php

(if applicable use this Page as pp.1 or pp.2 as needed )


-------------------------------------------------------
Eligibility Data Sheet

Eligibility Requirements
1c(1)
The ABC for this contract AS stated clearly at Invitation to Bid.

1c(1)
The prospective bidder must possess a valid license issued by the Philippine Contractors’ Accreditation B
(PCAB) in accordance with the provisions of RA 4566, for the specific category indicated in the Eligibility D
Sheet (EDS), out of the following PCAB categories:

a.   Size Range: (see allowable at below table)

b.  License Category: (see allowable at below table)

c.   Largest Single Project: (see allowable at below table)

Allowable Range of Contract Cost: (see allowable at below table)

License Single Largest Project/ Required Track


Size Range
Category Record

Large B AAA Above PhP150M

Large A AA Above PhP100M up to PhP150M

Medium B A Above PhP50M up to PhP100M

Medium A B Above PhP10M up to PhP100M

Small B C&D Above P500,000 up to PhP10M

Small A Trade Up to PhP500,000

1c(2) (1)  The following are the “Major Categories of Works” involved in the contract to be bid: (see sample based o
139, S-2016)

a.   BICWOPLC Buildings: Construction - without pile - low rise - concrete frame

(2)  The following are the “Similar Categories of Works” that shall be considered in the evaluation of the w
experience required for the contract to be bid:

a.   BICWPHCCP, BICWPLCCP, BICWPHCDP, BICWPLCDP, BICWOPHC, BIL, BIH, BIM

(3)  The following “Qualifiers” shall be applied to this contract:

  Must
have done a Single Largest Completed Contract for a Major/Similar Category of Works whose total cost is at least 5
a.  
Approved Budget of the Contract to be bid

2 Electronic Bidding will not be applied in this procurement.


y Data Sheet

ation to Bid.

se issued by the Philippine Contractors’ Accreditation Board


566, for the specific category indicated in the Eligibility Data
s:

ow table)

Allowable Range of

Contract Cost (ARCC)

No limit

Up to PhP300M

Up to PhP200M

Up to PhP100M

Up to PhP15M

Up to PhP500,000

rks” involved in the contract to be bid: (see sample based on D.O. No.

rise - concrete frame

orks” that shall be considered in the evaluation of the work

CDP, BICWOPHC, BIL, BIH, BIM

is contract:

for a Major/Similar Category of Works whose total cost is at least 50% of the

ement.
STANDARD FORMAT
BID DATA SHEET

ITB Clause

1.1 The Procuring Entity is DPWH - Butuan City District Engineering Office.

The scope of the Works under this Contract is stated in the Invitation to Bid.

The Contract Name is indicated in the Invitation to Bid.

The Procurement/Contract ID is also indicated in the Invitation to Bid.


2 The Approved Budget for the Contract is indicated in the Invitation to Bid.

The Funding Source is the Government of the Philippines through

CY 2020 Basic Educational Facilities Fund

The name of the Project is indicated in the Invitation to Bid.

5 The similar work category and qualifier must be met by the eligible bidder as per Department
Order No. 139, S-2016.
8.1 Insert any exceptions, e.g., provisions of approved loan agreement for a foreign-assisted
project pertaining to sub-contracting.
8.3
Insert any limitation on the extent of the portions of the Works that may sub- contracted.

9.1 The date and time of the Pre-Bid Conference are [ as indicated at IB]

The venue of the Pre-Bid Conference is DPWH-BCDEO Conference Hall


9.4 Electronic Bidding will not be adopted in this procurement.
11.1 The Procuring Entity’s address is:

DPWH - Butuan City District Engineering Office


R. Palma Street, Butuan City
(085) 342-5330/31, 225-4332/2022
14.2 a(3)(b) The minimum work experience requirements for the key personnel are the following:
Minimum Years Minimum Years
of Similar Experience of Similar and
(Same Position) Related Experience
Key Personnel
Project Manager 3 years 3 years
Project Engineer 2 years 2 years
Materials Engineer 2 years 2 years
Safety Officer 1 years 1 years
Foreman 1 years 1 years
14.2 a(3)(c) The minimum equipment requirements for the project:
1. See list of minimum equipment at Summary of Quantities of each project.
a. Show proof of ownership of equipment, deed of sales valid CR/OR, official receipt or
invoices.
b. Attached contract if to be purchased or rented.
c. If to be leased and/or under Purchase Agreement, it should be supportd by a
certification of availability of equipment from lessor for the duration of the contract.

The Pledged Equipment shall ne listed in complete by using the Attached Form at PBD
Annex to include the brand, capacity, engine, chassis and serial number and its
present location ready for the inspection during the Post-Qualification Stage.
Failure of the prospective bidders to state a technical description of the Pledge
Equipment and the specific loacation, whether owned, leased or under Purchased
Agreement shall result the bidder automatic post disqualification for award and
forfeiture of its Bid Security as per D.O 58 Series of 2012.

14.3a “No further instructions.”

There is no ceiling for Financial Proposals."


OR
The ABC is in the Invitation to Bid. Any bid with a financial component exceeding this amount
shall not be accepted."

14.3 b If ADB, adopt the provision under ITB 14.3b.

If WB, state: Subject to prior concurrence by the World Bank, for foreign- funded
procurement, a ceiling may be applied to bid prices provided the conditions in ITB 14.3b are
met.
17.1 Bids shall be valid until [unless renewed not later than one hundred twenty (120) days
from the date set for bid opening].
18.2 The Bid Security shall be valid until [unless renewed not later than one hundred twenty
(120) days from the date set for bid opening].
19.1
Select one, delete the other:

There is no provision for a value engineering change proposal.


OR
The bidding allows a value engineering change proposal (VECP) in accordance with rules to
be issued separately by the BAC.
20.4 The Bidder shall submit one (1) original and one (1) copy of the first (Technical) and second
(Financial) components of its bid.
21.4 d
The specific identification of this bidding process is the Contract ID and Contract Name as
stated at the Invitation to Bid.
22 The address for receipt of Bids is DPWH - Butuan City District Engineering Office
R. Palma Street, Butuan City

The deadline for receipt of Bids is stated at the Invitation to Bid


25 Electronic Bidding will not be adopted in this procurement.
26.1 The place of opening of Bids is [as stated above].
The date and time of opening of Bids are [ as stated at the Invitation to Bid].
28 Electronic Bidding is not adopted for Bids Opening and Preliminary Examination in this
procurement.
33
State whether Electronic Bidding is not adopted for Post-Qualification in this procurement.
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
Office of the District Engineer
Butuan City District Engineering Office
Butuan City

PROJECT :
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
ELEMENTARY SCHOOL , Butuan City, Agusan del Norte

DURATION : 205
ABC : PhP 28,687,461.58

SUMMARY OF QUANTITIES
:
ITEM NO. DESCRIPTION QTY. UNIT
PART I FACILITIES FOR THE ENGINEER
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) 6.80 mo
PART II OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 1.00 l.s.
B.5 Project Billboard/ Sign Board 1.00 ea
B.7 (2) Occupational Safety and Health Program 1.00 l.s.
B.9 Mobilization/Demobilization 1.00 l.s.
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
801(1) Removal of Structure and Obstruction 1.00 l.s.
803(1)a Structure Excavation (Common Soil) 469.24 m3
804(1)a Embankment from Structure Excavation 383.40 m3
804(1)b Embankment (Borrow) 240.04 m3
804(4) Gravel Fill 98.95 m3
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete, Class A, 28 days (4000 psi) 391.83 m3
900(1)c2 Structural Concrete, Class A, 28 days (Slab on Fill, 2500 psi) 56.28 m3
902(1)a Reinforcing Steel, Grade 40 34,876.10 kg
902(1)b Reinforcing Steel, Grade 60 70,518.00 kg
903(2) Formworks and Falseworks 1.00 l.s.
PART C FINISHING WORKS
1000(1) Soil Poisoning 170.17 L
1046(2)a1 CHB Non Load Bearing Wall (including Reinforcing Steel), 100 mm 219.20 m2
1046(2)a2 CHB Non Load Bearing Wall (including Reinforcing Steel), 150 mm 1,073.91 m2
1003(17) Carpentry and Joinery Works (Blackboard) 1.00 l.s.
1004(2) Finishing Hardware 1.00 l.s
1005(1) Casement Steel Window 108.00 m2
1005(5) Steel Window (Window Grills) 1.00 l.s
1006(6) Steel Doors and Frames 1.00 l.s.
1008(1)c Aluminum Glass Window (Awning Type) 2.16 m2
1009(1)a Jalousie Window (Glass) 48.00 m2
1010(4) Wooden Doors 1.00 l.s.
1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame) 649.00 m2
1003(15)c Moulding (Pre-cast) 265.60 m.
1016(1)a Waterproofing (Cement-Base) 183.00 m.
1018(1) Glazed Tiles and Trims 118.51 m2
1018(2) Unglazed Tiles 49.28 m2

38 of 72
1027(1) Cement Plaster Finish 2,443.24 m2
1038(1) Reflective Insulation 516.15 m2
1051(6) Railings 1.00 l.s.
1032(1)a Painting Works (Masonry/Concrete) 3,446.00 m2
1032(1)b Painting Works (Wood) 209.08 m2
1032(1)c Painting Works (Steel) 143.65 m2
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.4 mm thk 572.00 m2
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.5 mm thk.) 55.80 l.m.
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk.) 22.80 l.m.
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk.) 10.00 l.m.
1047(2)a Structural Steel, Trusses 10,076.43 kg
1047(2)b Structural Steel Purlins 17,209.50 kg
1047(3)a Bolts 107.10 kg
1047(6) Metal Structure Accessories (Steel Plates) 1,678.59 kg
1047(7)b Metal Structure Accessories (Sagrods) 235.00 kg
1047(4) Metal Structure Accessories (Cross Bracing) 520.85 kg
1047(3)c Metal Structure Accessories (Turnbuckle) 44.00 ea.
PART D PLUMBING/SANITARY WORKS
1001(5)a Catch Basin 28.00 ea
1001(8) Sewer Line Works 1.00 l.s.
1001(9) Storm Drainage and Downspout 1.00 l.s.
1001(11) Septic Vault 1.00 l.s.
1002(4) Plumbing Fixtures 1.00 l.s.
1002(24) Cold Water Lines 1.00 l.s.
1002(26) Cistern 1.00 l.s
PART E ELECTRICAL WORKS
1100(10) Conduits, Boxes, and Fittings 1.00 l.s.
1101(33) Wires and Wiring Devices 1.00 l.s.
1102(1) Panel Boards with Main and Branch Breakers 1.00 l.s.
1103(1) Lighting Fixtures and Lamps 1.00 l.s.
PART F MECHANICAL WORKS
1202(1) Fire Protection System 1.00 l.s.
1201(1) Water Pumping System 1.00 l.s.
1200(14) Ventilation 1.00 l.s.

EQUIPMENT REQUIREMENTS:

Plate Compactor 5 hp 1 UNIT


Concrete Vibrator 5 amp 1 UNIT
One Bagger Mixer 4 - 6 ft3/min 1 UNIT
Bar Cutter 1 UNIT
Bar Bender 1 UNIT
Welding Machine 500 amp 2 UNIT
Cutting Outfit 1 UNIT
Set of Minimum Material Testing Equipment 1 UNIT

39 of 72
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 64.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 180 C.D.
Project Description : Complete construction of 2-Storey 12-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.89% 156,000.00
Part II Other General Requirements 1.58% 275,814.08
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.28% 396,833.63
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.33% 5,988,000.95
PART C FINISHING WORKS 46.10% 8,041,232.82
PART D PLUMBING/SANITARY WORKS 10.45% 1,823,557.12
PART E ELECTRICAL WORKS 4.36% 760,618.07

Total 100% 17,442,056.67

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 3,639,079.09 A. Total Direct Cost 17,442,056.67
2. Materials 12,229,072.63 B. OCM and Profit 3,437,096.81
3. Rental of Equipment 1,573,904.94 C. Value Added Tax (12%) 2,505,498.44
4. Provisional Sum / Daywork D. Total Construction Cost 23,384,651.92
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 3,437,096.81 E. Eng'g & Administrative Overhead, 0.5% 117,510.81
6. Value Added Tax (12%) 2,505,498.44 F. RROW Acquisition
7. EAO, 0.5% 117,510.81 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 23,502,162.73 H. TOTAL ESTIMATED COST 23,502,162.73
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 6.00 mo - - 156,000.00 156,000.00 8% 12,480.00 20,217.60 188,697.60
#REF! Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 156,000.00 156,000.00 12,480.00 20,217.60 188,697.60
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
#REF! Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 lot 137,035.54 7,008.96 - 144,044.50 8% 11,523.56 18,668.17 174,236.23
#REF! Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 127,576.82 127,576.82 8% 10,206.15 16,533.96 154,316.93
#REF! Mobilization/ Demobilization
As Evaluated
As Submitted 140,217.88 7,927.52 127,668.68 275,814.08 22,568.26 35,805.89 334,188.23
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 413.71 m3 - 5,567.92 91,097.23 96,665.14 20% 19,333.03 13,919.78 129,917.95
#REF! Structure Excavation
As Evaluated
As Submitted #REF! 257.76 m3 - 7,050.94 33,318.02 40,368.96 20% 8,073.79 5,813.13 54,255.88
#REF! Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 335.90 m3 122,028.27 9,188.44 43,418.39 174,635.09 20% 34,927.02 25,147.45 234,709.56
#REF! Embankment from Borrow
As Evaluated
As Submitted #REF! 90.34 m3 58,244.10 20,264.01 6,656.33 85,164.44 20% 17,032.89 12,263.68 114,461.01
#REF! Gravel Fill
As Evaluated
As Submitted 180,272.37 42,071.31 174,489.96 396,833.63 79,366.73 57,144.04 533,344.40
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 384.71 m3 1,263,772.35 60,395.33 82,880.19 1,407,047.87 20% 281,409.57 202,614.89 1,891,072.33
#REF! Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 68,853.89 kg 2,542,851.62 530,498.28 205,391.47 3,278,741.37 20% 655,748.27 472,138.76 4,406,628.40
#REF! Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,577.60 m2 504,369.13 558,645.42 239,197.16 1,302,211.71 20% 260,442.34 187,518.49 1,750,172.54
#REF! Forms and Falseworks
As Evaluated
As Submitted 4,310,993.10 1,149,539.04 527,468.81 5,988,000.95 1,197,600.18 862,272.14 8,047,873.27
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 300.27 L 96,086.40 15,898.18 1,589.82 113,574.40 20% 22,714.88 16,354.71 152,643.99
#REF! Soil Poisoning
As Evaluated
As Submitted 96,086.40 15,898.18 1,589.82 113,574.40 22,714.88 16,354.71 152,643.99
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 285.37 m2 99,856.73 30,975.89 15,929.91 146,762.53 20% 29,352.51 21,133.80 197,248.84
#REF! 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 961.80 m2 561,645.73 125,575.39 64,579.43 751,800.54 20% 150,360.11 108,259.28 1,010,419.93
#REF! 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 661,502.46 156,551.28 80,509.34 898,563.07 179,712.62 129,393.08 1,207,668.77
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s 343,872.83 66,595.60 45.93 410,514.36 20% 82,102.87 59,114.07 551,731.30
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 70.87 m2 47,447.47 60,276.25 6,027.62 113,751.34 20% 22,750.27 16,380.19 152,881.80
#REF! Jalousie Window
As Evaluated
As Submitted #REF! 146.88 m2 272,857.73 187,386.24 98,502.62 558,746.59 20% 111,749.32 80,459.51 750,955.42
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 65.28 m2 56,433.61 9,369.31 4,925.13 70,728.06 20% 14,145.61 10,184.84 95,058.51
1005(5) Window Grilles
As Evaluated
As Submitted #REF! 43.00 set 64,500.00 - - 64,500.00 20% 12,900.00 9,288.00 86,688.00
#REF! Locksets
As Evaluated
As Submitted #REF! 172.00 pc 11,398.44 - - 11,398.44 20% 2,279.69 1,641.38 15,319.51
#REF! Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 37,200.00 9,818.40 981.84 48,000.24 20% 9,600.05 6,912.03 64,512.32
#REF! Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 833,710.08 333,445.80 110,483.15 1,277,639.03 255,527.81 183,980.02 1,717,146.86
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,161.01 m2 221,432.06 66,768.81 6,676.88 294,877.75 20% 58,975.55 42,462.40 396,315.70
#REF! Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 4,355.83 m 2
355,282.82 288,224.51 28,822.45 672,329.77 20% 134,465.95 96,815.49 903,611.21
#REF! Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
#REF! 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 144.00 m 243,681.41 6,582.10 7,670.87 257,934.38 20% 51,586.88 37,142.55 346,663.81
#REF! 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 661.00 m 2
410,897.43 152,040.64 15,204.06 578,142.13 20% 115,628.43 83,252.47 777,023.03
#REF! Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 841.24 m 2
119,245.77 43,258.80 4,325.88 166,830.45 20% 33,366.09 24,023.58 224,220.12
#REF! Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m 2
109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
#REF! Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m 2
53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
#REF! Unglazed Tiles
As Evaluated
As Submitted 1,534,110.90 642,490.41 74,475.84 2,251,077.15 450,215.44 324,155.12 3,025,447.71
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,943.76 m2 674,852.31 712,489.98 71,249.00 1,458,591.29 20% 291,718.26 210,037.15 1,960,346.70
#REF! Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 247.39 m 2
19,362.81 39,615.12 3,961.51 62,939.45 20% 12,587.89 9,063.28 84,590.62
#REF! Wood Painting
As Evaluated
As Submitted #REF! 125.09 m 2
17,234.96 18,929.24 1,892.92 38,057.13 20% 7,611.43 5,480.23 51,148.79
#REF! Metal Painting
As Evaluated
As Submitted 711,450.08 771,034.35 77,103.44 1,559,587.87 311,917.58 224,580.66 2,096,086.11
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 841.24 m2 347,086.71 115,856.97 11,585.70 474,529.38 20% 94,905.88 68,332.23 637,767.49
#REF! Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 64.20 m 13,549.22 1,474.29 147.43 15,170.94 20% 3,034.19 2,184.62 20,389.75
#REF! Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
#REF! Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 128.40 m 41,262.62 2,498.79 249.88 44,011.30 20% 8,802.26 6,337.63 59,151.19
#REF! Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 7,703.59 kg 428,855.23 49,752.65 103,653.95 582,261.83 20% 116,452.37 83,845.70 782,559.90
#REF! Structural Steel, Trusses
As Evaluated
As Submitted #REF! 10,028.53 kg 564,929.01 52,272.53 87,495.57 704,697.11 20% 140,939.42 101,476.38 947,112.91
#REF! Structural Steel, Purlins
As Evaluated
As Submitted #REF! 128.40 m 24,402.42 3,091.77 309.18 27,803.36 20% 5,560.67 4,003.68 37,367.71
#REF! Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
#REF! Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 293.65 kg 11,679.64 5,189.21 518.92 17,387.77 20% 3,477.55 2,503.84 23,369.16
#REF! Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 628.56 kg 25,750.36 11,107.54 1,110.75 37,968.65 20% 7,593.73 5,467.49 51,029.87
#REF! Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 52.00 pc 8,532.16 1,791.19 1.79 10,325.14 20% 2,065.03 1,486.82 13,876.99
#REF! Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,486,627.54 248,540.08 205,623.68 1,940,791.30 388,158.27 279,473.95 2,608,423.52
Sub-Total C.6
As Evaluated
As Submitted 5,323,487.45 2,167,960.10 549,785.26 8,041,232.82 1,608,246.60 1,157,937.54 10,807,416.96
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 45,831.25 10,578.67 1,057.87 57,467.79 20% 11,493.56 8,275.36 77,236.71
#REF! Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 31,668.25 7,362.18 736.22 39,766.65 20% 7,953.33 5,726.40 53,446.38
#REF! Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 193,090.94 44,552.97 4,455.30 242,099.20 20% 48,419.84 34,862.28 325,381.32
#REF! Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 326,472.09 37,833.19 3,783.32 368,088.60 20% 73,617.72 53,004.76 494,711.08
#REF! Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 84,458.63 20,979.97 2,098.00 107,536.59 20% 21,507.32 15,485.27 144,529.18
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 30.00 units 18,201.24 6,889.20 12,023.04 37,113.48 20% 7,422.70 5,344.34 49,880.52
#REF! Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 875,153.75 87,573.70 8,757.37 971,484.81 20% 194,296.96 139,893.81 1,305,675.58
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,574,876.14 215,769.88 32,911.11 1,823,557.12 364,711.43 262,592.22 2,450,860.77
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 90,605.14 17,183.92 1,718.39 109,507.45 20% 21,901.49 15,769.07 147,178.01
#REF! Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 212,531.55 20,038.24 2,003.82 234,573.61 20% 46,914.72 33,778.60 315,266.93
#REF! Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 251,941.00 4,288.65 428.87 256,658.52 20% 51,331.70 36,958.83 344,949.05
#REF! Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 120,058.00 10,292.76 1,029.28 131,380.04 20% 26,276.01 18,918.73 176,574.78
#REF! Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
#REF! Fire Alarm System
As Evaluated
As Submitted 699,225.69 55,811.25 5,581.13 760,618.070 152,123.610 109,529.010 1,022,270.690
TOTAL OF PART E
As Evaluated
As Submitted 12,088,854.75 3,631,151.57 1,290,236.27 17,010,242.590 3,402,048.550 2,449,474.950 22,861,766.090
TOTAL OF PART III
As Evaluated
As Submitted 12,229,072.63 3,639,079.09 1,573,904.94 17,442,056.670 3,437,096.810 2,505,498.440 23,384,651.920
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 55.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 175 C.D.
Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.99% 151,666.67
Part II Other General Requirements 1.61% 247,792.58
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.24% 343,879.89
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.84% 5,205,623.63
PART C FINISHING WORKS 45.48% 6,995,668.73
PART D PLUMBING/SANITARY WORKS 11.25% 1,729,864.72
PART E ELECTRICAL WORKS 4.61% 708,793.02
`

Total 100% 15,383,289.24

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 3,189,375.97 A. Total Direct Cost 15,383,289.24
2. Materials 10,816,171.39 B. OCM and Profit 3,029,225.88
3. Rental of Equipment 1,377,741.87 C. Value Added Tax (12%) 2,209,501.77
4. Provisional Sum / Daywork D. Total Construction Cost 20,622,016.89
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 3,029,225.88 E. Eng'g & Administrative Overhead, 0.5% 103,628.23
6. Value Added Tax (12%) 2,209,501.77 F. RROW Acquisition
7. EAO, 0.5% 103,628.23 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 20,725,645.12 H. TOTAL ESTIMATED COST 20,725,645.12
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.83 mo - - 151,666.67 151,666.67 8% 12,133.33 19,656.00 183,456.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 151,666.67 151,666.67 12,133.33 19,656.00 183,456.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S. 124,212.14 7,008.96 - 131,221.10 8% 10,497.69 17,006.25 158,725.04
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 112,378.72 112,378.72 8% 8,990.30 14,564.28 135,933.30
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 127,394.48 7,927.52 112,470.58 247,792.58 20,326.54 32,174.29 300,293.41
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 365.45 m3 - 4,918.41 80,470.57 85,388.98 20% 17,077.80 12,296.01 114,762.79
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted #REF! 223.43 m3 - 6,111.85 28,880.53 34,992.39 20% 6,998.48 5,038.90 47,029.77
Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 288.09 m3 104,659.50 7,880.61 37,238.47 149,778.58 20% 29,955.72 21,568.12 201,302.42
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 78.20 m3 50,417.18 17,540.91 5,761.84 73,719.94 20% 14,743.99 10,615.67 99,079.60
804(4) Gravel Fill
As Evaluated
As Submitted 155,076.68 36,451.78 152,351.42 343,879.89 68,775.99 49,518.70 462,174.58
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 335.41 m3 1,101,821.85 52,655.76 72,259.22 1,226,736.83 20% 245,347.37 176,650.10 1,648,734.30
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 59,947.73 kg 2,213,937.11 461,879.02 178,824.36 2,854,640.49 20% 570,928.10 411,068.23 3,836,636.82
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,225.34 m2 435,440.05 482,298.73 206,507.53 1,124,246.31 20% 224,849.26 161,891.47 1,510,987.04
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,751,199.01 996,833.52 457,591.10 5,205,623.63 1,041,124.73 749,609.80 6,996,358.16
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 259.98 L 83,193.60 13,764.98 1,376.50 98,335.08 20% 19,667.02 14,160.25 132,162.35
1000(1) Soil Poisoning
As Evaluated
As Submitted 83,193.60 13,764.98 1,376.50 98,335.08 19,667.02 14,160.25 132,162.35
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 267.94 m2 93,757.62 29,083.92 14,956.94 137,798.48 20% 27,559.70 19,842.98 185,201.16
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 838.99 m2 489,930.49 109,540.96 56,333.43 655,804.88 20% 131,160.98 94,435.90 881,401.76
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 583,688.12 138,624.89 71,290.37 793,603.36 158,720.68 114,278.88 1,066,602.92
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 296,777.99 59,706.40 5,970.64 362,455.03 20% 72,491.01 52,193.52 487,139.56
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 59.98 m2 40,156.61 51,014.10 5,101.41 96,272.12 20% 19,254.42 13,863.18 129,389.72
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 122.40 m2 227,381.44 156,155.20 82,085.52 465,622.16 20% 93,124.43 67,049.59 625,796.18
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 54.40 m 2
47,028.01 7,807.76 4,104.28 58,940.05 20% 11,788.01 8,487.37 79,215.43
1005(5) Window Grills
As Evaluated
As Submitted #REF! 39.00 set 58,500.00 - - 58,500.00 20% 11,700.00 8,424.00 78,624.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 156.00 pc 10,338.12 - - 10,338.12 20% 2,067.62 1,488.69 13,894.43
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 31,000.00 8,182.00 818.20 40,000.20 20% 8,000.04 5,760.03 53,760.27
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 711,182.17 282,865.46 98,080.05 1,092,127.68 218,425.53 157,266.38 1,467,819.59
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,000.20 m2 190,761.79 57,520.75 5,752.07 254,034.61 20% 50,806.92 36,580.98 341,422.51
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,825.21 m2 312,002.85 253,113.47 25,311.35 590,427.67 20% 118,085.53 85,021.58 793,534.78
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 127.60 m 215,928.80 5,832.47 6,797.24 228,558.52 20% 45,711.70 32,912.43 307,182.65
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 565.91 m 2
351,786.63 130,168.41 13,016.84 494,971.88 20% 98,994.38 71,275.95 665,242.21
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 723.31 m2 102,529.19 37,194.53 3,719.45 143,443.17 20% 28,688.63 20,655.82 192,787.62
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,356,580.68 569,445.19 66,372.65 1,992,398.52 398,479.70 286,905.39 2,677,783.61
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,336.71 m2 591,986.41 625,002.52 62,500.25 1,279,489.18 20% 255,897.84 184,246.44 1,719,633.46
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 218.61 m2 17,110.25 35,006.52 3,500.65 55,617.42 20% 11,123.48 8,008.91 74,749.81
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 112.50 m2 15,500.30 17,024.06 1,702.41 34,226.77 20% 6,845.35 4,928.65 46,000.77
1032(1)c Metal Painting
As Evaluated
As Submitted 624,596.97 677,033.09 67,703.31 1,369,333.37 273,866.67 197,184.00 1,840,384.04
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 723.31 m2 298,429.70 99,615.34 9,961.53 408,006.57 20% 81,601.31 58,752.95 548,360.83
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 55.20 m 11,649.79 1,267.61 126.76 13,044.17 20% 2,608.83 1,878.36 17,531.36
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 110.40 m 35,478.14 2,148.50 214.85 37,841.49 20% 7,568.30 5,449.17 50,858.96
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 6,440.06 kg 358,515.11 41,592.30 86,652.80 486,760.21 20% 97,352.04 70,093.47 654,205.72
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 8,515.07 kg 479,672.50 44,383.80 74,291.14 598,347.44 20% 119,669.49 86,162.03 804,178.96
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 110.40 m 20,981.52 2,658.34 265.83 23,905.69 20% 4,781.14 3,442.42 32,129.25
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 248.16 kg 9,870.32 4,385.34 438.53 14,694.19 20% 2,938.84 2,115.96 19,748.99
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 528.07 kg 21,633.56 9,331.74 933.17 31,898.48 20% 6,379.70 4,593.38 42,871.56
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 44.00 pc 7,219.52 1,515.62 1.52 8,736.66 20% 1,747.33 1,258.08 11,742.07
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,264,030.33 212,403.73 173,436.65 1,649,870.72 329,974.15 237,581.38 2,217,426.25
Sub-Total C.6
As Evaluated
As Submitted 4,623,271.86 1,894,137.33 478,259.53 6,995,668.73 1,399,133.75 1,007,376.28 9,402,178.76
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 43,151.00 10,006.85 1,000.69 54,158.54 20% 10,831.71 7,798.83 72,789.08
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 29,320.77 6,790.36 679.04 36,790.16 20% 7,358.03 5,297.78 49,445.97
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 172,839.11 39,956.24 3,995.62 216,790.97 20% 43,358.19 31,217.90 291,367.06
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 325,296.09 37,660.96 3,766.10 366,723.15 20% 73,344.63 52,808.13 492,875.91
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 71,748.04 18,033.35 1,803.33 91,584.71 20% 18,316.94 13,188.20 123,089.85
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 26.00 units 15,774.41 5,970.64 597.06 22,342.11 20% 4,468.42 3,217.26 30,027.79
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 848,514.95 84,509.21 8,450.92 941,475.08 20% 188,295.02 135,572.41 1,265,342.51
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,506,644.36 202,927.60 20,292.76 1,729,864.72 345,972.94 249,100.51 2,324,938.17
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 80,540.14 14,241.12 1,424.11 96,205.37 20% 19,241.07 13,853.57 129,300.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 202,341.55 17,124.36 1,712.44 221,178.35 20% 44,235.67 31,849.68 297,263.70
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 244,155.30 6,861.84 686.18 251,703.32 20% 50,340.66 36,245.28 338,289.26
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 101,458.00 8,863.21 886.32 111,207.53 20% 22,241.51 16,013.88 149,462.92
1003(1) Lighting Fixtures
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 652,584.99 51,098.21 5,109.82 708,793.020 141,758.600 102,066.190 952,617.810
TOTAL OF PART E
As Evaluated
As Submitted 10,688,776.91 3,181,448.45 1,113,604.62 14,983,829.990 2,996,766.010 2,157,671.480 20,138,267.480
TOTAL OF PART III
As Evaluated
As Submitted 10,816,171.39 3,189,375.97 1,377,741.87 15,383,289.240 3,029,225.880 2,209,501.770 20,622,016.890
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 46.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 150 C.D.
Project Description : Complete construction of 2-Storey 8-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.98% 130,000.00
Part II Other General Requirements 1.66% 218,951.28
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.19% 289,618.72
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.44% 4,423,246.32
PART C FINISHING WORKS 44.93% 5,943,512.95
PART D PLUMBING/SANITARY WORKS 12.17% 1,609,931.08
PART E ELECTRICAL WORKS 4.63% 612,125.66

Total 100% 13,227,386.01

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 2,728,009.94 A. Total Direct Cost 13,227,386.01
2. Materials 9,333,208.55 B. OCM and Profit 2,604,106.19
3. Rental of Equipment 1,166,167.47 C. Value Added Tax (12%) 1,899,779.08
4. Provisional Sum / Daywork D. Total Construction Cost 17,731,271.28
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 2,604,106.19 E. Eng'g & Administrative Overhead, 0.5% 89,101.87
6. Value Added Tax (12%) 1,899,779.08 F. RROW Acquisition
7. EAO, 0.5% 89,101.87 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 17,820,373.15 H. TOTAL ESTIMATED COST 17,820,373.15
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.79 5.00 mo - - 130,000.00 130,000.00 8% 10,400.00 16,848.00 157,248.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 130,000.00 130,000.00 10,400.00 16,848.00 157,248.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.38 1.00 l.s. 112,329.46 5,840.80 - 118,170.26 8% 9,453.62 15,314.87 142,938.75
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.97 1.00 l.s. - - 96,588.26 96,588.26 8% 7,727.06 12,517.84 116,833.16
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 115,511.80 6,759.36 96,680.12 218,951.28 18,019.23 28,436.47 265,406.98
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.48 313.84 m3 - 4,223.82 69,106.27 73,330.08 20% 14,666.02 10,559.53 98,555.63
803(1)a Structure Excavation
As Evaluated
As Submitted 0.26 185.75 m3 - 5,081.13 24,010.02 29,091.15 20% 5,818.23 4,189.13 39,098.51
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.98 240.28 m3 87,290.72 6,572.78 31,058.56 124,922.06 20% 24,984.41 17,988.78 167,895.25
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.64 66.06 m3 42,590.27 14,817.81 4,867.36 62,275.43 20% 12,455.09 8,967.66 83,698.18
804(4) Gravel Fill
As Evaluated
As Submitted 129,880.99 30,695.54 129,042.20 289,618.72 57,923.75 41,705.10 389,247.57
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 11.20 286.11 m3 939,871.35 44,916.19 61,638.25 1,046,425.79 20% 209,285.16 150,685.31 1,406,396.26
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 8.98 51,041.57 kg 1,885,022.60 393,259.77 152,257.24 2,430,539.61 20% 486,107.92 349,997.70 3,266,645.23
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 3.09 1,873.07 m2 366,510.97 405,952.04 173,817.90 946,280.92 20% 189,256.18 136,264.45 1,271,801.55
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,191,404.93 844,128.01 387,713.39 4,423,246.32 884,649.26 636,947.46 5,944,843.04
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.29 219.68 L 70,297.60 11,631.24 1,163.12 83,091.97 20% 16,618.39 11,965.24 111,675.60
1000(1) Soil Poisoning
As Evaluated
As Submitted 70,297.60 11,631.24 1,163.12 83,091.97 16,618.39 11,965.24 111,675.60
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted Err:509 250.52 m2 87,662.01 27,193.05 13,984.52 128,839.58 20% 25,767.92 18,552.90 173,160.40
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 4.60 716.18 m2 418,215.26 93,506.53 48,087.43 559,809.22 20% 111,961.84 80,612.53 752,383.59
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 505,877.27 120,699.58 62,071.95 688,648.80 137,729.76 99,165.43 925,543.99
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.63 1.00 l.s. 249,683.14 52,817.20 5,281.72 307,782.06 20% 61,556.41 44,320.62 413,659.09
1010(4) Wooden Doors
As Evaluated
As Submitted 0.32 49.10 m 2
32,872.45 41,760.46 4,176.05 78,808.96 20% 15,761.79 11,348.49 105,919.24
1009(1)a Jalousie Window
As Evaluated
As Submitted Err:509 97.92 m 2
181,905.15 124,924.16 65,668.42 372,497.73 20% 74,499.55 53,639.67 500,636.95
1005 (1) Steel Casement Window
As Evaluated
As Submitted 0.25 43.52 m 2
37,622.41 6,246.21 3,283.42 47,152.04 20% 9,430.41 6,789.89 63,372.34
1005 (5) Window Grills
As Evaluated
As Submitted 0.24 35.00 set 52,500.00 - - 52,500.00 20% 10,500.00 7,560.00 70,560.00
1004(2)a Locksets
As Evaluated
As Submitted Err:509 140.00 pc 9,277.80 - - 9,277.80 20% 1,855.56 1,336.00 12,469.36
1004(2)g Hinges
As Evaluated
As Submitted 0.17 1.00 l.s. 24,800.00 6,545.60 654.56 32,000.16 20% 6,400.03 4,608.02 43,008.21
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 588,660.95 232,293.63 79,064.16 900,018.75 180,003.75 129,602.69 1,209,625.19
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted Err:509 839.37 m2 160,087.71 48,271.53 4,827.15 213,186.40 20% 42,637.28 30,698.84 286,522.52
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 1.97 3,294.60 m 2
268,723.70 218,003.10 21,800.31 508,527.12 20% 101,705.42 73,227.90 683,460.44
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.99 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted Err:509 111.20 m 188,176.20 5,082.84 5,923.62 199,182.66 20% 39,836.53 28,682.30 267,701.49
1053(3)a2
stiffener As Evaluated
As Submitted 2.43 470.83 m2 292,682.05 108,298.48 10,829.85 411,810.38 20% 82,362.08 59,300.70 553,473.16
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted Err:509 605.38 m2 85,812.62 31,130.25 3,113.03 120,055.89 20% 24,011.18 17,288.05 161,355.12
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.64 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.23 50.68 m 2
53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,179,053.69 496,401.77 58,269.65 1,733,725.12 346,745.03 249,656.42 2,330,126.57
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 4.74 3,729.66 m2 509,120.52 537,515.05 53,751.50 1,100,387.07 20% 220,077.41 158,455.74 1,478,920.22
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.25 189.83 m2 14,857.68 30,397.91 3,039.79 48,295.38 20% 9,659.08 6,954.54 64,909.00
1032(1)b Wood Painting
As Evaluated
As Submitted 0.19 99.91 m2 13,765.65 15,118.88 1,511.89 30,396.42 20% 6,079.28 4,377.08 40,852.78
1032(1)c Metal Painting
As Evaluated
As Submitted 537,743.85 583,031.84 58,303.18 1,179,078.87 235,815.77 169,787.36 1,584,682.00
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 1.81 605.38 m2 249,772.68 83,373.71 8,337.37 341,483.76 20% 68,296.75 49,173.66 458,954.17
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.08 46.20 m 9,750.37 1,060.94 106.09 10,917.40 20% 2,183.48 1,572.11 14,672.99
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.05 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted Err:509 92.40 m 29,693.66 1,798.20 179.82 31,671.68 20% 6,334.34 4,560.72 42,566.74
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 4.13 5,176.53 kg 288,174.99 33,431.96 69,651.65 391,258.60 20% 78,251.72 56,341.24 525,851.56
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 7.28 7,001.60 kg 394,415.43 36,495.02 61,086.62 491,997.06 20% 98,399.41 70,847.58 661,244.05
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.08 92.40 m 17,560.62 2,224.92 222.49 20,008.03 20% 4,001.61 2,881.16 26,890.80
1003(11) Fascia Board
As Evaluated
As Submitted 0.53 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 202.67 kg 8,061.00 3,581.47 358.15 12,000.61 20% 2,400.12 1,728.09 16,128.82
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.15 427.58 kg 17,516.76 7,555.94 755.59 25,828.30 20% 5,165.66 3,719.28 34,713.24
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.04 36.00 pc 5,906.88 1,240.06 1.24 7,148.18 20% 1,429.64 1,029.34 9,607.16
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,041,432.57 176,267.32 141,249.54 1,358,949.44 271,789.90 195,688.74 1,826,428.08
Sub-Total C.6
As Evaluated
As Submitted 3,923,065.93 1,620,325.38 400,121.61 5,943,512.95 1,188,702.60 855,865.88 7,988,081.43
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.61 1.00 l.s. 39,506.00 9,149.12 914.91 49,570.03 20% 9,914.01 7,138.08 66,622.12
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.29 1.00 l.s. 25,799.54 6,004.11 600.41 32,404.06 20% 6,480.81 4,666.18 43,551.05
1002(6) Cold Water Line Works
As Evaluated
As Submitted Err:509 1.00 l.s. 147,422.78 34,062.99 3,406.30 184,892.07 20% 36,978.41 26,624.46 248,494.94
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.05 1.00 l.s. 323,532.09 37,488.73 3,748.87 364,769.69 20% 72,953.94 52,526.84 490,250.47
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.86 1.00 l.s. 65,879.25 16,383.24 1,638.32 83,900.81 20% 16,780.16 12,081.72 112,762.69
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted Err:509 20.00 units 12,134.16 4,592.80 459.28 17,186.24 20% 3,437.25 2,474.82 23,098.31
1001(6)b1 Catch basin
As Evaluated
As Submitted Err:509 1.00 lot 792,545.75 76,965.85 7,696.58 877,208.18 20% 175,441.64 126,317.98 1,178,967.80
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,406,819.57 184,646.83 18,464.68 1,609,931.08 321,986.22 231,830.08 2,163,747.38
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.39 1.00 l.s. 73,453.64 12,805.44 1,280.54 87,539.62 20% 17,507.92 12,605.70 117,653.24
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 1.37 1.00 l.s. 141,968.40 12,919.40 1,291.94 156,179.74 20% 31,235.95 22,489.88 209,905.57
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.44 1.00 l.s. 244,155.30 4,288.65 428.87 248,872.82 20% 49,774.56 35,837.69 334,485.07
1102(21) Panel Board
As Evaluated
As Submitted 0.44 1.00 l.s. 82,858.00 7,433.66 743.37 91,035.03 20% 18,207.01 13,109.04 122,351.08
1003(1) Lighting Fixtures
As Evaluated
As Submitted Err:509 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 566,525.34 41,454.83 4,145.48 612,125.660 122,425.130 88,146.090 822,696.880
TOTAL OF PART E
As Evaluated
As Submitted 9,217,696.75 2,721,250.58 939,487.36 12,878,434.730 2,575,686.960 1,854,494.610 17,308,616.300
TOTAL OF PART III
As Evaluated
As Submitted 9,333,208.55 2,728,009.94 1,166,167.47 13,227,386.010 2,604,106.190 1,899,779.080 17,731,271.280
GRAND TOTAL
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 32.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 140 C.D.
Project Description : Complete construction of 2-Storey 6-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.34% 121,333.33
Part II Other General Requirements 1.83% 165,697.10
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.26% 205,356.87
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.42% 3,120,847.89
PART C FINISHING WORKS 47.32% 4,290,596.84
PART D PLUMBING/SANITARY WORKS 10.15% 920,631.76
PART E ELECTRICAL WORKS 2.68% 242,990.66

Total 100% 9,067,454.45

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,902,460.85 A. Total Direct Cost 9,067,454.45
2. Materials 6,284,783.90 B. OCM and Profit 1,779,550.37
3. Rental of Equipment 880,209.68 C. Value Added Tax (12%) 1,301,640.60
4. Provisional Sum / Daywork D. Total Construction Cost 12,148,645.42
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 1,779,550.37 E. Eng'g & Administrative Overhead, 0.5% 61,048.47
6. Value Added Tax (12%) 1,301,640.60 F. RROW Acquisition
7. EAO, 0.5% 61,048.47 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 12,209,693.89 H. TOTAL ESTIMATED COST 12,209,693.89
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.67 mo - - 121,333.33 121,333.33 8% 9,706.67 15,724.80 146,764.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 121,333.33 121,333.33 9,706.67 15,724.80 146,764.80
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 89,810.36 5,840.80 - 95,651.16 8% 7,652.09 12,396.39 115,699.64
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 65,853.18 65,853.18 8% 5,268.25 8,534.57 79,656.00
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 92,992.70 6,759.36 65,945.04 165,697.10 13,758.89 21,534.72 200,990.71
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 244.62 m3 - 3,292.22 53,864.31 57,156.53 20% 11,431.31 8,230.54 76,818.38
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 139.08 m3 - 3,804.49 17,977.46 21,781.95 20% 4,356.39 3,136.60 29,274.94
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 159.64 m3 57,995.22 4,366.90 20,635.04 82,997.16 20% 16,599.43 11,951.59 111,548.18
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 46.06 m3 29,695.85 10,331.64 3,393.74 43,421.23 20% 8,684.25 6,252.66 58,358.14
804(4) Gravel Fill
As Evaluated
As Submitted 87,691.07 21,795.25 95,870.55 205,356.87 41,071.38 29,571.39 275,999.64
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 201.23 m3 661,040.55 31,590.95 43,352.08 735,983.58 20% 147,196.72 105,981.64 989,161.94
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 36,154.58 kg 1,335,229.31 278,560.04 107,849.28 1,721,638.63 20% 344,327.73 247,915.96 2,313,882.32
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,312.79 m2 256,878.78 284,522.09 121,824.81 663,225.68 20% 132,645.14 95,504.50 891,375.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,253,148.65 594,673.07 273,026.17 3,120,847.89 624,169.59 449,402.10 4,194,419.58
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 159.89 L 51,164.80 8,465.58 846.56 60,476.94 20% 12,095.39 8,708.68 81,281.01
1000(1) Soil Poisoning
As Evaluated
As Submitted 51,164.80 8,465.58 846.56 60,476.94 12,095.39 8,708.68 81,281.01
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 147.30 m2 51,543.25 15,988.89 8,222.57 75,754.71 20% 15,150.94 10,908.68 101,814.33
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 522.79 m2 305,284.64 68,256.97 35,102.39 408,644.01 20% 81,728.80 58,844.74 549,217.55
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 356,827.89 84,245.86 43,324.96 484,398.72 96,879.74 69,753.42 651,031.88
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 180,165.84 34,446.00 3,444.60 218,056.44 20% 43,611.29 31,400.13 293,067.86
1010(4) Wooden Dooor
As Evaluated
As Submitted #REF! 34.93 m2 23,385.64 29,708.61 2,970.86 56,065.11 20% 11,213.02 8,073.38 75,351.51
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 73.44 m2 136,428.86 93,693.12 49,251.31 279,373.30 20% 55,874.66 40,229.76 375,477.72
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 32.64 m2 28,216.81 4,684.66 2,462.57 35,364.03 20% 7,072.81 5,092.42 47,529.26
1005(5) Window Grill
As Evaluated
As Submitted #REF! 24.00 set 36,000.00 - - 36,000.00 20% 7,200.00 5,184.00 48,384.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 96.00 pc 6,361.92 - - 6,361.92 20% 1,272.38 916.12 8,550.42
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 18,600.00 4,909.20 490.92 24,000.12 20% 4,800.02 3,456.02 32,256.16
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 429,159.07 167,441.59 58,620.26 655,220.92 131,044.18 94,351.83 880,616.93
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 584.99 m2 111,571.43 33,642.33 3,364.23 148,577.99 20% 29,715.60 21,395.23 199,688.82
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 2,313.83 m2 188,727.30 153,105.73 15,310.57 357,143.60 20% 71,428.72 51,428.68 480,001.00
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 92.12 m 155,888.41 4,210.72 4,907.23 165,006.35 20% 33,001.27 23,760.91 221,768.53
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 332.94 m2 206,965.49 76,581.56 7,658.16 291,205.20 20% 58,241.04 41,933.55 391,379.79
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 434.28 m 2
61,559.19 22,331.83 2,233.18 86,124.21 20% 17,224.84 12,401.89 115,750.94
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 824,033.23 338,202.14 39,913.44 1,202,148.80 240,429.77 173,109.43 1,615,688.00
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 2,553.91 m2 348,623.73 368,067.08 36,806.71 753,497.52 20% 150,699.50 108,503.64 1,012,700.66
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 133.27 m 2
10,430.83 21,340.83 2,134.08 33,905.74 20% 6,781.15 4,882.43 45,569.32
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 62.73 m 2
8,642.97 9,492.62 949.26 19,084.85 20% 3,816.97 2,748.22 25,650.04
1032(1)c Metal Painting
As Evaluated
As Submitted 367,697.53 398,900.52 39,890.05 806,488.11 161,297.62 116,134.29 1,083,920.02
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 434.28 m2 179,179.22 59,809.73 5,980.97 244,969.92 20% 48,993.98 35,275.67 329,239.57
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 32.90 m 6,943.45 755.52 75.55 7,774.51 20% 1,554.90 1,119.53 10,448.94
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 65.80 m 21,145.49 1,280.53 128.05 22,554.08 20% 4,510.82 3,247.79 30,312.69
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 3,535.91 kg 196,842.45 22,836.22 47,576.65 267,255.32 20% 53,451.06 38,484.77 359,191.15
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 5,170.61 kg 291,271.76 26,951.20 45,111.84 363,334.80 20% 72,666.96 52,320.21 488,321.97
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 65.80 m 12,505.29 1,584.41 158.44 14,248.14 20% 2,849.63 2,051.73 19,149.50
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 146.82 kg 5,839.62 2,594.52 259.45 8,693.59 20% 1,738.72 1,251.88 11,684.19
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 314.91 kg 12,900.99 5,564.90 556.49 19,022.38 20% 3,804.48 2,739.22 25,566.08
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 26.00 pc 4,266.08 895.60 0.90 5,162.57 20% 1,032.51 743.41 6,938.49
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 809,483.16 144,671.47 127,708.72 1,081,863.35 216,372.66 155,788.33 1,454,024.34
Sub-Total C.6
As Evaluated
As Submitted 2,838,365.67 1,141,927.17 310,303.99 4,290,596.84 858,119.36 617,845.98 5,766,562.18
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,531.75 4,288.65 428.87 23,249.27 20% 4,649.85 3,347.89 31,247.01
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 70,144.32 16,265.37 1,626.54 88,036.22 20% 17,607.24 12,677.22 118,320.68
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 162,352.47 18,830.48 1,883.05 183,066.00 20% 36,613.20 26,361.50 246,040.70
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 56,067.25 14,143.80 1,414.38 71,625.43 20% 14,325.09 10,314.06 96,264.58
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 16.00 units 9,707.33 3,674.24 367.42 13,748.99 20% 2,749.80 1,979.85 18,478.64
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 479,028.95 49,621.17 4,962.12 533,612.23 20% 106,722.45 76,840.16 717,174.84
SPL-2 Fire Protection System
As Evaluated
As Submitted 801,631.80 108,181.78 10,818.18 920,631.76 184,126.35 132,570.96 1,237,329.07
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 30,928.20 9,663.64 966.36 41,558.20 20% 8,311.64 5,984.38 55,854.22
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 63,995.82 7,780.56 778.06 72,554.44 20% 14,510.89 10,447.84 97,513.17
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 36,455.00 3,145.01 314.50 39,914.51 20% 7,982.90 5,747.69 53,645.10
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 60,585.00 5,432.29 543.23 66,560.52 20% 13,312.10 9,584.71 89,457.33
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 210,954.02 29,124.22 2,912.42 242,990.660 48,598.130 34,990.650 326,579.440
TOTAL OF PART E
As Evaluated
As Submitted 6,191,791.20 1,895,701.49 692,931.31 8,780,424.020 1,756,084.810 1,264,381.080 11,800,889.910
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 6,284,783.90 1,902,460.85 880,209.68 9,067,454.450 1,779,550.370 1,301,640.600 12,148,645.420
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 23.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 120 C.D.
Project Description : Complete construction of 2-Storey 4-Classroom School Buidling (with stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.50% 104,000.00
Part II Other General Requirements 1.96% 135,880.93
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.20% 152,645.07
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.68% 2,338,468.06
PART C FINISHING WORKS 46.56% 3,232,938.03
PART D PLUMBING/SANITARY WORKS 11.38% 790,140.37
PART E ELECTRICAL WORKS 2.74% 189,943.30

Total 100% 6,944,015.76

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,448,880.00 A. Total Direct Cost 6,944,015.76
2. Materials 4,819,676.82 B. OCM and Profit 1,360,520.55
3. Rental of Equipment 675,458.93 C. Value Added Tax (12%) 996,544.37
4. Provisional Sum / Daywork D. Total Construction Cost 9,301,080.68
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 1,360,520.55 E. Eng'g & Administrative Overhead, 0.5% 46,739.10
6. Value Added Tax (12%) 996,544.37 F. RROW Acquisition
7. EAO, 0.5 % 46,739.10 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 9,347,819.78 H. TOTAL ESTIMATED COST 9,347,819.78
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.00 mo - - 104,000.00 104,000.00 8% 8,320.00 13,478.40 125,798.40
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 104,000.00 104,000.00 8,320.00 13,478.40 125,798.40
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 76,734.52 4,672.64 - 81,407.16 8% 6,512.57 10,550.37 98,470.10
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 50,281.01 50,281.01 8% 4,022.48 6,516.42 60,819.91
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 79,916.86 5,591.20 50,372.87 135,880.93 11,373.60 17,670.55 164,925.08
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 196.98 m3 - 2,651.06 43,374.18 46,025.23 20% 9,205.05 6,627.63 61,857.91
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 105.37 m3 - 2,882.36 13,620.11 16,502.47 20% 3,300.49 2,376.36 22,179.32
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 111.83 m3 40,626.44 3,059.07 14,455.13 58,140.64 20% 11,628.13 8,372.25 78,141.02
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 33.92 m3 21,868.94 7,608.54 2,499.25 31,976.73 20% 6,395.35 4,604.65 42,976.73
804(4) Gravel Fill
As Evaluated
As Submitted 62,495.38 16,201.03 73,948.67 152,645.07 30,529.02 21,980.89 205,154.98
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 151.93 m3 499,090.05 23,851.38 32,731.11 555,672.54 20% 111,134.51 80,016.85 746,823.90
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 27,248.42 kg 1,006,314.81 209,940.79 81,282.16 1,297,537.76 20% 259,507.55 186,845.44 1,743,890.75
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 960.52 m2 187,948.73 208,174.31 89,134.72 485,257.76 20% 97,051.55 69,877.12 652,186.43
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,693,353.58 441,966.47 203,148.00 2,338,468.06 467,693.61 336,739.41 3,142,901.08
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 115.60 L 36,992.00 6,120.59 612.06 43,724.65 20% 8,744.93 6,296.35 58,765.93
1000(1) Soil Poisoning
As Evaluated
As Submitted 36,992.00 6,120.59 612.06 43,724.65 8,744.93 6,296.35 58,765.93
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 129.91 m2 45,458.14 14,101.26 7,251.83 66,811.23 20% 13,362.25 9,620.82 89,794.30
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 399.98 m2 233,569.41 52,222.55 26,856.39 312,648.35 20% 62,529.67 45,021.36 420,199.38
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 279,027.54 66,323.81 34,108.22 379,459.58 75,891.92 54,642.18 509,993.68
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 133,071.00 26,408.60 2,640.86 162,120.46 20% 32,424.09 23,345.35 217,889.90
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 24.05 m2 16,101.48 20,454.97 2,045.50 38,601.94 20% 7,720.39 5,558.68 51,881.01
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 48.96 m2 90,952.58 62,462.08 32,834.21 186,248.86 20% 37,249.77 26,819.84 250,318.47
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 21.76 m2 18,811.20 3,123.10 1,641.71 23,576.02 20% 4,715.20 3,394.95 31,686.17
1005(5) Window Grill
As Evaluated
As Submitted #REF! 20.00 set 30,000.00 - - 30,000.00 20% 6,000.00 4,320.00 40,320.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 80.00 pc 5,301.60 - - 5,301.60 20% 1,060.32 763.43 7,125.35
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 12,400.00 3,272.80 327.28 16,000.08 20% 3,200.02 2,304.01 21,504.11
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 306,637.85 115,721.55 39,489.56 461,848.96 92,369.79 66,506.26 620,725.01
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 424.17 m2 80,899.25 24,393.70 2,439.37 107,732.32 20% 21,546.46 15,513.45 144,792.23
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,783.22 m2 145,448.15 117,995.35 11,799.54 275,243.04 20% 55,048.61 39,635.00 369,926.65
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 73.42 m 124,243.67 3,355.96 3,911.08 131,510.71 20% 26,302.14 18,937.54 176,750.39
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 237.86 m2 147,860.91 54,711.63 5,471.16 208,043.70 20% 41,608.74 29,958.29 279,610.73
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 315.48 m 2
44,719.29 16,222.82 1,622.28 62,564.39 20% 12,512.88 9,009.27 84,086.54
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 642,492.68 265,009.43 31,683.50 939,185.61 187,837.13 135,242.72 1,262,265.46
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,946.86 m2 265,757.84 280,579.61 28,057.96 574,395.41 20% 114,879.08 82,712.94 771,987.43
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 104.49 m 2
8,178.26 16,732.22 1,673.22 26,583.71 20% 5,316.74 3,828.05 35,728.50
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 50.14 m 2
6,908.31 7,587.44 758.74 15,254.49 20% 3,050.90 2,196.65 20,502.04
1032(1)c Metal Painting
As Evaluated
As Submitted 280,844.41 304,899.27 30,489.93 616,233.61 123,246.72 88,737.64 828,217.97
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 315.48 m2 130,163.63 43,448.40 4,344.84 177,956.87 20% 35,591.37 25,625.79 239,174.03
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 23.90 m 5,044.02 548.84 54.88 5,647.75 20% 1,129.55 813.28 7,590.58
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 47.80 m 15,361.01 930.24 93.02 16,384.27 20% 3,276.85 2,359.33 22,020.45
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 2,271.38 kg 126,446.66 14,669.42 30,562.05 171,678.12 20% 34,335.62 24,721.65 230,735.39
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 3,687.15 kg 207,705.22 19,218.84 32,169.15 259,093.20 20% 51,818.64 37,309.42 348,221.26
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 47.80 m 9,084.39 1,150.98 115.10 10,350.47 20% 2,070.09 1,490.47 13,911.03
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 101.34 kg 4,030.70 1,790.82 179.08 6,000.60 20% 1,200.12 864.09 8,064.81
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 214.42 kg 8,784.19 3,789.10 378.91 12,952.21 20% 2,590.44 1,865.12 17,407.77
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 18.00 pc 2,953.44 620.03 0.62 3,574.09 20% 714.82 514.67 4,803.58
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 588,162.07 108,565.52 95,758.02 792,485.62 158,497.10 114,117.94 1,065,100.66
Sub-Total C.6
As Evaluated s
As Submitted 2,134,156.56 866,640.17 232,141.28 3,232,938.03 646,587.59 465,543.09 4,345,068.71
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,103.75 4,217.17 421.72 22,742.64 20% 4,548.53 3,274.94 30,566.11
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 62,014.42 14,379.53 1,437.95 77,831.90 20% 15,566.38 11,207.79 104,606.07
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 161,176.47 18,715.66 1,871.57 181,763.70 20% 36,352.74 26,173.97 244,290.41
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 46,716.75 12,022.23 1,202.22 59,941.20 20% 11,988.24 8,631.53 80,560.97
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 12.00 units 7,280.50 2,755.68 275.57 10,311.74 20% 2,062.35 1,484.89 13,858.98
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 385,396.15 40,781.29 4,078.13 430,255.57 20% 86,051.11 61,956.80 578,263.48
SPL-2 Fire Protection System
As Evaluated
As Submitted 686,487.77 94,229.64 9,422.96 790,140.37 158,028.07 113,780.20 1,061,948.64
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 25,137.80 8,457.60 845.76 34,441.16 20% 6,888.23 4,959.53 46,288.92
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 52,894.17 6,115.24 611.52 59,620.93 20% 11,924.19 8,585.41 80,130.53
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 24,259.70 2,573.19 257.32 27,090.21 20% 5,418.04 3,900.99 36,409.24
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 41,985.00 4,002.74 400.27 46,388.01 20% 9,277.60 6,679.87 62,345.48
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 163,266.67 24,251.49 2,425.15 189,943.300 37,988.660 27,351.830 255,283.790
TOTAL OF PART E
As Evaluated
As Submitted 4,739,759.96 1,443,288.80 521,086.07 6,704,134.830 1,340,826.950 965,395.420 9,010,357.200
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 4,819,676.82 1,448,880.00 675,458.93 6,944,015.760 1,360,520.550 996,544.370 9,301,080.680
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING Appropriation :


( 9.5m x 14.00m ) Source of Fund :
Project ID : Target Start Date :
Location : Total Project Duration : 115 C.D.
Project Description : Complete construction of 2-Storey 2-Classroom School Buidling (with stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 2.05% 99,666.67
Part II Other General Requirements 2.20% 107,225.89
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.01% 97,854.73
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 31.95% 1,556,092.30
PART C FINISHING WORKS 43.89% 2,137,714.37
PART D PLUMBING/SANITARY WORKS 15.19% 739,573.28
PART E ELECTRICAL WORKS 2.71% 132,171.50

Total 100% 4,870,298.74

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 991,254.38 A. Total Direct Cost 4,870,298.74
2. Materials 3,400,548.90 B. OCM and Profit 949,735.78
3. Rental of Equipment 478,495.46 C. Value Added Tax (12%) 698,404.14
4. Provisional Sum / Daywork D. Total Construction Cost 6,518,438.66
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 949,735.78 E. Eng'g & Administrative Overhead, 0.5% 32,755.97
6. Value Added Tax (12%) 698,404.14 F. RROW Acquisition
7. EAO, 0.5% 32,755.97 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 6,551,194.63 H. TOTAL ESTIMATED COST 6,551,194.63
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 3.83 mo - - 99,666.67 99,666.67 8% 7,973.33 12,916.80 120,556.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 99,666.67 99,666.67 7,973.33 12,916.80 120,556.80
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 63,384.94 4,672.64 - 68,057.58 8% 5,444.61 8,820.26 82,322.45
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 34,975.55 34,975.55 8% 2,798.04 4,532.83 42,306.42
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 66,567.28 5,591.20 35,067.40 107,225.89 9,081.20 13,956.85 130,263.94
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 144.01 m3 - 1,938.16 31,710.40 33,648.56 20% 6,729.71 4,845.39 45,223.66
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 66.34 m3 - 1,814.71 8,575.10 10,389.81 20% 2,077.96 1,496.13 13,963.90
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 64.02 m3 23,257.67 1,751.25 8,275.22 33,284.13 20% 6,656.83 4,792.92 44,733.88
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 21.78 m3 14,042.02 4,885.44 1,604.77 20,532.23 20% 4,106.45 2,956.64 27,595.32
804(4) Gravel Fill
As Evaluated
As Submitted 37,299.69 10,389.55 50,165.49 97,854.73 19,570.95 14,091.08 131,516.76
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 102.63 m3 337,139.55 16,111.81 22,110.14 375,361.50 20% 75,072.30 54,052.06 504,485.86
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 18,342.24 kg 677,399.56 141,321.38 54,714.99 873,435.92 20% 174,687.18 125,774.77 1,173,897.87
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 608.26 m2 119,020.63 131,828.70 56,445.55 307,294.88 20% 61,458.98 44,250.46 413,004.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,133,559.73 289,261.89 133,270.69 1,556,092.30 311,218.46 224,077.29 2,091,388.05
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 75.31 L 24,099.20 3,987.39 398.74 28,485.32 20% 5,697.06 4,101.89 38,284.27
1000(1) Soil Poisoning
As Evaluated
As Submitted 24,099.20 3,987.39 398.74 28,485.32 5,697.06 4,101.89 38,284.27
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 112.48 m2 39,359.03 12,209.30 6,278.85 57,847.18 20% 11,569.44 8,329.99 77,746.61
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 227.17 m2 132,656.54 29,659.97 15,253.18 177,569.69 20% 35,513.94 25,570.04 238,653.67
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 172,015.57 41,869.27 21,532.03 235,416.87 47,083.38 33,900.03 316,400.28
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 85,976.15 19,519.40 1,951.94 107,447.49 20% 21,489.50 15,472.44 144,409.43
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 13.71 m2 9,178.85 11,660.61 1,166.06 22,005.51 20% 4,401.10 3,168.79 29,575.40
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 24.48 m2 45,476.29 31,231.04 16,417.10 93,124.43 20% 18,624.89 13,409.92 125,159.24
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 10.88 m2 9,405.60 1,561.55 820.86 11,788.01 20% 2,357.60 1,697.47 15,843.08
1005 (5) Window Grill
As Evaluated
As Submitted #REF! 16.00 set 24,000.00 - - 24,000.00 20% 4,800.00 3,456.00 32,256.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 64.00 pc 4,241.28 - - 4,241.28 20% 848.26 610.74 5,700.28
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 6,200.00 1,636.40 163.64 8,000.04 20% 1,600.01 1,152.01 10,752.06
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 184,478.17 65,609.00 20,519.60 270,606.76 54,121.36 38,967.37 363,695.49
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 263.35 m2 50,227.07 15,145.06 1,514.51 66,886.64 20% 13,377.33 9,631.68 89,895.65
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,252.61 m 2
102,169.00 82,884.98 8,288.50 193,342.49 20% 38,668.50 27,841.32 259,852.31
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 55.82 m 94,460.39 2,551.48 2,973.53 99,985.40 20% 19,997.08 14,397.90 134,380.38
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 142.77 m 2
88,750.12 32,839.40 3,283.94 124,873.45 20% 24,974.69 17,981.78 167,829.92
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 196.68 m 2
27,879.39 10,113.81 1,011.38 39,004.58 20% 7,800.92 5,616.66 52,422.16
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 462,807.37 191,864.70 23,511.92 678,184.01 135,636.82 97,658.51 911,479.34
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,339.81 m2 182,891.94 193,092.14 19,309.21 395,293.30 20% 79,058.66 56,922.24 531,274.20
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 75.71 m 2
5,925.70 12,123.61 1,212.36 19,261.67 20% 3,852.33 2,773.68 25,887.68
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 37.55 m 2
5,173.66 5,682.25 568.23 11,424.14 20% 2,284.83 1,645.08 15,354.05
1032(1)c Metal Painting
As Evaluated
As Submitted 193,991.30 210,898.01 21,089.80 425,979.11 85,195.82 61,341.00 572,515.93
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 196.68 m2 81,148.04 27,087.08 2,708.71 110,943.82 20% 22,188.76 15,975.91 149,108.49
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 14.90 m 3,144.60 342.16 34.22 3,520.98 20% 704.20 507.02 4,732.20
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 29.80 m 9,576.53 579.94 57.99 10,214.46 20% 2,042.89 1,470.88 13,728.23
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 1,008.85 kg 56,162.21 6,515.53 13,574.36 76,252.09 20% 15,250.42 10,980.30 102,482.81
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 2,143.69 kg 120,758.74 11,173.73 18,702.98 150,635.45 20% 30,127.09 21,691.50 202,454.04
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 29.80 m 5,663.49 717.56 71.76 6,452.81 20% 1,290.56 929.20 8,672.57
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 55.85 kg 2,221.38 986.95 98.69 3,307.02 20% 661.40 476.21 4,444.63
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 113.93 kg 4,667.40 2,013.30 201.33 6,882.03 20% 1,376.41 991.01 9,249.45
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 10.00 pc 1,640.80 344.46 0.34 1,985.60 20% 397.12 285.93 2,668.65
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 363,572.00 72,159.56 63,310.74 499,042.30 99,808.45 71,862.08 670,712.83
Sub-Total C.6
As Evaluated
As Submitted 1,400,963.60 586,387.94 150,362.84 2,137,714.37 427,542.89 307,830.88 2,873,088.14
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 17,675.75 3,788.31 378.83 21,842.89 20% 4,368.58 3,145.38 29,356.85
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 53,018.02 12,257.96 1,225.80 66,501.77 20% 13,300.35 9,576.25 89,378.37
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 160,000.47 18,543.43 1,854.34 180,398.24 20% 36,079.65 25,977.35 242,455.24
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 32,018.30 8,368.42 836.84 41,223.55 20% 8,244.71 5,936.19 55,404.45
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 8.00 units 4,853.66 1,837.12 183.71 6,874.50 20% 1,374.90 989.93 9,239.33
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 371,746.15 39,720.51 3,972.05 415,438.71 20% 83,087.74 59,823.17 558,349.62
SPL-2 Fire Protection System
As Evaluated
As Submitted 645,112.09 85,873.81 8,587.38 739,573.28 147,914.65 106,498.55 993,986.48
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 19,023.20 2,325.32 232.53 21,581.05 20% 4,316.21 3,107.67 29,004.93
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 37,258.20 3,747.40 374.74 41,380.34 20% 8,276.07 5,958.77 55,615.18
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 18,390.10 2,001.37 200.14 20,591.61 20% 4,118.32 2,965.19 27,675.12
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 23,385.00 2,573.19 257.32 26,215.51 20% 5,243.10 3,775.03 35,233.64
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 117,046.50 13,750.00 1,375.00 132,171.500 26,434.300 19,032.690 177,638.490
TOTAL OF PART E
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF PART III
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 3,400,548.90 991,254.38 478,495.46 4,870,298.740 949,735.780 698,404.140 6,518,438.660
GRAND TOTAL
As Evaluated

You might also like