Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Cagmanaba Hs ABC, Dupa, Pow, Gantt

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 125

labor Equipment operator

foreman leadman skilled semi skilled unskilled driver heavy High skilled light skilled
97.25 89.15 70.35 64.95 54.14 70.35 80.95 80.95 75.75
2009 ACEL RATES
(Minimum Operation = 8 hrs. per day)

No. Name & Capacity Description Hourly Rate Daily Rate


1 Air Compressor 86-125 cfm/42Hp 358.00 2,864.00
2 Asphalt Batching Plant 1,139.63 9,117.04
3 Asphalt Distributor 10 ft wide 936.00 7,488.00
4 Asphalt Paver/Finisher PF-180 1,349.00 10,792.00
5 Backhoe SE 130 LC-2, 0.80 cu.m. 1,537.00 12,296.00
6 Backhoe, Wheel Type PW60-3, 0.28 cu.m. 840.00 6,720.00
7 Backhoe with Pavement Breaker 2,074.95 16,599.60
8 Bulldozer D65A-8/155Hp 3,379.00 27,032.00
9 Clampshell 315.00 2,520.00
10 Chain Saw 120.00 960.00
11 Concrete Paver/Finisher GP-2500 Slipform 6,237.00 49,896.00
12 Concrete Batching Plant 30 cu.m. 1,208.03 9,664.24
13 Crawler Crane 46-50T 1,956.00 15,648.00
14 Crawler Crane 36-40T 1,729.00 13,832.00
15 Concrete Vibrator 91.25 730.00
16 Concrete Mixer 1.5-2 Bagger 190.00 1,520.00
17 Concrete Mixer 1-Bagger 172.00 1,376.00
18 Concrete Screeder 545.00 4,360.00
19 Concrete Saw 32.63 261.04
20 Diesel Hammer K25-DSL 1,249.00 9,992.00
21 Drop Hammer 160.00 1,280.00
22 Dump Truck 1,420.00 11,360.00
23 Forklift 597.00 4,776.00
24 Generator Set All Make 1,296.67 10,373.36
25 Oxygen/Acetylene Cutting Outfit 110.00 880.00
26 Payloader 1.5 cu.m. 1,733.00 13,864.00
27 Plate Compactor 123.00 984.00
28 Power Broom Towed Type (Engine 2m wide) 130.55 1,044.40
29 Rebar Bender 351.50 2,812.00
30 Rebar Cutter 219.75 1,758.00
31 Road Grader 140Hp / G710A 2,173.00 17,384.00
32 Road Roller, Vibratory Single Smooth Drum, SP 56 1,846.00 14,768.00
33 Road Roller, Pneumatic Tire/Static W251D 553.00 4,424.00
34 Service Truck / Stake Truck 6-8 MT/195Hp 851.00 6,808.00
35 Service Vehicle Frontier, 3.2 AT II 4x4 1,360.00 10,880.00
36 Transit Mixer 5-6 cu.m. 1,279.00 10,232.00
37 Tower Lights 5Hp / 2.70 KW Generator 328.12 2,624.96
38 Truck-Mounted Crane 21-25T 1,427.00 11,416.00
39 Truck, 6-wheeler 5T 711.88 5,695.04
40 Vibro Hammer Hydraulic Driven 3,069.00 24,552.00
41 Water Truck (1000 Gal.) 1,065.00 8,520.00
42 Welding Machine 121.50 972.00
Construction of Health Station at Brgy. Roxas
Brgy. Roxas, Jipapad, Eastern Samar
PORTLAND CEMENT

Source: BORONGAN

BASIC PRICE: 300.00 per bag

LOADING: Free

HAULING (Borongan to Jipapad)

Road Condition: Paved


Terrain: Flat
Distance = 155 km.
Speed = 35 kph
Hauling Time = 4.42857142857143 hrs. (8 hrs work/day)

UNLOADING
Manual unloading:
Rate of Manual unloading = 0.50 min. per bag
No. of bags/truck = 10,000.00 kg. / 40.00 kg. per bag
= 250.00 bags
Time = 250.00 bags x 0.50 min. per bag
= 125.00 min.
= 2.08 hrs.

RETURN TRIP
Distance = 155.00 km.
Speed = 55.00 kph
Hauling Time = 2.82 hrs.

TOTAL TIME = HAULING + UNLOADING +


= 4.43 + 2.08 +
= 9.33 hrs.
= 1.1663 days (8 hrs work/day)

10% Allowance for Delay = 0.11663 days

TOTAL TIME = 1.28 days

COST: Equipment No. Of Days Rate Amount


*Cargo Truck 1.2829 9512.00 12,202.82
* Rental = - per hour = - per day
Truck capacity 250 Bags

HAULING COST PER BAG = 12,202.82 / 250


= 48.81

HAULING PRICE PER BAG say 49.00

MAT'L. COST = BASIC PRICE + HAULING COST

300.00 + 49.00

MAT'L. COST = 349.00

PREPARED: REVIEWED AND CHECKED BY:

ENGR. ZEDRICK B. TEJONES ENGR. JUDITH B. LOMUNTAD


Engineer II Municipal Engineer

APPROVED BY:

HON. BENJAMIN E. VER, MD


Municipal Mayor
Construction of Health Station at Brgy. Roxas
Brgy. Roxas, Jipapad, Eastern Samar

SAND

Source: TACLOBAN

BASIC PRICE: 635.00 per cu.m.

LOADING: Free

HAULING (Tacloban to Jipapad)

Road Condition: Paved


Terrain: Flat
Distance = 241.00 km.
Speed = 30.00 kph
Hauling Time = 8.03 hrs. (8 hrs work/day)

UNLOADING
Time: 10.00 min.
= 0.17 hr.

RETURN TRIP
Distance = 241.00 km.
Speed = 55.00 kph
Hauling Time = 4.38 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 8.03 + 0.17 +
= 12.58 hrs.
= 1.57 days (8 hrs work/day)

10% Allowance for Delay = 0.16 days

TOTAL TIME = 1.73 days


COST: Equipment No. Of Days Rate Amount
Dumptruck 1.73 11,360.00 19,652.80

Dumptruck capacity: 8.00 cu.m.

HAULING COST PER CU.M. = 19,652.80 / 8.00


= 2,456.60
SAY 2,457.00

HAULING PRICE /CU.M.

MAT'L. COST = BASIC PRICE + HAULING COST

635.00 + 2,457.00

MAT'L. COST = 3,092.00

PREPARED: REVIEWED AND CHECKED BY:

ENGR. ZEDRICK B. TEJONES ENGR. JUDITH B. LOMUNTAD


Engineer II Municipal Engineer

HON. BENJAMIN E. VER, MD


Municipal Mayor

Construction of Health Station at Brgy. Roxas


Brgy. Roxas, Jipapad, Eastern Samar

GRAVEL,G1

Source: TACLOBAN
BASIC PRICE: 800.00 per cu.m.

LOADING: Free

HAULING (Tacloban to Jipapad)

Road Condition: Paved


Terrain: Flat
Distance = 241 km.
Speed = 30 kph
Hauling Time = 8.03333333333333 hrs. (8 hrs work/day)

UNLOADING
Time: 10 min.
= 0.166666666666667 hr.

RETURN TRIP
Distance = 241 km.
Speed = 55 kph
Hauling Time = 4.38181818181818 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 8.03333333333333 + 0.166666667 +
= 12.5818181818182 hrs.
= 1.57272727272727 days (8 hrs work/day)

10% Allowance for Delay = 0.157272727272727 days

TOTAL TIME = 1.73 days

COST: Equipment No. Of Days Rate Amount


Dumptruck 1.73 11360.00 19,652.80

Dumptruck capacity: 8 cu.m.

HAULING COST PER CU.M. = 19,652.80 / 8


= 2,456.60
SAY 2,457.00

HAULING PRICE PER CU.M.


MAT'L. COST = BASIC PRICE + HAULING COST

800.00 + 2,457.00

MAT'L. COST = 3,257.00

PREPARED: REVIEWED AND CHECKED BY:

ENGR. ZEDRICK B. TEJONES ENGR. JUDITH B. LOMUNTAD


Engineer II Municipal Engineer

HON. BENJAMIN E. VER, MD


Municipal Mayor

Construction of Health Station at Brgy. Roxas


Brgy. Roxas, Jipapad, Eastern Samar

REINFORCING STEEL BARS, GRADE 40

Source: BORONGAN

BASIC PRICE: 50.00 per kg.

LOADING: Free

HAULING (Borongan to Project Site

Road Condition: Paved


Terrain: Flat
Distance = 155.00 km.
Speed = 35.00 kph
Hauling Time = 4.43 hrs. (8 hrs work/day)

UNLOADING
Manual Unloading: Free
Time = 4.00 hrs.

RETURN TRIP
Distance = 155.00 km.
Speed = 55.00 kph
Hauling Time = 2.82 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 4.43 + 4.00 +
= 11.25 hrs.
= 1.41 days (8 hrs work/day)

10% Allowance for Delay = 0.14 days

TOTAL TIME = 1.55 days

COST: Equipment No. Of Days Rate Amount


*Cargo Truck 1.55 9,512.00 14,709.63

* Rental = 1,125.00 per hour = 9,000.00 per day


Truck capacity 5.00 Tons = 5,000.00 kg.

HAULING COST PER KG. = 14,709.63 / 5,000.00


= 2.94 + -
say 3.00
STOCKPILING by Payloader

Bucket Capacity 1.53 cu.m.

No. of scoops = Truck capacity / Bucket Capacity


= 3.27

Cycle Time = 10.00 sec.

Stockpiling Time = No. of scoops x Cycle Time


= 32.68 sec.
= 0.01 hrs.
= 0.00 days (@ 8hrs/day)

STOCKPILING COST: Equipment No. of Days Rate Amount


Payloader 0.00 1,733.00 1.97
MAT'L. COST = BASIC PRICE + HAULING COST

50.00 + 3.00

MAT'L. COST = 53.00

PREPARED: REVIEWED AND CHECKED BY:

ENGR. ZEDRICK B. TEJONES ENGR. JUDITH B. LOMUNTAD


Engineer II Municipal Engineer

HON. BENJAMIN E. VER, MD


Municipal Mayor

PHENOLIC BOARD (00.19 X 1.2 X 2.4)

Source: BORONGAN

BASIC PRICE: 1,400.00 per piece

LOADING: Free

HAULING (Borongan to Project Site

Road Condition: Paved


Terrain: Flat
Distance = 155.00 km.
Speed = 35.00 kph
Hauling Time = 4.43 hrs. (8 hrs work/day)

UNLOADING
Manual Unloading: Free
Time = 2.00 hrs.
RETURN TRIP
Distance = 155.00 km.
Speed = 55.00 kph
Hauling Time = 2.82 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 4.43 + 2.00 +
= 9.25 hrs.
= 1.16 days (8 hrs work/day)

10% Allowance for Delay = 0.12 days

TOTAL TIME = 1.27 days

COST: Equipment No. Of Days Rate Amount


*Cargo Truck 1.27 9,512.00 12,093.83

* Rental = 1,189.00 per hour = 9,512.00 per day


Truck capacity 10.00 cu.m = 144.00 pcs

HAULING COST PER pc. = 12,093.83 / 144.00


= 83.98 + -
say 84.00
STOCKPILING by Payloader

Bucket Capacity 1.53 cu.m.

No. of scoops = Truck capacity / Bucket Capacity


= 6.54

Cycle Time = 10.00 sec.

Stockpiling Time = No. of scoops x Cycle Time


= 65.36 sec.
= 0.02 hrs.
= 0.00 days (@ 8hrs/day)

STOCKPILING COST: Equipment No. of Days Rate Amount


Payloader 0.00 - -

MAT'L. COST = BASIC PRICE + HAULING COST

1,400.00 + 84.00
MAT'L. COST = 1,484.00
RETURN TRIP
2.82
RETURN TRIP
4.38
RETURN TRIP
4.381818181818
RETURN TRIP
2.82
0.05
RETURN TRIP
2.82
Republic of the Philippines
MUNICIPALITY OF JIPAPAD
OFFICE OF THE MUNICIPAL ENGINEER
Jipapad, Eastern Samar

PROGRAM OF WORKS ITEMIZED BREAKDOWN

DIRECT COST TOTAL MARK-UP VAT TOTAL COST


ITEM NO. ITEM DESCRIPTION % QUANTITY UNIT
MATERIAL LABOR EQUIPMENT TOTAL % VALUE 5%
PART II OTHER GENERAL REQUIREMENTS
B.1 Temporary Facility 0.50% 1.00 l.s. 26,322.50 2,737.44 - 29,059.94 8% 2,324.80 1,569.24 32,953.98
B.5 Project Billboard/ Sign Board 0.10% 1.00 ea 3,182.34 1,837.12 - 5,019.46 20% 1,003.89 301.17 6,324.52
B.7(2) Occupational Safety and Health 0.90% 1.00 l.s. 15,411.00 36,720.00 - 52,131.00 8% 4,170.48 2,815.07 59,116.55
B.9 Mobilization/ Demobilization 0.61% 1.00 l.s. - - 38,490.16 38,490.16 0% - 1,924.51 40,414.67
TOTAL OF PART II 44,915.84 41,294.56 38,490.16 124,700.56 7,499.17 6,609.99 138,809.72
CIVIL, MECHANICAL, ELECTRICAL AND
PART III
SANITARY/PLUMBING WORKS
PART A EARTHWORKS
800(1) Clearing and Grubbing 0.11% 120.00 m2 - 461.43 5,451.29 5,912.72 20% 1,182.54 354.76 7,450.02
800(6) Removal of Structures and Obstruction 0.39% 120.00 m2 - 8,224.88 12,182.49 20,407.37 20% 4,081.47 1,224.44 25,713.28
803(1)a Structure Excavation 0.82% 91.89 m3 - 2,473.40 40,467.59 42,941.00 20% 8,588.20 2,576.46 54,105.66
803(3) Structure Excavation (Foundation Fill) 0.21% 55.18 m3 - 1,509.32 9,459.08 10,968.40 20% 2,193.68 658.10 13,820.18
804(1)b Embankment from Borrow 0.87% 74.97 m3 33,736.50 2,050.78 9,690.61 45,477.89 20% 9,095.58 2,728.67 57,302.14
804(4) Gravel Fill 0.27% 12.50 m3 10,495.80 2,802.73 920.64 14,219.17 20% 2,843.83 853.15 17,916.16
TOTAL OF PART A 44,232.30 17,522.55 78,171.70 139,926.55 27,985.31 8,395.58 176,307.44
PART B PLAIN AND REINFORCED CONCRETE WORKS

900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 13.48% 128.03 m3 672,167.61 20,099.64 14,210.86 706,478.10 20% 141,295.62 42,388.69 890,162.41

901(1) Lean Concrete 1.12% 3.71 m3 14,961.38 33,374.55 10,432.46 58,768.38 20% 11,753.68 3,526.10 74,048.16
902(1)a Reinforcing Steel, Grade 40 7.62% 5,251.86 kgs 343,081.69 40,463.98 15,666.32 399,212.00 20% 79,842.40 23,952.72 503,007.12
902(1)b Reinforcing Steel, Grade 60 14.06% 9,437.91 kgs 636,358.16 72,716.23 28,153.33 737,227.71 20% 147,445.54 44,233.66 928,906.92
903(2) Forms and Falseworks 7.52% 795.04 m2 148,161.32 172,310.56 73,778.81 394,250.69 20% 78,850.14 23,655.04 496,755.87
TOTAL OF PART B 1,814,730.16 338,964.95 142,241.77 2,295,936.88 459,187.38 137,756.21 2,892,880.47
PART C FINISHING WORKS
C.1 Termite Control Works and Waterproofing
1000(1) Soil Poisoning 0.08% 9.00 L 3,780.00 476.52 47.65 4,304.17 20% 860.83 258.25 5,423.25
1016(1)a Waterproofing 1.28% 117.99 m2 37,166.85 27,095.22 2,709.52 66,971.60 20% 13,394.32 4,018.30 84,384.22
Sub-Total C.1 40,946.85 27,571.74 2,757.17 71,275.76 14,255.15 4,276.55 89,807.47
C.2. Masonry Works
DIRECT COST TOTAL MARK-UP VAT TOTAL COST
ITEM NO. ITEM DESCRIPTION % QUANTITY UNIT
MATERIAL LABOR EQUIPMENT TOTAL % VALUE 5%

1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 1.06% 108.00 m2 37,791.38 11,723.01 6,028.77 55,543.17 20% 11,108.63 3,332.59 69,984.39

1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 2.03% 135.82 m2 79,312.46 17,733.05 9,119.54 106,165.05 20% 21,233.01 6,369.90 133,767.97

Sub-Total C.2 117,103.84 29,456.06 15,148.32 161,708.22 32,341.64 9,702.49 203,752.36


C.3 Fabricated Materials
1004(2)a Locksets 0.31% 11.00 set 16,500.00 - - 16,500.00 20% 3,300.00 990.00 20,790.00
1004(2)g Hinges 0.01% 11.00 set 728.97 - - 728.97 20% 145.79 43.74 918.50
1007(1) Aluminum Framed Glass Doors 1.25% 15.12 m2 65,338.81 - - 65,338.81 20% 13,067.76 3,920.33 82,326.90
1008(1) Aluminum Framed Glass Windows 1.50% 36.14 m2 78,875.55 - - 78,875.55 20% 15,775.11 4,732.53 99,383.19

1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 0.35% 7.00 set 14,700.00 3,214.96 321.50 18,236.46 20% 3,647.29 1,094.19 22,977.94

1010(2)b Wooden Doors (Wood Panel) 1.19% 13.23 m2 59,251.48 3,038.14 303.81 62,593.43 20% 12,518.69 3,755.61 78,867.73
Sub-Total C.3 235,394.81 6,253.10 625.31 242,273.22 48,454.64 14,536.40 305,264.26
C.4 Finishing Works
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 4.17% 240.00 m2 157,951.20 55,203.86 5,520.39 218,675.45 20% 43,735.09 13,120.53 275,531.07
1018(1) Glazed Tiles and Trims 7.41% 249.90 m2 237,933.94 136,714.52 13,671.45 388,319.91 20% 77,663.98 23,299.19 489,283.08
1018(2) Unglazed Tiles 2.54% 90.00 m2 95,285.22 34,465.85 3,446.58 133,197.65 20% 26,639.53 7,991.86 167,829.04
1021(1)c Plain Cement Finish with floor hardener 0.18% 23.40 m2 7,916.69 1,345.72 134.57 9,396.98 20% 1,879.40 563.82 11,840.19
1027(1) Plain Cement Plaster Finish 1.83% 622.66 m2 50,787.20 41,201.30 4,120.13 96,108.63 20% 19,221.73 5,766.52 121,096.88
1053(2)a1 38 mm Ø Stainless Steel Pipe Railings 0.83% 108.80 m 32,870.89 4,973.14 5,795.77 43,639.80 20% 8,727.96 2,618.39 54,986.16
1038(1) Reflective Insulation 0.45% 120.00 m2 17,010.00 6,170.72 617.07 23,797.79 20% 4,759.56 1,427.87 29,985.22
Sub-Total C.4 599,755.13 280,075.11 33,305.97 913,136.21 182,627.24 54,788.18 1,150,551.64
C.5 Painting Works
1032(1)a Masonry/Concrete Painting 4.21% 747.63 m2 102,055.89 107,747.72 10,774.77 220,578.39 20% 44,115.68 13,234.70 277,928.76
1032(1)b Wood Painting 0.13% 26.46 m2 2,070.98 4,237.10 423.71 6,731.79 20% 1,346.36 403.91 8,482.06
Sub-Total C.5 104,126.87 111,984.82 11,198.48 227,310.18 45,462.04 13,638.61 286,410.82
C.6 Roof Framing and Roofing Works
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk 2.44% 231.58 m2 92,764.46 31,893.56 3,189.36 127,847.38 20% 25,569.48 7,670.84 161,087.70
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) 0.15% 32.32 m 6,953.49 742.20 74.22 7,769.90 20% 1,553.98 466.19 9,790.07
1003(5) Roof Frame (Wood) 3.97% 1,701.22 bd.ft. 94,706.10 36,767.88 76,601.68 208,075.66 20% 41,615.13 12,484.54 262,175.34
1047(6) Metal Structure Accessories, Steel Plates 1.35% 957.00 kgs 52,252.20 16,911.54 1,691.15 70,854.90 20% 14,170.98 4,251.29 89,277.16
1047(7)b Metal Structure Accessories, Sag Rods 0.23% 232.30 kgs 7,805.31 4,105.08 - 11,910.39 20% 2,382.08 714.62 15,007.09
1047(4) Metal Structure Accessories, Cross Bracing 0.70% 636.25 kgs 25,306.19 11,243.43 - 36,549.62 20% 7,309.92 2,192.98 46,052.52
1047(3)a Metal Structure Accessories (Bolts) 0.23% 340.00 ea 4,250.00 7,807.76 - 12,057.76 20% 2,411.55 723.47 15,192.78
1047(3)c Metal Structure Accessories, Turn Buckle 0.10% 32.00 ea 4,352.00 1,102.27 - 5,454.27 20% 1,090.85 327.26 6,872.39
Sub-Total C.6 288,389.75 110,573.73 81,556.41 480,519.89 96,103.98 28,831.19 605,455.06
TOTAL OF PART C 1,385,717.26 565,914.57 144,591.66 2,096,223.49 419,244.70 125,773.42 2,641,241.60
DIRECT COST TOTAL MARK-UP VAT TOTAL COST
ITEM NO. ITEM DESCRIPTION % QUANTITY UNIT
MATERIAL LABOR EQUIPMENT TOTAL % VALUE 5%
PART D PLUMBING/SANITARY WORKS
1001(8) Sewer Line Works 0.68% 1.00 l.s. 16,040.00 3,788.31 16,040.00 35,868.31 20% 7,173.66 2,152.10 45,194.07
1002(6) Cold Water Line Works 0.14% 1.00 l.s. 6,056.00 1,358.07 135.81 7,549.88 20% 1,509.98 452.99 9,512.85
1001(9) Downspout/Storm Drain 1.70% 1.00 l.s. 75,856.38 12,257.96 1,225.80 89,340.14 20% 17,868.03 5,360.41 112,568.57
1002(5) Sanitary/Plumbing Fixtures 3.06% 1.00 l.s. 140,052.80 18,543.43 1,854.34 160,450.57 20% 32,090.11 9,627.03 202,167.72
1001(6)b1 Catch basin 0.44% 3.00 units 19,859.15 2,755.68 275.57 22,890.39 20% 4,578.08 1,373.42 28,841.89
1001(11) Septic Vault 0.22% 3.75 sq.m 9,195.44 1,556.96 800.70 11,553.10 20% 2,310.62 693.19 14,556.91
TOTAL OF PART D 267,059.76 40,260.41 20,332.21 327,652.39 65,530.48 19,659.14 412,842.00
PART E ELECTRICAL WORKS
1100(19) Conduits, Boxes, and Fittings 1.35% 1.00 l.s. 56,613.59 12,805.44 1,280.54 70,699.57 20% 14,139.91 4,241.97 89,081.46
1101(18) Wires and Wiring Devices 2.38% 1.00 l.s. 110,332.95 12,919.40 1,291.94 124,544.29 20% 24,908.86 7,472.66 156,925.81
1102(21) Panel Board 0.39% 1.00 l.s. 18,390.10 2,001.37 200.14 20,591.61 20% 4,118.32 1,235.50 25,945.43
1103(1) Lighting Fixtures 0.73% 1.00 l.s. 30,245.00 7,433.66 743.37 38,422.03 20% 7,684.41 2,305.32 48,411.75
1208(1) Fire Alarm System (Emergency Lights) 0.34% 1.00 l.s. 13,890.00 3,759.12 375.91 18,025.03 20% 3,605.01 1,081.50 22,711.54
TOTAL OF PART E 229,471.64 38,918.99 3,891.90 272,282.53 54,456.51 16,336.95 343,075.98
TOTAL OF PART III 3,741,211.12 1,001,581.47 389,229.24 5,132,021.83 1,026,404.37 307,921.30 6,466,347.50
GRAND TOTAL 3,786,126.96 1,042,876.03 427,719.40 5,256,722.40 1,033,903.53 314,531.29 6,605,157.22
Republic of the Philippines
MUNICIPALITY OF JIPAPAD
OFFICE OF THE MUNICIPAL ENGINEER
Jipapad, Eastern Samar

APPROVED BUDGET FOR THE CONTRACT


Project Title: Construction of Health Station at Brgy. Cagmanaba
Location: Brgy. Cagmanaba, Jipapad, Eastern Samar Contract Duration : 264 CD
MARK-UPS IN
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT TOTAL COST UNIT COST
DIRECT COST COST
OCM PROFIT % VALUE
PART II OTHER GENERAL REQUIREMENTS
B.1 Temporary Facility 1.00 l.s. 29,059.94 - 8.00% 8.00% 2,324.80 1,569.24 3,894.04 32,953.98 32,953.98
B.5 Project Billboard/ Sign Board 1.00 ea 5,019.46 12.00% 8.00% 20.00% 1,003.89 301.17 1,305.06 6,324.52 6,324.52
B.7(2) Occupational Safety and Health 1.00 l.s. 52,131.00 - 8.00% 8.00% 4,170.48 2,815.07 6,985.55 59,116.55 59,116.55
B.9 Mobilization/ Demobilization 1.00 l.s. 38,490.16 - - 0.00% - 1,924.51 1,924.51 40,414.67 40,414.67
TOTAL OF PART II 124,700.56 7,499.17 6,609.99 14,109.16 138,809.72
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
800(1) Clearing and Grubbing 120.00 m2 5,912.72 12.00% 8.00% 20.00% 1,182.54 354.76 1,537.30 7,450.02 62.08
800(6) Removal of Structures and Obstruction 120.00 m2 20,407.37 12.00% 8.00% 20.00% 4,081.47 1,224.44 5,305.91 25,713.28 214.28
803(1)a Structure Excavation 91.89 m3 42,941.00 12.00% 8.00% 20.00% 8,588.20 2,576.46 11,164.66 54,105.66 588.81
803(3) Structure Excavation (Foundation Fill) 55.18 m3 10,968.40 12.00% 8.00% 20.00% 2,193.68 658.10 2,851.78 13,820.18 250.47
804(1)b Embankment from Borrow 74.97 m3 45,477.89 12.00% 8.00% 20.00% 9,095.58 2,728.67 11,824.25 57,302.14 764.33
804(4) Gravel Fill 12.50 m3 14,219.17 12.00% 8.00% 20.00% 2,843.83 853.15 3,696.98 17,916.16 1,433.87
TOTAL OF PART A 139,926.55 27,985.31 8,395.58 36,380.89 176,307.44
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 128.03 m3 706,478.10 12.00% 8.00% 20.00% 141,295.62 42,388.69 183,684.31 890,162.41 6,952.66
901(1) Lean Concrete 3.71 m3 58,768.38 12.00% 8.00% 20.00% 11,753.68 3,526.10 15,279.78 74,048.16 19,945.63
902(1)a Reinforcing Steel, Grade 40 5,251.86 kgs 399,212.00 12.00% 8.00% 20.00% 79,842.40 23,952.72 103,795.12 503,007.12 95.78
902(1)b Reinforcing Steel, Grade 60 9,437.91 kgs 737,227.71 12.00% 8.00% 20.00% 147,445.54 44,233.66 191,679.20 928,906.92 98.42
903(2) Forms and Falseworks 795.04 m2 394,250.69 12.00% 8.00% 20.00% 78,850.14 23,655.04 102,505.18 496,755.87 624.82
TOTAL OF PART B 2,295,936.88 459,187.38 137,756.21 596,943.59 2,892,880.47
PART C FINISHING WORKS
C.1 Termite Control Works and Waterproofing
1000(1) Soil Poisoning 9.00 L 4,304.17 12.00% 8.00% 20.00% 860.83 860.83 1,721.67 6,025.84 669.54
1016(1)a Waterproofing 117.99 m2 66,971.60 12.00% 8.00% 20.00% 13,394.32 13,394.32 26,788.64 93,760.23 794.65
C.2. Masonry Works
100 mm CHB Non Load Bearing Wall (including
1046(2)a1 108.00 m2 55,543.17 12.00% 8.00% 20.00% 11,108.63 11,108.63 22,217.27 77,760.43 720.00
Reinforcing Steel)

150 mm CHB Non Load Bearing Wall (including


1046(2)a2 135.82 m2 106,165.05 12.00% 8.00% 20.00% 21,233.01 21,233.01 42,466.02 148,631.08 1,094.32
Reinforcing Steel)
C.3 Fabricated Materials
1004(2)a Locksets 11.00 set 16,500.00 12.00% 8.00% 20.00% 3,300.00 990.00 4,290.00 20,790.00 1,890.00
1004(2)g Hinges 11.00 set 728.97 12.00% 8.00% 20.00% 145.79 43.74 189.53 918.50 83.50
1007(1) Aluminum Framed Glass Doors 15.12 m2 65,338.81 12.00% 8.00% 20.00% 13,067.76 3,920.33 16,988.09 82,326.90 5,444.90
MARK-UPS IN
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT TOTAL COST UNIT COST
DIRECT COST COST
OCM PROFIT % VALUE
1008(1) Aluminum Framed Glass Windows 36.14 m2 78,875.55 12.00% 8.00% 20.00% 15,775.11 4,732.53 20,507.64 99,383.19 2,749.95
1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 7.00 set 18,236.46 12.00% 8.00% 20.00% 3,647.29 1,094.19 4,741.48 22,977.94 3,282.56
1010(2)b Wooden Doors (Wood Panel) 13.23 m2 18,236.46 12.00% 8.00% 20.00% 3,647.29 1,094.19 4,741.48 22,977.94 1,736.81
C.4 Finishing Works
MARK-UPS IN
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT TOTAL COST UNIT COST
DIRECT COST COST
OCM PROFIT % VALUE
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 240.00 m2 218,675.45 12.00% 8.00% 20.00% 43,735.09 13,120.53 56,855.62 275,531.07 1,148.05
1018(1) Glazed Tiles and Trims 249.90 m2 388,319.91 12.00% 8.00% 20.00% 77,663.98 23,299.19 100,963.17 489,283.08 1,957.92
1018(2) Unglazed Tiles 90.00 m2 133,197.65 12.00% 8.00% 20.00% 26,639.53 7,991.86 34,631.39 167,829.04 1,864.77
1021(1)c Plain Cement Finish with floor hardener 23.40 m2 9,396.98 12.00% 8.00% 20.00% 1,879.40 563.82 2,443.22 11,840.19 505.99
1027(1) Plain Cement Plaster Finish 622.66 m2 96,108.63 12.00% 8.00% 20.00% 19,221.73 5,766.52 24,988.25 121,096.88 194.48
1053(2)a1 38 mm Ø Stainless Steel Pipe Railings 108.80 m 43,639.80 12.00% 8.00% 20.00% 8,727.96 2,618.39 11,346.35 54,986.16 505.39
1038(1) Reflective Insulation 120.00 m2 23,797.79 12.00% 8.00% 20.00% 4,759.56 1,427.87 6,187.43 29,985.22 249.88
C.5 Painting Works
1032(1)a Masonry/Concrete Painting 747.63 m2 220,578.39 12.00% 8.00% 20.00% 44,115.68 44,115.68 88,231.35 308,809.74 413.05
1032(1)b Wood Painting 26.46 m2 6,731.79 12.00% 8.00% 20.00% 1,346.36 1,346.36 2,692.72 9,424.51 356.18
C.6 Roof Framing and Roofing Works

1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk 231.58 m2 127,847.38 12.00% 8.00% 20.00% 25,569.48 7,670.84 33,240.32 161,087.70 695.60

1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) 32.32 m 7,769.90 12.00% 8.00% 20.00% 1,553.98 466.19 2,020.17 9,790.07 302.91

1003(5) Roof Frame (Wood) 1,701.22 bd.ft. 208,075.66 12.00% 8.00% 20.00% 41,615.13 12,484.54 54,099.67 262,175.34 154.11
1047(6) Metal Structure Accessories, Steel Plates 957.00 kgs 70,854.90 12.00% 8.00% 20.00% 14,170.98 4,251.29 18,422.27 89,277.16 93.29
1047(7)b Metal Structure Accessories, Sag Rods 232.30 kgs 11,910.39 12.00% 8.00% 20.00% 2,382.08 714.62 3,096.70 15,007.09 64.60
1047(4) Metal Structure Accessories, Cross Bracing 636.25 kgs 36,549.62 12.00% 8.00% 20.00% 7,309.92 2,192.98 9,502.90 46,052.52 72.38
1047(3)a Metal Structure Accessories (Bolts) 340.00 ea 12,057.76 12.00% 8.00% 20.00% 2,411.55 723.47 3,135.02 15,192.78 44.68
1047(3)c Metal Structure Accessories, Turn Buckle 32.00 ea 5,454.27 12.00% 8.00% 20.00% 1,090.85 327.26 1,418.11 6,872.39 214.76
TOTAL OF PART C 2,096,223.49 419,244.70 125,773.42 545,018.12 2,641,241.60
PART D PLUMBING/SANITARY WORKS
1001(8) Sewer Line Works 1.00 l.s. 35,868.31 12.00% 8.00% 20.00% 7,173.66 2,152.10 9,325.76 45,194.07 45,194.07
1002(6) Cold Water Line Works 1.00 l.s. 7,549.88 12.00% 8.00% 20.00% 1,509.98 452.99 1,962.97 9,512.85 9,512.85
1001(9) Downspout/Storm Drain 1.00 l.s. 89,340.14 12.00% 8.00% 20.00% 17,868.03 5,360.41 23,228.44 112,568.57 112,568.57
1002(5) Sanitary/Plumbing Fixtures 1.00 l.s. 160,450.57 12.00% 8.00% 20.00% 32,090.11 9,627.03 41,717.14 202,167.72 202,167.72
1001(6)b1 Catch basin 3.00 units 22,890.39 12.00% 8.00% 20.00% 4,578.08 1,373.42 5,951.50 28,841.89 9,613.96
1001(11) Septic Vault 3.75 sq.m 11,553.10 12.00% 8.00% 20.00% 2,310.62 693.19 3,003.81 14,556.91 3,881.84
TOTAL OF PART D 327,652.39 65,530.48 19,659.14 85,189.62 412,842.00
PART E ELECTRICAL WORKS
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 70,699.57 12.00% 8.00% 20.00% 14,139.91 4,241.97 18,381.88 89,081.46 89,081.46
1101(18) Wires and Wiring Devices 1.00 l.s. 124,544.29 12.00% 8.00% 20.00% 24,908.86 7,472.66 32,381.52 156,925.81 156,925.81
1102(21) Panel Board 1.00 l.s. 20,591.61 12.00% 8.00% 20.00% 4,118.32 1,235.50 5,353.82 25,945.43 25,945.43
1103(1) Lighting Fixtures 1.00 l.s. 38,422.03 12.00% 8.00% 20.00% 7,684.41 2,305.32 9,989.73 48,411.75 48,411.75
1208(1) Fire Alarm System (Emergency Lights) 1.00 l.s. 18,025.03 12.00% 8.00% 20.00% 3,605.01 1,081.50 4,686.51 22,711.54 22,711.54
TOTAL OF PART E 272,282.53 54,456.51 16,336.95 70,793.46 343,075.98
TOTAL OF PART III 5,132,021.83 1,026,404.37 307,921.30 1,334,325.67 6,466,347.50
TOTAL 5,256,722.40 1,033,903.53 314,531.29 1,348,434.82 6,605,157.22

Preparation and Submission: Evaluation: Approval:

Prepared and Submitted by: Reviewed as to Unit Cost: Approved:


MARK-UPS IN
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT TOTAL COST UNIT COST
DIRECT COST COST
OCM PROFIT % VALUE

ZEDRICK B. TEJONES JUDITH B. LOMUNTAD HON. BENJAMIN E. VER, MD


Engineer II Municipal Engineer Municipal Mayor
PROJECT MONITORING FORM
GHANTT CHART

SUB-PROJECT TITLE : Construction of Health Station at Brgy. Cagmanaba TOTAL PROJECT COST: 6,605,157.22
LOCATION:
LOCATION Brgy. Cagmanaba, Jipapad, Eastern Samar SUB-PROJECT DURATION: 264.00 CD

DURATION MONTH 1 MONTH 2


ITEM
ITEM No. DESCRIPTION (WORKING AMOUNT WEIGHT %
NO.
DAYS) WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3
0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
I B.1 Temporary Facility 2 32,953.98 0.50% 1.00 1.00

0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


II B.5 Project Billboard/ Sign Board 1 6,324.52 0.10% 1.00

0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%


III B.7(2) Occupational Safety and Health 50 59,116.55 0.90% 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


IV B.9 Mobilization/ Demobilization 3 40,414.67 0.61% 1.00 1.00 1.00

0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


V 800(1) Clearing and Grubbing 1 7,450.02 0.11% 1.00

0.39% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Removal of Structures and
VI 800(6) Obstruction 2 25,713.28 0.39% 1.00 1.00

0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


VII 803(1)a Structure Excavation 2 54,105.66 0.82% 1.00 1.00

0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Structure Excavation (Foundation
V 803(3) 1 13,820.18 0.21% 1.00
Fill)

0.00% 0.87% 0.00% 0.00% 0.00% 0.00% 0.00%


VIII 804(1)b Embankment from Borrow 1 57,302.14 0.87% 1.00

0.00% 0.27% 0.00% 0.00% 0.00% 0.00% 0.00%


IX 804(4) Gravel Fill 2 17,916.16 0.27% 1.00 1.00

0.00% 8.09% 5.39% 0.00% 0.00% 0.00% 0.00%


Structural Concrete (Ready Mix,
X 900(1)c1 5 890,162.41 13.48% 1.00 1.00 1.00 1.00 1.00
Class A, 28 days)

0.00% 0.00% 1.12% 0.00% 0.00% 0.00% 0.00%


XI 901(1) Lean Concrete 1 74,048.16 1.12% 1.00

0.00% 0.00% 3.81% 3.81% 0.00% 0.00% 0.00%


XII 902(1)a Reinforcing Steel, Grade 40 6 503,007.12 7.62% 1.00 1.00 1.00 1.00 1.00 1.00

OF 0.00% 0.00% 0.00% 2.64% 5.27% 5.27% 0.88%


ESTI
902(1)b Reinforcing Steel, Grade 60 16 928,906.92 14.06% 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
MATE
D
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.63%
- 903(2) Forms and Falseworks 23 496,755.87 7.52% 1.00 1.00 1.00 1.00 1.00

0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1000(1) Soil Poisoning 1 5,423.25 0.08% 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1016(1)a Waterproofing 10 84,384.22 1.28%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


100 mm CHB Non Load Bearing
0 1046(2)a1 4 69,984.39 1.06%
Wall (including Reinforcing Steel)

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Prepar 150 mm CHB Non Load Bearing
1046(2)a2 6 133,767.97 2.03%
ed by: Wall (including Reinforcing Steel)
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0 1004(2)a Locksets 5 20,790.00 0.31%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1004(2)g Hinges 5 918.50 0.01%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1007(1) Aluminum Framed Glass Doors 5 82,326.90 1.25%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Aluminum Framed Glass
0 1008(1) 5 99,383.19 1.50%
Windows

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Frames (Jambs, Sill, Head,
0 1010(1) 2 22,977.94 0.35%
Transoms and Mullions)
JOEL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LESLI
1010(2)b Wooden Doors (Wood Panel) 5 78,867.73 1.19%
E E.
CAPI
CIVIL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Fiber Cement Board Ceiling on
ENGI 1003(1)a1 25 275,531.07 4.17%
Metal Frame
NEER
PRC
Licens 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
e No. 1018(1) Glazed Tiles and Trims 23 489,283.08 7.41%
01261
68 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0 1018(2) Unglazed Tiles 6 167,829.04 2.54%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Plain Cement Finish with floor
- 1021(1)c 1 11,840.19 0.18%
hardener
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0 1027(1) Plain Cement Plaster Finish 11 121,096.88 1.83%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


38 mm Ø Stainless Steel Pipe
0 1053(2)a1 3 54,986.16 0.83%
Railings
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0 1038(1) Reflective Insulation 3 29,985.22 0.45%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1032(1)a Masonry/Concrete Painting 45 277,928.76 4.21%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1032(1)b Wood Painting 2 8,482.06 0.13%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Prepainted Metal Sheets, Long
0 1014(1)b1 14 161,087.70 2.44%
Span, Corrugated, 0.5 mm thk

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Fabricated Metal Roofing
0 1013(2)a1 1 9,790.07 0.15%
Accessory (Ridge/Hip Rolls)
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0 1003(5) Roof Frame (Wood) 9 262,175.34 3.97%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Metal Structure Accessories, Steel
0 1047(6) 10 89,277.16 1.35%
Plates

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Metal Structure Accessories, Sag
0 1047(7)b Rods 3 15,007.09 0.23%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Metal Structure Accessories,
0 1047(4) 7 46,052.52 0.70%
Cross Bracing

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Metal Structure Accessories
0 1047(3)a 5 15,192.78 0.23%
(Bolts)

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Metal Structure Accessories, Turn
0 1047(3)c 1 6,872.39 0.10%
Buckle

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1001(8) Sewer Line Works 2 45,194.07 0.68%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


- 1002(6) Cold Water Line Works 1 9,512.85 0.14%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1001(9) Downspout/Storm Drain 4 112,568.57 1.70%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1002(5) Sanitary/Plumbing Fixtures 11 202,167.72 3.06%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1001(6)b1 Catch basin 2 28,841.89 0.44%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1001(11) Septic Vault 1 14,556.91 0.22%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1100(19) Conduits, Boxes, and Fittings 9 89,081.46 1.35%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1101(18) Wires and Wiring Devices 9 156,925.81 2.38%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1102(21) Panel Board 1 25,945.43 0.39%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


0 1103(1) Lighting Fixtures 4 48,411.75 0.73%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%


Fire Alarm System (Emergency
0 1208(1) 3 22,711.54 0.34%
Lights)

TOTAL 264.00 6,605,157.22 100.00%


Projected Weekly Accomplishment (%) 2.93% 9.33% 10.43% 6.55% 5.38% 5.38% 2.62%
Cummulative Projected Weekly Accomplishment (%) 2.93% 12.26% 22.69% 29.24% 34.62% 40.00% 42.62%
Projected Weekly Disbursement (Php) 193,299.55 616,409.73 688,710.66 432,767.59 355,434.08 355,434.08 173,141.07
Cummulative Projected Weekly Disbursement (Php) 193,299.55 809,709.28 1,498,419.94 1,931,187.54 2,286,621.62 2,642,055.70 2,815,196.77
SLIPPAGE 6 12 18 24 30 36 42

Prepared by:

Engr. JOEL LESLIE E. CAPITO


Civil Engineer
MONTH 3 MONTH 4 MONTH 5

WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.11% 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1.96% 1.96% 1.96% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.77% 0.51% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.53% 0.53% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 1.35% 0.68% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.25% 0.06% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.00% 0.25% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.20% 0.30% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.35% 0.00% 0.00%
1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.96% 0.24% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.67% 1.00% 1.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2.07% 2.00% 1.96% 0.77% 1.04% 1.88% 4.09% 1.87% 1.00% 1.00%
44.69% 46.69% 48.65% 49.42% 50.46% 52.34% 56.43% 58.30% 59.30% 60.30%
136,682.47 131,953.15 129,588.49 50,630.53 68,745.88 124,170.84 270,418.38 123,520.17 66,127.46 66,127.46
2,951,879.25 3,083,832.39 3,213,420.88 3,264,051.41 3,332,797.29 3,456,968.13 3,727,386.51 3,850,906.69 3,917,034.14 3,983,161.60
48 54 60 66 72 78 84 90 96 102
MONTH 5 MONTH 6 MONTH 7 MONTH 8 MONTH 9 MONTH 10 MONTH 11

WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1.00% 1.00% 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.97% 1.93% 1.93% 1.93% 0.64% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 1.27% 1.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.67% 1.00% 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.83% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.19% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.87% 1.05% 0.52% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.32% 2.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.81% 0.54% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.08% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.20% 0.50% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.09% 0.14% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.34% 0.34% 0.00% 0.00% 0.00% 0.00%
1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.14% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.70% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.39% 1.67% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 0.22% 0.00% 0.00% 0.00%
1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 0.00% 0.00% 0.00%
1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.90% 0.45% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.79% 1.58%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.39% 0.00%
1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.55% 0.18%
1.00 1.00 1.00 1.00

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.34%
1.00 1.00 1.00

1.00% 1.00% 2.92% 3.20% 1.93% 1.93% 1.31% 1.00% 1.77% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.96% 1.05% 1.99% 2.65% 0.81% 1.08% 1.20% 3.66% 2.11% 0.90% 2.18% 2.11%
60.30% 61.30% 64.22% 67.42% 69.36% 71.29% 72.60% 73.60% 75.37% 75.93% 76.49% 77.05% 77.61% 78.17% 78.73% 79.30% 80.26% 81.31% 83.30% 85.95% 86.76% 87.84% 89.04% 92.69% 94.80% 95.70% 97.89% 100.00%
66,127.46 66,127.46 192,637.97 211,553.59 127,639.07 127,639.07 86,581.58 66,052.84 116,814.63 37,057.17 37,057.17 37,057.17 37,057.17 37,057.17 37,057.17 37,057.17 63,707.52 69,037.59 131,700.64 174,783.56 53,566.30 71,555.73 79,122.57 241,480.97 139,251.15 59,387.64 144,256.66 139,431.68
3,983,161.60 4,049,289.06 4,241,927.03 4,453,480.62 4,581,119.68 4,708,758.75 4,795,340.33 4,861,393.17 4,978,207.80 5,015,264.97 5,052,322.14 5,089,379.31 5,126,436.48 5,163,493.64 5,200,550.81 5,237,607.98 5,301,315.50 5,370,353.08 5,502,053.73 5,676,837.29 5,730,403.59 5,801,959.31 5,881,081.88 6,122,562.85 6,261,814.01 6,321,201.64 6,465,458.31 6,604,889.99
102 108 114 120 126 132 138 144 150 156 162 168 174 180 186 192 198 204 210 216 222 228 234 240 246 252 258 264
Quantity Derivation

Project: Construction of Health Station at Brgy. Cagmanaba


Location: Brgy. Cagmanaba, Jipapad, Eastern Samar

PART II
B.1 Temporary Facility
Quantity : 1.00 l.s.

B.5 Project Billboard/ Sign Board


Quantity : 1.00 ea

B.7(2) Occupational Safety and Health


Quantity : 1.00 l.s.

B.9 Mobilization/ Demobilization


Quantity : 1.00 l.s.
PART III
800(1) Clearing and Grubbing
Quantity : 120.00 m2

L W H Q Vol/Area Unit
Building Area 10.00 12 1 120 m2

Total 120 m2

800(6) Removal of Structures and Obstruction


Quantity : 120.00 m2

L W H Q Vol/Area Unit
Building Area 10.00 12.00 1 120.00 m2

Total 120 m2

803(1)a Structure Excavation


Quantity : 91.89 m3

L W H Q Vol/Area Unit
F1 1.50 1.50 1.50 22 74.25 m3
FTB 0.25 0.30 228.00 1 17.10 m3
WF1 0.30 0.60 3.00 1 0.54 m3

Total 91.89 m3

803(3) Structure Excavation (Foundation Fill)


Quantity : 55.18 m3

L W H Q Vol/Area Unit
F1 1.50 1.50 0.30 22 14.85 m3
C1 0.40 0.40 1.20 22 4.22 m3
FTB 0.25 0.30 228.00 1 17.10 m3
WF1 0.30 0.60 3.00 1 0.54 m3

Excavation 91.89 less Con. Vol. 36.714 m3


Total 55.18 m3

804(1)b Embankment from Borrow


Quantity : 74.97 m3

L W H Q Vol/Area Unit
Building Area 10.00 12 0.6 1 72.00 m3
Frontage 3.00 1.65 0.6 1 2.97 m3

Total 74.97 m3

804(4) Gravel Fill


Quantity : 12.50 m3

L W H Q Vol/Area Unit
Building Area 10.00 12 0.1 1 12.00 m3
Frontage 3.00 1.65 0.1 1 0.50 m3

Total 12.495 m3

PART B PLAIN AND REINFORCED CONCRETE WORKS


900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
Quantity : 128.03 m3

L W H Q Vol/Area Unit
Footing (F1) 1.50 1.50 0.30 22.00 14.85 m3
Slab on fill (Interior of Building) 10.50 12.50 0.10 1.00 13.13 m3
Slab on fill (Exterior of Building) 3.00 1.65 0.10 1.00 0.50 m3
2F Slab 10.50 12.50 0.10 1.00 13.13 m3
2F Terrace 3.00 1.65 0.10 1.00 0.50 m3
Footing Beam (FTB1) 0.25 0.30 228.00 1.00 17.10 m3
Wall Footing (WF1) 0.30 0.60 3.00 1.00 0.54 m3
Columns (C1) 0.40 0.40 4.80 22.00 16.90 m3
2F Beam (GB1) 0.30 0.40 3.00 29.00 10.44 m3
2F Beam (GB2) 0.30 0.40 4.00 5.00 2.40 m3
Roof Beam (RB1) 0.25 0.35 3.00 29.00 7.61 m3
Roof Beam (RB2) 0.25 0.35 4.00 5.00 1.75 m3
Slabs (2F) 10.50 12.50 0.12 1.00 15.75 m3
Porch (GF) 3.00 1.65 0.10 1.00 0.50 m3
Entrance Stairs 0.47 3.00 2.00 1.00 2.82 m3
Staircase (GF-2F) 1.76 1.20 4.00 1.00 8.45 m3
Ramp 6.83 1.65 0.10 1.50 1.69 m3

Total 128.03 m3

901(1) Lean Concrete


Quantity : 3.71 m3

L W H Q Vol/Area Unit

Plain/Lean Concrete (F1) 1.50 1.50 0.075 22.00 3.71 m3

Total 3.71 m3

902(1)a Reinforcing Steel, Grade 40


Quantity : 5,251.86 kgs

902(1)b Reinforcing Steel, Grade 60


Quantity : 9,437.91 kgs

Description Hardware Qty. of bar


Cut Number of Total No. Total Wt.
ITEM Dia. Length Qty. Unit Wt.
Factor Lenght Sets of Bars.
NUMBER (mm) RSB (pcs.) (kg/m) Ø10mm Ø12mm Ø16mm Ø20mm
(m) (m) (pcs) (kgs.)
(m)

Footing (F1) 16∅ 1.20 6.00 22.00 22.00 96.80 1.580 917.66 0.00 0.00 917.67 0.00

2F Beam (GB1)
Main Bar (Continuous) 16∅ 4.50 6.00 7.00 29.00 152.25 1.580 1,443.33 0.00 0.00 1443.33 0.00
Cut Top Bars 16∅ 5.74 6.00 2.00 29.00 55.49 1.580 526.01 0.00 0.00 526.02 0.00
Cut Bottom Bars 16∅ 2.14 6.00 2.00 29.00 20.71 1.580 196.37 0.00 0.00 196.38 0.00
Stirrups/Tie Bars 10∅ 1.00 6.00 28.00 29.00 135.33 0.616 500.19 500.20 0.00 0.00 0.00

2F Beam (GB2)
Main Bar (Continuous) 16∅ 3.60 5.75 7.00 5.00 21.91 1.580 199.08 0.00 0.00 199.08 0.00
Cut Top Bars 16∅ 6.24 6.00 2.00 5.00 10.40 1.580 98.59 0.00 0.00 98.60 0.00
Cut Bottom Bars 16∅ 2.86 6.00 2.00 5.00 4.76 1.580 45.14 0.00 0.00 45.15 0.00
Stirrups/Tie Bars 10∅ 1.00 6.00 33.00 5.00 27.50 0.616 101.64 101.64 0.00 0.00 0.00

Roof Beam (RB1)


Main Bar (Continuous) 16∅ 4.50 6.00 7.00 29.00 152.25 1.580 1,443.33 0.00 0.00 1443.33 0.00
Cut Top Bars 16∅ 5.74 6.00 3.00 29.00 83.23 1.580 789.02 0.00 0.00 789.03 0.00
Cut Bottom Bars 16∅ 2.14 6.00 3.00 29.00 31.07 1.580 294.56 0.00 0.00 294.56 0.00
Stirrups/Tie Bars 10∅ 1.00 6.00 28.00 29.00 135.33 0.616 500.19 500.20 0.00 0.00 0.00

Roof Beam (RB2)


Main Bar (Continuous) 16∅ 3.60 6.00 7.00 5.00 21.00 1.580 199.08 0.00 0.00 199.08 0.00
Cut Top Bars 16∅ 6.24 6.00 3.00 5.00 15.60 1.580 147.89 0.00 0.00 147.89 0.00
Cut Bottom Bars 16∅ 2.86 6.00 3.00 5.00 7.14 1.580 67.71 0.00 0.00 67.72 0.00
Stirrups/Tie Bars 10∅ 1.00 6.00 33.00 5.00 27.50 0.616 101.64 101.64 0.00 0.00 0.00

Wall Footing WF
Horizontal Bars 16∅ 3.00 5.75 5.00 1.00 2.61 1.580 23.70 0.00 0.00 23.70 0.00
Stirrups/Tie Bars 10∅ 1.50 6.00 12.00 1.00 3.00 0.616 11.09 11.09 0.00 0.00 0.00

Columns (C1)
Vertical Bars 20∅ 6.00 6.00 4.00 22.00 88.00 2.466 1,302.05 0.00 0.00 0.00 1302.05
Vertical Bars 16∅ 6.00 6.00 4.00 22.00 88.00 1.580 834.24 0.00 0.00 834.24 0.00
Stirrups/Tie Bars 1 12∅ 1.50 6.00 33.00 22.00 181.50 0.888 967.03 0.00 967.04 0.00 0.00
Stirrups/Tie Bars 2 10∅ 1.50 6.00 33.00 22.00 181.50 0.616 670.82 670.83 0.00 0.00 0.00

Staircase
Vertical Bars 16∅ 6.00 6.00 12.00 8.00 96.00 1.580 910.08 0.00 0.00 910.08 0.00
Stirrups/Tie Bars 12∅ 4.00 6.00 33.00 10.00 220.00 0.888 1,172.16 0.00 1172.16 0.00 0.00

Total 13,463 1,886 2,139 8,136 1,302


kgs kgs kgs kgs KGS

Description Hardware Qty. of bar


Cut Number of Total No. Total Wt.
ITEM Dia. Length Qty. Unit Wt.
Factor Lenght Sets of Bars.
NUMBER (mm) RSB (pcs.) (kg/m) Ø10mm Ø12mm Ø16mm Ø20mm
(m) (m) (pcs) (kgs.)
(m)
Slab on fill (Interior of Building) 1.0833 10∅ 1,312.50 1.00 1.00 1.00 1,312.50 0.616 808.50 808.50 0.00 0.00 0.00
Slab on fill (Exterior of Building) 1.0833 10∅ 49.50 1.00 1.00 1.00 53.62 0.616 33.03 33.04 0.00 0.00 0.00

Total 842 842 - - -


kgs kgs kgs kgs KGS

Qty. of bar
Total Total
Unit
Slab Reinforcing Steel Bar Size Area Spacing Factor Number of
Weight
Weight
Bars (Kg) Ø10mm Ø12mm Ø16mm Ø20mm

One-way 1 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
One-way 2 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
One-way 3 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
One-way 4 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
Two-way 1 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 2 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 3 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 4 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 5 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 6 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 7 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 8 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00

Total (kgs) 5,173 2,524.72 2,649 - -

Meter per
Number Tie Lenght Number of kilogram Total Wt.
Tie Wires Factor Factor
of ties (m) Sets (m) of Tie
(kgs.)
Wire

Footing (F1) 6.00 6.00 36.00 0.30 22.00 53.00 4.48


Slab on fill (Interior of Building) 1312.50 16.00 21000.00 0.30 1.00 53.00 118.87
Slab on fill (Exterior of Building) 49.50 16.00 792.00 0.30 1.00 53.00 4.48

2F Beam (GB1)
Stirrups/Tie Bars 7.00 28.00 196.00 0.30 3.00 53.00 3.33

2F Beam (GB2)
Stirrups/Tie Bars 7.00 33.00 231.00 0.30 6.00 53.00 7.85

Roof Beam (RB1)


Stirrups/Tie Bars 7.00 28.00 196.00 0.30 2.00 53.00 2.22

Roof Beam (RB2)


Stirrups/Tie Bars 7.00 33.00 231.00 0.30 1.00 53.00 1.31

Wall Footing WF
Stirrups/Tie Bars 7.00 12.00 84.00 0.30 1.00 53.00 0.48

Columns (C1)
Stirrups/Tie Bars 1 4.00 33.00 132.00 0.30 22.00 53.00 16.44
Stirrups/Tie Bars 2 4.00 33.00 132.00 0.30 22.00 53.00 16.44

Staircase
Stirrups/Tie Bars 4.00 49.00 196.00 0.30 10.00 53.00 11.09

One-way Slab (12.5 Spacing) 78.19 0.42 33.00


Two-way Slab (12.5 Spacing) 146.75 0.55 81.30

Total (kgs) 301.28

903(2) Forms and Falseworks


Quantity : 795.04 m2

L W H Q Vol/Area Unit
Footing (F1) 1.50 1.50 0.30 22.00 39.60 m2
2F Slab 10.50 12.50 0.10 1.00 4.60 m2
2F Terrace 3.00 1.65 0.10 1.00 0.93 m2
Footing Beam (FTB1) 0.25 0.30 228.00 1.00 250.80 m2
Wall Footing (WF1) 0.30 0.60 3.00 1.00 5.40 m2
Columns (C1) 0.40 0.40 4.80 22.00 168.96 m2
2F Beam (GB1) 0.30 0.40 3.00 29.00 121.80 m2
2F Beam (GB2) 0.30 0.40 4.00 5.00 28.00 m2
Roof Beam (RB1) 0.25 0.35 3.00 29.00 104.40 m3
Roof Beam (RB2) 0.25 0.35 4.00 5.00 24.00 m4
Slabs (2F) 10.50 12.50 0.12 1.00 5.52 m5
Porch (GF) 3.00 1.65 0.10 1.00 0.93 m6
Entrance Stairs 0.47 3.00 2.00 1.00 13.88 m7
Staircase (GF-2F) 1.76 1.20 4.00 1.00 23.68 m8
Ramp 6.83 1.65 0.10 1.50 2.54 m9

Total 795.04 m2

PART C FINISHING WORKS


C.1 Termite Control Works and Waterproofing
1000(1) Soil Poisoning
Quantity : 9.00 L

L W H Q Vol/Area Unit
Building Area 10.00 12 1 120.00 m2
Frontage 3.00 1.65 1 4.95 m2
Ext Staircase 1.50 6 1 9.00 m2
Area 133.95 m2
Soilguard per L coverage 15 m2
Total 9 L

1016(1)a Waterproofing
Quantity : 117.99 m2

L W H Q Vol/Area Unit
A1 11.00 0.9 2 19.80 m2
A2 13.00 0.9 2 23.40 m2
A3 7.00 0.9 2 12.60 m2
A4 1.65 0.9 2 2.97 m2
A5 4.00 0.9 2 7.20 m2
A6 14.65 0.9 2 26.37 m2
A7 51.30 0.5 1 25.65 m2

Total 117.99 m2

C.2. Masonry Works


1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
Quantity : 108.00 m2

L W H Q Vol/Area Unit
A1 30.00 3.00 1 90.00 m2
A2 6.00 3.00 1 18.00 m2

Area 108 m2
Less Window & Door Opening 9.87 m2
Total 98.13 m2

1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
Quantity : 135.82 m2

L W H Q Vol/Area Unit
A1 10.00 3.00 2 60.00 m2
A2 12.00 3.00 2 72.00 m2
A3 51.30 0.5 2 51.30 m2
A4 0.00 m2
A5 0.00 m2
A6 0.00 m2
A6 0.00 m3

Area 183.3 m2
Less Window & Door Opening 47.48 m2
Total 135.82 m2

C.3 Fabricated Materials


1004(2)a Locksets
Quantity : 11.00 set

1004(2)g Hinges
Quantity : 11.00 set

1007(1) Aluminum Framed Glass Doors


Quantity : 15.12 m2

L W H Q Vol/Area Unit
D1 1.80 2.1 4 15.12 m2 3.78

Total 15.12 m2

1008(1) Aluminum Framed Glass Windows


Quantity : 36.14 m2

L W H Q Vol/Area Unit
W1 2.80 1.10 3.00 9.24 m2
W2 1.40 1.10 17.00 26.18 m2
W3 0.60 0.30 4.00 0.72 m2
Total 36.14 m2

1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)


Quantity : 7.00 set

1010(2)b Wooden Doors (Wood Panel)


Quantity : 13.23 m2

L W H Q Vol/Area Unit
D2 2.10 0.90 3 5.67 m2
D3 2.10 1.00 2 4.20 m2
D4 2.10 0.80 2 3.36 m2
Total 13.23 m2

C.4 Finishing Works


1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
Quantity : 240.00 m2

L W H Q Vol/Area Unit
GF 10.00 12.00 120.00 m2
2F 10.00 12.00 120.00 m2

Total 240 m2

1018(1) Glazed Tiles and Trims


Quantity : 249.90 m2

L W H Q Vol/Area Unit
GF 10.00 12.00 120.00 m2
Porch 1.65 3.00 4.95 m2
2F 10.00 12.00 120.00 m2
Terrace 1.65 3.00 4.95 m2

Total 249.9 m2

1018(2) Unglazed Tiles


Quantity : 90.00 m2

L W H Q Vol/Area Unit
PWD Male CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
PWD Female CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
2F Male CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
2F Female CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2

Total 90 m2

1021(1)c Plain Cement Finish with floor hardener


Quantity : 23.40 m2

L W H Q Vol/Area Unit
Staircase 7.50 1.2 1 9.00 m2
Main Ent Ramp 8.00 1.5 1 12.00 m2
Service Ent/Ext 3.00 0.8 1 2.40 m2

Total 23.4 m2

1027(1) Plain Cement Plaster Finish


Quantity : 622.66 m2

Existing Parapet L W H Q Vol/Area Unit


Concrete Gutter 2.50 16.20 2 81.00 m2
Columns 0.40 0.40 22 3.52 m2

Total 84.52 m2
Existing Struc. 84.52 m2
1046(2)a2 108.00 m2
1046(2)a2 183.30 m2
less 1007(1) 15.12 m2
1008(1) 36.14 m2
1010(2)b 13.23 m2
Total 622.66 m2

1053(2)a1 38 mm Ø Stainless Steel Pipe Railings


Quantity : 108.80 m

L W H Q Length Unit
Top Handrail 34.00 1 34.00 m
Bottom Handrail 34.00 1 34.00 m
Vert Support 0.90 45.33 40.80 m

Total 108.8 m

1038(1) Reflective Insulation


Quantity : 120.00 m2

L W H Q Vol/Area Unit
Service Ent 10.00 12 120.00 m2

Total 120 m2

C.5 Painting Works


1032(1)a Masonry/Concrete Painting
Quantity : 747.63 m2

W1 W2 H Q Area Unit
C1 0.40 0.40 4.80 22.00 84.48 m2

Total 84.48 m2
900(1)c1 84.48 m2
1046(2)a1 216.00 m2
1046(2)a2 271.64 m2
1003(1)a1 240.00 m2
less 1007(1) 15.12 m2
1008(1) 36.14 m2
1010(2)b 13.23 m2
Total 747.63 m2

1032(1)b Wood Painting


Quantity : 26.46 m2

L W H Q Vol/Area Unit
D2 2.10 0.90 3 5.67 m2
D3 2.10 1.00 2 4.20 m2
D4 2.10 0.8 2 3.36 m2
Total 26.46 m2

C.6 Roof Framing and Roofing Works


1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
Quantity : 231.58 m2

L W H Q Vol/Area Unit
10.44 12 N/A 1 125.28 m2
10.63 10 N/A 1 106.30 m3
Total 231.58 m2

1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls)


Quantity : 32.32 m

1003(5) Roof Frame (Wood)


Quantity : 1701.22 bd.ft.

Tot
Length Bd.Ft. per Number of Length Tot Length
Thk (in) Width (in) Length Total Bd.Ft.
(ft) Pc. Truss Reqd. (m) Reqd. (ft)
Reqd. (m)
HT1
Top & Bottom Chord 2 6 12.00 12.00 2.00 20.44 40.88 134.03 134.03
Vertical and Diagonal Member 2 4 12.00 8.00 2.00 17.74 35.48 116.33 77.55
HT2
Top & Bottom Chord 2 6 12.00 12.00 4.00 13.34 53.36 174.95 174.95
Vertical and Diagonal Member 2 4 12.00 8.00 4.00 11.01 44.02 144.33 96.22
HT3
i Top & Bottom Chord 2 6 12.00 12.00 10.00 6.00 60.00 196.72 196.72
Vertical and Diagonal Member 2 4 12.00 8.00 10.00 4.83 48.30 158.36 105.57
HT4
Top & Bottom Chord 2 6 12.00 12.00 6.00 4.81 28.86 94.62 94.62
Vertical and Diagonal Member 2 4 12.00 8.00 6.00 4.07 24.42 80.07 53.38
HT5
Top & Bottom Chord 2 6 12.00 12.00 2.00 10.42 20.84 68.33 68.33
Vertical and Diagonal Member 2 4 12.00 8.00 2.00 10.79 21.58 70.75 47.17

PURLINS 2 4 12.00 8.00 2.00 35.09 70.18 230.10 153.40


2 4 12.00 8.00 2.00 49.35 98.70 323.61 215.74

Total (bd.ft) 1,701.22

1047(6) Metal Structure Accessories, Steel Plates


Quantity : 957.00 kgs
Total
Weight
Quantity Sets Weight
Per Piece
(Kg)

HT1 (Gusset Plate) 18.00 2.00 1.86 66.96


HT2 (Gusset Plate) 13.00 4.00 1.86 96.72
HT3 (Gusset Plate) 10.00 10.00 1.86 186.00
HT4 (Gusset Plate) 9.00 6.00 1.86 100.44
HT5 (Gusset Plate) 11.00 2.00 1.86 40.92
Base Plate 6.00 11.00 7.06 465.96

Total (kgs) 957.00

1047(7)b Metal Structure Accessories, Sag Rods


Quantity : 232.30 kgs

Total
Weight
Length Sets Weight
Per Piece
(Kg)

12mm diameter Sagrod 65.40 4.00 0.8880 232.30

Total (kgs) 232.30

1047(4) Metal Structure Accessories, Cross Bracing


Quantity : 636.25 kgs

Total
Weight
Length Sets Weight
Per Piece
(Kg)

16mm diameter Cross Bracing 100.80 4.00 1.5780 636.25

Total (kgs) 636.25

1047(3)a Metal Structure Accessories (Bolts)


Quantity : 340.00 ea

1047(3)c Metal Structure Accessories (Turnbuckle)


Quantity : 32.00 ea

PART D PLUMBING/SANITARY WORKS


1001(8) Sewer Line Works
Quantity : 1.00 l.s.

1002(6) Cold Water Line Works


Quantity : 1.00 l.s.

1001(9) Downspout/Storm Drain


Quantity : 1.00 l.s.

1002(5) Sanitary/Plumbing Fixtures


Quantity : 1.00 l.s.

1001(6)b1 Catch basin


Quantity : 3.00 units

1001(11) Septic Vault (Concrete/CHB)


Quantity : 3.75 sq.m.

PART E ELECTRICAL WORKS


1100(19) Conduits, Boxes, and Fittings
Quantity : 1.00 l.s.

1101(18) Wires and Wiring Devices


Quantity : 1.00 l.s.

1102(21) Panel Board


Quantity : 1.00 l.s.

1103(1) Lighting Fixtures


Quantity : 1.00 l.s.

1208(1) Fire Alarm System (Emergency Lights)


Quantity : 1.00 l.s.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.1 Temporary Facility


Unit of Measurement : each
Output : 1

Designation No. of Person/s No. of Month/s Hourly Rate Amount (PhP)

A. Labor
a. Const. Foreman 1 8.00 100.36 802.88
b. Skilled Labor 1 8.00 73.01 584.08
c. Unskilled Labor 3 8.00 56.27 1,350.48

Sub - Total for A 2,737.44

Name and Capacity No of Unit/s No. of Month/s Monthly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 273.74

Sub - Total for B


C. Total (A + B) 2,737.44
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 2,737.44

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. 14ft corr roof sheet pcs 14 400.00 5,600.00
b. 2x4x12 coco lumber pcs 10.00 240.00 2,400.00
c. 2x3x12 coco lumber pcs 20.00 180.00 3,600.00
d. 2x2x12 coco lumber pcs 30.00 120.00 3,600.00
e. 1/4" thk. Ord. plywood pcs 21 479.00 10,059.00
f. assrtd nails kgs 9 101.50 913.50
g. umbrella nails kgs 2 75.00 150.00

Sub - Total for F 26,322.50


G. Direct Unit Cost (E + F) 29,059.94
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 2,324.80
J. Value Added Tax (VAT) 5% of (G + H + I) 1,569.24
K. Total Unit Cost (G + H + I + J) 32,953.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.5 Project Billboard/ Sign Board


Unit of Measurement : ea
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 8.00 100.36 802.88


b. Skilled Laborer 1 8.00 73.01 584.08
c. Unskilled Laborer 1 8.00 56.27 450.16

Sub - Total for A 1,837.12

Name and Capacity No of Unit/s No. of Day/s Daily Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 183.71

Sub - Total for B -


C. Total (A + B) 1,837.12
D. Output = 1 ea
E. Direct Unit Cost (C ÷ D) 1,837.12

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 8' x 8' Tarpaulin ft2 64.00 20.00 1,280.00


b. Good Lumber (Frames) bd-ft 48.00 38.44 1,845.12
c. Assorted Common Working Nails kg 1.00 57.22 57.22

Sub - Total for F 3,182.34


G. Direct Unit Cost (E + F) 5,019.46
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 602.34
I. Contractor's Profit (CP) 8% of G 401.56
J. Value Added Tax (VAT) 5% of (G + H + I) 301.17
K. Total Unit Cost (G + H + I + J) 6,324.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.7(2) Occupational Safety and Health


Unit of Measurement : lot
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 30.00 680.00 20,400.00


b. First Aider 1 30.00 544.00 16,320.00

Sub - Total for A 36,720.00

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 36,720.00
D. Output = 1 lot
E. Direct Unit Cost (C ÷ D) 36,720.00

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 1,000.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 150.00 0.25 37.50
b. Safety Shoes man-days 150.00 2.77 415.50
c. Safety Vest man-days 150.00 2.22 333.00
d. Working Gloves man-days 150.00 7.67 1,150.50
e. Rubber Boots man-days 150.00 1.39 208.50
f. Rain Coats man-days 150.00 0.34 51.00
-
-
-
-

Signages and Barricades


a. PPE Signage (4' x 8') set 5.00 506.37 2,531.85
b. Safety First (4' x 4') set 5.00 270.87 1,354.35
c. Warning Signs (2' x 3') sets 35.00 123.68 4,328.80
d. Caution Tape, 100ft roll 5.00 800.00 4,000.00

Sub - Total for F 15,411.00


G. Direct Unit Cost (E + F) 52,131.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 4,170.48
J. Value Added Tax (VAT) 5% of (G + H + I) 2,815.07
K. Total Unit Cost (G + H + I + J) 59,116.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.9 Mobilization/Demobilization


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

38,490.16
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B 38,490.16


C. Total (A + B) 38,490.16
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 38,490.16

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 38,490.16


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 3,079.21
J. Value Added Tax (VAT) 5% of (G + H + I) 2,078.47
K. Total Unit Cost (G + H + I + J) 43,647.85
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(1) Clearing and Grubbing


Unit of Measurement : m2
Output per hour : 70.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 269.17

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. dump truck (12 cu.yd.) 1 1.00 1,420.00 1,420.00


b. pay loader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 26.92

Sub - Total for B 3,179.92


C. Total (A + B) 3,449.09
D. Output per Hour = 70.00 m3
E. Direct Unit Cost (C ÷ D) 49.27

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F) 49.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5.91
I. Contractor's Profit (CP) 8% of G 3.94
J. Value Added Tax (VAT) 5% of (G + H + I) 2.96
K. Total Unit Cost (G + H + I + J) 62.08
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(6) Removal of Structures and Obstruction


Unit of Measurement : m2
Output per hour : 15.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 5 1.00 73.01 365.05
c. Unskilled Laborer 10 1.00 56.27 562.70

Sub - Total for A 1,028.11

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. dump truck (12 cu.yd.) 1 1.00 1,420.00 1,420.00


Minor Tools (10% of Labor Cost) 102.81

Sub - Total for B 1,522.81


C. Total (A + B) 2,550.92
D. Output per Hour = 15.00 m3
E. Direct Unit Cost (C ÷ D) 170.06

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F) 170.06
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 20.41
I. Contractor's Profit (CP) 8% of G 13.60
J. Value Added Tax (VAT) 5% of (G + H + I) 10.20
K. Total Unit Cost (G + H + I + J) 214.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)a Structure Excavation (Common Soil)


Unit of Measurement : m3
Output per hour : 10.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 269.17

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Backhoe (0.80 m3) 1 1.00 1,537.00 1,537.00


b. Dump Truck (12 yd3) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 26.92

Sub - Total for B 4,403.92


C. Total (A + B) 4,673.09
D. Output per Hour = 10.00 m3
E. Direct Unit Cost (C ÷ D) 467.31

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F) 467.31
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 56.08
I. Contractor's Profit (CP) 8% of G 37.38
J. Value Added Tax (VAT) 5% of (G + H + I) 28.04
K. Total Unit Cost (G + H + I + J) 588.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(3) Structure Excavation (Foundation Fill)


Unit of Measurement : m3
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 269.17

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 1 1.00 123.00 123.00


b. Backhoe (0.80 m3) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 26.92

Sub - Total for B 1,686.92


C. Total (A + B) 1,956.09
D. Output per Hour = 9.84 m3
E. Direct Unit Cost (C ÷ D) 198.79

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 198.79


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 23.85
I. Contractor's Profit (CP) 8% of G 15.90
J. Value Added Tax (VAT) 5% of (G + H + I) 11.93
K. Total Unit Cost (G + H + I + J) 250.47
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)b Embankment from Common Borrow by Equipment


Unit of Measurement : m3
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 269.17

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m3) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 26.92

Sub - Total for B 1,271.92


C. Total (A + B) 1,541.09
D. Output per Hour = 9.84 m3
E. Direct Unit Cost (C ÷ D) 156.61

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Embankment Materials m3 1.25 360.00 450.00


(w/ 25% Shrinkage Factor)

Sub - Total for F 450.00


G. Direct Unit Cost (E + F) 606.61
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 72.79
I. Contractor's Profit (CP) 8% of G 48.53
J. Value Added Tax (VAT) 5% of (G + H + I) 36.40
K. Total Unit Cost (G + H + I + J) 764.33
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(4) Gravel Bedding


Unit of Measurement : m3
Output per hour : 1.20

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 269.17

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor 1 0.50 123.00 61.50


Minor Tools (10% of Labor Cost) 26.92

Sub - Total for B 88.42


C. Total (A + B) 357.59
D. Output per Hour = 1.20 m3
E. Direct Unit Cost (C ÷ D) 297.99

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel Bedding (G1) m3 1.05 800.00 840.00


(w/ 5% Shrinkage Factor)

Sub - Total for F 840.00


G. Direct Unit Cost (E + F) 1,137.99
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 136.56
I. Contractor's Profit (CP) 8% of G 91.04
J. Value Added Tax (VAT) 5% of (G + H + I) 68.28
K. Total Unit Cost (G + H + I + J) 1,433.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)


Unit of Measurement : m3
Output per hour : 3.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
b. Unskilled Laborer 6 1.00 56.27 337.62

Sub - Total for A 584.00

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. One Bagger Mixer 1 1.00 172.00 172.00
Minor Tools (10% of Labor Cost) 58.40

Sub - Total for B 412.90


C. Total (A + B) 996.90
D. Output per Hour = 3.72 m3
E. Direct Unit Cost (C ÷ D) 267.98

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel m3 1.00 1,200.00 1,200.00


b. Sand m 3
0.50 1,700.00 850.00
c. Portland Cement bags 10.00 320.00 3,200.00

Sub - Total for F 5,250.00


G. Direct Unit Cost (E + F) 5,517.98
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 662.16
I. Contractor's Profit (CP) 8% of G 441.44
J. Value Added Tax (VAT) 5% of (G + H + I) 331.08
K. Total Unit Cost (G + H + I + J) 6,952.66
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 901(1) Lean Concrete


Unit of Measurement : m3
Output per hour : 0.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 8.00 100.36 802.88


b. Skilled Laborer 2 8.00 73.01 1,168.16
b. Unskilled Laborer 10 8.00 56.27 4,501.60

Sub - Total for A 6,472.64

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 8.00 172.00 1,376.00


Minor Tools (10% of Labor Cost) 647.26

Sub - Total for B 2,023.26


C. Total (A + B) 8,495.90
D. Output per Hour = 3.72 m3
E. Direct Unit Cost (C ÷ D) 11,799.87

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement (40 kgs) bags 9.00 320.00 2,880.00


b. Coarse Sand m 3
1.00 750.00 750.00
c. Gravel m3 0.50 800.00 400.00

Sub - Total for F 4,030.00


G. Direct Unit Cost (E + F) 15,829.87
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 1,899.58
I. Contractor's Profit (CP) 8% of G 1,266.39
J. Value Added Tax (VAT) 5% of (G + H + I) 949.79
K. Total Unit Cost (G + H + I + J) 19,945.63
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)a1 Reinforcing Steel of Reinforced Concrete Structures for Two-Storey, Grade 40
Unit of Measurement : kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 3 1.00 73.01 219.03
c. Unskilled Laborer 12 1.00 56.27 675.24

Sub - Total for A 994.63

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 99.46

Sub - Total for B 385.09


C. Total (A + B) 1,379.72
D. Output per Hour = 129.094 kg
E. Direct Unit Cost (C ÷ D) 10.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Deformed Reinforcing Steel kg 1.00 61.00 61.00


Grade
b. #16 60/GradeIron
Galvanized 40 Wire kg 0.015 81.00 1.22
c. Consumables (5% of Materials Cost) 3.11

Sub - Total for F 65.33


G. Direct Unit Cost (E + F) 76.01
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9.12
I. Contractor's Profit (CP) 8% of G 6.08
J. Value Added Tax (VAT) 5% of (G + H + I) 4.56
K. Total Unit Cost (G + H + I + J) 95.78
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)b1 Reinforcing Steel of Reinforced Concrete Structures for Two-Storey, Grade 60
Unit of Measurement : kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 3 1.00 73.01 219.03
c. Unskilled Laborer 12 1.00 56.27 675.24

Sub - Total for A 994.63

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 99.46

Sub - Total for B 385.09


C. Total (A + B) 1,379.72
D. Output per Hour = 129.094 kg
E. Direct Unit Cost (C ÷ D) 10.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Deformed Reinforcing Steel kg 1.00 63.00 63.00


Grade
b. #16 60/GradeIron
Galvanized 40 Wire kg 0.015 81.00 1.22
c. Consumables (5% of Materials Cost) 3.21

Sub - Total for F 67.43


G. Direct Unit Cost (E + F) 78.11
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9.37
I. Contractor's Profit (CP) 8% of G 6.25
J. Value Added Tax (VAT) 5% of (G + H + I) 4.69
K. Total Unit Cost (G + H + I + J) 98.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 903(2) Formworks and Falseworks


Unit of Measurement : m2
Output per hour : 4.5

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
Installation
a. Construction Foreman 1 1.00 100.36 100.36
b. Skilled Laborer 4 1.00 73.01 292.04
c. Unskilled Laborer 6 1.00 56.27 337.62
Stripping
a. Construction Foreman 1 0.56 100.36 56.20
b. Unskilled Laborer 6 0.56 56.27 189.07
Sub - Total for A 975.29

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Area = 205.01 m2
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8 m full extension 62 14.00 4.50 3,906.00
c. Adjustable U-head Jack, 0.6m 80 14.00 0.85 952.00
d. Adjustable Base Jack, 0.6m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Round Wing Nut 558 14.00 0.15 1,171.80
Minor Tools (10% of Labor Cost) 97.53

Sub - Total for B 19,024.60


C. Sub-Total for C (B/Area) 92.80
D. Output per Hour = 4.5 m²
E. Direct Unit Cost (A ÷ D) + C 309.53

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Phenolic Board (0.019 x 1.2 x 2.4) - 4 uses pc 0.347 1,450.00 125.79


c. Good Lumber - 3 uses bd ft 4.727 38.44 60.57

Sub - Total for F 186.36


G. Direct Unit Cost (E + F) 495.89
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 59.51
I. Contractor's Profit (CP) 8% of G 39.67
J. Value Added Tax (VAT) 5% of (G + H + I) 29.75
K. Total Unit Cost (G + H + I + J) 624.82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1000(1) Soil Poisoning


Unit of Measurement : L
Output per hour : 5.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 2 1.00 56.27 112.54

Sub - Total for A 285.91

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 28.59

Sub - Total for B 28.59


C. Total (A + B) 314.50
D. Output per Hour = 5.40 L
E. Direct Unit Cost (C ÷ D) 58.24

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Soil Poisoning L 1.00 420.00 420.00

Sub - Total for F 420.00


G. Direct Unit Cost (E + F) 478.24
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 57.39
I. Contractor's Profit (CP) 8% of G 38.26
J. Value Added Tax (VAT) 5% of (G + H + I) 28.69
K. Total Unit Cost (G + H + I + J) 602.58
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1016(1)a Waterproofing


Unit of Measurement : m2
Output per hour : 1.60

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 229.64

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 22.96

Sub - Total for B 22.96


C. Total (A + B) 252.60
D. Output per Hour = 2.10 m2
E. Direct Unit Cost (C ÷ D) 157.88

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cementitious Waterproofing gal 0.24 1,250.00 300.00


e. Consumables (5% of Materials Cost) 15.00

Sub - Total for F 315.00


G. Direct Unit Cost (E + F) 472.88
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 56.75
I. Contractor's Profit (CP) 8% of G 37.83
J. Value Added Tax (VAT) 5% of (G + H + I) 28.37
K. Total Unit Cost (G + H + I + J) 595.83
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.825

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 415.19

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.52

Sub - Total for B 213.52


C. Total (A + B) 628.71
D. Output per Hour = 3.825 m2
E. Direct Unit Cost (C ÷ D) 164.37

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 100 mm thk CHB (Non-Load Bearing) pc 13.00 8.11 105.43


b. Cement bag 0.525 217.50 114.19
c. Sand cu.m 0.04 369.43 16.25
d. Reinforcing Steel kg 3.24 34.22 110.87
e. #16 Tie wire kg 0.05 63.50 3.18

Sub - Total for F 349.92


G. Direct Unit Cost (E + F) 514.29
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 61.71
I. Contractor's Profit (CP) 8% of G 41.14
J. Value Added Tax (VAT) 5% of (G + H + I) 30.86
K. Total Unit Cost (G + H + I + J) 648.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.18

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 415.19

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.52

Sub - Total for B 213.52


C. Total (A + B) 628.71
D. Output per Hour = 3.180 m2
E. Direct Unit Cost (C ÷ D) 197.71

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm thk CHB (Non-Load Bearing) pc 13.00 9.80 127.40


b. Cement bag 1.500 217.50 326.25
c. Sand cu.m 0.04 369.43 16.25
d. Reinforcing Steel kg 3.24 34.22 110.87
e. #16 Tie wire kg 0.05 63.50 3.18

Sub - Total for F 583.95


G. Direct Unit Cost (E + F) 781.66
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 93.80
I. Contractor's Profit (CP) 8% of G 62.53
J. Value Added Tax (VAT) 5% of (G + H + I) 46.90
K. Total Unit Cost (G + H + I + J) 984.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2)a Lockset


Unit of Measurement : set
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Lockset set 1.00 1,500.00 1,500.00

Sub - Total for F 1,500.00


G. Direct Unit Cost (E + F) 1,500.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 180.00
I. Contractor's Profit (CP) 8% of G 120.00
J. Value Added Tax (VAT) 5% of (G + H + I) 90.00
K. Total Unit Cost (G + H + I + J) 1,890.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2)g Hinges


Unit of Measurement : set
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Hinges set 1.00 66.27 66.27

Sub - Total for F 66.27


G. Direct Unit Cost (E + F) 66.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 7.95
I. Contractor's Profit (CP) 8% of G 5.30
J. Value Added Tax (VAT) 5% of (G + H + I) 3.98
K. Total Unit Cost (G + H + I + J) 83.50
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1007(1) Aluminum Framed Glass Doors


Unit of Measurement : m2
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for this item is considered/included in the installation of the fabricated material)

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m2
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

D1 - Fixed Bronze Glass on top and side (0.40m),


Double Swing Glass Doors w/ Aluminum Frame m2 0.33 4,365.00 1,440.45
(2.10mx1.80m)
D2 - Double Swing Glass Doors w/ Aluminum
m2 0.33 4,365.00 1,440.45
Frame (2.10mx1.80m)
D3 - Single Swing Glass Doors w/ Aluminum
m2 0.33 4,365.00 1,440.45
Frame (2.10mx0.90m)

Sub - Total for F 4,321.35


G. Direct Unit Cost (E + F) 4,321.35
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 518.56
I. Contractor's Profit (CP) 8% of G 345.71
J. Value Added Tax (VAT) 5% of (G + H + I) 259.28
K. Total Unit Cost (G + H + I + J) 5,444.90
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1007(1) Aluminum Framed Glass Doors


Unit of Measurement : m2
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for this item is considered/included in the installation of the fabricated material)

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m2
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

W1 - Fixed Corner Glass Window w/ Aluminum


m2 0.17 4,365.00 727.50
Frame (3.00mx1.20m)
W2 - Half Fized Half Awning Type Glass Window w/
m2 0.17 4,365.00 727.50
Aluminum Frame (0.70mx1.80m)
W3 - Double Sliding Glass Window w/ Aluminum
m2 0.17 4,365.00 727.50
Frame (1.60mx1.20m)

W4 - Fixed Glass on top and side (0.50m & 0.30m),


Double Sliding Window w/ Aluminum Frame m2 0.17 4,365.00
(2.40mx1.20m)
W4 - Fixed Glass Counter Window w/ Aluminum
m2 0.17 4,365.00 727.50
Frame (2.00mx1.20m)
W5 - Awning Type Glass Window w/ Aluminum
m2 0.17 4,365.00 727.50
Frame (0.50mx0.50m)

Sub - Total for F 2,182.50


G. Direct Unit Cost (E + F) 2,182.50
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 261.90
I. Contractor's Profit (CP) 8% of G 174.60
J. Value Added Tax (VAT) 5% of (G + H + I) 130.95
K. Total Unit Cost (G + H + I + J) 2,749.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement : set
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 100.36 200.72


b. Skilled Laborer 1 2.00 73.01 146.02
c. Unskilled Laborer 1 2.00 56.27 112.54

Sub - Total for A 459.28

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 45.93

Sub - Total for B 45.93


C. Total (A + B) 505.21
D. Output = 1 set
E. Direct Unit Cost (C ÷ D) 505.21

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Door Jambs set 1.00 2,000.00 2,000.00


b. Consumables (5% of Materials Cost) 100.00

Sub - Total for F 2,100.00


G. Direct Unit Cost (E + F) 2,605.21
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 312.62
I. Contractor's Profit (CP) 8% of G 208.42
J. Value Added Tax (VAT) 5% of (G + H + I) 156.31
K. Total Unit Cost (G + H + I + J) 3,282.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)b Wooden Panel Door


Unit of Measurement : m2
Output : 0.36

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 229.64

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 22.96

Sub - Total for B 22.96


C. Total (A + B) 252.60
D. Output per Hour = 0.36 m2
E. Direct Unit Cost (C ÷ D) 701.68

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. D4. Wooden Panel Door (0.90m x 2.10m)


m2 1.00 4,478.57 4,478.57
D5. Wooden Panel Door (1.00m x 2.10m)

Sub - Total for F 4,478.57


G. Direct Unit Cost (E + F) 5,180.25
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 621.63
I. Contractor's Profit (CP) 8% of G 414.42
J. Value Added Tax (VAT) 5% of (G + H + I) 310.81
K. Total Unit Cost (G + H + I + J) 6,527.11
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
Unit of Measurement : m2
Output per hour : 1.243

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 2 1.00 56.27 112.54

Sub - Total for A 285.91

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 28.59

Sub - Total for B 28.59


C. Total (A + B) 314.50
D. Output per Hour = 1.243 m2
E. Direct Unit Cost (C ÷ D) 253.02

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 4.5mm Fiber Cement Board pc 0.365 550.00 200.75


b. Metal Furring pc 1.131 130.00 147.03
and specifications
c. Carrying ) 3m length
Channels pc 0.357 150.00 53.55
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 20.00 120.00
f. Wall Angle pc 0.238 100.00 23.80
g. Rivets pc 14 1.50 21.00
h. 1" Metal Screw pc 4 3.00 12.00

Sub - Total for F 658.13


G. Direct Unit Cost (E + F) 911.15
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 109.34
I. Contractor's Profit (CP) 8% of G 72.89
J. Value Added Tax (VAT) 5% of (G + H + I) 54.67
K. Total Unit Cost (G + H + I + J) 1,148.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(1) Glazed Tiles and Trims


Unit of Measurement : m2
Output per hour : 1.365

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 5 1.00 73.01 365.05
c. Unskilled Laborer 5 1.00 56.27 281.35

Sub - Total for A 746.76

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 74.68

Sub - Total for B 74.68


C. Total (A + B) 821.44
D. Output per Hour = 1.365 m2
E. Direct Unit Cost (C ÷ D) 601.78

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Glazed Tiles (0.60m x 0.60m) m2 1.050 740.00 777.00


b. Cement bags 0.325 217.50 70.69
c. Sand m3 0.026 369.43 9.70
d. Tile Grout bags 0.125 250.00 31.25
e. Tile Adhesive (25 kg) bags 0.143 250.00 35.75
f. Consumables (3% of Materials Cost) 27.73

Sub - Total for F 952.12


G. Direct Unit Cost (E + F) 1,553.90
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 186.47
I. Contractor's Profit (CP) 8% of G 124.31
J. Value Added Tax (VAT) 5% of (G + H + I) 93.23
K. Total Unit Cost (G + H + I + J) 1,957.92
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(2) Unglazed Tiles


Unit of Measurement : m2
Output per hour : 1.95

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 5 1.00 73.01 365.05
c. Unskilled Laborer 5 1.00 56.27 281.35

Sub - Total for A 746.76

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 74.68

Sub - Total for B 74.68


C. Total (A + B) 821.44
D. Output per Hour = 1.95 m2
E. Direct Unit Cost (C ÷ D) 421.25

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Unglazed Tiles (0.30m x 0.30m) m2 1.050 842.86 885.00


b. Cement bags 0.325 217.50 70.69
c. Sand m3 0.026 369.43 9.70
d. Tile Grout bags 0.125 250.00 31.25
e. Tile Adhesive (25 kg) bags 0.125 250.00 31.25
f. Consumable (3% of Materials Cost) 30.84

Sub - Total for F 1,058.72


G. Direct Unit Cost (E + F) 1,479.97
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 177.60
I. Contractor's Profit (CP) 8% of G 118.40
J. Value Added Tax (VAT) 5% of (G + H + I) 88.80
K. Total Unit Cost (G + H + I + J) 1,864.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1021(1)c Plain Cement Floor Finish with Floor Hardener
Unit of Measurement : m2
Output per hour : 5.95

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 342.18

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 34.22

Sub - Total for B 34.22


C. Total (A + B) 376.40
D. Output per Hour = 5.95 m2
E. Direct Unit Cost (C ÷ D) 63.26

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 0.726 320.00 232.32


b. Sand m3 0.055 1,700.00 93.50
c. Floor Hardener bag 0.050 250.00 12.50

Sub - Total for F 338.32


G. Direct Unit Cost (E + F) 401.58
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 48.19
I. Contractor's Profit (CP) 8% of G 32.13
J. Value Added Tax (VAT) 5% of (G + H + I) 24.09
K. Total Unit Cost (G + H + I + J) 505.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1027(1) Cement Plaster Finish


Unit of Measurement : m2
Output per hour : 7.125

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 4 1.00 56.27 225.08

Sub - Total for A 471.46

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 47.15

Sub - Total for B 47.15


C. Total (A + B) 518.61
D. Output per Hour = 7.125 m2
E. Direct Unit Cost (C ÷ D) 72.79

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 0.330 217.50 71.78


b. Sand cu.m 0.027 369.43 9.79

Sub - Total for F 81.56


G. Direct Unit Cost (E + F) 154.35
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 18.52
I. Contractor's Profit (CP) 8% of G 12.35
J. Value Added Tax (VAT) 5% of (G + H + I) 9.26
K. Total Unit Cost (G + H + I + J) 194.48
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1053(2)a1 38 mm Ø G.I. Pipe Railings


Unit of Measurement : m
Output per hour : 6.255

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 2 1.00 56.27 112.54

Sub - Total for A 285.91

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 391.00 293.25


b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of labor cost) 28.59

Sub - Total for B 333.20


C. Total (A + B) 619.11
D. Output per Hour = 6.255 m
E. Direct Unit Cost (C ÷ D) 98.98

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 38 mm Ø G.I. Pipe pc 0.330 868.00 286.44


c. Welding Rod pcs 0.015 86.36 1.30
d. Consumables (5% of material cost) 14.39

Sub - Total for F 302.12


G. Direct Unit Cost (E + F) 401.10
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 48.13
I. Contractor's Profit (CP) 8% of G 32.09
J. Value Added Tax (VAT) 5% of (G + H + I) 24.07
K. Total Unit Cost (G + H + I + J) 505.39
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1038(1) Reflective Insulation


Unit of Measurement : m2
Output per hour : 5.56

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 2 1.00 56.27 112.54

Sub - Total for A 285.91

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 28.59

Sub - Total for B 28.59


C. Total (A + B) 314.50
D. Output per Hour = 5.56 m2
E. Direct Unit Cost (C ÷ D) 56.56

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflective Insulation, 10 mm thk m2 1.000 135.00 135.00


b. Consumbles (5% of Materials Cost) 6.75

Sub - Total for F 141.75


G. Direct Unit Cost (E + F) 198.31
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 23.80
I. Contractor's Profit (CP) 8% of G 15.87
J. Value Added Tax (VAT) 5% of (G + H + I) 11.90
K. Total Unit Cost (G + H + I + J) 249.88
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)a Painting Works (Masonry Painting)


Unit of Measurement : m2
Output per hour : 2.10

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 302.65

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 30.27

Sub - Total for B 30.27


C. Total (A + B) 332.92
D. Output per Hour = 2.10 m2
E. Direct Unit Cost (C ÷ D) 158.53

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete Neutralizer gal 0.08 412.32 32.99


b. Concrete Sealer/Primer gal 0.04 644.00 25.76
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats) gal 0.08 547.00 43.76
e. Consumables (5% of Materials Cost) 6.50

Sub - Total for F 136.51


G. Direct Unit Cost (E + F) 295.04
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 35.40
I. Contractor's Profit (CP) 8% of G 23.60
J. Value Added Tax (VAT) 5% of (G + H + I) 17.70
K. Total Unit Cost (G + H + I + J) 371.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)b Painting Works (Wood Painting)


Unit of Measurement : m2
Output per hour : 1.89

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 302.65

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 30.27

Sub - Total for B 30.27


C. Total (A + B) 332.92
D. Output per Hour = 1.89 m2
E. Direct Unit Cost (C ÷ D) 176.15

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Glazzing Putty gal 0.05 550.00 27.50


b. Flat Wall Enamel gal 0.04 558.75 22.35
c. Enamel Quick Dry gal 0.04 558.75 22.35
d. Paint Thinner gal 0.01 234.13 2.34
f. Consumables (5% of Materials Cost) 3.73

Sub - Total for F 78.27


G. Direct Unit Cost (E + F) 254.41
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 30.53
I. Contractor's Profit (CP) 8% of G 20.35
J. Value Added Tax (VAT) 5% of (G + H + I) 15.26
K. Total Unit Cost (G + H + I + J) 320.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1014(1)b1 Prepainted Metal Sheets ( Corrugated, Long Span,0.5mm thk)
Unit of Measurement : m2
Output per hour : 2.076

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 2 1.00 56.27 112.54

Sub - Total for A 285.91

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 28.59

Sub - Total for B 28.59


C. Total (A + B) 314.50
D. Output per Hour = 2.076 m2
E. Direct Unit Cost (C ÷ D) 151.49

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Prepainted Metal Sheets ( Corrugated, Long


m2 1.05 338.64 355.57
Span,0.5mm thk)
b. J-bolt with washers pc 10 4.50 45.00

Sub - Total for F 400.57


G. Direct Unit Cost (E + F) 552.07
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 66.25
I. Contractor's Profit (CP) 8% of G 44.17
J. Value Added Tax (VAT) 5% of (G + H + I) 33.12
K. Total Unit Cost (G + H + I + J) 695.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)q1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls)


Unit of Measurement : m
Output per hour : 10

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 229.64

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 22.96

Sub - Total for B 22.96


C. Total (A + B) 252.60
D. Output per Hour = 10.6 m
E. Direct Unit Cost (C ÷ D) 25.26

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ridge Roll m 1.05 168.00 176.40


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (5% of Materials Cost) 10.25

Sub - Total for F 215.15


G. Direct Unit Cost (E + F) 240.41
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 36.06
I. Contractor's Profit (CP) 10% of G 24.04
J. Value Added Tax (VAT) 5% of (G + H + I) 15.03
K. Total Unit Cost (G + H + I + J) 315.53

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(5) Roof Frame (Wood)


Unit of Measurement : bd.ft.
Output per hour : 25.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Fabrication
a. Construction Foreman 1 1.00 100.36 100.36
b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 2 1.00 56.27 112.54

Erection
a. Skilled Laborer 3 0.49 73.01 107.32
b. Unskilled Laborer 3 0.49 56.27 82.72

Sub - Total for A 548.96

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 371.00 278.25


b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
Minor Tools (10 % of Labor Cost) 54.90

Sub - Total for B 1,143.70


C. Total (A + B) 1,692.66
D. Output per Hour = 85.00 kg
E. Direct Unit Cost (C ÷ D) 66.64

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Truss kg 1.00 49.45 49.45


b. Acetylene kg 0.011 60.00 0.66
c. Oxygen kg 0.022 53.70 1.18
d. Welding Rod kg 0.020 86.36 1.73
e. Consumables (5% of Materials Cost) 2.65

Sub - Total for F 55.67


G. Direct Unit Cost (E + F) 122.31
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 14.68
I. Contractor's Profit (CP) 8% of G 9.78
J. Value Added Tax (VAT) 5% of (G + H + I) 7.34
K. Total Unit Cost (G + H + I + J) 154.11
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(6) Metal Structure Accessories (Steel Plates)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 229.64

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 22.96

Sub - Total for B 22.96


C. Total (A + B) 252.60
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) 19.44

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Plates kg 1.05 52.00 54.60

Sub - Total for F 54.60


G. Direct Unit Cost (E + F) 74.04
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8.88
I. Contractor's Profit (CP) 8% of G 5.92
J. Value Added Tax (VAT) 5% of (G + H + I) 4.44
K. Total Unit Cost (G + H + I + J) 93.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(7)b Metal Structure Accessories (Sagrods)


Unit of Measurement : kg
Output : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 229.64

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) 229.64
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) 17.67

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Sagrod with nuts and bolts kg 1.05 32.00 33.60

Sub - Total for F 33.60


G. Direct Unit Cost (E + F) 51.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6.15
I. Contractor's Profit (CP) 8% of G 4.10
J. Value Added Tax (VAT) 5% of (G + H + I) 3.08
K. Total Unit Cost (G + H + I + J) 64.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 1 1.00 73.01 73.01
c. Unskilled Laborer 1 1.00 56.27 56.27

Sub - Total for A 229.64

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) 229.64
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) 17.67

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cross Bracing kg 1.05 37.88 39.77

Sub - Total for F 39.77


G. Direct Unit Cost (E + F) 57.45
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6.89
I. Contractor's Profit (CP) 8% of G 4.60
J. Value Added Tax (VAT) 5% of (G + H + I) 3.45
K. Total Unit Cost (G + H + I + J) 72.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)a Metal Structure Accessories (Bolts)


Unit of Measurement : each
Output per hour : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.10 100.36 10.04


b. Skilled Laborer 1 0.10 73.01 7.30
c. Unskilled Laborer 1 0.10 56.27 5.63

Sub - Total for A 22.96

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) 22.96
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) 22.96

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Anchor Bolt pc 1.00 12.50 12.50

Sub - Total for F 12.50


G. Direct Unit Cost (E + F) 35.46
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4.26
I. Contractor's Profit (CP) 8% of G 2.84
J. Value Added Tax (VAT) 5% of (G + H + I) 2.13
K. Total Unit Cost (G + H + I + J) 44.68
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)


Unit of Measurement : pc
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.15 100.36 15.05


b. Skilled Laborer 1 0.15 73.01 10.95
c. Unskilled Laborer 1 0.15 56.27 8.44

Sub - Total for A 34.45

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) 34.45
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D) 34.45

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Standard Turnbuckle pc 1.00 136.00 136.00

Sub - Total for F 136.00


G. Direct Unit Cost (E + F) 170.45
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 20.45
I. Contractor's Profit (CP) 8% of G 13.64
J. Value Added Tax (VAT) 5% of (G + H + I) 10.23
K. Total Unit Cost (G + H + I + J) 214.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 13.25 100.36 1,329.77


b. Skilled Laborer 1 13.25 73.01 967.38
c. Unskilled Laborer 2 13.25 56.27 1,491.16

Sub - Total for A 3,788.31

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 149.12

Sub - Total for B 149.12


C. Total (A + B) 3,937.42
D. Output = 1
E. Direct Unit Cost (C ÷ D) 3,937.42

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. uPVC pipe, 50mm dia.x3m, S-1000 lengths 25.00 390.00 9,750.00


b. Elbow, 50mm dia-45 degr bend pcs 25.00 81.00 2,025.00
c. Wye, 50mm dia. pcs 12.00 126.00 1,512.00
d. uPVC Tee 50mm dia.x 50mm dia. pcs 8.00 135.00 1,080.00
e. Clean out with cover, 50mm dia. pcs 5.00 59.00 295.00
f. uPVC P-trap, 50mm dia. pcs 4.00 107.00 428.00
g. PVC cement can 5.00 190.00 950.00
h. Consumables (5% of Materials)

Sub - Total for F 16,040.00


G. Direct Unit Cost (E + F) 19,977.42
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,397.29
I. Contractor's Profit (CP) 8% of G 1,598.19
J. Value Added Tax (VAT) 5% of (G + H + I) 1,198.65
K. Total Unit Cost (G + H + I + J) 25,171.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works


Unit of Measurement : pc
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.75 100.36 476.71


b. Skilled Laborer 1 4.75 73.01 346.80
c. Unskilled Laborer 2 4.75 56.27 534.57

Sub - Total for A 1,358.07

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 135.81

Sub - Total for B 135.81


C. Total (A + B) 1,493.88
D. Output = 1
E. Direct Unit Cost (C ÷ D) 1,493.88

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

c. PPRC Pipe, 20mm dia. X 4m, PN 16 length 20.00 275.50 5,510.00


d. PP-R Coupling 20mm dia. pcs 20.00 15.80 316.00
g. PP-R Elbow 20mm dia.- 90 deg pcs 10.00 12.64 126.40
h.PP-R Tee 20mm dia. pcs 7.00 14.80 103.60
k. Consumables (5% of Materials)

Sub - Total for F 6,056.00


G. Direct Unit Cost (E + F) 7,549.88
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 905.99
I. Contractor's Profit (CP) 8% of G 603.99
J. Value Added Tax (VAT) 5% of (G + H + I) 452.99
K. Total Unit Cost (G + H + I + J) 9,512.85
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 26.00 100.36 2,609.36


b. Skilled Laborer 2 26.00 73.01 3,796.52
c. Unskilled Laborer 4 26.00 56.27 5,852.08

Sub - Total for A 12,257.96

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,225.80

Sub - Total for B 1,225.80


C. Total (A + B) 13,483.76
D. Output = 1
E. Direct Unit Cost (C ÷ D) 13,483.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. uPVC Drain Pipe, 50mm dia.x3m pcs 22.00 1,975.29 43,456.38


b. Roof Drain (Dome-type strainer) pcs 12.00 1,500.00 18,000.00
c.uPVC Sanitary Pipe, 50mm dia.x 3m, S-1000 lengths 25.00 500.00 12,500.00
d.Elbow, 50mm dia. 90 deg bend pcs 25.00 38.00 950.00
e. PVC solvent, 400cc cans 5.00 190.00 950.00
f. Consumables 5%

Sub - Total for F 75,856.38


G. Direct Unit Cost (E + F) 89,340.14
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,720.82
I. Contractor's Profit (CP) 8% of G 7,147.21
J. Value Added Tax (VAT) 5% of (G + H + I) 5,360.41
K. Total Unit Cost (G + H + I + J) 112,568.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 80.75 100.36 8,104.07


b. Skilled Laborer 1 80.75 73.01 5,895.56
c. Unskilled Laborer 1 80.75 56.27 4,543.80

Sub - Total for A 18,543.43

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,854.34

Sub - Total for B 1,854.34


C. Total (A + B) 20,397.77
D. Output = 1
E. Direct Unit Cost (C ÷ D) 20,397.77

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ bidet, fittings & accs. sets 4.00 9,000.00 36,000.00
d. Steel Counter Sink (4 Faucet) sets 1.00 6,028.00 6,028.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 7.00 6,500.00 45,500.00
g. Gate Valve 20mm dia pcs 4.00 330.00 1,320.00
i. Check Valve, 20mm dia. pcs 2.00 954.00 1,908.00
k.S.S. Floor Drain 4'x4'' pcs 4.00 280.00 1,120.00
l. Mirror m2 4.00 5,379.20 21,516.80
m. Handrail (PWD) sets 4.00 4,500.00 18,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 4.00 165.00 660.00
o. Fire Extinguisher, 5 lbs Capacity set 2.00 4,000.00 8,000.00

Sub - Total for F 140,052.80


G. Direct Unit Cost (E + F) 160,450.57
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 19,254.07
I. Contractor's Profit (CP) 8% of G 12,836.05
J. Value Added Tax (VAT) 5% of (G + H + I) 9,627.03
K. Total Unit Cost (G + H + I + J) 202,167.72
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin


Unit of Measurement : units
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 100.36 401.44


b. Skilled Laborer 1 4.00 73.01 292.04
c. Unskilled Laborer 1 4.00 56.27 225.08

Sub - Total for A 918.56

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 91.86

Sub - Total for B 91.86


C. Total (A + B) 1,010.42
D. Output = 1
E. Direct Unit Cost (C ÷ D) 1,010.42

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement pcs 2.00 217.50 435.00


b. Sand cu.m 0.50 369.43 184.72
c. Pre-fabricated flat bar drain for CB 300x300 pcs 6.00 1,000.00 6,000.00

Sub - Total for F 6,619.72


G. Direct Unit Cost (E + F) 7,630.13
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 915.62
I. Contractor's Profit (CP) 8% of G 610.41
J. Value Added Tax (VAT) 5% of (G + H + I) 457.81
K. Total Unit Cost (G + H + I + J) 9,613.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(11) Septic Vault (Concrete/CHB)


Unit of Measurement : m2
Output per hour : 3.18

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 100.36 100.36


b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 3 1.00 56.27 168.81

Sub - Total for A 415.19

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.52

Sub - Total for B 213.52


C. Total (A + B) 628.71
D. Output per Hour = 3.180 m2
E. Direct Unit Cost (C ÷ D) 197.71

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm thk CHB (Non-Load Bearing) pc 15.00 9.80 147.00


b. Cement bag 4.500 217.50 978.75
c. Sand cu.m 3.00 369.43 1,108.29
d. Reinforcing Steel kg 6.28 34.22 214.90
e. #16 Tie wire kg 0.05 63.50 3.18

Sub - Total for F 2,452.12


G. Direct Unit Cost (E + F) 2,649.82
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 317.98
I. Contractor's Profit (CP) 8% of G 211.99
J. Value Added Tax (VAT) 5% of (G + H + I) 158.99
K. Total Unit Cost (G + H + I + J) 3,338.78
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.00 100.36 4,014.40


b. Skilled Laborer 1 68.00 73.01 4,964.68
c. Unskilled Laborer 1 68.00 56.27 3,826.36

Sub - Total for A 12,805.44

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,280.54

Sub - Total for B 1,280.54


C. Total (A + B) 14,085.98
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 14,085.98

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 210.00 69.00 14,490.00


b. 25mmØ PVC conduit length 4.00 92.00 368.00
c. 32mmØ PVC conduit length 12.00 120.00 1,440.00
d. 65mmØ RSC conduit length 5.00 2,233.35 11,166.75
d. 90mmØ RSC conduit length 4.00 3,580.46 14,321.84
d. 32mmØ RSC elbow pc 2.00 320.00 640.00
e. 20mmØ PVC adpater pc 250.00 8.00 2,000.00
f. 25mmØ PVC adapter pc 4.00 14.00 56.00
g. 32mmØ PVC adapter pc 2.00 16.00 32.00
h. 20mmØ locknut and bushing pr 500.00 8.00 4,000.00
j. 25mmØ locknut and bushing pr 2.00 14.00 28.00
j. 32mmØ locknut and bushing pr 2.00 16.00 32.00
k. 20mmØ liquidtight flexible metal conduit pc 3.00 20.00 60.00
l. 20mmØ connector m 2.00 10.00 20.00
m. Ulitiity box, deep type pc 85.00 30.00 2,550.00
n. junction box, deep type pc 75.00 31.00 2,325.00
o. 90mmØ entrance cap pc 1.00 684.00 684.00
p. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F 56,613.59


G. Direct Unit Cost (E + F) 70,699.57
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8,483.95
I. Contractor's Profit (CP) 8% of G 5,655.97
J. Value Added Tax (VAT) 5% of (G + H + I) 4,241.97
K. Total Unit Cost (G + H + I + J) 89,081.46
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 45.00 100.36 4,516.20


b. Skilled Laborer 1 65.00 73.01 4,745.65
c. Unskilled Laborer 1 65.00 56.27 3,657.55

Sub - Total for A 12,919.40

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,291.94

Sub - Total for B 1,291.94


C. Total (A + B) 14,211.34
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 14,211.34

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 THHN wire,stranded m 1340.00 23.00 30,820.00


b. 5.5mm2 THHN wire,stranded m 60.00 24.00 1,440.00
c.14.0mm2 THHN, wire, stranded m 12.00 86.00 1,032.00
c.100.0mm2 THHN, wire, stranded m 11.00 691.00 7,601.00
c.200.0mm2 THHN, wire, stranded m 14.00 1,336.00 18,704.00
d.2.0mm2 TW wire, stranded m 216.00 24.00 5,184.00
e. 3.5mm2 TW wire, stranded m 670.00 23.00 15,410.00
f.5.5mm2 TW wire stranded m 30.00 24.00 720.00
g.8.0mm2 TW wire stranded m 8.00 65.00 520.00
g.22.0mm2 TW wire stranded m 7.00 156.00 1,092.00
g.30.0mm2 TW wire stranded m 12.00 210.00 2,520.00
h. one gang switch set 10.00 92.00 920.00
i. two gang switch set 6.00 126.00 756.00
j. three gang switch set 4.00 145.00 580.00
j. 2- gang ,three way switch set 4.00 175.00 700.00
k. Duplex C.O. grounding type, 15A, 250V set 40.00 330.00 13,200.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 4.00 420.00 1,680.00

m. KWHR meter set 1.00 2,200.00 2,200.00


n. Tape, bolt&nut, mica tube, terminal lugs, JB lot 1.00 5,253.95 5,253.95
cover clamps, screw and anchors
Sub - Total for F 110,332.95
G. Direct Unit Cost (E + F) 124,544.29
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 14,945.31
I. Contractor's Profit (CP) 8% of G 9,963.54
J. Value Added Tax (VAT) 5% of (G + H + I) 7,472.66
K. Total Unit Cost (G + H + I + J) 156,925.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 7.00 100.36 702.52


b. Skilled Laborer 1 7.00 73.01 511.07
c. Unskilled Laborer 2 7.00 56.27 787.78

Sub - Total for A 2,001.37

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 200.14

Sub - Total for B 200.14


C. Total (A + B) 2,201.51
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 2,201.51

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

LPA - Flush Mounted, NEMA 1 Enclosure w/ 14,790.10


set 1.00
Ground Terminal 14,790.10
Main: 100at, 100af, 2p, 240v ,18KAIC
Branches: 6 - 15at, 50af, 2p, 240v
10 - 20at, 50af, 2p, 240v
3 - 30at, 50af, 2p, 240v

40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure 1,200.00


set 1.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure 1,200.00
set 1.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure 1,200.00
set 1.00 1,200.00
Sub - Total for F 18,390.10
G. Direct Unit Cost (E + F) 20,591.61
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,470.99
I. Contractor's Profit (CP) 8% of G 1,647.33
J. Value Added Tax (VAT) 5% of (G + H + I) 1,235.50
K. Total Unit Cost (G + H + I + J) 25,945.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 26.00 100.36 2,609.36


b. Skilled Laborer 1 26.00 73.01 1,898.26
c. Unskilled Laborer 2 26.00 56.27 2,926.04

Sub - Total for A 7,433.66

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 743.37

Sub - Total for B 743.37


C. Total (A + B) 8,177.03
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 8,177.03

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 36 watts FL set 15.00 70.00 1,050.00


b. 2 x 36 watts FL recessed fixture box type w/ set 15.00 1,173.00 17,595.00
canopy base and stem -
c. 12 watts LED Round Vertical Pinlight Fixture E27
set 29.00 260.00 7,540.00

d. 12 watts LED Bulb set 29.00 140.00 4,060.00

Sub - Total for F 30,245.00


G. Direct Unit Cost (E + F) 38,422.03
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,610.64
I. Contractor's Profit (CP) 8% of G 3,073.76
J. Value Added Tax (VAT) 5% of (G + H + I) 2,305.32
K. Total Unit Cost (G + H + I + J) 48,411.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

b. Skilled Laborer 1 24.00 100.36 2,408.64


c. Unskilled Laborer 1 24.00 56.27 1,350.48

Sub - Total for A 3,759.12

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 375.91

Sub - Total for B 375.91


C. Total (A + B) 4,135.03
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 4,135.03

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Emergency Lights set 1.00 13,890.00 13,890.00

Sub - Total for F 13,890.00


G. Direct Unit Cost (E + F) 18,025.03
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,163.00
I. Contractor's Profit (CP) 8% of G 1,442.00
J. Value Added Tax (VAT) 5% of (G + H + I) 1,081.50
K. Total Unit Cost (G + H + I + J) 22,711.54
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING Appropriation :


Source of Fund :
Project ID : Target Start Date :
Location : Total Project Duration :
Project Description :

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF!
Part II Other General Requirements #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF!
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF!
PART C FINISHING WORKS #REF!
PART D PLUMBING/SANITARY WORKS #REF!
PART E ELECTRICAL WORKS #REF!

Total

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, % #REF!
6. Value Added Tax #REF! F. RROW Acquisition
7. EAO, % G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST H. TOTAL ESTIMATED COST #REF!

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 64.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 180 C.D.
Project Description : Complete construction of 2-Storey 12-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.89% 156,000.00
Part II Other General Requirements 1.58% 275,814.08
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.28% 396,833.63
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.33% 5,988,000.95
PART C FINISHING WORKS 46.10% 8,041,232.82
PART D PLUMBING/SANITARY WORKS 10.45% 1,823,557.12
PART E ELECTRICAL WORKS 4.36% 760,618.07

Total 100% 17,442,056.67

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 3,639,079.09 A. Total Direct Cost 17,442,056.67
2. Materials 12,229,072.63 B. OCM and Profit 3,437,096.81
3. Rental of Equipment 1,573,904.94 C. Value Added Tax (12%) 2,505,498.44
4. Provisional Sum / Daywork D. Total Construction Cost 23,384,651.92
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 3,437,096.81 E. Eng'g & Administrative Overhead, 0.5% 117,510.81
6. Value Added Tax (12%) 2,505,498.44 F. RROW Acquisition
7. EAO, 0.5% 117,510.81 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 23,502,162.73 H. TOTAL ESTIMATED COST 23,502,162.73
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted Err:509 6.00 mo - - 156,000.00 156,000.00 8% 12,480.00 20,217.60 188,697.60
Err:509 Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 156,000.00 156,000.00 12,480.00 20,217.60 188,697.60
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted ### 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
B.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 59116.55 1.00 lot 137,035.54 7,008.96 - 144,044.50 8% 11,523.56 18,668.17 174,236.23
B.7(2) Occupational Safety and Health
As Evaluated
As Submitted 40414.67 1.00 l.s. - - 127,576.82 127,576.82 8% 10,206.15 16,533.96 154,316.93
B.9 Mobilization/ Demobilization
As Evaluated
As Submitted 140,217.88 7,927.52 127,668.68 275,814.08 22,568.26 35,805.89 334,188.23
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted ### 413.71 m3 - 5,567.92 91,097.23 96,665.14 20% 19,333.03 13,919.78 129,917.95
803(1)a Structure Excavation
As Evaluated
As Submitted Err:509 257.76 m3 - 7,050.94 33,318.02 40,368.96 20% 8,073.79 5,813.13 54,255.88
Err:509 Embankment from Structure Excavation
As Evaluated
As Submitted 57302.14 335.90 m3 122,028.27 9,188.44 43,418.39 174,635.09 20% 34,927.02 25,147.45 234,709.56
804(1)b Embankment from Borrow
As Evaluated
As Submitted 17916.16 90.34 m3 58,244.10 20,264.01 6,656.33 85,164.44 20% 17,032.89 12,263.68 114,461.01
804(4) Gravel Fill
As Evaluated
As Submitted 180,272.37 42,071.31 174,489.96 396,833.63 79,366.73 57,144.04 533,344.40
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted ### 384.71 m3 1,263,772.35 60,395.33 82,880.19 1,407,047.87 20% 281,409.57 202,614.89 1,891,072.33
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted ### 68,853.89 kg 2,542,851.62 530,498.28 205,391.47 3,278,741.37 20% 655,748.27 472,138.76 4,406,628.40
902(1)a Reinforcing Steel, Grade 40
As Evaluated
As Submitted ### 2,577.60 m2 504,369.13 558,645.42 239,197.16 1,302,211.71 20% 260,442.34 187,518.49 1,750,172.54
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,310,993.10 1,149,539.04 527,468.81 5,988,000.95 1,197,600.18 862,272.14 8,047,873.27
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted ### 300.27 L 96,086.40 15,898.18 1,589.82 113,574.40 20% 22,714.88 16,354.71 152,643.99
1000(1) Soil Poisoning
As Evaluated
As Submitted 96,086.40 15,898.18 1,589.82 113,574.40 22,714.88 16,354.71 152,643.99
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted ### 285.37 m2 99,856.73 30,975.89 15,929.91 146,762.53 20% 29,352.51 21,133.80 197,248.84
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted ### 961.80 m2 561,645.73 125,575.39 64,579.43 751,800.54 20% 150,360.11 108,259.28 1,010,419.93
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 661,502.46 156,551.28 80,509.34 898,563.07 179,712.62 129,393.08 1,207,668.77
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted ### 1.00 l.s 343,872.83 66,595.60 45.93 410,514.36 20% 82,102.87 59,114.07 551,731.30
1010(4) Wooden Doors
As Evaluated
As Submitted Err:509 70.87 m 2
47,447.47 60,276.25 6,027.62 113,751.34 20% 22,750.27 16,380.19 152,881.80
Err:509 Jalousie Window
As Evaluated
As Submitted Err:509 146.88 m 2
272,857.73 187,386.24 98,502.62 558,746.59 20% 111,749.32 80,459.51 750,955.42
1005(1) Steel Casement Window
As Evaluated
As Submitted Err:509 65.28 m 2
56,433.61 9,369.31 4,925.13 70,728.06 20% 14,145.61 10,184.84 95,058.51
1005(5) Window Grilles
As Evaluated
As Submitted ### 43.00 set 64,500.00 - - 64,500.00 20% 12,900.00 9,288.00 86,688.00
1004(2)a Locksets
As Evaluated
As Submitted 918.50 172.00 pc 11,398.44 - - 11,398.44 20% 2,279.69 1,641.38 15,319.51
1004(2)g Hinges
As Evaluated
As Submitted Err:509 1.00 l.s. 37,200.00 9,818.40 981.84 48,000.24 20% 9,600.05 6,912.03 64,512.32
Err:509 Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 833,710.08 333,445.80 110,483.15 1,277,639.03 255,527.81 183,980.02 1,717,146.86
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted ### 1,161.01 m2 221,432.06 66,768.81 6,676.88 294,877.75 20% 58,975.55 42,462.40 396,315.70
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted ### 4,355.83 m2 355,282.82 288,224.51 28,822.45 672,329.77 20% 134,465.95 96,815.49 903,611.21
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted ### 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(2)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted Err:509 144.00 m 243,681.41 6,582.10 7,670.87 257,934.38 20% 51,586.88 37,142.55 346,663.81
Err:509 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted ### 661.00 m2 410,897.43 152,040.64 15,204.06 578,142.13 20% 115,628.43 83,252.47 777,023.03
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted ### 841.24 m2 119,245.77 43,258.80 4,325.88 166,830.45 20% 33,366.09 24,023.58 224,220.12
1038(1) Reflective Insulation
As Evaluated
As Submitted ### 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted ### 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,534,110.90 642,490.41 74,475.84 2,251,077.15 450,215.44 324,155.12 3,025,447.71
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted ### 4,943.76 m2 674,852.31 712,489.98 71,249.00 1,458,591.29 20% 291,718.26 210,037.15 1,960,346.70
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted ### 247.39 m2 19,362.81 39,615.12 3,961.51 62,939.45 20% 12,587.89 9,063.28 84,590.62
1032(1)b Wood Painting
As Evaluated
As Submitted Err:509 125.09 m2 17,234.96 18,929.24 1,892.92 38,057.13 20% 7,611.43 5,480.23 51,148.79
Err:509 Metal Painting
As Evaluated
As Submitted 711,450.08 771,034.35 77,103.44 1,559,587.87 311,917.58 224,580.66 2,096,086.11
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted ### 841.24 m2 347,086.71 115,856.97 11,585.70 474,529.38 20% 94,905.88 68,332.23 637,767.49
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted ### 64.20 m 13,549.22 1,474.29 147.43 15,170.94 20% 3,034.19 2,184.62 20,389.75
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted Err:509 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
Err:509 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted Err:509 128.40 m 41,262.62 2,498.79 249.88 44,011.30 20% 8,802.26 6,337.63 59,151.19
Err:509 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted ### 7,703.59 kg 428,855.23 49,752.65 103,653.95 582,261.83 20% 116,452.37 83,845.70 782,559.90
1003(5) Structural Steel, Trusses
As Evaluated
As Submitted Err:509 10,028.53 kg 564,929.01 52,272.53 87,495.57 704,697.11 20% 140,939.42 101,476.38 947,112.91
Err:509 Structural Steel, Purlins
As Evaluated
As Submitted Err:509 128.40 m 24,402.42 3,091.77 309.18 27,803.36 20% 5,560.67 4,003.68 37,367.71
Err:509 Fascia Board
As Evaluated
As Submitted ### 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted ### 293.65 kg 11,679.64 5,189.21 518.92 17,387.77 20% 3,477.55 2,503.84 23,369.16
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted ### 628.56 kg 25,750.36 11,107.54 1,110.75 37,968.65 20% 7,593.73 5,467.49 51,029.87
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted ### 52.00 pc 8,532.16 1,791.19 1.79 10,325.14 20% 2,065.03 1,486.82 13,876.99
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,486,627.54 248,540.08 205,623.68 1,940,791.30 388,158.27 279,473.95 2,608,423.52
Sub-Total C.6
As Evaluated
As Submitted 5,323,487.45 2,167,960.10 549,785.26 8,041,232.82 1,608,246.60 1,157,937.54 10,807,416.96
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted ### 1.00 l.s. 45,831.25 10,578.67 1,057.87 57,467.79 20% 11,493.56 8,275.36 77,236.71
1001(8) Sewer Line Works
As Evaluated
As Submitted ### 1.00 l.s. 31,668.25 7,362.18 736.22 39,766.65 20% 7,953.33 5,726.40 53,446.38
1002(6) Cold Water Line Works
As Evaluated
As Submitted ### 1.00 l.s. 193,090.94 44,552.97 4,455.30 242,099.20 20% 48,419.84 34,862.28 325,381.32
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted ### 1.00 l.s. 326,472.09 37,833.19 3,783.32 368,088.60 20% 73,617.72 53,004.76 494,711.08
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted Err:509 1.00 l.s. 84,458.63 20,979.97 2,098.00 107,536.59 20% 21,507.32 15,485.27 144,529.18
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted ### 30.00 units 18,201.24 6,889.20 12,023.04 37,113.48 20% 7,422.70 5,344.34 49,880.52
1001(6)b1 Catch basin
As Evaluated
As Submitted Err:509 1.00 lot 875,153.75 87,573.70 8,757.37 971,484.81 20% 194,296.96 139,893.81 1,305,675.58
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,574,876.14 215,769.88 32,911.11 1,823,557.12 364,711.43 262,592.22 2,450,860.77
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted ### 1.00 l.s. 90,605.14 17,183.92 1,718.39 109,507.45 20% 21,901.49 15,769.07 147,178.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted ### 1.00 l.s. 212,531.55 20,038.24 2,003.82 234,573.61 20% 46,914.72 33,778.60 315,266.93
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted ### 1.00 l.s. 251,941.00 4,288.65 428.87 256,658.52 20% 51,331.70 36,958.83 344,949.05
1102(21) Panel Board
As Evaluated
As Submitted ### 1.00 l.s. 120,058.00 10,292.76 1,029.28 131,380.04 20% 26,276.01 18,918.73 176,574.78
1103(1) Lighting Fixtures
As Evaluated
As Submitted ### 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 699,225.69 55,811.25 5,581.13 760,618.070 152,123.610 109,529.010 1,022,270.690
TOTAL OF PART E
As Evaluated
As Submitted 12,088,854.75 3,631,151.57 1,290,236.27 17,010,242.590 3,402,048.550 2,449,474.950 22,861,766.090
TOTAL OF PART III
As Evaluated
As Submitted 12,229,072.63 3,639,079.09 1,573,904.94 17,442,056.670 3,437,096.810 2,505,498.440 23,384,651.920
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 55.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 175 C.D.
Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.99% 151,666.67
Part II Other General Requirements 1.61% 247,792.58
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.24% 343,879.89
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.84% 5,205,623.63
PART C FINISHING WORKS 45.48% 6,995,668.73
PART D PLUMBING/SANITARY WORKS 11.25% 1,729,864.72
PART E ELECTRICAL WORKS 4.61% 708,793.02
`

Total 100% 15,383,289.24

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 3,189,375.97 A. Total Direct Cost 15,383,289.24
2. Materials 10,816,171.39 B. OCM and Profit 3,029,225.88
3. Rental of Equipment 1,377,741.87 C. Value Added Tax (12%) 2,209,501.77
4. Provisional Sum / Daywork D. Total Construction Cost 20,622,016.89
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 3,029,225.88 E. Eng'g & Administrative Overhead, 0.5% 103,628.23
6. Value Added Tax (12%) 2,209,501.77 F. RROW Acquisition
7. EAO, 0.5% 103,628.23 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 20,725,645.12 H. TOTAL ESTIMATED COST 20,725,645.12
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.83 mo - - 151,666.67 151,666.67 8% 12,133.33 19,656.00 183,456.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 151,666.67 151,666.67 12,133.33 19,656.00 183,456.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S. 124,212.14 7,008.96 - 131,221.10 8% 10,497.69 17,006.25 158,725.04
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 112,378.72 112,378.72 8% 8,990.30 14,564.28 135,933.30
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 127,394.48 7,927.52 112,470.58 247,792.58 20,326.54 32,174.29 300,293.41
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 365.45 m3 - 4,918.41 80,470.57 85,388.98 20% 17,077.80 12,296.01 114,762.79
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted #REF! 223.43 m3 - 6,111.85 28,880.53 34,992.39 20% 6,998.48 5,038.90 47,029.77
Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 288.09 m3 104,659.50 7,880.61 37,238.47 149,778.58 20% 29,955.72 21,568.12 201,302.42
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 78.20 m3 50,417.18 17,540.91 5,761.84 73,719.94 20% 14,743.99 10,615.67 99,079.60
804(4) Gravel Fill
As Evaluated
As Submitted 155,076.68 36,451.78 152,351.42 343,879.89 68,775.99 49,518.70 462,174.58
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 335.41 m3 1,101,821.85 52,655.76 72,259.22 1,226,736.83 20% 245,347.37 176,650.10 1,648,734.30
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 59,947.73 kg 2,213,937.11 461,879.02 178,824.36 2,854,640.49 20% 570,928.10 411,068.23 3,836,636.82
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,225.34 m2 435,440.05 482,298.73 206,507.53 1,124,246.31 20% 224,849.26 161,891.47 1,510,987.04
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,751,199.01 996,833.52 457,591.10 5,205,623.63 1,041,124.73 749,609.80 6,996,358.16
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 259.98 L 83,193.60 13,764.98 1,376.50 98,335.08 20% 19,667.02 14,160.25 132,162.35
1000(1) Soil Poisoning
As Evaluated
As Submitted 83,193.60 13,764.98 1,376.50 98,335.08 19,667.02 14,160.25 132,162.35
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 267.94 m2 93,757.62 29,083.92 14,956.94 137,798.48 20% 27,559.70 19,842.98 185,201.16
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 838.99 m2 489,930.49 109,540.96 56,333.43 655,804.88 20% 131,160.98 94,435.90 881,401.76
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 583,688.12 138,624.89 71,290.37 793,603.36 158,720.68 114,278.88 1,066,602.92
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 296,777.99 59,706.40 5,970.64 362,455.03 20% 72,491.01 52,193.52 487,139.56
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 59.98 m2 40,156.61 51,014.10 5,101.41 96,272.12 20% 19,254.42 13,863.18 129,389.72
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 122.40 m 2
227,381.44 156,155.20 82,085.52 465,622.16 20% 93,124.43 67,049.59 625,796.18
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 54.40 m2 47,028.01 7,807.76 4,104.28 58,940.05 20% 11,788.01 8,487.37 79,215.43
1005(5) Window Grills
As Evaluated
As Submitted #REF! 39.00 set 58,500.00 - - 58,500.00 20% 11,700.00 8,424.00 78,624.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 156.00 pc 10,338.12 - - 10,338.12 20% 2,067.62 1,488.69 13,894.43
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 31,000.00 8,182.00 818.20 40,000.20 20% 8,000.04 5,760.03 53,760.27
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 711,182.17 282,865.46 98,080.05 1,092,127.68 218,425.53 157,266.38 1,467,819.59
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,000.20 m2 190,761.79 57,520.75 5,752.07 254,034.61 20% 50,806.92 36,580.98 341,422.51
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,825.21 m2 312,002.85 253,113.47 25,311.35 590,427.67 20% 118,085.53 85,021.58 793,534.78
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 127.60 m 215,928.80 5,832.47 6,797.24 228,558.52 20% 45,711.70 32,912.43 307,182.65
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 565.91 m2 351,786.63 130,168.41 13,016.84 494,971.88 20% 98,994.38 71,275.95 665,242.21
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 723.31 m2 102,529.19 37,194.53 3,719.45 143,443.17 20% 28,688.63 20,655.82 192,787.62
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m 2
109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,356,580.68 569,445.19 66,372.65 1,992,398.52 398,479.70 286,905.39 2,677,783.61
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,336.71 m2 591,986.41 625,002.52 62,500.25 1,279,489.18 20% 255,897.84 184,246.44 1,719,633.46
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 218.61 m2 17,110.25 35,006.52 3,500.65 55,617.42 20% 11,123.48 8,008.91 74,749.81
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 112.50 m2 15,500.30 17,024.06 1,702.41 34,226.77 20% 6,845.35 4,928.65 46,000.77
1032(1)c Metal Painting
As Evaluated
As Submitted 624,596.97 677,033.09 67,703.31 1,369,333.37 273,866.67 197,184.00 1,840,384.04
Sub-Total C.5
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
C.6 Roof Framing and Roofing Works
As Submitted #REF! 723.31 m2 298,429.70 99,615.34 9,961.53 408,006.57 20% 81,601.31 58,752.95 548,360.83
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 55.20 m 11,649.79 1,267.61 126.76 13,044.17 20% 2,608.83 1,878.36 17,531.36
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 110.40 m 35,478.14 2,148.50 214.85 37,841.49 20% 7,568.30 5,449.17 50,858.96
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 6,440.06 kg 358,515.11 41,592.30 86,652.80 486,760.21 20% 97,352.04 70,093.47 654,205.72
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 8,515.07 kg 479,672.50 44,383.80 74,291.14 598,347.44 20% 119,669.49 86,162.03 804,178.96
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 110.40 m 20,981.52 2,658.34 265.83 23,905.69 20% 4,781.14 3,442.42 32,129.25
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 248.16 kg 9,870.32 4,385.34 438.53 14,694.19 20% 2,938.84 2,115.96 19,748.99
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 528.07 kg 21,633.56 9,331.74 933.17 31,898.48 20% 6,379.70 4,593.38 42,871.56
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 44.00 pc 7,219.52 1,515.62 1.52 8,736.66 20% 1,747.33 1,258.08 11,742.07
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,264,030.33 212,403.73 173,436.65 1,649,870.72 329,974.15 237,581.38 2,217,426.25
Sub-Total C.6
As Evaluated
As Submitted 4,623,271.86 1,894,137.33 478,259.53 6,995,668.73 1,399,133.75 1,007,376.28 9,402,178.76
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 43,151.00 10,006.85 1,000.69 54,158.54 20% 10,831.71 7,798.83 72,789.08
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 29,320.77 6,790.36 679.04 36,790.16 20% 7,358.03 5,297.78 49,445.97
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 172,839.11 39,956.24 3,995.62 216,790.97 20% 43,358.19 31,217.90 291,367.06
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 325,296.09 37,660.96 3,766.10 366,723.15 20% 73,344.63 52,808.13 492,875.91
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 71,748.04 18,033.35 1,803.33 91,584.71 20% 18,316.94 13,188.20 123,089.85
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 26.00 units 15,774.41 5,970.64 597.06 22,342.11 20% 4,468.42 3,217.26 30,027.79
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 848,514.95 84,509.21 8,450.92 941,475.08 20% 188,295.02 135,572.41 1,265,342.51
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,506,644.36 202,927.60 20,292.76 1,729,864.72 345,972.94 249,100.51 2,324,938.17
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 80,540.14 14,241.12 1,424.11 96,205.37 20% 19,241.07 13,853.57 129,300.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 202,341.55 17,124.36 1,712.44 221,178.35 20% 44,235.67 31,849.68 297,263.70
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 244,155.30 6,861.84 686.18 251,703.32 20% 50,340.66 36,245.28 338,289.26
1102(21) Panel Board
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 1.00 l.s. 101,458.00 8,863.21 886.32 111,207.53 20% 22,241.51 16,013.88 149,462.92
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 652,584.99 51,098.21 5,109.82 708,793.020 141,758.600 102,066.190 952,617.810
TOTAL OF PART E
As Evaluated
As Submitted 10,688,776.91 3,181,448.45 1,113,604.62 14,983,829.990 2,996,766.010 2,157,671.480 20,138,267.480
TOTAL OF PART III
As Evaluated
As Submitted 10,816,171.39 3,189,375.97 1,377,741.87 15,383,289.240 3,029,225.880 2,209,501.770 20,622,016.890
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 46.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 150 C.D.
Project Description : Complete construction of 2-Storey 8-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.98% 130,000.00
Part II Other General Requirements 1.66% 218,951.28
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.19% 289,618.72
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.44% 4,423,246.32
PART C FINISHING WORKS 44.93% 5,943,512.95
PART D PLUMBING/SANITARY WORKS 12.17% 1,609,931.08
PART E ELECTRICAL WORKS 4.63% 612,125.66

Total 100% 13,227,386.01

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 2,728,009.94 A. Total Direct Cost 13,227,386.01
2. Materials 9,333,208.55 B. OCM and Profit 2,604,106.19
3. Rental of Equipment 1,166,167.47 C. Value Added Tax (12%) 1,899,779.08
4. Provisional Sum / Daywork D. Total Construction Cost 17,731,271.28
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 2,604,106.19 E. Eng'g & Administrative Overhead, 0.5% 89,101.87
6. Value Added Tax (12%) 1,899,779.08 F. RROW Acquisition
7. EAO, 0.5% 89,101.87 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 17,820,373.15 H. TOTAL ESTIMATED COST 17,820,373.15
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.00 mo - - 130,000.00 130,000.00 8% 10,400.00 16,848.00 157,248.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 130,000.00 130,000.00 10,400.00 16,848.00 157,248.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 112,329.46 5,840.80 - 118,170.26 8% 9,453.62 15,314.87 142,938.75
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 96,588.26 96,588.26 8% 7,727.06 12,517.84 116,833.16
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 115,511.80 6,759.36 96,680.12 218,951.28 18,019.23 28,436.47 265,406.98
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 313.84 m3 - 4,223.82 69,106.27 73,330.08 20% 14,666.02 10,559.53 98,555.63
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 185.75 m3 - 5,081.13 24,010.02 29,091.15 20% 5,818.23 4,189.13 39,098.51
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 240.28 m3 87,290.72 6,572.78 31,058.56 124,922.06 20% 24,984.41 17,988.78 167,895.25
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 66.06 m3 42,590.27 14,817.81 4,867.36 62,275.43 20% 12,455.09 8,967.66 83,698.18
804(4) Gravel Fill
As Evaluated
As Submitted 129,880.99 30,695.54 129,042.20 289,618.72 57,923.75 41,705.10 389,247.57
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 286.11 m3 939,871.35 44,916.19 61,638.25 1,046,425.79 20% 209,285.16 150,685.31 1,406,396.26
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 51,041.57 kg 1,885,022.60 393,259.77 152,257.24 2,430,539.61 20% 486,107.92 349,997.70 3,266,645.23
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,873.07 m2 366,510.97 405,952.04 173,817.90 946,280.92 20% 189,256.18 136,264.45 1,271,801.55
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,191,404.93 844,128.01 387,713.39 4,423,246.32 884,649.26 636,947.46 5,944,843.04
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 219.68 L 70,297.60 11,631.24 1,163.12 83,091.97 20% 16,618.39 11,965.24 111,675.60
1000(1) Soil Poisoning
As Evaluated
As Submitted 70,297.60 11,631.24 1,163.12 83,091.97 16,618.39 11,965.24 111,675.60
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 250.52 m2 87,662.01 27,193.05 13,984.52 128,839.58 20% 25,767.92 18,552.90 173,160.40
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 716.18 m2 418,215.26 93,506.53 48,087.43 559,809.22 20% 111,961.84 80,612.53 752,383.59
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 505,877.27 120,699.58 62,071.95 688,648.80 137,729.76 99,165.43 925,543.99
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 249,683.14 52,817.20 5,281.72 307,782.06 20% 61,556.41 44,320.62 413,659.09
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 49.10 m 2
32,872.45 41,760.46 4,176.05 78,808.96 20% 15,761.79 11,348.49 105,919.24
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 97.92 m2 181,905.15 124,924.16 65,668.42 372,497.73 20% 74,499.55 53,639.67 500,636.95
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 43.52 m2 37,622.41 6,246.21 3,283.42 47,152.04 20% 9,430.41 6,789.89 63,372.34
1005 (5) Window Grills
As Evaluated
As Submitted #REF! 35.00 set 52,500.00 - - 52,500.00 20% 10,500.00 7,560.00 70,560.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 140.00 pc 9,277.80 - - 9,277.80 20% 1,855.56 1,336.00 12,469.36
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 24,800.00 6,545.60 654.56 32,000.16 20% 6,400.03 4,608.02 43,008.21
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 588,660.95 232,293.63 79,064.16 900,018.75 180,003.75 129,602.69 1,209,625.19
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 839.37 m2 160,087.71 48,271.53 4,827.15 213,186.40 20% 42,637.28 30,698.84 286,522.52
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,294.60 m 2
268,723.70 218,003.10 21,800.31 508,527.12 20% 101,705.42 73,227.90 683,460.44
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 111.20 m 188,176.20 5,082.84 5,923.62 199,182.66 20% 39,836.53 28,682.30 267,701.49
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 470.83 m2 292,682.05 108,298.48 10,829.85 411,810.38 20% 82,362.08 59,300.70 553,473.16
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 605.38 m2 85,812.62 31,130.25 3,113.03 120,055.89 20% 24,011.18 17,288.05 161,355.12
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,179,053.69 496,401.77 58,269.65 1,733,725.12 346,745.03 249,656.42 2,330,126.57
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 3,729.66 m2 509,120.52 537,515.05 53,751.50 1,100,387.07 20% 220,077.41 158,455.74 1,478,920.22
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 189.83 m2 14,857.68 30,397.91 3,039.79 48,295.38 20% 9,659.08 6,954.54 64,909.00
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 99.91 m2 13,765.65 15,118.88 1,511.89 30,396.42 20% 6,079.28 4,377.08 40,852.78
1032(1)c Metal Painting
As Evaluated
As Submitted 537,743.85 583,031.84 58,303.18 1,179,078.87 235,815.77 169,787.36 1,584,682.00
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 605.38 m2 249,772.68 83,373.71 8,337.37 341,483.76 20% 68,296.75 49,173.66 458,954.17
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 46.20 m 9,750.37 1,060.94 106.09 10,917.40 20% 2,183.48 1,572.11 14,672.99
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 92.40 m 29,693.66 1,798.20 179.82 31,671.68 20% 6,334.34 4,560.72 42,566.74
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 5,176.53 kg 288,174.99 33,431.96 69,651.65 391,258.60 20% 78,251.72 56,341.24 525,851.56
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 7,001.60 kg 394,415.43 36,495.02 61,086.62 491,997.06 20% 98,399.41 70,847.58 661,244.05
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 92.40 m 17,560.62 2,224.92 222.49 20,008.03 20% 4,001.61 2,881.16 26,890.80
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 202.67 kg 8,061.00 3,581.47 358.15 12,000.61 20% 2,400.12 1,728.09 16,128.82
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 427.58 kg 17,516.76 7,555.94 755.59 25,828.30 20% 5,165.66 3,719.28 34,713.24
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 36.00 pc 5,906.88 1,240.06 1.24 7,148.18 20% 1,429.64 1,029.34 9,607.16
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,041,432.57 176,267.32 141,249.54 1,358,949.44 271,789.90 195,688.74 1,826,428.08
Sub-Total C.6
As Evaluated
As Submitted 3,923,065.93 1,620,325.38 400,121.61 5,943,512.95 1,188,702.60 855,865.88 7,988,081.43
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 39,506.00 9,149.12 914.91 49,570.03 20% 9,914.01 7,138.08 66,622.12
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 25,799.54 6,004.11 600.41 32,404.06 20% 6,480.81 4,666.18 43,551.05
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 147,422.78 34,062.99 3,406.30 184,892.07 20% 36,978.41 26,624.46 248,494.94
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 323,532.09 37,488.73 3,748.87 364,769.69 20% 72,953.94 52,526.84 490,250.47
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 65,879.25 16,383.24 1,638.32 83,900.81 20% 16,780.16 12,081.72 112,762.69
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 20.00 units 12,134.16 4,592.80 459.28 17,186.24 20% 3,437.25 2,474.82 23,098.31
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 792,545.75 76,965.85 7,696.58 877,208.18 20% 175,441.64 126,317.98 1,178,967.80
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,406,819.57 184,646.83 18,464.68 1,609,931.08 321,986.22 231,830.08 2,163,747.38
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 73,453.64 12,805.44 1,280.54 87,539.62 20% 17,507.92 12,605.70 117,653.24
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 141,968.40 12,919.40 1,291.94 156,179.74 20% 31,235.95 22,489.88 209,905.57
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 244,155.30 4,288.65 428.87 248,872.82 20% 49,774.56 35,837.69 334,485.07
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 82,858.00 7,433.66 743.37 91,035.03 20% 18,207.01 13,109.04 122,351.08
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 566,525.34 41,454.83 4,145.48 612,125.660 122,425.130 88,146.090 822,696.880
TOTAL OF PART E
As Evaluated
As Submitted 9,217,696.75 2,721,250.58 939,487.36 12,878,434.730 2,575,686.960 1,854,494.610 17,308,616.300
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 9,333,208.55 2,728,009.94 1,166,167.47 13,227,386.010 2,604,106.190 1,899,779.080 17,731,271.280
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 32.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 140 C.D.
Project Description : Complete construction of 2-Storey 6-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.34% 121,333.33
Part II Other General Requirements 1.83% 165,697.10
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.26% 205,356.87
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.42% 3,120,847.89
PART C FINISHING WORKS 47.32% 4,290,596.84
PART D PLUMBING/SANITARY WORKS 10.15% 920,631.76
PART E ELECTRICAL WORKS 2.68% 242,990.66

Total 100% 9,067,454.45

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,902,460.85 A. Total Direct Cost 9,067,454.45
2. Materials 6,284,783.90 B. OCM and Profit 1,779,550.37
3. Rental of Equipment 880,209.68 C. Value Added Tax (12%) 1,301,640.60
4. Provisional Sum / Daywork D. Total Construction Cost 12,148,645.42
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 1,779,550.37 E. Eng'g & Administrative Overhead, 0.5% 61,048.47
6. Value Added Tax (12%) 1,301,640.60 F. RROW Acquisition
7. EAO, 0.5% 61,048.47 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 12,209,693.89 H. TOTAL ESTIMATED COST 12,209,693.89
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.67 mo - - 121,333.33 121,333.33 8% 9,706.67 15,724.80 146,764.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 121,333.33 121,333.33 9,706.67 15,724.80 146,764.80
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 89,810.36 5,840.80 - 95,651.16 8% 7,652.09 12,396.39 115,699.64
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 65,853.18 65,853.18 8% 5,268.25 8,534.57 79,656.00
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 92,992.70 6,759.36 65,945.04 165,697.10 13,758.89 21,534.72 200,990.71
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 244.62 m3 - 3,292.22 53,864.31 57,156.53 20% 11,431.31 8,230.54 76,818.38
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 139.08 m3 - 3,804.49 17,977.46 21,781.95 20% 4,356.39 3,136.60 29,274.94
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 159.64 m3 57,995.22 4,366.90 20,635.04 82,997.16 20% 16,599.43 11,951.59 111,548.18
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 46.06 m3 29,695.85 10,331.64 3,393.74 43,421.23 20% 8,684.25 6,252.66 58,358.14
804(4) Gravel Fill
As Evaluated
As Submitted 87,691.07 21,795.25 95,870.55 205,356.87 41,071.38 29,571.39 275,999.64
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 201.23 m3 661,040.55 31,590.95 43,352.08 735,983.58 20% 147,196.72 105,981.64 989,161.94
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 36,154.58 kg 1,335,229.31 278,560.04 107,849.28 1,721,638.63 20% 344,327.73 247,915.96 2,313,882.32
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,312.79 m2 256,878.78 284,522.09 121,824.81 663,225.68 20% 132,645.14 95,504.50 891,375.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,253,148.65 594,673.07 273,026.17 3,120,847.89 624,169.59 449,402.10 4,194,419.58
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 159.89 L 51,164.80 8,465.58 846.56 60,476.94 20% 12,095.39 8,708.68 81,281.01
1000(1) Soil Poisoning
As Evaluated
As Submitted 51,164.80 8,465.58 846.56 60,476.94 12,095.39 8,708.68 81,281.01
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 147.30 m2 51,543.25 15,988.89 8,222.57 75,754.71 20% 15,150.94 10,908.68 101,814.33
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 522.79 m2 305,284.64 68,256.97 35,102.39 408,644.01 20% 81,728.80 58,844.74 549,217.55
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 356,827.89 84,245.86 43,324.96 484,398.72 96,879.74 69,753.42 651,031.88
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 180,165.84 34,446.00 3,444.60 218,056.44 20% 43,611.29 31,400.13 293,067.86
1010(4) Wooden Dooor
As Evaluated
As Submitted #REF! 34.93 m2 23,385.64 29,708.61 2,970.86 56,065.11 20% 11,213.02 8,073.38 75,351.51
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 73.44 m2 136,428.86 93,693.12 49,251.31 279,373.30 20% 55,874.66 40,229.76 375,477.72
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 32.64 m 2
28,216.81 4,684.66 2,462.57 35,364.03 20% 7,072.81 5,092.42 47,529.26
1005(5) Window Grill
As Evaluated
As Submitted #REF! 24.00 set 36,000.00 - - 36,000.00 20% 7,200.00 5,184.00 48,384.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 96.00 pc 6,361.92 - - 6,361.92 20% 1,272.38 916.12 8,550.42
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 18,600.00 4,909.20 490.92 24,000.12 20% 4,800.02 3,456.02 32,256.16
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 429,159.07 167,441.59 58,620.26 655,220.92 131,044.18 94,351.83 880,616.93
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 584.99 m2 111,571.43 33,642.33 3,364.23 148,577.99 20% 29,715.60 21,395.23 199,688.82
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 2,313.83 m2 188,727.30 153,105.73 15,310.57 357,143.60 20% 71,428.72 51,428.68 480,001.00
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 92.12 m 155,888.41 4,210.72 4,907.23 165,006.35 20% 33,001.27 23,760.91 221,768.53
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 332.94 m2 206,965.49 76,581.56 7,658.16 291,205.20 20% 58,241.04 41,933.55 391,379.79
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 434.28 m2 61,559.19 22,331.83 2,233.18 86,124.21 20% 17,224.84 12,401.89 115,750.94
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 824,033.23 338,202.14 39,913.44 1,202,148.80 240,429.77 173,109.43 1,615,688.00
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 2,553.91 m2 348,623.73 368,067.08 36,806.71 753,497.52 20% 150,699.50 108,503.64 1,012,700.66
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 133.27 m2 10,430.83 21,340.83 2,134.08 33,905.74 20% 6,781.15 4,882.43 45,569.32
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 62.73 m2 8,642.97 9,492.62 949.26 19,084.85 20% 3,816.97 2,748.22 25,650.04
1032(1)c Metal Painting
As Evaluated
As Submitted 367,697.53 398,900.52 39,890.05 806,488.11 161,297.62 116,134.29 1,083,920.02
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 434.28 m2 179,179.22 59,809.73 5,980.97 244,969.92 20% 48,993.98 35,275.67 329,239.57
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 32.90 m 6,943.45 755.52 75.55 7,774.51 20% 1,554.90 1,119.53 10,448.94
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 65.80 m 21,145.49 1,280.53 128.05 22,554.08 20% 4,510.82 3,247.79 30,312.69
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 3,535.91 kg 196,842.45 22,836.22 47,576.65 267,255.32 20% 53,451.06 38,484.77 359,191.15
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 5,170.61 kg 291,271.76 26,951.20 45,111.84 363,334.80 20% 72,666.96 52,320.21 488,321.97
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 65.80 m 12,505.29 1,584.41 158.44 14,248.14 20% 2,849.63 2,051.73 19,149.50
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 146.82 kg 5,839.62 2,594.52 259.45 8,693.59 20% 1,738.72 1,251.88 11,684.19
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 314.91 kg 12,900.99 5,564.90 556.49 19,022.38 20% 3,804.48 2,739.22 25,566.08
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 26.00 pc 4,266.08 895.60 0.90 5,162.57 20% 1,032.51 743.41 6,938.49
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 809,483.16 144,671.47 127,708.72 1,081,863.35 216,372.66 155,788.33 1,454,024.34
Sub-Total C.6
As Evaluated
As Submitted 2,838,365.67 1,141,927.17 310,303.99 4,290,596.84 858,119.36 617,845.98 5,766,562.18
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,531.75 4,288.65 428.87 23,249.27 20% 4,649.85 3,347.89 31,247.01
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 70,144.32 16,265.37 1,626.54 88,036.22 20% 17,607.24 12,677.22 118,320.68
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 162,352.47 18,830.48 1,883.05 183,066.00 20% 36,613.20 26,361.50 246,040.70
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 56,067.25 14,143.80 1,414.38 71,625.43 20% 14,325.09 10,314.06 96,264.58
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 16.00 units 9,707.33 3,674.24 367.42 13,748.99 20% 2,749.80 1,979.85 18,478.64
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 479,028.95 49,621.17 4,962.12 533,612.23 20% 106,722.45 76,840.16 717,174.84
SPL-2 Fire Protection System
As Evaluated
As Submitted 801,631.80 108,181.78 10,818.18 920,631.76 184,126.35 132,570.96 1,237,329.07
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 30,928.20 9,663.64 966.36 41,558.20 20% 8,311.64 5,984.38 55,854.22
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 63,995.82 7,780.56 778.06 72,554.44 20% 14,510.89 10,447.84 97,513.17
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 36,455.00 3,145.01 314.50 39,914.51 20% 7,982.90 5,747.69 53,645.10
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 60,585.00 5,432.29 543.23 66,560.52 20% 13,312.10 9,584.71 89,457.33
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 210,954.02 29,124.22 2,912.42 242,990.660 48,598.130 34,990.650 326,579.440
TOTAL OF PART E
As Evaluated
As Submitted 6,191,791.20 1,895,701.49 692,931.31 8,780,424.020 1,756,084.810 1,264,381.080 11,800,889.910
TOTAL OF PART III
As Evaluated
As Submitted 6,284,783.90 1,902,460.85 880,209.68 9,067,454.450 1,779,550.370 1,301,640.600 12,148,645.420
GRAND TOTAL
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 23.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 120 C.D.
Project Description : Complete construction of 2-Storey 4-Classroom School Buidling (with stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.50% 104,000.00
Part II Other General Requirements 1.96% 135,880.93
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.20% 152,645.07
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.68% 2,338,468.06
PART C FINISHING WORKS 46.56% 3,232,938.03
PART D PLUMBING/SANITARY WORKS 11.38% 790,140.37
PART E ELECTRICAL WORKS 2.74% 189,943.30

Total 100% 6,944,015.76

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,448,880.00 A. Total Direct Cost 6,944,015.76
2. Materials 4,819,676.82 B. OCM and Profit 1,360,520.55
3. Rental of Equipment 675,458.93 C. Value Added Tax (12%) 996,544.37
4. Provisional Sum / Daywork D. Total Construction Cost 9,301,080.68
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 1,360,520.55 E. Eng'g & Administrative Overhead, 0.5% 46,739.10
6. Value Added Tax (12%) 996,544.37 F. RROW Acquisition
7. EAO, 0.5 % 46,739.10 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 9,347,819.78 H. TOTAL ESTIMATED COST 9,347,819.78
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.00 mo - - 104,000.00 104,000.00 8% 8,320.00 13,478.40 125,798.40
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 104,000.00 104,000.00 8,320.00 13,478.40 125,798.40
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 76,734.52 4,672.64 - 81,407.16 8% 6,512.57 10,550.37 98,470.10
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 50,281.01 50,281.01 8% 4,022.48 6,516.42 60,819.91
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 79,916.86 5,591.20 50,372.87 135,880.93 11,373.60 17,670.55 164,925.08
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 196.98 m3 - 2,651.06 43,374.18 46,025.23 20% 9,205.05 6,627.63 61,857.91
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 105.37 m3 - 2,882.36 13,620.11 16,502.47 20% 3,300.49 2,376.36 22,179.32
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 111.83 m3 40,626.44 3,059.07 14,455.13 58,140.64 20% 11,628.13 8,372.25 78,141.02
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 33.92 m3 21,868.94 7,608.54 2,499.25 31,976.73 20% 6,395.35 4,604.65 42,976.73
804(4) Gravel Fill
As Evaluated
As Submitted 62,495.38 16,201.03 73,948.67 152,645.07 30,529.02 21,980.89 205,154.98
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 151.93 m3 499,090.05 23,851.38 32,731.11 555,672.54 20% 111,134.51 80,016.85 746,823.90
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 27,248.42 kg 1,006,314.81 209,940.79 81,282.16 1,297,537.76 20% 259,507.55 186,845.44 1,743,890.75
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 960.52 m2 187,948.73 208,174.31 89,134.72 485,257.76 20% 97,051.55 69,877.12 652,186.43
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,693,353.58 441,966.47 203,148.00 2,338,468.06 467,693.61 336,739.41 3,142,901.08
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 115.60 L 36,992.00 6,120.59 612.06 43,724.65 20% 8,744.93 6,296.35 58,765.93
1000(1) Soil Poisoning
As Evaluated
As Submitted 36,992.00 6,120.59 612.06 43,724.65 8,744.93 6,296.35 58,765.93
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 129.91 m2 45,458.14 14,101.26 7,251.83 66,811.23 20% 13,362.25 9,620.82 89,794.30
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 399.98 m2 233,569.41 52,222.55 26,856.39 312,648.35 20% 62,529.67 45,021.36 420,199.38
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 279,027.54 66,323.81 34,108.22 379,459.58 75,891.92 54,642.18 509,993.68
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 133,071.00 26,408.60 2,640.86 162,120.46 20% 32,424.09 23,345.35 217,889.90
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 24.05 m2 16,101.48 20,454.97 2,045.50 38,601.94 20% 7,720.39 5,558.68 51,881.01
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 48.96 m2 90,952.58 62,462.08 32,834.21 186,248.86 20% 37,249.77 26,819.84 250,318.47
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 21.76 m 2
18,811.20 3,123.10 1,641.71 23,576.02 20% 4,715.20 3,394.95 31,686.17
1005(5) Window Grill
As Evaluated
As Submitted #REF! 20.00 set 30,000.00 - - 30,000.00 20% 6,000.00 4,320.00 40,320.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 80.00 pc 5,301.60 - - 5,301.60 20% 1,060.32 763.43 7,125.35
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 12,400.00 3,272.80 327.28 16,000.08 20% 3,200.02 2,304.01 21,504.11
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 306,637.85 115,721.55 39,489.56 461,848.96 92,369.79 66,506.26 620,725.01
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 424.17 m2 80,899.25 24,393.70 2,439.37 107,732.32 20% 21,546.46 15,513.45 144,792.23
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,783.22 m2 145,448.15 117,995.35 11,799.54 275,243.04 20% 55,048.61 39,635.00 369,926.65
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 73.42 m 124,243.67 3,355.96 3,911.08 131,510.71 20% 26,302.14 18,937.54 176,750.39
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 237.86 m2 147,860.91 54,711.63 5,471.16 208,043.70 20% 41,608.74 29,958.29 279,610.73
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 315.48 m2 44,719.29 16,222.82 1,622.28 62,564.39 20% 12,512.88 9,009.27 84,086.54
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 642,492.68 265,009.43 31,683.50 939,185.61 187,837.13 135,242.72 1,262,265.46
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,946.86 m2 265,757.84 280,579.61 28,057.96 574,395.41 20% 114,879.08 82,712.94 771,987.43
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 104.49 m2 8,178.26 16,732.22 1,673.22 26,583.71 20% 5,316.74 3,828.05 35,728.50
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 50.14 m2 6,908.31 7,587.44 758.74 15,254.49 20% 3,050.90 2,196.65 20,502.04
1032(1)c Metal Painting
As Evaluated
As Submitted 280,844.41 304,899.27 30,489.93 616,233.61 123,246.72 88,737.64 828,217.97
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 315.48 m2 130,163.63 43,448.40 4,344.84 177,956.87 20% 35,591.37 25,625.79 239,174.03
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 23.90 m 5,044.02 548.84 54.88 5,647.75 20% 1,129.55 813.28 7,590.58
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 47.80 m 15,361.01 930.24 93.02 16,384.27 20% 3,276.85 2,359.33 22,020.45
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 2,271.38 kg 126,446.66 14,669.42 30,562.05 171,678.12 20% 34,335.62 24,721.65 230,735.39
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 3,687.15 kg 207,705.22 19,218.84 32,169.15 259,093.20 20% 51,818.64 37,309.42 348,221.26
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 47.80 m 9,084.39 1,150.98 115.10 10,350.47 20% 2,070.09 1,490.47 13,911.03
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 101.34 kg 4,030.70 1,790.82 179.08 6,000.60 20% 1,200.12 864.09 8,064.81
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 214.42 kg 8,784.19 3,789.10 378.91 12,952.21 20% 2,590.44 1,865.12 17,407.77
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 18.00 pc 2,953.44 620.03 0.62 3,574.09 20% 714.82 514.67 4,803.58
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 588,162.07 108,565.52 95,758.02 792,485.62 158,497.10 114,117.94 1,065,100.66
Sub-Total C.6
As Evaluated s
As Submitted 2,134,156.56 866,640.17 232,141.28 3,232,938.03 646,587.59 465,543.09 4,345,068.71
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,103.75 4,217.17 421.72 22,742.64 20% 4,548.53 3,274.94 30,566.11
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 62,014.42 14,379.53 1,437.95 77,831.90 20% 15,566.38 11,207.79 104,606.07
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 161,176.47 18,715.66 1,871.57 181,763.70 20% 36,352.74 26,173.97 244,290.41
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 46,716.75 12,022.23 1,202.22 59,941.20 20% 11,988.24 8,631.53 80,560.97
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 12.00 units 7,280.50 2,755.68 275.57 10,311.74 20% 2,062.35 1,484.89 13,858.98
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 385,396.15 40,781.29 4,078.13 430,255.57 20% 86,051.11 61,956.80 578,263.48
SPL-2 Fire Protection System
As Evaluated
As Submitted 686,487.77 94,229.64 9,422.96 790,140.37 158,028.07 113,780.20 1,061,948.64
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 25,137.80 8,457.60 845.76 34,441.16 20% 6,888.23 4,959.53 46,288.92
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 52,894.17 6,115.24 611.52 59,620.93 20% 11,924.19 8,585.41 80,130.53
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 24,259.70 2,573.19 257.32 27,090.21 20% 5,418.04 3,900.99 36,409.24
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 41,985.00 4,002.74 400.27 46,388.01 20% 9,277.60 6,679.87 62,345.48
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 163,266.67 24,251.49 2,425.15 189,943.300 37,988.660 27,351.830 255,283.790
TOTAL OF PART E
As Evaluated
As Submitted 4,739,759.96 1,443,288.80 521,086.07 6,704,134.830 1,340,826.950 965,395.420 9,010,357.200
TOTAL OF PART III
As Evaluated
As Submitted 4,819,676.82 1,448,880.00 675,458.93 6,944,015.760 1,360,520.550 996,544.370 9,301,080.680
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING Appropriation :


( 9.5m x 14.00m ) Source of Fund :
Project ID : Target Start Date :
Location : Total Project Duration : 115 C.D.
Project Description : Complete construction of 2-Storey 2-Classroom School Buidling (with stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 2.05% 99,666.67
Part II Other General Requirements 2.20% 107,225.89
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.01% 97,854.73
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 31.95% 1,556,092.30
PART C FINISHING WORKS 43.89% 2,137,714.37
PART D PLUMBING/SANITARY WORKS 15.19% 739,573.28
PART E ELECTRICAL WORKS 2.71% 132,171.50

Total 100% 4,870,298.74

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 991,254.38 A. Total Direct Cost 4,870,298.74
2. Materials 3,400,548.90 B. OCM and Profit 949,735.78
3. Rental of Equipment 478,495.46 C. Value Added Tax (12%) 698,404.14
4. Provisional Sum / Daywork D. Total Construction Cost 6,518,438.66
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 949,735.78 E. Eng'g & Administrative Overhead, 0.5% 32,755.97
6. Value Added Tax (12%) 698,404.14 F. RROW Acquisition
7. EAO, 0.5% 32,755.97 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 6,551,194.63 H. TOTAL ESTIMATED COST 6,551,194.63
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 3.83 mo - - 99,666.67 99,666.67 8% 7,973.33 12,916.80 120,556.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 99,666.67 99,666.67 7,973.33 12,916.80 120,556.80
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 63,384.94 4,672.64 - 68,057.58 8% 5,444.61 8,820.26 82,322.45
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 34,975.55 34,975.55 8% 2,798.04 4,532.83 42,306.42
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 66,567.28 5,591.20 35,067.40 107,225.89 9,081.20 13,956.85 130,263.94
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 144.01 m3 - 1,938.16 31,710.40 33,648.56 20% 6,729.71 4,845.39 45,223.66
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 66.34 m3 - 1,814.71 8,575.10 10,389.81 20% 2,077.96 1,496.13 13,963.90
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 64.02 m3 23,257.67 1,751.25 8,275.22 33,284.13 20% 6,656.83 4,792.92 44,733.88
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 21.78 m3 14,042.02 4,885.44 1,604.77 20,532.23 20% 4,106.45 2,956.64 27,595.32
804(4) Gravel Fill
As Evaluated
As Submitted 37,299.69 10,389.55 50,165.49 97,854.73 19,570.95 14,091.08 131,516.76
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 102.63 m3 337,139.55 16,111.81 22,110.14 375,361.50 20% 75,072.30 54,052.06 504,485.86
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 18,342.24 kg 677,399.56 141,321.38 54,714.99 873,435.92 20% 174,687.18 125,774.77 1,173,897.87
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 608.26 m2 119,020.63 131,828.70 56,445.55 307,294.88 20% 61,458.98 44,250.46 413,004.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,133,559.73 289,261.89 133,270.69 1,556,092.30 311,218.46 224,077.29 2,091,388.05
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 75.31 L 24,099.20 3,987.39 398.74 28,485.32 20% 5,697.06 4,101.89 38,284.27
1000(1) Soil Poisoning
As Evaluated
As Submitted 24,099.20 3,987.39 398.74 28,485.32 5,697.06 4,101.89 38,284.27
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 112.48 m2 39,359.03 12,209.30 6,278.85 57,847.18 20% 11,569.44 8,329.99 77,746.61
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 227.17 m2 132,656.54 29,659.97 15,253.18 177,569.69 20% 35,513.94 25,570.04 238,653.67
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 172,015.57 41,869.27 21,532.03 235,416.87 47,083.38 33,900.03 316,400.28
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 85,976.15 19,519.40 1,951.94 107,447.49 20% 21,489.50 15,472.44 144,409.43
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 13.71 m2 9,178.85 11,660.61 1,166.06 22,005.51 20% 4,401.10 3,168.79 29,575.40
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 24.48 m2 45,476.29 31,231.04 16,417.10 93,124.43 20% 18,624.89 13,409.92 125,159.24
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 10.88 m 2
9,405.60 1,561.55 820.86 11,788.01 20% 2,357.60 1,697.47 15,843.08
1005 (5) Window Grill
As Evaluated
As Submitted #REF! 16.00 set 24,000.00 - - 24,000.00 20% 4,800.00 3,456.00 32,256.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 64.00 pc 4,241.28 - - 4,241.28 20% 848.26 610.74 5,700.28
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 6,200.00 1,636.40 163.64 8,000.04 20% 1,600.01 1,152.01 10,752.06
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 184,478.17 65,609.00 20,519.60 270,606.76 54,121.36 38,967.37 363,695.49
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 263.35 m2 50,227.07 15,145.06 1,514.51 66,886.64 20% 13,377.33 9,631.68 89,895.65
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,252.61 m2 102,169.00 82,884.98 8,288.50 193,342.49 20% 38,668.50 27,841.32 259,852.31
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 55.82 m 94,460.39 2,551.48 2,973.53 99,985.40 20% 19,997.08 14,397.90 134,380.38
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 142.77 m2 88,750.12 32,839.40 3,283.94 124,873.45 20% 24,974.69 17,981.78 167,829.92
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 196.68 m2 27,879.39 10,113.81 1,011.38 39,004.58 20% 7,800.92 5,616.66 52,422.16
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 462,807.37 191,864.70 23,511.92 678,184.01 135,636.82 97,658.51 911,479.34
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,339.81 m2 182,891.94 193,092.14 19,309.21 395,293.30 20% 79,058.66 56,922.24 531,274.20
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 75.71 m2 5,925.70 12,123.61 1,212.36 19,261.67 20% 3,852.33 2,773.68 25,887.68
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 37.55 m2 5,173.66 5,682.25 568.23 11,424.14 20% 2,284.83 1,645.08 15,354.05
1032(1)c Metal Painting
As Evaluated
As Submitted 193,991.30 210,898.01 21,089.80 425,979.11 85,195.82 61,341.00 572,515.93
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 196.68 m2 81,148.04 27,087.08 2,708.71 110,943.82 20% 22,188.76 15,975.91 149,108.49
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 14.90 m 3,144.60 342.16 34.22 3,520.98 20% 704.20 507.02 4,732.20
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 29.80 m 9,576.53 579.94 57.99 10,214.46 20% 2,042.89 1,470.88 13,728.23
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 1,008.85 kg 56,162.21 6,515.53 13,574.36 76,252.09 20% 15,250.42 10,980.30 102,482.81
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 2,143.69 kg 120,758.74 11,173.73 18,702.98 150,635.45 20% 30,127.09 21,691.50 202,454.04
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 29.80 m 5,663.49 717.56 71.76 6,452.81 20% 1,290.56 929.20 8,672.57
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 55.85 kg 2,221.38 986.95 98.69 3,307.02 20% 661.40 476.21 4,444.63
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 113.93 kg 4,667.40 2,013.30 201.33 6,882.03 20% 1,376.41 991.01 9,249.45
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 10.00 pc 1,640.80 344.46 0.34 1,985.60 20% 397.12 285.93 2,668.65
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 363,572.00 72,159.56 63,310.74 499,042.30 99,808.45 71,862.08 670,712.83
Sub-Total C.6
As Evaluated
As Submitted 1,400,963.60 586,387.94 150,362.84 2,137,714.37 427,542.89 307,830.88 2,873,088.14
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 17,675.75 3,788.31 378.83 21,842.89 20% 4,368.58 3,145.38 29,356.85
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 53,018.02 12,257.96 1,225.80 66,501.77 20% 13,300.35 9,576.25 89,378.37
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 160,000.47 18,543.43 1,854.34 180,398.24 20% 36,079.65 25,977.35 242,455.24
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 32,018.30 8,368.42 836.84 41,223.55 20% 8,244.71 5,936.19 55,404.45
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 8.00 units 4,853.66 1,837.12 183.71 6,874.50 20% 1,374.90 989.93 9,239.33
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 371,746.15 39,720.51 3,972.05 415,438.71 20% 83,087.74 59,823.17 558,349.62
SPL-2 Fire Protection System
As Evaluated
As Submitted 645,112.09 85,873.81 8,587.38 739,573.28 147,914.65 106,498.55 993,986.48
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 19,023.20 2,325.32 232.53 21,581.05 20% 4,316.21 3,107.67 29,004.93
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 37,258.20 3,747.40 374.74 41,380.34 20% 8,276.07 5,958.77 55,615.18
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 18,390.10 2,001.37 200.14 20,591.61 20% 4,118.32 2,965.19 27,675.12
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 23,385.00 2,573.19 257.32 26,215.51 20% 5,243.10 3,775.03 35,233.64
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 117,046.50 13,750.00 1,375.00 132,171.500 26,434.300 19,032.690 177,638.490
TOTAL OF PART E
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF PART III
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 3,400,548.90 991,254.38 478,495.46 4,870,298.740 949,735.780 698,404.140 6,518,438.660
GRAND TOTAL
As Evaluated

You might also like