Cagmanaba Hs ABC, Dupa, Pow, Gantt
Cagmanaba Hs ABC, Dupa, Pow, Gantt
Cagmanaba Hs ABC, Dupa, Pow, Gantt
foreman leadman skilled semi skilled unskilled driver heavy High skilled light skilled
97.25 89.15 70.35 64.95 54.14 70.35 80.95 80.95 75.75
2009 ACEL RATES
(Minimum Operation = 8 hrs. per day)
Source: BORONGAN
LOADING: Free
UNLOADING
Manual unloading:
Rate of Manual unloading = 0.50 min. per bag
No. of bags/truck = 10,000.00 kg. / 40.00 kg. per bag
= 250.00 bags
Time = 250.00 bags x 0.50 min. per bag
= 125.00 min.
= 2.08 hrs.
RETURN TRIP
Distance = 155.00 km.
Speed = 55.00 kph
Hauling Time = 2.82 hrs.
300.00 + 49.00
APPROVED BY:
SAND
Source: TACLOBAN
LOADING: Free
UNLOADING
Time: 10.00 min.
= 0.17 hr.
RETURN TRIP
Distance = 241.00 km.
Speed = 55.00 kph
Hauling Time = 4.38 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 8.03 + 0.17 +
= 12.58 hrs.
= 1.57 days (8 hrs work/day)
635.00 + 2,457.00
GRAVEL,G1
Source: TACLOBAN
BASIC PRICE: 800.00 per cu.m.
LOADING: Free
UNLOADING
Time: 10 min.
= 0.166666666666667 hr.
RETURN TRIP
Distance = 241 km.
Speed = 55 kph
Hauling Time = 4.38181818181818 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 8.03333333333333 + 0.166666667 +
= 12.5818181818182 hrs.
= 1.57272727272727 days (8 hrs work/day)
800.00 + 2,457.00
Source: BORONGAN
LOADING: Free
UNLOADING
Manual Unloading: Free
Time = 4.00 hrs.
RETURN TRIP
Distance = 155.00 km.
Speed = 55.00 kph
Hauling Time = 2.82 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 4.43 + 4.00 +
= 11.25 hrs.
= 1.41 days (8 hrs work/day)
50.00 + 3.00
Source: BORONGAN
LOADING: Free
UNLOADING
Manual Unloading: Free
Time = 2.00 hrs.
RETURN TRIP
Distance = 155.00 km.
Speed = 55.00 kph
Hauling Time = 2.82 hrs.
TOTAL TIME = HAULING + UNLOADING +
= 4.43 + 2.00 +
= 9.25 hrs.
= 1.16 days (8 hrs work/day)
1,400.00 + 84.00
MAT'L. COST = 1,484.00
RETURN TRIP
2.82
RETURN TRIP
4.38
RETURN TRIP
4.381818181818
RETURN TRIP
2.82
0.05
RETURN TRIP
2.82
Republic of the Philippines
MUNICIPALITY OF JIPAPAD
OFFICE OF THE MUNICIPAL ENGINEER
Jipapad, Eastern Samar
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 13.48% 128.03 m3 672,167.61 20,099.64 14,210.86 706,478.10 20% 141,295.62 42,388.69 890,162.41
901(1) Lean Concrete 1.12% 3.71 m3 14,961.38 33,374.55 10,432.46 58,768.38 20% 11,753.68 3,526.10 74,048.16
902(1)a Reinforcing Steel, Grade 40 7.62% 5,251.86 kgs 343,081.69 40,463.98 15,666.32 399,212.00 20% 79,842.40 23,952.72 503,007.12
902(1)b Reinforcing Steel, Grade 60 14.06% 9,437.91 kgs 636,358.16 72,716.23 28,153.33 737,227.71 20% 147,445.54 44,233.66 928,906.92
903(2) Forms and Falseworks 7.52% 795.04 m2 148,161.32 172,310.56 73,778.81 394,250.69 20% 78,850.14 23,655.04 496,755.87
TOTAL OF PART B 1,814,730.16 338,964.95 142,241.77 2,295,936.88 459,187.38 137,756.21 2,892,880.47
PART C FINISHING WORKS
C.1 Termite Control Works and Waterproofing
1000(1) Soil Poisoning 0.08% 9.00 L 3,780.00 476.52 47.65 4,304.17 20% 860.83 258.25 5,423.25
1016(1)a Waterproofing 1.28% 117.99 m2 37,166.85 27,095.22 2,709.52 66,971.60 20% 13,394.32 4,018.30 84,384.22
Sub-Total C.1 40,946.85 27,571.74 2,757.17 71,275.76 14,255.15 4,276.55 89,807.47
C.2. Masonry Works
DIRECT COST TOTAL MARK-UP VAT TOTAL COST
ITEM NO. ITEM DESCRIPTION % QUANTITY UNIT
MATERIAL LABOR EQUIPMENT TOTAL % VALUE 5%
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 1.06% 108.00 m2 37,791.38 11,723.01 6,028.77 55,543.17 20% 11,108.63 3,332.59 69,984.39
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 2.03% 135.82 m2 79,312.46 17,733.05 9,119.54 106,165.05 20% 21,233.01 6,369.90 133,767.97
1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 0.35% 7.00 set 14,700.00 3,214.96 321.50 18,236.46 20% 3,647.29 1,094.19 22,977.94
1010(2)b Wooden Doors (Wood Panel) 1.19% 13.23 m2 59,251.48 3,038.14 303.81 62,593.43 20% 12,518.69 3,755.61 78,867.73
Sub-Total C.3 235,394.81 6,253.10 625.31 242,273.22 48,454.64 14,536.40 305,264.26
C.4 Finishing Works
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 4.17% 240.00 m2 157,951.20 55,203.86 5,520.39 218,675.45 20% 43,735.09 13,120.53 275,531.07
1018(1) Glazed Tiles and Trims 7.41% 249.90 m2 237,933.94 136,714.52 13,671.45 388,319.91 20% 77,663.98 23,299.19 489,283.08
1018(2) Unglazed Tiles 2.54% 90.00 m2 95,285.22 34,465.85 3,446.58 133,197.65 20% 26,639.53 7,991.86 167,829.04
1021(1)c Plain Cement Finish with floor hardener 0.18% 23.40 m2 7,916.69 1,345.72 134.57 9,396.98 20% 1,879.40 563.82 11,840.19
1027(1) Plain Cement Plaster Finish 1.83% 622.66 m2 50,787.20 41,201.30 4,120.13 96,108.63 20% 19,221.73 5,766.52 121,096.88
1053(2)a1 38 mm Ø Stainless Steel Pipe Railings 0.83% 108.80 m 32,870.89 4,973.14 5,795.77 43,639.80 20% 8,727.96 2,618.39 54,986.16
1038(1) Reflective Insulation 0.45% 120.00 m2 17,010.00 6,170.72 617.07 23,797.79 20% 4,759.56 1,427.87 29,985.22
Sub-Total C.4 599,755.13 280,075.11 33,305.97 913,136.21 182,627.24 54,788.18 1,150,551.64
C.5 Painting Works
1032(1)a Masonry/Concrete Painting 4.21% 747.63 m2 102,055.89 107,747.72 10,774.77 220,578.39 20% 44,115.68 13,234.70 277,928.76
1032(1)b Wood Painting 0.13% 26.46 m2 2,070.98 4,237.10 423.71 6,731.79 20% 1,346.36 403.91 8,482.06
Sub-Total C.5 104,126.87 111,984.82 11,198.48 227,310.18 45,462.04 13,638.61 286,410.82
C.6 Roof Framing and Roofing Works
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk 2.44% 231.58 m2 92,764.46 31,893.56 3,189.36 127,847.38 20% 25,569.48 7,670.84 161,087.70
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) 0.15% 32.32 m 6,953.49 742.20 74.22 7,769.90 20% 1,553.98 466.19 9,790.07
1003(5) Roof Frame (Wood) 3.97% 1,701.22 bd.ft. 94,706.10 36,767.88 76,601.68 208,075.66 20% 41,615.13 12,484.54 262,175.34
1047(6) Metal Structure Accessories, Steel Plates 1.35% 957.00 kgs 52,252.20 16,911.54 1,691.15 70,854.90 20% 14,170.98 4,251.29 89,277.16
1047(7)b Metal Structure Accessories, Sag Rods 0.23% 232.30 kgs 7,805.31 4,105.08 - 11,910.39 20% 2,382.08 714.62 15,007.09
1047(4) Metal Structure Accessories, Cross Bracing 0.70% 636.25 kgs 25,306.19 11,243.43 - 36,549.62 20% 7,309.92 2,192.98 46,052.52
1047(3)a Metal Structure Accessories (Bolts) 0.23% 340.00 ea 4,250.00 7,807.76 - 12,057.76 20% 2,411.55 723.47 15,192.78
1047(3)c Metal Structure Accessories, Turn Buckle 0.10% 32.00 ea 4,352.00 1,102.27 - 5,454.27 20% 1,090.85 327.26 6,872.39
Sub-Total C.6 288,389.75 110,573.73 81,556.41 480,519.89 96,103.98 28,831.19 605,455.06
TOTAL OF PART C 1,385,717.26 565,914.57 144,591.66 2,096,223.49 419,244.70 125,773.42 2,641,241.60
DIRECT COST TOTAL MARK-UP VAT TOTAL COST
ITEM NO. ITEM DESCRIPTION % QUANTITY UNIT
MATERIAL LABOR EQUIPMENT TOTAL % VALUE 5%
PART D PLUMBING/SANITARY WORKS
1001(8) Sewer Line Works 0.68% 1.00 l.s. 16,040.00 3,788.31 16,040.00 35,868.31 20% 7,173.66 2,152.10 45,194.07
1002(6) Cold Water Line Works 0.14% 1.00 l.s. 6,056.00 1,358.07 135.81 7,549.88 20% 1,509.98 452.99 9,512.85
1001(9) Downspout/Storm Drain 1.70% 1.00 l.s. 75,856.38 12,257.96 1,225.80 89,340.14 20% 17,868.03 5,360.41 112,568.57
1002(5) Sanitary/Plumbing Fixtures 3.06% 1.00 l.s. 140,052.80 18,543.43 1,854.34 160,450.57 20% 32,090.11 9,627.03 202,167.72
1001(6)b1 Catch basin 0.44% 3.00 units 19,859.15 2,755.68 275.57 22,890.39 20% 4,578.08 1,373.42 28,841.89
1001(11) Septic Vault 0.22% 3.75 sq.m 9,195.44 1,556.96 800.70 11,553.10 20% 2,310.62 693.19 14,556.91
TOTAL OF PART D 267,059.76 40,260.41 20,332.21 327,652.39 65,530.48 19,659.14 412,842.00
PART E ELECTRICAL WORKS
1100(19) Conduits, Boxes, and Fittings 1.35% 1.00 l.s. 56,613.59 12,805.44 1,280.54 70,699.57 20% 14,139.91 4,241.97 89,081.46
1101(18) Wires and Wiring Devices 2.38% 1.00 l.s. 110,332.95 12,919.40 1,291.94 124,544.29 20% 24,908.86 7,472.66 156,925.81
1102(21) Panel Board 0.39% 1.00 l.s. 18,390.10 2,001.37 200.14 20,591.61 20% 4,118.32 1,235.50 25,945.43
1103(1) Lighting Fixtures 0.73% 1.00 l.s. 30,245.00 7,433.66 743.37 38,422.03 20% 7,684.41 2,305.32 48,411.75
1208(1) Fire Alarm System (Emergency Lights) 0.34% 1.00 l.s. 13,890.00 3,759.12 375.91 18,025.03 20% 3,605.01 1,081.50 22,711.54
TOTAL OF PART E 229,471.64 38,918.99 3,891.90 272,282.53 54,456.51 16,336.95 343,075.98
TOTAL OF PART III 3,741,211.12 1,001,581.47 389,229.24 5,132,021.83 1,026,404.37 307,921.30 6,466,347.50
GRAND TOTAL 3,786,126.96 1,042,876.03 427,719.40 5,256,722.40 1,033,903.53 314,531.29 6,605,157.22
Republic of the Philippines
MUNICIPALITY OF JIPAPAD
OFFICE OF THE MUNICIPAL ENGINEER
Jipapad, Eastern Samar
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk 231.58 m2 127,847.38 12.00% 8.00% 20.00% 25,569.48 7,670.84 33,240.32 161,087.70 695.60
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) 32.32 m 7,769.90 12.00% 8.00% 20.00% 1,553.98 466.19 2,020.17 9,790.07 302.91
1003(5) Roof Frame (Wood) 1,701.22 bd.ft. 208,075.66 12.00% 8.00% 20.00% 41,615.13 12,484.54 54,099.67 262,175.34 154.11
1047(6) Metal Structure Accessories, Steel Plates 957.00 kgs 70,854.90 12.00% 8.00% 20.00% 14,170.98 4,251.29 18,422.27 89,277.16 93.29
1047(7)b Metal Structure Accessories, Sag Rods 232.30 kgs 11,910.39 12.00% 8.00% 20.00% 2,382.08 714.62 3,096.70 15,007.09 64.60
1047(4) Metal Structure Accessories, Cross Bracing 636.25 kgs 36,549.62 12.00% 8.00% 20.00% 7,309.92 2,192.98 9,502.90 46,052.52 72.38
1047(3)a Metal Structure Accessories (Bolts) 340.00 ea 12,057.76 12.00% 8.00% 20.00% 2,411.55 723.47 3,135.02 15,192.78 44.68
1047(3)c Metal Structure Accessories, Turn Buckle 32.00 ea 5,454.27 12.00% 8.00% 20.00% 1,090.85 327.26 1,418.11 6,872.39 214.76
TOTAL OF PART C 2,096,223.49 419,244.70 125,773.42 545,018.12 2,641,241.60
PART D PLUMBING/SANITARY WORKS
1001(8) Sewer Line Works 1.00 l.s. 35,868.31 12.00% 8.00% 20.00% 7,173.66 2,152.10 9,325.76 45,194.07 45,194.07
1002(6) Cold Water Line Works 1.00 l.s. 7,549.88 12.00% 8.00% 20.00% 1,509.98 452.99 1,962.97 9,512.85 9,512.85
1001(9) Downspout/Storm Drain 1.00 l.s. 89,340.14 12.00% 8.00% 20.00% 17,868.03 5,360.41 23,228.44 112,568.57 112,568.57
1002(5) Sanitary/Plumbing Fixtures 1.00 l.s. 160,450.57 12.00% 8.00% 20.00% 32,090.11 9,627.03 41,717.14 202,167.72 202,167.72
1001(6)b1 Catch basin 3.00 units 22,890.39 12.00% 8.00% 20.00% 4,578.08 1,373.42 5,951.50 28,841.89 9,613.96
1001(11) Septic Vault 3.75 sq.m 11,553.10 12.00% 8.00% 20.00% 2,310.62 693.19 3,003.81 14,556.91 3,881.84
TOTAL OF PART D 327,652.39 65,530.48 19,659.14 85,189.62 412,842.00
PART E ELECTRICAL WORKS
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 70,699.57 12.00% 8.00% 20.00% 14,139.91 4,241.97 18,381.88 89,081.46 89,081.46
1101(18) Wires and Wiring Devices 1.00 l.s. 124,544.29 12.00% 8.00% 20.00% 24,908.86 7,472.66 32,381.52 156,925.81 156,925.81
1102(21) Panel Board 1.00 l.s. 20,591.61 12.00% 8.00% 20.00% 4,118.32 1,235.50 5,353.82 25,945.43 25,945.43
1103(1) Lighting Fixtures 1.00 l.s. 38,422.03 12.00% 8.00% 20.00% 7,684.41 2,305.32 9,989.73 48,411.75 48,411.75
1208(1) Fire Alarm System (Emergency Lights) 1.00 l.s. 18,025.03 12.00% 8.00% 20.00% 3,605.01 1,081.50 4,686.51 22,711.54 22,711.54
TOTAL OF PART E 272,282.53 54,456.51 16,336.95 70,793.46 343,075.98
TOTAL OF PART III 5,132,021.83 1,026,404.37 307,921.30 1,334,325.67 6,466,347.50
TOTAL 5,256,722.40 1,033,903.53 314,531.29 1,348,434.82 6,605,157.22
SUB-PROJECT TITLE : Construction of Health Station at Brgy. Cagmanaba TOTAL PROJECT COST: 6,605,157.22
LOCATION:
LOCATION Brgy. Cagmanaba, Jipapad, Eastern Samar SUB-PROJECT DURATION: 264.00 CD
Prepared by:
WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.11% 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.96% 1.96% 1.96% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.77% 0.51% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.53% 0.53% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 1.35% 0.68% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.25% 0.06% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.00% 0.25% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.20% 0.30% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.35% 0.00% 0.00%
1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.96% 0.24% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.67% 1.00% 1.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2.07% 2.00% 1.96% 0.77% 1.04% 1.88% 4.09% 1.87% 1.00% 1.00%
44.69% 46.69% 48.65% 49.42% 50.46% 52.34% 56.43% 58.30% 59.30% 60.30%
136,682.47 131,953.15 129,588.49 50,630.53 68,745.88 124,170.84 270,418.38 123,520.17 66,127.46 66,127.46
2,951,879.25 3,083,832.39 3,213,420.88 3,264,051.41 3,332,797.29 3,456,968.13 3,727,386.51 3,850,906.69 3,917,034.14 3,983,161.60
48 54 60 66 72 78 84 90 96 102
MONTH 5 MONTH 6 MONTH 7 MONTH 8 MONTH 9 MONTH 10 MONTH 11
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00% 1.00% 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.97% 1.93% 1.93% 1.93% 0.64% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 1.27% 1.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.67% 1.00% 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.83% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.19% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.87% 1.05% 0.52% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.32% 2.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.81% 0.54% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.08% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.20% 0.50% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.09% 0.14% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.34% 0.34% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.14% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.70% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.39% 1.67% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 0.22% 0.00% 0.00% 0.00%
1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 0.00% 0.00% 0.00%
1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.90% 0.45% 0.00%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.79% 1.58%
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.39% 0.00%
1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.55% 0.18%
1.00 1.00 1.00 1.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.34%
1.00 1.00 1.00
1.00% 1.00% 2.92% 3.20% 1.93% 1.93% 1.31% 1.00% 1.77% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.96% 1.05% 1.99% 2.65% 0.81% 1.08% 1.20% 3.66% 2.11% 0.90% 2.18% 2.11%
60.30% 61.30% 64.22% 67.42% 69.36% 71.29% 72.60% 73.60% 75.37% 75.93% 76.49% 77.05% 77.61% 78.17% 78.73% 79.30% 80.26% 81.31% 83.30% 85.95% 86.76% 87.84% 89.04% 92.69% 94.80% 95.70% 97.89% 100.00%
66,127.46 66,127.46 192,637.97 211,553.59 127,639.07 127,639.07 86,581.58 66,052.84 116,814.63 37,057.17 37,057.17 37,057.17 37,057.17 37,057.17 37,057.17 37,057.17 63,707.52 69,037.59 131,700.64 174,783.56 53,566.30 71,555.73 79,122.57 241,480.97 139,251.15 59,387.64 144,256.66 139,431.68
3,983,161.60 4,049,289.06 4,241,927.03 4,453,480.62 4,581,119.68 4,708,758.75 4,795,340.33 4,861,393.17 4,978,207.80 5,015,264.97 5,052,322.14 5,089,379.31 5,126,436.48 5,163,493.64 5,200,550.81 5,237,607.98 5,301,315.50 5,370,353.08 5,502,053.73 5,676,837.29 5,730,403.59 5,801,959.31 5,881,081.88 6,122,562.85 6,261,814.01 6,321,201.64 6,465,458.31 6,604,889.99
102 108 114 120 126 132 138 144 150 156 162 168 174 180 186 192 198 204 210 216 222 228 234 240 246 252 258 264
Quantity Derivation
PART II
B.1 Temporary Facility
Quantity : 1.00 l.s.
L W H Q Vol/Area Unit
Building Area 10.00 12 1 120 m2
Total 120 m2
L W H Q Vol/Area Unit
Building Area 10.00 12.00 1 120.00 m2
Total 120 m2
L W H Q Vol/Area Unit
F1 1.50 1.50 1.50 22 74.25 m3
FTB 0.25 0.30 228.00 1 17.10 m3
WF1 0.30 0.60 3.00 1 0.54 m3
Total 91.89 m3
L W H Q Vol/Area Unit
F1 1.50 1.50 0.30 22 14.85 m3
C1 0.40 0.40 1.20 22 4.22 m3
FTB 0.25 0.30 228.00 1 17.10 m3
WF1 0.30 0.60 3.00 1 0.54 m3
L W H Q Vol/Area Unit
Building Area 10.00 12 0.6 1 72.00 m3
Frontage 3.00 1.65 0.6 1 2.97 m3
Total 74.97 m3
L W H Q Vol/Area Unit
Building Area 10.00 12 0.1 1 12.00 m3
Frontage 3.00 1.65 0.1 1 0.50 m3
Total 12.495 m3
L W H Q Vol/Area Unit
Footing (F1) 1.50 1.50 0.30 22.00 14.85 m3
Slab on fill (Interior of Building) 10.50 12.50 0.10 1.00 13.13 m3
Slab on fill (Exterior of Building) 3.00 1.65 0.10 1.00 0.50 m3
2F Slab 10.50 12.50 0.10 1.00 13.13 m3
2F Terrace 3.00 1.65 0.10 1.00 0.50 m3
Footing Beam (FTB1) 0.25 0.30 228.00 1.00 17.10 m3
Wall Footing (WF1) 0.30 0.60 3.00 1.00 0.54 m3
Columns (C1) 0.40 0.40 4.80 22.00 16.90 m3
2F Beam (GB1) 0.30 0.40 3.00 29.00 10.44 m3
2F Beam (GB2) 0.30 0.40 4.00 5.00 2.40 m3
Roof Beam (RB1) 0.25 0.35 3.00 29.00 7.61 m3
Roof Beam (RB2) 0.25 0.35 4.00 5.00 1.75 m3
Slabs (2F) 10.50 12.50 0.12 1.00 15.75 m3
Porch (GF) 3.00 1.65 0.10 1.00 0.50 m3
Entrance Stairs 0.47 3.00 2.00 1.00 2.82 m3
Staircase (GF-2F) 1.76 1.20 4.00 1.00 8.45 m3
Ramp 6.83 1.65 0.10 1.50 1.69 m3
Total 128.03 m3
L W H Q Vol/Area Unit
Total 3.71 m3
Footing (F1) 16∅ 1.20 6.00 22.00 22.00 96.80 1.580 917.66 0.00 0.00 917.67 0.00
2F Beam (GB1)
Main Bar (Continuous) 16∅ 4.50 6.00 7.00 29.00 152.25 1.580 1,443.33 0.00 0.00 1443.33 0.00
Cut Top Bars 16∅ 5.74 6.00 2.00 29.00 55.49 1.580 526.01 0.00 0.00 526.02 0.00
Cut Bottom Bars 16∅ 2.14 6.00 2.00 29.00 20.71 1.580 196.37 0.00 0.00 196.38 0.00
Stirrups/Tie Bars 10∅ 1.00 6.00 28.00 29.00 135.33 0.616 500.19 500.20 0.00 0.00 0.00
2F Beam (GB2)
Main Bar (Continuous) 16∅ 3.60 5.75 7.00 5.00 21.91 1.580 199.08 0.00 0.00 199.08 0.00
Cut Top Bars 16∅ 6.24 6.00 2.00 5.00 10.40 1.580 98.59 0.00 0.00 98.60 0.00
Cut Bottom Bars 16∅ 2.86 6.00 2.00 5.00 4.76 1.580 45.14 0.00 0.00 45.15 0.00
Stirrups/Tie Bars 10∅ 1.00 6.00 33.00 5.00 27.50 0.616 101.64 101.64 0.00 0.00 0.00
Wall Footing WF
Horizontal Bars 16∅ 3.00 5.75 5.00 1.00 2.61 1.580 23.70 0.00 0.00 23.70 0.00
Stirrups/Tie Bars 10∅ 1.50 6.00 12.00 1.00 3.00 0.616 11.09 11.09 0.00 0.00 0.00
Columns (C1)
Vertical Bars 20∅ 6.00 6.00 4.00 22.00 88.00 2.466 1,302.05 0.00 0.00 0.00 1302.05
Vertical Bars 16∅ 6.00 6.00 4.00 22.00 88.00 1.580 834.24 0.00 0.00 834.24 0.00
Stirrups/Tie Bars 1 12∅ 1.50 6.00 33.00 22.00 181.50 0.888 967.03 0.00 967.04 0.00 0.00
Stirrups/Tie Bars 2 10∅ 1.50 6.00 33.00 22.00 181.50 0.616 670.82 670.83 0.00 0.00 0.00
Staircase
Vertical Bars 16∅ 6.00 6.00 12.00 8.00 96.00 1.580 910.08 0.00 0.00 910.08 0.00
Stirrups/Tie Bars 12∅ 4.00 6.00 33.00 10.00 220.00 0.888 1,172.16 0.00 1172.16 0.00 0.00
Qty. of bar
Total Total
Unit
Slab Reinforcing Steel Bar Size Area Spacing Factor Number of
Weight
Weight
Bars (Kg) Ø10mm Ø12mm Ø16mm Ø20mm
One-way 1 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
One-way 2 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
One-way 3 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
One-way 4 10∅ 12.0000 12.5 3.0620 36.74 0.616 271.61 271.62 0.00 0.00 0.00
Two-way 1 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 2 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 3 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 4 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 5 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 6 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 7 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Two-way 8 10∅ 9.0000 12.5 3.6030 32.43 0.616 179.78 179.78 0.00 0.00 0.00
12∅ 9.0000 12.5 4.6030 41.43 0.888 331.08 0.00 331.09 0.00 0.00
Meter per
Number Tie Lenght Number of kilogram Total Wt.
Tie Wires Factor Factor
of ties (m) Sets (m) of Tie
(kgs.)
Wire
2F Beam (GB1)
Stirrups/Tie Bars 7.00 28.00 196.00 0.30 3.00 53.00 3.33
2F Beam (GB2)
Stirrups/Tie Bars 7.00 33.00 231.00 0.30 6.00 53.00 7.85
Wall Footing WF
Stirrups/Tie Bars 7.00 12.00 84.00 0.30 1.00 53.00 0.48
Columns (C1)
Stirrups/Tie Bars 1 4.00 33.00 132.00 0.30 22.00 53.00 16.44
Stirrups/Tie Bars 2 4.00 33.00 132.00 0.30 22.00 53.00 16.44
Staircase
Stirrups/Tie Bars 4.00 49.00 196.00 0.30 10.00 53.00 11.09
L W H Q Vol/Area Unit
Footing (F1) 1.50 1.50 0.30 22.00 39.60 m2
2F Slab 10.50 12.50 0.10 1.00 4.60 m2
2F Terrace 3.00 1.65 0.10 1.00 0.93 m2
Footing Beam (FTB1) 0.25 0.30 228.00 1.00 250.80 m2
Wall Footing (WF1) 0.30 0.60 3.00 1.00 5.40 m2
Columns (C1) 0.40 0.40 4.80 22.00 168.96 m2
2F Beam (GB1) 0.30 0.40 3.00 29.00 121.80 m2
2F Beam (GB2) 0.30 0.40 4.00 5.00 28.00 m2
Roof Beam (RB1) 0.25 0.35 3.00 29.00 104.40 m3
Roof Beam (RB2) 0.25 0.35 4.00 5.00 24.00 m4
Slabs (2F) 10.50 12.50 0.12 1.00 5.52 m5
Porch (GF) 3.00 1.65 0.10 1.00 0.93 m6
Entrance Stairs 0.47 3.00 2.00 1.00 13.88 m7
Staircase (GF-2F) 1.76 1.20 4.00 1.00 23.68 m8
Ramp 6.83 1.65 0.10 1.50 2.54 m9
Total 795.04 m2
L W H Q Vol/Area Unit
Building Area 10.00 12 1 120.00 m2
Frontage 3.00 1.65 1 4.95 m2
Ext Staircase 1.50 6 1 9.00 m2
Area 133.95 m2
Soilguard per L coverage 15 m2
Total 9 L
1016(1)a Waterproofing
Quantity : 117.99 m2
L W H Q Vol/Area Unit
A1 11.00 0.9 2 19.80 m2
A2 13.00 0.9 2 23.40 m2
A3 7.00 0.9 2 12.60 m2
A4 1.65 0.9 2 2.97 m2
A5 4.00 0.9 2 7.20 m2
A6 14.65 0.9 2 26.37 m2
A7 51.30 0.5 1 25.65 m2
Total 117.99 m2
L W H Q Vol/Area Unit
A1 30.00 3.00 1 90.00 m2
A2 6.00 3.00 1 18.00 m2
Area 108 m2
Less Window & Door Opening 9.87 m2
Total 98.13 m2
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
Quantity : 135.82 m2
L W H Q Vol/Area Unit
A1 10.00 3.00 2 60.00 m2
A2 12.00 3.00 2 72.00 m2
A3 51.30 0.5 2 51.30 m2
A4 0.00 m2
A5 0.00 m2
A6 0.00 m2
A6 0.00 m3
Area 183.3 m2
Less Window & Door Opening 47.48 m2
Total 135.82 m2
1004(2)g Hinges
Quantity : 11.00 set
L W H Q Vol/Area Unit
D1 1.80 2.1 4 15.12 m2 3.78
Total 15.12 m2
L W H Q Vol/Area Unit
W1 2.80 1.10 3.00 9.24 m2
W2 1.40 1.10 17.00 26.18 m2
W3 0.60 0.30 4.00 0.72 m2
Total 36.14 m2
L W H Q Vol/Area Unit
D2 2.10 0.90 3 5.67 m2
D3 2.10 1.00 2 4.20 m2
D4 2.10 0.80 2 3.36 m2
Total 13.23 m2
L W H Q Vol/Area Unit
GF 10.00 12.00 120.00 m2
2F 10.00 12.00 120.00 m2
Total 240 m2
L W H Q Vol/Area Unit
GF 10.00 12.00 120.00 m2
Porch 1.65 3.00 4.95 m2
2F 10.00 12.00 120.00 m2
Terrace 1.65 3.00 4.95 m2
Total 249.9 m2
L W H Q Vol/Area Unit
PWD Male CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
PWD Female CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
2F Male CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
2F Female CR 1.50 3.00 1 4.50 m2
9.00 2.00 1 18.00 m2
Total 90 m2
L W H Q Vol/Area Unit
Staircase 7.50 1.2 1 9.00 m2
Main Ent Ramp 8.00 1.5 1 12.00 m2
Service Ent/Ext 3.00 0.8 1 2.40 m2
Total 23.4 m2
Total 84.52 m2
Existing Struc. 84.52 m2
1046(2)a2 108.00 m2
1046(2)a2 183.30 m2
less 1007(1) 15.12 m2
1008(1) 36.14 m2
1010(2)b 13.23 m2
Total 622.66 m2
L W H Q Length Unit
Top Handrail 34.00 1 34.00 m
Bottom Handrail 34.00 1 34.00 m
Vert Support 0.90 45.33 40.80 m
Total 108.8 m
L W H Q Vol/Area Unit
Service Ent 10.00 12 120.00 m2
Total 120 m2
W1 W2 H Q Area Unit
C1 0.40 0.40 4.80 22.00 84.48 m2
Total 84.48 m2
900(1)c1 84.48 m2
1046(2)a1 216.00 m2
1046(2)a2 271.64 m2
1003(1)a1 240.00 m2
less 1007(1) 15.12 m2
1008(1) 36.14 m2
1010(2)b 13.23 m2
Total 747.63 m2
L W H Q Vol/Area Unit
D2 2.10 0.90 3 5.67 m2
D3 2.10 1.00 2 4.20 m2
D4 2.10 0.8 2 3.36 m2
Total 26.46 m2
L W H Q Vol/Area Unit
10.44 12 N/A 1 125.28 m2
10.63 10 N/A 1 106.30 m3
Total 231.58 m2
Tot
Length Bd.Ft. per Number of Length Tot Length
Thk (in) Width (in) Length Total Bd.Ft.
(ft) Pc. Truss Reqd. (m) Reqd. (ft)
Reqd. (m)
HT1
Top & Bottom Chord 2 6 12.00 12.00 2.00 20.44 40.88 134.03 134.03
Vertical and Diagonal Member 2 4 12.00 8.00 2.00 17.74 35.48 116.33 77.55
HT2
Top & Bottom Chord 2 6 12.00 12.00 4.00 13.34 53.36 174.95 174.95
Vertical and Diagonal Member 2 4 12.00 8.00 4.00 11.01 44.02 144.33 96.22
HT3
i Top & Bottom Chord 2 6 12.00 12.00 10.00 6.00 60.00 196.72 196.72
Vertical and Diagonal Member 2 4 12.00 8.00 10.00 4.83 48.30 158.36 105.57
HT4
Top & Bottom Chord 2 6 12.00 12.00 6.00 4.81 28.86 94.62 94.62
Vertical and Diagonal Member 2 4 12.00 8.00 6.00 4.07 24.42 80.07 53.38
HT5
Top & Bottom Chord 2 6 12.00 12.00 2.00 10.42 20.84 68.33 68.33
Vertical and Diagonal Member 2 4 12.00 8.00 2.00 10.79 21.58 70.75 47.17
Total
Weight
Length Sets Weight
Per Piece
(Kg)
Total
Weight
Length Sets Weight
Per Piece
(Kg)
A. Labor
a. Const. Foreman 1 8.00 100.36 802.88
b. Skilled Labor 1 8.00 73.01 584.08
c. Unskilled Labor 3 8.00 56.27 1,350.48
Name and Capacity No of Unit/s No. of Month/s Monthly Rate Amount (PhP)
B. Equipment
F. Materials
a. 14ft corr roof sheet pcs 14 400.00 5,600.00
b. 2x4x12 coco lumber pcs 10.00 240.00 2,400.00
c. 2x3x12 coco lumber pcs 20.00 180.00 3,600.00
d. 2x2x12 coco lumber pcs 30.00 120.00 3,600.00
e. 1/4" thk. Ord. plywood pcs 21 479.00 10,059.00
f. assrtd nails kgs 9 101.50 913.50
g. umbrella nails kgs 2 75.00 150.00
A. Labor
Name and Capacity No of Unit/s No. of Day/s Daily Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
38,490.16
a. Mobilization/ Demobilization (0.75% of Civil Works)
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 902(1)a1 Reinforcing Steel of Reinforced Concrete Structures for Two-Storey, Grade 40
Unit of Measurement : kg
Output per hour : 129.094
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 902(1)b1 Reinforcing Steel of Reinforced Concrete Structures for Two-Storey, Grade 60
Unit of Measurement : kg
Output per hour : 129.094
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Installation
a. Construction Foreman 1 1.00 100.36 100.36
b. Skilled Laborer 4 1.00 73.01 292.04
c. Unskilled Laborer 6 1.00 56.27 337.62
Stripping
a. Construction Foreman 1 0.56 100.36 56.20
b. Unskilled Laborer 6 0.56 56.27 189.07
Sub - Total for A 975.29
Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)
B. Equipment
Area = 205.01 m2
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8 m full extension 62 14.00 4.50 3,906.00
c. Adjustable U-head Jack, 0.6m 80 14.00 0.85 952.00
d. Adjustable Base Jack, 0.6m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Round Wing Nut 558 14.00 0.15 1,171.80
Minor Tools (10% of Labor Cost) 97.53
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.825
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.18
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
(Labor cost for this item is considered/included in the installation of the fabricated material)
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
(Labor cost for this item is considered/included in the installation of the fabricated material)
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement : set
Output : 1.00
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
Unit of Measurement : m2
Output per hour : 1.243
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1021(1)c Plain Cement Floor Finish with Floor Hardener
Unit of Measurement : m2
Output per hour : 5.95
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1014(1)b1 Prepainted Metal Sheets ( Corrugated, Long Span,0.5mm thk)
Unit of Measurement : m2
Output per hour : 2.076
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Fabrication
a. Construction Foreman 1 1.00 100.36 100.36
b. Skilled Laborer 2 1.00 73.01 146.02
c. Unskilled Laborer 2 1.00 56.27 112.54
Erection
a. Skilled Laborer 3 0.49 73.01 107.32
b. Unskilled Laborer 3 0.49 56.27 82.72
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Minor Tools (10% of labor cost) 149.12
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Water Closet complete w/ bidet, fittings & accs. sets 4.00 9,000.00 36,000.00
d. Steel Counter Sink (4 Faucet) sets 1.00 6,028.00 6,028.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 7.00 6,500.00 45,500.00
g. Gate Valve 20mm dia pcs 4.00 330.00 1,320.00
i. Check Valve, 20mm dia. pcs 2.00 954.00 1,908.00
k.S.S. Floor Drain 4'x4'' pcs 4.00 280.00 1,120.00
l. Mirror m2 4.00 5,379.20 21,516.80
m. Handrail (PWD) sets 4.00 4,500.00 18,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 4.00 165.00 660.00
o. Fire Extinguisher, 5 lbs Capacity set 2.00 4,000.00 8,000.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1 l.s.
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF!
Part II Other General Requirements #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF!
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF!
PART C FINISHING WORKS #REF!
PART D PLUMBING/SANITARY WORKS #REF!
PART E ELECTRICAL WORKS #REF!
Total
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.89% 156,000.00
Part II Other General Requirements 1.58% 275,814.08
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.28% 396,833.63
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.33% 5,988,000.95
PART C FINISHING WORKS 46.10% 8,041,232.82
PART D PLUMBING/SANITARY WORKS 10.45% 1,823,557.12
PART E ELECTRICAL WORKS 4.36% 760,618.07
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted Err:509 6.00 mo - - 156,000.00 156,000.00 8% 12,480.00 20,217.60 188,697.60
Err:509 Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 156,000.00 156,000.00 12,480.00 20,217.60 188,697.60
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted ### 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
B.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 59116.55 1.00 lot 137,035.54 7,008.96 - 144,044.50 8% 11,523.56 18,668.17 174,236.23
B.7(2) Occupational Safety and Health
As Evaluated
As Submitted 40414.67 1.00 l.s. - - 127,576.82 127,576.82 8% 10,206.15 16,533.96 154,316.93
B.9 Mobilization/ Demobilization
As Evaluated
As Submitted 140,217.88 7,927.52 127,668.68 275,814.08 22,568.26 35,805.89 334,188.23
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted ### 413.71 m3 - 5,567.92 91,097.23 96,665.14 20% 19,333.03 13,919.78 129,917.95
803(1)a Structure Excavation
As Evaluated
As Submitted Err:509 257.76 m3 - 7,050.94 33,318.02 40,368.96 20% 8,073.79 5,813.13 54,255.88
Err:509 Embankment from Structure Excavation
As Evaluated
As Submitted 57302.14 335.90 m3 122,028.27 9,188.44 43,418.39 174,635.09 20% 34,927.02 25,147.45 234,709.56
804(1)b Embankment from Borrow
As Evaluated
As Submitted 17916.16 90.34 m3 58,244.10 20,264.01 6,656.33 85,164.44 20% 17,032.89 12,263.68 114,461.01
804(4) Gravel Fill
As Evaluated
As Submitted 180,272.37 42,071.31 174,489.96 396,833.63 79,366.73 57,144.04 533,344.40
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted ### 384.71 m3 1,263,772.35 60,395.33 82,880.19 1,407,047.87 20% 281,409.57 202,614.89 1,891,072.33
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted ### 68,853.89 kg 2,542,851.62 530,498.28 205,391.47 3,278,741.37 20% 655,748.27 472,138.76 4,406,628.40
902(1)a Reinforcing Steel, Grade 40
As Evaluated
As Submitted ### 2,577.60 m2 504,369.13 558,645.42 239,197.16 1,302,211.71 20% 260,442.34 187,518.49 1,750,172.54
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,310,993.10 1,149,539.04 527,468.81 5,988,000.95 1,197,600.18 862,272.14 8,047,873.27
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted ### 300.27 L 96,086.40 15,898.18 1,589.82 113,574.40 20% 22,714.88 16,354.71 152,643.99
1000(1) Soil Poisoning
As Evaluated
As Submitted 96,086.40 15,898.18 1,589.82 113,574.40 22,714.88 16,354.71 152,643.99
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted ### 285.37 m2 99,856.73 30,975.89 15,929.91 146,762.53 20% 29,352.51 21,133.80 197,248.84
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted ### 961.80 m2 561,645.73 125,575.39 64,579.43 751,800.54 20% 150,360.11 108,259.28 1,010,419.93
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 661,502.46 156,551.28 80,509.34 898,563.07 179,712.62 129,393.08 1,207,668.77
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted ### 1.00 l.s 343,872.83 66,595.60 45.93 410,514.36 20% 82,102.87 59,114.07 551,731.30
1010(4) Wooden Doors
As Evaluated
As Submitted Err:509 70.87 m 2
47,447.47 60,276.25 6,027.62 113,751.34 20% 22,750.27 16,380.19 152,881.80
Err:509 Jalousie Window
As Evaluated
As Submitted Err:509 146.88 m 2
272,857.73 187,386.24 98,502.62 558,746.59 20% 111,749.32 80,459.51 750,955.42
1005(1) Steel Casement Window
As Evaluated
As Submitted Err:509 65.28 m 2
56,433.61 9,369.31 4,925.13 70,728.06 20% 14,145.61 10,184.84 95,058.51
1005(5) Window Grilles
As Evaluated
As Submitted ### 43.00 set 64,500.00 - - 64,500.00 20% 12,900.00 9,288.00 86,688.00
1004(2)a Locksets
As Evaluated
As Submitted 918.50 172.00 pc 11,398.44 - - 11,398.44 20% 2,279.69 1,641.38 15,319.51
1004(2)g Hinges
As Evaluated
As Submitted Err:509 1.00 l.s. 37,200.00 9,818.40 981.84 48,000.24 20% 9,600.05 6,912.03 64,512.32
Err:509 Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 833,710.08 333,445.80 110,483.15 1,277,639.03 255,527.81 183,980.02 1,717,146.86
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted ### 1,161.01 m2 221,432.06 66,768.81 6,676.88 294,877.75 20% 58,975.55 42,462.40 396,315.70
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted ### 4,355.83 m2 355,282.82 288,224.51 28,822.45 672,329.77 20% 134,465.95 96,815.49 903,611.21
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted ### 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(2)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted Err:509 144.00 m 243,681.41 6,582.10 7,670.87 257,934.38 20% 51,586.88 37,142.55 346,663.81
Err:509 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted ### 661.00 m2 410,897.43 152,040.64 15,204.06 578,142.13 20% 115,628.43 83,252.47 777,023.03
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted ### 841.24 m2 119,245.77 43,258.80 4,325.88 166,830.45 20% 33,366.09 24,023.58 224,220.12
1038(1) Reflective Insulation
As Evaluated
As Submitted ### 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted ### 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,534,110.90 642,490.41 74,475.84 2,251,077.15 450,215.44 324,155.12 3,025,447.71
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted ### 4,943.76 m2 674,852.31 712,489.98 71,249.00 1,458,591.29 20% 291,718.26 210,037.15 1,960,346.70
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted ### 247.39 m2 19,362.81 39,615.12 3,961.51 62,939.45 20% 12,587.89 9,063.28 84,590.62
1032(1)b Wood Painting
As Evaluated
As Submitted Err:509 125.09 m2 17,234.96 18,929.24 1,892.92 38,057.13 20% 7,611.43 5,480.23 51,148.79
Err:509 Metal Painting
As Evaluated
As Submitted 711,450.08 771,034.35 77,103.44 1,559,587.87 311,917.58 224,580.66 2,096,086.11
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted ### 841.24 m2 347,086.71 115,856.97 11,585.70 474,529.38 20% 94,905.88 68,332.23 637,767.49
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted ### 64.20 m 13,549.22 1,474.29 147.43 15,170.94 20% 3,034.19 2,184.62 20,389.75
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted Err:509 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
Err:509 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted Err:509 128.40 m 41,262.62 2,498.79 249.88 44,011.30 20% 8,802.26 6,337.63 59,151.19
Err:509 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted ### 7,703.59 kg 428,855.23 49,752.65 103,653.95 582,261.83 20% 116,452.37 83,845.70 782,559.90
1003(5) Structural Steel, Trusses
As Evaluated
As Submitted Err:509 10,028.53 kg 564,929.01 52,272.53 87,495.57 704,697.11 20% 140,939.42 101,476.38 947,112.91
Err:509 Structural Steel, Purlins
As Evaluated
As Submitted Err:509 128.40 m 24,402.42 3,091.77 309.18 27,803.36 20% 5,560.67 4,003.68 37,367.71
Err:509 Fascia Board
As Evaluated
As Submitted ### 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted ### 293.65 kg 11,679.64 5,189.21 518.92 17,387.77 20% 3,477.55 2,503.84 23,369.16
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted ### 628.56 kg 25,750.36 11,107.54 1,110.75 37,968.65 20% 7,593.73 5,467.49 51,029.87
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted ### 52.00 pc 8,532.16 1,791.19 1.79 10,325.14 20% 2,065.03 1,486.82 13,876.99
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,486,627.54 248,540.08 205,623.68 1,940,791.30 388,158.27 279,473.95 2,608,423.52
Sub-Total C.6
As Evaluated
As Submitted 5,323,487.45 2,167,960.10 549,785.26 8,041,232.82 1,608,246.60 1,157,937.54 10,807,416.96
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted ### 1.00 l.s. 45,831.25 10,578.67 1,057.87 57,467.79 20% 11,493.56 8,275.36 77,236.71
1001(8) Sewer Line Works
As Evaluated
As Submitted ### 1.00 l.s. 31,668.25 7,362.18 736.22 39,766.65 20% 7,953.33 5,726.40 53,446.38
1002(6) Cold Water Line Works
As Evaluated
As Submitted ### 1.00 l.s. 193,090.94 44,552.97 4,455.30 242,099.20 20% 48,419.84 34,862.28 325,381.32
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted ### 1.00 l.s. 326,472.09 37,833.19 3,783.32 368,088.60 20% 73,617.72 53,004.76 494,711.08
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted Err:509 1.00 l.s. 84,458.63 20,979.97 2,098.00 107,536.59 20% 21,507.32 15,485.27 144,529.18
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted ### 30.00 units 18,201.24 6,889.20 12,023.04 37,113.48 20% 7,422.70 5,344.34 49,880.52
1001(6)b1 Catch basin
As Evaluated
As Submitted Err:509 1.00 lot 875,153.75 87,573.70 8,757.37 971,484.81 20% 194,296.96 139,893.81 1,305,675.58
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,574,876.14 215,769.88 32,911.11 1,823,557.12 364,711.43 262,592.22 2,450,860.77
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted ### 1.00 l.s. 90,605.14 17,183.92 1,718.39 109,507.45 20% 21,901.49 15,769.07 147,178.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted ### 1.00 l.s. 212,531.55 20,038.24 2,003.82 234,573.61 20% 46,914.72 33,778.60 315,266.93
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted ### 1.00 l.s. 251,941.00 4,288.65 428.87 256,658.52 20% 51,331.70 36,958.83 344,949.05
1102(21) Panel Board
As Evaluated
As Submitted ### 1.00 l.s. 120,058.00 10,292.76 1,029.28 131,380.04 20% 26,276.01 18,918.73 176,574.78
1103(1) Lighting Fixtures
As Evaluated
As Submitted ### 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 699,225.69 55,811.25 5,581.13 760,618.070 152,123.610 109,529.010 1,022,270.690
TOTAL OF PART E
As Evaluated
As Submitted 12,088,854.75 3,631,151.57 1,290,236.27 17,010,242.590 3,402,048.550 2,449,474.950 22,861,766.090
TOTAL OF PART III
As Evaluated
As Submitted 12,229,072.63 3,639,079.09 1,573,904.94 17,442,056.670 3,437,096.810 2,505,498.440 23,384,651.920
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.99% 151,666.67
Part II Other General Requirements 1.61% 247,792.58
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.24% 343,879.89
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.84% 5,205,623.63
PART C FINISHING WORKS 45.48% 6,995,668.73
PART D PLUMBING/SANITARY WORKS 11.25% 1,729,864.72
PART E ELECTRICAL WORKS 4.61% 708,793.02
`
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.83 mo - - 151,666.67 151,666.67 8% 12,133.33 19,656.00 183,456.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 151,666.67 151,666.67 12,133.33 19,656.00 183,456.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S. 124,212.14 7,008.96 - 131,221.10 8% 10,497.69 17,006.25 158,725.04
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 112,378.72 112,378.72 8% 8,990.30 14,564.28 135,933.30
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 127,394.48 7,927.52 112,470.58 247,792.58 20,326.54 32,174.29 300,293.41
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 365.45 m3 - 4,918.41 80,470.57 85,388.98 20% 17,077.80 12,296.01 114,762.79
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted #REF! 223.43 m3 - 6,111.85 28,880.53 34,992.39 20% 6,998.48 5,038.90 47,029.77
Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 288.09 m3 104,659.50 7,880.61 37,238.47 149,778.58 20% 29,955.72 21,568.12 201,302.42
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 78.20 m3 50,417.18 17,540.91 5,761.84 73,719.94 20% 14,743.99 10,615.67 99,079.60
804(4) Gravel Fill
As Evaluated
As Submitted 155,076.68 36,451.78 152,351.42 343,879.89 68,775.99 49,518.70 462,174.58
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 335.41 m3 1,101,821.85 52,655.76 72,259.22 1,226,736.83 20% 245,347.37 176,650.10 1,648,734.30
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 59,947.73 kg 2,213,937.11 461,879.02 178,824.36 2,854,640.49 20% 570,928.10 411,068.23 3,836,636.82
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,225.34 m2 435,440.05 482,298.73 206,507.53 1,124,246.31 20% 224,849.26 161,891.47 1,510,987.04
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,751,199.01 996,833.52 457,591.10 5,205,623.63 1,041,124.73 749,609.80 6,996,358.16
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 259.98 L 83,193.60 13,764.98 1,376.50 98,335.08 20% 19,667.02 14,160.25 132,162.35
1000(1) Soil Poisoning
As Evaluated
As Submitted 83,193.60 13,764.98 1,376.50 98,335.08 19,667.02 14,160.25 132,162.35
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 267.94 m2 93,757.62 29,083.92 14,956.94 137,798.48 20% 27,559.70 19,842.98 185,201.16
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 838.99 m2 489,930.49 109,540.96 56,333.43 655,804.88 20% 131,160.98 94,435.90 881,401.76
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 583,688.12 138,624.89 71,290.37 793,603.36 158,720.68 114,278.88 1,066,602.92
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 296,777.99 59,706.40 5,970.64 362,455.03 20% 72,491.01 52,193.52 487,139.56
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 59.98 m2 40,156.61 51,014.10 5,101.41 96,272.12 20% 19,254.42 13,863.18 129,389.72
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 122.40 m 2
227,381.44 156,155.20 82,085.52 465,622.16 20% 93,124.43 67,049.59 625,796.18
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 54.40 m2 47,028.01 7,807.76 4,104.28 58,940.05 20% 11,788.01 8,487.37 79,215.43
1005(5) Window Grills
As Evaluated
As Submitted #REF! 39.00 set 58,500.00 - - 58,500.00 20% 11,700.00 8,424.00 78,624.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 156.00 pc 10,338.12 - - 10,338.12 20% 2,067.62 1,488.69 13,894.43
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 31,000.00 8,182.00 818.20 40,000.20 20% 8,000.04 5,760.03 53,760.27
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 711,182.17 282,865.46 98,080.05 1,092,127.68 218,425.53 157,266.38 1,467,819.59
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,000.20 m2 190,761.79 57,520.75 5,752.07 254,034.61 20% 50,806.92 36,580.98 341,422.51
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,825.21 m2 312,002.85 253,113.47 25,311.35 590,427.67 20% 118,085.53 85,021.58 793,534.78
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 127.60 m 215,928.80 5,832.47 6,797.24 228,558.52 20% 45,711.70 32,912.43 307,182.65
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 565.91 m2 351,786.63 130,168.41 13,016.84 494,971.88 20% 98,994.38 71,275.95 665,242.21
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 723.31 m2 102,529.19 37,194.53 3,719.45 143,443.17 20% 28,688.63 20,655.82 192,787.62
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m 2
109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,356,580.68 569,445.19 66,372.65 1,992,398.52 398,479.70 286,905.39 2,677,783.61
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,336.71 m2 591,986.41 625,002.52 62,500.25 1,279,489.18 20% 255,897.84 184,246.44 1,719,633.46
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 218.61 m2 17,110.25 35,006.52 3,500.65 55,617.42 20% 11,123.48 8,008.91 74,749.81
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 112.50 m2 15,500.30 17,024.06 1,702.41 34,226.77 20% 6,845.35 4,928.65 46,000.77
1032(1)c Metal Painting
As Evaluated
As Submitted 624,596.97 677,033.09 67,703.31 1,369,333.37 273,866.67 197,184.00 1,840,384.04
Sub-Total C.5
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
C.6 Roof Framing and Roofing Works
As Submitted #REF! 723.31 m2 298,429.70 99,615.34 9,961.53 408,006.57 20% 81,601.31 58,752.95 548,360.83
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 55.20 m 11,649.79 1,267.61 126.76 13,044.17 20% 2,608.83 1,878.36 17,531.36
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 110.40 m 35,478.14 2,148.50 214.85 37,841.49 20% 7,568.30 5,449.17 50,858.96
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 6,440.06 kg 358,515.11 41,592.30 86,652.80 486,760.21 20% 97,352.04 70,093.47 654,205.72
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 8,515.07 kg 479,672.50 44,383.80 74,291.14 598,347.44 20% 119,669.49 86,162.03 804,178.96
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 110.40 m 20,981.52 2,658.34 265.83 23,905.69 20% 4,781.14 3,442.42 32,129.25
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 248.16 kg 9,870.32 4,385.34 438.53 14,694.19 20% 2,938.84 2,115.96 19,748.99
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 528.07 kg 21,633.56 9,331.74 933.17 31,898.48 20% 6,379.70 4,593.38 42,871.56
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 44.00 pc 7,219.52 1,515.62 1.52 8,736.66 20% 1,747.33 1,258.08 11,742.07
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,264,030.33 212,403.73 173,436.65 1,649,870.72 329,974.15 237,581.38 2,217,426.25
Sub-Total C.6
As Evaluated
As Submitted 4,623,271.86 1,894,137.33 478,259.53 6,995,668.73 1,399,133.75 1,007,376.28 9,402,178.76
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 43,151.00 10,006.85 1,000.69 54,158.54 20% 10,831.71 7,798.83 72,789.08
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 29,320.77 6,790.36 679.04 36,790.16 20% 7,358.03 5,297.78 49,445.97
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 172,839.11 39,956.24 3,995.62 216,790.97 20% 43,358.19 31,217.90 291,367.06
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 325,296.09 37,660.96 3,766.10 366,723.15 20% 73,344.63 52,808.13 492,875.91
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 71,748.04 18,033.35 1,803.33 91,584.71 20% 18,316.94 13,188.20 123,089.85
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 26.00 units 15,774.41 5,970.64 597.06 22,342.11 20% 4,468.42 3,217.26 30,027.79
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 848,514.95 84,509.21 8,450.92 941,475.08 20% 188,295.02 135,572.41 1,265,342.51
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,506,644.36 202,927.60 20,292.76 1,729,864.72 345,972.94 249,100.51 2,324,938.17
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 80,540.14 14,241.12 1,424.11 96,205.37 20% 19,241.07 13,853.57 129,300.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 202,341.55 17,124.36 1,712.44 221,178.35 20% 44,235.67 31,849.68 297,263.70
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 244,155.30 6,861.84 686.18 251,703.32 20% 50,340.66 36,245.28 338,289.26
1102(21) Panel Board
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 1.00 l.s. 101,458.00 8,863.21 886.32 111,207.53 20% 22,241.51 16,013.88 149,462.92
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 652,584.99 51,098.21 5,109.82 708,793.020 141,758.600 102,066.190 952,617.810
TOTAL OF PART E
As Evaluated
As Submitted 10,688,776.91 3,181,448.45 1,113,604.62 14,983,829.990 2,996,766.010 2,157,671.480 20,138,267.480
TOTAL OF PART III
As Evaluated
As Submitted 10,816,171.39 3,189,375.97 1,377,741.87 15,383,289.240 3,029,225.880 2,209,501.770 20,622,016.890
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.98% 130,000.00
Part II Other General Requirements 1.66% 218,951.28
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.19% 289,618.72
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.44% 4,423,246.32
PART C FINISHING WORKS 44.93% 5,943,512.95
PART D PLUMBING/SANITARY WORKS 12.17% 1,609,931.08
PART E ELECTRICAL WORKS 4.63% 612,125.66
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.00 mo - - 130,000.00 130,000.00 8% 10,400.00 16,848.00 157,248.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 130,000.00 130,000.00 10,400.00 16,848.00 157,248.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 112,329.46 5,840.80 - 118,170.26 8% 9,453.62 15,314.87 142,938.75
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 96,588.26 96,588.26 8% 7,727.06 12,517.84 116,833.16
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 115,511.80 6,759.36 96,680.12 218,951.28 18,019.23 28,436.47 265,406.98
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 313.84 m3 - 4,223.82 69,106.27 73,330.08 20% 14,666.02 10,559.53 98,555.63
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 185.75 m3 - 5,081.13 24,010.02 29,091.15 20% 5,818.23 4,189.13 39,098.51
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 240.28 m3 87,290.72 6,572.78 31,058.56 124,922.06 20% 24,984.41 17,988.78 167,895.25
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 66.06 m3 42,590.27 14,817.81 4,867.36 62,275.43 20% 12,455.09 8,967.66 83,698.18
804(4) Gravel Fill
As Evaluated
As Submitted 129,880.99 30,695.54 129,042.20 289,618.72 57,923.75 41,705.10 389,247.57
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 286.11 m3 939,871.35 44,916.19 61,638.25 1,046,425.79 20% 209,285.16 150,685.31 1,406,396.26
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 51,041.57 kg 1,885,022.60 393,259.77 152,257.24 2,430,539.61 20% 486,107.92 349,997.70 3,266,645.23
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,873.07 m2 366,510.97 405,952.04 173,817.90 946,280.92 20% 189,256.18 136,264.45 1,271,801.55
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,191,404.93 844,128.01 387,713.39 4,423,246.32 884,649.26 636,947.46 5,944,843.04
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 219.68 L 70,297.60 11,631.24 1,163.12 83,091.97 20% 16,618.39 11,965.24 111,675.60
1000(1) Soil Poisoning
As Evaluated
As Submitted 70,297.60 11,631.24 1,163.12 83,091.97 16,618.39 11,965.24 111,675.60
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 250.52 m2 87,662.01 27,193.05 13,984.52 128,839.58 20% 25,767.92 18,552.90 173,160.40
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 716.18 m2 418,215.26 93,506.53 48,087.43 559,809.22 20% 111,961.84 80,612.53 752,383.59
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 505,877.27 120,699.58 62,071.95 688,648.80 137,729.76 99,165.43 925,543.99
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 249,683.14 52,817.20 5,281.72 307,782.06 20% 61,556.41 44,320.62 413,659.09
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 49.10 m 2
32,872.45 41,760.46 4,176.05 78,808.96 20% 15,761.79 11,348.49 105,919.24
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 97.92 m2 181,905.15 124,924.16 65,668.42 372,497.73 20% 74,499.55 53,639.67 500,636.95
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 43.52 m2 37,622.41 6,246.21 3,283.42 47,152.04 20% 9,430.41 6,789.89 63,372.34
1005 (5) Window Grills
As Evaluated
As Submitted #REF! 35.00 set 52,500.00 - - 52,500.00 20% 10,500.00 7,560.00 70,560.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 140.00 pc 9,277.80 - - 9,277.80 20% 1,855.56 1,336.00 12,469.36
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 24,800.00 6,545.60 654.56 32,000.16 20% 6,400.03 4,608.02 43,008.21
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 588,660.95 232,293.63 79,064.16 900,018.75 180,003.75 129,602.69 1,209,625.19
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 839.37 m2 160,087.71 48,271.53 4,827.15 213,186.40 20% 42,637.28 30,698.84 286,522.52
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,294.60 m 2
268,723.70 218,003.10 21,800.31 508,527.12 20% 101,705.42 73,227.90 683,460.44
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 111.20 m 188,176.20 5,082.84 5,923.62 199,182.66 20% 39,836.53 28,682.30 267,701.49
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 470.83 m2 292,682.05 108,298.48 10,829.85 411,810.38 20% 82,362.08 59,300.70 553,473.16
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 605.38 m2 85,812.62 31,130.25 3,113.03 120,055.89 20% 24,011.18 17,288.05 161,355.12
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,179,053.69 496,401.77 58,269.65 1,733,725.12 346,745.03 249,656.42 2,330,126.57
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 3,729.66 m2 509,120.52 537,515.05 53,751.50 1,100,387.07 20% 220,077.41 158,455.74 1,478,920.22
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 189.83 m2 14,857.68 30,397.91 3,039.79 48,295.38 20% 9,659.08 6,954.54 64,909.00
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 99.91 m2 13,765.65 15,118.88 1,511.89 30,396.42 20% 6,079.28 4,377.08 40,852.78
1032(1)c Metal Painting
As Evaluated
As Submitted 537,743.85 583,031.84 58,303.18 1,179,078.87 235,815.77 169,787.36 1,584,682.00
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 605.38 m2 249,772.68 83,373.71 8,337.37 341,483.76 20% 68,296.75 49,173.66 458,954.17
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 46.20 m 9,750.37 1,060.94 106.09 10,917.40 20% 2,183.48 1,572.11 14,672.99
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 92.40 m 29,693.66 1,798.20 179.82 31,671.68 20% 6,334.34 4,560.72 42,566.74
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 5,176.53 kg 288,174.99 33,431.96 69,651.65 391,258.60 20% 78,251.72 56,341.24 525,851.56
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 7,001.60 kg 394,415.43 36,495.02 61,086.62 491,997.06 20% 98,399.41 70,847.58 661,244.05
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 92.40 m 17,560.62 2,224.92 222.49 20,008.03 20% 4,001.61 2,881.16 26,890.80
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 202.67 kg 8,061.00 3,581.47 358.15 12,000.61 20% 2,400.12 1,728.09 16,128.82
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 427.58 kg 17,516.76 7,555.94 755.59 25,828.30 20% 5,165.66 3,719.28 34,713.24
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 36.00 pc 5,906.88 1,240.06 1.24 7,148.18 20% 1,429.64 1,029.34 9,607.16
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,041,432.57 176,267.32 141,249.54 1,358,949.44 271,789.90 195,688.74 1,826,428.08
Sub-Total C.6
As Evaluated
As Submitted 3,923,065.93 1,620,325.38 400,121.61 5,943,512.95 1,188,702.60 855,865.88 7,988,081.43
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 39,506.00 9,149.12 914.91 49,570.03 20% 9,914.01 7,138.08 66,622.12
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 25,799.54 6,004.11 600.41 32,404.06 20% 6,480.81 4,666.18 43,551.05
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 147,422.78 34,062.99 3,406.30 184,892.07 20% 36,978.41 26,624.46 248,494.94
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 323,532.09 37,488.73 3,748.87 364,769.69 20% 72,953.94 52,526.84 490,250.47
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 65,879.25 16,383.24 1,638.32 83,900.81 20% 16,780.16 12,081.72 112,762.69
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 20.00 units 12,134.16 4,592.80 459.28 17,186.24 20% 3,437.25 2,474.82 23,098.31
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 792,545.75 76,965.85 7,696.58 877,208.18 20% 175,441.64 126,317.98 1,178,967.80
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,406,819.57 184,646.83 18,464.68 1,609,931.08 321,986.22 231,830.08 2,163,747.38
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 73,453.64 12,805.44 1,280.54 87,539.62 20% 17,507.92 12,605.70 117,653.24
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 141,968.40 12,919.40 1,291.94 156,179.74 20% 31,235.95 22,489.88 209,905.57
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 244,155.30 4,288.65 428.87 248,872.82 20% 49,774.56 35,837.69 334,485.07
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 82,858.00 7,433.66 743.37 91,035.03 20% 18,207.01 13,109.04 122,351.08
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 566,525.34 41,454.83 4,145.48 612,125.660 122,425.130 88,146.090 822,696.880
TOTAL OF PART E
As Evaluated
As Submitted 9,217,696.75 2,721,250.58 939,487.36 12,878,434.730 2,575,686.960 1,854,494.610 17,308,616.300
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 9,333,208.55 2,728,009.94 1,166,167.47 13,227,386.010 2,604,106.190 1,899,779.080 17,731,271.280
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.34% 121,333.33
Part II Other General Requirements 1.83% 165,697.10
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.26% 205,356.87
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.42% 3,120,847.89
PART C FINISHING WORKS 47.32% 4,290,596.84
PART D PLUMBING/SANITARY WORKS 10.15% 920,631.76
PART E ELECTRICAL WORKS 2.68% 242,990.66
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.67 mo - - 121,333.33 121,333.33 8% 9,706.67 15,724.80 146,764.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 121,333.33 121,333.33 9,706.67 15,724.80 146,764.80
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 89,810.36 5,840.80 - 95,651.16 8% 7,652.09 12,396.39 115,699.64
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 65,853.18 65,853.18 8% 5,268.25 8,534.57 79,656.00
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 92,992.70 6,759.36 65,945.04 165,697.10 13,758.89 21,534.72 200,990.71
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 244.62 m3 - 3,292.22 53,864.31 57,156.53 20% 11,431.31 8,230.54 76,818.38
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 139.08 m3 - 3,804.49 17,977.46 21,781.95 20% 4,356.39 3,136.60 29,274.94
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 159.64 m3 57,995.22 4,366.90 20,635.04 82,997.16 20% 16,599.43 11,951.59 111,548.18
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 46.06 m3 29,695.85 10,331.64 3,393.74 43,421.23 20% 8,684.25 6,252.66 58,358.14
804(4) Gravel Fill
As Evaluated
As Submitted 87,691.07 21,795.25 95,870.55 205,356.87 41,071.38 29,571.39 275,999.64
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 201.23 m3 661,040.55 31,590.95 43,352.08 735,983.58 20% 147,196.72 105,981.64 989,161.94
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 36,154.58 kg 1,335,229.31 278,560.04 107,849.28 1,721,638.63 20% 344,327.73 247,915.96 2,313,882.32
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,312.79 m2 256,878.78 284,522.09 121,824.81 663,225.68 20% 132,645.14 95,504.50 891,375.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,253,148.65 594,673.07 273,026.17 3,120,847.89 624,169.59 449,402.10 4,194,419.58
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 159.89 L 51,164.80 8,465.58 846.56 60,476.94 20% 12,095.39 8,708.68 81,281.01
1000(1) Soil Poisoning
As Evaluated
As Submitted 51,164.80 8,465.58 846.56 60,476.94 12,095.39 8,708.68 81,281.01
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 147.30 m2 51,543.25 15,988.89 8,222.57 75,754.71 20% 15,150.94 10,908.68 101,814.33
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 522.79 m2 305,284.64 68,256.97 35,102.39 408,644.01 20% 81,728.80 58,844.74 549,217.55
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 356,827.89 84,245.86 43,324.96 484,398.72 96,879.74 69,753.42 651,031.88
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 180,165.84 34,446.00 3,444.60 218,056.44 20% 43,611.29 31,400.13 293,067.86
1010(4) Wooden Dooor
As Evaluated
As Submitted #REF! 34.93 m2 23,385.64 29,708.61 2,970.86 56,065.11 20% 11,213.02 8,073.38 75,351.51
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 73.44 m2 136,428.86 93,693.12 49,251.31 279,373.30 20% 55,874.66 40,229.76 375,477.72
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 32.64 m 2
28,216.81 4,684.66 2,462.57 35,364.03 20% 7,072.81 5,092.42 47,529.26
1005(5) Window Grill
As Evaluated
As Submitted #REF! 24.00 set 36,000.00 - - 36,000.00 20% 7,200.00 5,184.00 48,384.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 96.00 pc 6,361.92 - - 6,361.92 20% 1,272.38 916.12 8,550.42
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 18,600.00 4,909.20 490.92 24,000.12 20% 4,800.02 3,456.02 32,256.16
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 429,159.07 167,441.59 58,620.26 655,220.92 131,044.18 94,351.83 880,616.93
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 584.99 m2 111,571.43 33,642.33 3,364.23 148,577.99 20% 29,715.60 21,395.23 199,688.82
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 2,313.83 m2 188,727.30 153,105.73 15,310.57 357,143.60 20% 71,428.72 51,428.68 480,001.00
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 92.12 m 155,888.41 4,210.72 4,907.23 165,006.35 20% 33,001.27 23,760.91 221,768.53
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 332.94 m2 206,965.49 76,581.56 7,658.16 291,205.20 20% 58,241.04 41,933.55 391,379.79
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 434.28 m2 61,559.19 22,331.83 2,233.18 86,124.21 20% 17,224.84 12,401.89 115,750.94
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 824,033.23 338,202.14 39,913.44 1,202,148.80 240,429.77 173,109.43 1,615,688.00
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 2,553.91 m2 348,623.73 368,067.08 36,806.71 753,497.52 20% 150,699.50 108,503.64 1,012,700.66
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 133.27 m2 10,430.83 21,340.83 2,134.08 33,905.74 20% 6,781.15 4,882.43 45,569.32
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 62.73 m2 8,642.97 9,492.62 949.26 19,084.85 20% 3,816.97 2,748.22 25,650.04
1032(1)c Metal Painting
As Evaluated
As Submitted 367,697.53 398,900.52 39,890.05 806,488.11 161,297.62 116,134.29 1,083,920.02
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 434.28 m2 179,179.22 59,809.73 5,980.97 244,969.92 20% 48,993.98 35,275.67 329,239.57
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 32.90 m 6,943.45 755.52 75.55 7,774.51 20% 1,554.90 1,119.53 10,448.94
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 65.80 m 21,145.49 1,280.53 128.05 22,554.08 20% 4,510.82 3,247.79 30,312.69
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 3,535.91 kg 196,842.45 22,836.22 47,576.65 267,255.32 20% 53,451.06 38,484.77 359,191.15
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 5,170.61 kg 291,271.76 26,951.20 45,111.84 363,334.80 20% 72,666.96 52,320.21 488,321.97
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 65.80 m 12,505.29 1,584.41 158.44 14,248.14 20% 2,849.63 2,051.73 19,149.50
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 146.82 kg 5,839.62 2,594.52 259.45 8,693.59 20% 1,738.72 1,251.88 11,684.19
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 314.91 kg 12,900.99 5,564.90 556.49 19,022.38 20% 3,804.48 2,739.22 25,566.08
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 26.00 pc 4,266.08 895.60 0.90 5,162.57 20% 1,032.51 743.41 6,938.49
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 809,483.16 144,671.47 127,708.72 1,081,863.35 216,372.66 155,788.33 1,454,024.34
Sub-Total C.6
As Evaluated
As Submitted 2,838,365.67 1,141,927.17 310,303.99 4,290,596.84 858,119.36 617,845.98 5,766,562.18
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,531.75 4,288.65 428.87 23,249.27 20% 4,649.85 3,347.89 31,247.01
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 70,144.32 16,265.37 1,626.54 88,036.22 20% 17,607.24 12,677.22 118,320.68
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 162,352.47 18,830.48 1,883.05 183,066.00 20% 36,613.20 26,361.50 246,040.70
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 56,067.25 14,143.80 1,414.38 71,625.43 20% 14,325.09 10,314.06 96,264.58
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 16.00 units 9,707.33 3,674.24 367.42 13,748.99 20% 2,749.80 1,979.85 18,478.64
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 479,028.95 49,621.17 4,962.12 533,612.23 20% 106,722.45 76,840.16 717,174.84
SPL-2 Fire Protection System
As Evaluated
As Submitted 801,631.80 108,181.78 10,818.18 920,631.76 184,126.35 132,570.96 1,237,329.07
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 30,928.20 9,663.64 966.36 41,558.20 20% 8,311.64 5,984.38 55,854.22
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 63,995.82 7,780.56 778.06 72,554.44 20% 14,510.89 10,447.84 97,513.17
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 36,455.00 3,145.01 314.50 39,914.51 20% 7,982.90 5,747.69 53,645.10
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 60,585.00 5,432.29 543.23 66,560.52 20% 13,312.10 9,584.71 89,457.33
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 210,954.02 29,124.22 2,912.42 242,990.660 48,598.130 34,990.650 326,579.440
TOTAL OF PART E
As Evaluated
As Submitted 6,191,791.20 1,895,701.49 692,931.31 8,780,424.020 1,756,084.810 1,264,381.080 11,800,889.910
TOTAL OF PART III
As Evaluated
As Submitted 6,284,783.90 1,902,460.85 880,209.68 9,067,454.450 1,779,550.370 1,301,640.600 12,148,645.420
GRAND TOTAL
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.50% 104,000.00
Part II Other General Requirements 1.96% 135,880.93
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.20% 152,645.07
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.68% 2,338,468.06
PART C FINISHING WORKS 46.56% 3,232,938.03
PART D PLUMBING/SANITARY WORKS 11.38% 790,140.37
PART E ELECTRICAL WORKS 2.74% 189,943.30
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.00 mo - - 104,000.00 104,000.00 8% 8,320.00 13,478.40 125,798.40
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 104,000.00 104,000.00 8,320.00 13,478.40 125,798.40
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 76,734.52 4,672.64 - 81,407.16 8% 6,512.57 10,550.37 98,470.10
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 50,281.01 50,281.01 8% 4,022.48 6,516.42 60,819.91
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 79,916.86 5,591.20 50,372.87 135,880.93 11,373.60 17,670.55 164,925.08
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 196.98 m3 - 2,651.06 43,374.18 46,025.23 20% 9,205.05 6,627.63 61,857.91
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 105.37 m3 - 2,882.36 13,620.11 16,502.47 20% 3,300.49 2,376.36 22,179.32
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 111.83 m3 40,626.44 3,059.07 14,455.13 58,140.64 20% 11,628.13 8,372.25 78,141.02
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 33.92 m3 21,868.94 7,608.54 2,499.25 31,976.73 20% 6,395.35 4,604.65 42,976.73
804(4) Gravel Fill
As Evaluated
As Submitted 62,495.38 16,201.03 73,948.67 152,645.07 30,529.02 21,980.89 205,154.98
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 151.93 m3 499,090.05 23,851.38 32,731.11 555,672.54 20% 111,134.51 80,016.85 746,823.90
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 27,248.42 kg 1,006,314.81 209,940.79 81,282.16 1,297,537.76 20% 259,507.55 186,845.44 1,743,890.75
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 960.52 m2 187,948.73 208,174.31 89,134.72 485,257.76 20% 97,051.55 69,877.12 652,186.43
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,693,353.58 441,966.47 203,148.00 2,338,468.06 467,693.61 336,739.41 3,142,901.08
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 115.60 L 36,992.00 6,120.59 612.06 43,724.65 20% 8,744.93 6,296.35 58,765.93
1000(1) Soil Poisoning
As Evaluated
As Submitted 36,992.00 6,120.59 612.06 43,724.65 8,744.93 6,296.35 58,765.93
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 129.91 m2 45,458.14 14,101.26 7,251.83 66,811.23 20% 13,362.25 9,620.82 89,794.30
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 399.98 m2 233,569.41 52,222.55 26,856.39 312,648.35 20% 62,529.67 45,021.36 420,199.38
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 279,027.54 66,323.81 34,108.22 379,459.58 75,891.92 54,642.18 509,993.68
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 133,071.00 26,408.60 2,640.86 162,120.46 20% 32,424.09 23,345.35 217,889.90
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 24.05 m2 16,101.48 20,454.97 2,045.50 38,601.94 20% 7,720.39 5,558.68 51,881.01
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 48.96 m2 90,952.58 62,462.08 32,834.21 186,248.86 20% 37,249.77 26,819.84 250,318.47
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 21.76 m 2
18,811.20 3,123.10 1,641.71 23,576.02 20% 4,715.20 3,394.95 31,686.17
1005(5) Window Grill
As Evaluated
As Submitted #REF! 20.00 set 30,000.00 - - 30,000.00 20% 6,000.00 4,320.00 40,320.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 80.00 pc 5,301.60 - - 5,301.60 20% 1,060.32 763.43 7,125.35
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 12,400.00 3,272.80 327.28 16,000.08 20% 3,200.02 2,304.01 21,504.11
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 306,637.85 115,721.55 39,489.56 461,848.96 92,369.79 66,506.26 620,725.01
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 424.17 m2 80,899.25 24,393.70 2,439.37 107,732.32 20% 21,546.46 15,513.45 144,792.23
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,783.22 m2 145,448.15 117,995.35 11,799.54 275,243.04 20% 55,048.61 39,635.00 369,926.65
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 73.42 m 124,243.67 3,355.96 3,911.08 131,510.71 20% 26,302.14 18,937.54 176,750.39
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 237.86 m2 147,860.91 54,711.63 5,471.16 208,043.70 20% 41,608.74 29,958.29 279,610.73
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 315.48 m2 44,719.29 16,222.82 1,622.28 62,564.39 20% 12,512.88 9,009.27 84,086.54
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 642,492.68 265,009.43 31,683.50 939,185.61 187,837.13 135,242.72 1,262,265.46
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,946.86 m2 265,757.84 280,579.61 28,057.96 574,395.41 20% 114,879.08 82,712.94 771,987.43
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 104.49 m2 8,178.26 16,732.22 1,673.22 26,583.71 20% 5,316.74 3,828.05 35,728.50
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 50.14 m2 6,908.31 7,587.44 758.74 15,254.49 20% 3,050.90 2,196.65 20,502.04
1032(1)c Metal Painting
As Evaluated
As Submitted 280,844.41 304,899.27 30,489.93 616,233.61 123,246.72 88,737.64 828,217.97
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 315.48 m2 130,163.63 43,448.40 4,344.84 177,956.87 20% 35,591.37 25,625.79 239,174.03
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 23.90 m 5,044.02 548.84 54.88 5,647.75 20% 1,129.55 813.28 7,590.58
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 47.80 m 15,361.01 930.24 93.02 16,384.27 20% 3,276.85 2,359.33 22,020.45
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 2,271.38 kg 126,446.66 14,669.42 30,562.05 171,678.12 20% 34,335.62 24,721.65 230,735.39
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 3,687.15 kg 207,705.22 19,218.84 32,169.15 259,093.20 20% 51,818.64 37,309.42 348,221.26
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 47.80 m 9,084.39 1,150.98 115.10 10,350.47 20% 2,070.09 1,490.47 13,911.03
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 101.34 kg 4,030.70 1,790.82 179.08 6,000.60 20% 1,200.12 864.09 8,064.81
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 214.42 kg 8,784.19 3,789.10 378.91 12,952.21 20% 2,590.44 1,865.12 17,407.77
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 18.00 pc 2,953.44 620.03 0.62 3,574.09 20% 714.82 514.67 4,803.58
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 588,162.07 108,565.52 95,758.02 792,485.62 158,497.10 114,117.94 1,065,100.66
Sub-Total C.6
As Evaluated s
As Submitted 2,134,156.56 866,640.17 232,141.28 3,232,938.03 646,587.59 465,543.09 4,345,068.71
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,103.75 4,217.17 421.72 22,742.64 20% 4,548.53 3,274.94 30,566.11
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 62,014.42 14,379.53 1,437.95 77,831.90 20% 15,566.38 11,207.79 104,606.07
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 161,176.47 18,715.66 1,871.57 181,763.70 20% 36,352.74 26,173.97 244,290.41
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 46,716.75 12,022.23 1,202.22 59,941.20 20% 11,988.24 8,631.53 80,560.97
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 12.00 units 7,280.50 2,755.68 275.57 10,311.74 20% 2,062.35 1,484.89 13,858.98
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 385,396.15 40,781.29 4,078.13 430,255.57 20% 86,051.11 61,956.80 578,263.48
SPL-2 Fire Protection System
As Evaluated
As Submitted 686,487.77 94,229.64 9,422.96 790,140.37 158,028.07 113,780.20 1,061,948.64
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 25,137.80 8,457.60 845.76 34,441.16 20% 6,888.23 4,959.53 46,288.92
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 52,894.17 6,115.24 611.52 59,620.93 20% 11,924.19 8,585.41 80,130.53
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 24,259.70 2,573.19 257.32 27,090.21 20% 5,418.04 3,900.99 36,409.24
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 41,985.00 4,002.74 400.27 46,388.01 20% 9,277.60 6,679.87 62,345.48
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 163,266.67 24,251.49 2,425.15 189,943.300 37,988.660 27,351.830 255,283.790
TOTAL OF PART E
As Evaluated
As Submitted 4,739,759.96 1,443,288.80 521,086.07 6,704,134.830 1,340,826.950 965,395.420 9,010,357.200
TOTAL OF PART III
As Evaluated
As Submitted 4,819,676.82 1,448,880.00 675,458.93 6,944,015.760 1,360,520.550 996,544.370 9,301,080.680
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 2.05% 99,666.67
Part II Other General Requirements 2.20% 107,225.89
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.01% 97,854.73
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 31.95% 1,556,092.30
PART C FINISHING WORKS 43.89% 2,137,714.37
PART D PLUMBING/SANITARY WORKS 15.19% 739,573.28
PART E ELECTRICAL WORKS 2.71% 132,171.50
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 3.83 mo - - 99,666.67 99,666.67 8% 7,973.33 12,916.80 120,556.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 99,666.67 99,666.67 7,973.33 12,916.80 120,556.80
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 63,384.94 4,672.64 - 68,057.58 8% 5,444.61 8,820.26 82,322.45
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 34,975.55 34,975.55 8% 2,798.04 4,532.83 42,306.42
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 66,567.28 5,591.20 35,067.40 107,225.89 9,081.20 13,956.85 130,263.94
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 144.01 m3 - 1,938.16 31,710.40 33,648.56 20% 6,729.71 4,845.39 45,223.66
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 66.34 m3 - 1,814.71 8,575.10 10,389.81 20% 2,077.96 1,496.13 13,963.90
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 64.02 m3 23,257.67 1,751.25 8,275.22 33,284.13 20% 6,656.83 4,792.92 44,733.88
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 21.78 m3 14,042.02 4,885.44 1,604.77 20,532.23 20% 4,106.45 2,956.64 27,595.32
804(4) Gravel Fill
As Evaluated
As Submitted 37,299.69 10,389.55 50,165.49 97,854.73 19,570.95 14,091.08 131,516.76
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 102.63 m3 337,139.55 16,111.81 22,110.14 375,361.50 20% 75,072.30 54,052.06 504,485.86
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 18,342.24 kg 677,399.56 141,321.38 54,714.99 873,435.92 20% 174,687.18 125,774.77 1,173,897.87
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 608.26 m2 119,020.63 131,828.70 56,445.55 307,294.88 20% 61,458.98 44,250.46 413,004.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,133,559.73 289,261.89 133,270.69 1,556,092.30 311,218.46 224,077.29 2,091,388.05
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 75.31 L 24,099.20 3,987.39 398.74 28,485.32 20% 5,697.06 4,101.89 38,284.27
1000(1) Soil Poisoning
As Evaluated
As Submitted 24,099.20 3,987.39 398.74 28,485.32 5,697.06 4,101.89 38,284.27
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 112.48 m2 39,359.03 12,209.30 6,278.85 57,847.18 20% 11,569.44 8,329.99 77,746.61
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 227.17 m2 132,656.54 29,659.97 15,253.18 177,569.69 20% 35,513.94 25,570.04 238,653.67
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 172,015.57 41,869.27 21,532.03 235,416.87 47,083.38 33,900.03 316,400.28
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 85,976.15 19,519.40 1,951.94 107,447.49 20% 21,489.50 15,472.44 144,409.43
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 13.71 m2 9,178.85 11,660.61 1,166.06 22,005.51 20% 4,401.10 3,168.79 29,575.40
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 24.48 m2 45,476.29 31,231.04 16,417.10 93,124.43 20% 18,624.89 13,409.92 125,159.24
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 10.88 m 2
9,405.60 1,561.55 820.86 11,788.01 20% 2,357.60 1,697.47 15,843.08
1005 (5) Window Grill
As Evaluated
As Submitted #REF! 16.00 set 24,000.00 - - 24,000.00 20% 4,800.00 3,456.00 32,256.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 64.00 pc 4,241.28 - - 4,241.28 20% 848.26 610.74 5,700.28
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 6,200.00 1,636.40 163.64 8,000.04 20% 1,600.01 1,152.01 10,752.06
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 184,478.17 65,609.00 20,519.60 270,606.76 54,121.36 38,967.37 363,695.49
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 263.35 m2 50,227.07 15,145.06 1,514.51 66,886.64 20% 13,377.33 9,631.68 89,895.65
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,252.61 m2 102,169.00 82,884.98 8,288.50 193,342.49 20% 38,668.50 27,841.32 259,852.31
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 55.82 m 94,460.39 2,551.48 2,973.53 99,985.40 20% 19,997.08 14,397.90 134,380.38
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 142.77 m2 88,750.12 32,839.40 3,283.94 124,873.45 20% 24,974.69 17,981.78 167,829.92
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 196.68 m2 27,879.39 10,113.81 1,011.38 39,004.58 20% 7,800.92 5,616.66 52,422.16
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 462,807.37 191,864.70 23,511.92 678,184.01 135,636.82 97,658.51 911,479.34
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,339.81 m2 182,891.94 193,092.14 19,309.21 395,293.30 20% 79,058.66 56,922.24 531,274.20
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 75.71 m2 5,925.70 12,123.61 1,212.36 19,261.67 20% 3,852.33 2,773.68 25,887.68
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 37.55 m2 5,173.66 5,682.25 568.23 11,424.14 20% 2,284.83 1,645.08 15,354.05
1032(1)c Metal Painting
As Evaluated
As Submitted 193,991.30 210,898.01 21,089.80 425,979.11 85,195.82 61,341.00 572,515.93
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 196.68 m2 81,148.04 27,087.08 2,708.71 110,943.82 20% 22,188.76 15,975.91 149,108.49
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 14.90 m 3,144.60 342.16 34.22 3,520.98 20% 704.20 507.02 4,732.20
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 29.80 m 9,576.53 579.94 57.99 10,214.46 20% 2,042.89 1,470.88 13,728.23
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 1,008.85 kg 56,162.21 6,515.53 13,574.36 76,252.09 20% 15,250.42 10,980.30 102,482.81
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 2,143.69 kg 120,758.74 11,173.73 18,702.98 150,635.45 20% 30,127.09 21,691.50 202,454.04
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 29.80 m 5,663.49 717.56 71.76 6,452.81 20% 1,290.56 929.20 8,672.57
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 55.85 kg 2,221.38 986.95 98.69 3,307.02 20% 661.40 476.21 4,444.63
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 113.93 kg 4,667.40 2,013.30 201.33 6,882.03 20% 1,376.41 991.01 9,249.45
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 10.00 pc 1,640.80 344.46 0.34 1,985.60 20% 397.12 285.93 2,668.65
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 363,572.00 72,159.56 63,310.74 499,042.30 99,808.45 71,862.08 670,712.83
Sub-Total C.6
As Evaluated
As Submitted 1,400,963.60 586,387.94 150,362.84 2,137,714.37 427,542.89 307,830.88 2,873,088.14
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 17,675.75 3,788.31 378.83 21,842.89 20% 4,368.58 3,145.38 29,356.85
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 53,018.02 12,257.96 1,225.80 66,501.77 20% 13,300.35 9,576.25 89,378.37
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 160,000.47 18,543.43 1,854.34 180,398.24 20% 36,079.65 25,977.35 242,455.24
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 32,018.30 8,368.42 836.84 41,223.55 20% 8,244.71 5,936.19 55,404.45
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 8.00 units 4,853.66 1,837.12 183.71 6,874.50 20% 1,374.90 989.93 9,239.33
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 371,746.15 39,720.51 3,972.05 415,438.71 20% 83,087.74 59,823.17 558,349.62
SPL-2 Fire Protection System
As Evaluated
As Submitted 645,112.09 85,873.81 8,587.38 739,573.28 147,914.65 106,498.55 993,986.48
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 19,023.20 2,325.32 232.53 21,581.05 20% 4,316.21 3,107.67 29,004.93
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 37,258.20 3,747.40 374.74 41,380.34 20% 8,276.07 5,958.77 55,615.18
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 18,390.10 2,001.37 200.14 20,591.61 20% 4,118.32 2,965.19 27,675.12
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 23,385.00 2,573.19 257.32 26,215.51 20% 5,243.10 3,775.03 35,233.64
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 117,046.50 13,750.00 1,375.00 132,171.500 26,434.300 19,032.690 177,638.490
TOTAL OF PART E
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF PART III
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 3,400,548.90 991,254.38 478,495.46 4,870,298.740 949,735.780 698,404.140 6,518,438.660
GRAND TOTAL
As Evaluated