Buckeye Lake Dam Final Report - March 2015
Buckeye Lake Dam Final Report - March 2015
Buckeye Lake Dam Final Report - March 2015
en
March 2015
Status: Final
CONTENTS
Introduction ..................................................................................................................................................................... 1
1.1
1.3
1.2
2
1.4
2.1
2.2
2.2.1
2.2.2
4 Existing Embankment Conditions with Respect to Established Dam Safety Guidance and
Engineering Best Practices ................................................................................................................................................ 15
5
5.1
5.2
5.3
5.3.1
5.3.2
5.3.4
Partial rerouting of inflows and outflows from the lake without changes to the dam 20
5.3.3
5.3.5
5.3.6
Breach of the embankment and rerouting drainage from the lake area ........................... 19
5.4
Installation of toe drains, relief wells, or stability berms along existing dam................. 20
Conclusions..................................................................................................................................................................... 22
Page I
List of Appendices
Title
H
I
Glossary of Terms
Page II
EXECUTIVE SUMMARY
The U.S. Army Corps of Engineers, Huntington District (the District) and the Ohio Department of
Natural Resources (ODNR) have a long history of cooperation with regard to dam safety issues.
From June 2014 to February 2015, the District, as an external expert, was retained by ODNR to
complete an assessment of the condition of Buckeye Lake Dam, Ohio using engineering best
practices. The assessment included evaluation of previous engineering consultant reports, site
reconnaissance, and public meeting participation. Completion of these tasks resulted in the
identification of extensive embankment defects deemed by the District to pose significant public
risks, conclusions regarding these defects, and recommendations to ODNR for development and
implementation of a risk reduction plan for Buckeye Lake Dam. During the assessment period the
District gained further knowledge of ODNRs risk-informed inventory management processes and
visited current ODNR dam risk reduction projects , including construction at Roosevelt Lake and
Pond Lick Dams. The District acknowledges and concurs with ODNRs programmatic efforts
focused on dam safety risk assessment and reduction.
After a review of the consultant reports and past USACE high pool observation records, and during
the period from August 2014 through December 2014, the District conducted site reconnaissance
and participated in public meetings. These efforts resulted in the determination that numerous
defects, of which the most significant are many encroachments by private interests, exist along the
entire 4.1 miles of the embankment at Buckeye Lake. The District has concluded, using applicable
engineering standards of practice, that the Buckeye Lake Dam embankment does not meet current
dam safety requirements. Additionally, several seepage and internal erosion initiation observations
were documented by USACE and ODNR personnel during 1968 and 1990 emergency reponses.
Embankment defect conditions observed during the 2014 site reconnaissance included sheet pile
and masonry wall deterioration, trees rooted in the embankment, seepage, wet areas, and
subsidence features. Most importantly, approximately 370 houses with associated structures,
utilities, and open excavations have displaced or disrupted large portions of the embankment. Of
these structures, more than 15 percent show misalignment of walls and retaining features, which is
indicative of differential settlement. The extent of these man-made embankment defects for
designed water-retaining structures is unprecedented in the experience of the District. The design
and construction of this dam did not contemplate the secondary placement of these structures. It is
likely that embankment defects beyond those observed during reconnaissance exist since large
areas of the dam cannot be inspected due to the presence of residences, appurtenant structures,
and vegetation. Limited stability analyses described in previous reports also have not adequately
defined embankment defects and failure modes, which resulted in the apparent underestimation of
internal erosion and overtopping failure risks.
The previously referenced engineering consultants, retained during the period from 1978 to 2003,
appropriately used the data and methodology available during that time. However, the advent and
complete implementation of risk-based analysis methodology includes more comprehensive
evaluations of known or potential defects in dams and appurtenant structures. Additionally,
significant advances in both semi-quantitative and quantitative analysis and modeling would
Page III
include more extensive subsurface explorations and laboratory testing to better characterize
embankment and foundation conditions.
The District acknowledges limitations, as did the previously retained consultants, Ohio Department
of Natural Resources, and the public, regarding geotechnical, hydrologic, and hydraulic information
as would be required for more comprehensive modeling, analysis, and risk assessments of Buckeye
Lake Dam. These limitations include limited data regarding embankment foundation conditions, fill
characteristics, seepage pathways and gradients, prior reconstruction efforts, and detrimental
modifications to the dam resulting from the construction of numerous homes and related
components. Nevertheless, the available data are sufficient to support the Districts opinion that
the likelihood of dam failure is high based on prior near-failures and adverse conditions at and
above normal pool, including but not limited to seepage, wall and dam misalignment, and
requirements on several occasions for emergency response actions to prevent breaching. Available
geotechnical data substantiates that the embankment is comprised of random, uncompacted
material without filters or cutoffs to intercept internal erosion processes that could lead to
breaching. The extent of cracks and depressions along the crest of the embankment, together with
collapsed structures which were built into the downstream slope of the dam, pose serious stability
related risks. Potential failure modes include internal erosion of the embankment fill and
foundation soils, instability of the embankment, and overtopping and erosion of the embankment.
Although additional hydraulic, loss of life, and economics data is recommended to better quantify
the consequences of dam failure, the District has determined that embankment breaching,
downcutting, and lake discharge and resulting flooding would most probably occur without
sufficient warning or evacuation time. Numerous residences built within the downstream
embankment slope and immediately downstream of the appurtenant structures would likely be
adversely impacted in the event of a breach. Considering the immediate proximity of the
downstream population, a catastrophic breach of Buckeye Lake Dam could pose unacceptable life
loss and economic consequences. Therefore, immediate interim risk reduction measures are
recommended to reduce risk of catastrophic dam failure as a result of breaching during normal
pool retention.
The District recommends that interim risk reduction measures be implemented immediately. The
District further recommends that comprehensive risk reduction alternatives be evaluated, selected,
and implemented by ODNR. Selection of remediation alternatives should be based on the potential
for proposed actions to reduce risk to a tolerable level. If no action is taken, the public would
remain at significant risk of embankment failure and subsequent flooding, even at normal pool
elevation. More detailed analysis of hydrologic and hydraulic parameters, using current modeling
methodology, and additional geotechnical site characterization are recommended. This site
characterization would be used to better determine when and where embankment failures are
most likely to occur (to improve emergency response planning), perform additional risk analysis,
and design the selected major remediation alternative(s).
Page IV
1 INTRODUCTION
The U.S. Army Corps of Engineers, Huntington District (the District) was tasked by the Ohio
Department of Natural Resources (ODNR) to conduct an assessment of the condition of Buckeye
Lake Dam and appurtenant structures, as well as to make recommendations for the repair,
operation, and maintenance of the dam utilizing engineering best practices. Specific efforts
included participation during technical meetings with ODNR staff, field reconnaissance, and review
of previous consultant reports and other technical documents, which included the ODNR's
continuing site evaluations, assessments of embankment and foundation conditions, and
replacement design alternatives. The Huntington District was also tasked to provide engineering
support to the ODNR during public meetings and technical briefings. This report summarizes
District evaluations of the dam's stability and related comprehensive risk reduction alternatives
along with recommendations for interim operations and maintenance. The report also presents
recommendations regarding more detailed geotechnical, hydraulic, and hydrologic analyses. While
this assessment is specific to Buckeye Lake Dam, the process and assessment methodology used
would be applicable to other dams statewide.
Task
Task 1
Task 2
Task 3
Task 4
Task 5
Task 6
Task 7
Action
Coordination Meeting with
ODNR
Review Existing Reports
Stakeholder Meeting
Site Visit/Reconnaissance
Community Meetings
Due Date
18 June 2014
Buckeye Lake Dam is part of Buckeye Lake State Park, situated near the edge of Millersport and the
Village of Buckeye Lake in Fairfield, Licking, and Perry counties of Ohio, approximately 23 miles
east of downtown Columbus, 9 miles south of Newark, and 22 miles west of Zanesville. The earthen
embankment was constructed from 1825 to 1832 and is approximately 4.1 miles long. Buckeye
Lake, previously named the Big Swamp and Licking Summit Reservoir, functioned to maintain
minimal water depths for navigation within adjacent and downstream reaches of the Ohio and Erie
Page 1
Canal System. Notably, the dam was not designed for the purpose of retaining a permanent
recreational pool or as a foundation for adjacent structures.
In 1894 the Ohio legislature designated Buckeye Lake as a public park. In 1895 the State sold
downstream portions of the embankment and adjacent acreages to private interests. These
interests constructed industrial and retail structures and leased undeveloped lands adjacent to, and
within, the embankment footprint for fishing camps and cottages. Subsequent development
included an amusement park, hotels, docks, and marinas. Access to the site was provided by
extensive road systems and by rail.
The State re-designated the lake and the state owned land as a state park in 1949. From 1949 to
the 1960s attendance for the adjacent amusement park began to decline, and park structures were
subsequently removed and backfilled with debris. Buckeye Lake continues to support recreational
uses such as fishing and boating and is not established for flood control. The dam is a partially
state-owned structure, for which ODNR has accepted operation and maintenance responsibility.
However, complex shared ownership and use creates ambiguities regarding the extent of mutual
responsibilities and liabilities for dam failure. Today Buckeye Lake State Park attracts many
visitors, and there are numerous residents who live adjacent to the lake and within the village of
Buckeye Lake.
Buckeye Lake Dam consists of an earthen embankment (West Bank and North Bank reaches), a
primary spillway (Amil gate spillway), a secondary spillway (Sellers Point spillway), low-level
drains, the Crane Lake closure structure, and the Thornport diversion structure. West Bank is 8400
feet long and is located to the west of the Sellers Point spillway. North Bank is 13,000 feet long and
is located to the east of the Sellers Point spillway. The maximum height of the embankment is
about 16 feet. The shoreline along about 40 percent of West Bank and all of North Bank is
protected with sheet piling. The sheet piling provides protection against wave related erosion and
was not designed as a structural component of the dam. The Amil gate spillway was designed to
maintain the normal pool level during frequently occurring rainfall events. The Sellers Point
spillway is a 472 feet long concrete ogee weir. It was designed to discharge water from the lake
during infrequently occurring floods. Both spillways have gated low-flow pipes that can be used to
lower the lake level to winter pool elevation. The Crane Lake closure structure and the Thornport
diversion structure are appurtenances that better assure impoundment of the lake and
management of the pool level.
Buckeye Lake surface area is 3,030 acres at the top of the dam (approximately El. 894.5 ft.) and
2,800 acres at summer pool (El. 891.75 ft.). Lake storage capacity is approximately 14,000 acre-feet
at summer pool elevation. The embankment was constructed using random, uncompacted earth fill
without filters, cutoffs, or foundation treatment. Historical mapping and reports indicate that two
borrow areas were used for embankment fill materials; however, the characteristics of these
materials and their placement locations within the dam were not documented. The dam failed
upon initial filling in 1832 in an area on the North Bank known as the Black Diamond Wreck site
and was repaired by placing 10,000 wagon loads of random earthfill consisting of coarse stone
Page 2
(Gardner, 1995). The project continued to be operated and maintained by the State of Ohio and
others until 1894. Subsequent operation and maintenance of the canal system required dredging,
on-site dredge materials disposal, and embankment protection. The reservoir also required
construction of diversion structures for both inflows and the discharge of excess storm waters to
the South Fork Licking River (SFLR) and Muskingum watersheds.
The site geology includes glacial outwash, glacial till, lacustrine, and alluvial deposits. Glacial
outwash, lacustrine, and alluvial deposits tend to be highly variable and intermixed with permeable
layers. These geologic conditions are complex and require extensive foundation characterization
and analysis for engineering design of a dam. A description of site-specific geology is included as
Appendix A. A limited number of soil borings were performed by Dodson-Lindblom Associates, Inc.
(DLA, 1987, 1995) and Paul C. Rizzo Associates, Inc. (1997) within the embankment, foundation,
and lake bed. The embankment materials were classified as clayey silts and silty clays with various
amounts of sand, gravel, and organics. Sand and silt lenses were also encountered within the
embankment. A layer of organic silt was encountered within the earthen foundation directly
beneath the embankment.
Elevation data for the dam are summarized in Table 2. For referenced pool elevations and project
features, the District assumed the National Geodetic Vertical Datum of 1929 (NGVD 29) in this
study.
Table 2: Pertinent Elevation Data (NGVD 29)
Feature
Approximate Top of Dam
27 May 1968
10 June 1990 High Pool
Pool When Increased Seepage has been Observed
Sellers Point Spillway Crest
Amil Gate Spillway Crest
Summer (Normal) Pool
Winter Pool
Elevation (ft.)
893-897
894.17
893.74
892.25
892.2
891.75
891.75
888.75
The USACE memorandum dated 29 March 1939 (Appendix G) documented conditions observed
during reconnaissance performed during the period of 14 to 15 March 1939 and included general
recommendations. Based on frequently observed seepages through the embankment,
strengthening of the embankment was recommended. This through-seepage was attributed to
scour of embankment soils following failure of sheet pile and masonry walls at several locations,
animal burrowing, and by decomposition of embedded tree roots. Preliminary hydraulic
calculations suggested the spillway capacity might have been inadequate for a flood with a 110year recurrence interval. Therefore it was recommended to increase the discharge capacity of the
spillway from 3,600 to 28,000 cubic feet per second.
Page 3
USACE conducted site reconnaissance on 28 June 1990 (Appendix G) to document defects and other
problematic site conditions observed during and subsequent to a storm event that occurred 08-09
June 1990. During the storm event, which continued for 6 hours, 3.5 to 4.0 inches of rain fell within
the Buckeye Lake and adjacent drainage areas. Initiation of internal erosion was observed in a
failing foundation wall within the basement of a residence at Station 153+75. The Ohio National
Guard was deployed to sandbag the floor area adjacent to the failing wall to counterbalance the
hydrostatic head. Low areas along the dam crest were sandbagged to prevent dam failure.
Embankment seepage was noted at Lakeside, Sellers Point, Black Diamond Point, and the
Amusement Park. However, it is probable that not all seepage areas were identified and adequately
documented due to inundation of the dam toe. Several embankment subsidence areas and cavities
were noted adjacent to the sheet pile and masonry walls were noted in the 1990 reconnaissance.
Depressions within the embankment were also noted.
Engineering reports from consultants submitted during the period from 1978 to 2003 defined
project conditions from visual observations, limited subsurface exploration data, and stability and
seepage analyses. These reports also included the submittal of preliminary geotechnical and
structural design concepts for the remediation of deficiencies as cited by some consultants. Some
reports included limited drainage basin hydrology and hydraulic characterizations and related
modeling efforts. District reviews of these reports and analyses formed one of the bases for
subsequent recommendations. However, the District does not concur with all of the consultant
findings and recommendations. Detailed discussion and resolution of variances among these
reports was not included in the scope of this assessment.
A USACE report, as prepared by GAI Consultants, Inc. (1978), concluded that the overall condition
of the facility was poor and potentially unsafe. The consultant identified potential serious
maintenance and operations related problems including an inadequate spillway system, seepage
Page 4
through the embankment, instability of the shore protection walls, and embankment irregularities
and distress along the dam crest.
Dodson-Lindblom Associates , Inc. (DLA, 1987) performed a study of spillway and lake storage
capacity requirements and an analysis of embankment structural integrity. This analysis concluded
that the embankment was stable under normal and elevated pool conditions. However, the
consultant also noted that this preliminary conclusion was limited by assumptions regarding
probable hydrologic events and durations and by inadequate information with respect to
residential basement wall designs and related features. Proposed embankment remedial actions
included reach specific construction of a partial cutoff wall or embankment toe drain, diversion of
all drainage away from the reservoir, and removal of all four- to six-inch or larger diameter trees
from the crest. The consultant recommended the construction of a U-shaped, concrete gravity
spillway at Sellers Point and the replacement of the existing spillway with a gated outlet structure.
These spillway recommendations were implemented in 1992. Additional recommendations
included the construction of a concrete parapet wall along the crest of the embankment and
modifications to the SFLR to improve conveyance. SFLR channel cleaning was completed in 2014.
Gardner and Associates (1995) provided technical responses to the 1987 DLA report, including
statements that the dam had the following deficiencies: the embankment was poorly compacted
and leaky, slope instability occurred at pools greater than elevation 892 feet, and the dam would be
overtopped during the probable maximum flood (PMF). The consultant also concluded that the
construction of a parapet wall could result in an embankment failure during PMF, which was
understood by this consultant to require a lake pool elevation of 896.5 feet, due to the effects of the
resulting increase in hydrostatic head. The consultant therefore recommended that PMF related
conditions be addressed by other alternatives.
Dodson-Lindblom Associates , Inc. (DLA, 1995) evaluated the sheet piling at Buckeye Lake. Based
on visual and ultrasonic investigations and analysis, the consultant recommended the 1940s and
1960s sheet piling sections be replaced. The 1940s sheet piling installation was determined to have
reached the end of its useful life, requiring approximately 1,100 linear feet of replacement piling.
The 1960s piling installation was determined to have 10 to 15 years of remaining life, resulting in
the recommendation for replacement of an additional 3,680 linear feet.
DLA responses to Gardner and Associates (1996) comments included reanalysis of embankment
slope stability and an underseepage analysis. Resulting slope stability safety factors were stated as
being slightly below the generally accepted minimum required safety factor of 1.5 at the Sellers
Point Spillway crest elevation (892 ft.). Additionally, slope stability analyses were not performed
for pool levels higher than 892 feet.
Gardner and Associates (1996) evaluated the adequacy of the U-shape, concrete gravity spillway to
pass the outflow of the PMF or other high pool events and thereby prevent overtopping of the
embankment crest during these events. Consultant reanalysis of spillway discharge conditions
established that the crest elevation was not sufficient to prevent PMF overtopping of the
embankment. Therefore, Gardner and Associates recommended modifications to the U-shaped,
Page 5
concrete gravity spillway. These modifications included addition of four radial arm gates along the
spillway crest which would function to regulate PMF discharges.
DLA (1996) noted that there were some inconsistencies in the analysis by Gardner and Associates.
However, both consultants determined that embankment overtopping would occur during the PMF.
Additionally, DLA noted that Gardner and Associates proposed spillway modifications would not
be sufficient to regulate PMF related discharges and prevent embankment overtopping. Therefore,
DLA determined that raising the embankment crest, together with Sellers Point spillway
modifications, would be required to minimize risk of overtopping and preclude uncontrolled
release of lake waters to the SFLR during the PMF.
Paul C. Rizzo Associates, Inc. (1997) concluded that the dam crest could be raised an additional two
feet without compromising embankment stability. This determination was established by field
observations, subsurface explorations, laboratory testing, piezometer and observation well data,
evaluations, and stability analysis. The consultant conclusions were based on limited information
and on the assumption that house foundations built into the embankment would not contribute to
failure. This consultant also stated, without the opportunity to obtain additional hydrologic and
hydraulic data, analysis, or modeling, that raising the embankment crest to elevation 896.5 feet to
retain the PMF would only marginally affect discharge and flood related impacts downstream of the
SFLR.
T. Davis Syndor (2002) submitted vegetation evaluations and maintenance recommendations and
concluded that tree roots stabilize slopes and have been used to armor levees. This conclusion
seems to be based on the assumption that mature tree root systems would not result in additional
embankment defects and internal erosion pathways. Additional vegetation related concerns
referenced toppling of mature trees and related root wad displacements of embankment soil.
A DLZ report (2003) included mapping of the embankment, evaluations of trees and related defects
along the embankment crest, an assessment of sheetpile wall conditions, and conceptual remedial
designs intended to bring the embankment into compliance with dam safety requirements. Project
mapping (perfomed in 2000) included comparisons with the 1990 surveys. Vegetation
maintenance recommendations were reviewed. Evaluations of sheet pile wall systems included
visual reconnaissance, ultrasonic testing, coupon sampling, and test pit excavations. Using the
sheet pile data, the consultant established rates of corrosion for the walls. Calculations were
performed to determine factors of safety based on the yield stress limits as defined by the steel
thicknesses. Factors of safety (yield stress=1.0) ranged between 1.2 and 1.9. The 1948, 1961, and
1962 sheet piling strengths were at or below the allowable stresses and approaching the yield
stresses. A schedule was developed for phased replacement of the dam sheet pile walls. Data from
geotechnical exploration programs were also reviewed by DLZ, and during this phase of project
evaluations, DLZ considered embankment improvement alternatives as well as requirements for an
adjacent retention structure to be constructed within the lake. The consultant generally defined the
soils within the lake, in the area of the proposed adjacent structure, as consisting of loose sediment
and soft, medium, and stiff clayey silts and silty clays with interbedded sand and gravel layers.
Alternatives for the adjacent structure included post and panel wall, double row sheet pile wall, IPage 6
wall, inverted T-wall, and pre-cast concrete box. A double row sheet pile wall was the
recommended remediation alternative.
Fuller, Mossbarger, Scott & May Engineers (FMSM, 2003) developed a watershed management plan
for the SFLR. Five alternatives were presented to reduce flooding downstream of the Sellers Point
spillway. Alternatives included design and construction of an outlet to Jonathon Creek, design and
construction of an outlet at Maple Bay, installation of gates at the Sellers Point Spillway,
modifications to improve conveyance within adjacent and down channel reaches of the SFLR, and
design and construction of channels which would divert flows from the Kirkersville Feeder canal
and a reach of the SFLR to a tributary stream north of Interstate 70. The consultant recommended
an alternative which included modifications to improve conveyance of the SFLR. These
modifications are now complete.
District staff continued to review the consultant reports and other data obtained during site
reconnaissance and open house public meetings. As previously noted, these reports contained
relevant geotechnical and hydraulic data. During this evaluation the District relied substantially on
these consultant reports, field observations, and dam and levee safety guidance.
The District has concluded that the consultants were in general agreement regarding geotechnical
conditions and relic construction methods as limiting their ability to analyze embankment
conditions. Sufficient approximations of complex site conditions, resulting from both initial
embankment construction and subsequent modifications, could not be made for these analyses.
Modifications included maintenance, repairs, and the placement of numerous residential and
commercial structures within and adjacent to the embankment. Embankment sections evaluated
for stability were analyzed without sufficient consideration of excavated areas where numerous
privately owned structures have been constructed into the dam. Paul C. Rizzo Associates, Inc.
(1997) modeled a hypothetical embankment section which included a house structure. However,
this house structure condition was predicated on assumed wall characteristics. Recent
observations of basement walls, foundations, and retaining walls indicate substantially less
favorable site conditions than those considered by this consultant.
Seepage and internal erosion related embankment and foundation conditions were not adequately
evaluated in the previously referenced reports. The term internal erosion is used generically to
describe erosion of particles by water passing through a body of soil. Internal erosion is a
significant threat to earthen embankment stability and can lead to dam failure. Types of internal
erosion mechanisms include backward erosion piping, concentrated leak erosion, and contact
erosion, resulting in embankment subsidence and breaching.
Limited seepage analyses were performed by consultants to establish phreatic surfaces as related
to embankment slope stability, but only one analysis was performed to address internal erosion
related failure modes. This simplified flow net analysis was used to approximate factors of safety
against initiation of internal erosion through the embankment foundation, as was cited in DLAs
Page 7
responses to Gardner and Associates Report (1996). This analysis resulted in acceptable factors of
safety. However, as with the previously referenced stability analyses, the embankment section
evaluated did not include fill characterization, excavations, embedded structures, or other
anomalies that would increase embankment susceptibility to internal erosion by shortening
seepage paths and forming pathways for concentrated seepage flows. Additionally, this analysis did
not evaluate the potential for internal erosion through the embankment. The analysis also assumed
a spillway crest defined pool condition of 892.2 feet. However, seepage has been observed to
increase within various embankment locations at higher pools. Evidence of internal erosion
initiation, such as subsidence features in the downstream embankment toe area, was encountered
during the August 2014 inspection. Additionally, none of the previously referenced models were
calibrated using piezometer readings or seepage observations during elevated pools. Due to
observed conditions indicative of internal erosion processes and excessive seepage through the
embankment and foundation at numerous locations, as well as limitations to the above mentioned
seepage analysis, the District does not consider this seepage analysis to be comprehensive or
reliable for evaluation of Buckeye Lake Dam conditions. Therefore, the District has concluded that
these analyses do not sufficiently define defects as observed in the field during prior high pool
conditions and during the August 2014 reconnaissance, and that the result has been the apparent
underestimation of internal erosion and overtopping failure risks.
The Buckeye Lake PMF was originally developed in 1987 by Dodson-Lindblom Associates for the
Spillway Adequacy and Embankment Stability and Seepage Study. As part of the Dodson analysis,
the Snyder Method and Soil Conservation Service (SCS) Method were both used to develop
synthetic unit hydrographs for the Buckeye Lake watershed. This practice is currently not
recommended due to the vast differences in parameter development between the two methods.
For consistency, only one unit hydrograph method should be considered for use during a
hydrological analysis.
The Probable Maximum Precipitation (PMP) rainfall referenced in the Dodson study was 23.6
inches using a 6-hour duration event based on Hydrometeorological (HMR) Report 51. HMR 51
provides estimates of area-averaged PMP for the United States east of the 105th meridian. HMR 52
provides a procedure for obtaining drainage area averaged PMP amounts from the storm area
averaged PMP provided in HMR 51. This procedure determines isohyetal values for up to twelve 6hour periods, a total of 72 hours, for an elliptical precipitation pattern. Included in the technique
are adjustments for both basin shape and effects of storm pattern orientation. The Dodson study
does not appear to have followed the procedure outlined in HMR 52.
In 2000, Fuller, Mossbarger, Scott, & May Engineers (FMSM), published an updated study of the
PMF for Buckeye Lake. The FMSM study followed the procedures outlined in HMR 52. However,
the PMP was focused on a 6-hour duration instead of a 72-hour duration event. The District
recommends that the PMF be updated using a 72-hour duration event and by following the
procedures outlined in HMR 52. Furthermore, other storm events have occurred in the Buckeye
Lake basin since the Dodson study was published in 1987. Precipitation and streamflow data for
these storms is available, and updated unit hydrographs could be computed and used to update the
Page 8
PMF. Wave run up and freeboard calculations should also be considered to provide additional
information. An updated PMP study was developed for the State of Ohio in 2013. This study could
be used to evaluate the probability of dam overtopping in lieu of HMR 51 and 52.
The use of frequency rainfall data to develop storm inflow and pool elevations related to frequency,
which, in lieu of statistical analysis of historical pool levels, would provide a hypothetical
measurement of probability/frequency of occurrence which is a major component of risk analysis.
Projected frequency intervals for flood events could be analyzed using available historical inflow
and pool elevation data. If this historical data is not available, inflow data could be estimated using
frequency rainfall from the National Weather Service NOAA Atlas 14 and computed using a
hydrologic software program such as HEC-HMS. Pool elevations based on the inflows computed
from the frequency rainfall could also be estimated in HEC-HMS. The data computed from this
analysis could then be used to identify an estimated frequency of overtopping. This analysis would
also provide a relative indication of the frequency of dam overtopping. The District recommends
that existing stream gages be modified or new gages installed, to measure and record inflow and
outflow data daily.
The last dam break model for Buckeye Lake was developed in 1987 using National Weather Service
(NWS) DAMBRK. DAMBRK was a DOS-based numerical model developed in the late 1970s to
forecast downstream flooding resulting from dam failures. Dam breach parameters were
calculated using the latest 1980s criteria and input into the DAMBRK model to simulate flow
through a breach in the dam. At that time, DAMBRK was the best method for analyzing a dam
breach.
Additional methodology is now available to assess the safety of a dam and consequences associated
with failure. Criteria for developing breach parameters have changed since the referenced dam
break model was developed, and that model is no longer used. Additional studies have been
conducted which now provide a wider array of breach characterizations. Dam break models are
now simulated by unsteady flow analysis using HEC-RAS, a software package developed by the US
Army Corps of Engineers Hydrologic Engineering Center.
The recently developed 100-year storm inundation mapping for the Buckeye Lake Emergency
Action Plan (EAP) was revised in 2012. This mapping shows impacted areas immediately
downstream of the project. However, impacted areas further downstream within locations, such as
the City of Newark, have not been included. The SFLR drainage area and Buckeye Lake discharges
should be modeled for areas downstream of the dam to and including the headwaters of Dillon
Lake. Updated modeling would incorporate embankment breach parameters as established by the
latest criteria. Numerous potential failure and non-failure scenarios would then be calculated. This
analysis would also include major tributaries of the Licking River as well as main stem conveyance
so that backwater conditions could be defined for embankment failure or non-failure scenarios.
Inundation mapping could be generated based on the results of the new dam break model and
updated PMF for failure and non-failure scenarios. More accurate flooding consequences could
then be determined based on the results of the new model. Failure consequences, such as potential
loss of life and property damages, could be determined using travel times, Federal Emergency
Page 9
Management Agency (FEMA) delineations, and the revised inundation mapping. The new dam
break models and inundation maps could also be used to update the current Emergency Action
Plans (EAP) to assist state, county, and local officials during potential emergencies.
Prior to the 25-28 August 2014 reconnaissance, the USACE published a notice of intent, which
included a request for input from property owners and others. Property owners were asked to flag
areas of concern and to provide photographs and other information for review during the
reconnaissance. The public also provided comments to the District and ODNR during open house
meetings on 28 and 29 October and 19 November 2014. During the period from 25-28 August and
15 December, Huntington District, ODNR, and local interests conducted embankment, structures,
spillway, and shoreline evaluations. Limited reconnaissance of South Fork Licking River and
adjacent canal reaches was also completed. The pool elevation at the time of the 25-28 August
inspection was 891.8 feet. No precipitation occurred during this inspection period.
During the reconnaissance, staff encountered numerous defects which could affect embankment
stability (see Figures 1-3). These conditions were observed throughout both the West Bank and the
North Bank. These defects included docks, wall systems, house foundations and adjacent
structures, embedded utilities, and subsidence areas. Indications of additional defects include
structural misalignments, several drainage sumps, and wet areas within the entire 4.1 mile reach of
the embankment. However, exterior observations of the 370 homes were limited since complete
structural and geotechnical analysis could not be effected during the Districts reconnaissance and
evaluations of the Buckeye Lake Dam.
The observed defects and related potential failure modes are shown in Table 3. It should be noted
that the embankment overtopping failure mode would include subsequent embankment
downcutting and breaching. Internal erosion failure modes encompass a variety of interrelated
erosion mechanisms and subsequent breach. These include but are not limited to backward
erosion piping, concentrated leak erosion, and contact erosion.
Page 10
Table 3: Buckeye Lake Embankment Defects Observed During 2014 USACE Site Recoinnaissance with Related Potential
Failure Modes
Embankment
overtopping
Internal
erosion
X
X
X
Slope
failure
X
X
X
Page 11
Figure 1. Typical Embankment Distress Observations 1) Differential settlement of structure built into
crest/embankment longitudinal cracking 2) Failing masonry unit wall supporting landside embankment materials 3)
Unsupported excavation into downstream face of embankment which could cause weakening of embankment soils and
embankment failure 4) Several rows of masonry unit walls were noted in old house foundations likely indicating seepage
related displacement
Page 12
Figure 2. Typical Distress Observations 1) One of many depressions behind masonry wall 2) Tree with root system
spanning the entire embankment crest 3) Numerous cracks within base of, and pipe/utility penetrations through,
masonry wall observed during winter pool drawdown 4) Dock structures cantilevering from the dam put stress on the
sheetpiling for which it was not designed
Page 13
Figure 3. Other Wall and Seepage Observations 1) Displaced portion of masonry wall 2) Numerous rust holes observed
in sheetpiling 3) Several depressions possibly due to boils, together with very shallow ground water conditions, were
observed 4) Location of persistent seepage near Black Diamond Point
Water quality testing was performed for piezometers and adjacent lake waters within the
embankment to determine upstream to downstream seepage continuity with the lake. At one
piezometer, B-13A-2, water was measured to have comparable specific conductance, dissolved
oxygen, pH, and temperature when referenced to lake water. These similarities in piezometer and
lake water parameters may be indicative of a defect within the embankment foundation at this
location. Piezometer B-13A-2 is located near Station 113+00 (referencing DLZ, 2003 stationing) on
the downstream slope of the embankment, and the sensing zone is located in the dam foundation.
Although this seepage relationship was established for only one piezometer, it is likely that,
considering the limited number of piezometers along the 4.1 miles of embankment, other seepage
locations exist.
Page 14
During the reconnaissance the SFLR riparian clearing and channelization project was noted to have
resulted in fluvial geomorphic impacts which will require additional excavation of depositional
features and bank stabilization. These requirements could be included in a revised operation and
maintenance manual to better assure necessary long-term bank full channel conveyance.
As referenced, Ohio designated Buckeye Lake as a State Park in 1949. The District has determined,
using applicable engineering standards of practice, that the Buckeye Lake Dam embankment does
not meet dam safety standards. Furthermore, it is the Districts opinion that the likelihood of dam
failure is high and poses significant risks to the public, based on prior near-failures and adverse
conditions at and above normal pool, including but not limited to seepage, wall and dam
misalignment, and requirements on several occasions for emergency response actions to prevent
breaching. Potential dam failure modes include internal erosion of the embankment fill and
foundation soils, instability of the embankment, and overtopping and erosion of the embankment.
The District concluded that the relic embankment, constructed as a canal system component in
1832, was completed with currently unacceptable foundation and fill placement practices, which
did not include filters or positive cutoffs. Additionally, the land transfer of 1894, which included a
portion of the embankment and adjacent lands, did not restrict the placement of structures within
the dam. This transfer allowed for the construction of numerous residential and commercial
structures, which are defects as defined by established dam safety standards. Concerns regarding
these structures include excavation of embankment fill during construction, shortened seepage
paths, and resulting higher global and exit gradients, concentrated leak erosion along embankmentwall foundation contacts and associated utility alignments, increased probability of an unfiltered
seepage exit condition developing due to embankment material filter incompatibility with house
foundation drains, and additional embankment instability resulting from house foundation and
retaining wall defects.
The ODNR has designated Buckeye Lake Dam as a Class I high-hazard potential dam. A high-hazard
potential dam classification signifies the adverse consequences to lives and property that would
occur in the event of a catastrophic dam failure. Additionally, consequences of embankment failure
and spillway releases would include economic damages and probable loss of life within adjacent
and downstream areas. The District recommends that ODNR continue to reevaluate the
consequences of embankment failures and South Fork Licking River flooding to better define
present extents of inundation damages and loss of life. Selection of remediation alternatives should
be based on the potential for proposed actions to reduce risk to a tolerable level. As previously
mentioned, limited stability analyses have not adequately defined embankment defects and failure
modes, which resulted in the apparent underestimation of internal erosion and overtopping failure
risks. The District has determined that embankment breaching, downcutting, and lake discharge
Page 15
and resulting flooding would most probably occur without sufficient warning or evacuation time.
Estimates for breach, non-breach, and incremental consequences of this unstable embankment
have not been fully developed. However, numerous residences built within the downstream
embankment slope and immediately downstream of the embankment and appurtenant structures
would likely be adversely impacted in the event of a breach.
5 RISK REDUCTION
The US Army Corps of Engineers (USACE) risk assessment process is a systematic and evidencebased approach for quantifying and describing the nature, likelihood, and magnitude of risks
associated with existing and future conditions without actions and the values of the risk reduction
resulting from a changed condition due to some action. The risk management process involves
determining problems and initiating actions to identify, evaluate, select, implement, monitor, and
modify actions taken to alter levels of risk, as compared to taking no action. The purpose of risk
management is to choose and implement technically sound integrated actions to reduce risks after
consideration of the effectiveness and costs of each increment of risk reduction. Risk management
for dams includes short-term Interim Risk Reduction Measures (IRRMs); improvements to
monitoring and surveillance activities, emergency action planning, operations and maintenance,
and staff training; and implementation of comprehensive risk reduction alternatives.
Additional information would be obtained by implementing the USACE risk assessment process for
Buckeye Lake Dam; however, this process was not included in this scope of work. Presently ODNR
uses an indexing approach for assessing risk and prioritization of its dams, including 56 Class I
dams.
These interim risk reduction measures would be implemented to reduce the probability and
consequences of catastrophic failure, to the extent that is practicable, during the period that
comprehensive risk reduction alternatives are selected and finalized. The District recommends
implementation of the following IRRMs.
1) Draw down to winter or lower pool elevation to partially address existing critical embankment
conditions until completion of selected comprehensive risk reduction alternative(s). This
measure would increase storage capacity for storm event inflows and minimize the probability
of reaching pool elevations where excess seepage is known to occur, thus reducing risk of
internal erosion related failure. In addition, operating with a decreased volume of water stored
in the lake will reduce the flooding impact in the event of a catastrophic dam failure.
2) Update the Emergency Action Plan and implement related training and exercises to improve
emergency preparedness.
3) Educate the public about risks, and implement a system for the public to communicate or report
potential adverse conditions to ODNR.
4) Stockpile sand and bags onsite for emergency responses.
Page 16
5) Stockpile emergency filter aggregate and stone on site for emergency responses.
6) Re-establish and maintain emergency access to and along the dam crest to transport and allow
placement of sand bags, aggregate, and stone at critical areas.
7) Complete embankment crest profile surveys to better determine locations of subsidence areas,
and sandbag these areas to temporarily restore them to required elevations.
8) Continue site characterization to better locate and define defects. These efforts would facilitate
planning for and implementation of additional emergency responses. These efforts may include
the following:
a) Conduct video inspections of sewers adjacent to the downstream toe of dam.
b) Conduct geochemical characterization to better define lake water, embankment seepage,
outslope area springs, and extents of comingling.
c) Perform geophysical investigations and additional subsequent subsurface explorations
together with sampling and laboratory testing to better define embankment fill
characteristics and adjacent wall system voids and subsidence features. Geophysical
investigations could include Multichannel Analysis of Surface Waves (MASW) and Electrical
Resistivity Measurements.
d) Using data obtained during subsurface investigations and high pool seepage observations,
complete more comprehensive embankment characterization and stability and seepage
analyses and modeling.
e) Perform thermal sensing of the embankment, house foundations and walls, and adjacent
areas to define voids and seepage conditions.
9) Reroute residence drainage and utility features away from the embankment crest and backfill
excavations with compacted impervious materials to reduce risks associated with internal
erosion failure mechanisms.
10) Consider clearing and grubbing of large trees located within the dam crest and adjacent to the
wall systems. Root excavation areas would then be backfilled and compacted with suitable
impervious material, These measures would reduce risks associated with internal erosion
mechanisms.
11) To the extent allowable, prevent additional construction of residences and appurtenant
structures (i.e. wall systems, patios, swimming pools, sidewalks, and utilities) within the
embankment, which would otherwise constitute additional embankment defects.
12) Limit dock construction or reconstruction to require placement of floating or self-supported
structures separate from the wall system and embankment, to prevent further damage to the
embankment and wall system.
13) Continue to purchase properties, as they become available on the open market, to increase
embankment access and stockpiling areas.
14) Modify existing gages or install new gages to measure and record inflow and outflow data to
provide data for hydrologic and hydraulic analysis, to better establish operational schedules,
and to provide for emergency responses.
15) Complete additional hydrologic and hydraulic analysis to better determine optimum discharge
requirements and consequences, and revise lake spillways operations schedules accordingly.
Page 17
1) Considering the size and high hazard potential classification of the dam, one or more full-time
dam tenders should be employed.
2) Continue to work with the public and others to monitor and evaluate defects or other
potentially problematic conditions along the embankment crest and outslope areas during both
extended rainfall events and elevated lake pools. Conduct workshops and provide dam safety
training to identify these conditions. Locations of concerns should be mapped, and annotated
photographs should be retained by ODNR to reference site conditions.
3) Implement comprehensive site surveillance plans, including defined response requirements
during elevated pools, to affect timely emergency actions.
4) Complete additional embankment crest profile surveys during 2015 and thereafter at yearly
intervals.
5) Read piezometers and observation wells monthly when lake elevations are at or below El.
892.25 ft (Sellers Point Spillway crest). Since embankment seepage has been observed at
elevations above 892.25 ft, the piezometers and observation wells should be read more
frequently during lake impoundment above this pool in order to better correlate hydrostatic
heads and phreatic surfaces within the embankment and foundation to lake pool levels.
6) Install additional piezometers, and obtain readings to better define hydrostatic head and
related stability and seepage conditions within the embankment crest, slope, toe, and adjacent
downstream areas.
7) Monitor embankment wall systems since many sections of sheet piling (1948, 1961 and 1962)
were determined to be essentially already at or beyond their allowable stress limit (DLZ,
2003). These sections of sheet piling may have been subjected to additional corrosion related
loss of steel, which would continue to affect the stability of the wall in the near future.
8) Monitor subsidence features and backfill with suitable impervious materials.
9) Document and characterize maintenance dredging and survey sediment depositional areas
adjacent to the embankment.
10) Inspect, monitor, and maintain spillway discharge stilling features, downstream channel slope
protection, and effect vegetation controls to ensure required conveyance. The established
operations plans could be modified to provide for additional releases from the Sellers Point
Spillway conduits to improve downstream environmental quality.
11) Maintain dense grass cover within embankment and downslope areas.
12) Dredge and maintain SFLR conveyance to reduce out of bank flooding conditions.
13) Measure and record inflow, outflow, and pool elevation daily.
This abreviated assessment has resulted in the recommendation that comprehensive risk reduction
actions should be considered for Buckeye Lake Dam. The District suggests several alternatives that
may better assure public safety. If no action is taken to make significant structural improvements,
then the existing defects would become more severe, resulting in increased public risk due to
embankment failure and subsequent flooding. The risks identified during normal pool loading are
most probably high. The District also acknowledges that this project is not a flood risk management
Page 18
structure and is intended for recreational purposes only. The following risk reduction alternatives
are based on reviews of consultant reports together with site reconnaissance and public input.
Breach of the embankment, dewatering the lake, and re-routing drainage from the lake area
Relocation of downstream at-risk population
Repair or replacement of the dam
Partial rerouting of inflows to and outflows from the lake without changes to the dam
Modification or addition of outlet structures
Installation of toe drains, relief wells and stability berms at locations along existing dam
5.3.1 BREACH OF THE EMBANKMENT AND REROUTING DRAINAGE FROM THE LAKE AREA
Breaching the embankment, dewatering the lake, and rerouting drainage from the lake area could
mitigate the consequences of dam failure. Although Buckeye Lake was not designed as a flood risk
reduction project, rerouting drainage could result in additional localized flooding and downstream
channel erosion. Additional adverse impacts would include degradation within adjacent channels,
elimination of recreational benefits, and significant economic impacts. Furthermore, inadvertent
impoundment of localized storm event runoff may occur. Significant adverse local economic,
cultural, and social impacts would occur.
Relocating the downstream at risk population, including those residing on the dam, would reduce
the potential for loss of life and economic consequences from flooding. Relocating this population
would be disruptive, costly, and most probably not allowable under existing ownership rights.
Significant adverse local economic, cultural, and social impacts would occur.
Repair or replacement of the existing dam would require resolution of complex ownership issues.
Either of these alternatives would substantially address embankment deficiencies and better assure
safe operation of the dam or replacement structure. These actions would reduce the risk of dam
breach related downstream flooding. Additionally, privately owned structures within and on the
existing dam embankment would be less susceptible to seepage and internal erosion related
conditions. Significant impacts to the lakeside property owners would occur during and after
construction. Additional real estate interests would be required, and existing private property
ownership rights would require subordination to better assure the continued safe operation and
maintenance of the dam and adjacent structures.
Page 19
5.3.4 PARTIAL REROUTING OF INFLOWS AND OUTFLOWS FROM THE LAKE WITHOUT CHANGES
TO THE DAM
Rerouting of inflows to and outflows from the lake could somewhat mitigate the risk of dam failure
by reducing the probability of elevated pool related breaching. Partial diversions of inflows and
outflows from the lake to adjacent drainage features could result in increased localized flooding.
Lake water quality would be degraded by this proposed action and recreational uses diminished
within the area. Adverse economic impacts would be similar to those as previously described for
alternative 5.1.2.
Modifications to the existing Amil gate or Sellers Point spillways together with additional outlet
structures would regulate discharges to adjacent drainage features. Controlled diversion of
outflows from the lake would somewhat mitigate the risk of dam failure by reducing the probability
of elevated pool related breaching. However, these modifications would not signicantly reduce
risks associated with previously referenced geotechnical embankment failure modes. Additionally,
diverting outflows to adjacent drainage could result in increased localized flooding.
5.3.6 INSTALLATION OF TOE DRAINS, RELIEF WELLS, OR STABILITY BERMS ALONG EXISTING
DAM
Installation of toe drains and relief wells along the toe of the embankment would reduce gradients
within the foundation; however, these features would not address embankment through-seepage
conditions. While installation of stability berms would reduce the potential for initiation of some
internal erosion mechanisms, berm construction would require access through adjacent lands and
removal of private structures along the toe of the dam.
The District has made observations and formed recommendations that are related to, but are
outside the scope of, this report. However, ODNR may wish to consider these points in its decision
making process, so they have been briefly described below.
Spillway adequacy and SFLR conveyance should be re-evaluated during the continuing
design phases to further determine required discharge conditions and to establish the
basis for additional modifications.
Extents and long-term functionality of the SFLR channel improvements project, together
with down channel conditions, should be reviewed. This review should include FEMA
Page 20
The lake and adjacent discharge channels, together with tributary and SFLR aquatic and
riparian habitat areas, are severely impacted by baseline environmental conditions.
These impacts include intermittent stranding of fish, lack of vegetation related shading
and habitat, high seasonal water temperatures, and reduced dissolved oxygen.
Proposed actions could include modification of spillway operations to maintain low flow
conditions which would result in improved aquatic and riparian habitats.
During site reconnaissance and public meetings, several property owners discussed
individual and collective interests in continuing to review project proposals and
alternatives which would better assure long term operational requirements for Buckeye
Lake. Therefore, the District recommends that ODNR continue to schedule public
meetings with these property owners and others during the selection process. ODNR
would review this input to better assure participation of interested parties. A summary
of findings from these coordination meetings would become a part of the decision
making process.
Page 21
6 CONCLUSIONS
The District has completed assessments which included a review of project history (including past
failures), technical publications, site reconnaissance, public coordination, and identification of
defects. Upon completion of these tasks, the District recommends that immediate non-structural
risk reduction measures should be implemented, and comprehensive risk reduction alternatives
should be further analyzed, selected, and effected by ODNR.
The District acknowledges data limitations, as did the previously retained consultants, Ohio
Department of Natural Resources, and the public. These limitations included geotechnical,
hydrologic, and hydraulic information required for more comprehensive analysis and risk
assessments of Buckeye Lake dam. Specifically, there is limited data regarding embankment
foundation conditions, fill characteristics, seepage pathways and gradients, prior reconstruction
efforts, and detrimental modifications to the dam resulting from the construction of numerous
homes and related components. Nevertheless, the available data are sufficient to support the
Districts opinion that the likelihood of embankment failure is high based on adverse conditions
existing and occuring frequently at and above normal pool, posing significant risks to the public.
Prior experience, together with consultant reports and evaluations, input from ODNR including the
determination of the project as a Class I high hazard potential dam, project performance history,
and site reconnaissance resulted in the Districts conclusion that the Buckeye Lake Dam
embankment has extensive defects requiring comprehensive risk reduction actions. ODNR should
consider comprehensive risk reduction alternatives based on the outcome of site geotechnical and
hydraulic characterization and further evaluations of project risk. ODNR should consider the
implementation of the preferred alternatives. Concurrently with evaluation, selection, and
implementation of comprehensive risk reduction actions, ODNR should consider the immediate
implementation of IRRM and O&M recommendations. It should be emphasized that IRRMs, by
definition, are interim measures designed to immediately reduce risk as much as practicable until
comprehensive risk reduction measures are completed.
Page 22
APPENDIX A
Geology and History of Buckeye Lake
Regional Geology
Buckeye Lake Dam is in Fairfield, Licking, and Perry counties of Ohio, approximately 23
miles east of downtown Columbus, 9 miles south of Newark, and 22 miles west of
Zanesville. It lies in the Till Plains section of the Central Lowlands of the Appalachian
Plateau. The lake lies near the far eastern boundary of the edge of the low Plateau as
shown in Figure A.1. The Till Plain is virtually featureless except for low broad
successions of end-moraines and a few large stream valleys that cut up to 50 feet
below surface. The western and northern parts of the Appalachian Plateau were
glaciated during the Pleistocene Ice Ages, which resulted in the hills being of lower relief
and the valleys more broad. Buckeye Lake is located just west of this boundary.
In the Pleistocene, there were four major glacial advances and retreats recognized in
North America; the Nebraskan, Kansan, Illinoian, and Wisconsin. The last two glacial
episodes, the Illinoian and Wisconsin covered the area of Buckeye Lake and had the
greatest impact. The Illinoian Glacial Stage (~300,000 to 130,000 years ago), and
Wisconsin Glacial Stage (~24,000 to 14,000 years ago in Ohio) are major divisions of
geologic time and resulted in the deposition of extensive glacial deposits in North
America during the late Pleistocene. Pre-existing valleys were blocked with glacial
outwash, streams were diverted, and modified drainage patterns were formed in areas
untouched by glacial ice. The landforms, which are characteristic of those formed by a
dynamic river system, resulted during long periods of time in regions of moderate
elevation underlain by thin and gently dipping sedimentary beds with varying resistance
to erosion. Many of the areas that remained prominent were sandstone ridges that were
more resistant to erosion. After the Illinoian glaciation, the Sangamonian interglacial
period lasted approximately 100,000 years, before the subsequent Wisconsin Glacial
episode commenced, during which, streams eroded much of the glacial outwash
deposited during the Illinoian episode.
The Wisconsin ice eroded and transported additional entrained rock debris. Glacial till
was deposited directly by the glacier and is derived from subglacial erosion and
entrainment from movement of the ice over unconsolidated sediments. The content of
till can vary from clays to mixtures of clay, sand, gravel and boulders.
Page 1
Approximate Glacial
Boundary Line
Buckeye Lake
Figure A.1 Allegheny Plateau extending from Southwestern New York to Northeastern
Kentucky (Musser, 2007).
Page 2
Drainage History
One of the biggest changes as a result of the glaciations during the Pleistocene were
changes in drainage patterns of major streams and rivers. During pre-glacial times, the
area was drained by the Teays River system which flowed in south and west directions
from the higher ground of the Allegheny Plateau to the northeast to the Low Plateau and
created a drainage divide across Ohio, Figure A.2.
Figure A.2 Pre-Kansan Teays Stage Drainage Divide (Stout et. al., 1943)
The Kansan ice sheet brought the first change to the natural drainage system, filling
pre-existing valleys with glacial drift. The damming of the Teays River and several of its
tributaries caused them to divert and new streams to form. The Newark River,
originating at the southern border of the ice sheet (Figure A.3), extended in a southwest
direction from Carroll County to Circleville which now drains the area previously drained
Page 3
by the Groveport tributary of the Teays River. The Newark River passed through Licking
County along the Cambridge River Valley.
Figure A.3 Post-Kansan Deep Stage Drainage (Stout et. al. 1943)
The recession of the Kansan ice sheet caused regional uplift to take place and the
rivers began a new cycle of down-cutting. Uplift ended during the Illinoian glaciations
and thus ended the accelerated erosion. The extent of the Illinoian ice sheet was
blocked by a sandstone escarpment east of Newark which contained the eastern flow of
the ice sheet (Franklin, 1961). The Newark River became dammed by the Illinoian ice
sheet when it reached this sandstone ridge. The Newark River valley was filled with
glacial outwash and lacustrine deposits. As the ice sheet receded, a series of terminal
moraines were formed at different stages of recession. The moraines formed natural
dams which obstructed drainage of rivers and ice melt water. A large terminal moraine
mapped just north of Hanover, created a natural dam that blocked flow of the natural
preglacial drainage. This blockage created glacial Lake Licking in the area of Marne,
Page 4
approximately 14 miles northeast of Buckeye Lake (Frolking and Pachell, 2006). The
waters of Lake Licking rose until they overtopped and eroded sandstone ridges south of
Hanover (Tight, 1897). The waters of the Newark River and those of Lake Licking were
shifted to the Licking River. The water flowed south and eroded the present Licking
River valley to Zanesville where it joins the Muskingum River.
The Wisconsin glaciation did not alter the drainage pattern in the area; however, the
new drainage system carried sand and gravel outwash and deposited throughout the
valleys of the Licking River. The present drainage system is shown in Figure A.4.
Page 5
Site Geology
The Wisconsin and Illinoian extents lie just east of Buckeye Lake as shown in Figure
A.5. Wisconsin terminal moraines are mapped northeast, east, and southeast of the
lake. The topography of the region flattens out southwest of Newark to form the till plain
in this area.
Figure A.5 Glacial Geology of Ohio, location of Buckeye Lake at red star (ODNR, 2005)
Page 6
In the Geology of Licking County report, Read (1878) interprets a postglacial lake of
considerable size covered the area south and southwest of Newark, including Buckeye
Lake area, during the late Pleistocene. The limited data at the site and mapping of the
region in 2005, Figure A.6, suggests that the lacustrine deposits do not cover the entire
till plains area but surround several existing or historic lakes, swamps, and bogs. It is
suggested that many kettle lakes formed in these low lying areas as a result of ice
calving off as the Wisconsin glacier receded and melted. The ice was partially buried
and filled in by glacial outwash transported by melt waters from the receding glacier.
When the ice blocks melted they left behind depressions called kettles which filled with
water and debris. Kettle lakes formed within the ground moraine region behind the
terminal moraines to the east.
deposits. The till is composed of soft to hard silty clay with trace fine sand and rock
fragments. North of the outwash deposits and south of Buckeye Lake, Wisconsin till
(yellow in Figure A.6) is mapped at the surface with varying depths but a maximum of
300 feet. In both areas, the till is underlain by interbedded shales, siltstones, and
sandstones of the Mississippian age Logan and Cuyahoga Formations.
Borings through the embankment and into the foundation were performed by DLA in
1987 and Paul C.Rizzo Associates, Inc. (Rizzo) in 1997. Both exploration programs
were limited in extent and cover a small portion of the site, DLA borings extend a
maximum of 20 feet into the foundation and Rizzo borings extend 10 feet. DLA (1987)
borings indicate that the soils underlying the embankment consist of lacustrine deposits
with silts and clays commonly laminated and interbedded together with sand and gravel
layers, containing organic matter. These deposits overlie glacial till. Rizzo (1997)
reclassified the lacustrine deposits previously mapped by DLA to be either embankment
fill material or till, composed of silty clay with trace fine sand and rock fragments.
However, the lacustrine materials and till have similar classifications, both being a silty
clay or clayey silt (CL to ML), and Rizzo notes zones beneath the embankment fill which
contained organic materials and laminations that could be attributed to the lacustrine
kettle lake soils. Rizzo also mapped lenses of loose sand and gravel with trace amounts
of silt and clay within embankment and the foundation till at varying depths. Although
these deposits have not been fully mapped or characterized by these limited
explorations to date, Wisconsin outwash is expected beneath the embankment and the
lake. During the formation of the kettle lake, some of the outwash would have collapsed
into the depression, although there may have been some reworking of the outwash and
underlying till materials. The lacustrine sediments and till are generally soft to medium
stiff in the upper 5 to 10 feet of the foundation, with increasing stiffness at depth. At a
depth of approximately 100 feet, Mississippian age interbedded shales, siltstones, and
sandstones underlie the Wisconsin till.
Page 8
Page 9
Figure A.7 Ohio Canal System 1825-1913, location of Buckeye Lake at red star (The
Ohio Historical Society, 1971).
Page 10
References
Frolking, T.A. and Pachell, M.A., 2006. Glacial Lake Licking: Late-Glacial Drainage
Diversion and the Formation of Black Hand Gorge, Licking County, Ohio. The Ohio
Journal of Science, v106, n3, p. 103-111.
Forsyth, J. L., 1966. Glacial map of Licking County, Ohio. State of Ohio, Department of
Natural Resources, Division of Geological Survey.
Stout, W., ver Steeg, K. & Lamb, G.F. (1943) Geology of water in Ohio, Ohio Division of
Geological Survey, Bulletin 44
Tight, W.G., 1894. Lake Licking A Contribution to the buried drainage of Ohio. Ohio
State Academy of Science, 1st Annual Report, p. 17-20.
Page 11
APPENDIX B
Piezometer Data from Site Reconnaissance
Piezometer Readings
Eighteen piezometers and nine monitoring wells were read during this assessment.
Most of the piezometers were installed during the Paul C. Rizzo Associates, Inc. (Rizzo)
study. Boring logs and piezometer installation logs from the Rizzo report indicate that
most of the sensing zones are along the base of the embankment or within the
foundation. No logs or installations reports were available for the monitoring wells at
Mud Island or the piezometers at Station 113+35. Two sets of readings were obtained
when USACE staff were on site. Piezometer and monitoring well readings were taken
26-27 August 2014 during the site reconnaissance at pools of El. 891.8 feet and 19
November 2014 at an El. 891.7 feet pool. Readings taken at the piezometers correlate
very closely with those taken during the Rizzo study while under normal pool conditions.
Without readings taken during elevated pools, it is not possible to project piezometer
readings which may occur during higher pools up to the embankment crest elevation.
Hydrolab Readings
When piezometers were read on 19 November 2014, water samples were collected
using a bailer. A hydrolab was used to compare specific conductance, dissolved
oxygen, pH, and temperature with pool parameters. A correlation between piezometer
and pool parameters could be indicative of a seepage path connection to the pool. Of
all the piezometers installed in the 4.1-mile reach of embankment, readings at
piezometer B13A-2 indicated water quality conditions similar to pool. B13A-2 is a
downstream slope piezometer at Station 113+35, and based on a measured depth, it is
probable that the sensing zone is within the embankment foundation.
Possible evidence of embankment movement
While making readings in the piezometers, total depth soundings were obtained. Most
of the piezometer soundings indicated relative depths within 1 foot of the original
installation. Piezometer soundings may vary as a result of accumulations of iron
precipitants from bio-fouling, sediment introduced at open pipe joints, or sensing zone
filter incompatibility. Piezometer B1A-1B at Station 50+80 was originally installed to a
depth of 17.5 feet; however, it was only possible to insert the water level indicator to a
depth of 4.78 feet. Based on embankment sections as presented in the Rizzo report,
this depth of 4.78 feet corresponds to the base of the embankment. It is possible that
this piezometer has been sheared at the embankment-foundation contact. Also, while
collecting water samples, the bailer insertion required force at piezometer B2-A3 near
Station 65+00 because this riser pipe was bent within the top two feet. This
displacement could also be a result of embankment movement.
Page 1
APPENDIX C
Site Reconnaissance Photos
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 001 Beginning of west embankment masonry wall as seen from
the west abutment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 002 Masonry wall alignment as seen from west abutment.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 1 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 003 Some voids in the masonry wall allow a tile probe to
penetrate through the wall and contact the embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 004 One of many depressions observed behind the masonry wall
along the west embankment.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 2 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 005 Typical settlement feature observed behind the masonry
wall along the west embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 006 Drainage pipes penetrate through the masonry wall along
the west embankment.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 3 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 007 Settlement induced cracking observed in numerous
structures along the west embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 008 One of many large trees rooted along the west embankment.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 4 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 007 Structural distress in relatively new house resulting from
embankment displacement along the west embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 008 Structure exhibiting distress resulting from embankment
differential settlement and movement. Although not evident in this
photo, the lakeside of house was several inches out of alignment.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 5 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 009 A concrete block wall from an old structure is leaning 3-4
inches from vertical and concaved in alignment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 010 Lagoon behind western embankment intercepts flow from
reservoir through a steel pipe with no flap gate.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 6 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 011 Flap gate on a drainpipe connecting the pool to a
downstream lagoon is missing.
BUCKEYE LAKE
25 AUGUST 2014
Photo 012 Wood decks and patio structures inhibit monitoring the
crest of the dam for signs of distress. Additionally they preclude grass
growth which provides erosion protection of this earthen dam.
________________________________________________________________________
APPENDIX C
PAGE 7 OF 25
PROJECT PHOTOGRAPHS
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 013 One of many misaligned sections in the masonry wall.
BUCKEYE LAKE
25 AUGUST 2014
Photo 014 Hole in base of misaligned segment of masonry wall.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 8 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 015 Displaced masonry wall in western embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 016 Boathouse structure excavated halfway through the lakeside
of the embankment by Mud Island.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 9 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 017 Failing concrete block wall from an old structure built into
the embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 018 Excavation into downstream face of embankment to
construct new house. Note that no bracing is in use. This is very risky
construction practice with regard to dam safety.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 10 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 019 Sinkholes along masonry wall and several trees growing
through the wall.
BUCKEYE LAKE
25 AUGUST 2014
Photo 020 Current flow from Amil Gate Spillway should be evaluated.
Fish were observed to be trapped and dead in the rocks downstream.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 11 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 021 View from west side of Sellers Point spillway. Note the
large amount of eroded material deposited along the base of east training
wall.
BUCKEYE LAKE
25 AUGUST 2014
Photo 022 Settlement along sidewalk behind eastern training wall at
Sellers Point spillway.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 12 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 023 Cracks in sidewalks and porches along the crest of the dam
and adjacent to houses which formed as a result of embankment
displacement along northern dam reach.
BUCKEYE LAKE
25 AUGUST 2014
Photo 024 Another photograph of same structure in Photo 023. Note
that the sidewalk is misaligned with structure indicating embankment
displacement.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 13 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 025 Drain pipe penetrations through the sheetpile wall along
north reach of the embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 026 Concrete masonry unit wall left from after a house was
removed. Note redundant concrete walls most probably due to seepage
related displacement and distress along upstream wall.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 14 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 027 Although small vegetation is not harmful to the dam, it
hinders monitoring capability for depressions and cracking.
BUCKEYE LAKE
25 AUGUST 2014
Photo 028 Sheetpiling was bowed out and embankment fill material
was settling behind Smittys Tavern.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 15 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 029 Dock structures cantilevered off of the dam put stress on the
sheetpiling that it was not designed for and have caused the wall to bow
out.
BUCKEYE LAKE
25 AUGUST 2014
Photo 030 House at Station 107+50 exhibiting significant differential
settlement along embankment. Note settlement in crest between
sidewalk and front of house.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 16 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 031 Damaged waler on top of the sheetpiling.
BUCKEYE LAKE
25 AUGUST 2014
Photo 032 Several depressions were observed in the crest between
Stations 107+00 and 107+50.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 17 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 033 Large segmental block wall constructed as a retaining wall.
Note that the #57 stone used as drainage material is not filter compatible
with embankment materials.
BUCKEYE LAKE
25 AUGUST 2014
Photo 034 Numerous rust holes were observed in the waler along the
1948 sheet piling. Also, several pipe penetrations were observed.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 18 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 035 Dock structures cantilevering off of the dam put stress on
the sheet piling that it was not designed for.
BUCKEYE LAKE
25 AUGUST 2014
Photo 036 Concrete masonry unit wall with numerous cracks.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 19 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 037 Several depressions approximately 3.6 feet deep were noted
near the center of the embankment crest between Stations 129+16 to
139+70.
BUCKEYE LAKE
Photo 038 Failing shallow retaining wall.
25 AUGUST 2014
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 20 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 039 Area of nearly year round seepage pointed out by resident.
Station 152+50 along Black Diamond Bend. Note seepage was not
occurring during the day of inspection.
BUCKEYE LAKE
25 AUGUST 2014
Photo 040 Failing concrete wall built into the downstream
embankment slope along the north reach.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 21 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 041 Construction of new residential structure at the toe of the
landward side of the embankment.
BUCKEYE LAKE
25 AUGUST 2014
Photo 042 Several depressions approximately 3.5 deep near centerline
of crest between Stations 171+50 and 176+49.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 22 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 043 South Fork Licking River channel (facing upstream) after
ODNR widening project. Note the recent deposition. A maintenance
program will be essential to maintain conveyance capacity.
BUCKEYE LAKE
25 AUGUST 2014
Photo 044 Unsupported excavation into embankment.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 23 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 045 Residence at Station 112+25 with several depressions at the
ground surface possibly from boils. Soil was very soft and groundwater
was very shallow at this location.
BUCKEYE LAKE
25 AUGUST 2014
Photo 046 Thinning and loss of sheetpile wall. Holes were observed
through the wall. The wall beneath the water surface was not observed
during the August inspection.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 24 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
15 DECEMBER 2014
Photo 047 Segment of masonry wall with attempted repair as observed
at winter pool. Note the voids and cracks beneath the upper section of
wall and the pipe penetration.
________________________________________________________________________
PROJECT PHOTOGRAPHS
APPENDIX C
PAGE 25 OF 25
BUCKEYE VILLAGE, OH
BUCKEYE LAKE
25 AUGUST 2014
Photo 011 Flap gate on a drainpipe connecting the pool to a
downstream lagoon is missing.
BUCKEYE LAKE
25 AUGUST 2014
Photo 012 Wood decks and patio structures inhibit monitoring the
crest of the dam for signs of distress. Additionally they preclude grass
growth which provides erosion protection of this earthen dam.
________________________________________________________________________
APPENDIX C
PAGE 7 OF 25
PROJECT PHOTOGRAPHS
APPENDIX D
Dam Safety Guidance
The dam safety guidance referenced within this appendix is not intended to be all
encompassing. These and other local, state, and federal documents are available and can
be accessed by the public and others.
Unknown foundation
treatment during
construction, with
problematic soils known
to exist
Unknown compaction
during construction
Adequate grass cover
Page 2
Foundation treatment
during construction of the
dam
Page 3
APPENDIX E
Glossary of Terms
Abbreviations
DLA ..................................................... Dodson Lindblom and Associates, Inc.
EAP ..................................................... Emergency Action Plan
FEMA .................................................. Federal Emergency Management Agency
FMSM ................................................. Fuller, Mossbarger, Scott & May Engineers
HECHMS .......................................... Hydrologic Engineering Center Hydrology Modeling System
HMR .................................................... Hydrometeorological Report
IRRM .................................................. Interim Risk Reduction Measure
NGVD 29 ........................................... National Geodetic Vertical Datum of 1929
NOAA ................................................. Nation Oceanic and Atmospheric Administration
NWS .................................................... National Weather Service
ODNR ................................................. Ohio Department of Natural Resources
O&M .................................................... Operations and Maintenance
PMF ..................................................... Probable Maximum Flood
PMP..................................................... Probable Maximum Precipitation
SCS U.S. Department of Agriculture, Soil Conservation Service
SFLR ............................................ South Fork Licking River
The District ...................................... U.S. Army Corps of Engineers, Huntington District
USACE ................................................ United States Army Corps of Engineers
Page 1
Acceptable Risk A risk, for the purposes of life or work, everyone who might be impacted is
prepared to accept assuming no changes in risk control mechanisms. Such risk is regarded as
insignificant and adequately controlled. Action to father reduce such risk is usually not required.
Acrefoot A unit of volumetric measure that would cover 1 acre to a depth of 1 foot. It is equal to
43, 560 cubic feet. This is approximately 325,851.4 U.S. gallons.
Adverse Consequences The outcome of the failure of a dam or its appurtenances, including
immediate, short and longterm, direct and indirect losses and effects. Loss may include human
casualties, project benefits, monetary and economic damages, and environmental impact.
Appurtenant structure Ancillary features of a dam such as inlet and outlet works, spillways,
tunnels, or power plants.
Berm A nearly horizontal step in the sloping profile of an embankment dam. Also a step in a rock
or earth cut.
Borrow area The area from which natural materials, such as rock, gravel or soil, used for
construction purposes is excavated.
Breach An opening through a dam that allows the uncontrolled draining of a reservoir. A
controlled breach is a constructed opening. An uncontrolled breach is an unintentional opening
caused by discharge from the reservoir. A breach is generally associated with partial or total failure
of the dam.
Channel A general term for any natural feature or artificial facility for conveying water.
Clays Fine grain soils with particle diameters less than 0.075 mm. These soils have cohesion, low
permeability, and low shear strength.
Clearing Removal of larger vegetation, structures, obstructions, etc., in an area.
Compaction Immediate removal of air from the pore spaces within a soil matrix, typically via
mechanical action.
Conduit A closed channel to convey water through, around, or under a dam.
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Leakage Concentrated flow through preferential paths (e.g., crack in cohesive soil, open rock
defect)
Lens A stratum that is thicker in the middle and thinner towards the edges.
National Geodetic Vertical Datum of 1929 The vertical control datum established for vertical
control surveying in the United States of America by the General Adjustment of 1929.
Nonstructural risk reduction Risk reduction by measures that do not require structural
modification or construction related to the dam and its appurtenant works.
Observation well Perforated casing which is advanced through the ground and is used to
determine the groundwater surface.
Outlet A designed opening through which water can be discharged downchannel from a reservoir.
Outlet structure A dam appurtenance that provides release of water (generally controlled) from a
reservoir.
Parapet wall A wall built along the top of a dam to provide additional freeboard.
Periodic Assessments (PA) A USACE study which occurs on a 10 year frequency for each dam
project and consists of a site visit, a potential failure modes analysis, and a semiquantitative risk
assessment. Primary purposes of the PA include evaluating project conditions and associated risks;
prioritizing data collection, analyses, and study needs. Operations and maintenance requirements
would be reviewed. Emergency action planning, training, and other reoccurring needs would be
identified.
Periodic Inspections (PI) USACE inspections which occur on a 5 year frequency performed for
dams and other civil works structures where failure or partial failure would adversely affect the
operational integrity of the project, endanger the lives and safety of the public or cause substantial
property damage.
Phreatic surface A vertical location which may define the water table within which the pore water
pressure is under atmospheric conditions.
Page 8
Page 9
Page 10
Wave runup Wind or navigation related wave generation above the elevation of a retained pool.
Page 11
APPENDIX F
USACE Past Observations During High Pools
APPENDIX G
ODNR-USACE Buckeye Lake Support Agreement
Dodson-Lindblom Associates, 1987. Buckeye Lake Dam: Spillway Adequacy and Embankment
Stability and Seepage Study. Prepared for Ohio Department of Natural Resources.
Dodson-Lindblom Associates, 1995. Buckeye Lake Dam, Fairfield and Licking Counties, Ohio:
Evaluation of Existing Sheet Piling. Prepared for Ohio Department of Natural Resources.
Dodson-Lindblom Associates, 1996. DLAs Responses to Gardner and Associates Report. Prepared for
Ohio Department of Natural Resources.
DLZ Ohio, 2003. Preliminary Design Report, Dam Improvements, Buckeye Lake State Park. Prepared
for Ohio Department of Natural Resources.
Fuller, Mossbarger, Scott, and May Engineers, 2003.South Fork Licking River Watershed Study.
Prepared for Ohio Department of Natural Resources.
GAI Consultants, 1978. Buckeye Lake Dam, Licking, Fairfield, and Perry Counties, Ohio. Phase I
Inspection Report, National Program of Inspection of Non-Federal Dams. Prepared for the U.S. Army
Corps of Engineers, Pittsburgh District.
Gardner, W.S. and Associates, 1995. Buckeye Lake Dam, Review of Embankment Stability, Overview,
Buckeye Lake Dam, ODNR Phase III. Prepared for Buckeye Lake Association.
Gardner, W.S. and Associates, 1996. Buckeye Lake: Spillway adequacy. Prepared for the Save the
Lake Committee.
Rizzo, Paul C. Associates, 1997. Report: Buckeye Lake Dam Stability Study, Buckeye Lake State Park,
Fairfield, Licking, and Perry Counties, Ohio, Project No. 95-1590. Prepared for Ohio Department of
Natural Resources.
Snyder, T.D., 2002. Trees on the Dam at Buckeye Lake. Prepared for the Save the Lake Committee.
Page 1
APPENDIX I
Ohio Administrative Code Chapter 1501:21-13 Classification and Design of Dams, Dikes,
and Levees
Lawriter - OAC
LAW
Writer
Search OAC:
Go
Route: Ohio Administrative Code 1501:21 Division of Soil and Water Resources - Dam Safety
GoTo:
Go
Prev | Next
1501:21-13-01 Classification of
dams.
1501:21-13-02 Design flood for
dams and determination of critical
flood.
1501:21-13-03 Spillway design,
general requirements.
1501:21-13-04 Pipe conduit
spillways, general requirements.
1501:21-13-05 Pipe conduit
spillways, special requirements.
1501:21-13-06 Requirements for
drains and other pipe conduits.
1501:21-13-07 Freeboard
requirements for dams.
(2) Dams having a total storage volume greater than five hundred acre-feet
or a height of greater than forty feet shall be placed in class II. A dam shall
be placed in class II when sudden failure of the dam would result in at least
one of the following conditions, but loss of human life is not probable.
1501:21-13-09 Classification of
levees.
Lawriter - OAC
Lawriter - OAC
Lawriter - OAC
Lawriter - OAC
Lawriter - OAC
(B) For class III dams that are upground reservoirs, the minimum elevation
of the top of the dam shall be at least three feet higher than the elevation
of the designed maximum operating pool level unless otherwise approved
by the chief.
R.C. 119.032 review dates: 03/08/2010 and 03/05/2015
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.06 , 1521.061 , 1521.062
Prior Effective Dates: 4-15-72; 10-15-81; 12-9-99; 1-16-05
Lawriter - OAC
the normal drawdown level, to the top of dam elevation. The design of the
staff gauge will be reviewed and approved by the chief.
(D) Grass vegetation or other vegetation of similar properties are the only
acceptable vegetative covers for earthen dam embankment surfaces or
vegetated earth spillways. Trees and brush are not acceptable surface
covers.
(E) The applicant shall demonstrate to the satisfaction of the chief that the
structure will be consistent and in accordance with all applicable state and
local floodplain regulations and requirements.
Effective: 05/23/2010
R.C. 119.032 review dates: 03/08/2010 and 05/15/2015
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.06 , 1521.061
Prior Effective Dates: 4-15-72; 10-15-81; 12-9-99; 1-16-05
of
residential,
commercial,
industrial,
or
publicly owned
Lawriter - OAC
Lawriter - OAC
Lawriter - OAC
(B) For levees in class II and class III, the minimum elevations of the top of
the levee shall be two feet higher than the maximum adjacent water
surface elevations during passage of the design flood.
(C) Where special conditions of severe frost damage, ice damage, stream
obstruction, wave action, or impact of other structures may occur, the chief
may require elevations higher than required in paragraph (A) of this rule.
Effective: 05/23/2010
R.C. 119.032 review dates: 03/08/2010 and 05/15/2015
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.06 , 1521.061 , 1521.062
Prior Effective Dates: 10-15-81; 12-9-99; 1-16-05