Concrete Frme Building
Concrete Frme Building
Concrete Frme Building
On
10/05/2012
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Concrete
Framed Buildings
Contents
1 Benefits of Concrete Framed
Buildings
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
4 Structural forms
INTRODUCTION
We hope that this will be the book that you first turn to when a new
project arrives on your desk and you need answers to client questions
such as: Whats the best frame option for my building? How deep?
What span?
6 Flat Slabs
8 Ribbed and Waffle Slabs
9 Beams and Slabs
10 Post-tensioned Slabs
12 Hybrid Concrete
Construction
14 Precast Concrete
16 Tunnel form
18 Innovations in Concrete
Mixes and Emerging
Best Practice
20 Concrete Mixes for
Construction Methods
22 Sustainability
24 Summary
25 References
The Concrete Centre can provide more information on any of these topics, either through our National
Helpline on 0845 812 0000 or our website at www.concretecentre.com. Our team of regional engineers,
architects and contractors can also come to discuss your project with you.
Post-tensioned one way slab and band beam construction was used at Cardinal Place, London.
Cover pictures:
Main:
Flat slab construction at the Visage
Development, Swiss Cottage. Courtesy
of Getjar Ltd
Inset top:
Inclined columns are a feature of the
Albion Wharf development, London.
Courtesy of Foster and Partners.
Photography Nigel Young.
Inset below: Twinwall construction at More London.
Courtesy of John Doyle Construction.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Speed of construction
Concrete is highly compatible with fast programme
construction, from rapid mobilisation at the start
though modern methods of construction, including
sophisticated formwork systems, post-tensioning,
and precast elements. Modern formwork systems
have markedly increased construction rates. It is
now common to achieve 500m2 per week per crane.
Cellular structures can be built at a rate of up to 50
bedrooms per week.
The speed of the various forms of concrete
construction is given in the specific information in
the Structual Forms section of this publication, see
page 4.
Frame costs
While recent price rises in reinforcement and
structural steel have increased frame costs, the
difference between steel and concrete frame costs
remains insignificant, with full fit-out whole-building
costs broadly similar. These whole project inital costs
come from a cost comparison study [2]. Prices as of
June 06.
RC Flat Slab
27,624,300
Steel Composite
28,028,600
6 Storey Office
RC Flat Slab
6,775,300
Steel Composite
6,813,100
3 Storey office
Programme
Generally, insitu concrete-framed buildings
take no longer to construct than steel-framed
buildings: indeed, they can be faster. Prerequisites
for fast construction in any material are design
discipline, repetition, integration, simplification
and standardisation of design details. Rationalising
reinforcement, designing and detailing for
prefabrication, precasting or part-precasting can
help progress concrete construction on site. Many
contractors appreciate the opportunity to discuss
buildability and influence designs for construction.
More important, however, is the whole project
programme. Concrete provides a safe working
platform and semi-internal conditions, allowing
services installation and follow-on trades to
commence early in the programme, while flexibility
allows accommodation of design changes later in
the process.
Foundation costs
Foundations typically represent approximately
3% of whole project initial cost. For the heaviest
reinforced concrete solution, foundations will be
more expensive, but still represent only a small
percentage of the whole and can be offset by using
post-tensioned slabs which are typically 15% lighter.
Cladding costs
The thinner the overall structural and services zone,
the less the cladding costs. Cladding can represent
up to 25% of the construction cost, so it is worth
minimising the cladding area. This can be achieved
with a concrete flat slab and separate services zone.
To obtain best
value consider early
specialist contractor
involvement.
UK Concrete frame
contractors have
expertise that can
reduce costs and
maximise value when
harnessed early in the
design process.
Performance in Use
Co-ordination
Fire protection
Design flexibility
Services co-ordination
and installation
Mechanical and electrical services are an expensive
and programme-critical element in construction,
with significant maintenance and replacement
issues. The soffit of a concrete flat slab provides a
zone for services distribution free of any downstand
beams. This reduces design team coordination effort
and risk of errors. It allows flexibility in design and
adaptability in use. A flat soffit permits maximum
off site fabrication of services, higher quality work
and quicker installation. M&E contractors quote an
additional cost of horizontal services distribution
below a profiled slab of up to 15%.
Vibration control
For concrete buildings, vibration criteria for most
uses are covered without any change to the normal
design. For some uses, such as laboratories or
hospitals, additional measures may be needed, but
these are significantly less than for other materials.
In a recent independent study [4] into the vibration
performance of hospital floors, concrete emerged as
the solution least in need of significant modification
to meet the stringent criteria. This gives great
flexibility for change in use and avoids the cost
penalties of providing extra mass and stiffness.
The diagrams below show the increases in mass and
construction depth needed to upgrade an office
frame to hospital vibration criteria for night wards
and operating theatres.
200%
50%
150%
% increase
% increase
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Acoustics
100%
50%
30%
20%
10%
Operating thea
tre
Night ward
Office
0%
te
osi
mp
Co
40%
ck
de
m
Sli
RC
fla
la
ts
PT
b
sla
Operating thea
tre
Night ward
Office
0%
te
osi
mp
Co
eck
md
Sli
f
RC
lat
sla
PT
sla
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
PAGE 3
Environmental
Other Benefits
Thermal mass
Minimal maintenance
Adaptability
Markets and working practices are constantly
changing, therefore it makes sense to consider a
material that can accommodate changing needs or
be adapted with minimum effort. A concrete frame
can easily be adapted to other uses. Holes can be cut
through slabs and walls relatively simply, while there
are methods to strengthen the frame if required.
Partitions
Sealing and fire stopping at partition heads is
simplest with flat soffits. Significant savings of up
to 10% of the partitions package can be made
compared to the equivalent dry lining package
abutting a profiled soffit with downstands. This
can represent up to 4% of the frame cost, and a
significant reduction in programme length.
Air tightness
Part L of the Building Regulations requires precompletion pressure testing. Failing these tests
means a time consuming process of inspecting joints
and interfaces, resealing where necessary. Concrete
edge details are simpler to seal, with less failure risk.
Some contractors have switched to concrete frames
on this criterion alone.
Modern
methods of
construction
Concrete construction has
undergone a revolution in speed
and efficiency in recent years.
Forming the concrete into shape
is potentially the most costly and
labour intensive part of the process.
However, modern high efficiency
modular formwork standardises and
mechanises this process. It often
employs whole ready assembled
tables or complex moulds, swung
into place. Alternatively, elements
may be factory precast, requiring
only assembly, or stitching together
with in-situ elements. The result
is an economic and swift process,
capable of excellent quality and
finishes to suit the frames needs.
Aesthetics
Internal fair-faced concrete can be both aesthetically
pleasing and durable, ensuring buildings keep looking
good with little maintenance. Precast concrete
cladding also looks good. It is available in many
different colours, textures and finishes, including
brick, stone and tile faced.
STRUCTURAL FORMS
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
CONCRETE FRAME CONSTRUCTION COMES IN MANY FORMS; HERE ARE THE TYPICAL ONES WHICH ARE
DETAILED IN THIS PUBLICATION.
Hybrid Concrete
Construction - page 12
Precast - page 14
12 11 10
FLAT SLAB
RIBBED SLAB
WAFFLE SLAB
ONE-WAY SLAB AND BAND BEAM
TWO-WAY BEAM & SLAB
P/T FLAT SLAB
The diagram shows approximate lead-in times and construction speeds for each of type of construction detailed in this publication.
Times and speeds are typical but will vary, depending on availability of contractors and materials and site constraints.
Depth (mm)
800
700
600
500
Spans (m)
400
200
300
100
9 10 11 12 13 14 15
FLAT SLAB
TROUGHED SLAB
ONE-WAY SLAB
P/T FLAT SLAB
HYBRID HOLLOWCORE AND TOPPING
The line graphs show span and depth information for different live loads for each slab form. For loads not
shown, interpolation between graphs is acceptable. For further information on this, the reader should use Concept.xls [5], a spreadsheet allowing 13 different reinforced concrete slab forms to be considered.
Qk = 2.5kN/m2
700
700
600
600
500
400
300
500
400
300
200
200
100
100
Qk = 7.5kN/m2
800
Depth in mm
Depth in mm
800
10 11 12 13 14 15
Qk = 5.0kN/m2
800
Flat Slab
Troughed Slab
One-way Slab
P/T Flat Slab
Hybrid Hollowcore
and topping
700
700
600
600
500
400
300
500
400
300
200
200
100
100
0
4
10 11 12 13 14 15
Span in m
10 11 12 13 14 15
Qk = 10.0kN/m2
800
Depth in mm
Key
Span in m
Span in m
Depth in mm
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
These graphs show typical depths required for different spans for each slab form. The design has been taken
from BS 8110 Part 1 using a superimposed dead load of 1.5kN/m2, and C28/35 strength class concrete. The
graphs assume that multiple, square bays are considered, except for the hybrid hollowcore and topping which is
assumed to be a single span.
The diagram below shows the economic spans and the typical range of depths for different types of floor
construction. It therefore covers imposed loads of between 2.5 and 10 kN/m2.
10 11 12 13 14 15
Span in m
FLAT SLABS
Flat slabs are highly versatile elements widely used in construction, providing minimum
depth, fast construction and allowing exible column grids.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Points to Note
Design
Flat slabs may be designed using the strip method
set out in BS 8110 Part 1, finite element analysis
(FEA) programmes or yield line analysis [6]. Use FEA
[7] or yield line analysis for irregular grids.
Flat slab
Markets:
Residential
Commercial
Hospitals
Laboratories
Hotels
Benefits:
Cost
Speed
Flexibility
Sound control
Fire resistance
Robustness
Thermal mass
Durable finishes
Construction
Construction of flat slabs is one of the quickest
methods available. Table forms can be used; these
are becoming more lightweight so that larger
areas can be constructed on one table form, with
formwork lifted by crane. Table forms should be used
as repetitively as possible to take most advantage of
the construction method. Downstand beams should
be avoided wherever possible as forming beams
significantly slows construction. Edge beams need
not be used for most cladding loads [1].
Reinforcement should be rationalised fairly heavily
as this gives the most economic solution. (see figure
below). Detailing can be done by the designer or
the contractor. Prefabricated reinforcement mats,
normally detailed by the supplier, can speed up
construction on site.
TIME
Slow
Fast
High
COST
Finance
Labour, plant & preliminaries
Low
Material
Highly
detailed
Usual
Rationalised
Highly
rationalised
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
PAGE 7
Lead times
Speed on site
Procuring
This is one of the most common forms of concrete
construction. All CONSTRUCT [8] members and
many other concrete frame contractors can
undertake this type of construction.
Leeds Oncology Wing at St James Hospital. Flat slabs were used to simplify the construction of the concrete frame and the internal partitions.
Courtesy of Faber Maunsell
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Ribbed and Wafe slabs provide a lighter and stiffer slab than an equivalent at slab,
reducing the extent of foundations. They provide a very good form where slab vibration is
an issue, such as laboratories and hospitals.
Ribbed slabs are made up of wide band beams running between columns with equal depth
narrow ribs spanning the orthogonal direction. A thin topping slab completes the system.
Ribbed slab
Wafe slabs tend to be deeper than the equivalent ribbed slab. Wafe slabs have a thin
topping slab and narrow ribs spanning in both directions between column heads or band
beams. The column heads or band beams are the same depth as the ribs.
Points to Note
Design
Frequently ribs are designed as L-sections to allow
a hole on one side of the rib. This allows design to
proceed before the service holes have been finalised.
Waffle slabs work best with a square grid. Ribbed
slabs should be orientated so that the ribs span the
longer distance, and the band beams the shorter
distance. The most economic layout is lx:ly = 4:3.
Waffle slab
Markets:
Vibration critical projects
Hospitals
Laboratories
Construction
Both waffle and ribbed slabs are constructed using
table forms with moulds positioned on the table
forms. Speed of construction depends on repetition,
so that the moulds on the table forms do not need
to be repositioned.
Lead times
Both ribbed and waffle slabs need moulds to be
procured before starting on site. The lead-in times
for these moulds depends on whether the mould is
standard or needs to be fabricated.
Procuring
Benefits:
Flexible
Relatively light, therefore
less foundation costs
Speed
Fairly slim floor depths
Robustness
Excellent vibration
characteristics
Thermal mass
Good services integration
Durable finishes
Fire resistance
Speed on site
This is a slower form of construction than flat slabs,
but the use of table forms increases the speed.
Where partitions need to be sealed acoustically or
for fire up to the soffit, ribbed and waffle slabs take
longer on site. Lightweight floor blocks can be used
as permanent formwork, which give a flat soffit,
although these take away some of the benefits of the
lighter weight slab design. If partition locations are
known, the moulds may be omitted on these lines.
Exposed waffle slabs are excellent for providing the full benefits of fabric energy storage.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Beam and slab construction involves the use of one or two way spanning slabs onto beams
spanning in one or two directions. The beams can be wide and at or narrow and deep,
depending on the structures requirements. Beams tend to span between columns or walls
and can be simply supported or continuous.
This form of construction is commonly used for irregular grids and long spans, where at
slabs are unsuitable. It is also used for transferring columns, walls or heavy point loads to
columns or walls below.
It is not a fast method of construction as formwork tends to be labour intensive.
Points to Note
Design
This is a very common form of construction and as
such is well covered in standard codes and guidance.
Beams can be designed as either L or T beams using
the slab as a flange.
Construction
The formwork tends not to be reused. Beam
reinforcement can be prefabricated and craned into
place. Slabs tend to be lightly reinforced and can
normally be reinforced with standard mesh.
Lead times
Fast lead times as formwork tends to be made on
site.
Procuring
All concrete frame contractors, and indeed general
builders, are able to do this type of work.
Speed on site
Slow and laborious on site due to time for formwork
and fixing reinforcement in the beams.
Markets:
Transfer structures
Heavily loaded slabs
Long spans unsuitable
for flat slabs
Benefits:
Flexibility
Sound control
Fire resistance
Robustness
Thermal mass
POST-TENSIONED SLABS
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Post-tensioned (PT) slabs are typically at slabs, band beam and slabs or ribbed slabs.
PT slabs offer the thinnest slab type, as concrete is worked to its strengths, mostly being
kept in compression. Longer spans can be achieved due to prestress, which can be used to
counteract deections.
Bonded
Unbonded
Markets:
Commercial
Hospitals
Car parks
Residential
Long spans
Benefits:
Cost
Speed
Reduced material use
Sound control
Robustness
Thermal mass
Minimal deliveries
Fire resistance
Post-tensioning can use bonded or unbonded systems. Currently the most common type is
bonded. Bonded systems have tendons that run typically in at ducts, grouted up after the
tendons have been taken to full prestress. Bonded systems do not rely on the anchorages
after the ducts have been grouted, with the prestress locked into the slab even if a tendon
is inadvertently cut. Unbonded systems have tendons that run in a small protective sheath.
Unbonded systems are more exible, with no need for a separate grouting stage.
Normal reinforcement is required wherever prestress is not present. This includes the edges
of the slab and in any closure or inll strips. It is also needed at anchorages, where there
are large bursting stresses due to high local forces. Normal reinforcement is also needed in
unbonded systems for the ultimate load case. In bonded systems, this ultimate load case
can be resisted partially or fully by the bonded strands.
Around column heads shear and bending reinforcement is required for both bonded and
unbonded slabs.
There are a number of computer programs available for the design of post-tensioned slabs.
They cover the design of the tendons, and any normal reinforcement.
CLOSURE STRIPS ARE REQUIRED IF THE BUILDING HAS MORE THAN ONE CORE OR STIFF POINT
Closure strip
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Points to Note
Design
Procuring
Speed on site
Construction
Contractors should be aware of the need to protect
ducts and tendons from damage prior to concreting.
The tensioning jack needs to have a working space
of approximately one metre. If the site is constricted
it may be necessary to have a normally reinforced
strip around the edge of the slab and prestress via a
stressing pan.
Stressing pan to provide top access to
post-tensioning strands.
Lead times
Lead times depend on the method of procurement.
If the design is by the main designer, procurement
is only slightly longer than for normal reinforced
concrete. If the design of the post-tensioned slabs is
by a specialist, lead in time should reflect work to be
done before start on site.
A bonded post-tensioned slab just prior to the concrete being placed. Note the minimal amount of
reinforcement required.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Markets:
All: particularly suited
to offices bespoke
and speculative
Schools
Car parks
Retail
Sports stadia
Benefits:
Cost
Speed
Accuracy for
prefabricated elements
Sound control
Fire resistance
Robustness
Thermal mass
Durability
High quality finishes
Safety
Key
Precast
Insitu
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Points to Note
Design
Construction
Full coordination of the services through the building
needs to take place early in the design process, as
they need to be incorporated into precast elements.
Also items frequently sorted out on site must be
resolved before the project gets to site, allowing
faster and safer construction.
Lead times
Depending on the precast elements of the
construction up to twenty weeks lead in time can be
necessary. However rapid progress of insitu elements
can be made, with substructure often completed in
this period. The design should be fully coordinated
prior to the precast elements being manufactured if
coordination affects the precast elements.
Speed on site
One of the main benefits of HCC is speed. A recent
project constructed 4200m2 in an eleven day cycle,
with three cranes, using insitu concrete for vertical
elements and floor toppings, and precast beams and
slabs.
Procuring
Since a standardised layout allows the full benefits
to be realised, use of HCC should be considered from
design concept stage.
A lead frame contractor (usually a concrete frame
contractor) should be appointed early together with
specialist supplier(s) of the precast elements. This
will provide the best advice to the design team and
hence the best finished building.
The Home Office Project used hybrid concrete construction to achieve a floor cycle time of 4200m2
in eleven days. Courtesy of Pell Frischmann.
PRECAST CONCRETE
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Precast concrete can form all types of structures, from cellular type construction such
as crosswall where wall and slabs are precast, to stick frame construction with columns,
beams and slabs. Precast concrete is particularly suited to uses where either speed on site
or a ne fair faced concrete nish is required. A high degree of repetition is advisable, as
the cost of the mould required for each element reduces the more the mould is used.
Crosswall is generally associated with cellular
and orthogonal grids but there is scope
for other geometries [11]
Precast
Markets:
Residential
Hotels
Car parks
Shopping centres
Commercial
Student accommodation
Prisons
Benefits:
Speed
Accuracy for
prefabricated elements
Sound control
Fire resistance
Robustness
Thermal mass
Durable finishes
Safety
Reduced risk
Minimal deliveries
The use of precast concrete at the Gloucester Docks project meant that the car park element
of the project was erected in just seven weeks. The car park is a 15.6m clear span with a circular
ramp structure at each end. Courtesy of Composite.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Points to Note
Design
Procuring
Construction
The use of precast can be helpful on a tight site
provided access is not a problem. Precast elements
can be craned into place from a lorry, eliminating
any need for storage areas for reinforcement or
shutters.
Coordination between the specialist subcontractor
and other subcontractors is vital to ensure the best is
achieved from precast. The specialist subcontractor
should be appointed as soon as possible to enable
both coordination and buildability aspects to be fully
integrated into the precast design.
Some insitu stitching is required at joints, but
normally only involves grouting up connections.
Speed on site
750
1000
Raised floor
400
Top flange
Polybuthylen
Pipework
150
50
150
Horizontal ceiling surface
Lead times
Lead times are approximately four months for
structural precast frames. This includes preparing all
drawings for product manufacture and coordinating
with other subcontractors. Lead times for simple
standard elements, such as stair flights or hollowcore
slabs, are significantly less.
600
TUNNEL FORM
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Tunnel form is a formwork system used to form cellular structures. The system has been
recognised as a modern method of construction, and has excellent productivity and quality
benets.
Tunnel form
Markets:
Residential
Housing
Hotel
Hostel
Student accommodation
Prisons
Benefits:
Cost
Speed
Accuracy for prefabricated
elements
Sound control
Fire resistance
Robustness
Thermal mass
Durable finishes
Safety
Reduced risk
Minimal deliveries
The system consists of half tunnel forms which, when tted together, form the full
tunnel. The system also has gable end forms and stripping platforms. Tunnels are formed
by pouring the walls and slab together. This is done on a 24 hour cycle, achieving fast cycle
times. The formwork from the previous days pour is struck rst thing in the morning, as
soon as the strength of the concrete has been checked, reaching at least 15N/mm2 cube
strength. The forms are easily struck by a simple set of handles. Wheels on the forms are
then lowered, and the formwork lifted out of the tunnel by a lifting triangle attached to
the crane. The forms are then lifted into position for the next pour, the reinforcement xed
and the concrete poured that same day.
Accuracy is maintained by the use of cruciforms. These t into the top of the wall forms to
provide an accurate line for the formwork for the walls above. This means that accuracies
of 3mm are achieved for room sizes.
Tunnels can be between 8 11m long and 2.4 6.8m width. Wider tunnels can be formed
with the use of a table form between the two half tunnels, but this slows down the
process.
Tunnel form buildings have been built up to 40 storeys high, but can also be used for low
rise housing, for example, on the Nightingale Estate in Hackney, London, three storey
houses were constructed using the system. Tunnel form for low rise construction is widely
used across mainland Europe.
Day two of a three day cycle for the floor plate. The tunnels are struck, moved and poured in a
daily cycle. Note: The walls can be used to span between column supports on a lower level.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Points to Note
Design
Construction
The formwork supplier will help train the contractors
labour force in the early stages of the construction
to achieve the 24 hour cycle.
The system requires a gang of 9 workmen, plus
dedicated use of the crane. As a known volume of
concrete is poured daily at the same time, producers
can provide the concrete at the right time, causing
little wastage.
Lead times
Many concrete frame contractors have their own
tunnel formwork, while others hire formwork for the
project.
Reinforcement is normally standard mesh, which is
readily available.
Procuring
The concrete frame contractor should be involved
early in the design process to ensure that tunnel
form can be used most efficiently.
Speed on site
Speeds of 300m2 of floor per day are typical for
tunnel form. This allows up to 8 bedrooms to be
constructed per day.
The Abito housing development in Salford, Manchester used tunnel form and precast concrete bathroom pods to provide a robust and fast construction.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
High Performance
Concretes
There are no definitive rules for the design of
high performance concretes (HPCs) but, generally
speaking, they usually contain low water contents
and relatively high powder contents. For example,
the high-rise pumping of concrete will require mix
designs containing an excess volume of paste, with
low water and air contents.
Until recent years, superplasticisers did not exhibit
sufficient water reduction capabilities and mixes
often had to contain very high levels of Portland
cement. The development of polycarboxylate based
admixtures has significantly changed this, enabling
the boundaries of HPCs to be expanded.
Cement replacement materials, such as pulverised
fuel ash (pfa) and ground granulated blastfurnace
slag (ggbs) have been used in concretes for a long
time, and their inclusion is nearly always required
in HPCs. Other ultra-fine materials are frequently
included, such as microsilica and limestone powder,
to provide ternary and even quaternary blends of
powder content. It should be stressed that HPCs of
good and consistent quality are best produced in
wet-batch, pan mixer type plants.
The consistency of HPCs are generally of a high
workability and flow, enabling faster and easier
pumping and placement of the concrete, reducing
labour and producing better off-form finishes.
Benefits
Building Owner
Less maintenance
Longer service life
More durable
Smaller column sizes
Designer
Contractor
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Flowing concretes
In order to maintain cohesion and reduce bleed, sand
contents of between 45 and 50% (dependent upon
sand gradings) are incorporated into the mix.
Powder contents are normally > 380 kg/m3 and
often include replacement materials such as pfa
or ggbs in order to reduce the cost of the powder
component and, in the case of pfa, to further
improve mix cohesion. Relatively low water contents
are required, achieved by including a polycarboxylate
based superplasticiser, which also imparts the
required high workability.
A benefit accruing from using this type of admixture
is the high water reduction capability, which enables
high strength flowing concretes to be designed at
moderate cement contents. e.g., a C40/50 strength
class flowing concrete can be designed with only
380 kg/m3 of cement.
Self-compacting concrete
SCC contains relatively high powder contents. This
is required to eliminate bleed (segregation) of the
concrete and maintain its cohesion.
Powder (or binder) contents are usually of the order
500 to 550 kg/m3, with sand contents between 48
and 55%. Binary, ternary and even quaternary blends
of Portland cement (CEM I) and filler materials
comprise the binder content. It is possible, with
judicious mix design, to produce SCCs of up to
100 N/mm2 characteristic cube strength that
contain less than 400 kg/m3 of CEM I. Water
contents are normally within the range of 170 to
190 litres/m3. Coarse aggregate sizes may be up to
20 mm maximum, although the optimum is 10 to
14 mm.
A polycarboxylate superplasticiser is normally
included in the mix. A second admixture (a viscosity
modifier) is frequently added to improve cohesion
and reduce bleed.
When placing SCCs, remember that the material
should not be allowed to free-fall, since this will
1. Cost of concrete/m
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Courtesy of LUSAS.
CONCRETES FOR
CONSTRUCTION METHODS
Slipform and jumpform techniques are fast and
efficient systems for constructing cores and shafts
in high rise structures. The concrete requirements of
the systems are, however, quite different from each
other.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Maturity meters
Rudimentary maturity meters, trialled in the
1950s, did not gain acceptance. Other systems for
monitoring early age strength were subsequently
developed, such as temperature matched curing
and pull-out tests. The widespread use of
computers in the late 1980s and the development
of microprocessors led to a resurgence of interest
in maturity meters. These comprise thermocouple
or thermistor sensors embedded into freshly
placed concrete to monitor the materials insitu
temperature history. The data is then transferred,
either by wires or more recently developed Radio
Frequency Identification (i.e. wireless), to a data
logger or hand held palmtop computer. A simple
computer programme converts this data into a
maturity value and, consequently, measurement of
actual in-situ compressive strength.
Prior to using maturity meters in a project, the
actual concrete mixes to be used will have to be
calibrated and tested under laboratory controlled
conditions in order to produce a maturity curve for
each mix (compressive strength vs maturity).
Benefits
The benefits obtained from being able to accurately
assess the early age insitu strength of a structural
member are very significant in concrete frame
construction. These are:
Earlier removal of formwork and propping
Earlier post-tensioning of slabs
Faster construction cycles
Elimination of early age cube testing
Earlier removal of forms in jump form and tunnel
form construction
Reduced costs of concrete testing
Faster project completion
In the past few years, the use of maturity meters
in concrete pavement construction in the USA
has shown that roads can be opened more quickly
after construction than previously possible. This
technology is now being applied to modern concrete
frame construction.
The concept of
concrete maturity
was first defined in
1951: the maturity
of concrete may be
defined as its age
multiplied by the
average temperature
above freezing that it
has maintained.
From this definition,
a law of strength gain
with maturity was
developed concrete
of the same mixture
at the same maturity
(temperature x time)
has approximately
the same strength,
whatever combination
of temperature and
time goes to make up
that maturity [17].
SUSTAINABILITY
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Sustainability during
Construction
Concrete is the ultimate local material. Material
supply is UK based, we are to all intents and
purposes self sufficient in the raw materials needed
to produce concrete:
99.9% of all aggregates used in the UK are UK in
origin
90% of Ordinary Portland Cement produced
in the UK (10% imported due to international
companies)
100% of UK reinforcement bar is produced from
scrap steel
100% admixtures produced in UK
100% pfa produced in the UK
90% ggbs produced in the UK
Typically, raw materials for concrete are sourced
locally to the concrete producers plant, and plants
are local to the construction site. This:
Signicantly reduces transportation
environmental, economic and social impacts
80% of all aggregates are used within 30 miles
of extraction
Supports local economy
Supports local jobs
Does not transport environmental impacts to
other countries that may have lower levels of
environmental protection legislation
Concrete production also uses materials that would
otherwise be sent to landfill:
Blended concretes use pfa and ggbs, by-products
of other industries
Sustainable
Development
is development
that meets the
needs of the
present without
compromising the
ability of future
generations to
meet their own
needs
BRUNDTLAND REPORT
Sustainability in Use
Concrete can help reduce a buildings operational
energy requirements, primarily through the
exploitation of thermal mass, thus making more
sustainable buildings.
Thermal mass
Heavy weight buildings such as concrete can reduce
energy consumption by several times, depending
on the design. The frames thermal mass can store
energy (fabric energy storage FES) either in the
winter reducing the need for heating, or in the
summer reducing the need for cooling. This
technology has been used for hundreds of years in
hotter climates, but it seems to have been forgotten
by our hi-tech society.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
PAGE 23
Robustness/fire/terrorism
Concrete is inherently robust, capable of
withstanding loads of up to 100 MPa. The US
Federal study into the 9/11 attack on the Pentagon,
Washington DC, stated that this concrete buildings
structural resilience provided vital resistance to its
collapse.
Sustainability at
End of Life
Concrete can be part of a virtuous cycle, provided
life-cycle impacts are considered from day one
of the design stage. When a building, or part of
a building, reaches the end of its functional life,
the most effective solution is to refurbish. Failing
that, value should be recovered through recycling
or re-use of components. Only if there is no other
alternative should disposal be considered. The
good news is that, with concrete, there is no need
for disposal almost everything can be recovered,
including reinforcement, which can be returned to
the scrap metal resource from which it was made.
Once a concrete building has reached the end of
its useful life, up to 95% of even the most heavily
reinforced concrete can be recycled, commonly
for use in road and runway sub-bases. Recycled
aggregates accounted for almost a fifth of the UKs
aggregates supply in 2001 and that proportion is set
to grow in the years to come. Reinforcement can be
recycled and remade into new reinforcement. UK
reinforcement is made from 100% scrap steel, with
reinforcement further recycled at the end of its first,
second, third life etc.
Aggregate abstraction can be used to create very
attractive sites for wildlife. Over 700 of the UKs
4,000 SSSIs have their origins in quarries. Many
are still maintained and supported by the quarry
companies [15].
RSPB Dungeness Reserve. This former quarry has been restored in an award-winning project. Courtesy of Hanson Aggregates.
SUMMARY
A concrete frame can improve the overall performance of your building. There are many
forms of fast, efcient and effective concrete frames.
Flat slabs are a cost effective form of construction, providing at softs which will speed up follow-on trades
such as M&E and internal partitions.
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Flat slabs are a slim form of construction, reducing the overall height of the building.
Ribbed and wafe slabs are excellent for areas where vibration particularly needs to be controlled.
Beams and slabs are a very exible common form of construction.
Post-tensioning concrete increases its structural efciency, allowing it to span longer distances or reducing
the depth of section required.
Hybrid concrete construction is a fast form of construction, bringing together the nish quality of precast
with the flexibility and mouldability of insitu concrete.
Precast concrete allows fast construction on site with minimal waste and provides excellent factory quality
finishes requiring little or no finishing on site.
Tunnel form is a formwork system which provides a fast and highly robust construction. It is particularly
useful for residential structures, including hotels and student hostels.
New high performance concretes have been developed over the past few years which can bring benets to
the building owner, the designer and the contractor. High performance concretes tend to be more durable
and easy to lay.
Concrete producers can supply concretes to meet the requirements of all the construction forms presented
in this publication.
Concrete is a local product, with low embodied energy, and is fully recyclable at the end of its life.
Concrete is durable and requires little or no maintenance. It does not burn and is not susceptible to rot.
Concretes thermal mass can be used to reduce dramatically the energy required to heat or cool a building,
leading to lower operational costs.
REFERENCES
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
Economic Concrete Frame Elements -a handbook for the rapid sizing of concrete frames, 97.358, British
Cement Association, 1997.
2.
Commercial Buildings Cost Model Study, CCIP 010, The Concrete Centre, 2006
3.
High Performance Buildings: Using Tunnel form Concrete Construction, TCC/04/02, The Concrete Centre,
2005. Visit www.concretecentre.com/publications
4.
Hospital Floor Vibration Study, Comparison of Hospital Floor Structures with respect to NHS Vibration
Criteria, Study commissioned by The Concrete Centre, 2004
5.
Concept - an invaluable design tool for the conceptual design of reinforced concrete frames, TCC/03/012,
The Concrete Centre, 2004
6.
Kennedy G, Goodchild C H, Practical Yield Line: Applied Yield Line Theory, TCC/03/03, The Concrete Centre, 2004
7.
Brooker O, How to Design Reinforced Concrete Flat Slabs Using Finite Element Analysis, TCC/03/027,
The Concrete Centre, 2006
8.
9.
Post-tensioned Concrete Floors: Design Handbook, TR43, The Concrete Society, 2005
10. Hybrid Concrete Construction: Combining precast and insitu concrete for better value structural frames,
TCC/03/010, The Concrete Centre, 2005
11. High Performance Buildings; Using Crosswall Construction, TCC/03/026, The Concrete Centre, 2006
12. Thermal Mass: A concrete solution for the changing climate, TCC/05/05,The Concrete Centre, 2005.
13. Sustainable Concrete: The Environmental, Social and Economic Sustainability Credentials of Concrete,
TCC/05/03, The Concrete Centre, 2006
14. Concrete and Sound Insulation: Meeting Approved Document E Requirements For New Build Residential
Properties, TCC/04/03, The Concrete Centre, 2006
15. Quarry Products Association (QPA) - visit www.qpa.org
16. Rationalisation of flat slab reinforcement, 97.506, British Cement Association, 2000
17. Saul AGA, Principles underlying the steam curing of concrete at atmospheric temperature, Magazine of
Concrete Research, Vol.2, No.6, 1951
CI/SfB
UDC
Licensed copy from CIS: SHEFFIELDUN, SHEFFIELD UNIVERSITY, 10/05/2012, Uncontrolled Copy.
624.94 - 033.3
Ref. TCC/03/024
ISBN 1-904818-40-4
First published 2006
The Concrete Centre 2006
All advice or information from The Concrete Centre is
intended for those who will evaluate the significance and
limitations of its contents and take responsibility for its use
and application. No liability (including that for negligence) for
any loss resulting from such advice or information is accepted.
Readers should note that all the Concrete Centre publications
are subject to revision from time to time and should therefore
ensure that they are in possession of the latest version.
www.concretecentre.com