Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

NI000401R122ver2 Subs Construction Manual

Download as pdf or txt
Download as pdf or txt
You are on page 1of 57

Substation Construction

Manual

This material is made available on the basis that it may be necessary for
a Registered Professional Engineer of Queensland (RPEQ) to undertake
or oversee the engineering services to meet statutory obligations.

Substation Construction Manual


Revision History
Description of Change

Approval
Date

Initial version

25/03/2013

Draft 2a

Content revised and additional content added,


including safety, working in substations, project
delivery, quality, project documentation,
environment, civil works, communications,
control building electrical services.

11/02/2014 R. Bowser

Draft 2b

Content revised to include the use of recently


developed Substation Construction Tools.
References updated and re-organised.

06/05/2014 P. Le/ R. Bowser

Version
1

i
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Revised By

Reference NI000401R122 Ver 2

Substation Construction Manual


Table of Contents
1.

PURPOSE AND SCOPE ............................................................................................. 1

2.

RESPONSIBILITIES ................................................................................................... 1

3.

DEFINITIONS, ABBREVIATIONS AND ACRONYMS ................................................. 1

4.

REFERENCES ............................................................................................................ 2
4.1

4.2

5.

Ergon Energy Controlled Documents........................................................................... 2


4.1.1 Substation Manuals .........................................................................................2
4.1.2 Substation Construction Tools ........................................................................2
4.1.3 Policies and Business Rules ...........................................................................2
4.1.4 Work Instructions, Guides & Reference Documents .......................................2
4.1.5 Forms ..............................................................................................................4
4.1.6 Asset Management Substation Standards ......................................................5
Australian/International Standards and Legislation ...................................................... 6

SAFETY LEGISLATION AND POLICIES .................................................................... 7


5.1

Ergon Energy Workplace Health and Safety Policy ..................................................... 7

5.2

Queensland Safety Legislation .................................................................................... 7

5.3

Safety in Design (Risk Management)........................................................................... 8

5.4

Daily Task Risk Management Plan (DTRMP) .............................................................. 8

5.5

Personal Protective Equipment (PPE) ......................................................................... 8

5.6

Pre-Start Meeting ......................................................................................................... 8

5.7

Site Inductions.............................................................................................................. 8

5.8

Construction Signage ................................................................................................... 8

5.9

Incident Reporting and Emergency Contacts ............................................................... 8

5.10

Working in Energised Substations ............................................................................... 9


5.10.1 Substation Entry ..............................................................................................9
5.10.2 Exclusion Zones, Authorised Persons, Safety Observers ...............................9
5.10.3 Training and Authorisations ..........................................................................10
5.10.4 Access to Substation Entry Keys ..................................................................10
5.10.5 Construction Safety Requirements ...............................................................10
5.10.6 Site Hygiene, Protection of Property and Final Cleaning ..............................11
5.10.7 Construction Release and Safety Clearance ................................................11

6.

LEGISLATION AND STANDARDS ........................................................................... 12

7.

QUALITY MANAGEMENT ........................................................................................ 13

8.

7.1

Workmanship and Materials....................................................................................... 13

7.2

Quality Management Plan (QMP) .............................................................................. 13

7.3

Inspection and Test Plans .......................................................................................... 13

PROJECT DELIVERY ............................................................................................... 14


8.1

Project Phases ........................................................................................................... 14


ii
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual

9.

8.2

Project Staging and Contingency Planning ................................................................ 14

8.3

Bill of Materials ........................................................................................................... 15

8.4

Material Ordering (Electrical) ..................................................................................... 15

8.5

Delivery of Plant and Materials to Site ....................................................................... 16

8.6

Work Specifications.................................................................................................... 17

DRAWINGS, DOCUMENTATION, AND RECORDS ................................................. 17


9.1

General ...................................................................................................................... 17

9.2

Drawings (Physical, Schematics, Schedules) ............................................................ 17

9.3

Project Documentation and Deliverables ................................................................... 18

9.4

Interpretation of Revision Clouding on Drawings ....................................................... 21

9.5

Greenlining of Electrical Drawings ............................................................................. 21

9.6

As Built Drawings ....................................................................................................... 21

10. ENVIRONMENT ........................................................................................................ 22


10.1

General ...................................................................................................................... 22

10.2

Noise .......................................................................................................................... 22

10.3

Oil Handling................................................................................................................ 22

10.4

SF6 Gas Handling ...................................................................................................... 23

10.5

Erosion & Sediment Control ....................................................................................... 23

10.6

Cultural Heritage ........................................................................................................ 23

11. CIVIL Works .............................................................................................................. 24


11.1

General ...................................................................................................................... 24

11.2

11.3

Civil Construction Work .............................................................................................. 24


11.2.1 Asbestos .......................................................................................................24
11.2.2 Safe Work and Builders Area ........................................................................25
11.2.3 Exclusion Zones ............................................................................................25
11.2.4 Excavations ...................................................................................................25
11.2.5 Star Pickets ...................................................................................................25
11.2.6 Earth Grid ......................................................................................................25
11.2.7 Confined Spaces ...........................................................................................26
11.2.8 Hot Works .....................................................................................................26
11.2.9 Scaffold Certificate ........................................................................................26
Mobile Plant ............................................................................................................... 26

11.4

Other References ....................................................................................................... 26

12. PRIMARY PLANT ..................................................................................................... 27


12.1

General ...................................................................................................................... 27

12.2

Power Transformers................................................................................................... 27

12.3

HV Circuit Breakers (Outdoor) ................................................................................... 28

12.4

Current Transformers, Including CT Marshalling Box ................................................ 28

12.5

Voltage Transformers, Including VT Marshalling Box ................................................ 29

12.6

Disconnectors and Earthing Switches........................................................................ 29


iii
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


12.7

Surge Diverters and Station Post Insulators .............................................................. 29

12.8

Load Control Plant ..................................................................................................... 29

12.9

Capacitor Banks ......................................................................................................... 30

12.10 HV Switchboards........................................................................................................ 30
12.11 HV Cables .................................................................................................................. 30
12.11.1 General .........................................................................................................30
12.11.2 Thermal Backfill .............................................................................................31
12.11.3 Cable Marking and Identification ...................................................................31
12.11.4 Cable Terminations .......................................................................................31
12.12 Busbars and Conductors............................................................................................ 32
12.12.1 Overhead Conductors ...................................................................................32
12.12.2 Rigid Busbars ................................................................................................32
12.12.3 Droppers and Flexible Connections ..............................................................33
12.13 Clearances ................................................................................................................. 33
12.14 Lightning..................................................................................................................... 34

13. EARTHING ................................................................................................................ 35


13.1

Main Earth Grid .......................................................................................................... 35

13.2

Extending Fences and Earth Grids in Energised Substations ................................... 35

13.3

Support Structures, Equipment, Cable Trench Covers .............................................. 36

13.4

Panels and Building Equipment ................................................................................. 37

13.5

Cable Screens............................................................................................................ 37

14. SECONDARY SYSTEMS.......................................................................................... 39


14.1

Protection and Control Panels ................................................................................... 39

14.2

Remote Terminal Units and Local Control Facility ..................................................... 39

14.3

Communications ........................................................................................................ 39

14.4

Metering ..................................................................................................................... 41

14.5

LV Cabling, Secondary Wiring and Terminals ........................................................... 41


14.5.1 General .........................................................................................................41
14.5.2 Installation .....................................................................................................41
14.5.3 Cable Cores and Terminations .....................................................................42
14.5.4 Optical Fibre Cables ......................................................................................43

15. MISCELLANEOUS .................................................................................................... 44


15.1

Substation Auxiliary AC Supplies ............................................................................... 44

15.2

DC Supply Systems ................................................................................................... 45

15.3

Lighting....................................................................................................................... 45

15.4

15.5

Nameplates, Signage, Labelling ................................................................................ 45


15.4.1 General Requirements ..................................................................................45
15.4.2 Rating Plates, Nameplates and Operational Signs .......................................46
15.4.3 Labels ............................................................................................................46
15.4.4 Safety Signs ..................................................................................................46
Painting ...................................................................................................................... 46

15.6

Locks, Keys, Operating Equipment, Miscellaneous Control Building Furniture ......... 47


iv
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


15.7

Control Building Electrical Services ........................................................................... 47

15.8

Commissioned / De-commissioned Plant Data Capture Forms ................................. 48

16. ELECTRICAL CONSTRUCTION TESTING .............................................................. 49


16.1

General Scope ........................................................................................................... 49

16.2

Specific Requirements for Secondary Wiring and Associated Equipment ................. 49

16.3

Construction Release and Handover ......................................................................... 50

16.4

Construction Safety Clearance .................................................................................. 50

16.5

Outstanding Items ...................................................................................................... 51

v
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


1.

PURPOSE AND SCOPE

This document is a reference for the constructors of Ergon Energy substations and it covers all
aspects of substation construction for both Greenfield and Brownfield substation projects to meet
the performance expected by Ergon Energy. The manual is applicable for all substation projects
regardless of internal/external construction delivery mode.
The Substation Construction Manual is not intended to replace Asset Management Standards, but
rather to act as a reference document that cross-references existing Standards and Process
Documentation and plug any gaps where Asset Management Documentation does not exist.

2.

RESPONSIBILITIES

The Group Manager Works Enablement is the Process Owner responsible for approving this
Reference.
The Manager Substation Design is the Subject Matter Expert (SME) for the content and shall
implement and maintain this Reference.
The Manager Management Systems is the Management System Representative and is
responsible for the endorsement of this Reference prior to submission for approval.

3.

DEFINITIONS, ABBREVIATIONS AND ACRONYMS

AMO

Asset Management Officer

Brownfield Site

An existing energised site

DTRMP

Daily Task Risk Management Plan

Greenfield Site

Is a term used to describe undeveloped land in a city or rural area.

HVE

High Voltage Entry

HV

High Voltage (greater than 1000 V a.c.)

ITP

Inspection and Test Plan

LV

Low Voltage (Exceeding 50 V a.c., but not exceeding 1000 V a.c.)

NAR

Network Access Restrictions

OFLS

Officer For Local Security

PC

Principal Contractor

PPE

Personal Protective Equipment

QMP

Quality Management Plan

RPEQ

Registered Professional Engineer Queensland

SID

Safety in Design

SPRMP

Simple Project Risk Management Plan

SWMS

Safe Work Method Statements

SWP

Standard Work Practice

Page 1 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


4.

REFERENCES

4.1

Ergon Energy Controlled Documents

4.1.1

Substation Manuals

NI000401R121

Substation Design Manual

NI000401R122

Substation Construction Manual

MN000301R171

Test and Commissioning Manual

NA000403R328

Queensland Electricity Connection and Metering Manual (Reference)

4.1.2

Substation Construction Tools

MN000301F188

Construction Tool Earthing Transformer

MN000301F190

Construction Tool Reactor

MN000301F191

Construction Tool Ring Main Unit

MN000301F192

Construction Tool Substation General

MN000301F193

Construction Tool Transmission Cable

NA001801F109

Construction Tool NOMAD

SP0233C10

Construction Tool Recloser

SP0406C06

Construction Tool Local Supply Transformer

SP0407C05

Construction Tool HV Cable (up to 33kV)

SP0504C13

Construction Tool Power Transformer

SP0507C06

Construction Tool Current Transformer

SP0508C06

Construction Tool Voltage Transformer

SP0509C06

Construction Tool Circuit Breaker

SP0512C05

Construction Tool Surge Diverter

SP0514C05

Construction Tool Isolator/Earth Switch

SP0515C06

Construction Tool Bus Assembly

4.1.3

Policies and Business Rules

EP02

Health and Safety Policy

EP12

Environment and Cultural Heritage Policy

EP101

Drug and Alcohol Policy

ES00100R100

Drug and Alcohol Policy Business Rules

4.1.4

Work Instructions, Guides & Reference Documents

BS001404R114

Laser Safety Guidelines: Optical Fibre Laser

BS001404R140

Management of SF6 Gas and its By-Products (Reference)

BS001404R152

Inspect Insulated Tools Before Use (Field Instruction)

BS001405R100

Authorised Person (Quick Reference Guide)


Page 2 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


BS001409R104

Hot Work (Field Instruction)

BS001409R113

Asbestos Management Plan (Reference)

BS001409R120
CS000501R110

Contractor Asbestos Related Work or Asbestos Removal Work


(Reference)
Field/Workshop Personal Protective Equipment (Reference)

CS000501W114

Prepare and Implement Daily / Task Risk Management Plans

ES000702W100

Make Site Safe Manage Environmental Spills (Work Instruction


(Manual))

ES000704R100

Single Incident Management Framework (Reference)

ES000802R103

Manage Ergon Energy Site Inductions (Reference)

ES000900R102

Safety First Your Guide to Safe Work

ES000901R102

Health and Safety Risk Control Guide (Reference)

ES000901R151

Confined Space Management Plan (Reference)

ES000901R163

Health, Safety and Environment Handbook (Reference)

ES000901R166

Management Asbestos (Quick Reference Guide)

ES000904R101

Environmental Control Measures (Reference)

ES000904R121

Soil Erosion and Sediment Control (Reference)

ES000904R122

Environmental Management of Fuel and Oil (Reference)

ES000906R100

Cultural Heritage Discovery Process (Field Instruction)

HR000500R101

Requirements for Supervision of Apprentices (Reference)

HR000500R105

Switching and Access Training and Authorisation

MN000301R166

Construction and Wiring Guidelines for Ergon Energy Substation


Panels (Reference)
Greenlining and Bluelining of Ergon Energy Substation Drawings
(Reference)

MN000301R167
MP000903R117

Environmental Protection Requirements (Reference)

NI000401R117

Substation Controlled Drawings

NI000401R118

Substation Controlled Drawings (Quick Reference Guide)

NI000703R100

Project Environmental Management Plan (Reference)

P53H05B03

Appoint a Safety Observer (Work Instruction)

P53K05R03

Queensland Electricity Supply Industry Substation Barrier Chart


(Reference)
Roles and Responsibilities of a Safety Observer Field Instruction
(Reference)
Appendix B Exclusion Zones in Millimetres (External Reference)

P61B10R21
P98R75
RTHS4301
RTHS9702

Ergon Energy Generic Field Induction Program Overview (Training


Material)
Care and Use of Personal Safety Equipment (Training Material)

RTSW6602

Safe Entry to HV Enclosures Participant Guide (Training Material)

SB0301

Civil Works (Standard Work Practice)

Page 3 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


SB0301R04
SB0401

Earthmat Connection Inside a Substation Job Safety Analysis


(Reference)
Installation of Photo Voltaic Systems

SC1800R15

Safety Signage at Construction Sites (Reference)

SGM002

Substation Earthing Strategy

SP0502

Safe Entry to High Voltage Enclosures (Standard Work Practice)

SP0502R04
SP0510

Safe Entry to High Voltage Enclosures SWP SP0502 Field


Instruction (Reference)
Substation Earth System Injection Testing (Standard Work Practice)

SP0515

Bus Assembly Testing SWP

SP0515C01

Bus Assembly Test Report

STMP004

Standard for Communications Equipment Installation (Standard)

SWMS001 to 005

Working at Heights (>2m)

SWMS006

Working on or Near a Road or Railway

SWMS012

Temporary Support of Poles or Structures

SWMS014

Movement of Powered Mobile Plant

SWMS015

Excavations (Safe Work Method Statement)

SWMS016

Confined Space

SWMS015R01

Excavations Job Safety Analysis (Reference)

WR000800R100

Contractor WHS Management Guidelines

4.1.5

Forms

BS001405M100

Request for Authorisation Letter (Training Material)

BS001409F101

Confined Space Entry Permit (Form)

BS001409F104

Hot Work Permit (Form)

CS000501F115

Daily Task Risk Management Plan (Form)

HR000506F104
MN000301F174

Technical Training and Development Contractor Induction Nomination


(Form)
Commissioning Authority for Energising Electrical Plant (Form)

MN000301F175

Construction Release (Form)

MN000301F123

Construction Safety Clearance High Voltage Apparatus (Form)

NA000403F189

Commissioned Substation Plant Record/Data Form

NA000403F190

De-Commissioned Substation Plant Record/Data Form

NI000401F104

Transmittal Note

P53K45B01C01

Site Induction Checklist (Form)

PW000702F100

Simple Project Risk Management Plan (Form)

SWMS015F01

Permit to Dig Ergon Energy Controlled Properties (Form)

WR001001F113

Construction Work Pre Start Checklist (Includes a Sample Site


Induction) (Form)

Page 4 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


4.1.6

Asset Management Substation Standards

STNW3000

Substation Design Standard System

STNW3001

Substation Equipment Identification

STNW3003

Substation Design Requirements

STNW3007

Substation Standards on Climatic and Seismic Conditions

STNW3013

Clearances in Air

STNW3014

Busbar Design

STNW3015

Primary Plant Ratings

STNW3017

Power Capacitor Applications and Shunt Capacitor Design Guide

STNW3018

Cables and Cabling

STNW3022

DC Supplies

STNW3023

AC Supplies

SS-1-6.1

Civil Works

STNW3028

Substation Earthing

STNW3029

Safety Earthing

STNW3030

Soil Resistivity Testing

STNW3031

Substation Surge Protection

STNW3032

Substation Direct Lightning Strike Shielding

STNW3033

Selection of Surge Arresters

STNW3034

Insulation Co-ordination

STNW3035

Substation Fire Protection

STNW3036

Oil Containment

STNW3037

Substation Signage

STNW3039

Substation Security

STNW3040

Substation Lighting

STNW3041

Audible Noise

STNW1002

Protection Standard

STNW3106

SCADA Standard Point List

STNW3107

SCADA Point Naming

SS-2-3.10

Capacitor Automatic Control

SS-2-3.11

SCADA Point List for ICCP

SS-2-3.12

OLTC AVR Control

SS-2-3.20

SCADA Point List for IGM

SS-2-3.21

SCADA Auto Reclose Implementation

SS-2-3.22

SCADA Auto Close

STNW3114

Substation Metering

SS-2-4.2

Ripple Control Receiver Internal Program Features Type RO

STNW1169

Network Operational Identification and Naming Standard Substation,


Generation and Communication Equipment

STNW1004

Standard for Auto-Reclose


Page 5 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


AM-P-SUP-0001
4.2

Risk Analysis for Distribution Sub-Transmission and Transmission


Auto-reclose Standards

Australian/International Standards and Legislation

AS 1111

ISO Metric Hexagon Commercial Bolts and Screws

AS 1112

ISO Metric Hexagon Nuts, Including Thin Nuts, Slotted Nuts and
Castle Nuts

AS 1214

Hot-Dip Galvanised Coatings on Threaded Fasteners (ISO Metric


Coarse Thread Series)

AS 1670

Fire Detection, Warning, Control and Intercom Systems System


design, installation and commissioning

AS 2067

Substations and High Voltage Installations exceeding 1kV AC

AS 2436

Guide to Noise and Vibration Control on Construction, Demolition and


Maintenance Sites

AS 2601

The Demolition of Structures

AS 2791

High Voltage Switchgear and Controlgear Use and Handling of


Sulphur Hexafluoride (SF6) in High-Voltage Switchgear and
Controlgear

AS 2865

Confined Spaces

AS/NZS 3000

Australian/New Zealand Wiring Rules

AS/NZS 4576

Guidelines for Scaffolding

AS/NZS 5000.1

Electric Cables Polymeric Insulated For Working Voltages up to


and Including 0.6/1 (1.2) kV

AS 62271.301

High Voltage Switchgear and Controlgear Dimensional


Standardisation of Terminals

AS HB20

Graphical Symbols for Fire Protection Drawings

AS/ACIF S008

Requirements for Customer Cabling Products

AS/ACIF S009

Installation Requirements for Customer Cabling (Wiring rules)

AS/NZS ISO 9001

Quality Management Systems Requirements

AS/NZS ISO 10005

Quality Management Systems Guidelines for Quality Plans

ENA EG-1

Substation Earthing Guide

IEEE 80

Guide for Safety in AC Substation Grounding

Professional Engineers Act 2002


Queensland Electrical Safety Act 2002 Code of Practice: Works
Queensland Electrical Safety Regulation 2013
Queensland Work, Health and Safety Act 2011
Queensland Work, Health and Safety Regulation 2011
Queensland Environmental Protection Act 1994
Queensland Workplace Health and Safety Scaffolding Code of Practice 2009
Queensland Workplace Health and Safety Confined Spaces Code of Practice 2011
Page 6 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


5.

SAFETY LEGISLATION AND POLICIES

5.1

Ergon Energy Workplace Health and Safety Policy

Ergon Energy is committed to working in a way which ensures the health and safety of its
Employees, Contractors, Customers and Members of the Public.
The Ergon Health and Safety Policy (EP02) targets a level of zero work-related injuries and illness
at all times. The full Policy document (EP02) is available on the Ergon Process Zone.
Refer also to the Ergon Drug and Alcohol Policy EP101 and Drug and Alcohol Policy Business
Rules ES00100R100.
5.2

Queensland Safety Legislation

The Qld Electrical Safety Act 2002 provides that an electricity entity has an obligation to ensure
that its works:
(a) are electrically safe, and
(b) are operated in a way that is electrically safe
This obligation includes the requirement that the electricity entity inspects, tests and maintains the
works.
The Act also places obligations in regards to electrical safety on all persons, including employers,
self-employed persons, designers, manufacturers, importers, suppliers, installers, repairers,
persons in control of electrical equipment, workers and other people at a place where electrical
equipment is located.
The Queensland Work, Health and Safety Act 2011 provides the framework to protect the health,
safety, and welfare of all workers at work, and of all other people who might be affected by the
work.
Under the WH&S Act everyone has duties (obligations), and the duties for a person conducting a
business or undertaking are defined and involve:
Management or control of workplaces
Management or control of fixtures, fittings or plant at workplaces
Design of plant, substances or structures
Manufacture of plant, substances or structures
Importation of plant, substances or structures
Supply of plant, substances or structures
Installation, construction, commissioning of plant or structures
Officers, workers and all other persons also have duties to work and act in a manner which
contributes positively to the protection of the health, safety and welfare of themselves and all
others who might be affected by the work. In particular, personnel must comply at all times with
all workplace health and safety directions, rules and guidelines given.
Site offices, accommodation, sanitary facilities, water etc., must meet the requirements of the latest
issue of the Act and Regulations.
All construction work must be carried out under a Work, Health and Safety Management Plan or a
Site Safety Plan, as required by the Queensland Work, Health and Safety Regulation 2011. This
Plan must be complementary to Ergon Energy requirements for entering and working in
substations. Responsibility for preparation of the appropriate Plan will be defined in the project
documentation or in MP000903R110 Work Health and Safety Conditions.
Page 7 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


5.3

Safety in Design (Risk Management)

Section 17 Management of Risks of the Work Health and Safety Act 2011 states A duty imposed on a person to ensure health and safety requires the person
(a) to eliminate risks to health and safety, so far as is reasonably practicable; and
(b) if it is not reasonably practicable to eliminate risks to health and safety, to minimise those risks
so far as is reasonably practicable.
During design development, the Designers will assess and document any hazards or risks
associated with the design, construction, ongoing operation and maintenance, or decommissioning
of the various parts and components of the substation. Any residual risks assessed as higher than
low risk and not covered by a relevant SWMS, SWP, or Work Instruction will be documented by the
Designer in a Safety in Design Report.
All Constructors must refer to the Safety in Design (SID) report provided by the Design group, prior
to commencing any construction work. For Ergon Energy workgroups, the SID Report is
PW000702F100 Simple Project Risk Management Plan (SPRMP).
5.4

Daily Task Risk Management Plan (DTRMP)

All construction crews must complete CS000501F115 Daily Task Risk Management Plan
(DTRMP), or equivalent prior to commencement of any work on site. This task requires careful
review and identification of the likely hazards involved, plus the controls to be used in managing
risk during the site activities. Completion of the DTRMP is covered in CS000501W114 Prepare
and Implement Daily / Task Risk Management Plans.
5.5

Personal Protective Equipment (PPE)

The minimum PPE required for construction sites and particularly for substations can be found in
CS000501R110: Field/Workshop Personal Protective Equipment. Particular attention should be
given to the requirement to remove all metallic jewellery and eyewear, as well as any other metallic
or non-metallic item that might get caught in panels, on structures, machinery, etc. (eg. watches,
rings, necklaces, key chains, neck ties, etc.).
Refer also to RTHS9702 Care and Use of Personal Safety Equipment (Training Material).
5.6

Pre-Start Meeting

A pre-start meeting must be conducted prior to the commencement of any construction on site.
Refer to WR001001F113: Construction Work Pre-Start Checklist, to be used as a guide for all
works. Refer also to Section 7.3 of this Manual in relation to inspection points required.
5.7

Site Inductions

To manage site inductions in Ergon Energy substations, refer to ES000802R103: Manage Ergon
Energy Site Inductions and P53K45B01C01: Site Induction Checklist.
5.8

Construction Signage

Construction signage shall be supplied in accordance with the Queensland Work, Health and
Safety legislation. Refer also to SC1800R15: Safety Signage at Construction Sites where Ergon
Energy is the Principal Contractor.
5.9

Incident Reporting and Emergency Contacts

For guidance on reporting incidents, refer to ES000704R100 Single Incident Management


Framework, ES000703R100 Incident Classification Table and ES000703R101 Guidelines for
Page 8 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Incident Classification Table for incident reporting requirements. Emergency Contacts and lines of
communication must be established prior to commencement of work on site.
5.10 Working in Energised Substations
All personnel must at all times comply with the Electrical Safety Rules and Regulations as set out
by Ergon Energy when working on, or in the vicinity of electrical apparatus that is live, or is capable
of being made live from any source of supply.
Ergon Energy reserves the right to evict any personnel from the site at any time should their
presence on-site be considered to constitute a hazard.
5.10.1

Substation Entry

In a Commissioned HV Substation, all personnel must comply with Standard Work Practice
SP0502: Safe Entry to High Voltage Enclosures at all times. This document must be read in full
and strictly adhered to as well as the site specific requirements in the project documents. Refer
also to the Field Instruction version of this document SP0502R04.
For all construction work in an energised substation, the Officer For Local Security (OFLS) must be
contacted. The OFLS will advise on any potential hazards, conditions & approval of movement or
routes of all mobile plant off designated roads including storage of materials & amenities etc. Refer
to SWP SP0502: Safe Entry to High Voltage Enclosures.
Only those Personnel who have successfully completed the required SEHVE Training and have
been duly authorised are allowed entry to the site, unless accompanied at all times by a SEHVE
Authorised Person. (Refer to Section 5.10.2 and 5.10.3 below). These requirements also apply to
an uncommissioned construction site, as soon as any HV Conductor (including earthing
conductors) becomes connected to, or within approach distance of a commissioned HV network.
In the event of a work crew containing a number of unauthorised persons (eg. civil contractor),
there should not need to be one authorised person for every unauthorised person, but there must
be a sufficient number of authorised personnel to ensure that the unauthorised persons are
accompanied and supervised by an authorised person at all times. Reference document
HR000500R101 details requirements for supervision of apprentices and others without SEHVE
training.
On arrival at the substation gate, it is essential that a check be done for any Network Access
Restrictions (NAR). Check for notification signs on the gates and also check with the Operational
Control Centre (OCC) 1800 615 784 for restrictions when checking into the substation. Current
lists of NAR can be found in the Ergon Process Zone. Contractors should seek advice from their
relevant Ergon Energy contact person. Ie. Superintendent, Technical Representative, etc.
Particular attention must be given to the requirements for locking of gates and keeping them
locked, except during entry and exit. At all times when gates are unlocked (eg. to receive
deliveries), they must be manned.
For guidance in relation to management of non GCWI/unauthorised specialist workers who come
onto site for very short, infrequent durations (eg. plumbers, concrete cutters, crane drivers, delivery
drivers, etc.), refer to Section 6.5.3 of WR000800R100 Contractor WHS Management Guidelines.
5.10.2

Exclusion Zones, Authorised Persons, Safety Observers

The Exclusion Zones for trained and untrained persons can be found in Schedule 2 of the
Queensland Electrical Safety Regulation and are replicated in the Ergon Energy Reference
P98R75: Appendix B Exclusion Zones in Millimetres. The Exclusion Zones are specified in two
different categories, as follows:
(a) Exclusion Zones for Authorised Persons and Instructed Persons (ie. under the supervision of
an Authorised Person)
Page 9 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


(b) Exclusion Zones for Untrained Persons (neither Authorised nor Instructed)
However, for Authorised and Instructed Persons, the values listed in Table 1 of Ergon Substation
Standard SS-1-3.1 Clearances in Air apply, as in some cases they are slightly larger than those
given in the Safety Regulation and P98R75.
Authorised Persons and their required competencies are defined in the Queensland Electrical
Safety Regulation and in the Ergon Energy Quick Reference Guide BS001405R100: Authorised
Person. In general, an Authorised Person must be able to demonstrate competence in recognising
communication, low voltage and high voltage conductors, understand the dangers involved in live
high voltage substations and be familiar with the appropriate Exclusion Zones. The training
requirements for Authorised Persons are indicated in Section 5.10.3.
A Safety Observer is required where it is possible that an Exclusion Zone may be compromised.
Refer to Work Instruction P53H05B03: Appoint a Safety Observer, Field Instruction P61B10R21
Roles and Responsibilities of a Safety Observer and definition in the Queensland Electrical Safety
Regulation. The person appointed to be a Safety Observer must be an Authorised Person and
also have the knowledge and competencies indicated in the above Work Instructions, so generally
will need to have had adequate experience working in similar situations in live HV substations.
However, a formal electrical qualification is not essential.
Refer also to Section 11.2.3 of this Manual in relation to Civil construction work.
5.10.3

Training and Authorisations

To be authorised for unaccompanied entry into a HV substation, personnel must have successfully
completed the training course RTSW66 Safe Entry to High Voltage Enclosures. Prerequisites for
this training are RTHS4301 Field Induction for Ergon personnel, or as indicated on HR000506F104
Contractor Training Nomination Form.
On successful completion of the training, the relevant supervisor or employer must forward a
Request for Authorisation to Ergon Energy, either BS001405M100 (non electrical) or
BS001405M101 (electrical), as appropriate.
For personnel who require further authorisations, such as Individual of a Workgroup, Access
Permit Recipient, Switching Operator Assistant, etc., further training courses are necessary, as
indicated in Reference document HR000500R105.
5.10.4

Access to Substation Entry Keys

Only authorised personnel may hold substation entry keys and such keys are issued subject to
strict conditions of use. Following authorisation for substation entry, personnel may apply for a key
if required, by completing a Request for Issue of Key form and forwarding by email to the
appropriate Officer for Local Security. Until the form becomes available online, for Ergon
personnel it may be obtained from the local AMO, or for Contractors through the relevant Ergon
contact person.
5.10.5

Construction Safety Requirements

Refer to reference documents SP0502, BS001404R152 and SB0301 for specific instructions in
relation to use of mobile plant/equipment, carrying objects in a HV enclosure, use of 00 gloves and
exclusion zones. Refer also to Section 5.10.2, in relation to exclusion zones.
In addition, the training material RTSW6602 Safe Entry to High Voltage Enclosures has additional
material for safety requirements inside substations, including use of portable electric tools,
handling extension leads, battery rooms, barriers, safety signs, storage and handling materials and
other specific hazards.
All high risk and non-standard construction activities must be carried out in accordance with
appropriate Safe Work Method Statements (SWMS). A list of Ergon Energys SWMS can be found
in the document ES000901R102: Health and Safety Risk Control Guide or at the front of the
Page 10 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Daily/Task Risk Management Plan. If an appropriate SWMS is not available, then one must be
developed prior to commencement of the high risk activity.
5.10.6

Site Hygiene, Protection of Property and Final Cleaning

At all times during the course of work on a substation site, whether green-field or brown-field, the
site must be maintained in as clean and tidy a state as possible, according to the state of the work,
so as to minimise the risk of injury or illness, enable efficient and safe access for construction
vehicles and personnel, etc. and otherwise meet Work, Health and Safety requirements.
Appropriate bins shall be provided and used for disposal of rubbish, waste, etc. and arrangements
made for appropriate removal of the rubbish from the site regularly, in accordance with local
regulations.
Particular care must be taken not to cause any damage to public and private properties, land,
streets, including public utilities and the soil and space beneath such properties abutting and/or
adjacent to the works. The constructor must make good any loss or damage caused.
On completion of the works, all rubbish, waste, excess material, plant and temporary work,
including sanitary conveniences, offices, sheds, hoardings, protective covers etc., must be taken
down and cleared away as appropriate, unless otherwise agreed with the Ergon Project Manager.
Any damage done to the substation buildings, structures, plant, earth grid, substation surfaces
(driveways, access roads, gravel surfacing, etc.), drainage, or property must be made good, before
departing the site. All gravel surfacing must be raked and graded to even-finished levels.
All doors, windows, etc., must be checked and eased to ensure proper operation and closure.
The complete works must be cleaned, including but not limited to the work described below:

Clean all windows, both inside and out.


Remove all render and other spots on metal sashes, box sections and on other surfaces.
Dust all walls, ledges and projections.
Wash, if necessary, to clean all walls.
Remove all paint spots from floors and walls.
Clean all hardware, ironmongery and other fittings.
Thoroughly clean all porcelain insulators and bushings immediately prior to testing.
Sweep all building floors and dispose of rubbish.
Check outdoor concrete slabs and roads for soil/gravel and sweep if necessary.
Check and clear all drains.
Check any other services not already done.

5.10.7

Construction Release and Safety Clearance

Following completion of the electrical installation, including construction testing in a part of the site
(eg. the 66kV switchyard) and issue of MN000301F175: Construction Release for that area, the
associated HV plant must now be considered as capable of being made live and therefore no
longer accessible to personnel.
Refer also to Section 16.3 for further detail.

Page 11 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


6.

LEGISLATION AND STANDARDS

All construction work, and the associated supply of materials and equipment, must be undertaken
in accordance with all relevant Legislative and Regulatory requirements, the latest revisions of the
relevant Ergon Energy Asset Management Standards, Specifications and EESS drawings, and the
relevant Australian Standards.
Where no Australian Standard exists, then the latest revision of the relevant International
Electrotechnical Commission (IEC) Standard, British Standard (BS), or the NATSPEC BASIC
Standard (in that order of preference) applies.
A list of the most relevant Australian/International Standards & Queensland legislation is provided
in Section 4.2 of this manual, but is by no means exhaustive.
Any deviations from the Ergon Energy Standards and Specifications must be with the approval of
Asset Management and following approval must be clearly stated in the Project Design
Documentation. A documented and approved risk assessment must be produced in consultation
with the relevant SMEs in instances where the Project Scope Statement or Project Sponsor directs
work to be undertaken which is not in accordance with the standards.
A list of Ergon Energy Asset Management Substation Standards is provided in Section Error!
Reference source not found. of this manual. The Ergon Energy Standards provide reference to
the applicable Australian Standards.
Safety legislation and policies are outlined in Section 5 of this manual. Electrical safety
requirements are not negotiable and must be strictly complied with at all times.

Page 12 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


7.

QUALITY MANAGEMENT

7.1

Workmanship and Materials

Work must be done by appropriately qualified, competent tradespersons in an entirely sound,


secure, neat, efficient and tradesman like manner, complying with the relevant Ergon Energy
Standards. Where materials or work methods are included in the published Standards of the
Standards Association of Australia, the materials and workmanship used must not be inferior to
those in the relevant Standard.
Unless otherwise specified, all materials used must be entirely suitable for the intended application,
whether stated or implied, and be free from defects. Where materials bearing the Australian
Standards mark are available, these materials must be the minimum standard for use. All
manufactured materials must be used strictly in accordance with the manufacturers instructions
and recommendations.
7.2

Quality Management Plan (QMP)

All construction work must be covered by a Quality Management Plan in accordance with AS/NZS
ISO 10005, which ensures the work is carried out in accordance with the project documents and
the relevant Ergon Energy standards. Inspection and Test Plans must be included in the QMP.
The ITPs must clearly show all inspection witness and hold points, testing requirements and how
the work will comply with the project documentation.
7.3

Inspection and Test Plans

All constructors must carry out sufficient inspection and construction testing of the works installed
by them using ITPs, to confirm correct and adequate installation in accordance with the drawings
and relevant Ergon Energy standards.
The relevant constructor is responsible for developing and obtaining RPEQ approval of ITPs for all
construction testing to be carried out on their portion of the works. Form 16, inspection hold points
and any additional tests required by the Certifying RPEQ must be integrated into the ITPs and
discussed in the pre-start meeting.
7.3.1 Electrical Works
The minimum requirements for electrical construction testing are described in Section 16 of this
Manual.
Specialist testing of HV plant and functional testing of the secondary systems (protection, control,
etc.) is the responsibility of the test and commissioning groups, but is dependent on adequate
construction testing being completed first by the constructors.
7.3.2 Civil Works
Refer to SS-1-6.1 Civil Works for testing frequency and acceptance criteria. The Constructor must
have a training plan showing each workers qualifications, inductions, training, licences,
competencies and authorisation status. This also includes workers of subcontractors that have
been engaged by the Principal Contractor.

Page 13 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


8.

PROJECT DELIVERY

8.1

Project Phases

This section provides a general overview of the phases, milestones and deliverables involved in an
Ergon Energy project. More specific deliverables for the constructors are indicated in Section 9 of
this Manual.
The Ergon Energy project delivery model comprises four distinct phases being:
(a)

Concept Phase

This phase normally commences with the issue of a Recommended Works Report (RWR) and is
complete at the initiation of an approved project (PIA). During this phase, concept Single Line
Diagrams and General Arrangement drawings are produced.
The milestone for this phase is WPIA (Works Planning Project Initiation Advice).
(b)

Development Phase

This phase normally commences with the issue of a Project Initiation Advice (PIA) and is complete
at the handover of the approved, integrated design to the Project Manager, as follows:
Work Specification completed and approved
All Design Drawings RPEQ approved, transitioned to Released for Construction state in
EDMS, printed to an electronic drawing set (Adobe pdf) and issued to Project Manager together
with Transmittal (NI000401F104), Work Specification and Bill of Materials.
The milestone for this phase is DC (Design Complete).
(c)

Implementation Phase (construction, testing, commissioning)

This phase commences at the handover of the approved designs and is complete at the issuing of
the Certificate of Practical Completion.
The milestones for this phase are CCM (Construction Commenced), FCA (First Capacity
Available), and CPC (Certificate of Practical Completion)
The Design Groups provide construction support activities during the implementation phase of a
project and provide deliverables as listed in NI000401R121 Substation Design Manual.
The constructors provide the majority of their deliverables during this phase of the project, as listed
in Section 9.2 of this Manual.
(d)

Finalisation Phase

This phase generally commences when First Capacity is available (FCA) and is completed by
project close out.
The milestone for this phase is PCO (Project Close Out).
The constructors provide some further deliverables, also as listed in Section 9.2 of this Manual.
8.2

Project Staging and Contingency Planning

For project works in existing live substations (brownfield), construction, testing and commissioning
are likely to need to be carried out in stages, to minimise outages of supply to customers. In such
cases, access is available to only a portion of the works area at a time and sometimes may require
work to be done under the strict conditions of an Ergon Access Permit.

Page 14 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


In many cases (eg. feeder cut-overs), it will be necessary to energise the completed stage, before
access to the next stage can be made available. Therefore it is essential that the Master copy
drawings be fully marked up to reflect the current operating status of the substation. (Refer to
Section 9.5 of this document). Depending on the complexity of the project and changes made to
the substation, in some cases it may be necessary that the drawings be updated in EDMS and
reissued for construction of the next stage.
When existing live circuits have to be taken out of service, generally a contingency plan will be
essential, to enable the circuit to be returned to service quickly in the event of an emergency on the
high voltage system. Such plan should be prepared by the relevant design group, in conjunction
with input from the construction and/or commissioning groups.
Refer to the project documentation for the specific staging required on a particular project.
8.3

Bill of Materials

For each project, a Bill of Materials (BOM) will be prepared by the Electrical Designers, specifying
all substation electrical materials required for the project, except for minor and consumable items
such as bolts, nuts, screws, cable and wire numbering ferules, terminal lugs for LV cables,
miscellaneous terminals, LV cable clamps and ties, grease, cleaning fluids, which would normally
be sourced by the Constructor. The BOM will collate the requirements for each particular item
listed, so as to assist with procurement of materials and should indicate the specific division of
procurement responsibilities.
There may also be separate Bills of Materials from the Communications and/or Distribution design
groups, in the event that the Constructor is also required to install equipment for those disciplines.
However, a Civil Bill of Materials will not be produced, as it is expected that the Civil Constructor
will need to use both the issued construction drawings and on-site measurements to estimate the
quantities of the various materials required to complete the Civil Works.
8.4

Material Ordering (Electrical)

It is the responsibility of the electrical Constructor to confirm that all plant and materials have been
ordered in a timely manner to meet the project schedule requirements, either through the Ergon
Logistics system (store), or by direct purchase where necessary.
Long lead time items, as defined by the project delivery milestones (eg HV plant, protection relays
etc.), will be ordered by the Designers (or Tech Rep for contract works), prior to Gate 3
(construction) funding approval, in order to meet the project schedule timelines. Estimated arrival
dates for such items will be indicated on the Bill of Materials.
Following receipt of Gate 3 funding approval, the requisitions for all of the items ordered in
advance as indicated above, will be modified to transfer the costs to the project, which will then
enable those items to be collected by the Constructor from a holding location as advised by the
Project Manager.
The Constructor (via the Tech Rep for contract works) will use the Bill of Materials to requisition all
remaining items on the Bill of Materials from the Logistics system as required. These items will
also be made available for pickup from the same holding location as for the long lead time
materials, or as specified in the requisition.
On commencement of construction, the Constructor must take responsibility for maintaining the
BOM, keeping it up to date with details of equipment and materials ordered, received, etc.
Updates on the status of long lead time items will be forwarded to the Constructor by the Design
Manager as available, so that the BOM can be updated accordingly.
The Constructor must be responsible for procurement of all other items required, which are not
already on the BOM at the commencement of construction, either from the Logistics system or by
direct purchase if necessary.
Page 15 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Where lead times on outstanding materials appear that they will impact on the project delivery
schedule, the Constructor must notify the Project Manager as soon as possible and assist with
finding a resolution that minimises the impact on project delivery and quality.
The status of each item and the precise allocation of procurement responsibilities on a specific
project will be indicated on the BOM, but should be checked and confirmed between the relevant
design and construction groups, to ensure no items are missed.
8.5

Delivery of Plant and Materials to Site

The Constructor must arrange and co-ordinate the transport to the site and unloading of all
materials, plant, and equipment, including any necessary cranage, except for any items being
delivered directly to site under separate contract (eg. power transformers). This responsibility
includes the costs of storage, handling, insurance and other charges.
Prior to pickup of the materials from the holding location, the Constructor must give the Project
Manager at least seven (7) days notice of intention, to ensure that the materials will be available at
that location.
On pickup of materials from the Ergon holding location, the Constructor must check off each item
on a Materials Movement Form, sign and date the form and forward a copy of the signed off form
to the Design Manager as soon as possible. This form will include the description of each item,
quantity, date, name and signature of recipient.
The Constructor must check as far as practicable that the issued plant, equipment and materials
appear to be in undamaged condition and are the correct items before leaving the Ergon storage
depot. For major plant items in large wooden crates, visual inspection of the condition of crates
and checking of contract/item numbers/ descriptions on the outside of the crates will be sufficient at
this stage, to avoid the need for un-crating and re-crating before despatch. Smaller items, such as
protection relays are generally more easily unpacked for a quick visual inspection and check of
model number inside the box.
Any defects or damage found are to be reported to the Project Manager and/or Design Manager
and recorded on the Materials Movement Form. All equipment and materials leaving the storage
site without a defect register will be deemed to have been supplied in undamaged condition.
As soon as possible after arrival on site, all equipment must be fully un-crated to enable proper
checking for transport or other damage and that the correct items have been received (in case of
errors in the data on the outside of the crates). Again any defects or damage found are to be
reported in writing to the Project Manager and/or Design Manager as soon as possible.
The Constructor must ensure that no equipment is damaged as a result of reasonable handling
during loading, transportation to site, unloading and site works. Any damage caused by
inadequate handling by the Constructor or their Sub-Contractors will be rectified at the expense of
the Constructor.
The Constructor must obtain all necessary road and rail traffic permits and be responsible for the
payment of all charges. All Regulations, including load limits on roads and bridges along the
planned transport route(s) must be observed.
On completion of the construction works, all unused quantities of supplied items must be suitably
packed and returned either to the storage location from which they were collected, or as otherwise
advised by the Project Manager.
In relation to direct deliveries of plant to site under separate contract, such as power transformers,
the Principal Contractor on site (generally the electrical Constructor) must be responsible for
ensuring the site readiness and clear access for the arrival of the plant on site, on the agreed
dates. Refer to Section 12.2 of this Manual and any relevant clauses in the project Specification.

Page 16 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


8.6

Work Specifications

For all substation design and/or construction projects, a project specific Work Specification will be
issued.
The Work Specification will include project specific information in relation to scope of works,
staging, outages, procurement responsibilities, certification and inspection requirements, etc. The
Specification will also include reference to the Design, Construction and Commissioning Manuals
and should complement and clarify the construction drawings provided by the designers.

9.

DRAWINGS, DOCUMENTATION, AND RECORDS

9.1

General

In the event of conflict between the requirements of the issued construction drawings and the Work
Specification or any other relevant document, the relevant Design Manager must be contacted for
clarification. In the case of an externally designed and constructed project, the Contractors
Construction group should seek clarification first from their own Design Manager. If the issue
appears to be a conflict in Ergon Energys requirements, the Contractors Design Manager or
Representative will then contact the Ergon Technical Representative (Ergon Design Manager) for
clarification.
9.2

Drawings (Physical, Schematics, Schedules)

Construction must be carried out only in accordance with drawings which:


1.

Have been signed off by the relevant RPEQ who is either carrying out or directly supervising
the design work, and

2.

Have been transitioned to Released for Construction status in the Ergon EDMS, as indicated
by:
(a) The tag 1 Work May Start in the Drawing Status box just above the Drawing
Number,
and
(b) Ergon signatures populating the Checked and Approved slots of the Revision Control
box, confirming that the drawing has been transitioned accordingly. The Drawn by slot
may indicate Contractor - XXXX. (where XXXX denotes the name of the Contractor).

Earlier issues of the drawings must not be used for construction, even if bearing a Contractors
Approved for Construction stamp, as the release of the drawings for construction is to be
controlled by Ergon Energy. This ensures that the drawings are issued for construction only after
all Ergon requirements have been satisfied, as well as locking the construction version in the Ergon
EDMS, to ensure consistency for all work groups that may need to access the drawings.
Following Gate 3 approval for the project, the originating Ergon Substation Design group will print
and collate the required number of construction sets of the drawings, appropriately stamped in
accordance with the Substation Controlled Drawings process documents NI000401R117 & R118.
The collated sets of printed drawings will be issued via the Ergon Project Manager, to all involved
Constructors.
A Drawing Transmittal must accompany the issued drawings to confirm the correct drawings and
their revisions to be used.
The Master copy set of the drawings will be issued to the first group in each of the Civil and
Electrical disciplines to commence construction of the works. Use of the Master copy drawings is
described in more detail in Section 9.6, but the Master copy set must be passed on to the next
Page 17 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


appropriate work group. (eg. Panel Construction group passes on marked up Master copies to
Field Construction group, then to Test group, etc.).
9.3

Project Documentation and Deliverables

The project specification will define the specific requirements for a particular project, however the
tables below summarise the minimum requirements for constructors during the Implementation and
Finalisation stages of a project.
(a)

Implementation Phase

Construction
Discipline

Deliverable

Principal
Contractor

Quality Program
Quality Assurance program.
Project Quality Plan.
Works Program/Schedule.
Environmental and Cultural Heritage Management Plan
Work, Health and Safety Management Plan.
Register of records (objective quality evidence).
Technical Data as required by Specification (eg. Thermal Backfill data)

Substation
Design

Printed, stamped design drawing sets issued to relevant construction groups,


as per NI000401R117 & R118.

Workshop
Construction

Pre-start meeting.
Completed modular building & panels, including point to point testing of
wiring.
Building footing design details provided to Project Manager or delegated
officer for use of site civil construction group.
Building(s) installed on site.
As-built drawing markups on Master copy drawing set forwarded to Project
Manager or delegated officer for use of site construction groups.
Copies of greenlined circuitry drawings forwarded to Project Manager or
delegated officer, confirming precise point to point testing completed, for
reference of site construction & test groups.

Civil Work
Construction

Meetings & Coordination


Pre-Start Meeting.
Project progress meetings.
Coordination with other work groups on site or preparing to come to site.
Construction Work
All civil work defined in the project documentation completed in accordance
with the Ergon Energy standards, procedures and this Manual.
As-built drawing markups transferred to the Master copies of the drawings.
Inspection and Testing
Test Results and Certificates returned to Design Manager.

Substation
Construction

Meetings & Coordination


Pre-Start Meeting.
Page 18 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Project progress meetings.
Coordination with other work groups on site or preparing to come to site.
Construction Work
All structures & HV plant installed & connected.
Secondary systems cabling & panels, earthing, etc. completed.
Construction testing of electrical installations (except that already done by
workshop on panels).
Construction Testing
Certified ITPs.
Certification of test equipment.
Test result sheets & supplementary sheets.
Problem or non-conformance reports.
List of outstanding work and defects.
Remedial work reports.
Completed Commissioned /De-commissioned Substation Plant Data Capture
Forms NA000403F189 /NA000403F190 & associated plant nameplate
photographs.
Drawings
As-built drawing markups transferred to Master copies and made available
for reference of other groups, including Communications, SCADA, Test, etc.
Greenlined working copies of schematic drawings, indicating construction
testing completed.
File compression/decompression software, where necessary.
Clearances & Certification
Competency and authorisation records.
Request for approval to subcontract work.
Notice of intention to commence supply or manufacture.
Notice of Inspection or Test.
Construction Release MN000301F175.
Construction Safety Clearance - High voltage Apparatus MN000301F123
Certificate of Practical Completion.
Variations.
SCADA
Construction

Meetings & Coordination


Pre-start meeting.
Project progress meetings.
Coordination with other work groups on site or preparing to come to site.
SCADA Works
LCF programed (may occur off site before installation in panel).
All points from the LCF to the RTU tested and commissioned.
ABB & LCF communicating correctly.
Miscellaneous configuration requirements.

Communications Meetings & Coordination


Construction
Pre-start meeting.
Page 19 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Project progress meetings.
Coordination with other work groups on site or preparing to come to site.
Communications Works
MUX configurations loaded.
Stride MUX and Cable drawings changed from Planned to existing during
commissioning.
New cross-connects added.
Coordination with other work groups on site or preparing to come to site.
As-built drawing markups on Master copies forwarded to Communications
Design group for finalising of drawings.
Field Test
(division of
responsibilities
between Ergon
& external
Contractor as
per the project
specification)

Meetings & Coordination


Pre-start meeting.
Project progress meetings.
Coordination with other work groups on site or preparing to come to site
Pre-commissioning & Commissioning Test Works
Control/protection panels & building services FAT tested.
HV plant, earthing, etc. SAT tested.
Functional testing of all secondary systems, including integration with
existing systems (eg. Bus Zone, AC & DC Supplies), OCC and remote end
substations completed.
Completed works switched into live service & carrying load as intended.
As-built drawing markups transferred to Site Initial Record copies to be kept
on site.
As-built drawing markups transferred to Master copies and forwarded to
Substation Design group for finalising of drawings.
Training
Onsite handover/training session, as required.

Commissioning
Group

Meetings & Coordination


Pre-start meeting.
Project progress meetings.
Coordination with other work groups on site or preparing to come to site.
Commissioning Works
Project commissioning plan & schedule completed.
Coordination of all internal and external work groups associated with project
commissioning.
Field Test and HV plant manufacturers test results audit checked.
Authority to Energise form completed and submitted.
AFWs and other documents required for commissioning submitted.
Completed works switched into live service & carrying load as intended.

(b)

Finalisation Phase

The following list summarises the minimum project documentation and other commitments
required as part of the project finalisation phase.
Page 20 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Construction
Discipline
Substation
Construction
(local AMO)
Field Test /
Commissioning
Group
(local AMO)

9.4

Deliverables
Final Release (as-built) drawings (including Civil & Communications) placed
in the substation, with marked up copies and old revisions replaced.
Final Release (as-built) drawings (including Civil & Communications) filed in
the Test office, with marked up copies and old revisions replaced.
Test results & signed off Protection Setting Requests (PSRs) filed in Test
office (and copy forwarded to Design Manager).
Copy of signed off PSRs returned to Protection group via Design Manager.

Interpretation of Revision Clouding on Drawings

Anything shown within the boundaries of the revision clouding on a drawing issued for construction
must be interpreted as either new or modified in relation to the existing installation.
If any doubt or uncertainty exists, the Constructor must check against the previous Final Release
version of the drawing to confirm exactly what is already existing and what has to be added or
modified. The previous revisions are available for viewing in the EDMS, otherwise copies can be
obtained on request to the Ergon Design Manager.
9.5

Greenlining of Electrical Drawings

Refer to Section 16 of this Manual for details of Electrical Construction Testing to be carried out.
During the process of continuity testing and associated visual checking of secondary wiring, the
Site Test copy (Set 12) of each relevant schematic must be greenlined and marked up with
corrections, in accordance with Ergon Energy Quality Document MN000301R167: Greenlining and
Bluelining of Ergon Energy Substation Drawings. This provides a record not only of the as-built
state of the works, but also of the progress of construction testing, for the benefit of both the
Construction and the following Test groups.
All markups (corrections, additions, deletions) on the Site Test Copy, but not the greenlining, must
be transferred to the Master copy set as indicated in Section 9.6. (Bluelining is for functional
testing to be carried out by the relevant Test Group). The Site Test copy set must then be returned
to the Project Manager, for forwarding to the appropriate Test group for Site Integration Testing
(SIT). This is the reason why it is essential that the greenlining process be done on the Set
12 copy of the drawings.
9.6

As Built Drawings

All construction and test changes to the issued drawings must be marked up, firstly on the
workgroups working copy of the drawings, then transferred to the Master copy on site prior to
departure from site (or earlier if a significant time period has elapsed since the changes were made
and other workgroups on site are dependent on the up to date Master copy also).
The Master copy drawings provide the source of the latest information for each work group on
commencement on-site, as well as the collation of all changes to be forwarded back to the Design
Office on completion of commissioning. Refer to the reference documents NI000401R117 and
NI000401R118 Substation Controlled Drawings.
Refer also to SS-1-6.1 Civil Works for additional requirements in relation to civil works drawings.

Page 21 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


10. ENVIRONMENT
10.1 General
Ergon Energy is committed to responsible Environmental Management ensuring that all business
activities associated with the supply of electricity are carried out with as little adverse impact on the
environment as possible. Refer to the Environment and Cultural Heritage Policy document EP12.
All activities carried out on the site must comply with the project Environmental and Cultural
Heritage Management Plan and the environmental requirements of substation standard SS-1-1.4
Substation Design Requirements. Refer also to the reference documents MP000903R117 and
NI000703R100 and the Queensland Environmental Protection Act.
Constructors must comply with all By Laws and Regulations of Local and other Statutory
Authorities having jurisdiction over the work.
10.2 Noise
Noise emanating from substations may be of concern in sensitive environments eg. residential,
rural, adjacent to schools, hospitals, etc. Substation standard SS-1-10.1 Audible Noise, in
conjunction with the various Legislation, Standards and other documents referenced therein, sets
out Ergon requirements in relation to management and limitation of substation noise. In addition,
the Local Authority may have some specific requirements and some specific noise level limits may
be included in the Construction specification for a particular project.
Noises created by substation plant such as transformers (hum, tap changer, fans, etc.), CTs, VTs,
circuit breakers (tripping/closing) are generally addressed through appropriate design, such as
appropriate positioning/alignment of plant, acoustic walls or screens, or in some cases specifying
low noise HV plant. The constructors must ensure that the design features provided to manage
noise level are implemented correctly to a high standard. For example, improperly fastened
metallic fittings on structures or busbars may be a source of additional vibration noise; gaps left
around the base or other part of acoustic screens are likely to reduce their effectiveness, etc.
Construction noises need to be managed through restriction of noise producing activities to the
allowable working hours as specified by Ergon and the Local Authority, use of well maintained, low
noise vehicles and construction equipment, scheduling particularly noisy activities to the time of
day with highest background noise level if possible, use of noise shielding where possible (eg.
within site workshop), etc. Refer also to AS 2436 for guidance on control of construction noise and
vibration.
10.3 Oil Handling
Substation sites contain a considerable quantity of oil in transformers, CTs, VTs, vehicles and
other operating equipment, which can pose a significant environmental & fire hazard risk, if not
handled appropriately.
All handling of oil on site must be carried out in accordance with Ergon work instruction
ES000904R122. Refer also to work instruction ES000702W100 for the requirements for
management of any fuel or oil spill.
Any oil or chemical spills must be contained and the resultant waste, including contaminated soil
disposed of in a manner consistent with the Environmental Protection requirements, Standards and
Work Instructions referred to above.
Power transformers will generally require oil containment systems, consisting of bund walls,
drainage & oil/water separation facilities to prevent transformer oil entering the environment in the
event of any small or large loss of oil from the transformer. Refer to Ergon Standards SS-1-9.2 Oil
Containment and SS-1-6.1 Civil Works for the requirements for oil containment systems.

Page 22 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


10.4 SF6 Gas Handling
Sulphur Hexafluoride (SF6) gas and its toxic, corrosive by-products produced in the event of an arc
due to an equipment fault, need to be handled carefully following strict procedures, to avoid or at
least minimise the potential for environmental damage or personnel contamination.
The gas and its by-products must be handled, tracked and reported in accordance with AS 2791
and Ergon Energy Work Instruction BS001404R140, using appropriate PPE, as specified in that
Instruction.
10.5 Erosion & Sediment Control
Reference document ES000904R121 sets out the Ergon Energy obligations and requirements in
relation to Soil Erosion and Sediment Control Document. Document ES000904R101 tabulates a
range of control measures available for field crews to mitigate potential environmental and cultural
heritage risks. Specific control measures/mitigation strategies required for the site will be set out in
the site Erosion and Sediment Control Plan (ESCP) and the Environmental Management Plan.
10.6 Cultural Heritage
In the event of discovery of items/areas of possible cultural heritage, work must be stopped
immediately and the procedure of ES000906R100 Cultural Heritage Discovery Process (Field
Instruction) followed to ensure that the cultural heritage value is protected from harm as far as
possible. Refer also to the other cultural heritage documents referred to in the Field Instruction.

Page 23 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


11.

CIVIL WORKS

11.1

General

This section is a reference guide on how to comply with the minimum standards required by Ergon
Energy for civil construction work inside or immediately adjacent to electrical substations. Civil
construction work may include but not be limited to new substations, upgrade of existing
substations and survey or geotechnical investigations.
This Section 11 must be read in conjunction with the other relevant sections of this document, the
Ergon Energy Standards, the Reference documents and the project documents.
11.2

Civil Construction Work

Civil construction work includes but is not limited to Demolition, Earthworks, Roadworks, Footings,
Buildings, Bunds, Oil/Water Separation, Hydraulics, Structures, Electrical Conduits, Cable Pits and
Ducts, Earth Grids and Tails, Fences and Switchyard Surfacing. Relocating HV or LV cables is
considered electrical construction work and shall be undertaken by suitably qualified personnel.
All civil construction work must comply with the following documents:
1. The project documents and the Work May Start drawings (Refer to Section 9.2 of this
Manual).
2. The Ergon Energy Standard SS-1-6.1 Civil Works sets out the majority of the
requirements for civil design and construction.
3. The Referenced Australian Standards and Codes
4. The Ergon Energy Safe Work Practices (SWP)
5. Queensland Workplace Health and Safety Code of Practices for Construction
6. All sections of this document.
Inspection requirements and acceptance criteria can be found in the project documents and the
Ergon Energy Standard SS-1-6.1 Civil Works.
Standard Work Practice SB0301: Civil Works details the requirements for performing civil works
inside a substation. This document must be read in full and strictly adhered to. Special attention
must be given to the requirements for the safety of workers on roofs and high areas, in excavations
and working in and around live electrical equipment.
All dimensions and levels must be verified on site prior to the commencement of construction work.
Dimensions must not be scaled from drawings.
11.2.1 Asbestos
Every Ergon Energy site has an Asbestos Register that must be reviewed before carrying out any
work on-site.
The following documents are a reference to guide Constructors on the requirements for managing
asbestos:
BS001409R113: Asbestos Management Plan
BS001409R120: Contractor Asbestos Related Work or Asbestos Removal Work Reference
Guide
ES000901R166: Manage Asbestos Quick Reference
SWMS009 Disturbance of Asbestos Underground
Page 24 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


11.2.2 Safe Work and Builders Area
The Safe Work Areas and the Builders Area (or Builder Storage Areas) are typically nominated on
the plan but must be verified with the Substation Construction Co-ordinator during the pre-start
meeting.
The Safe Work Areas must be demarcated by the appropriate barrier (i.e. fences, bunting, flags) as
defined in P53K05R03: Queensland Electricity Supply Industry Substation Barrier Chart and the
project documents. Civil works typically require steel mesh panels and green flags. Refer to the
Temporary Fence Drawing EESS-10174-01, SWP SB0301: Civil Works and Section 13.2 of this
manual for construction and earthing details. The Constructor must not hinder the operation of the
substation and site access must be made available to Ergon Energy Crews at all times to respond
to power outages or emergencies. In the Constructors absence, measures must be implemented
to inform the Ergon Energy Crews of potential hazards within the site.
Builders Areas are typically outside the substation and must be away from the site accesses and
where no harm can come to the public.
11.2.3 Exclusion Zones
The Ergon Energy Substation Construction Co-ordinator or the Electrical Constructor in control of
the site must identify exclusion zones, safe work areas and no go areas to the Civil Constructor as
part of the site induction. Refer also to Section 5 of this document.
11.2.4 Excavations
Extreme caution must be exercised when excavating inside or adjacent to substations to avoid
damage to or contact with existing underground services.
A Permit to Dig is required for all excavations >300mm. For excavations outside the substation, a
Dial before You Dig and a Permit to Dig is required. Refer to the following Ergon Energy
References:
SWMS015 Excavations
SWMS015F01 Permit to Dig - Form
SWMS015R01 Excavations Job Safety Analysis
SWP SB301 Civil Works
Drawings provided by the Designers for the Permit to Dig should indicate with reasonable accuracy
the locations of underground cables, conduits, drains, earth grid, etc., but cannot be guaranteed
100%. Therefore the responsibility still lies with the Constructor to check for the possibility of
unexpected underground services or cables, before commencing excavations.
11.2.5 Star Pickets
A check of existing conduits, cables or services must be carried out and approval must be sought
from the Ergon Substation Construction Coordinator before using star pickets on a brownfield site.
Once approved, the star pickets must be driven no further than 300mm deep and a marker or
obstruction must be placed on the star picket to prevent overdriving. Refer also to Section 5.9 in
the SWP SB0301 Civil Works document.
11.2.6 Earth Grid
The substation earth grid installation must meet the requirements of Sections 13.1 and 13.2 of this
Manual, Ergon standard SS-1-6.1 Civil Works, Standard Work Practice SB0301: Civil Works and
the project Specification. The electrical materials required for the earth grid will be identified in the
Bill of Materials prepared by the electrical designers and generally provided as free issue by Ergon
Page 25 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Energy. (except that backfill materials remain the responsibility of the Civil constructor, as indicated
in Section 8.3 of this Manual).
The Civil Constructor must advise the Design Manager or other appropriate Ergon contact person
in writing when the earthing materials will be required. Arrangements will then be made to provide
the materials for pickup by the Constructor, as per Section 8.4 of this Manual. Pickup location,
date of availability and any other specific detail required will be provided in the Specification.
11.2.7 Confined Spaces
Working in confined spaces must be avoided wherever possible. If this is not possible, the work
must comply with the Queensland WHS Confined Spaces Code of Practice, AS 2865 and the
documents below.
ES000901R151 Confined Space Management Plan
BS001409F101 Confined Space Entry Permit
SWMS016 Confined Space
11.2.8 Hot Works
Any hot works performed on-site (welding, grinding etc.) requires a permit and must comply with
the following documents:
BS001409R104 Hot Work Field Instruction
BS001409F104 Hot Work Permit
All hot works must be performed by a qualified and experienced boilermaker. Welding must only
be performed by experienced personnel who are certified in accordance with AS1796.
11.2.9 Scaffold Certificate
Where scaffolding is used on-site a Certificate of Compliance is required in accordance with
AS/NZS 4576 and the Queensland WHS Scaffolding Code of Practice.
11.3

Mobile Plant

Refer to SWMS014 Movement of Powered Mobile Plant for guidance of Ergon Energys
requirements for movement of mobile plant in substations.
11.4

Other References

Other references include


SWMS001-005 Work at Heights (>2m)
SWMS006 Working on or near Road or Railway
SWMS012 Temporary Support of Poles or Structures
SWP SB401 Installation of Photo Voltaic Systems
ES00900R102 Safety First Your Guide to Safe Work
ES00901R163 HSE Handbook

Page 26 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


12.

PRIMARY PLANT

12.1

General

Typically, primary plant consists of the high voltage equipment, associated structures and the cable
and busbar interconnections, that make up the high voltage installation of the switchyard, as
indicated in the following sections.
All items of primary plant must be located and installed with the orientations shown on the General
Arrangement and Section Drawings and must be erected strictly in accordance with the
appropriate manufacturers detailed Installation Manual.
Generally, primary plant must not be installed until all erection of poles, towers, termination
structures and overhead works (landing spans, strung busbars, overhead earthwires) have been
completed, unless absolutely necessary and agreed by the Ergon Project Manager or Design
Manager.
All HV plant will be purchased by Ergon Energy under period contracts and received into the
Logistics system. Refer to Section 8.4 in relation to requisitioning items out of the Logistics
system. Except for power transformers (refer section 12.2), all requisitioned items must be
collected from the appropriate Ergon Energy storage depot as advised and transported to site, by
the Constructor.
As soon as possible following arrival of plant at site, the Constructor must open all crates
sufficiently to enable inspection and checking that all required components have been received
and are in good condition. Any equipment damage or deficiencies must be reported promptly in
writing to the Project Manager and/or Design Manager for follow up. This action will help to
minimise potential construction delays in the event that the equipment manufacturer needs to be
contacted for supply of missing components or rectification of damage.
The Constructor must provide all galvanised bolts, nuts, washers, etc. required for mounting the
equipment to the support structures, unless supplied by the Manufacturer. Bolts and nuts, etc.
must be ISO metric of the appropriate size in accordance with AS1111 and AS1112 and
galvanised in accordance with AS1214.
12.2

Power Transformers

Supply, delivery to site, installation and testing of any power transformers required for the
substation is generally the subject of a separate contract between Ergon Energy and the
Transformer Supplier (excluding station service transformers).
A Representative from the Transformer Supplier will conduct a pre-delivery site visit to review the
site access and discuss with the Constructor any requirements or co-ordination necessary before
and during transformer delivery.
Prior to delivery of a power transformer, the following site works must be completed:
The base course of the substation driveway must be completed. This does not require the
concrete edging, kerb and channelling, or bitumen to be completed, but a solid compacted road
base which allows transformer delivery to proceed safely, independent of weather conditions.
The transformer footing and bund wall must be complete and have had sufficient time to cure,
so as to achieve a significant percentage of the design strength. (Typically 28 days If a
shorter lead time is absolutely necessary due to unavoidable project constraints, this must be
negotiated with the project team, including civil and electrical SMEs). Painting of the slab and
bund can be done at any suitable time after curing of the concrete is complete as above, either
before or after delivery of the transformer, dependent on the urgency of transformer delivery.
(Allow two to three days to complete painting).
Page 27 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Ensure all of the conditions as agreed at the pre-delivery site meeting are in place.
Installation and test of the 415V, 63A AC supply for use by the Transformer Installation Crew.
The Transformer Supplier will not deliver the power transformers if the conditions are not met. To
avoid the possibility of delays and disruption due to the site not being ready when required, the
Constructor and Project Manager (or Design Manager) must liaise regarding the site preparedness
and the transformer delivery schedule.
During assembly and testing of the transformers, the following conditions must be observed:
Earthworks or any dust producing activity must not be carried out in the vicinity of the
transformer assembly area at this time, so as to avoid dust entering the transformers or oil via
open pipework connections, access covers, etc.
Clear access to the transformer assembly area must be maintained to enable the transformer
installation crew to complete the work safely and efficiently. Generally there will be some crane
work and oil filling and whilst this work is being undertaken it is generally unsafe for other
activities to be happening in the area.
During testing no other work can take place on or around the transformer.
Following completion of transformer installation and testing and subsequent hand-over of the
transformer by the Manufacturers Installation Crew, external HV, LV and multi-core cable
connections can be installed on the transformer, in accordance with the relevant Design Drawings.
12.3

HV Circuit Breakers (Outdoor)

HV circuit breakers must be erected on their support stands and assembled, in accordance with
the Manufacturers Installation Manual.
Some specialised aspects of the assembly (e.g. gas pipe connections, re-gassing from transport
pressure to full operating pressure) and testing may be required to be completed by the Circuit
Breaker Supplier, or other person Trained and Authorised by the Supplier. This requirement
depends on the Manufacturer of the circuit breaker and may change from time to time, therefore
should be checked for each project.
Responsibility for sourcing appropriately qualified personnel for all aspects of the circuit breaker
installation lies with the Substation Constructor, unless specified otherwise in the project
documentation.
12.4

Current Transformers, Including CT Marshalling Box

Current transformers are generally fully assembled and filled with insulating oil ready to be erected
on their support structures. CTs must be stored on-site and handled strictly in accordance with the
Manufacturers Instruction Manual.
CT marshalling boxes must be fabricated and fitted out in accordance with the latest versions of
the standard CT marshalling box drawings EESS-10224-01 to 06. Wiring and cable termination
details will be indicated on the Project Specific Substation Drawings.
A second set of CT rating plates is provided by the CT Manufacturer. These are to be fixed to the
side of the CT marshalling box with stainless steel fasteners in the positions indicated on the
standard marshalling box drawing EESS-10224-02, with the plates arranged in phase order A-B-C
from top to bottom.
Spare CT secondary cores must be earthed at the marshalling box, as should be indicated on the
Project Design Drawings.
Cable screens and other earth connections must be bonded to the earthing bar internal to the
marshalling box.
Page 28 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Cables must be fitted with approved glands at the entry point through the gland plate in the bottom
of the marshalling box. Refer also to Section 14.5.
12.5

Voltage Transformers, Including VT Marshalling Box

Voltage transformers are generally fully assembled and filled with insulating oil ready to be erected
on their support structures. VTs must be stored on-site and handled strictly in accordance with the
Manufacturers Instruction Manual.
VT marshalling boxes must be fabricated and fitted out in accordance with the latest versions of
the standard VT marshalling box drawings EESS-10225-01 to 06. Wiring and cable termination
details will be indicated on the Project Specific Substation Drawings.
A second set of VT rating plates is provided by the VT Manufacturer. These are to be fixed to the
side of the VT marshalling box with stainless steel fasteners in the positions indicated on the
standard marshalling box drawing EESS-10225-02, with the plates arranged in phase order A-B-C
from top to bottom.
Cable screens and other earth connections must be bonded to the earthing bar internal to the
marshalling box.
Cables must be fitted with approved glands at the entry point through the gland plate in the bottom
of the marshalling box. Refer also to Section 14.5.
12.6

Disconnectors and Earthing Switches

Disconnectors and earthing switches must be erected strictly in accordance with the erection
instructions in the Manufacturers Instruction Manual.
Care must be taken to ensure that all disconnectors and earthing switches are erected with the
correct orientation, as indicated on the Switchyard General Arrangement and Section Drawings
issued for the Project. i.e. The earthing switches must be at the correct end of their associated
disconnectors and the operating mechanisms must be on the correct side of their structures, as
indicated on the design drawings. Generally, the objective will be to facilitate easy viewing of
operating number plates and handles by an Operator walking from the control building towards the
switchyard.
12.7

Surge Diverters and Station Post Insulators

Surge diverters and station post insulators must be erected strictly in accordance with the
Manufacturers Instruction Manual.
In the event that surge diverters or station post insulators are supplied in more than one section,
these sections must be joined together to form one unit before being erected onto the support
structure.
12.8

Load Control Plant

The load control plant must be assembled and installed as indicated in the Load Control Drawings,
plus the Manufacturers Assembly Instruction Manual.
Erection and installation includes (but is not necessarily limited to) the following activities:
Erection of suitably designed structures and surrounding safety enclosure for the outdoor
coupling cell.
Connection of high voltage conductors to the coupling cell
Installation of the internal cubicles housing the ripple control transmitter, controller, etc.
Cabling and connections between the external coupling cell and the internal transmitter and
controller
Page 29 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Auxiliary supply connections
Control cabling and connections to the SCADA RTU panel.
The Load Control Plant Supplier will perform on-site testing and pre-commissioning of the plant.
The Construction Workgroup must assist with this work, particularly rectifying any installation
defects to the satisfaction of the Load Control Plant Supplier.
12.9

Capacitor Banks

Capacitor banks (either cubicle enclosed or outdoor type) must be installed and erected in
accordance with the Project Design Drawings and the Manufacturers Instruction Manual, as
required.
Erection of support structures and an enclosure fence may be required for outdoor type capacitor
banks.
HV connections, auxiliary supply and control cable connections must be made in accordance with
the relevant Project Design Drawings.
12.10 HV Switchboards
Switchboards may be supplied pre-installed by SPS in a transportable building, or packaged as
individual panels as supplied by the Switchgear Supplier, to be installed in a building on site. In
some cases, installation may be carried out by the Switchboard Supplier, under the supply
contract.
In the case of switchboards requiring on-site installation, the panels must be requisitioned and
collected from the appropriate Ergon Energy storage depot and transported to site, as for most
other items of HV plant.
Before installation of a switchboard in a building on-site, the following requirements must be met:
The switchroom floor must be prepared to the Switchboard Manufacturers Specification. The
preferred method and finish are supplied with the switchboard drawings and data.
The substation building and vehicle access must be sufficiently completed and clear to enable
the installation to proceed unhindered.
The switchroom must be sealed, air-conditioners or other ventilation systems operational (as
installed), and a power supply suitable to run the individual switchboard panel heaters must be
available.
These requirements are to provide a dust free and secure environment to ensure the longevity of
the equipment. This is a hold and inspection point. Installation must not proceed if the conditions
are not met.
Installation of the switchboard must be carried out in accordance with the Manufacturers
Installation Manual.
12.11 HV Cables
12.11.1 General
Installation and termination of HV and LV cables must be carried out in accordance with SS-1-4.4
Cables and Cabling.
The Constructor must supply all tools and equipment, plus minor materials required for the
installation, termination and testing of the HV power cables. All supplied items must be entirely
satisfactory for the service conditions and intended operational requirements, whether such
conditions or operational requirements are directly specified or not.
Cable-laying must also meet the following requirements:
Page 30 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Conduits must be spaced to ensure required current ratings are met (in accordance with the
Cable Rating Design Report).
Cables to be installed so as to exclude cable wastage and cable damage.
The finished cable routes must not undermine foundations of substation equipment or encroach
on any other substation works.
HV power cables must be supported and clamped as the cables rise into the Control Building or
onto the transformer. Cable clamps must not cause circulating current problems (e.g.
separation of the cable clamp from a steel bracket by a non-metallic spacer or similar; use of
non-magnetic cable clamps).
Cable glands must be nickel plated brass. Refer also to SS-1-4.4 Cables and Cabling.
The HV power cable drum must be placed at an appropriate location to ensure that the cable
can be pulled / installed efficiently. Generally the cable drum can be placed at the transformer
and the cable can then be pulled from somewhere in the vicinity of the Control Building.
Refer also to Section 10.2 of SS-1-6.1 Civil Works for further information on laying of conduits.
12.11.2 Thermal Backfill
If thermal backfill is required to reach the specified Soil Thermal Resistivity in the cable trench, the
material data must be forwarded to the Ergon Design Manager, for checking and confirmation by
the Network Rating and Utilisation Officer, before backfilling commences. The material data must
include the following:
Current thermal dry out curve to determine the moisture content
Compaction Test Results from a Geotechnical Soils Laboratory to determine compaction
ranges, compaction methods including layer thickness, minimum moisture level, and number of
passes for the chosen compaction method.
Demonstration of compliance with the project specific requirements.
Refer also to the Ergon Energy Cable Trench Installation Specification. Backfilling of the trench
must be in accordance with the Geotechnical Soils Laboratory recommendations and the
requirements in the Ergon Energy Standard SS-1-6.1 Civil Works.
12.11.3 Cable Marking and Identification
All cables from the power transformers must be permanently marked according to phase with
appropriately coloured heat shrink PVC sleeving at four locations:
(i)

Inside the transformer cable boxes.

(ii) Immediately outside the transformer cable boxes (single core cables).
(iii) Inside the indoor switchgear or the outdoor Ring Main Units.
(iv) Immediately outside the indoor switchgear or outdoor Ring Main Units (single core cables).
In addition, all HV cables from the power transformers must be permanently labelled T1 or T2 etc.
at location (ii) and feeder name/number at location (iv).
For auxiliary transformer cables, the marking and labelling must be at locations (iii), (iv) and at or
immediately beneath the cable outdoor terminations, permanently labelled Aux Transformer 1 or 2.
12.11.4 Cable Terminations
Cable terminations must be done in accordance with the relevant manufacturers instructions and
Ergon standard SS-1-4.4 Cables and Cabling.
Page 31 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


High voltage cable connection lugs must comply with AS 62271.301-2005 Dimensional
Standardisation and Terminals. The connections must be either two hole or four hole as
appropriate. A single hole connection must not be used.
HV cable screens must be earthed at one or more ends, in accordance with SS-1-4.4 Cables and
Cabling and any project specific requirements of the design drawings and/or specification. The
stranded copper screen must be brought out under the heat shrink termination, the strands twisted
together and inserted into an appropriately sized crimp lug with ring termination. The size of the
crimp lug must be consistent with the total screen conductor area. The screen tail must be of
appropriate length to allow connection to the earth point without the need for any additional linkage
and routed so that phase to earthed metal clearances are not compromised. Refer also to Section
13.5.
Indoor switchboards and circuit breakers are subject to partial discharge testing prior to
commissioning and must be free of any external cable connections during testing. Therefore the
timing of cable termination works and testing needs to be co-ordinated between the Construction
and Testing groups. In some cases, the cables may be terminated and connected to the
switchboard, then unbolted from the switchboard terminals later for testing purposes.
12.12 Busbars and Conductors
12.12.1 Overhead Conductors
Landing spans, strung busbars and overhead earth wires must be installed in accordance with the
Substation General Arrangement and Section Drawings, plus the relevant Standard Assembly
Drawing(s). The conductors must be strung to the correct sags and/or tensions as specified on the
appropriate drawing.
Conductor drums must be stored on level ground with the axis horizontal and must not be dropped
off vehicles or distorted in any way which might lead to difficulty in running off the conductor. The
protecting battens must remain in place on the drums as long as possible to prevent damage to the
outer layers of conductors.
After being run off the drum, the conductor must be supported above the ground on rollers or
similar, until erected. The conductor must not be driven over or walked on by pedestrians. Every
precaution must be taken to ensure that the conductors when erected are left without any
scratches, cuts, protruding strands, bird caging, rough welds, deposits of grease or dirt,
deformation or adhesions.
Only conductor which is free of imperfections must be used for compression terminations. All
grease and foreign matter must be wiped away and any light scratches must be removed by
rubbing down with fine emery cloth. Steel wool must not be used.
EPV Operators must have successfully completed the appropriate training and assessment and
properly secured harnesses must be worn at all times while working in the EPV.
12.12.2 Rigid Busbars
Rigid aluminium tubular busbars must be fabricated in accordance with the relevant Fabrication
Drawings and erected as indicated on the Substation General Arrangement and Section Drawings.
Busbar supports must be expansion, sliding or fixed type, and busbar joints must be either butt or
expansion type, as indicated on the Substation General Arrangement and Section Drawings and
the relevant Assembly Drawings.
All welding of aluminium must be carried out by a skilled Welder using the Metal Inert Gas (MIG)
process. The weld filler alloy to be used on all B6101 aluminium alloy must be aluminium alloy
B4043.
Individual weld runs must be completed as quickly as possible and time for cooling must be
allowed between successive runs to limit distortion and loss of strength in the weld zone. When
Page 32 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


welding terminal palms, earth loops, etc. to tubular busbars, the cross-sectional area of the welds
must be at least equal to the cross-sectional area of the palm, loop, etc. or the busbar, whichever
is less.
Vibration damping conductors must be laid loosely along the whole length inside the busbar tube
and tack welded at one end to prevent migration along the bus.
12.12.3 Droppers and Flexible Connections
Droppers and flexible conductor connections between HV plant must be installed as indicated on
the Substation General Arrangement and Section Drawings and the relevant Assembly Drawings.
All conductor ends must be cleaned with a wire brush, imperfections smoothed with fine emery
cloth and coated with Penetrox A or equivalent jointing compound before insertion into the
compression or bolted connectors.
Compression must be continued until the two halves of the compression die meet solidly. Multiple,
overlapping compressions must be carried out over the whole of the available compression length.
Where compression connector detail drawings specify a dimension across the flats after
compression, the compression must be continued until this dimension is achieved.
Where it is necessary to bolt an aluminium terminal lug onto a copper equipment terminal palm (or
vice versa), the copper palm must be tinned and positioned underneath the aluminium. This is to
minimise the risk of any corrosive copper salts being washed onto the aluminium by moisture.
Bolted electrical joints must be made using stainless steel bolts, nuts and washers. For aluminium
to aluminium connections, a load spread washer must be placed on each side of the connection,
with the addition of a spring washer between the nut and the load spread washer on that side. For
tinned copper connections, the load spread washer can be replaced by a standard flat washer. An
anti-seize compound such as Locktite 767 or equivalent must be added to each nut and bolt prior
to assembly.
All bolted connections must be made in accordance with Australian Standard AS 62271.301: High
Voltage Switchgear and Controlgear Dimensional Standardisation of Terminals. The torque
applied to each bolted connection must be in accordance with the relevant table in the Standard.
12.13 Clearances
Ergon Energy Substation SS-1-3.1 Clearances in Air sets out all Safety and Electrical Clearances
that must be observed through both Design and Construction Practices.
Table 1 of the above Standard, sets out the minimum phase to earth and phase to phase
clearances that must be observed for all parts that will become energised at some time. Flexible
conductor connections between HV plant, droppers, and HV cable terminations and lugs must be
installed so as to avoid compromise of those clearances through bending, sagging or swaying of
conductors, or protrusion of cable termination lug bolts towards each other, etc. Generally, it is
desirable to arrange HV flexible conductors to curve upwards between two items of plant, using the
natural curve of the conductors, if possible.
The arrangement of overhead strung bus, droppers and flexible connections must also ensure that
the appropriate section clearances (also in Table 1) are achieved.
In 3 phase HV cable termination boxes, the cable lugs and bolts should preferably be installed with
all the lugs on the same side of the equipment terminal palm for each phase and the bolts facing in
the same direction, with the toes of the bolts pointing into the larger clearance gap. This is not
always possible (e.g. in switchgear panels, etc.), so may have to be modified on site for particular
cases, but the principle is always to arrange so as to obtain the largest possible phase to earth and
phase to phase clearances in all parts of the cable termination box (subject to achieving the
minimum values in Table 1 of SS-1-3.1 Clearances in Air).

Page 33 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


In exposed outdoor situations, at the lower voltages, consideration needs to be made of the
possibility of infringement of the minimum clearances by birds, reptiles, or climbing animals.
Insulation of exposed live terminals, etc. may need to be provided to prevent contact by vermin,
whether specified in the design or not.
12.14 Lightning
Lightning protection, consisting of an integrated combination of lightning masts and overhead
earthwires above the incoming feeder landing spans must be installed in accordance with the
Substation General Arrangement and Section Drawings, plus the relevant Standard Assembly
Drawing(s) and Substation Standard SS-1-8.2 Substation Lightning Protection.
In the event of any lighting fixtures, or other LV auxiliary circuits needing to be installed on lightning
towers, care needs to be taken to achieve sufficient clearance and insulation between the lightning
current circuit and the LV circuit to prevent lightning current causing any back flash-over in the LV
system of the substation.

Page 34 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


13.

EARTHING

The substation earthing system must be constructed and commissioned strictly in accordance with
Ergon Energy Standards SS-1-7.1 Substation Earthing and SS-1-7.2 Safety Earthing and the
relevant Australian Standards and Guidelines: Refer to:
IEEE 80-2000 Guide for Safety in AC Substation Grounding
ENA EG1-2006 Substation Earthing Guide
AS 2067 Switchgear Assemblies and ancillary equipment for alternative voltages above 1kV.
Queensland Electrical Safety Act 2002 Code of Practice: Works
The work shall be carried out by an Electrical Fitter Mechanic possessing a current Queensland
Electrical Workers and Contractors Board Certificate of Competency.
13.1

Main Earth Grid

Earth grid conductor crimp connections, including lugs must be well compressed such that all
conductor strands make solid contact with other conductors and the outer strands are solidly
compressed into the inner surface of the surrounding crimp connector. Gaps between conductors
must be minimal.
Quality of crimp connections is dependent on factors such as crimp type, compression pressure,
calibration and serviceability of compression tool and dies, care and skill of the operator. Prior to
commencement of the earth grid connections, the Ergon Design Manager (or Representative) may
require to inspect a random sample of three (3) to five (5) completed earth grid joints of each type
and may request to view a small number of further samples on a random basis during the course
of the work, to ensure consistency is maintained. These samples must be cut through by hacksaw
to expose the cross-section of the joint, for the approval of the Design Manager (or
Representative). Refer to the specification on a particular project for project specific requirements.
Back-filling of the earth grid conductor excavations must not be carried out until the Ergon Energy
Design Manager (or Representative) has been notified and had time for Final Inspection of the laid
earth grid conductor and jointing. Refer to reference documents SB0301 & SWMS015 for
requirements in relation to excavating for the earth grid and to the SS-1-6.1 Civil Works for details
of back-filling requirements.
All earth grid connections must be ductored as part of the Construction Testing, as described in
Section 16 below.
Other earth grid testing, including measurement of the resistance of the buried earth grid system to
the general mass of the earth, Step and Touch Potentials, Earth Potential Rise (EPR), etc. will be
carried out as part of Commissioning, by the Specialist Test Workgroup, as per the Test and
Commissioning Manual.
To prevent the transfer of dangerous voltages outside the substation, all conducting services
leaving the earth grid area (metallic pipes, fences, control, protection and communication cables,
etc.) must be isolated as specified in SS-1-7.1: Substation Earthing.
13.2

Extending Fences and Earth Grids in Energised Substations

When erecting a fence inside or near the outside of an energised substation, the construction
procedures must ensure that no connection is made between the substation earth grid and any
remote earth. There must also be no possibility of any Personnel (Staff or Public) being able to
contact both the substation earth potential and remote earth potential at the same time, as the
substation earth grid potential may be considerably different from that of remote earth.
Refer to Standard Work Practice SB0301: Civil Works for procedures to be followed when
constructing fences or working on the earth grid in and near a HV substation. Supply of insulation
Page 35 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


mats, gloves, temporary jumper leads, and other safety equipment required is the responsibility of
the relevant Constructor.
When constructing a new section of earth grid in an area adjacent to the existing earth grid of the
substation, due consideration must be given to the risks associated with transferred potentials in
the event of an earth fault occurring during installation of the new earth grid. Following are the
minimum requirements:
(a) A Work Method Statement must be prepared indicating how the risks will be minimised.
(b) Prior to commencement of installation of conductors, a 3 metre isolation zone must be
cordoned off with tape, measured from the existing metal fence or other defined boundary
between the existing earth grid and the new work area.
(c) Installation and connection of the new section of earth grid must be carried out in two stages,
as described in (d) and (e) below.
(d) The new earth grid conductors must be installed, commencing at the boundary of the work
area furthest from the existing grid and working back towards that existing grid, until the
boundary of the isolation zone is reached. No conductive material is permitted to breach the
Isolation Zone, including earthing conductors, fencing materials, construction AC supply
cabling (unless electrical isolation provided), etc. No special safety requirements such as
insulating gloves and mats are required at this stage, provided the Isolation Zone is not
breached.
(e) Following completion of the work in (d) above, including making of connections, backfilling and
compacting, the task of connecting the conductors across the Isolation Zone to the existing
grid can be commenced, subject to the following safety requirements:
The principle of working towards the existing grid must be adhered to as much as possible.
Whenever conductors are handled, 00 insulated gloves must be worn.
When connections are made to the existing earth grid, insulating mats must be used also.
Temporary jumper leads must be applied between the existing and new earth grid
conductors, before the final connection is made.
A new fence must not be extended across the Isolation Zone until the earth grid is
completely finished.
13.3

Support Structures, Equipment, Cable Trench Covers

All support structures, equipment earth points, marshalling boxes and cable trench covers, etc.
must be connected to the main earth grid, in accordance with Ergon Energy Substation Standard
Earthing Drawings (EESS-10031-01 to EESS-10031-55). These drawings are readily available in
the Substation Design module on the Design and Constructors page on the internet.
(http://www.ergon.com.au/contractors,-suppliers--and--developers/design-and-constructioncontractors)
The earthing tails from the earth grid must be fitted neatly into the provided slots in the foundation,
shaped to the structure earth connection point, cut to length and fitted with the appropriate
compression terminal lug.
Bare copper strap and lugs must be tinned over the whole connection area where earth
connections are made to equipment and structures.
The Constructor must supply all compression tools and dies, plus minor materials such as hot dip
galvanised bolts, nuts, etc. required for jointing and fastening the earthing conductors to structures
and equipment. All fasteners must be both non-corroding and non-corrosive.

Page 36 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Portable earthing device attachment saddles must be fabricated in accordance with Drawing
EESS-10031-53, then fitted at each point indicated by an asterisk on the relevant Substation
Elevation Drawings and indicated generally in the Standard Earthing Drawings EESS-10031-01 to
55.
Cable trench covers must be earthed in accordance with Drawings EESS-100301-24 and 55, if
made of conductive material.
All bolted earth connections must use a minimum of two bolts, unless indicated otherwise in the
Standard Drawings.
Electrical plugs/sockets, etc. installed in the switchyard should have the earth pin connected to the
substation earth grid as near as practicable to the outlet.
13.4

Panels and Building Equipment

Project Drawings should indicate the main earthing requirements for the building equipment, but
may miss some of the detail, due to the complexity that arises from the number of connections
required. Hence, some guidelines are provided for the assistance of the Construction Workgroup.
All control and protection panels, switchboards, battery chargers, cable trays and ladders and
sundry metalwork in the Control Building must be connected to the main earth grid.
Each separate HV Switchboard or GIS must have at least two earthing tails connected directly
back to the main earth grid in the ground, one at each end of the switchboard or GIS. In a Control
Building Room containing a single row of control/protection panels, exactly the same arrangement
must be applied to the row of panels. Where there are two or more sets of panels, including some
possibly along the walls (AC and DC supply panels, etc.), the earth bars of the different sets of
panels must be bonded together via the earth bar in the overhead cable tray and again two
connections made directly back to the grid, one from either end of the cable tray earth bar.
Cable tray and other sundry metalwork may be earthed via tails off any of the main earth
connections indicated above.
Each individual switchboard panel or control/protection panel must be connected to the main earth
bar run in the cable tray above. The earth bars at the top and bottom of each panel must also be
connected together with an insulated green/yellow earthing conductor of equivalent cross-sectional
area to the earth bars themselves.
Bare copper strap and lugs must be tinned over the whole connection area where earth
connections are made to panels, switchboards, battery chargers, cable trays, etc.
Earthing of the Control Building itself walls, roof, etc. must be separate from the internal
substation equipment earthing and have its own direct connections to the main earth grid, so that
the equipment earthing is not dependent on the building earthing or vice versa.
13.5

Cable Screens

Cable screens are to be earthed at either one or both ends, dependent on the function of the cable,
as specified in Ergon Energy Substation Standards SS-1-4.4 Cables and Cabling and SS-1-7.1
Substation Earthing.
The Constructor must prepare the cable and provide all necessary materials required for effective
connection of the screen, including the required length of earthwire.
The cable screen must be bonded to an earth strap where available, otherwise to the appropriate
earthing terminal of the panel, marshalling box, etc.
For both HV and multicore cables, the cable termination/screen earthing arrangement must provide
sufficient clearance in air from the live parts to ensure that the rated impulse withstand and power
frequency withstand levels are not compromised.
Page 37 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Stranded copper screens (generally on HV cables) must be earthed in accordance with Section
12.11.4. Brass tape screens on multicore cables must be earthed to a suitable earth bar via a
stranded copper conductor earth tail, of minimum cross section of 2.5mm2, with standard greenyellow insulation.

Page 38 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


14.

SECONDARY SYSTEMS

14.1

Protection and Control Panels

Protection and Control Panels are supplied as single panel cubicles which must be installed in the
locations indicated on the relevant Building Layout Drawings, bolted together using the joining
brackets provided at the top of each panel and dyna-bolted securely to the floor. Four dyna-bolts
(minimum 12mm diameter) plus square washers (approx. 25mm) are required per panel.
Panels must be lifted only by the eye bolts provided at the top of each panel.
Earthing of panels is covered in Section 13.4.
Lift-off rear panel doors must be removed and placed out of the way during internal fit-out and
wiring of the panels to provide safe passage and exit for Personnel in the event of an emergency.
Relays and other panel equipment must be mounted in the panels and wired in accordance with
the approved design drawings, which should be based on the latest versions of the relevant Relay
Application Guides and ZSS template drawings. Wiring construction work must meet the detailed
requirements and standards in MN000301R166: Construction and Wiring Guidelines for Ergon
Energy Substation Panels.
Where a modular building is specified, the substation control/protection panels and other building
equipment, including MV switchboards and overhead cable tray, etc. will be constructed and
installed off site as part of the building construction, whereas for a brick/block building, installation
of panels and equipment will need to be done on site, following sufficient completion of the building
construction (subject to agreement with the building constructor).
14.2

Remote Terminal Units and Local Control Facility

The SCADA Remote Terminal Unit (RTU) racks must be installed in the panel locations indicated
on the relevant Design Drawings for the Project.
The Local Control Facility (LCF) (also referred to as a HMI Human Machine Interface) must be
installed either on the desktop or in the allocated panel, as indicated on the Drawings, dependent
on which type of LCF is provided. A touch screen LCF will be installed in an allocated panel.
Any spare cards in an RTU rack must be fully wired out to terminals, as indicated on the Design
Drawings for the RTU, so as to be readily available in the future if needed.
Loading of RTU configuration files into RTUs and functional testing will be carried out by the
appropriate Secondary Systems Group and programming of the LCF will be carried out by Ergon
Energy SCADA Group.
14.3

Communications

Communications and signalling requirements are generally designed, supplied and installed by
Ergon Communications work groups, but some associated work is generally the responsibility of
the substation constructor. Specifically,

Installation of completed communications equipment cubicles, including the 48V DC supply


panel (where required), supplied by Communications work group.

Provision of AC & DC power supplies from the appropriate Distribution panels to the
Communications panels.

Installation of fibre optic cable ducts and termination enclosures as per Drawings 899364-01
and 899364-02, as required.

Page 39 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual

Installation of a concrete communications antenna pole based on the standard


Communications pole drawings supplied by the Communications designers. Orientation is to
be in accordance with the site specific layout drawing.

Supply and installation of public telephone services and telephone isolation equipment, if
required by the design. (In most new substations, the telephone service will now be provided
by the Ergon Communications workgroup, via the communications panels).

The DC power supply cabling from the substation 110V DC Distribution Panel, or from the 48V DC
Supply Panel as required, must be installed in accordance with the design drawings, Ergon
Substation Standards SS-1-5.1 DC Supplies and SS-1-4.4 Cables and Cabling and STMP004
Standard for Communications Equipment Installation.
The location and type of the outdoor conduits, pits, termination enclosures and splice enclosures
will depend on the incoming optical fibre cable type and location of the terminating structure.
Where more than one fibre optic cable enters the substation, the conduits for each cable must
follow diverse paths into the substation control building and not use common pits or ducts or
termination enclosures. The internal OFS 800 termination enclosure must be mounted on the wall
of the equipment room as close as practicable to the communications equipment cubicles and in
accordance with AS/ACIF S009:2001 Installation Requirements for Customer Cabling (Wiring
Rules). The final position of conduits, cable pits, termination enclosures, etc. must be determined
in conjunction with the Communications workgroup.
The required orientation of the communications antenna and of any future microwave dish to be
mounted on the concrete pole must be double-checked before installation of the pole. - Orientation
is to be in accordance with the site specific layout drawing, as is the antenna mounting
arrangements.
If a direct connection to the public telephone network is required, a 10 Pair lead-in cable must be
installed from the public telephone network to the substation. This includes telecommunications
conduits from the property boundary to the substation control building, and, in consultation with the
Carriers contractor, from the property boundary to the public network connection point. All
materials used must be in accordance with AS/ACIF S008:2010 Requirements for Customer
Cabling Products. All telecommunications equipment must be installed in accordance with
AS/ACIF S009:2006 Installation Requirements for Customer Cabling (Wiring Rules).
Where required, a telephone Line Isolation Unit (LIU) must be installed in the substation building to
isolate the public telephone network from the telephone equipment installed in the substation.
The telephone line isolation unit must be equipped with sufficient high voltage isolation links to
allow for termination and isolation of the 10 pair lead-in cable, as well as sufficient optical isolation
modules to isolate two PSTN telephone lines, with capability of expansion to four telephone lines
by the addition of isolation modules.
The exchange side of the isolation unit must be powered from the Carriers network. The
subscriber side of the isolation unit must be powered from the substation DC supply.
During any work on the network side of the LIU, any accessible exposed earthed metal within two
metres of the LIU must be covered with insulating rubber mats of appropriate rating (10kV), to
prevent any inadvertent personnel contact with the earthed metal. This is to protect personnel
against potentially dangerous touch potentials between the substation earth grid and the external
public telephone network.
Telecommunications conduits and cables within the substation must be unbroken between the
property boundary and the telephone line isolation unit. The use of PSTN telecommunications pits
within the substation boundary is not permitted.

Page 40 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


14.4

Metering

All metering must be installed in accordance with Substation Standard SS-2-4.1 Metering, the
Queensland Electricity Connection and Metering Manual NA000403R328 (QECMM) and the
relevant Design Drawings.
Revenue metering circuits must be sealable at the locations as indicated in SS-2-4.1 Metering and
the EESS-100316 Series of Drawings.
Metering VT and CT loads must be balanced on all three phases as far as possible. For any 3
phase installation, the least loaded metering winding must carry not less than 80% of the load
experienced by the most heavily loaded metering winding. Transducers and meters must be
connected to the preferred phases as indicated in the Manufacturers' Installation Guides. In the
event of contradiction with the Project Design Drawings, the Designers must be consulted for
clarification.
14.5
14.5.1

LV Cabling, Secondary Wiring and Terminals


General

This Section describes the general requirements for all LV cables, secondary wiring and terminals
for all AC and DC circuits, CT and VT secondary circuits, control, alarm and protection circuits.
All secondary wiring must comply with the following common requirements, in addition to the
specific requirements of other relevant Sections of this Manual:

0.6/1kV PVC/PVC insulated conductor conforming to AS/NZS 5000.1

Stranded Conductors

All Control and Protection Panel wiring must be grey.

14.5.2

Installation

All LV cables and wiring must be installed and terminated in accordance with Ergon substation
standard SS-1-4.4 Cables and Cabling and quality document MN000301R166 Construction
and Wiring Guidelines for Ergon Energy Substation Panels.

In order to minimise induced voltages, cable runs must, wherever possible, be at right angles
to the busbars. Where parallel runs are unavoidable, the multicore cables must be separated
from the busbars by as large a distance as practicable.

Within the Control Building, so far as is possible, cables which extend outside the Control
Building must be physically separated from internal cabling and particularly from those cables
containing low level signals.

Where cables enter the building adequate vermin proofing must be installed.

AC and DC circuits must be run in separate cables.

Where X and Y protections are used, the X and Y secondary circuits must also be run in
separate cables.

Cables exiting the Control Building must be laid neatly in concrete trenches, then, exit the
trenches at appropriate points in electrical grade PVC conduits to reach the switchyard
equipment, as indicated on the appropriate Cable Route Diagrams and other Associated
Drawings. Control cables must not be direct buried and must not be run in the same ducts or
conduits as HV cables. Cable segregation distances between LV AC power cables, control
cables and instrumentation cables must be maintained in accordance with Sections 6.3 and
6.4 of SS-1-4.4 Cables and Cabling.

Due care must be taken to avoid damage to cables during laying. Large heavy cables may
need to be supported on rollers when running across other cables, but winches should not be
Page 41 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


used, unless absolutely necessary. Cables must be laid parallel with one another as far as
possible, not bunched or crossed, so that each cable may be identified throughout its entire
length.

Where cables exit from conduits, or enter equipment cubicles for termination, they must be
adequately protected against mechanical damage and adequately supported by clamps
attached either to the panel or the structure. Cables not enclosed within ducts or conduits
must be clamped at intervals not exceeding 300mm (approximately).

Upon installation of cables, both ends must be suitably sealed to prevent ingress of moisture,
dirt, or vermin (until glanded and terminated).

Any exposed outdoor wiring between terminal boxes and cubicles must be wired with
PVC/PVC multicore cables protected from ultraviolet light by painting with single pack epoxy
paint.

Each cable must be fitted with a permanent non-corroding cable marking tag at each end just
before the cable gland, stamped with the unique cable number, as per the Cable Schedule
and appropriate Connection Diagram.

For long cable runs, additional markers must be provided at 30m intervals along the length of
the cable.

Cable screens of multicore cables must be connected to the substation earth grid at both ends
of the cable. Refer also to Section 13.5 of this manual and Section 6.3.3 of SS-1-4.4 Cables
and Cabling.

14.5.3

Cable Cores and Terminations

All Switchyard cable glands must be chrome or brass PVC glands are not acceptable.

Cable cores must be labelled strictly in accordance with the numbering specified on the
relevant Connection Diagrams.

Wire number ferrules must be interlocking, non-rotating type, fitted firmly over the insulation at
both ends of each conductor, as close as possible to the terminals and indelibly marked with
non-deteriorating black lettering on a white background. Clip-on type ferrules are not
acceptable.

Earthing of equipment generally requires that each item be individually connected to the earth
bar. Should looping of earth wires be unavoidable, it must be arranged such that
disconnection of any item of equipment from its earth connection during test or maintenance
will not interrupt the earthing connections to other plant remaining in service.

Terminals in 415V and 240V AC circuits must be protected by inherent design features or an
insulated cover to protect against inadvertent contact. All such terminals and surrounding
barriers must be identified by red colouring and be marked in red "415/240V AC" by means of
a label attached to the terminal barriers or covers.

All fuse holders must be installed at the front of the terminal boards and no live metal is to be
exposed at the back.

All fuses and links must be clearly labelled with the circuit function and fuse size or Link as
per the approved Design Drawings.

All cable cores must be terminated, including spare cores, as indicated in the approved Design
Drawings.

Connections to equipment terminals must be made with appropriate crimp lugs to suit the
particular equipment, as generally indicated by MN000301R166 Construction and Wiring
Guidelines for Ergon Energy Substation Panels. Circular lugs must be used where possible,
Page 42 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


rather than forked lugs. The latter are to be used only where the type of equipment dictates
that these are the most suitable type of lug.

Document MN000301R166 indicates the minimum required Standards for termination of cores
and crimping of lugs. The lug manufacturers recommendations must also be followed.

14.5.4

Optical Fibre Cables

Optical fibre cables must be run in white conduits, as specified in the design and segregated from
all other cables. The optical fibre conduit may be run in the main cable duct or cable ladder, but
must be clamped to the side of the duct or ladder to be kept clear of the other cables.
Refer also to Sections 11 and 14 of STMP004 Standard for Communications Equipment
Installation, Section 14.3 of this manual, and documents MN000301R166 and BS001404R114 for
other essential requirements in relation to installation of optical fibre cables.

Page 43 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


15.

MISCELLANEOUS

15.1

Substation Auxiliary AC Supplies

This Section describes the General Construction requirements of the low voltage 415V AC supply
system for the substation equipment and services plus the on-site construction power needs,
within the earth grid area only. It is not intended to apply to the constructors site office,
workshop and amenities AC supply, which must be installed as a separate system, where these
facilities are outside the substation earth grid area.
The major AC supply equipment, as required by the design, will be specified and procured by the
appropriate design team and will be available for collection by the constructor as indicated in
Section 8.4 of this Manual and the project specification.
All items must be entirely satisfactory for the service conditions and intended operational
requirements, whether such conditions or operational requirements are directly specified or not.
The AC supply system must be installed and tested in accordance with AS/NZS 3000 Wiring
Rules. Additional RCD protection must be installed on LV circuits if required by AS/NZS 3000.
The station supply pad mounted or pole mounted 11kV/415V transformers, RMUs, associated HV
and LV cables, the 415V AC three phase main switchboard and sub-boards must be installed and
tested as indicated on the relevant Design Drawings and in accordance with Ergon Energy
Substation Standard SS-1-5.2 AC Supplies.
Prior to commissioning of the 11kV/415V station supply transformers, a temporary source of LV AC
supply for on-site construction, operation and testing purposes (eg. battery chargers, fans, tap
changers, etc.) will be needed. The substation Constructor must arrange either:
(a) Sufficient LV generating capacity, or
(b) LV Supply to the site from the Ergon Energy Distribution Network, if readily available. The
temporary connection is to be requested for the duration of the Construction/Commissioning
period. This connection will be subject to Ergon Energy Standard Terms and Condition for
supply and will be metered and charged accordingly.
The following conditions apply to the use of temporary supplies:
The temporary supply must be connected to the substation AC supply panel, so as to function,
as far as possible, in the same manner as the final permanent supply will do.
The temporary supply must remain wholly within the substation earth grid area and not
be used to supply equipment outside that area, so as to avoid the possibility of touch
potential problems due to transference of the substation earth potential to an area that might be
at a different earth potential.
Access to all live parts must be restricted in accordance with the requirements of AS/NZS 3000
and any related document, to minimise the risk of accidental contact by personnel.
All outstanding and/or uncompleted works must be made safe at all times, including the cutover
from temporary to permanent arrangement.
A written statement detailing the status of the temporary AC supply and associated isolations,
locks and tags must be provided in handing over to the next work group (Test/Commissioning,
etc.)
Within a live substation site (brownfield), power supply for on-site construction, office and facilities
purposes may be available directly from the existing AC supply system for the site, provided the
tools and equipment connected do not overload the relevant circuits used, or otherwise impact on
the supply to the live substation equipment.
Page 44 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


15.2

DC Supply Systems

This Section describes the General Construction requirements of the batteries, battery chargers,
battery stands, DC isolation and test panels, DC/DC converters, DC/AC inverters, and DC
distribution boards for the Substation DC Supply Systems and the Communications DC Supply
System.
The major DC supply equipment items as indicated above are selected (by the Designer) from the
standard Ergon Energy inventory items sourced on the Ergon Energy Period Contract for DC
supply equipment.
All items, whether sourced from the Period Contract or elsewhere (for non-contract items) must be
entirely satisfactory for the service conditions and intended operational requirements, whether such
conditions or operational requirements are directly specified or not.
Installation of the DC Supply Systems, including all cabling between battery banks, isolation and
test panels, DC distribution board, battery charger, DC/DC converter and DC/AC inverter must be
carried out as described in Ergon Energy Substation Standard SS-1-5.1 DC Supplies.
Bolts, nuts, washers and inter-connections must be of an inherently corrosion resistant material or
otherwise protected against corrosion and must be supplied by the Construction Workgroup.
Racks, signage and inter-cell/inter-tier/inter-row connectors are supplied by the Battery
Manufacturer, together with the batteries and must be installed in accordance with the Instruction
Manual supplied.
The Battery and Battery Charger Instruction Manuals (supplied with the equipment) also contain
Factory Acceptance Test results. The batteries and chargers must be inspected, installed and
tested in accordance with the requirements of the Instruction Manuals.
15.3

Lighting

All switchyard and building lighting must be installed in accordance with Ergon Energy substation
standards SS-1-9.6 Substation Lighting and Section 9.3 of SS-1-1.4 Substation Design
Requirements, in locations and orientations as shown on the relevant design drawings.
All switchyard lights must be able to be maintained without need for an outage of any HV
equipment. For example, swing-down lights and their counter-balances must not encroach within
the relevant exclusion zones for nearby HV plant, at any point of their swing-down paths.
Cabling to each light must be connected as indicated on the relevant Design Drawings. Minor
materials required to complete the connections are to be supplied by the Constructor.
15.4

Nameplates, Signage, Labelling

15.4.1 General Requirements


Rating plates, nameplates, signs and labels installed on outdoor equipment must be of stainless
steel or non-ferrous metal, with etched or engraved lettering and fixed with stainless steel screws
or monel rivets. Indoor labels must be engraved traffolyte or other approved material.
Rating plates, nameplates, signs and labels must be located such that they can be easily and
safely read from normal operating positions and access ways around the equipment, at ground or
floor level.
Full details of all signs, labels, etc. required, including content, sizes and details of lettering, in
accordance with the respective Template Drawings will be provided in the Project Design, for
ordering purposes. All fasteners required must be supplied by the Construction Workgroup.

Page 45 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


15.4.2 Rating Plates, Nameplates and Operational Signs
All CT and VT marshalling boxes must incorporate rating plates showing all relevant rating data of
the associated HV plant. A second set of rating plates is usually sourced from the CT or VT
Manufacturer for installation on the appropriate marshalling box.
All switchyard operational signs must align with the approved Operating Single Line Diagram. The
Standards for content, sizing, and layout of operational signs are indicated on typical Drawings eg.
963817-01 to 07.
Switchyard Operational Number signs are required on each HV operational point only. i.e. circuit
breakers, disconnectors, earthing switches, voltage transformers, power transformers (all ratings),
HV fuses, disconnectors and earthing switches in RMUs and HV switchboards. Current
transformers and surge diverters are not operating points and therefore must not be allocated
Operating Numbers, although they may have been shown on the Operating Diagram for
information.
15.4.3 Labels
All equipment, operating devices, relays, etc. must be suitably labelled such that they can be
readily identified from drawings. Circuit breaker and transformer control cubicles, control panels
and relay panels must also be labelled. Cubicles and switchboard panels with rear access must
also be labelled on the rear of the panel.
On manufactured equipment, most labels should be supplied and installed by the Equipment
Manufacturer, however, some additional labelling may be provided by the Project Designer to
match the equipment identifications shown on the Project Drawings. e.g. bay numbering, device
identification, etc.
All labels must be in the English language.
15.4.4 Safety Signs
Warning and Safety Signs must be installed around and within the substation, as specified in the
Ergon Energy Standard SS-1-9.3 Substation Signage.
These signs warn Personnel of dangerous voltage levels, correct operating procedures and safety
requirements within the substations.
Warning signs must conform to the relevant Australian Standard and Work Health and Safety Act
2011. The required signs and locations will be provided in the Project Design Drawings, however
the Constructor should still double check that all the necessary signs have been provided and that
the specified locations are suitable.
15.5

Painting

All surfaces of structures and equipment must be finished with an appropriate coating system
which will provide the necessary protection against corrosion for the design life of the equipment.
Minimum coatings for all exterior surfaces not specified as hot dip galvanised must be one coat of
primer, one undercoat and two finishing coats of an approved colour and quality paint. The top
coat must be single pack epoxy.
The interior of outdoor control cubicles, cabinets must receive the same number of coats as the
exterior. The Constructor must make good any damage to the paint incurred during delivery,
erection or commissioning, before completion of the works.

Page 46 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


15.6

Locks, Keys, Operating Equipment, Miscellaneous Control Building Furniture

Where building locks are required, they must be flush mounting types, suitable for Ergon Energys
master key system.
Locks must be constructed and located on equipment so that they remain serviceable in the whole
range of Queensland climatic conditions for an indefinite lifetime, including continuous periods of
up to two years without operation or maintenance.
Building entry & internal door lock barrels are to be replaced by the appropriate Ergon lock barrels,
according to the substation region.
All HV operating points (circuit breakers, disconnectors, earthing switches, VT secondary fuses)
must be fitted with the appropriate Ergon switching padlock (again according to the substation
region).
Panel, cubicle and miscellaneous equipment keys, equipment operating handles and the like must
be hung on a shadow board(s) mounted in the control building, in the same room(s) as the
associated equipment. The control building must also include a plan desk, chair, drawing hanger
for storage of substation drawings and two drawer filing cabinet (to fit under desk).
Operating equipment such as portable earthing devices (PEDs), HV test sticks, DNOBs, HV
gloves, etc must be neatly stored in an efficient manner that ensures the equipment remains in
serviceable condition and is readily accessible when required. PEDs must be hung neatly and
singly on smoothly curved brackets, either in the control building, or in an external operating
equipment shed, as specified by the designers. Circuit breaker trolleys for MV switchboards
should be stored in the switchboard room in readily accessible position, but parked neatly so as to
be clear of personnel access paths. A substation sign-in/out log book must be placed on the
control room desk, near the telephone.
Switching padlocks, door lock barrels and operating equipment as listed above are available as
Ergon Energy stores stock. Quantities and voltage/current ratings as appropriate, will be specified
by the designers for the specific project.
15.7

Control Building Electrical Services

This includes control building lighting and power circuits, air conditioning, fire protection and
security systems as required.
All materials supplied and all work carried out must comply with the requirements of the latest
addition of the Australian/New Zealand Wiring rules (AS/NZS 3000) and amendments thereto, the
Queensland Electrical Safety Act and Regulations, other relevant SAA Codes, Ergon Energy
Standards and the design drawings provided for the project.
All light switches and GPOs must be flush mounted on blockwork, except that outlets of 63A
capacity or greater rating (single or three phase) may be surface mounted. Where blockwork is
required to be core filled, the Contractor must install conduits into flush mounted wall boxes, to
allow drawing in of cables after core filling.
Each electrical socket outlet must be engraved or labelled to indicate its respective circuit number.
In some cases, labels may be fixed to the wall adjacent to the switch, if fixing to the switch is not
suitable.
The control building electrical circuits must be cabled and connected to the appropriate circuit
breakers on the AC Distribution Board, as indicated on the project electrical design drawings.
The AC Distribution Board will be provided as free-issue to the building constructor for installation
as indicated on the building layout drawings, to enable the connection of the building electrical
circuits as in the paragraph above.
The final installation must ensure that the loads are as evenly balanced as possible across the
three phase supply.
Page 47 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Equipment Manuals provided by equipment suppliers must include full operating instructions, as
constructed drawings, test results, manufacturers product data and safety instructions for the safe
installation and use of the equipment.
The air-conditioning system must be supplied, installed and commissioned in accordance with the
requirements of the project Specification, Section 21.4 of SS-1-1.4 Substation Design
Requirements, the design drawings and the relevant SAA Codes and other relevant Regulations.
A fire protection system must be installed in accordance with SS-1-9.1 Substation Fire Protection,
the project Civil Specification (where supplied), the Workplace Health and Safety Act and
Regulations, the appropriate Australian Standards referenced in SS-1-9.1 Substation Fire
Protection and the design drawings. The system must include Fire Indicator Panel (including
manual call point), detectors, cables, conduits, accessories and fire extinguishers, as indicated
generally by the Fire and Communications Services Layout drawing. The Fire Indicator Panel
must be approved by the Insurance Council of Australia.
A plastic laminated as installed Location diagram of the complete installation must be securely
mounted on the wall adjacent to the Fire Indicator Panel. The Location diagram must use symbols
that comply with AS 1670 and Handbook AS HB20 and must indicate the position of the fire
indicator panel, detectors, alarm groups and alarm zone circuit numbers. A complete circuit
diagram indicating all wiring and terminal connection details of the output contacts for alarm and/or
control purposes, plus details of provisions for future connection of the panel for system monitoring
by the Fire Brigade are also required.
The fire protection system must include an air conditioning shutdown signal from the Fire Indication
Panel to the relevant circuit on the AC Distribution Board, in the event of a fire. Fire extinguishers
must be mounted securely on suitable brackets, enabling ready access to the extinguishers if
required, with appropriate identification signs in accordance with the Regulations and located as
indicated on the design drawings.
A building security system, including Intruder Alarm Panel where required, must be supplied,
installed and commissioned in accordance with the project specification, SS-1-9.5 Substation
Physical Security and Monitoring and the relevant Standards and Regulations, etc references
therein.
15.8

Commissioned / De-commissioned Plant Data Capture Forms

Following installation of each item of new HV plant or protection relay into its correct position in the
substation, a Commissioned Substation Plant Data Record Form NA000403F189 must be
completed for each item and a clear, readable photograph of the nameplate(s) attached.
Similarly, for any existing items of plant de-commissioned and removed from their service
positions, a De-Commissioned Substation Plant Data Record Form NA000403F190 must be
completed and nameplate photo attached.
The form(s) should be completed prior to issue of the Construction Release MN000301F175, in
case access to HV plant is still needed to view and photograph plant details. As well as the
nameplate photograph (essential), a general photograph of the item of plant is also useful.
As well as major HV plant items, completed forms will be required for items such as transformer
bushings, CTs, oil pumps, cooling fans, surge diverters and HV links. Secondary items needing to
be recorded include protection relays, battery banks, chargers, revenue and statistical meters,
metering CTs, RTU cards, etc.
A single form can be used for a set of 3 single phase items of plant (eg. CTs, VTs, surge
diverters). The completed forms and nameplate photos must be forwarded to the regional AMO
(Asset Maintenance Officer) through the Project Manager, as early as possible prior to
commissioning of the plant.

Page 48 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


16.

ELECTRICAL CONSTRUCTION TESTING

16.1

General Scope

All construction groups must monitor and ensure the quality of their completed work, by carrying
out Construction Testing and rectifying any deficiencies found, prior to handover to the Test group.
The construction work & testing must be verified by completion of the relevant Substation
Construction Tools, which are available individually on the Process Zone and conveniently grouped
as a package on Ergons internet website for Design and Construction Contractors (under Zone
Substation Design and Construction).
The extent of Construction Testing done must be indicated in the completed Construction Tools
and include (but not be limited to):
(a) Continuity testing of all field wiring and cables in marshalling cubicles and site primary plant.
Point to point testing of panel and primary plant internal wiring will generally have been
completed by the relevant Suppliers and accordingly does not need to be repeated, unless the
wiring has been modified since completion of the F.A.T. In the event that the Field
Construction group are also responsible for wiring of the control, protection and other panels
(either directly or by sub-contract), then that group will also be responsible for continuity
testing of the panel wiring.
(b) Continuity testing of all cables (and connections) entering the Control/Communications
Buildings and any additional inter-panel wiring, DC/AC supplies and any other wiring in the
Building that has not been checked during FAT Testing of Control/Protection Panels.
(Unchecked wiring should be readily determined from the greened-out copies of Schematics
marked up during FAT Testing).
(c) Insulation Resistance Testing (at 500V) of all wiring installed on site including control cables,
panel wiring and inter-panel wiring.
(d) Ductoring of all earth mat connections. A minimum current of 50A is used for resistance
measurement to check continuity of earth connections from all structures, plant, equipment
and fittings to the main earth grid. Resistance is measured to a common reference point (the
No 1 Transformer 11kV neutral connection point). Refer also to Section 5.3 of SGM002
Substation Earthing Strategy and Section 5.7 of SP0515 Bus Assembly Testing SWP. Results
must be recorded on Earth System Continuity Test Report or equivalent.
(e) Ductoring of HV connections to primary plant. Refer to Section 5.6 of SP0515 Bus Assembly
Testing SWP. Results must be recorded on SP0515C01 Bus Assembly Test Report or
equivalent.
All construction works must be verified by the Substation Construction Coordinator or equivalent
Contractor representative supervising and coordinating the work, through a combination of
checking the completed Construction Tools and adequate inspection of the completed work.
At the completion of construction, a verified electronic copy of all relevant completed Construction
Tools must be saved to Ergons nominated Network Storage drive for maintenance and quality
records and a copy forwarded to the Ergon Project Manager. Where the constructor does not have
suitable access to the Ergon network, the Ergon Project Manager will arrange for saving of the
electronic copy on the network drive.
16.2

Specific Requirements for Secondary Wiring and Associated Equipment

Ergon Quality Document MN000301R167: Green-lining and Blue-lining of Ergon Energy


Substation Drawings provides further details of the requirements for Continuity Testing and Visual
Page 49 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


Identification of Cabling, Wiring and Terminations. A working copy of each relevant Schematic
must be green-lined progressively, in accordance with the procedure outlined in the same
document. (Blue-lining is for Functional Testing to be carried out by the relevant Test Workgroup).
All cabling, wiring and termination of wiring must meet the Requirements and Standards of Ergon
Energy Quality Document MN000301R166: Construction and Wiring Guidelines.
Check that all equipment is mounted securely and that all electrical connections, including cable
screens are properly crimped, with the correct type of lugs and tightened properly (tug test).
Check connection and insulation of cable screens in accordance with Design Requirements. i.e.
Are they connected correctly and earthed at the correct end(s).
For Insulation Resistance Testing of Cables, each core is to be meggered individually, with every
other core in the cable earthed.
With all cores in a cable shorted together at one end, megger the insulation of the whole cable to
earth.
Megger the insulation between different sources of supply in panels. Care must be taken to
disconnect or short out terminals of equipment which may be damaged during this testing and to
restore any disconnected items to their exact original state.
Check cable entries, fuses, links, indicating lamps and any other equipment.
16.3

Construction Release and Handover

On completion of all Construction Inspection/Test Checklists and rectification of any outstanding


works identified therein, each involved Construction group must provide to the Ergon
Commissioning Officer/Engineer a completed MN000301F175: Construction Release. All plant to
which the Release applies must be identified clearly and concisely on the form. This Release is to
provide confirmation :
(i)

that all construction has been completed fully in accordance with the design drawings and
the Construction Manual, and

(ii) that the relevant construction group(s) is/are now clear of the listed plant and now consider
all the relevant HV plant and equipment to be live.
As the HV Equipment will now be subject to test voltages used by the Test Workgroup carrying out
Site Integration Testing, any further access required (e.g. to correct an error or omission) will be
done under the coordination of the Commissioning Officer/Engineer and the Test Workgroup.
Ergon Energys High Voltage Isolation and Access Procedures (HVIA) apply to those parts of the
site now considered as capable of being made live.
If Construction and Commissioning of the Substation is occurring in stages, then the Construction
Release may apply to a Section of the equipment only, in which case access to other areas of the
work may still be available.
Upon receipt of the above document, Site Integration Testing (SIT) will be commenced, followed by
final pre-energisation testing, HV Switching, energisation and post energisation on load testing, in
accordance with the Test and Commissioning Manual.
16.4

Construction Safety Clearance

On completion of all Site Construction Works, as indicated above, each involved Construction
group must provide to the Project Manager a completed MN000301F123: Construction Safety
Clearance High Voltage Apparatus, confirming that all personnel in the group are now clear of all
parts of the electrical works and now consider all the relevant HV plant and equipment to be live.
This will assist to enable the Project Manager to sign off his agreement that final commissioning
and subsequent energisation of the complete works may now proceed.
Page 50 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

Substation Construction Manual


16.5

Outstanding Items

In the event of any outstanding items of work unable to be completed at the time of handover of the
Construction Release, these need to be noted clearly on the Construction Release, and discussed
with the Ergon Energy Commissioning Officer and Project Manager for follow up.

Page 51 of 51
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Reference NI000401R122 Ver 2

You might also like